UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
OPERATIVE PLASTERERS’ &
CEMENT MASONS’ INT’L ASS’N OF
THE U.S. & CANADA, AFL-CIO,
Petitioner,
v. Civil Action No. 12-974 (JEB)
PULLMAN SHARED SYS.
TECH., INC., et al.,
Respondents.
MEMORANDUM OPINION
This case arises from a dispute between two rival labor organizations – the Operative
Plasterers’ & Cement Masons’ International Association, AFL-CIO (OPCMIA) and the
International Union of Bricklayers and Craftworkers (BAC) – over who should receive the work
assignment on a construction project in Indiana from contractor Pullman Shared Systems
Technology, Inc. (SST). In filing this suit, Petitioner OPCMIA seeks to vacate an arbitration
award upholding SST’s assignment of the work to BAC. OPCMIA contends that this decision
cannot stand because the arbitrator ignored the plain language of the parties’ agreement and
dispensed his own brand of industrial justice. Both sides now move for summary judgment.
Under the “extremely deferential” standard of review for such labor decisions, the Court will
confirm the award, thereby granting Respondents’ Motion and denying Petitioner’s.
I. Background
The background facts in this case are largely agreed upon. In the construction industry,
there has been general recognition that two unions – BAC and OPCMIA – dominate the trades of
1
plastering and cement-finishing work. See Pet.’s Mot., Exh. 2 (May 15, 2012, Greenberg
Arbitration Award) at 4. For many years the two unions worked cooperatively, crafting a map
that divided up the country on a county-by-county basis so that the jurisdiction of each could be
clearly demarcated. See id. In 1998, however, this arrangement was abrogated, resulting in a
“period of significant and on-going friction as the unions battled to win new work in territory
historically reserved to the other” and brought numerous jurisdictional challenges before
organized labor’s dispute-resolution bodies. See id. at 4-5. The dispute here over which union
would handle a work assignment to install fireproofing materials on an SST project at a BP
Products plant in Whiting, Indiana, is the latest in this ongoing chronicle. See id. at 2.
Both unions and SST are parties to the National Maintenance Agreement (NMA), a
collective bargaining agreement between an employer and labor organizations “for the purpose
of construction, maintenance, repair, replacement, renovation and modernization work”
performed by that employer. See Pet.’s Statement of Undisputed Material Facts (SUMF), ¶¶ 4-5.
All parties agree that the NMA sets forth a jurisdictional dispute-resolution process, which
requires that such disputes be submitted to an umpire and articulates the standards and criteria
the umpire is to use when deciding a jurisdictional dispute. See id., ¶¶ 6-9. Pursuant to Article
1, Section 7 of the NMA, the parties sought to resolve this dispute internally; when that was
unsuccessful, OPCMIA requested arbitration on May 1, 2012. See id., ¶¶ 12-14. A hearing was
held on May 10 by Umpire Paul Greenberg in Washington, D.C., and five days later he issued an
award confirming SST’s assignment of the project to BAC. See id., ¶¶ 15, 18, 26.
OPCMIA then petitioned this Court to vacate Greenberg’s award, naming both BAC and
SST as Respondents, and all parties now move for summary judgment regarding the award’s
enforceability. See ECF Nos. 1, 11 & 13.
2
II. Analysis
A. Deferential Review
In a recent opinion, curiously omitted from Petitioner’s Motion, this Circuit provided a
comprehensive discussion of the “extremely deferential standard of review for labor arbitration
decisions.” Nat’l Postal Mail Handlers Union v. Am. Postal Workers Union, 589 F.3d 437, 439
(D.C. Cir. 2009). A labor arbitrator’s decision “must be upheld so long as it ‘draws its essence
from the collective bargaining agreement.’ That standard is met . . . if the arbitrator ‘premise[d]
his award on his construction of the contract.’” Id. at 441 (quoting United Steelworkers of Am.
v. Enterprise Wheel & Car Corp., 363 U.S. 593, 597 & 598 (1960)).
Courts “are not authorized to review the arbitrator’s decision on the merits despite
allegations that the decision rests on factual errors or misinterprets the parties’ agreement.”
Major League Baseball Players Ass’n v. Garvey, 532 U.S. 504, 509 (2001). If an arbitrator is
“even arguably construing or applying the contract and acting within the scope of his authority,”
then a court may not overturn his decision, even if the court is convinced the arbitrator
committed “serious error.” Id. (quoting E. Associated Coal Corp. v. United Mine Workers of
Am., Dist. 17, 531 U.S. 57, 62 (2000)) (internal quotation marks omitted). A court may vacate a
labor arbitration award “only when the arbitrator strays from interpretation and application of the
agreement and effectively ‘dispense[s] his own brand of industrial justice.’” Id. (quoting
Enterprise Wheel, 363 U.S. at 597); see also Allied Pilots Ass’n v. Am. Airlines, Inc., 734 F.
Supp. 2d, 90, 96-98 (D.D.C. 2010).
In sum, as this Circuit noted in Nat’l Postal, the “relevant question under the Supreme
Court’s precedents is not whether the arbitrator erred – or even seriously erred – in interpreting
the contract. Rather, the question is whether the arbitrator was ‘even arguably construing or
3
applying the contract.’” 589 F.3d at 441 (quoting Garvey, 532 U.S. at 509). Significantly,
“[c]ourts do not review the substantive reasonableness of a labor arbitrator’s contract
interpretation. This extraordinarily deferential standard is essential to preserve the efficiency and
finality of the labor arbitration process.” See id. (internal citations omitted). This deference
ensures that the judiciary does not usurp the function entrusted to the arbitrator. See Garvey, 532
U.S. at 510; see also Allied Pilots Ass’n, 734 F. Supp. 2d at 96-98 (recognizing that policy of
settling labor disputes by arbitration would be undermined if courts could disturb merits of
awards).
Petitioner acknowledges the substantial deference that the Court must afford the
arbitrator’s decision, but contends that even under such a standard, the award cannot stand since
“[n]arrow review – even extremely narrow review – does not mean ‘no review.’” Pet.’s Mot. at
8; see also Pet.’s Opp. at 3 (“a United States District judge wields a gavel, not a rubber stamp”);
Verizon Washington, D.C. Inc. v. Commc’ns Workers of America, AFL-CIO, 571 F.3d 1296,
1304 (D.C. Cir. 2009) (Henderson, J., concurring) (noting that while courts apply a “largely
‘hands off’ standard of review to an arbitral award, that does not mean anything goes”)
(emphasis in original).
B. Umpire’s Decision
In seeking vacatur here, OPCMIA maintains that the arbitrator was dispensing his own
“industrial justice” by disregarding the plain language of the parties’ agreement. Pet.’s Mot. at 2.
Both sides begin by agreeing that Section 10 of the NMA governs this dispute. This section
states:
In rendering a decision, the Umpire shall determine:
a. First, whether a previous agreement of record or applicable agreement,
including a disclaimer agreement, between the National and International
4
Unions to the dispute governs;
b. Only if the Umpire finds that a dispute is not covered by an appropriate or
applicable agreement of record or agreement between the crafts to the
dispute, shall consideration be given to the established trade practice in the
industry and prevailing practice in the locality. Where there is a previous
decision of record governing the case, the Umpire shall give equal weight
to such decision of record, unless the prevailing practice in the locality in
the past ten (10) years favors one craft. In that case, the Umpire shall base
any decision on the prevailing practice in the locality. Except that if the
Umpire finds that a craft has improperly obtained the prevailing practice
in the locality through raiding, the undercutting of wages or by the use of
vertical agreements, the Umpire shall rely on the decision of record and
established trade practice in the industry rather than the prevailing practice
in the locality;
c. Only if none of the above criteria is found to exist, the Umpire shall then
consider that because efficiency, cost or continuity and good management
are essential to the well being of the industry, the interests of the consumer
or the past practices of the employer shall not be ignored;
d. The Umpire shall set forth the basis for their decision and shall explain
their findings regarding the applicability of the above criteria. If lower-
ranked criteria are relied upon, the Umpire shall explain why the higher-
ranked criteria were not deemed applicable.
NMA at 4-5.
Petitioner contends that the arbitrator “ignored the ranking of criteria in Section 10,
choosing to resolve the dispute over SST’s assignment of fireproofing work on his own terms.”
Pet.’s Mot. at 2. Since the parties concur that no “previous agreement of record” or “applicable
agreement” governs, Section 10(a) does not apply, and the Umpire must look to 10(b). In doing
so, Petitioner complains that Greenberg improperly “decided the dispute based solely on a
decision of record issued in 2004, without regard to the parties’ evidence of prevailing local
practice.” Id. OPCMIA stresses that the arbitrator’s interpretation strayed so far afield from the
agreement that it cannot be said that he was applying the contract, even under the “extremely
5
deferential” standard of review. See id. at 9 (citing Garvey, 532 U.S. at 509); see also id. at 11-
15.
Respondents counter that the arbitrator “rationally interpreted the contract, which by its
express terms incorporates industry practice.” Resp.’s Mot. at 2. BAC and SST note that the
arbitrator looked to the appropriate criteria in the NMA, particularly a 2004 decision of record
and the “‘overwhelming weight’ of arbitration decisions in BAC/OPCMIA disputes since 2004,
which had given the [2004 decision of record] controlling weight.” Resp.’s Mot. at 4; see also
id. at 2-3, 15-31. Even though the Umpire’s decision may not constitute the cleanest or simplest
reading of the NMA, the Court believes it is certainly an arguable construction that requires
deference.
In his seventeen-page decision, Greenberg provides an extensive description of the
background and history of the parties’ dispute, an explanation of the language within the parties’
agreement setting forth the standard for making jurisdictional awards, and a lengthy discussion
of “trade practice, prevailing local practice, and decisions of record,” all of which factor into his
interpretation of the parties’ agreement here. See Award at 2-17.
His analysis begins with the relevant provision of the NMA, which sets forth the standard
for resolving jurisdictional disputes that he must interpret and apply. See id. at 2-3. As he notes,
the critical language comes in Section 10(b). Pointing to that language, Greenberg observes that
“the crux of this dispute revolves around a decision of record adopted by the [Settlement of
Jurisdictional Disputes in the Construction Industry (“the Plan”)] in 2004 involving OPCMIA
and BAC. The task before me is to determine (a) whether the 2004 decision of record applies in
this NMA dispute, and if so (b) how the decision of record applies in this NMA dispute.” Id. at 4
(emphasis in original).
6
To resolve these questions, Greenberg begins with what he determines to be a decision of
record. This decision was issued by a National Arbitration Panel in 2004 in an attempt to settle
the longstanding OPCMIA/BAC dispute. See id. at 5-8. This Panel was convened pursuant to a
“special mechanism for addressing repetitive jurisdictional challenges,” which assembles three
Plan arbitrators to hear and resolve disputes when called upon by the Joint Administrative
Committee. Id. at 5. The Panel issued a decision on February 11, 2004 (later clarified on March
11, 2004), which held that “[h]enceforth, all jurisdictional disputes between the BAC and the
OPCM that are brought before the Plan shall be resolved in favor of the work assignment of the
involved Employer.” Id. at 7 (citing 2004 Panel Decision). While this decision was decided
pursuant to the Plan, rather than under the NMA, the Plan contains the same decisional standard
found in Section 10(b) of the NMA. See id. at 3.
Greenberg’s decision goes on to trace the way this 2004 decision was applied in
subsequent disputes before other arbitrators. See id. at 8-11. In each of these decisions resolving
disputes between OPCMIA and BAC over work assignments, the Panel’s “employer preference”
approach prevailed:
• United Exterior Improvements (2004 Kelly decision relying on 2004 Panel
decision to find that jurisdictional dispute would be resolved by employer
preference), see id. at 8-9;
• J.R. Phillips, Inc. (2006 McMahon consolidated decision adopting employer-
preference approach; no need to make determination on prevailing practice), see
id. at 9;
• RG Constr. Serv., Inc. (2006 Pagan decision stressing that Panel’s decision was
unreviewable authority), see id. at 9-10;
• J.R. Phillips, Inc. (2009 Kelly decision adopting 2004 Panel decision as
“exclusively govern[ing]” and superseding any claim of “prevailing practice in
the industry”), see id. at 10; and
7
• Commodore Const. Corp. (Kelly 2010 decision embracing 2004 Panel decision
and noting that “jurisdictional disputes between OPCMIA and BAC shall be
based on employer preference, without regard to prevailing local practice”).
See id.
Reviewing this “overwhelming weight of Plan jurisprudence” subsequent to the 2004
Panel decision, Greenberg recognized “the primacy of employer preference as the governing
criterion for making awards in disputes between BAC and OPCMIA involving plastering or
cement finishing tasks, with Plan arbitrators consistently declaring that the normal area practice
considerations . . . do not apply to disputes between these two parties.” Id. at 11. He further
observed that while there is a fairly robust history of the awards under the Plan, “the history of
these parties before the NMA appears to be significantly less extensive.” Id. at 12. Greenberg
did, however, point to an award issued in late 2011 “at the same facility as the instant matter,”
where the Umpire sustained the contractor’s assignment of the fireproofing work to BAC. See
id. at 12 (citing J.T. Thorpe & Son, Inc., NMAPC No. AI-197-11 (2011)).
Based on all of the considerations discussed above, Greenberg concluded:
Looking at the record as a whole, however, I believe BAC has the
better argument in this case. I find that, notwithstanding the text of
NMA Article I, Section 10(b) suggesting local practice ordinarily
prevails over the mandate of a decision of record, the 2004
decision of record applies under the NMA and operates in the same
manner under the NMA as under the Plan, i.e., employer
preference controls in work assignment disputes between BAC and
OPCMIA in connection with plastering and cement finishing tasks.
Id. at 14. He provided additional “observations” to support his conclusions, including:
• the 2004 Plan decision operates differently from other decisions of record due to
the “unique origin of the 2004 decision of record, the unique nature of the
disputes between the two International Unions, and the body of arbitral decisions
interpreting the 2004 decision,” id. at 14-15;
8
• the Joint Administrative Committee “effectively has ratified the body of arbitral
law holding that prevailing local practice has no role in resolving work
assignment disputes between BAC and OPCMIA,” id. at 15; and
• adoption of the same decisional standard in the NMA as was being used under the
Plan leads to the conclusion that “NMAPC was seeking to bring greater
predictability and consistency to the jurisdictional dispute resolution process in all
sectors of the industry, with jurisdictional awards at sites subject to the NMA
being made under the same standard as awards at sites subject to the Plan.”
Id. at 16.
In addition to its argument about plain language, Petitioner submits that Greenberg’s
decision ignores evidence that the group that administers the NMA, the National Maintenance
Agreement Policy Committee, declined in 2011 to adopt the employer-preference policy set out
in the 2004 decision. See Pet.’s Mem. at 7-8. The Court finds that the Umpire properly
considered this evidence in ultimately determining that it did not support a conclusion that
NMAPC had rejected the employer-preference approach. See Award at 16.
The Court finds that the Umpire’s reasoning and conclusions in the Award are “not
outside traditional juridical and interpretive bounds: The arbitrator was ‘arguably construing or
applying the contract.’” Nat’l Postal, 589 F.3d at 443 (quoting Garvey, 532 U.S. at 509). His
decision, moreover, does not “manifest an infidelity” to his obligation to “draw[] its essence
from the collective bargaining agreement.” Enterprise Wheel, 363 U.S. at 597. He has neither
“rendered a judgment based on external legal sources, wholly without regard to the terms of the
parties’ contract,” Am. Postal Workers Union, AFL-CIO v. USPS, 789 F.2d 1, 3 (D.C. Cir.
1986), nor made a finding “completely inexplicable and border[ing] on the irrational.” Garvey v.
Roberts, 203 F.3d 580, 590 (9th Cir. 2000).
On the contrary, Greenberg recognized his duty to interpret Article I, Section 10 of the
NMA, and his decision is indeed rooted in this language. See Award at 2-4, 14-16; see also
9
Allied Pilots Ass’n, 734 F. Supp. 2d at 98 (where arbitrator “explained its reasoning in terms of
the CBA’s language, purpose and history,” court found decision “drew its essence from the
CBA”). The Court need not agree with the arbitrator’s “reasoning or judgment, so long as we
find that his award rested on his construction of the CBA.” U.S. Postal Service v. Am. Postal
Workers Union, 553 F.3d 686, 695 (D.C. Cir. 2009).
In seeking to vacate the award, Petitioner’s argument “reflects a misunderstanding of
contract interpretation principles and of the proper role of courts in reviewing labor arbitration
decisions.” Nat’l Postal, 589 F. 3d at 443. Here, as in Nat’l Postal,
[t]he fact that an arbitrator relies on a substantive background
principle of law or an established canon of construction – and does
not follow the plain text of a contract – does not automatically
mean the arbitrator has gone rogue. As the Supreme Court has
explained, a labor arbitrator is “not confined to the express
provisions of the contract,” but may also look to other sources –
including the “industrial common law” – for help in construing the
agreement. United Steelworkers of Am. v. Warrior & Gulf
Navigation Co., 363 U.S. 574, 581-82 (1960). The Court has
further stated that an arbitrator may “look for guidance from many
sources,” and the award is legitimate if it can be “read as
embodying a construction of the agreement itself, perhaps with the
arbitrator looking to ‘the law’ for help in determining the sense of
the agreement.” Enterprise Wheel, 363 U.S. at 597-98. Relying
on traditional canons of construction or other settled interpretive
principles – and not merely on the plain text of a contract – might
be seriously misguided in certain cases, but such reliance cannot be
dismissed as the arbitrator’s dispensing “his own brand of
industrial justice.”
Id. at 443; see also Transp.-Commc’n Emp. Union v. Union Pac. R. Co., 385 U.S. 157, 161
(1966) (noting that collective bargaining agreements “call[] into being a new common law – the
common law of a particular industry or of a particular plant” and “[i]n order to interpret such an
agreement it is necessary to consider the scope of other related collective bargaining agreements,
as well as the practice, usage and custom pertaining to all such agreements. This is particularly
10
true when the agreement is resorted to for the purpose of settling a jurisdictional dispute over
work assignments.”).
Additionally, in Madison Hotel v. Hotel & Rest. Employees, Local 25, AFL-CIO, 144
F.3d 855 (D.C. Cir. 1998) (en banc), this Circuit recognized that the “parties’ past practice, the
‘industrial common law’ of the hotel business, [and] the structure of the contract as a whole”
“could be properly considered by the arbitrator in interpreting the contract and formulating the
award.” Id. at 859. The court there sustained the arbitrator’s award, finding that he permissibly
drew on these sources, as well as the explicit provisions of the contract itself, and thus
“purport[ed] to be interpreting the contract in rendering his final decision.” Id. (internal
quotation marks and citation omitted).
Were the Court reviewing this contract interpretation de novo, it may have reached a
different outcome, but “the arbitrator was at least ‘arguably construing or applying’ the
Agreement in reaching his decision.” Nat’l Postal, 589 F.3d at 444 (quoting Garvey, 532 U.S. at
509); see also Verizon Washington, D.C. Inc., 571 F.3d at 1303 (“‘[A]n arbitrator must find facts
and a court may not reject those findings simply because it disagrees with them. The same is
true of the arbitrator’s interpretation of the contract. The arbitrator may not ignore the plain
language of the contract; but the parties having authorized the arbitrator to give meaning to the
language of the agreement, a court should not reject an award on the ground that the arbitrator
misread the contract . . . .’”) (quoting United Paperworkers Int’l Union, AFL-CIO v. Misco, Inc.,
484 U.S. 29, 38 (1987)); U.S. Postal Serv., 553 F.3d at 689 (“‘a federal court may not overrule
an arbitrator’s decision simply because the court believes its own interpretation of the contract
would be the better one’”) (quoting W.R. Grace & Co. v. Local Union 759, Int’l Union of the
United Rubber, Cork, Linoleum & Plastic Workers of Am., 461 U.S. 757, 764 (1983)); Hotel
11
Ass’n of Washington v. Hotel & Rest. Emp. Union, Local 25, AFL-CIO, 963 F.2d 388 (D.C. Cir.
1992) (“Neither a disagreement with the arbitrator’s findings of fact nor a difference of opinion
about the correct interpretation of the contract is an occasion for judicial intervention.”); Allied
Pilots Ass’n, 734 F. Supp. 2d at 98 (noting that it is outside of a court’s purview to correct the
arbitrator’s interpretation, “even if that interpretation was badly mistaken”) (internal quotation
marks and citation omitted). The Court, therefore, confirms Greenberg’s award. 1
III. Conclusion
For the foregoing reasons, the Court will issue a contemporaneous Order this day
granting Respondents’ Motion for Summary Judgment and denying Petitioner’s. The award will
be confirmed.
/s/ James E. Boasberg
JAMES E. BOASBERG
United States District Judge
Date: December 17, 2012
1
In reaching this decision, the Court does not rely on Exhibits “A” through “N” of the Declaration of Timothy J.
Driscoll. Petitioner’s Motion to Strike, ECF No. 16, will thus be denied as moot.
12