UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
____________________________________
)
SIERRA CLUB, )
)
Plaintiff, )
)
v. ) Civil Action No. 11-1278 (PLF)
)
LISA P. JACKSON, Administrator, )
U.S. Environmental Protection Agency, )
)
Defendant. )
____________________________________)
OPINION AND ORDER
In Sierra Club v. Jackson, Civil Action No. 01-1537, 2011 WL 181097
(D.D.C. Jan. 20, 2011), this Court ordered the Environmental Protection Agency to promulgate
long-overdue emission standards under the Clean Air Act by February 21, 2011. See Sierra Club
v. Jackson, 2011 WL 181097, at *14. In accordance with that order, EPA signed two final rules
regulating hazardous air pollutants on February 21, 2011. But then, two days before those rules
were to go into effect, EPA imposed an administrative stay on their effective date.
On July 14, 2011, Sierra Club filed a complaint in this Court seeking judicial
review of that administrative stay. This matter now is before the Court on EPA’s motion to
dismiss Sierra Club’s complaint for lack of subject matter jurisdiction under Rule 12(b)(1) of the
Federal Rules of Civil Procedure. Upon consideration of the parties’ papers, the oral arguments
presented by counsel on September 8, 2011, the relevant legal authorities, and the entire record in
this case, the Court will deny EPA’s motion to dismiss.1
1
The papers reviewed in connection with the pending motion include:
the plaintiff’s complaint (“Compl.”) [Dkt. No. 1]; the defendant’s motion to dismiss for lack of
subject matter jurisdiction (“Mot.”) [Dkt. No. 12]; the response of intervenors in support of
defendant’s motion to dismiss for lack of subject matter jurisdiction (“Intervenors’ Response”)
I. BACKGROUND
This case arises from seven related cases, consolidated under Civil Action
No. 01-1537, that were filed in 2001 before this Court. The 2001 proceedings concerned the
EPA’s failure to discharge fully its duty under the 1990 Clean Air Act amendments to
promulgate regulations governing the discharge of certain hazardous air pollutants. See Sierra
Club v. Jackson, 2011 WL 181097, at *1; Sierra Club v. Johnson, 444 F. Supp. 2d 46, 47
(D.D.C. 2006).
As the Court previously has discussed, Section 112(c)(6) of the Clean Air Act
requires that EPA regulate the sources of especially dangerous hazardous air pollutants by
assuring that sources accounting for 90% of those pollutants are subject to protective emission
standards. See 42 U.S.C. § 7412(c)(6); see also Sierra Club v. Jackson, 2011 WL 181097, at *2.
By statute, EPA was to have promulgated its Section 112(c)(6) emission standards, among
others, by November 15, 2000. 42 U.S.C. § 7412(c)(6).
EPA failed to comply with that statutory deadline. See Sierra Club v. Jackson,
2011 WL 181097, at *3. Consequently, in 2001, Sierra Club filed seven different complaints
against EPA before this Court, each seeking relief for EPA’s failure to discharge a different
aspect of its regulatory duties under the Clean Air Act. Id.
[Dkt. No. 19]; the plaintiff’s opposition to the defendant’s motion to dismiss (“Opp.”) [Dkt.
No. 22]; the reply of intervenors to plaintiff’s opposition to defendant’s motion to dismiss
(“Intervenors’ Reply”) [Dkt. No. 24]; the plaintiff’s reply to intervenors’ response in support of
defendant’s motion to dismiss for lack of subject matter jurisdiction (“Pl. Reply to Intervenors’
Response”) [Dkt. No. 26]; and the defendant’s reply in support of its motion to dismiss for lack
of subject matter jurisdiction (“Reply”) [Dkt. No. 27].
2
On March 31, 2006, the Court issued an Order in the consolidated cases requiring
that EPA promulgate emission standards under the Clean Air Act on a prescribed schedule. See
Sierra Club v. Jackson, 2011 WL 181097, at *3-4. After the Court granted a number of EPA’s
unopposed requests for extensions, ultimately EPA was required to comply with its
Section 112(c)(6) obligations by January 16, 2011. See id. In December 2010, however, EPA
moved for an extension of that deadline to April 13, 2012. Id. at *5. The Court denied that
request and ordered that EPA promulgate the required emission standards by February 21, 2011.
See id. at *14.
In accordance with that order, on February 21, 2011, EPA signed two rules
regulating emission standards: (1) the “Boiler Rule,” defined by EPA as a rule “to regulate
emissions of hazardous air pollutants . . . from industrial, commercial, and institutional boilers
and process heaters located at major sources of [hazardous air pollutant] emissions”; and (2) the
“CISWI Rule,” defined by EPA as a rule to “regulate emissions of certain air pollutants from
commercial and industrial solid waste incineration units.” 76 FED . REG . 28,662, at 28,663 (May
18, 2011). One month later, on March 21, 2011, EPA published these two rules in the Federal
Register and established an effective date for both rules of May 20, 2011. See id. Also on
March 21, 2011, EPA announced that it was initiating an administrative reconsideration process
with respect to certain aspects of both rules, see id., a procedure provided for under the Clean Air
Act. See 42 U.S.C. 7607(d)(7)(B).
Shortly thereafter, multiple parties, including Sierra Club, filed petitions for
review of the Boiler Rule and the CISWI Rule in the United States Court of Appeals for the
District of Columbia Circuit. The court of appeals consolidated 16 petitions for review of the
3
Boiler Rule into one proceeding, U.S. Sugar Corp v. EPA, No. 11-1108, and consolidated
17 petitions for review of the CISWI Rule into another proceeding, American Forest & Paper
Ass’n v. EPA, No. 11-1125. Those petitions for review present substantive challenges to the
legal sufficiency of the Boiler Rule and the CISWI Rule under the Clean Air Act, a matter that
both Sierra Club and EPA agree is reserved for the exclusive jurisdiction of the court of appeals.
See 42 U.S.C. § 7607(b)(1); see also Sierra Club v. Johnson, 444 F. Supp. 2d at 60.
While those petitions for review were pending in the court of appeals, on
May 18, 2011, two days before the Boiler Rule and the CISWI Rule were to go into effect, EPA
issued a notice, referred to by the agency as the “Delay Notice,” staying the effective date of both
rules “until the proceedings for judicial review of these rules [in the court of appeals] are
complete or the EPA completes its reconsideration of the rules, whichever is earlier.” 76 FED .
REG . at 28,664. In the Delay Notice, EPA made explicit that it was staying the effective date of
these two rules “pursuant to the APA [that is, the Administrative Procedure Act], rather than . . .
the Clean Air Act.” Id. at 28,663. Specifically, EPA stated that it was acting pursuant to its
authority under 5 U.S.C. § 705 of the APA, rather than 42 U.S.C. § 7607(d)(7)(B) of the Clean
Air Act. Id.
Sierra Club filed this lawsuit on July 14, 2011 to challenge the validity of EPA’s
Delay Notice. See generally Compl. In its complaint, Sierra Club asserts that it has a cause of
action against EPA under the APA, and that this Court has jurisdiction to review the Delay
Notice under the federal question statute, 28 U.S.C. § 1331. Compl. ¶ 8. Sierra Club then
contends that the Delay Notice is unlawful for three independent reasons: (1) EPA failed to
provide notice or an opportunity for comment before issuing the Delay Notice, id. ¶¶ 33-36;
4
(2) EPA lacked the authority to issue the Delay Notice, id. ¶¶ 37-43; and (3) EPA failed to
provide adequate justification for the issuance of the Delay Notice. Id. ¶¶ 44-47.2 In its request
for relief, Sierra Club asks that the Court declare the Delay Notice unlawful and that the Court
vacate it. Id. at 10.
On August 11, 2011, EPA filed a motion to dismiss Sierra Club’s complaint for
lack of subject matter jurisdiction under Rule 12(b)(1) of the Federal Rules of Civil Procedure.
Sierra Club filed an opposition, and EPA replied.3 The Court heard oral argument on
September 8, 2011. This matter now is ripe for decision.
II. LEGAL STANDARD
Federal courts are courts of limited jurisdiction, with the ability to hear only the
cases entrusted to them by a grant of power contained in either the Constitution or in an act of
Congress. See, e.g., Beethoven.com LLC v. Librarian of Congress, 394 F.3d 939, 945 (D.C. Cir.
2
On July 15, 2011, Sierra Club filed a petition for review of the Delay Notice in the
court of appeals, raising the same three claims. See Sierra Club v. Jackson, No. 11-1263 (D.C.
Circuit, filed July 15, 2011). Sierra Club has represented to this Court that it filed that petition
for review in the court of appeals because it anticipated EPA’s jurisdictional arguments here and
wanted to protect itself in case this Court were to decide that it lacked subject matter jurisdiction
to review the Delay Notice. See Opp. at 5-6. After it filed its petition for review, Sierra Club
filed an unopposed motion to hold in abeyance the proceedings on the Delay Notice in the court
of appeals pending this Court’s resolution of EPA’s motion to dismiss (as well as the parties’
cross motions for summary judgment). The court of appeals granted Sierra Club’s motion on
August 30, 2011, holding the Delay Notice proceedings in abeyance pending further order of that
court.
3
On August 17, 2011, the Court granted the motion of the Coalition for Clean Air
Implementation (“Intervenors”) for leave to intervene as a defendant under Rule 24(b) of the
Federal Rules of Civil Procedure. See Order at 1, Aug. 17, 2011. Intervenors have filed two
briefs in support of EPA’s motion to dismiss and participated in the oral argument. See generally
Intervenors’ Response; Intervenors’ Reply.
5
2005); Hunter v. District of Columbia, 384 F. Supp. 2d 257, 259 (D.D.C. 2005). On a motion to
dismiss for lack of subject matter jurisdiction, the plaintiff bears the burden of establishing that
the Court has jurisdiction. See Brady Campaign to Prevent Gun Violence United with the
Million Mom March v. Ashcroft, 339 F. Supp. 2d 68, 72 (D.D.C. 2004). In determining whether
to grant a motion to dismiss for lack of subject matter jurisdiction, the Court must construe the
complaint in the plaintiff’s favor and treat all well-pled allegations of fact as true. See Jerome
Stevens Pharms., Inc. v. FDA, 402 F.3d 1249, 1253-54 (D.C. Cir. 2005). The Court need not
accept unsupported inferences or legal conclusions cast as factual allegations. See Primax
Recoveries, Inc. v. Lee, 260 F. Supp. 2d 43, 47 (D.D.C. 2003). Under Rule 12(b)(1) of the
Federal Rules of Civil Procedure, the Court may dispose of the motion on the basis of the
complaint alone, or it may consider materials beyond the pleadings “as it deems appropriate to
resolve the question whether it has jurisdiction to hear the case.” Scolaro v. D.C. Board of
Elections & Ethics, 104 F. Supp. 2d 18, 22 (D.D.C. 2000); see Lopez v. Council on
American-Islamic Relations Action Network, Inc., 741 F. Supp. 2d 222, 231 (D.D.C. 2010).
III. THE ADMINISTRATIVE PROCEDURE ACT AND THE CLEAN AIR ACT
In issuing the Delay Notice, EPA made explicit that it was acting under the APA,
5 U.S.C. § 705, rather than the Clean Air Act, 42 U.S.C. § 7607(d)(7)(B). 76 FED . REG .
at 28,663-64. As EPA stated in the Delay Notice, 5 U.S.C. § 705 provides that “[w]hen an
agency finds that justice so requires, it may postpone the effective date of action taken by it,
pending judicial review.” 5 U.S.C. § 705; see 76 FED . REG . at 28,663. By contrast, the authority
to stay a rule under the Clean Air Act is more limited, providing that a rule issued under the
6
Clean Air Act may be stayed by the EPA (or a court) during administrative reconsideration of
that rule “for a period not to exceed three months.” 42 U.S.C. § 7607(d)(7)(B); see 76 FED . REG .
at 28,663.
As EPA set forth in the Delay Notice, the agency concluded that it had
the discretion to decide whether it is appropriate to delay the
effective date of a rule under either provision [that is, 5 U.S.C.
§ 705 or 42 U.S.C. § 7607(d)(7)(B)], based on the specific facts
and circumstances before the Agency. Since petitions for judicial
review of both the [Boiler Rule] and the CIWSI Rule have been
filed, and . . . justice requires a delay of the effective dates, it is
reasonable for the EPA to exercise its authority to delay the
effective dates of the [Boiler Rule] and the CISWI Rule under the
APA for a period that exceeds three months.
76 FED . REG . at 28,663-64. Specifically, EPA delayed the effective date of both rules “until the
proceedings for judicial review of these rules are complete or the EPA completes its
reconsideration of the rules, whichever is earlier.” Id. at 28,664.
Because EPA, by its own admission, acted under the APA in issuing the Delay
Notice, Sierra Club asserts that this Court has jurisdiction to review this case under the federal
question statute, 28 U.S.C. § 1331. Compl. ¶ 8. Although EPA disagrees with Sierra Club, it is
unclear from EPA’s papers whether the agency contends (1) that this Court actually lacks
jurisdiction, or (2) that this Court has jurisdiction, but should defer to the ancillary jurisdiction of
the court of appeals. Initially, EPA asserts that this Court lacks jurisdiction over Sierra Club’s
complaint because “review of the Delay Notice lies in the exclusive jurisdiction of the United
States Court of Appeals for the D.C. Circuit.” Mot. at 1. Aside from that conclusory assertion,
however, EPA in fact never argues in its papers that this Court lacks jurisdiction. Rather, EPA’s
position in its papers is that judicial review of the Delay Notice is “within the ancillary
7
jurisdiction of the D.C. Circuit,” id. at 5, and that this Court “should defer to the D.C. Circuit’s
ancillary jurisdiction, instead of accepting Sierra Club’s invitation to proceed under federal
question jurisdiction.” Id. at 7. When pressed to clarify EPA’s position during oral argument,
counsel for EPA relied primarily on the agency’s ancillary jurisdiction argument, but ultimately
also asserted that the Clean Air Act divests this Court of jurisdiction over Sierra Club’s
complaint.
The Court disagrees with EPA. First and foremost, the Clean Air Act does not
divest this Court of jurisdiction to review a challenge to the Delay Notice, a final agency action
taken under the APA. Thus, this Court has jurisdiction over Sierra Club’s complaint under the
federal question statute. Furthermore, there is no basis for this Court to defer to any purported
ancillary jurisdiction that the court of appeals’ may have over this case. EPA’s motion to dismiss
therefore is denied.
A. The Administrative Procedure Act and the Federal Question Statute
The APA provides a cause of action to a “person suffering legal wrong because of
agency action, or adversely affected or aggrieved by agency action,” unless another statute “that
grants consent to suit expressly or impliedly forbids the relief which is sought.” 5 U.S.C. § 702.
It is established that the APA is “not a jurisdiction-conferring statute.” Oryszak v. Sullivan,
576 F.3d 552, 524 (D.C. Cir. 2009) (internal quotations and citation omitted). Rather, in cases
arising under the APA, subject matter jurisdiction comes from the federal question statute,
28 U.S.C. § 1331, which provides that “[t]he district courts shall have original jurisdiction of all
civil actions arising under the Constitution, laws, or treaties of the United States.” 28 U.S.C.
8
§ 1331; see, e.g., Beshir v. Holder, Civil Action No. 10-0652, 2011 WL 204798, at *7 (D.D.C.
Jan. 24, 2011) (“[W]hile the APA alone does not provide a jurisdictional basis for this court to
review administrative action (or inaction), jurisdiction is appropriate when the APA is considered
together with 28 U.S.C. § 1331[.]”) (citing Califano v. Sanders, 430 U.S. 99, 107 (1977)).
District courts therefore have jurisdiction to “review administrative action under the federal
question statute . . . , when Congress has not specifically prescribed another review route or
precluded review.” Fox v. Clinton, 751 F. Supp. 2d 122, 127 (D.D.C. 2010).
B. The Clean Air Act: An Unusual, Bifurcated Jurisdictional Scheme
As the court of appeals has recognized, the Clean Air Act contains an “unusual,
bifurcated jurisdictional scheme” that divides jurisdiction between the federal district and circuit
courts. Sierra Club v. Thomas, 828 F.2d 783, 794 (D.C. Cir. 1987). Under the Clean Air Act, “a
person may bring suit in district court against the Administrator of EPA for failure to perform a
nondiscretionary act or duty.” Environmental Def. v. Leavitt, 329 F. Supp. 2d 55, 63 (D.D.C.
2004) (citing 42 U.S.C. § 7604(a)(2)). That “citizen-suit provision provides the district court
with limited but exclusive jurisdiction to order the Administrator to perform nondiscretionary
duties.” Id. (citing 42 U.S.C. § 7604(a)(2)). Specifically, the district court “may compel EPA ‘to
perform purely ministerial acts, [but may not] order [EPA] to make particular judgmental
decisions.’” Id. (quoting N.Y. Public Interest Research Group, Inc. v. Whitman, 214 F. Supp. 2d
1, 3 (D.D.C. 2002)) (alternation in original).4
4
The Clean Air Act’s citizen-suit provision was the basis for this Court’s
jurisdiction in Sierra Club v. Jackson, Civil Action No. 01-1537. See Sierra Club v. Johnson,
444 F. Supp. 2d at 52 (citing 42 U.S.C. § 7604(a)(2)).
9
“In contrast, judicial review of final action by the EPA Administrator rests
exclusively in the appellate courts.” Environmental Def. v. Leavitt, 329 F. Supp. 2d at 63 (citing
42 U.S.C. § 7607(b)(1)). Congress has granted the United States Court of Appeals for the
District of Columbia Circuit exclusive jurisdiction to review “any . . . nationally applicable
regulations promulgated, or final action taken, by the Administrator under [the Clean Air Act.]”
42 U.S.C. § 7607(b)(1); see Sierra Club v. Johnson, 444 F. Supp. 2d at 60; see also
Royster-Clark Agribusiness, Inc. v. Johnson, 391 F. Supp. 2d 21, 26 (D.D.C. 2005).
IV. EPA’S MOTION TO DISMISS
EPA acknowledges, as it must, that the Delay Notice “was issued under the APA,
rather than the Clean Air Act[.]” Mot. at 6-7; see 76 FED . REG . at 28,663-64. EPA further
acknowledges that “[a]s a general matter” jurisdiction over an action under the APA would lie in
the district courts. Mot. at 6; see Reply at 3 n.1. EPA’s primary argument in its motion to
dismiss, however, is that because the Delay Notice “grow[s] out of” the petitions for review of
the Boiler Rule and CISWI Rule in the court of appeals, this matter “is properly within the D.C.
Circuit’s ancillary jurisdiction.” Mot. at 7 (internal quotations omitted) (alteration in original).
According to EPA, this Court therefore should “defer” to the court of appeals’ ancillary
jurisdiction, a “particularly appropriate” decision in this case “because judicial review of the
Delay Notice could involve at least some consideration of substantive issues . . . that are within
the exclusive jurisdiction of the D.C. Circuit.” Id.
Intervenors filed a brief in support of EPA’s argument, agreeing with EPA that
this Court should defer to the court of appeals’ ancillary jurisdiction, but arguing further that the
10
Clean Air Act actually divests this Court of jurisdiction over this case. See Intervenors’
Response at 1-2. During oral argument, EPA ultimately adopted this same argument, asserting
that Sections 307(b)(1) and 307(d) of the Clean Air Act provide that the court of appeals has
exclusive jurisdiction over review of the Delay Notice.
First, the Court will address EPA’s and Intervenors’ argument that the Clean Air
Act divests this Court of jurisdiction over this case. Having concluded that it does not, the Court
then disposes of EPA’s remaining arguments.
A. Sections 307(b)(1) and 307(d) of the Clean Air Act
“[F]ederal courts are vested with a virtually unflagging obligation to exercise the
jurisdiction given to them.” Hettinga v. United States, 560 F.3d 498, 506 (D.C. Cir. 2009)
(internal quotations omitted). Whether initial subject matter jurisdiction lies in the district courts
or in the courts of appeals “must of course be governed by the intent of Congress and not by any
views . . . about sound policy.” Florida Power & Light Co. v. Lorion, 470 U.S. 729, 746 (1985);
see General Elec. Uranium Mgmt. Corp. v. U.S. Department of Energy, 764 F.2d 896, 903 (D.C.
Cir. 1985) (“[W]e do not rely on factors of policy in lieu of statutory construction” in resolving
the question of subject matter jurisdiction.).
In the specific context of agency review, “[t]he normal default rule is that persons
seeking review of agency action go first to district court rather than a court of appeals.” Micei
Int’l v. Department of Commerce, 613 F.3d 1147, 1151 (D.C. Cir. 2010) (internal quotations
omitted). “[O]nly when a direct-review statute specifically gives the court of appeals
subject-matter jurisdiction to directly review agency action may a party seek initial review in an
11
appellate court.” Id. (internal quotations omitted). Conversely, “where a regulation is not based
on a statutory provision vesting exclusive jurisdiction in the court of appeals, jurisdiction lies in
the district courts.” In re Natural Res. Def. Council, 645 F.3d 400, 404-05 (D.C. Cir. 2011).5
Section 307(b)(1) of the Clean Air Act is a statute that vests exclusive jurisdiction
in the court of appeals. 42 U.S.C. § 7607(b)(1). It provides, among other things, that a petition
for review of “any . . . nationally applicable regulations promulgated, or final action taken, by the
Administrator under [the Clean Air Act] may be filed only in the United States Court of Appeals
for the District of Columbia [Circuit].” Id. Both sides agree that this Court plainly would lack
jurisdiction over Sierra Club’s complaint if the Delay Notice constituted a final action taken
under the Clean Air Act. In issuing the Delay Notice, however, EPA made explicit that it was
not acting under the Clean Air Act: the agency was acting “pursuant to the APA, rather than . . .
the Clean Air Act.” 76 FED . REG . at 28,663 (emphasis added); see also id. at 28,664 (“[I]t is
reasonable for the EPA to exercise its authority to delay the effective dates of the [Boiler Rule]
and the CISWI Rule under the APA for a period that exceeds three months.”) (emphasis added).
Where a case arises under the APA, subject matter jurisdiction comes from the federal question
statute, 28 U.S.C. § 1331, which unambiguously confers jurisdiction to review such a case on
“[t]he district courts.” 28 U.S.C. § 1331 (emphasis added); see, e.g., Beshir v. Holder, 2011 WL
204798, at *7.
5
The “the only exception” to this rule “is when the final agency action will be
exclusively reviewable in the courts of appeals and the court is acting to protect its future
jurisdiction.” In re Natural Res. Def. Council, 645 F.3d at 405. As discussed below, see
Part IV(D), this narrow exception does not apply.
12
Intervenors, and ultimately EPA, attempt to navigate their way around judicial
review in this Court under the APA and the federal question statute by claiming that “when EPA
promulgated the stays at issue . . . , it was acting at one level under the authority of section 705
[of the APA], but at a deeper level also under the authority of section 307(d) [of the Clean Air
Act].” Intervenors’ Response at 7. The basis for this argument appears to be the following:
The rulemaking subsection of the Clean Air Act, Section 307(d), states that certain rulemaking
provisions of the APA, as well as the APA’s scope-of-review standard, do not apply to the
rulemaking subsection of the Clean Air Act. See 42 U.S.C. § 7607(d)(1). Specifically,
Section 307(d) of the Clean Air Act states: “The provisions of section 553 through 557 and
section 706 of Title 5 shall not, except as expressly provided in this subsection, apply to actions
to which this subsection applies.” 42 U.S.C. § 7607(d)(1). Because Section 307(d) of the Clean
Air Act does not mention 5 U.S.C. § 705, Intervenors and EPA conclude: (1) the Clean Air Act
does not proscribe EPA from using 5 U.S.C. § 705 to stay the effectiveness of rules issued under
the Clean Air Act; thus (2) EPA’s authority to use 5 U.S.C. § 705 to stay the Boiler Rule and
CISWI Rule comes from the Clean Air Act, which (3) renders the Delay Notice, a stay issued
under 5 U.S.C. § 705, “at a deeper level” a final action under Section 307(b)(1) of the Clean Air
Act subject to the exclusive jurisdiction of the court of appeals. Intervenors’ Response at 7.
According to EPA and Intervenors, “[b]ecause section 307(d) is obviously part of the [Clean Air
Act], EPA was acting ‘under’ the authority of the [Clean Air Act] within the meaning of section
307(b)(1)” when it issued the Delay Notice. Id.
Assuming for the moment that the Clean Air Act does not proscribe EPA from
using the APA to stay rules pending judicial review — a contested issue raised in the parties’
13
summary judgment papers — that does not convert a stay under the APA into a stay under the
Clean Air Act. While EPA may have the discretion to decide whether to stay a rule under either
the Clean Air Act or the APA, it must suffer the jurisdictional consequences of that decision. By
its terms, the Clean Air Act provides the court of appeals with exclusive jurisdiction only to
review actions taken under the Clean Air Act. See 42 U.S.C. 7607(b)(1). Here, EPA specifically
invoked the APA to avoid the three-month limitation on stays issued under the Clean Air Act.
76 FED . REG . at 28,664 (“[I]t is reasonable for the EPA to exercise its authority to delay the
effective dates of the [Boiler Rule] and the CISWI Rule under the APA for a period that exceeds
three months.”) (emphasis added). Compare 42 U.S.C. § 7607(d)(7)(B) (“The effectiveness of
the rule may be stayed during . . . reconsideration . . . by the Administrator or the court for a
period not to exceed three months.”) (emphasis added). EPA cannot now claim that the Delay
Notice — an action under the APA for the purpose of overcoming an express limitation under the
Clean Air Act — ultimately is an action under the Clean Air Act.
“Congress, acting within its constitutional powers, may freely choose the court in
which judicial review of agency decisions may occur.” Micei Int’l v. Department of Commerce,
613 F.3d at 1151 (internal quotations omitted). Congress’ choice regarding review of agency
action under 5 U.S.C. § 705 is plain: jurisdiction lies in this Court, rather than the court of
appeals. See 28 U.S.C. § 1331. The Delay Notice, in both form and effect, is an action under the
authority of the APA, not the Clean Air Act, and thus the Clean Air Act does not divest this
Court of its jurisdiction under the federal question statute. Where, as here, “a regulation is not
based on a statutory provision vesting exclusive jurisdiction in the court of appeals, jurisdiction
lies in the district courts[.]” In re Natural Res. Def. Council, 645 F.3d at 405.
14
B. Ancillary Jurisdiction
As discussed, EPA’s primary argument is not one of exclusive jurisdiction but
rather ancillary jurisdiction. EPA argues that this case raises questions ancillary to, or growing
out of, the main action in the court of appeals — that is, the petitions for review of the Boiler
Rule and the CISWI Rule — and thus this Court should “defer to the D.C. Circuit’s ancillary
jurisdiction[.]” Mot. at 7. Even assuming that the court of appeals would have such jurisdiction
and would invoke such jurisdiction, the Court cannot rely on the doctrine of ancillary jurisdiction
where, as here, the intent of Congress is clear.
The doctrine of ancillary jurisdiction arises from the principle that bifurcated
jurisdiction between federal district courts and courts of appeals over identical litigation is not
favored. See Oljato Chapter of Navajo Tribe v. Train, 515 F.2d 654, 660 (D.C. Cir. 1975)). The
Supreme Court has invoked ancillary jurisdiction “for two separate, though sometimes related,
purposes: (1) to permit disposition by a single court of claims that are, in varying respects and
degrees, factually interdependent . . . ; and (2) to enable a court to function successfully, that is,
to manage its proceedings, vindicate its authority, and effectuate its decrees[.]” Kokkonen v.
Guardian Life Ins. Co. of Am., 511 U.S. 375, 379-80 (1994). As EPA acknowledges, ancillary
jurisdiction can be invoked only “in the absence of specific evidence of contrary congressional
intent[.]” Florida Power & Light Co. v. U.S. Nuclear Regulatory Comm’n, 470 U.S. at 743; see
Mot. at 6; Opp. at 11.
EPA appears to argue that the relevant statutory scheme is unclear whether
jurisdiction to review the Delay Notice is in this Court or in the court of appeals. See Mot.
at 5-7. Pointing to the text of 5 U.S.C. § 705, EPA claims that the second sentence of that
15
provision supports it conclusion that review of the Delay Notice should take place in the court of
appeals, because it shows that Congress has not unambiguously prescribed which court should
review this action. Id. at 8-9.
In full, 5 U.S.C. § 705 provides:
[1] When an agency finds that justice so requires, it may postpone
the effective date of action taken by it, pending judicial review.
[2] On such conditions as may be required and to the extent
necessary to prevent irreparable injury, the reviewing court,
including the court to which a case may be taken on appeal from or
on application for certiorari or other writ to a reviewing court, may
issue all necessary and appropriate process to postpone the
effective date of an agency action or to preserve status or rights
pending conclusion of the review proceedings.
5 U.S.C. § 705. EPA states: “Although section 705 authorizes the agencies to postpone the
effective date of a rule pending judicial review, the statute does not specify which court should
review such an action. The second sentence of section 705, however, authorizes the court with
jurisdiction to review the rule to postpone the effective date of the rule.” Mot. at 8-9. Thus,
according to EPA, because 5 U.S.C. § 705 does not specify whether this Court or the court of
appeals should review agency stays under that provision, the Court should infer that Congress
intended such review to take place in the court of appeals. See id.
The Court disagrees. The statutory scheme for review of agency stays issued
under the APA leaves no ambiguity. Although EPA correctly points out that the APA does not
say which court should review administrative stays under 5 U.S.C. § 705, it is established that the
APA is not a jurisdiction-conferring statute. Oryszak v. Sullivan, 576 F.3d at 524. The
provision conferring jurisdiction to review agency stays issued under 5 U.S.C. § 705 is the
16
federal question statute in which Congress unambiguously conferred such jurisdiction on “[t]he
district courts.” 28 U.S.C. § 1331. Thus, because EPA chose to issue its stay under the APA,
Congress has made clear that this Court has jurisdiction over this case, and ancillary jurisdiction
does not apply. See Florida Power & Light Co. v. U.S. Nuclear Regulatory Comm’n, 470 U.S.
at 743.
C. Substantive Overlap
In the context of its ancillary jurisdiction argument, EPA asserts that to resolve
this case, the Court “could have to address some issues pertaining to the substance of [the Boiler
Rule and the CISWI Rule.]” Reply at 4. Substantive review of the Boiler Rule and CISWI Rule,
however, is a matter reserved for the exclusive jurisdiction of the court of appeals. See 42 U.S.C.
§ 7607(b)(1); see also Sierra Club v. Johnson, 444 F. Supp. 2d at 60. EPA therefore argues that
because judicial review of the Delay Notice in this Court “could involve at least some
consideration of substantive issues in the Boiler and CISWI rulemakings that are within the
exclusive jurisdiction of the D.C. Circuit,” this Court should defer to the court of appeals’
ancillary jurisdiction. Mot. at 7.
Sierra Club’s complaint makes three independent claims: (1) EPA failed to
provide notice or an opportunity for comment before issuing the Delay Notice, Compl. ¶¶ 33-36;
(2) EPA’s authority to stay the effectiveness of the Boiler Rule and the CISWI Rule is expressly
limited by the Clean Air Act, and EPA’s Delay Notice violates that express limitation, see id.
¶¶ 37-43; and (3) EPA failed to provide adequate justification for the issuance of the Delay
Notice, id. ¶¶ 44-47.
17
The first two claims present discrete legal questions that do not involve any
substantive overlap with the petitions for review of the Boiler Rule and the CISWI Rule.
Although the third claim may present some substantive overlap with the court of appeals, any
such overlap would not create a jurisdictional problem. Indeed, the same substantive overlap is
inherent in the “unusual, bifurcated jurisdictional scheme” that divides jurisdiction under the
Clean Air Act between the federal district and circuit courts. Sierra Club v. Thomas, 828 F.2d
at 794.
As discussed, Sierra Club’s third claim is that EPA failed to justify the issuance of
the Delay Notice. See Compl. ¶ 44-47. Under 5 U.S.C. § 705, an agency may postpone the
effective date of a rule when it finds that “justice so requires.” 5 U.S.C. § 705. To the extent that
this “justice” standard requires that the Court assess the substantive quality of EPA’s Boiler Rule
and CISWI Rule, the Court can do so without interfering with the court of appeals’ exclusive
jurisdiction by employing the same framework utilized in Sierra Club v. Jackson, 2011 WL
181097. There, the question for the Court was whether EPA had met its heavy burden of
demonstrating that it would be impossible to promulgate substantively adequate Clean Air Act
regulations by the Court’s January 2011 deadline. As the Court explained:
Answering this question presents a complication . . . : the Clean
Air Act “‘does not allow district courts to address the content of
EPA’s conduct’” or “‘issue substantive determinations of its own’”
on promulgated regulations. Sierra Club v. Johnson, 444 F. Supp.
2d at 60 (quoting Sierra Club v. Browner, 130 F. Supp. 2d 78, 90
(D.D.C. 2001)). “[S]uch substantive judicial review is expressly
reserved for the appropriate court of appeals.” Sierra Club v.
Browner, 130 F. Supp. 2d at 90. Since the Court cannot “embroil
[itself] in an assessment of the substance of EPA’s actions or
omissions,” id. at 90, the Court must be cautious where, as here,
EPA’s motion for an extension of time focuses, in part, on the
18
substantive quality of its rules. The only way for this Court
simultaneously to comply with 42 U.S.C. § 7607(b) and the court
of appeals’ guidelines in NRDC v. Train[, 510 F.2d 692 (D.C. Cir.
1974)] is to give deference to EPA’s ultimate conclusion on the
substantive merit of its rules.
Sierra Club v. Jackson, 2011 WL 181097, at *7. If, in resolving Sierra Club’s third claim, this
Court is called upon to address matters relating to the substantive quality of EPA’s Boiler Rule
and CISWI Rule, see Mot. at 7-8; Intervenors’ Response at 12-13; Reply at 4, the Court will give
deference to EPA’s “ultimate conclusion on the substantive merit of its rules.” Id.6
D. TRAC Jurisdiction
Finally, EPA argues, primarily in its reply papers and during oral argument, that
jurisdiction exists in the court of appeals under its decision in Telecommunications Research
& Action Center v. FCC (“TRAC”), 750 F.2d 70 (D.C. Cir. 1984). According to EPA,
jurisdiction exists in that court under TRAC because this Court’s decision on the validity of the
Delay Notice “could impact” the pending petitions for review. Reply at 5.
TRAC is inapposite. In TRAC, the court of appeals was asked to decide whether
the district court had jurisdiction to compel the FCC to rule on certain matters that were pending
for an unreasonably long time. See TRAC, 750 F.2d at 72-74. By statute, judicial review of the
FCC’s final action was available only in the court of appeals. Id. at 75. The court of appeals
held: “[W]here a statute commits review of agency action to the Court of Appeals, any suit
seeking relief that might affect the Circuit Court’s future jurisdiction is subject to exclusive
review in the Court of Appeals.” Id. at 78-79; see also American Farm Bureau v. U.S. EPA,
6
The Court need only reach this third claim if the Court concludes that Sierra
Club’s first and second claims lack merit.
19
121 F. Supp. 2d 84, 91 (D.D.C. 2000) (discussing TRAC). “Because unreasonable agency delay
could . . . defeat appellate review of final agency orders, the TRAC court reasoned that the court
of appeals had exclusive jurisdiction to hear suits seeking relief that might affect the circuit
court’s future jurisdiction, even where the agency had not issued a final order.” American Farm
Bureau v. U.S. EPA, 121 F. Supp. 2d at 91; see also McGinn, Smith & Co. v. Financial Indus.
Regulatory Auth., Civil Action No. 11-0825, 2011 WL 1833242, at *5 (D.D.C. May 15, 2011).
TRAC therefore applies only “when [1] the final agency action will be exclusively
reviewable in the court of appeals and [2] the court is acting to protect its future jurisdiction.”
In re Natural Res. Def. Council, 645 F.3d at 405 (emphasis added); see Sierra Club v. Thomas,
828 F.2d at 790 (“TRAC, by its own terms, applies only in situations where a statute commits
review of agency action to the Court of Appeals and thus where interlocutory review of an
unreasonable delay claim is necessary to protect [the Court of Appeals’] prospective
jurisdiction.”) (internal quotations omitted); TRAC, 750 F.2d at 76 (“Because the statutory
obligation of a Court of Appeals to review on the merits may be defeated by an agency that fails
to resolve disputes, a Circuit Court may resolve claims of unreasonable delay in order to protect
its future jurisdiction.”). As the court of appeals recently cautioned, exclusive jurisdiction in the
court of appeals under TRAC is a “narrow exception . . . . not properly extended to cases where
the basis of prospective jurisdiction is a speculative chain of events.” In re Natural Res. Def.
Council, 645 F.3d at 405 (internal quotations omitted).
The first TRAC prong is met in this case: the final agency actions — that is, the
Boiler Rule and the CISWI Rule — are exclusively reviewable in the court of appeals. The
second TRAC prong, however, does not apply because nothing that happens here will affect the
court of appeals’ jurisdiction over the pending petitions for review of the Boiler Rule and the
CISWI Rule. Thus, there is no need for the court of appeals to protect its jurisdiction.
20
V. CONCLUSION
Embracing what she called the “now-infamous ‘duck test,’” Judge Patricia Wald
once said: “WHEREAS it looks like a duck, and WHEREAS it walks like a duck, and
WHEREAS it quacks like a duck, WE THEREFORE HOLD that it is a duck.” Dole v. Williams
Enterprises, Inc., 876 F.2d 186, 188 n.2 (D.C. Cir. 1989) (emphasis in original). EPA acted, by
its own admission, under the Administrative Procedure Act in issuing the Delay Notice, rather
than under the Clean Air Act. It did so because the APA’s administrative stay provision gave
EPA more flexibility than the Clean Air Act, the latter’s stay provision being expressly limited to
a maximum of three months, a time that has since passed in this case. But in its motion to
dismiss, EPA asks this Court to conclude that the agency in fact acted under the Clean Air Act —
the very Act that the agency expressly denied invoking in issuing the Delay Notice. In short,
whereas EPA invoked the APA, and whereas EPA relied on the authority of the APA to
overcome a limitation in the Clean Air Act, and whereas EPA disclaimed reliance on the Clean
Air Act, the Court therefore holds that the Delay Notice was issued under the APA, not the Clean
Air Act. Because EPA’s Delay Notice was issued under the APA, it is subject to judicial review
in this Court under 28 U.S.C. § 1331.
For the foregoing reasons, it is hereby
ORDERED that EPA’s motion to dismiss for lack of subject matter jurisdiction
[Dkt. No. 12] is DENIED.
SO ORDERED.
/s/
PAUL L. FRIEDMAN
DATE: September 27, 2011 United States District Judge
21