J-S26018-15
NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
SCOTT R. MONGER AND HOWARD S. IN THE SUPERIOR COURT OF
MORRIS PENNSYLVANIA
Appellants
v.
UPPER LEACOCK TOWNSHIP
Appellee No. 1623 MDA 2014
Appeal from the Judgment Entered on August 28, 2014
In the Court of Common Pleas of Lancaster County
Civil Division at No.: 2012-01094
BEFORE: OTT, J., WECHT, J., and JENKINS, J.
MEMORANDUM BY WECHT, J.: FILED APRIL 28, 2015
In this action, Appellants have raised several contract claims against
Appellee, Upper Leacock Township (“the Township” 1), that arise out of the
Township’s review of a land use application for a proposed seventy-one-acre
real estate development that was submitted by Appellants through their
business entity. Because we find that Appellants’ claims are inextricably
intertwined with the land use application process, which is governed by
Pennsylvania statute and local ordinance, we find that Appellants’ claims lie
____________________________________________
1
For simplicity’s sake, we use the Township to refer interchangeably to
Upper Leacock, as a municipal entity, the Upper Leacock Planning
Commission, and the Upper Leacock Board of Supervisors, the latter two of
whom reviewed and acted upon Appellants’ land use application.
J-S26018-15
in the exclusive jurisdiction of the Commonwealth Court. Accordingly, we
transfer this case to that court.
The land use application process undisputedly was governed by the
Township’s Subdivision and Land Development Ordinance (“SALDO”). In
connection with their November 5, 2007 application, Appellants sought
waivers of certain SALDO requirements. The Township issued a conditional
approval of the plan granting one waiver but denying another, which had the
effect of requiring Appellants to revise their plan to satisfy the relevant
ordinance. Thereafter, Appellants submitted a revised plan and requested
an extension from the SALDO-prescribed time period for complying with the
Township’s conditions. The extension was granted, but Appellants failed to
satisfy the conditions before the expiration of the extended deadline and did
not request a second extension. Thus, on May 1, 2008, after the expiration
of the time limit for establishing compliance, the Township voted to
disapprove the plan. A written decision documenting the Township’s
decision was mailed to Appellants the next day. See Trial Court Opinion
(“T.C.O.”), 8/28/2014, at 3-5.
Pursuant to 53 P.S. § 11002-A(a), Appellants had thirty days from the
date of the Township’s decision to appeal that decision “to the court of
common pleas of the judicial district wherein the land is located.” Section
11002-A(a) specifies that “[i]t is the express intent of the General Assembly
that, except in cases in which an unconstitutional deprivation of due process
would result from its application, the 30-day limitation in this section should
-2-
J-S26018-15
be applied in all appeals from decisions.” The decisions to which it refers are
“land use decisions rendered pursuant to Article IX,” 53 P.S. §§ 10901, et
seq., which governs zoning hearing board and other administrative
proceedings. See 53 P.S. §§ 10909.1(a)(5)-(6) (conferring the zoning
hearing board with exclusive jurisdiction over applications for variances or
special exceptions under the governing zoning ordinance). Appellants took
no other action in furtherance of seeking review of the Township’s decision.
On June 27, 2012, Appellants in their individual capacities filed a
complaint against the Township asserting breach of express contract, breach
of implied contract, and promissory estoppel. The Township filed preliminary
objections, which the trial court denied without prejudice. Following
discovery, on March 27, 2014, the Township filed a motion for summary
judgment alleging (1) that Appellants’ claims were time barred under the
Municipalities Planning Code (“MPC”), 53 P.S. §§ 10101, et seq.; (2) that the
claims were time barred under the governing statute of limitations; and (3)
that the complaint failed to state a cause of action upon which relief could be
granted. See T.C.O. at 5.
On May 19, 2014, the trial court held a hearing on the Township’s
motion. At that hearing, Appellants asserted that their claims were based
upon the proposition that the parties entered into a contract when
Appellants submitted their land use application, obligating the Township to
act in good faith in reviewing that application. Thereafter, the Township
requested leave to amend its motion for summary judgment to assert that
-3-
J-S26018-15
Appellants lacked standing to bring the instant law suit. The parties filed
supplemental briefs on that issue. See id. at 5-6.
Thereafter, on August 28, 2014, the trial court entered summary
judgment in favor of the Township. It so ruled on the basis that Appellants,
in violation of 53 P.S. § 11002-A(a), had failed to appeal the Township’s land
use decision to the court of common pleas within thirty days of the
Township’s adverse decision. It further noted that “The procedures for a
land use appeal in the MPC are ‘the exclusive mode for securing review of
any decision rendered pursuant to Article IX of the MPC.’” T.C.O. at 7
(quoting 53 P.S. 11001-A; emphasis added by the trial court). Appellants
filed a timely notice of appeal to this Court on September 25, 2014. On
September 29, 2014, the trial court entered an order directing Appellants to
prepare and file a concise statement of the errors complained of on appeal.
Appellants timely complied on October 20, 2014. In lieu of a full
Rule 1925(a) opinion, on October 27, 2014, the trial court issued a brief
statement indicating that its August 28, 2014 opinion was sufficient to
explain its reasoning. Accordingly, this case is ripe for our review.
Appellants raise the following issue:
Did the lower court commit legal error and/or abuse its
discretion in dismissing the entire Complaint and the common
law claims pleaded therein, by treating those claims as being in
the nature of an appeal of an “adverse land use decision” which
involved a prerequisite appellate process pursuant to the [MPC],
when Appellants’ common law contract-based claims were
propounded to redress [the Township’s] improper conduct—
irrespective of any land-use decisions or purportedly required
statutory appellate process?
-4-
J-S26018-15
Brief for Appellants at 2.
Before reaching the merits, we must address the Township’s
contention that this case should be transferred to the Commonwealth Court,
because its subject matter falls within that court’s exclusive jurisdiction. The
governing statute provides, in relevant part, as follows:
(a) General rule.—Except as provided in subsection (b), the
Commonwealth Court shall have exclusive jurisdiction of appeals
from final orders of the courts of common pleas in the following
cases
****
(4) Local government civil and criminal matters.—
(i) All actions or proceedings arising under any
municipality, institution district, public school, planning
or zoning code or under which a municipality or other
political subdivision or municipality authority may be
formed or incorporated or where is drawn in question
the application, interpretation or enforcement of any:
(A) statute regulating the affairs of political
subdivisions, municipality and other local authorities
or other public corporations or of the officers,
employees or agents thereof, acting in their official
capacity;
(B) home rule charter or local ordinance or
resolution . . . .
42 Pa.C.S. § 762.
Despite the fact that the Township specifically contends that this case
should be heard by the Commonwealth Court rather than this Court, see
Brief for Township at 12-14, Appellants do not address the issue in their
primary brief, and have not filed a reply brief. Nonetheless, insofar as the
-5-
J-S26018-15
trial court entered summary judgment on the basis that Appellants’ claims
were rooted in the Township’s land use decision, and consequently were
waived because Appellants failed to follow the prescribed procedure for
appealing that decision, an argument that subsection 762(a)(4)(i) does not
apply in this matter may be teased out from Appellants’ brief, which
naturally takes up that issue as presented. That is to say, if Appellants are
correct that the land use decision, as such, is not implicated in this case, and
that their claims sound solely in contract and/or estoppel, then section 762
might not govern the appellate jurisdictional question. However, for the
reasons that follow, we do not believe that we are the proper venue to test
this argument, not least because we find it facially unpersuasive, although
we do not intend to answer the question definitively.
A brief review of Appellants’ complaint supports our determination.
After a lengthy recitation of factual allegations aimed at establishing the
Township’s bad faith, Appellants set forth, in relevant part, the following
allegations in support of their claim for breach of express contract:
40. . . . . [Appellants] and [the Township] entered into an
express contract whereby [Appellants] submitted written
applications for land use approval, [Appellants] paid to [the
Township] the consideration of the required application and
review fees and [Appellant] delivered to [the Township] the
required land use plans and specifications, plus revisions thereto,
and [the Township] agreed to a review of the application and
supporting materials in accordance with all relevant legal
requirements.
41. In Pennsylvania, every party to a contract has an implied
duty of good faith and fair dealing in performance of contract
obligations.
-6-
J-S26018-15
42. In Pennsylvania, a municipality also has a duty of good
faith in the review and processing of a land use
application.
Complaint at 7-8 (emphasis added). In support of its claim for breach of
implied contract, in addition to the above allegations, Appellants asserted
that they and the Township “entered into an implied contract regarding
[the Township’s] review and processing of [Appellants’] land use
applications.” Id. at 8 ¶ 46 (emphasis added); see id. at 8 ¶ 47
(“[Appellants] undertook a series of actions . . . regarding [the
Township’s review and processing of [Appellants’] land use
applications.” (emphasis added)). Finally, in support of their claim for
promissory estoppel, Appellants alleged, inter alia, that it was foreseeable
that the Appellants “would have relied on the various promises by [the
Township] in order to induce [Appellants] to make their decisions and
expenditures regarding [Appellants’] land use applications, plans and
revisions, in light of the specific issues and concerns [that the
Township] had communicated to [Appellants].” Id. at 10 ¶ 57
(emphasis added).
It is true, as the trial court noted, that municipal bodies owe a duty of
good faith in reviewing a party’s land use application. See T.C.O. at 8 n.1
(citing Highway Materials v. Bd. of Supervisors, 974 A.2d 539
(Pa. Cmwlth. 2009); Raum v. Bd. of Supervisors of Tredyffrin Twp., 370
A.2d 777 (Pa. Cmwlth. 1977). However, we fail to see how resolving
allegations of bad faith in this context would not require a fact-finder to
-7-
J-S26018-15
measure the Township’s conduct relative to its legal obligations as set forth
in the MPC and other authorities. This, in turn, implicates the very concerns
that limn the boundary between our jurisdiction and that of our
Commonwealth Court.
Appellants’ argument on appeal only reinforces that this case belongs
before the Commonwealth Court. Regardless of the legal principle that
Appellants asserted as a basis for relief, their argument, perhaps
necessarily, is replete with technical arguments regarding, e.g., the
availability of an estoppel remedy in cases implicating the MPC. Appellants
assert the lack of on-point precedent on that question, but suggest that this
Court may find guidance in decisions on related topics such as Perrige v.
Horning, 654 A.2d 1183 (Pa. Super. 1995), J.B. Stevens v. Rullo, 658
A.2d 460, 462 (Pa. Cmwlth. 1995), and Day v. Civil Service Commission
of Borough of Carlisle, 931 A.2d 646 (Pa. 2007). Not surprisingly, the
second of these cases was decided by the Commonwealth Court and the
third contained our Supreme Court’s review of a Commonwealth Court
decision. In the one of these cases that was decided by this Court, we
expressly held that the restrictive covenant dispute at issue in that case did
not, under the MPC, fall within the exclusive jurisdiction of the township
board of supervisors. See Perrige, 654 A.2d at 1186-87. Conversely, the
land use review that Appellants allege was conducted in bad faith in this
matter undisputedly was undertaken by the Township pursuant to its
jurisdiction and authority under the MPC.
-8-
J-S26018-15
Notwithstanding the clear mandate of 42 Pa.C.S. § 762, it is well-
established that this Court has discretion to retain jurisdiction over an appeal
that more properly would have been filed in the Commonwealth Court under
section 762. See Wilson v. Sch. Dist. of Phila., 600 A.2d 210, 211
(Pa. Super. 1991). In determining whether to retain a case encompassed by
section 762, “we must balance the interests of the parties and matters of
judicial economy” against the following non-exhaustive list of factors:
(1) whether the case has already been transferred; (2) whether
our retention will disrupt the legislatively ordained division of
labor between the intermediate appellate courts; and
(3) whether there is a possibility of establishing two conflicting
lines of authority on a particular subject.
Trumbull Corp. v. Boss Constr., Inc., 747 A.2d 395, 399
(Pa. Super. 2000) (citations omitted). Furthermore, we frequently have
transferred cases when we perceived that the Commonwealth Court had
greater expertise in the issues at bar. See, e.g., Osser v. City of Phila.,
441 A.2d 1317, 1318 (Pa. Super. 1982).
It clearly is the case that MPC cases are encompassed by section 762
and consequently are decided far more frequently by the Commonwealth
Court, which reviews such cases according to its own extensive body of
precedent concerning such matters. Thus, the Commonwealth Court’s
greater expertise in such matters cannot be denied. Furthermore, although
we might issue a non-binding memorandum decision on the merits that
would avoid the prospect of conflicting binding lines of authority, there
-9-
J-S26018-15
remains a risk that such a memorandum would be at odds with related
precedent issued by the Commonwealth Court, which in turn could mislead
members of the bench and bar in future cases.
To be clear, our review of precedent and the parties’ arguments
suggests that the availability of contract or quasi-contract remedies under
these circumstances and whether they are materially separable from the
land use decision underlying the allegations remain open questions. Those
questions’ resolutions ultimately may have appellate jurisdictional
implications for future cases. However, those questions inherently implicate
the scope and effect of the MPC and, as such, fall within the Commonwealth
Court’s greater expertise in that subject matter. Indeed, that the court
deciding this matter may issue new precedential authority under the MPC
militates strongly in favor of, rather than against, transferring this case to
the Commonwealth Court, which is more fit to decide in the first instance the
relationship of these claims to the MPC. See Eldred Township v. Monroe
County, 478 A.2d 1357, 1358 (Pa. Super. 1984) (noting the Commonwealth
Court’s greater expertise in the subject matter and emphasizing that transfer
was preferable to “prevent unnecessary confusion and lack of coordination”
because the Commonwealth Court would “be the forum for similar cases in
this area of the law”). Accordingly, we transfer this case to the
Commonwealth Court.
- 10 -
J-S26018-15
Case transferred.
Judgment Entered.
Joseph D. Seletyn, Esq.
Prothonotary
Date: 4/28/2015
- 11 -