[Cite as Riley v. Hawley, 2011-Ohio-4422.]
COURT OF APPEALS
ASHLAND COUNTY, OHIO
FIFTH APPELLATE DISTRICT
TIM RILEY :
:
Plaintiff-Appellant :
:
-vs- :
:
JOEL HAWLEY :
:
Defendant-Appellee :
JUDGES:
Hon. W. Scott Gwin, P.J.
Hon. Sheila G. Farmer, J.
Hon. Julie A. Edwards, J.
Case No. 11-COA-010
OPINION
CHARACTER OF PROCEEDING: Appeal from the Municipal Court, Case No.
10-CVI-01443
JUDGMENT: Judgment Vacated; New Judgment Entered
DATE OF JUDGMENT ENTRY: August 30, 2011
APPEARANCES:
For Plaintiff-Appellant For Defendant-Appellee
TIM RILEY, PRO SE JOEL HAWLEY, PRO SE
4525 Gibbs Road 309 Country Road 40
Norwalk, OH 44857 Sullivan, OH 44880
Farmer, J.
{¶1} On October 13, 2010, appellant, Tim Riley, filed a complaint against
appellee, Joel Hawley, alleging breach of contract. The parties had entered into an oral
contract wherein appellant was to provide architectural work and obtain a building
permit for a property appellee was contracted to work on. Appellant alleged that
appellee owed him $2,640.90 for services rendered.
{¶2} On November 9, 2010, appellee filed a counterclaim, alleging that he had
to spend $2,995.00 to remedy appellant's errors.
{¶3} A hearing before a magistrate was held on November 17, 2010. By
decision filed January 20, 2011, the magistrate found against appellant on his complaint
and for appellee on his counterclaim. Appellant filed objections. By judgment order
filed March 9, 2011, the trial court approved and adopted the magistrate's decision and
awarded appellee $2,995.00.
{¶4} Appellant filed an appeal and this matter is now before this court for
consideration. Assignment of error is as follows:
I
{¶5} "THE TRIAL COURT ERRED BY AWARDING THE INCORRECT
AMOUNT OF DAMAGES IN FAVOR OF APPELLEE HAWLEY."
I
{¶6} Appellant claims the trial court erred in its determination of damages as it
did not apply the correct legal standard in awarding damages. We agree in part.
{¶7} A judgment supported by some competent, credible evidence will not be
reversed by a reviewing court as against the manifest weight of the evidence. C.E.
Morris Co. v. Foley Construction Co. (1978), 54 Ohio St.2d 279. A reviewing court must
not substitute its judgment for that of the trial court where there exists some competent
and credible evidence supporting the judgment rendered by the trial court. Myers v.
Garson, 66 Ohio St.3d 610, 1993-Ohio-9.
{¶8} As explained by our brethren from the Ninth District in McKinley v. Brandt
Construction, Inc., 168 Ohio App.3d 214, 2006-Ohio-3290, ¶10:
{¶9} "Any contract to perform work imposes on the contractor the duty to
perform the work in a workmanlike manner. Lin v. Gatehouse Constr. Co. (1992), 84
Ohio App.3d 96, 101, 616 N.E.2d 519. ' "Workmanlike manner" has been defined as
the way work is customarily done by other contractors in the community.' Jones v.
Davenport (Jan. 26, 2001), 2nd Dist. No. 18162, at 8, 2001 WL 62513, citing Salewsky
v. Williams (Sept. 17, 1990), 5th Dist. No. CA-8131, at 4, 1990 WL 139731. When a
contractor fails to perform in a workmanlike manner, the proper measure of damages is
the cost to repair the damage to the condition contemplated by the parties at the time of
the contract. McCray v. Clinton Cty. Home Improvement (1998), 125 Ohio App.3d 521,
523-524, 708 N.E.2d 1075."
{¶10} Appellant stated he drew and submitted plans and obtained the required
building permit in partial performance of the contract. T. at 3. Appellant argues the
work performed enabled appellee to secure the permit and therefore he should be paid
in full. In support of his position, appellant presented Plaintiff's Exhibit C, a copy of the
check he wrote to pay for the permit ($100.00). T. at 5. In the magistrate's
determination of damages, as approved and adopted by the trial court, there was no
acknowledgment of this cost:
{¶11} "Based upon all of the evidence, the Magistrate finds that the Plaintiff is
not entitled to recover any monies from the Defendant. The work he was contracted to
do was done in an unworkmanlike manner and was not fit for the purpose for which it
was intended. It ended up requiring Defendant to hire another architect to complete the
work and fix the errors, and also cost him money. Defendant is not required to pay for
these services.
{¶12} "The Magistrate finds that Defendant is entitled to recover the amount of
$2995.00 from Plaintiff for the damages he incurred as a result of relying upon the faulty
work done by Plaintiff. The evidence establishes that the work was done with errors
and deficiencies and that as a direct result, Defendant incurred costs of $2995.00.
Therefore, the Magistrate finds that the Defendant is entitled to judgment in the amount
of $2995.00 against the Plaintiff, with interest thereon at the statutory rate of 4 percent
per annum until paid, plus costs.
{¶13} "The Plaintiff's claim should be dismissed with costs taxed to Plaintiff."
{¶14} It was appellee's position that appellant did not have that much to do to
obtain the building permit. T. at 7. Once the permit was procured, mistakes were
discovered in the plans. T. at 8. Appellant was contacted to make the necessary
corrections, but he never did them. T. at 8-9, 21. As a result of following the plans, a
required retention pond was oversized and had to be corrected. T at 10, 17;
Defendant's Exhibit A. Appellee had to provide new plans, and paid $425.00 to an
architectural group for the work. T. at 9; Defendant's Exhibits B. The total cost for the
architectural work and to fix the pond amounted to $2,995.00. T. at 13; Defendant's
Exhibit D. It was appellee's opinion that sixty percent of what appellant drew had to be
redone. T. at 22.
{¶15} The trial court awarded appellee damages on his counterclaim pursuant to
Defendant's Exhibit D which included the amounts for the redesign and reconstruction
of the pond.
{¶16} We find the evidence is sufficient to support the trial court's determination
on the costs for repairs as a result of appellant's unsatisfactory plans. However, we
also find the trial court erred in not crediting appellant for the $100.00 permit he
obtained which was used to perform the work. Pursuant to App.R. 12(C), we hereby
adjust the judgment to appellee to $2,895.00 to reflect the $100.00 permit fee.
{¶17} The sole assignment of error is granted in part.
{¶18} The judgment of the Municipal Court of Ashland County, Ohio is hereby
vacated, and judgment is entered for appellee as against appellant in the amount of
$2,895.00.
By Farmer, J.
Gwin, P.J. and
Edwards, J. concur.
_s/ Sheila G. Farmer______________
__s/ W. Scott Gwin___________________
_Julie A. Edwards___________________
JUDGES
SGF/sg 816
IN THE COURT OF APPEALS FOR ASHLAND COUNTY, OHIO
FIFTH APPELLATE DISTRICT
TIM RILEY :
:
Plaintiff-Appellant :
:
-vs- : JUDGMENT ENTRY
:
JOEL HAWLEY :
:
Defendant-Appellee : CASE NO. 11-COA-010
For the reasons stated in our accompanying Memorandum-Opinion, the
judgment of the Municipal Court of Ashland County, Ohio is vacated, and judgment is
entered for appellee as against appellant in the amount of $2,895.00.
s/ Sheila G. Farmer______________
__s/ W. Scott Gwin___________________
_Julie A. Edwards___________________
JUDGES