[Cite as Southeast Land Dev., Ltd. v. Primrose Mgt. L.L.C., 193 Ohio App.3d 465, 2011-Ohio-2341.]
IN THE COURT OF APPEALS OF OHIO
THIRD APPELLATE DISTRICT
HANCOCK COUNTY
SOUTHEAST LAND
DEVELOPMENT, LTD.,
APPELLANT, CASE NOS. 5-10-04
5-10-11
v.
PRIMROSE MANAGEMENT,
L.L.C., ET AL., OPINION
APPELLEES.
Appeals from Hancock County Common Pleas Court
Trial Court No. 2006 CV 00720
Judgments Affirmed in Part, Reversed in Part and Causes Remanded
Date of Decision: May 16, 2011
APPEARANCES:
Matthew C. Huffman and Michael J. Warrell, for appellant.
James K. Wagner and Ronald A. Parsons Jr., for appellees.
WILLAMOWSKI, Judge.
Case Nos. 5-10-04 and 5-10-11
{¶ 1} These appeals are brought by plaintiff-appellant, Southeast Land
Development, Ltd. (“Southeast”), from judgments of the Court of Common Pleas
of Hancock County. For the reasons set forth below, the judgments are affirmed
in part and reversed in part.
{¶ 2} On March 17, 2005, Southeast accepted an offer from Primrose
Management, L.L.C. (“Primrose”) to purchase ten acres of undeveloped real estate
in Hancock County for $500,000. Closing was to be within 120 days of either the
approval of the planned-use development (“PUD”) or the rezoning of the property,
whichever was later. As part of the purchase agreement, Southeast agreed to
provide the following infrastructure improvements to the property on or before
May 31, 2006.
A. A dedicated right-of-way and improved street including
approved curb cuts, to be located along the south lot line of the
property.
B. Infrastructure, including a lift station, of sufficient size and
capacity for Buyer’s intended use of the Property, connected to the
sanitary sewer system of the City of Findlay, Ohio, shall be available
at the lot line of the Property. Buyer shall be responsible for any
connection of tap fees.
C. Infrastructure of sufficient size and capacity for Buyer’s
intended use of the Property, connected to the water system of the
City of Findlay, Ohio, shall be available at the lot line of the
Property. Buyer shall be responsible for any connection or tap fees.
D. Infrastructure of sufficient size and capacity for electrical and
gas service for Buyer’s intended use of the Property, connected to
-2-
Case Nos. 5-10-04 and 5-10-11
the appropriate utility provider, shall be available at the lot line of
the Property. Buyer shall be responsible for any connection fees.
E. Prior to September 1, 2005, or commencement of
construction, which ever [sic] is latter [sic]. Seller shall provide
temporary electrical and water service at the lot line of the Property,
of sufficient size and capacity, so that Buyer can construct its Senior
Retirement Community Project.
F. Seller must act in a diligent, reasonable, and good faith
manner in completing the installation of the infrastructure
improvements. Seller shall continuously monitor the progress of the
construction of Buyer’s Senior Retirement Community facility so
that the infrastructure improvements are completed in a timely
manner in accordance with this agreement.
The contract also provided that Southeast had the right to retain any excess soil
and that it had 30 days from Primrose’s written notice of excess soil to remove the
soil before the right terminated. Primrose assigned the contract to Findlay
Retirement, L.L.C., on February 2, 2006.
{¶ 3} On February 20, 2006, the contract was modified. The modifications
indicated that the electrical service had been made available at the lot line and that
Southeast had therefore satisfied that requirement of the contract. The time for
providing water service was extended to August 1, 2006, but required Southeast to
provide a temporary holding tank if it was not provided by June 1, 2006. The time
for the roadway curbs, sewer service, and gas service was extended until October
1, 2006. The modification also provided that the closing date would be February
-3-
Case Nos. 5-10-04 and 5-10-11
17, 2006, and that time was not of the essence.1 The closing actually occurred on
March 9, 2006.
{¶ 4} In April 2006, Primrose began working the site for its retirement-
home project. On or about May 4, 2006, Matt Carpenter, the assistant chief
engineer for the city of Findlay, issued a “stop work” order. The reasons for the
order were that no bonds had been posted by any party. A meeting was held on
May 17, 2006, to determine what steps to take. After the meeting, Jim Thares, the
owner and president of Primrose, determined that Luke Theis, a part owner of
Southeast, was noncommittal about continuing with the PUD. He then requested
that Todd Jenkins, an engineer project manager for Peterman Associates, prepare
plans for an independent project. These plans were then submitted to the city of
Findlay for approval on June 1, 2006. These plans were approved at the end of
June 2006, and Primrose posted the necessary construction bonds in July 2006.
Southeast did not post its bond. Primrose then proceeded with its independent
project.
{¶ 5} In June or July 2006, Primrose’s excavator wanted to remove the
excess soil from the site. He placed two phone calls to Theis to see if he wanted
the soil. Theis told him he would check and get back to him. Within the next
couple of days, the excavator removed the excess soil and gave it to a third party.
1
Although the modification set a closing date of February 17, 2006, Primrose did not sign it until
February 20, 2006, and Southeast did not sign it until February 23, 2006.
-4-
Case Nos. 5-10-04 and 5-10-11
{¶ 6} On November 28, 2006, Southeast filed a complaint for breach of
contract against Primrose. Southeast alleged that Primrose had breached the
agreement by filing its own plans to construct the utilities and changing the
layouts and by giving away the soil, which the contract specifically stated was
Southeast’s property. On January 2, 2007, Primrose filed its answer and a
counterclaim alleging that Southeast had anticipatorily breached the contract. On
January 30, 2007, Southeast filed its answer to the counterclaim. A trial was held
on the issues from April 28 through April 30, 2008. Both parties filed their
posttrial briefs on September 2, 2008. On June 5, 2009, the trial court entered
judgment in favor of Primrose on all claims. Southeast filed its notice of appeal
from this judgment on July 2, 2009. On January 15, 2010, the trial court granted
Primrose’s application for attorney fees. Southeast filed its notice of appeal from
this judgment on February 16, 2010. The two appeals were combined for
argument purposes, and the following assignments of error are raised.
First Assignment of Error
The trial court erred in finding that [Southeast] committed an
“anticipatory repudiation” of the Agreement.
Second Assignment of Error
The trial court erred in finding that [Southeast’s] own actions
constitute an absolute defense to [Southeast’s] breach of contract
claims asserted against [Primrose].
-5-
Case Nos. 5-10-04 and 5-10-11
Third Assignment of Error
The trial court erred in failing to award reasonable attorneys’ fees
in this matter to [Primrose].
{¶ 7} In the first assignment of error, Southeast alleges that the trial court
erred in finding that it committed an anticipatory breach of the contract. Southeast
argues that the evidence does not support the claim of anticipatory breach.
“Judgments supported by some competent, credible evidence going to all the
essential elements of the case will not be reversed by a reviewing court as being
against the manifest weight of the evidence.” C.E. Morris Co. v. Foley Constr.
Co. (1978), 54 Ohio St.2d 279, 376 N.E.2d 578, at syllabus.
The civil manifest weight of the evidence standard “affords more
deference to the fact-finder” than is afforded in criminal cases. State
v. Wilson, 113 Ohio St.3d 382, 2007-Ohio-2202, 865 N.E.2d 1264,
¶26. The civil standard “tends to merge the concepts of weight and
sufficiency.” Id. In determining whether a civil judgment is against
the manifest weight of the evidence, an appellate court does not
reweigh the evidence. Id.
H. Park Partners, L.L.C. v. Frick, 181 Ohio App.3d 691, 2009-Ohio-1462, 910 N.E.2d
527, ¶20.
Where one party to a contract refuses to perform under the terms
of the contract, an anticipatory repudiation is said to occur. [Blake
Homes, Ltd. v. FirstEnergy Corp., 173 Ohio App.3d 230, 2007-
Ohio-4606, 877 N.E.2d 1041.] An anticipatory breach of contract
by a promisor is a repudiation of the promisor’s contractual duty
before the time fixed for performance has arrived. [Metz v. Am.
Elec. Power Co., Inc., 172 Ohio App.3d 800, 2007-Ohio-3520, 877
N.E.2d 316.] An anticipatory breach of contract is one committed
before the time has come when there is a present duty of
-6-
Case Nos. 5-10-04 and 5-10-11
performance and is the outcome of words or acts evincing an
intention to refuse performance in the future. [McDonald v. Bedford
Datsun (1989), 59 Ohio App.3d 38, 570 N.E.2d 299.] An
anticipatory breach of contract must be an unequivocal repudiation
of the contract. [Sentinel Consumer Prod., Inc. v. Mills, Hall,
Walborn & Assoc., Inc. (1996), 110 Ohio App.3d 211, 673 N.E.2d
967.] A mere request for a change in terms or for cancellation does
not constitute a repudiation. [McDonald, supra.] Similarly, a mere
expression of doubt as to willingness or ability to perform is
insufficient to constitute repudiations of a contract. [Farmers
Comm. Co. v. Burks (1998), 130 Ohio App.3d 158, 719 N.E.2d 980.]
“Repudiation” of a contract is (1) a statement by the obligor to the
obligee indicating that the obligor will commit a breach that would
of itself give the obligee a claim for damages for total breach, or (2)
a voluntary affirmative act which renders the obligor unable or
apparently unable to perform without such a breach. [White Hat
Mgt. L.L.C. v. Ohio Farmers Ins. Co., 167 Ohio App.3d 663, 2006-
Ohio-3280, 856 N.E.2d 991.] * * * A party voluntarily disabling
himself or herself from performing gives the other party an
immediate cause of action. * * *
If a party has reasonable grounds to believe that the other party
will not perform under the contract, that party may demand adequate
assurance of performance from the other; the failure to provide such
assurance is treated as a repudiation of the contract. [Burke v.
Athens (1997), 123 Ohio App.3d 98, 703 N.E.2d 804.]
***
To prevail on a claim of anticipatory breach of contract, a
plaintiff must establish that there was a contract containing some
duty of performance not yet due, and that by word or deed, the
defendant refused future performance, causing damage to the
plaintiff. [Metz, supra].
18 Ohio Jurisprudence 3d (2011), Contracts, Section 237. If an anticipatory
breach of contract is found to occur, the injured party has the option of either
-7-
Case Nos. 5-10-04 and 5-10-11
terminating the contract and suing the breaching party immediately or continuing
the contract and suing the breaching party for damages after the time for
performance has passed. 18 Ohio Jurisprudence 3d (2011), Contracts, Section
238. See also Gilmore v. Am. Gas Mach. Co. (1952), 70 Ohio Law Abs. 569, 129
N.E.2d 93; Roehm v. Horst (1900), 178 U.S. 1, 20 S.Ct. 780, 44 L.Ed. 953; and
Hettrick Mfg. Co. v. Waxahachie Cotton Mills (1924), 1 F.2d 913.
{¶ 8} A meeting was held on May 17, 2006, to discuss the stop-work order.
At that meeting, Theis was questioned concerning the future of the project and
when he would get his bonds posted. Theis testified that he could not post his
bond until the plans were approved and he did not know when that would occur.
Thares testified that he determined after the meeting that he did not think Theis
was committed to proceeding with the project. Thares then instructed the engineer
to create alternative plans for a facility separate from Theis’s plan. These plans
were submitted to the city on June 1, 2006. The approval of the plans was
received at the end of June 2006, and the bond was posted at the beginning of July,
2006. Once the bond was posted, Theis lost the ability to have his plans approved
and perform under the contract. Although Thares admits he never asked Theis
directly whether he intended to complete the contract, he testified that when he
called Theis in July, Theis informed him that he would not be able to meet the
-8-
Case Nos. 5-10-04 and 5-10-11
deadlines. Thares also admitted that Theis never told him one way or another
whether he intended to go forward with the project.
{¶ 9} Robert Miller, the project manager for Charles Construction, was also
at the May 17, 2006, meeting. He recalled that when Theis was questioned about
posting the bond, he said that he would talk to the company owner.2 Jenkins had a
similar recall of the events at the meeting. He testified that Theis said he was not
sure what he was going to do about the bonds. He also testified that sometimes
the bond is posted before the approval and sometimes it is not posted until after.
Posting the bond before approval was the riskier option. He also testified that
Theis never indicated to him that he did not intend to go forward with the project.
Jenkins also did not have any idea why the approval of Theis’s plans took so long.
Also at the meeting was Carpenter. He testified that Southeast had submitted its
plans to the city for review before the June 2005 meeting. The plans were not
approved until June 2006, but no bond was posted. Like Miller, Carpenter
recalled that Theis was asked when Southeast would post its bond. He recalled
that Theis indicated that he would have to check with his business partners. No
question concerning whether Theis would continue the project occurred.
{¶ 10} The evidence in this case does not indicate that Theis or any other
representative of Southeast said that they would not perform under the contract.
2
At that time, Theis only owned 5 percent of the company.
-9-
Case Nos. 5-10-04 and 5-10-11
Theis merely expressed doubts about his ability to perform the contract by the
deadline due to issues with getting his plans approved. The mere expression of
doubt about ability to perform is not a repudiation of the contract. However, there
is some competent, credible evidence that could be considered a repudiation of the
contract in the voluntary actions taken by Theis. The testimony of Jenkins and
Carpenter was that Southeast’s plans were approved in June, although stamped
copies were never sent. Once the plans were approved, Southeast could have
posted the construction bond. The plans of Primrose were approved on the
contingency that Southeast did not post its bond before Primrose did. Southeast
did not post its bond before Primrose posted its bond on July 7, 2006. Thus,
Primrose’s plans became the ones used and Southeast was barred from proceeding.
Southeast could have posted its bond before Primrose, but did not do so.
Therefore, the trial court’s determination is supported by some competent, credible
evidence and will not be reversed on appeal. The first assignment of error is
overruled.
{¶ 11} In the second assignment of error, Southeast alleges that the trial
court erred in determining that Primrose’s breach of the contract was excused by
the anticipatory breach. As discussed above, when an anticipatory breach of the
contract occurs, the injured party can either treat the contract as terminated and sue
for damages or it can continue with the contract and sue for damages after the time
-10-
Case Nos. 5-10-04 and 5-10-11
for performance has passed. However, if one chooses to continue with the
contract rather than terminating it, that party must perform all the conditions of the
contract to be performed by him or her. Hettrick, 1 F.2d 913.
The promisee, if he pleases, may treat the notice of intention as
inoperative, and await the time when the contract is to be executed,
and then hold the other party responsible for all the consequences of
nonperformance; but in that case he keeps the contract alive for the
benefit of the other party as well as his own; he remains subject to
all his own obligations and liabilities under it * * *.
Roehm, 178 U.S. at 11. Although the case cited may be old, the logic is valid.
Take for example, a contract between A and B for A to sell B his house and B to
pay for the house. As part of the contract, A has the right to keep a chandelier and
replace it with another within two weeks. If A takes the chandelier and tells B that
he is not going to replace it, B has two choices. B can terminate the contract and
sue A for any damages. B’s other choice is to wait until the time for performance
has passed and then sue A for the damages. However, B must still perform its
obligations under the contract and pay for the house. In other words, the injured
party can either terminate the entire contract, which extinguishes its duties, or it
can continue with the contract which requires that it fulfill its obligations under the
contract as well. To allow a party to use the prior breach of the other party as a
reason not to perform any of its duties while continuing the contract would lead to
very inequitable results. In the example used above, it would permit B to obtain
-11-
Case Nos. 5-10-04 and 5-10-11
the house without the obligation of paying for it, which was not the original intent
of the contract.
{¶ 12} The contract in this case was a contract for the sale of real estate
along with some construction provisions. The contract contained the following
provision.
The Property shall be conveyed to Buyer or Buyer’s nominee
free and clear of any liens, encumbrances, mortgages, easements, or
special taxes or assessments * * * except for the rights of the Seller
to retain excess soil excavated by Buyer from the real estate to be
conveyed herein. Seller (sic) rights to retain excess soil for its use
shall not however conflict with the Buyer’s development of the real
estate in questions, and should Seller fail to exercise its rights to
remove excess dirt from the real estate to be conveyed to Buyer
herein within thirty (30) days of Buyer’s written notification to
remove said dirt, the rights of Seller shall terminate and Buyer shall
have the right to have the excess dirt removed from the real estate.
At the time of the anticipatory breach, Primrose did not choose to terminate the
contract and seek damages. Instead, Primrose continued with the contract by
retaining possession of the property and having the performance completed by a
third party. Primrose then sued for damages caused by the breach. This choice is
permitted. However, by continuing the contract, Primrose is required to abide by
all the terms of the contract, not just the ones that benefit it.
{¶ 13} Primrose argues that because Southeast anticipatorily breached the
contract, it is not liable for any subsequent breaches. In support of this argument,
Primrose relies upon Farmers Comm. Co. v. Burks (1998), 130 Ohio App.3d 158,
-12-
Case Nos. 5-10-04 and 5-10-11
719 N.E.2d 980. In Farmers, there was a contract for the farmer to sell corn to the
commission, which is a sale of goods, not real estate. The farmer anticipatorily
breached the contract and the commission chose to terminate the contract and sue
for damages immediately. This is one of the two options available to the injured
party when a contract is anticipatorily breached. However, this is not the option
chosen by Primrose. Thus, the holding in Farmers is not applicable to this case.
Primrose was required to complete its obligations under the contract.
{¶ 14} Ten thousand eight cubic yards of soil were removed from the site.
Prior to the removal of the soil, the subcontractor contacted Theis by telephone
about removing the soil. When no response was received within a couple days,
the soil was removed and given to a third party for fill dirt. The parties all agree
that no written notice concerning the soil was ever given to Southeast. Thares
testified that the soil was not usable as compactible fill dirt. However, he admitted
that it was given to the neighbor to use as fill and that he did not know what Theis
wanted to do with the soil. Theis testified that he wanted the soil, which was
sandy, to mix for baseball diamonds. The soil was worth $25 per cubic yard for
that purpose. The evidence of value provided by Theis was not contradicted by
anyone, since the only other testimony about the value was that it had no value as
compactible filler, not that it had no value for any other purpose. Given that there
is no question that Primrose chose to continue the contract and sue for damages;
-13-
Case Nos. 5-10-04 and 5-10-11
Primrose had a duty to fulfill its obligations under the contract. This means that
Primrose had a duty to send Southeast written notice that the excess soil should be
removed within 30 days. Until the written notice was given and the 30 days had
passed, Primrose did not own the soil it removed. By giving it to the neighbor
before Southeast’s rights had terminated, Primrose basically committed
conversion of Southeast’s property. At $25 per cubic yard, the value of this
property to Southeast would have been $250,200. Thus, the trial court erred in
finding that Primrose had not breached the contract as well.3 The second
assignment of error is sustained.
{¶ 15} The final assignment of error raises the question whether the trial
court improperly awarded attorney fees.
Pursuant to the “American Rule,” each party in a lawsuit must
generally bear its own attorney fees. Sorin v. Bd. Of Edn. Of Warrensville
Hts. School Dist. (1976), 46 Ohio St.2d 177, 179, 75 O.O.2d 224, 347
N.E.2d 527. However, a court may be empowered to award attorney fees
where there is a contractual agreement between the parties to shift fees.
McConnell v. Hunt Sports Ent. (1999), 132 Ohio App.3d 657, 699, 725
N.E.2d 1193. Fee-shifting contractual provisions are generally
enforceable “so long as the fees awarded are fair, just and reasonable as
determined by the trial court upon full consideration of all of the
circumstances of the case.” Wilborn v. Bank One Corp., 121 Ohio St.3d
546, 549, 2009-Ohio-306, 906 N.E.2d 396, at ¶8, quoting Nottingdale
Homeowners’ Assn. v. Darby (1987), 33 Ohio St.3d 32, 514 N.E.2d 702,
syllabus.
3
The trial court does find that Southeast had time to remove the soil and was notified verbally. However,
the contract specifically provides that Primrose will give Southeast written notice and that he will have 30
days to remove the soil, not a couple of days. Until the contract terms were met, Primrose had no
ownership rights to that soil.
-14-
Case Nos. 5-10-04 and 5-10-11
Unick v. Pro-Cision, Inc., 7th Dist. No. 09-MA-171, 2011-Ohio-1342, ¶ 25.
Although a contractual provision may entitle a prevailing party to
attorney’s fees, the prevailing party still has the burden of proving
the reasonableness of the fees. Stonehenge Land Co. v. Beazer
Homes Invests., L.L.C., 177 Ohio app.3d 7, 2008-Ohio-148, 893
N.E.2d 855, at ¶45. A trial court’s determination of reasonable
attorney’s fees must generally begin with a calculation of “the
number of hours reasonably expended on the case times an hourly
fee.” Bittner [v. Tri-County Toyota, Inc. (1991), 58 Ohio St.3d 143,
145, 569 N.E.2d 464]. This “lodestar figure” has been determined to
be “[t]he most useful starting point for determining the amount of a
reasonable fee,” because it “provides an objective basis on which to
make an initial estimate of the value of a lawyer’s services.”
Hensley v. Eckerhart (1983), 461 U.S. 424, 433, 103 S.Ct. 1933,
1939, 76 L.Ed.2d 40. See, also, Gisbrecht v. Barnhart (2002), 535
U.S. 789, 800-802, 122 S.Ct. 1817, 152 L.Ed.2d 996.
In order to establish this minimum baseline for the determination
of attorney fees, the party requesting the award bears the burden of
providing evidence of any hours worked that would be properly
billed to the client. The hours worked should be necessary to the
action and should not include “hours that are excessive, redundant,
or otherwise unnecessary.” Hensley at 434. The requesting party
“should exercise ‘billing judgment’ with respect to hours worked, *
* * and should maintain billing time records in a manner that will
enable a reviewing court to identify distinct claims.” Hensley at 437
(citations omitted). * * *
* * * “[T]he burden is on the fee applicant to produce
satisfactory evidence – in addition to the attorney’s own affidavits –
that the requested rates are in line with those prevailing in the
community for similar services by lawyers of reasonably comparable
skill, experience, and reputation.” Blum v. Stenson (1984), 465 U.S.
886, 895-896, 104 S.Ct. 1541, 79 L.Ed.2d 891, at fn. 11.
Once the requesting party has adequately proven an appropriate
number of hours worked and the attorney’s reasonable hourly fee,
the trial court may modify the baseline calculation by considering
-15-
Case Nos. 5-10-04 and 5-10-11
the factors * * * found in Prof. Cond.R. 1.5, which include “the time
and labor involved in maintaining the litigation; the novelty and
difficulty of the questions involved; the professional skill required to
perform the necessary legal services; the attorney’s inability to
accept other cases; the fee customarily charged; the amount involved
and the results obtained; any necessary time limitations; the nature
and length of the attorney/client relationship; the experience,
reputation, and ability of the attorney; and whether the fee is fixed or
contingent. * * *” Bittner [58 Ohio St.3d] at 145-146, [569 N.E.2d
46].
Unick, 2011-Ohio-1342, at ¶ 27-30. If all elements of the required proof are not
provided, the trial court may deny the request for attorney fees in its entirety. Id.
at ¶ 33.
{¶ 16} The reason for the award of attorney fees was that the contract
provided for them.
If any legal action, appeal, mediation, arbitration, or other
proceedings are initiated to enforce or interpret this Agreement, the
prevailing party shall be entitled to recover reasonable attorney and
paralegal fees, court costs, and other reasonably incurred expenses,
in addition to any other relief to which such party may be entitled.
“Prevailing party” means the party who obtains the greater part,
comparatively, of the relief sought by each, whether by compromise
and settlement, mediation, or a determination by any court or
arbitrator. The fees, costs, and expenses shall be included in, and be
a part of, any settlement, order, judgement (sic), or other
determination, which shall also provide for the recovery of any fees,
costs, and expenses incurred in enforcing such settlement, order,
judgement (sic) or determination.
Here, the evidence of the attorney fees were billing statements and an application
for attorney fees with an affidavit of the attorney attached. No additional
-16-
Case Nos. 5-10-04 and 5-10-11
information was provided by Primrose to indicate that the requested rates were in
line with those prevailing in the community for similar services by lawyers of
reasonably comparable skill, experience, and reputation. See Blum, 465 U.S. 886.
Additionally, a review of the statements provided shows that there were instances
where items were billed that may not have been reasonable. The attorneys for
Primrose billed for drafting of letters by associates and then review of the letters
by a partner, for researching nursing-home law, when the issue before the court
was a mere construction contract, not the running of a nursing home, for
researching a worker’s compensation claim, which was also not an issue, for
docketing answer dates, for daily phone calls to the court to check on the status,
and for a new associate to review all the information prepared by a prior associate
when the firm changed associates, even though the head attorney had not changed.
Some of these entries seem to be nothing more than a necessary cost of business
and thus not a cost of this case. No hearing was held on the matter, and the trial
court did not indicate in any way that it had considered the factors set forth in
Prof.Cond.R. 1.5 or reviewed the reasonableness of the fees.
{¶ 17} Moreover, because this court sustained the second assignment of
error, the outcome of the case is affected. Pursuant to the terms of the contract,
only the prevailing party is entitled to attorney fees. The trial court must now
reassess which party, if any, is the prevailing party for the purpose of attorney fees
-17-
Case Nos. 5-10-04 and 5-10-11
or if attorney fees are even justified under the facts of the case. For this reason,
the third assignment of error is sustained.
{¶ 18} The judgment of the Court of Common Pleas of Hancock County
appealed in appellate case No. 5-10-04 is affirmed in part and reversed in part.
The judgment of the Court of Common Pleas of Hancock County appealed in case
No. 5-10-11 is reversed. The matters are remanded to the trial court for further
proceedings.
So ordered.
ROGERS, P.J., and PRESTON, J., concur.
-18-