ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
TTF, L.L.C. ) ASBCA No. 59303
)
Under Contract No. FA825 l-09-C-0048 )
APPEARANCE FOR THE APPELLANT: i\1r. David Storey
President
APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq.
DCMA Chief Trial Attorney
Douglas R. Jacobson, Esq.
Trial Attorney
Defense Contract Management Agency
Bloomington, MN
OPINION BY ADMINISTRATIVE JUDGE PAUL
PURSUANT TO BOARD RULE 12.3
This is a timely appeal of a contracting officer's (CO's) final decision denying
appellant TTF, L.L.C.'s (TTF's) claim that it accepted a convenience termination
settlement under duress. The Contact Disputes Act (CDA), 41 U.S.C. §§ 7101-7109,
is applicable. TTF opted to use the accelerated procedure provided by Board
Rule 12.3, and the parties agreed to submit the appeal on the record under Board
Rule 11. We deny the appeal.
SUMMARY FINDINGS OF FACTS
1. The United States Air Force awarded Contact No. FA8251-09-C-0048 to
TTF on 28 September 2009. This was a firm fixed-price contract in the amount of
$156,000. Its subject matter was three types of aircraft structural panels, each of
which was identified by separate contract line item numbers. Under the contract, TTF
was required to provide three first article test reports, three first articles (FAs), and,
upon approval of the FAs, various production quantities. (R4, tab 2 at G-5 to -10)
2. The contract contained the following pertinent Federal Acquisition
Regulation (FAR) provisions: FAR 52.233-1, DISPUTES (JUL 2002); and
FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT
(FIXED-PRICE) (MAY 2004) (IAW FAR 49.502(b)(l)(i)). The latter clause provided,
in pertinent part:
(a) The Government may terminate performance of
work under this contract in whole or, from time to time, in
part if the Contracting Officer determines that a
termination is in the Government's interest. The
Contracting Officer shall terminate by delivering to the
Contractor a Notice of Termination specifying the extent
of termination and the effective date.
(b) After receipt of a Notice of Termination, and
except as directed by the Contracting Officer, the
Contractor shall immediately proceed with the following
obligations, regardless of any delay in determining or
adjusting any amounts due under this clause:
( 1) Stop work as specified in the notice.
(2) Place no further subcontracts or orders (referred
to as subcontracts in this clause) for materials, services, or
facilities, except as necessary to complete the continued
portion of the contract.
(3) Terminate all subcontracts to the extent they
relate to the work terminated.
(4) Assign to the Government, as directed by the
Contracting Officer, all right, title, and interest of the
Contractor under the subcontracts terminated, in which
case the Government shall have the right to settle or to pay
any termination settlement proposal arising out of those
terminations.
(5) With approval or ratification to the extent
required by the Contracting Officer, settle all outstanding
liabilities and termination settlement proposals arising
from the termination of subcontracts; the approval or
ratification will be final for purposes of this clause.
(6) As directed by the Contracting Officer, transfer
title and deliver to the Government-
2
(i) The fabricated or unfabricated parts, work in
process, completed work, supplies, and other material
produced or acquired for the work terminated; and
(ii) The completed or partially completed plans,
drawings, information, and other property that, if the
contract had been completed, would be required to be
furnished to the Government.
(7) Complete performance of the work not
terminated.
(8) Take any action that may be necessary, or that
the Contracting Officer may direct, for the protection and
preservation of the property related to this contract that is
in the possession of the Contractor and in which the
Government has or may acquire an interest.
(9) Use its best efforts to sell, as directed or
authorized by the Contracting Officer, any property of the
types referred to in subparagraph (b) (6) of this clause;
provided, however, that the Contractor (i) is not required to
extend credit to any purchaser and (ii) may acquire the
property under the conditions prescribed by, and at prices
approved by, the Contracting Officer. The proceeds of any
transfer or disposition will be applied to reduce any
payments to be made by the Government under this
contract, credited to the price or cost of the work, or paid
in any other manner directed by the Contracting Officer.
(R4, tab 2 at G-20)
3. On 13 September 2011, the CO issued Modification No. POOOOl which
changed the delivery schedule, updated the data package, and incorporated additional
clauses (R4, tab 3).
4. On 6 December 2011, the CO forwarded a memorandum to the "DCMA
TERMINATIONS DIVISION" regarding the "Assignment of Termination Case for
Settlement Contract FA8251-09-C-0048." In the "REMARKS" section of her
memorandum, the CO stated:
Delay in issuance of termination is due to discussions
being held with DLA attorney ... and the contractor.
3
Terminated due to poor quality of F .A. submittal and
government unable to sustain T4D.
(R4, tab 4 at G-35, -37)
5. On 5 January 2012, the CO issued Modification No. P00002 which
terminated the contract for convenience. The modification confirmed the
government's "Message" of 8 December 2011 which stated that the contract was being
terminated (R4, tab 5). DCMA was assigned the task of negotiating a settlement of the
termination (R4, tab 4).
6. On 5 January 2012, TTF submitted its first settlement proposal
"INVENTORY BASIS" to DCMA's Termination Contracting Officer (TCO),
Ms. Anita Diaz, on standard form 1435. The total amount which TTF sought through
this proposal was $93,980.50. (R4, tab 6)
7. On 25 June 2012, TTF revised its termination settlement proposal to state a
total amount of$99,909 (R4, tab 24 at G-273). 1 On 29 June 2012, Ms. Diaz requested
that the Defense Contract Audit Agency (DCAA) examine TTF's updated settlement
proposal of25 June 2012 (id.).
8. On 7 December 2012, DCAA issued its audit report ofTTF's revised
settlement proposal. It concluded generally that the proposal was "not acceptable for
negotiation of a fair and reasonable price." Specifically, DCAA stated:
• We questioned the proposed raw material, finished
components, and work-in-process for the following
reasons: certain raw materials were purchased before
contract award, and we could not determine if materials
were purchased for the specific contract; the contractor
did not provide verifiable support for the finished
components; and work-in-process was questioned based
on the results of a technical evaluation (See Exhibit,
Notes 1, 2, 3).
• We questioned general & administrative expenses based
on questioned total cost input base (raw material,
1
On 16 October 2012, TTF, once again, revised its termination settlement proposal to
state a total amount of$124,196.36 (R4, tab 22).
4
• finished components, and work-in-process) (see Exhibit,
Note 4).
(R4, tab 24 at G-273) In monetary terms, DCAA questioned $92,374 ofTFF's total
proposed costs of $99,909 (id. at G-276).
9. On 10 December 2012, the TCO forwarded a copy of DCAA' s audit report
to TTF for its "review and comments" (R4, tab 25). On 12 December 2012, TTF
provided the TCO with its evaluation of the audit report. It disagreed with the
majority ofDCAA's conclusions and requested partial payment in the amount of
$78,300. (R4, tab 26 at G-328-35) On 18 December 2012, the TCO forwarded TTF's
response to DCAA for further evaluation (R4, tab 27).
10. DCAA forwarded its response to the TCO on 20 December 2012. It
noted that its "total settlement amount is unchanged." DCAA also stated:
"We requested numerous time[ s] for the contractor to provide verifiable supporting
documentation ... used to manufacture the finished components ... and the
work-in-process ... but the support was not provided." DCAA also wrote: "We
requested a tour of the facility to observe the physical existence of the tools, but they
were not provided." DCAA stated further: "Additionally, the contractor did not
provide verifiable support for the material used to make the tools." (R4, tab 28 at 1)
On 14 January 2013, the TCO forwarded an email to TTF, requesting the supporting
documentation sought by the auditor. Ms. Diaz concluded by stating that she could
approve a partial payment of90% of the unquestioned settlement expenses.
(R4, tab 29 at 1)
11. On 1February2013, TTF confirmed by email the TCO's authorization ofa
partial payment. It also stated: "TTF will be increasing for the additional time spent
over the past month getting copies of requested documents." (R4, tab 31) By email of
4 February 2013, TTF informed the TCO that it was in complete disagreement with
DCMA's report concluding that the contract was zero percent completed (R4, tab 32).
12. By email dated 11 March 2013, TTF requested that the TCO forward a
settlement offer in writing. It also stated that it had already filed a delay claim "for
this contract under the Contract Disputes Act of 1978." (R4, tab 36 at G-453)
13. By cover letter dated 22 March 2013, the TCO forwarded her "best and
final offer" to TTF. Ms. Diaz offered a total amount of $27,340, which included the
partial payment of $7 ,545. (R4, tab 37 at G-459)
14. On 26 March 2013, TTF stated in writing its "complete disagreement over
the settlement offer." Nevertheless, it requested that the TCO "issue the modification
for a payment of $27,340.00 with the understanding that we do not agree with your
5
settlement decision." It concluded: "TTF continues to reserve all rights afforded
under the contract with regards to your decision." (R4, tab 38)
15. On 28 March 2013, the TCO forwarded Modification No. AOOOOl to TTF
for signature. It provided that TTF would be paid a total amount of $27 ,340 for the
termination of the contract. The modification stated that the settlement amount
"constitutes payment in full and complete settlement of the amount due the Contractor
for the complete termination of the contract," with the exception of the following
rights and liabilities:
(i) All rights and liabilities, if any, of the parties, as
to matters covered by any renegotiation authority.
(ii) All rights of the Government to take the benefit
of agreements or judgments affecting royalties paid or
payable in connection with the performance of the
contract.
(iii) All rights and liabilities, if any, of the parties
under those clauses inserted in the contract because of the
requirements of Acts of Congress and Executive Orders,
including, without limitation, any applicable clauses
relating to: labor law, contingent fees, domestic articles,
and employment of aliens.
(iv) All rights and liabilities, of the parties arising
under the contract and relating to reproduction rights,
patent infringements, inventions, or applications for
patents, including rights to assignments, invention reports,
licenses, covenants of indemnity against patent risks, and
bonds for patent indemnity obligations, together with all
rights and liabilities under the bonds.
(v) All rights and liabilities of the parties, arising
under the contract or otherwise, and concerning defects,
guarantees, or warranties relating to any articles or
component parts furnished to the Government by the
Contractor under the contract or this agreement.
(vi) All rights and liabilities of the parties under the
contract relating to any contract termination inventory
stored for the Government.
6
(vii) All rights and liabilities of the parties under
agreements relating to the future care and disposition by
the Contractor of Government-owned property remaining
in the Contractor's custody.
(viii) All rights and liabilities of the parties relating
to Government property furnished to the Contractor for the
performance of this contract.
(ix) All rights and liabilities of the parties under the
contract relating to options (except options to continue or
increase the work under the contract), covenants not to
compete and covenants of indemnity.
(x) All rights and liabilities, if any, of the parties
under those clauses of the contract relating to price
reductions for defective cost or pricing data.
(R4, tab 40 at G-472-74) There is no record evidence demonstrating that any of these
exceptions was applicable to the parties' negotiations.
16. On 3 April 2013, TTF appealed its delay claim on a deemed denial basis.
The Board docketed the appeal as ASBCA No. 58613 on 9 April 2013. (Gov't br.,
ex. G-1, ii 9)
17. By email dated 5 April 2013, TTF forwarded a signed page of Modification
No. AOOOOl to the TCO. TTF requested that the TCO sign the document and return it
to TTF so that it could process it for payment. The email contained only the first page
of the modification. (R4, tab 41)
18. On 8 April 2013, the TCO signed bilateral Modification No. AOOOO 1 and
forwarded a copy of the entire modification to TTF (R4, tab 42).
19. On 8 April 2013, the TCO received the first two pages of the modification
from TTF. On those pages, TTF wrote that it was not certifying the costs referenced in
the modification, that it was reserving its rights under the CDA, and that it had already
filed a CDA claim. (R4, tab 43 at G-484)
20. On 9 April 2013, the TCO executed unilateral Modification No. A00002
which rescinded Modification No. AOOOO 1 in its entirety (R4, tab 44 at G-490). In a
letter of 10 April 2013, the TCO explained that she had rescinded Modification
No. A00002 because TTF "made unauthorized changed to pages 2 and 3" which it had
not included in its email of 5 April 2013 (id. at G-492).
7
21. By email dated 12 April 2013, the TCO transmitted bilateral Modification
No. A00003 to TTF. In her cover letter, she wrote:
Previous Modification No. AOOOOl was rescinded because
you made changes on the modification transmitted to me
by mail. I am forwarding Modification No. A00003 for
you to endorse as is and return. Please sign the first page,
initial and date pages 2 and 3, and return the entire
modification to me. I will not sign it if you indicate you
are signing the modification under duress and will, instead,
process a settlement by determination under
FAR 49.109-7.
(R4, tab 45)
22. On 15 April 2013, TTF signed and initialed Modification No. A00003
without any reservations whatsoever. In its cover letter transmitting the executed
modification, TTF stated: "Please sign and send back asap, so that TTF can submit
into WA WF for payment." (R4, tab 46)
23. On 16 April 2013, the TCO executed Modification No. A00003 and
transmitted it to TTF for its use in invoicing for payment (R4, tab 4 7).
24. On 29 April 2013, the government paid TTF $19,795. It had previously
paid TTF $7,545 under this contract. (R4, tab 50)
25. On 12 August 2013, the Board denied TTF's delay claim in ASBCA
No. 58613. This was an unpublished decision issued pursuant to Board Rule 12.2.
(Gov't br., ex. G-1)
26. On 13 February 2014, TTF filed a claim in the amount of $95,710.55,
contending that it had accepted the settlement amount of $19,795 because it was under
financial duress (R4, tab 51 ).
27. On 1 May 2014, the TCO issued a final decision denying TTF's claim. She
found that TTF's claim was barred by the doctrines of accord and satisfaction and
release. The TCO also found the execution of the modification was intentional and
voluntary and not the product of duress. (R4, tab 52 at G-524-25)
28. This appeal followed.
8
DECISION
The only issues before the Board are whether bilateral Modification
No. A00003 constituted an accord and satisfaction of TTF's termination settlement
claim and whether the bilateral agreement was invalidated by duress.
With respect to an accord and satisfaction, the basic elements are proper subject
matter, competent parties, a meeting of the minds, and consideration. DTC Engineers
& Constructors, LLC, ASBCA No. 57614, 12-1BCA,-r34,967 at 171,898-99. Here,
all of these elements have been met. Further, TTF accepted the consideration offered
by the TCO as "payment in full and complete settlement of the amount due the
Contractor for the complete termination of the contract" (R4, tab 46 at 499).
Moreover, TTF signed and initialed the modification, as requested by the TCO,
without any reservations whatsoever (finding 21 ). Based upon these facts, the Board
concludes, as a matter of law, that TTF's claim is barred by the doctrine of accord and
satisfaction.
Regarding the issue of duress, TTF bears the burden of proof. Aerospace
Engineering & Support, Inc., ASBCA No. 45382, 95-2 BCA i-127,648 at 137,821.
Accordingly, it must establish that it involuntarily accepted the modification's terms,
that circumstances permitted no other alternative, and that such circumstances resulted
from the other party's actions. PNL Commercial Corp., ASBCA No. 53816, 04-1
BCA ,-r 32,414 at 160,457. Initially, we note that TTF has not proffered any evidence
that it involuntarily accepted the modification's terms. In fact, it signed and initialed
the modification without any reservations whatsoever (finding 22).
Regarding alternatives, as the government suggests in its brief, TTF could have
perfected an appeal with this Board (gov't br. at 15-16). As evidenced by the fact that
it had previously filed a delay claim under this contract, it was certainly familiar with
this process (findings 16, 25).
Finally, there is no evidence of coercion on the TCO's part. In fact, when she
transmitted the modification to TTF, Ms. Diaz stated that she would not sign the
modification "if you indicate that you are signing ... under duress and will, instead,
process a settlement by determination under FAR 49 .109-7" (finding 21 ). Under these
circumstances, TTF 's contentions that it was under duress must fail.
9
CONCLUSION
The appeal is denied.
Dated: 11 December 2014
MICHAEL T. PAUL
Administrative Judge
Armed Services Board
of Contract Appeals
!concur~
RICHARD SHACKLEFORD
Administrative Judge
Vice Chairman
Armed Services Board
of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 59303, Appeal ofTTF,
L.L.C., rendered in conformance with the Board's Charter.
Dated:
JEFFREY D. GARDIN
Recorder, Armed Services
Board of Contract Appeals
10