Filed 7/7/14 Civilian Conserv. Corps Camp Interest Group v. Valley Center Pauma Unified School Dist. CA4/1
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.
COURT OF APPEAL, FOURTH APPELLATE DISTRICT
DIVISION ONE
STATE OF CALIFORNIA
CIVILIAN CONSERVATION CORPS D064428
CAMP INTEREST GROUP,
Plaintiff and Appellant,
(Super. Ct. No.
v. 37-2013-00044300-CU-PT-NC)
VALLEY CENTER PAUMA UNIFIED
SCHOOL DISTRICT,
Defendants and Respondents.
APPEAL from a judgment of the Superior Court of San Diego County, Earl H.
Maas III, Judge. Affirmed.
Kevin K. Johnson, APLC, Kevin K. Johnson, Jeanne L. MacKinnon; Law Offices
of Kelly Aviles and Kelly Aviles for Plaintiff and Appellant.
Stutz Artiano Shinoff & Holtz, Daniel R. Shinoff and Robert M. Mahlowitz for
Defendants and Respondents.
After defendants Valley Center Pauma Unified School District and its board of
trustees (together District) partially demolished some structures on land the school
district owned, plaintiff Civilian Conservation Corps Camp Interest Group (Petitioner)
filed this action alleging two claims. The first claim, which purported to state a cause of
action under the California Environmental Quality Act (Pub. Resources Code, § 21000 et
seq.) (CEQA), alleged District should have complied with CEQA before partially
demolishing the buildings but did not do so. The second cause of action, which
purported to state claims under the Brown Act (Gov. Code, § 54950 et seq.)1 (Brown
Act), alleged District's board of trustees (Board) discussed and approved the demolition
outside of a public meeting, gave inadequate notice of the public meeting at which the
pre-approved demolition was to be ratified, and did not make certain documents available
to the public.
District demurred to Petitioner's first amended complaint and petition (FAC) and
the trial court sustained the demurrer without leave to amend. Petitioner asserts the
ruling on the demurrer was erroneous as a matter of law, and denying leave to amend to
cure any defects was an abuse of discretion.
1 All further statutory references are to the Government Code unless otherwise
specified.
2
I
FACTUAL AND PROCEDURAL BACKGROUND
A. The Facts2
In 2011, District acquired land from the California Department of Forestry
(property). The property is adjacent to an elementary school under District jurisdiction,
and had seven Depression-era buildings constructed on it that had some historic value.
Around February 5, 2013, District's chief business officer, Ms. Kimball, received a
structural assessment for the buildings that concluded all of the buildings would have
questionable stability during a major seismic event and could contain lead-based paint,
and six of the seven buildings presented significant health and safety risks because of
possible biohazard conditions and compromised structural integrity. On February 8,
2013, District also hired a firm to perform a hazardous building materials evaluation and,
on February 13, 2013, District's Superintendent Obermeyer accepted a proposal for a
contract with AAA Demolition to demolish the buildings but to leave the foundation
2 Because the challenged ruling arises in the context of a demurrer, we accept as
true the material factual allegations of Petitioner's FAC as the operative pleading at issue
(Olszewski v. Scripps Health (2003) 30 Cal.4th 798, 806), and also accept as true all
matters properly subject to judicial notice (Blank v. Kirwan (1985) 39 Cal.3d 311, 318),
but not "contentions, deductions, or conclusions of fact or law." (Moore v. Regents of
University of California (1990) 51 Cal.3d 120, 125.) Moreover, our factual recitation is
guided by the oft stated rule that, when examining the propriety of the ruling on a
demurrer, the courts " 'will not close their eyes to situations where a complaint contains
allegations of fact inconsistent with attached documents, or allegations contrary to facts
which are judicially noticed.' [Citation.] 'False allegations of fact, inconsistent with
annexed documentary exhibits [citation] or contrary to facts judicially noticed [citation],
may be disregarded . . . .' " (Hoffman v. Smithwoods RV Park, LLC (2009) 179
Cal.App.4th 390, 400 (Hoffman).)
3
slabs in place. Before demolition began, District received the results of the hazardous
building materials evaluation that determined the buildings had asbestos and lead-based
paints, and provided those results to AAA Demolition, which relayed the report to an
abatement company for pricing. On February 28, District retained a company to
transport "non friable asbestos waste" and obtained confirmation the electric meters at the
site had been removed and service had been shut off.
At a March 14, 2013, public meeting of District's Board,3 the Agenda listed, as an
item of business under the superintendent's division, that "[t]he Board will hear an update
on the California Department of Forestry Property" for "Information/Possible Action."
At that meeting, three people (including Mr. Vick and Mr. Brown, members of
Petitioner) spoke in favor of preserving the buildings, after which the District presented
its findings on the condition of the buildings. After two more speakers commented on
whether to preserve the buildings, the Board adopted a motion (the directive) that
directed District staff to "move forward and clear the site and prepare the site for future
school district use."4
3 The adequacy of the notice and the Board's activities are at the core of Petitioner's
Brown Act claim.
4 Petitioner has filed a motion for judicial notice in this court seeking judicial notice
of nearly 800 pages of materials, including a transcript of the Board meeting at which the
demolition was approved. We grant the motion as to exhibits F and G for the reasons
discussed at footnote 7, post. However, the remaining documents are either unnecessary
to the issues presented in this appeal (Arce v. Kaiser Foundation Health Plan, Inc. (2010)
181 Cal.App.4th 471, 482 [court "may decline to take judicial notice of matters that are
not relevant to dispositive issues on appeal"]) or are duplicative of documents already a
part of Petitioner's appellate record (Bravo Vending v. City of Rancho Mirage (1993) 16
4
On March 18, 2013, over Petitioner's objections, District began demolition efforts.
By March 22, 2013, the partial demolition of the buildings was completed and the
materials had been removed from the site. However, the foundations and footings, which
were not identified as hazardous, were left in place.
B. Procedural Background
Petitioner filed its initial petition and complaint for injunctive relief in April 2013
alleging, as its first cause of action, that District violated CEQA because it undertook a
project, which it defined as all approvals and work involved in the demolition of the
buildings, without conducting the requisite CEQA review for the project.5 However,
before District responded, Petitioner filed its FAC, which realleged the CEQA claim,
discarded the nuisance claim, and added a claim under the Brown Act. The Brown Act
claim asserted District (1) took action on an item not adequately appearing on the posted
agenda in violation of sections 54954.2 and 54954.3, (2) approved the demolition without
first conducting an open and public meeting in violation of various sections of the Brown
Act, and (3) did not provide documents to the public for inspection as required by section
54957.5.
District demurred to the FAC. It argued the CEQA claim should be dismissed as
moot because the demolition was complete and the physical changes to the environment
Cal.App.4th 383, 406, fn. 12), or are objectionable for other reasons, and we therefore
decline to grant Petitioner's request for judicial notice except as to Exhibits F and G.
5 Petitioner's initial petition and complaint also contained a second cause of action
alleging the demolition created asbestos and lead dust and created a public nuisance.
5
were irreversible. It argued the Brown Act claims should also be dismissed because (1)
the demolition was within the Superintendent's purview, which did not require a Board
directive, and therefore the directive had no prejudicial impact; and (2) even had a Board
directive been required, nullifying the Board's directive would be a purely advisory
opinion and would have no effect because the demolition was complete.
Petitioner opposed the demurrer, arguing the CEQA claim was not moot because
(1) the demolition was not completed because the building foundations were still in place,
and (2) the demolition was merely part of a larger contemplated development project that
would require CEQA review because District was considering placing a "Sports Field
Project" on the property. Petitioner argued the Brown Act claim remained viable because
it was prejudiced, asserting the Board's secret approval of the demolition prejudiced
Petitioner by depriving it of its right to participate in the decisionmaking process.
District's reply asserted Petitioner's arguments were insufficient to demonstrate the
causes of action stated in the FAC were not moot. District noted that Petitioner's pleaded
CEQA claim defined the "project" as the demolition of the structures and, because
judicially noticeable facts showed that project was complete, Petitioner had not overcome
District's mootness argument. District then noted that Petitioner, apparently recognizing
its pleaded CEQA claim was moot, was seeking to avoid the mootness argument by
claiming the demolition was a discrete part of a larger project that began when District
acquired the property in 2011 to build the sports field project. District argued that claim
was not pleaded but, even had Petitioner asserted that claim, it would have been subject
to demurrer for the independent reason that it would have been time-barred. As to the
6
Brown Act claims, District noted Petitioner had not even addressed a fatal flaw raised in
District's demurrer--that nullification of the Board's directive based on inadequate notice
of the proposed action would be a purely advisory opinion and would have no effect
because the demolition was already complete--and that Petitioner's other Brown Act
claims were factually defective.
The court sustained District's demurrer without leave to amend. As to the Brown
Act claim, the court ruled there were insufficient facts alleged, or proffered during oral
argument, to support judicial intervention under the Brown Act. As to the CEQA claim,
the court concluded the project alleged in the complaint (the demolition of the buildings)
had been completed. The court also noted, to the extent any other project is subsequently
pursued on the property, District would likely be required to comply with CEQA, and this
subsequent CEQA process would be the proper forum for discussing the impacts of (and
possible mitigation for) the already completed demolition of the alleged historical
buildings. Accordingly, the court sustained District's demurrer without leave to amend.
II
ANALYSIS OF CEQA CLAIM
A. General CEQA Principles
The Legislature enacted CEQA to "[e]nsure . . . the long-term protection of the
environment . . . ." (Pub. Resources Code, § 21001, subd. (d).) "The foremost principle
under CEQA is that the Legislature intended the act 'to be interpreted in such manner as
to afford the fullest possible protection to the environment within the reasonable scope of
7
the statutory language.' " (Laurel Heights Improvement Assn. v. Regents of University of
California (1988) 47 Cal.3d 376, 390.)
CEQA and its implementing regulations "have established a three-tiered process to
ensure that public agencies inform their decisions with environmental considerations."
(Davidon Homes v. City of San Jose (1997) 54 Cal.App.4th 106, 112 (Davidon Homes).)
The first tier requires the agency to determine whether or not CEQA applies to the
proposed activity or whether the project is exempted by statute or the Guidelines.6
(Davidon Homes, supra, 54 Cal.App.4th at p. 112.)
In cases in which CEQA applies to the project and there is no exemption, "the
agency must proceed with the second tier and conduct an initial study. [Citation.] If the
initial study reveals that the project will not have a significant environmental effect, the
agency must prepare a negative declaration, briefly describing the reasons supporting that
determination. [Citations.] Otherwise, the third step in the process is to prepare a full
environmental impact report (EIR) on the proposed project." (Davidon Homes, supra, 54
Cal.App.4th at p. 113.) The term "project" is given a broad interpretation (RiverWatch v.
Olivenhain Municipal Water Dist. (2009) 170 Cal.App.4th 1186, 1203), and whether an
activity constitutes a "project" is a question of law in the first instance. (Ibid.)
It has been repeatedly observed the EIR is the "heart of CEQA." (Guidelines,
§ 15003, subd. (a); Laurel Heights Improvement Assn. v. Regents of University of
6 All references to Guidelines are to the state CEQA Guidelines, which implement
CEQA, and are codified at California Code of Regulations, title 14, section 15000 et seq.
8
California, supra, 47 Cal.3d at p. 392; Pala Band of Mission Indians v. County of San
Diego (1998) 68 Cal.App.4th 556, 570.) The purpose of the EIR "is to inform the public
and its responsible officials of the environmental consequences of their decisions before
they are made." (Citizens of Goleta Valley v. Board of Supervisors (1990) 52 Cal.3d 553,
564.) When a public project requires an EIR prior to approval, the public agency may not
approve the project without first completing CEQA review or take actions that "give[]
impetus to a planned or forseeable project in a manner that forecloses alternatives or
mitigation measures that would ordinarily be part of CEQA review of that public
project." (Guidelines, § 15004, subd. (b)(2).) However, approval "cannot be equated
with the agency's mere interest in, or inclination to support, a project, no matter how well
defined." (Save Tara v. City of West Hollywood (2008) 45 Cal.4th 116, 136.)
B. Standard of Review
Because this matter arises from a judgment entered after the court sustained
District's demurrer without leave to amend, "[w]e apply well-established rules of review.
'A demurrer tests the legal sufficiency of the complaint. [Citation.] Therefore, we review
the complaint de novo to determine whether it contains sufficient facts to state a cause of
action. [Citation.] "We treat the demurrer as admitting all material facts properly pleaded,
but not contentions, deductions or conclusions of fact or law." [Citation.] The trial court
exercises its discretion in declining to grant leave to amend. [Citation.] If it is
reasonably possible the pleading can be cured by amendment, the trial court abuses its
discretion by not granting leave to amend. [Citation.] The plaintiff has the burden of
9
proving the possibility of cure by amendment.' " (Czajkowski v. Haskell & White, LLP
(2012) 208 Cal.App.4th 166, 173.)
C. Analysis
Petitioner's FAC asserted the project, which it defined as all approvals and work
"related . . . to the approval of demolition and demolition of historic buildings," was
required to have CEQA review, and District did not comply with CEQA before
approving and/or commencing the project. Petitioner sought a writ of mandate
compelling District to vacate and set aside approval of the project and to prepare and
certify a legally adequate EIR for the project.
We conclude the trial court correctly sustained the demurrer to Petitioner's pleaded
CEQA claim because CEQA does not allow for review of a completed project.7 (See,
7 On appeal, Petitioner appears to assert it should have been granted leave to amend
its CEQA claim because events subsequent to the trial court's ruling, of which Petitioner
has requested we take judicial notice, showed Petitioner's FAC was capable of being
amended to plead the existence of the sports field project. Petitioner notes that in
September 2013 the Board issued a "Notice of Preparation and Notice of Public Scoping
Meeting" informing the public that an environmental impact report (EIR) was being
prepared for the proposed sports field project to be built on the property. Although we
grant Petitioner's request for judicial notice as to these documents (Long v. Hultberg
(1972) 27 Cal.App.3d 606, 608 [judicial notice of facts occurring after judgment is
proper]), the existence of these facts does not undermine the trial court's ruling because,
even had Petitioner amended its FAC to allege these facts, the action still would have
been subject to general demurrer, albeit for a different reason: Petitioner could not have
pleaded District failed to comply with CEQA because these documents show the
administrative process, including the requirement that Petitioner exhaust its
administrative remedies (Porterville Citizens for Responsible Hillside Development v.
City of Porterville (2007) 157 Cal.App.4th 885, 909-910), was not yet complete. Even
had Petitioner amended its FAC to allege these subsequent facts, the claim would not
have been ripe at that stage of the proceedings. (Santa Barbara County Flower &
Nursery Growers Assn. v. County of Santa Barbara (2004) 121 Cal.App.4th 864, 875
10
e.g., Hixon v. County of Los Angeles (1974) 38 Cal.App.3d 370, 377-378 [upholding
dismissal of CEQA action demanding an EIR for tree removal where mature trees had
already been removed and replaced with young trees because "preparation of an EIR . . .
would be futile. The project is ended, the trees are cut down and the subject is now moot
insofar as resort to a planning or informational document, which is what an EIR is."];
accord, Environmental Coalition of Orange County, Inc. v. Local Agency Formation
Com. (1980) 110 Cal.App.3d 164, 171-173 [challenge to EIR for annexation moot where
annexation had already occurred and could not be ordered annulled because annexing city
was not a party to the action].) Because the project alleged by Petitioner was fully
complete, Petitioner's CEQA claim was moot because the court was unable to provide
Petitioner with effectual relief and any order would have no practical impact.
(Woodward Park Homeowners Assn. v. Garreks, Inc. (2000) 77 Cal.App.4th 880, 888
["A case is moot when any ruling by this court can have no practical impact or provide
the parties effectual relief [citation] [and] [c]ourts have applied this rule to CEQA
challenges . . . ."] (Woodward Park).)
Petitioner argues the court erred in concluding it could grant no effectual relief
because, under cases such as Bakersfield Citizens for Local Control v. City of Bakersfield
[trial court properly rejected petition without ruling on the merits where no final
determination approving or disapproving project because "[i]n the context of
administrative proceedings, a controversy is not ripe for adjudication until the
administrative process is completed and the agency makes a final decision that results in
a direct and immediate impact on the parties"].) Moreover, we also deny District's
request for judicial notice (seeking judicial notice of District's June 2014 recirculated
draft environment impact report) because our conclusions render moot any need to
consider the draft EIR.
11
(2004) 124 Cal.App.4th 1184 and Woodward Park, supra, 77 Cal.App.4th 880, a court
may require project modification, reconfiguration or restoration of the site to its original
condition. However, in Bakersfield Citizens, the court examined a project only partially
built, rather than one now fully complete.8 Under circumstances analogous to the present
case, courts have rejected the Bakersfield Citizens approach and instead adhere to cases
such as Hixon v. County of Los Angeles, supra, 38 Cal.App.3d 370 and Wilson & Wilson
v. City Council of Redwood City (2011) 191 Cal.App.4th 1559 to conclude the mootness
doctrine applied. (See, e.g., Santa Monica Baykeeper v. City of Malibu (2011) 193
Cal.App.4th 1538, 1547-1551 (Baykeeper).) Petitioner's reliance on Woodward Park
does not detract from our conclusion that the mootness doctrine applies. There, a timely
challenge was filed that resulted in a judgment mandating preparation of an adequate EIR
but, during the pendency of that action, the developer chose to finish constructing the
project. (Woodward Park, supra, 77 Cal.App.4th at pp. 888-889.) As explained by
Baykeeper, although Woodward Park's rejection of the mootness doctrine might have
application when a party seeks " ' " 'to avoid CEQA by continuing with construction of a
project in the face of litigation, delaying preparation of a court-ordered EIR pending
appeal, and then arguing the case is moot because the project has been completed and is
operating' " ' " (Baykeeper, at p. 1550, quoting Woodward Park, at p. 889), when "neither
8 Petitioner attempts to bring its action under the umbrella of Bakersfield Citizens by
arguing on appeal that the project is not complete. However, judicially noticeable facts
demonstrate that the project pleaded by Petitioner's FAC has been completed. To the
extent Petitioner's argument rests on the assertion that an unpleaded project--the sports
field project--is not completed, Petitioner's action would be premature. (See fn. 7, ante.)
12
the city nor the developer proceeded in violation of a court order" (Baykeeper, at p. 1550)
to complete the project, the mootness doctrine as enunciated in cases such as Hixon and
Wilson & Wilson controls. (Baykeeper, at p. 1550-1551.)
Petitioner also relies on the statement in Kriebel v. City Council (1980) 112
Cal.App.3d 693, in which this court rejected a motion to dismiss an appeal for mootness
where work on a project had begun despite a timely appeal challenging the approval of
the project (id at p. 707), to argue the trial court erred in concluding Petitioner's action
was moot. Kriebel is distinguishable for a pivotal reason: the project was only partially
built. In Kriebel, the owners of property next to a proposed subdivision development
sought a writ of mandate to set aside approval of the project by the city council, which
the trial court denied, and a timely appeal was filed but the developer began work on the
project and then moved to dismiss the appeal upon the grounds of mootness. This court,
although affirming the trial court's judgment, denied the motion to dismiss for mootness
and rejected the claim that approval and recording of the final subdivision map or
completion of grading and storm drains on the site mooted the appeal (id. at pp. 697, 701-
707), reasoning that, although the developer was at liberty to proceed with processing the
subdivision map and to commence work, such "land improvement work accomplished
pending the appeal are . . . at the risk of the applicant." (Id. at p. 707.) Because the
project in Kriebel was not complete, but had only proceeded as far as grading the hillside,
the project in Kriebel could still have been either halted or subjected to substantial
mitigation measures. (Accord, Tyler v. Cuomo (9th Cir. 2000) 236 F.3d 1124, 1137
13
[rejecting mootness challenge to project where "changes can still be made to help
alleviate any adverse effects"].)
Here, the project challenged by Petitioner's FAC was complete, and no changes to
the demolition could alleviate any adverse effects from the demolition, and therefore
Kriebel is inapposite. We conclude the trial court correctly ruled that, as a matter of law,
Petitioner's FAC did not state facts upon which any relief might effectively be granted,
and therefore correctly sustained without leave to amend District's demurrer to
Petitioner's CEQA claim.
II
ANALYSIS OF BROWN ACT CLAIM
Petitioner's Brown Act claim first asserted District took action on an item not
adequately appearing on the posted agenda. Petitioner's Brown Act claim also alleged,
on information and belief, that District's Board approved the demolition without first
conducting an open and public meeting, and that Board considered documents without
providing those documents to the public for inspection. The court ruled there were
insufficient facts alleged, or proffered during oral argument, to support judicial
intervention under the Brown Act.
A. General Principles
The Brown Act is designed to encourage public participation in government
decisionmaking. (Bell v. Vista Unified School Dist. (2000) 82 Cal.App.4th 672, 681.)
The Brown Act's provisions include several requirements that Petitioner claimed were
violated by District in connection with Board's March 14, 2013, directive. Petitioner
14
alleged District violated the provisions that: (1) an agenda must be posted at least 72
hours before a regular meeting and forbids action on any item not included on that
agenda (§§ 54954.2, subd. (a) & 54954.3); (2) a majority of the elected members of the
governing body may not, outside of an authorized meeting, discuss, deliberate about, or
take any action on any item of business within the subject matter jurisdiction of the
legislative body either directly or through intermediaries (§ 54952.2); and (3) any
writings distributed to all or a majority of the members of a legislative body in
connection with a matter to be discussed or considered at an open meeting must be made
available for public inspection upon request (§ 54957.5, subd. (a)).
B. Analysis
Petitioner argues the trial court erroneously sustained the demurrer, based on its
determination there were insufficient facts alleged or proffered to support judicial
intervention under the Brown Act, because the trial court misinterpreted the remedies
available to Petitioner. Petitioner argues on appeal its FAC adequately pleaded a claim
on which a court could (1) issue an injunction under section 54960, subdivision (a), to
compel District to comply with sections 54952.2, 54953 and 54957.5 in the future, and
(2) order Board to audio record its closed sessions under section 54960, subdivision (b).9
9 Petitioner's FAC, which alleged the agenda notice was insufficient under sections
54954.2, subdivision (a), and 54954.3, also sought a judgment declaring such action
violated the Brown Act and declaring any action taken by the Board to be null and void.
The trial court concluded, because the buildings had already been demolished, this aspect
of Petitioner's Brown Act claim was moot because a judgment nullifying the March 14
directive would result in nothing. On appeal, Petitioner provides no argument asserting
this aspect of the trial court's ruling (e.g. Petitioner's claim seeking nullification of the
15
Petitioner asserts, because it pleaded (as a past violation of the Brown Act) that the
agenda item was inadequately detailed in violation of sections 54954.2 and 54954.3 and
that District violated other Brown Act provisions, it adequately pleaded a claim for
injunctive and declaratory relief under section 54960 because the FAC further alleged
District is "likely to continue to violate the Brown Act in the future."
Section 54960 provides that an interested person may commence an action "by
mandamus, injunction, or declaratory relief for the purpose of stopping or preventing
violations or threatened violations of this chapter by members of the legislative body . . .
or to determine the applicability of this chapter to ongoing actions or threatened future
actions of the legislative body, or to determine the applicability of this chapter to past
actions of the legislative body, . . . or to compel the legislative body to audio record its
closed sessions as hereinafter provided." (Italics added.) In Regents of University of
California v. Superior Court (1999) 20 Cal.4th 509 (Regents), our Supreme Court
evaluated an analogous statutory scheme and concluded such a scheme is designed to
stop current violations or prevent future violations, and is not designed to remedy past
actions. (Id. at pp. 522-526.)
Petitioner relies on numerous cases, including California Alliance for Utility
Safety and Education v. City of San Diego (1997) 56 Cal.App.4th 1024 (CAUSE) and
March 14 directive was moot because no effective relief could be ordered for the harm
resulting from that directive) was erroneous, and we therefore deemed it abandoned and
do not further consider it. (See, e.g., Rossiter v. Benoit (1979) 88 Cal.App.3d 706, 710-
711 [failure to articulate any legal argument in support of a claim of error may, in the
discretion of the appellate court, be deemed an abandonment of that aspect of the
appeal].)
16
Common Cause v. Stirling (1983) 147 Cal.App.3d 518, to argue that any dispute over the
agency's duties under the Brown Act is sufficient evidence of a threatened future
violation of the Brown Act to support an action for declaratory and injunctive relief even
where, as here, the declaratory and injunctive relief action would have no impact on prior
actions of the agency. (CAUSE, at p. 1030; Common Cause, at p. 524.) However, in
Shapiro v. San Diego City Council (2002) 96 Cal.App.4th 904, this court recognized that
Regents called into question the vitality of Common Cause and CAUSE but concluded the
holdings in Common Cause and CAUSE remained viable after Regents "to the extent that
the showing of past violations that was made related specifically to present or future
ones." (Shapiro, at p. 916, fn. 6.) Thus, in Shapiro, this court concluded a claim under
section 54960 was viable when there is a showing of a pattern of past conduct that
provided an evidentiary basis to support the allegation that the legislative body would
continue violating the Brown Act.10 (Shapiro, supra, 96 Cal.App.4th at p. 915 ["so long
10 Similar considerations apply to other cases cited by Petitioner. For example, in
Frazer v. Dixon Unified School Dist. (1993) 18 Cal.App.4th 781, the court found certain
"gatherings" of a quorum of the board to discuss district business were "meetings" within
the ambit of the Brown Act, and observed that "the District's persistent denials that such a
gathering was a 'meeting' subject to the Brown Act warrants declaratory relief in favor of
appellants." (Id. at p. 798.) Similarly, in Environmental Defense Project of Sierra
County v. County of Sierra (2008) 158 Cal.App.4th 877 (EDP), the plaintiff challenged
whether county's so-called "streamlined zoning process" comported with state law, and
because county claimed it did comply with state law and that it intended to continue to
" ' "be in compliance with state law," ' " an actual controversy was presented over future
actions. (Id. at pp. 885-886.) Significantly, the EDP court contrasted its facts from those
in Burke v. City etc. of San Francisco (1968) 258 Cal.App.2d 32, 34, because in Burke
"no 'actual controversy' existed because there was no basis for the taxpayers/plaintiffs'
assumption that the practices and policies of a former city tax assessor would be followed
17
as the allegations and proof of the legislative body's practices extend to 'past actions and
violations that are related to present or future ones,' the Brown Act provisions are
brought into play to authorize and justify injunctive relief"].) Indeed, the Shapiro court
harmonized CAUSE with Regents and the statutory scheme by noting that, in CAUSE, the
declaratory relief action under section 54960 was deemed ripe, as against a demurrer,
because (1) there was an actual controversy between the parties over whether a past
Brown Act violation had occurred, (2) city failed to concede the facts alleged by
plaintiffs constitute a violation of the Brown Act, and (3) most importantly "the past
action was in fact an ongoing procedure from which the court could reasonably infer, in
light of the city attorney's refusal to change that procedure, that there would be
continuing or future threatened Brown Act violations." (Shapiro, at p. 916, fn. omitted.)
We distill from these authorities the requirement that, to state a viable claim for
declaratory and injunctive relief under section 54960, the plaintiff must allege the
legislative body is engaged in ongoing violations of, or the legislative body threatens to
violate in the future, the provisions of the Brown Act, and to support such allegations
with competent allegations of fact demonstrating either that the legislative body has a
historical pattern of violating Brown Act provisions or that the legislative body has an
ongoing practice or policy that transgresses Brown Act provisions. Measured against this
standard, we conclude the trial court correctly ruled Petitioner's FAC did not allege
by his successor and no reason to suppose that the city supervisors would abuse their
powers.' " (EDP, at p. 886.)
18
sufficient facts, nor did Petitioner proffer during oral argument any additional facts that
would support judicial intervention pursuant to the provisions of section 54960.
The FAC did specifically allege the notice of agenda for the March 14, 2013,
meeting was inadequately detailed as to the item addressing the property, in violation of
sections 54954.2 and 54954.3 of the Brown Act. However, Petitioner did not allege any
other facts demonstrating Board had a historical pattern of providing inadequate details
in its notices of agenda, or any facts that the Board had an ongoing practice or policy of
providing inadequate details in its notices of agenda.11 Accordingly, to the extent
Petitioner's claim for declaratory and injunctive relief under section 54960 rested on an
alleged violation of sections 54954.2 and 54954.3 of the Brown Act, it was inadequate
and the trial court correctly ruled it did not state a claim for declaratory or injunctive
relief to prevent violations or threatened violations of the Brown Act.
Petitioner's FAC also alleged Board violated various sections of the Brown Act by
issuing its directive (to move forward with the demolition) without first conducting an
open and public meeting. This allegation necessarily rests on Petitioner's allegation,
made solely on information and belief, that Board discussed and/or took action prior to
and outside of the March 14 meeting to develop a collective concurrence in violation of
11 Indeed, even had Petitioner made those allegations, the notice of agenda that was
attached to the FAC contained detailed descriptions of other "action" items. When
assessing the propriety of a ruling sustaining a demurrer, we disregard allegations of fact
inconsistent with attached documents or contrary to facts judicially noticed. (Hoffman,
supra, 179 Cal.App.4th at p. 400.)
19
sections 54952.2, 54953 and 54954.2.12 As this court recently explained in Gomes v.
Countrywide Home Loans, Inc. (2011) 192 Cal.App.4th 1149, although a " ' "[p]laintiff
may allege on information and belief any matters that are not within his personal
knowledge, if he has information leading him to believe that the allegations are true " '
[quoting Doe v City of Los Angeles (2007) 42 Cal.4th 531, 550, italics added by Gomes],
. . . a pleading made on information and belief is insufficient if it 'merely assert[s] the
facts so alleged without alleging such information that "lead[s] [the plaintiff] to believe
that the allegations are true." ' " (Id. at pp. 1158-1159, quoting Doe, at p. 551, fn. 5.)
Although the FAC does allege district staff took steps to evaluate the structural
integrity of the structures and to hire contractors in preparation for the demolition, it is
devoid of any facts suggesting any Board member was involved in (or was even apprised
of) the steps taken by staff, much less any facts that could lead a plaintiff to believe as
true the allegation that a group of Board members secretly met in advance of the March
14 public meeting to develop agreement on the course of action to be taken. Because
only the latter type of conduct comprises a "meeting" within the ambit of the Brown Act
(see Frazer v. Dixon Unified School Dist., supra, 18 Cal.App.4th at pp. 796-798 [no
evidence of any type of "collective deliberation" by Board members regarding the
memoranda received from staff; one-way transmission to and solitary review by Board
12 Petitioner does not dispute the March 14 meeting was an "open and public
meeting" of Board, and does not dispute that Board heard from several people (arguing
for and against preservation of the buildings) before it adopted a motion directing District
staff to move forward to clear the site. Accordingly, Petitioner's claim necessarily rests
on the allegation Board as a group discussed and/or took action prior to and outside of the
March 14 meeting on whether to approve the proposed demolition.
20
members of background materials relating to issue not within the ambit of open meeting
laws]), Petitioner's FAC contains no competent allegations to support its claim that any
violation of the open meetings laws occurred.
More importantly, Petitioner did not allege any facts demonstrating Board had a
historical pattern of engaging in secret meetings, or any facts that Board had an ongoing
practice or policy of conducting secret meetings in advance of open meetings to reach
collective concurrences on the action to be taken. To the extent Petitioner's claim for
declaratory and injunctive relief under section 54960 rested on alleged violation of
sections 54952.2, 54953 and 54954.2 of the Brown Act, it was inadequate and the trial
court correctly ruled it did not state a claim for declaratory or injunctive relief to prevent
violations or threatened violations of the Brown Act.
Petitioner's final claim for relief under section 54960 is based on its claim, again
made on information and belief, that certain written materials (specifically, the structural
evaluation, the hazardous materials evaluation, and the contracts relating to the
demolition) were provided to Board members at the March 14 meeting but were not made
available to the public at the meeting, in violation of section 54957.5. There are several
reasons why this allegation does not adequately state a claim for relief under section
54960. First, the allegation that documents were in fact distributed to Board members at
the March 14, 2013, meeting appears to be contradicted by the minutes of that meeting
21
annexed to the FAC,13 which justifies disregard of Petitioner's contrary allegation.
(Hoffman, supra, 179 Cal.App.4th at p. 400.) Second, the FAC was verified by Mr. Vick,
who was actually present (and indeed spoke) at the March 14 meeting, and presumably
witnessed what did and did not occur at that meeting. Because a plaintiff may not allege
facts on information and belief when he has reason to know them directly (see, e.g.,
Thompson v. Sutton (1942) 50 Cal.App.2d 272, 279 [holding that whether plaintiff owns
an easement is a fact "peculiarly within the knowledge of the party," and thus cannot be
alleged on information and belief]; Searcy v. Hemet Unified School Dist. (1986) 177
Cal.App.3d 792, 802 ["facts that are ascertainable from public records may not properly
be pleaded on information and belief"]), it was improper for the FAC to allege on
information and belief that documents were provided to Board members at the March 14
meeting when Petitioner had reason to know directly whether or not such documents
were provided to Board members at that meeting.
Finally, and most significantly, Petitioner did not allege any facts demonstrating
Board had a historical pattern of declining to make available to the public written
materials provided to Board members, or any facts that Board had an ongoing practice or
policy of declining to make available to the public written materials provided to Board
members. To the extent Petitioner's claim for declaratory and injunctive relief under
13 The FAC attached the minutes of the March 14 meeting. Although the minutes
identify (and attach as exhibits to the minutes) numerous documents on other agenda
items presented for approval at the March 14 meeting, the minute entry for the discussion
about directing staff to move forward with site clearance contains no similar
identification of documents.
22
section 54960 rested on an alleged violation of section 54957.5, it was inadequate and the
trial court correctly ruled it did not state a claim for declaratory or injunctive relief to
prevent violations or threatened violations of the Brown Act.
DISPOSITION
The judgment is affirmed. District is entitled to costs on appeal.
McDONALD, J.
WE CONCUR:
HUFFMAN, Acting P. J.
O'ROURKE, J.
23