ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Dellew Corporation ) ASBCA No. 58538
)
Under Contract No. FA52 l 5-08-C-0008 )
APPEARANCES FOR THE APPELLANT: Jonathan A. DeMella, Esq.
Kate H. Kennedy, Esq.
Dorsey & Whitney, LLP
Seattle, WA
James F. Nagle, Esq.
Oles Morrison Rinker & Baker, LLP
Seattle, WA
APPEARANCES FOR THE GOVERNMENT: Lt Col James H. Kennedy III, USAF
Air Force Chief Trial Attorney
Michelle D. Coleman, Esq.
Christine C. Piper, Esq.
Trial Attorneys
OPINION BY ADMINISTRATIVE JUDGE PAGE ON THE PARTIES'
CROSS-MOTIONS FOR SUMMARY JUDGMENT
Dellew Corporation (Dellew or appellant) seeks to recover $279,558 in
unrecovered amounts and settlement and proposal preparation costs following the
termination of its contract for the convenience of the Department of the Air Force,
15th Contracting Squadron (AF or government). The government moves for summary
judgment (gov't mot.), arguing that appellant cannot recover these costs; appellant
opposes the motion and seeks partial summary judgment (app. opp'n). We grant the
government's motion in part and deny appellant's cross-motion.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
1. On 18 July 2008, the government and Dellew entered into Contract
No. FA5215-08-C-0008, a firm-fixed-price FAR Part 12 commercial items contract to
provide Awards and Decorations (A&D) and Personnel Systems Management (PSM)
support services for Military Personnel Flight at various Air Base locations (R4, tab 1;
gov't mot. at 9; app. opp'n at 5, ~ 2). 1
2. Contract line item number (CLIN) 4001 provides for A&D and PSM support
services at Eielson and Elmendorf Air Force Bases (AFBs) in Alaska for option year
four. SubCLIN 4001AA is listed as 12 one-month units at a unit price of $18,887.52
for A&D and PSM support services at Eielson AFB. SubCLIN 4001AB lists a unit
price of $25,54 7.17 for 12 one-month units to provide A&D and PSM support services
at Elmendorf AFB. CLINs 4002-4005, and their respective subCLINs, list pricing for
A&D and PSM support services at an additional seven AFBs. All CLINs provide for
12 one-month units to be exercised during the period of performance under option year
four from 1April2012 - 31 March 2013. (R4, tab I at 27-31) 2
3. The contract incorporated by reference FAR clause 52.212-4, CONTRACT
TERMS AND CONDITIONS - COMMERCIAL ITEMS (FEB 2007). The clause states in
pertinent part:
(I) Termination for the Government's convenience.
The Government reserves the right to terminate this
contract, or any part hereof, for its sole convenience. In
the event of such termination, the Contractor shall
immediately stop all work hereunder and shall immediately
cause any and all of its suppliers and subcontractors to
cease work. Subject to the terms of this contract, the
Contractor shall be paid a percentage of the contract price
reflecting the percentage of work performed prior to the
notice of termination, plus reasonable charges the
Contractor can demonstrate to the satisfaction of the
Government using its standard record keeping system,
have resulted from the termination. The Contractor shall
not be required to comply with the cost accounting
standards or contract cost principles for this purpose. This
paragraph does not give the Government any right to audit
the Contractor's records. The Contractor shall not be paid
1
Each party proffered a proposed statement of facts in its respective brief. Appellant
stipulated to "the facts set forth in~~ 1, 2, 4-20 of Respondent's Motion for
Summary Judgment 'Statement of Material Facts"' (app. opp'n at 5). Further,
the "Government does not dispute~~ 2-6, 8-9, 11 and 13-14 ofDellew's
'Statement of Material Facts'" (gov't opp'n at 6).
2
For purposes of identifying references to the record, we adopt the sequential
pagination of documents as affixed by the parties to the Rule 4 file.
2
for any work performed or costs incurred which reasonably
could have been avoided.
(R4, tab 1at44) (Emphasis added) The contract also included FAR clause 52.217-9,
OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) (R4, tab 1 at 49).
4. By bilateral contract Modification No. POOO 10 and, pursuant to
FAR 52.212-4 and FAR 52.217-9, the government exercised option year four on
29 February 2012, effective 1April2012 (R4, tab 2). The modification incrementally
funded the contract in the amount of $1, 118,689 .62, which represents the funding for
six months (1April2012 through 30 September 2012) of the one-year option period,
which would have ended on 31 March 2013 (gov't mot. at 9; app. opp 'n at 5).
5. Bilateral Modification No. POOOIO (R4, tab 2) also incorporated by full text
DFARS clause 252.232-7007, LIMITATION OF GOVERNMENT'S OBLIGATION
(MAY 2006) which provided in part:
(a) Contract line items 4001 through 4005 are
incrementally funded. For these items, the sum of
$1, 118,689.62 of the total price is presently available for
payment and allotted to this contract. ...
(b) For items(s) [sic] identified in paragraph (a) of this
clause, the Contractor agrees to perform up to the point at
which the total amount payable by the Government,
including reimbursement in the event of termination of
those item(s) for the Government's convenience,
approximates the total amount currently allotted to the
contract. The Contractor is not authorized to continue
work on those item(s) beyond that point. The Government
will not be obligated in any event to reimburse the
Contractor in excess of the amount allotted to the contract
for those item(s) regardless of anything to the contrary in
the clause entitled "TERMINATION FOR THE
CONVENIENCE OF THE GOVERNMENT." As used in
this clause, the total amount payable by the Government in
the event of termination of applicable contract line item(s)
for convenience includes costs, profit and estimated
termination settlement costs for those item(s).
(c) Notwithstanding the dates specified in the allotment
schedule in paragraph G) of this clause, the Contractor will
notify the Contracting Officer in writing at least ninety
3
days prior to the date when, in the Contractor's best
judgment, the work will reach the point at which the total
amount payable by the Government, including any cost for
termination for convenience, will approximate 85 percent
of the total amount then allotted to the contract for
performance of the applicable item(s) .... If after such
notification additional funds are not allotted by the date
identified in the Contractor's notification, or by an agreed
substitute date, the Contracting Officer will terminate any
item( s) for which additional funds have not been allotted,
pursuant to the clause of this contract entitled
"TERMINATION FOR THE CONVENIENCE OF THE
GOVERNMENT."
(h) Nothing in this clause affects the right of the
Government to [terminate] this contract pursuant to the
clause of this contract entitled "TERMINATION FOR
CONVENIENCE OF THE GOVERNMENT."
(R4, tab 2 at 66-67)
6. DFARS 252.232-7007(c) is located within DFARS Subpart 232.7,
CONTRACT FUNDING. DFARS Subpart 232.7 permits a firm-fixed-price contract,
which normally must be fully funded, to be incrementally funded.
DFARS 232.703-1, GENERAL.
7. By letter dated 2 April 2012, the government notified Dellew that the subject
contract was terminated for the government's convenience effective 1 October 2012.
Dellew acknowledged receipt of the notice by signature on 2 April 2012. (R4, tab 3)
8. The termination notice provided:
Should the termination result in any costs directly related
to the termination, please provide sufficient documentation
to demonstrate such charges in accordance with FAR
52.212-4(1). Please provide any documentation by 9 July
2012.
(R4, tab 3)
4
9. Dellew submitted a letter to the government, dated 1 May 2012, with the
subject line "Funding Notification for Contract No. FA52 l 5-08-C-0008." The letter
stated:
Per DFARS Clause 252.232-7007(c) we are providing
90 day written notice of the total amount payable by the
Government, including any cost for termination for
convenience, and on which Dellew expects the amount to
be paid will approximate 85 percent of the total amount
currently allocated, $1, 118,689 .62. Specifically:
1. The estimated date when the 85 percent amount will
be reached is: July 31, 2012.
2. The estimated amount of additional funding, if any,
needed to continue performance through to
September 30, 2012, is: $250,000 to $300,000.
In connection with the April 2, 2012 letter from James K.
Watanabe indicating that the contract is terminated for the
Government's convenience effective October 1, 2012,
Dellew estimates that, in addition to the contract amounts
billed, Dellew will incur settlement expenses and
termination costs in the range of $250,000 to $300,000.
These costs include overhead costs continuing after the
termination, net of estimated mitigation, employee paid
time off and vacation pay accumulated at the date of
termination, settlement expenses and proposal preparation
costs, and profit on those costs consistent with the margin
on the terminated contract.
(R4, tab 4)
10. The government did not respond to Dellew's 1 May 2012 letter (app. opp'n
~ 4).
11. Effective 29 June 2012, the parties executed Modification No. P00012.
The modification incorporates a Department of Labor wage adjustment and increases
the total amount of option year four by $359.58 from $1, 118,689.62 to $1, 119,049.20.
(Gov't mot. at 12, attach. l; app. opp'n at 5) The government paid Dellew
5
$1,119,096.72 for its performance from 1April2012 to 30 September 2012 during
option year four (gov't mot. at 13, attach. 2; app. opp'n at 5). 3
12. Modification No. POOOl l dated 28 June 2012 terminated the contract for
the government's convenience effective 1 October 2012 (R4, tab 5).
13. The record contains an undated termination settlement proposal (TSP) for
the amount of $279,641 (R4, tab 6). Dellew stated, "this proposal is of necessity based
on projected costs and company operations subsequent to May 31, 2012, both through
the termination date of September 30, 2012, and through the expiration of the full
Option IV period ending March 31, 2013" (id. at 118). Dellew provided the following
cost elements as summarized below: 4
PACAF[SJ Anticipated Total Cost to 9-30-12
(Based on Actual 411 to 5-31 plus projected to 9-30-12) NOTE $ 665,059
G&A Expense (Used Actual Rate 1/1/12-5/31/12) 26.73% $ 177,770
Unrecovered Mitigated G&A 10/1/12-3/31/13 $ 173,024
Total Direct Cost $ 1,015,854
Profit (Used Actual from FY 2011 Financial Summary) 35.09% $ 356,466
$ 1,372,319
Less: Earned Contract Amount $ (1,118,690)
$ 253,630
Add: Settlement Expenses 20,525
G&A on Settlement Expenses 5,486 $ 26,011
$ 279.641
(Id. at 119)
3
Appellant's calculation of its termination settlement proposal credits the government
with having paid only $1, 118,690.00, not the $1, 119,096. 72 paid pursuant to
Modification No. P00012. Dellew later revised its proposal. The revised
termination settlement proposal recognized the $1,119,096.72 payment.
(Gov't mot., attach. 2) The difference is inconsequential for the determination
of entitlement.
4
Appellant apparently rounded some calculations upward to the nearest dollar.
5
Eielson AFB and Elmendorf AFB are part of the U.S. Air Force's Pacific Air Forces
(PACAF) Command. See www.pacaf.af.mil.
6
14. In response to the government's request for further detail regarding
Dellew's TSP, Dellew provided the following breakdown of its costs:
DELLEW CORPORATION - TERMINATION SETTLEMENT
PROPOSAL CALCULATION 4/1 to G&A 10/1112 Settlement
9/30/2012 to 3/31/13 Expenses
PACAF Anticipated Total Cost to 9-30-12
(Based on Actual 4/1 to 5-31 plus projected to 9-30-12) NOTE $ 665,059 $ 665,059
G&A Expense (Used Actual Rate 111/12-5/31/12) 26.73% $ 177,770 $ 177,770
~nrecovered Mitigated G&A 10/1112-3/31/13 $ 173 024 $ 173,024
Total Direct Cost $ 1,015,854
Profit (Used Actual from FY 2011 Financial Summary) 35.09% $ 356 466 $ 295,751 $ 60,715
$ 1,372,319
Less: Earned Contract Amount $ ( 1.118.690 $ (l,118,690)
$ 253,630
Add: Settlement Expenses 20,525 20,52~
G&A on Settlement Expenses 5,486 $ 26,011 5,48~
$ 279,641 $ 19,891 $ 233,739 $ 26,011
(R4, tab 7 at 125) (Emphasis in original)
15. On 4 September 2012, the government proposed settlement in the amount
of $26,011 (R4, tab 7). In the proposed settlement letter, the government stated that it
had determined Dellew's "settlement expenses" to be acceptable but did not accept
any other proposed expenses (id. at 123).
16. By letter dated 7 September 2012, Dellew submitted a certified claim for
$279,641, the full claimed amount of its TSP. The claim stated that Dellew decided to
submit a claim because it thought it was unlikely that Dellew and the government were
in a position to negotiate a mutually acceptable settlement. The claim was certified
pursuant to FAR 33.207. (R4, tab 8)
17. The contracting officer's final decision (COFD) was issued on 9 November
2012, granting Dellew's claim in part and denying the claim in part. The contracting
officer (CO) accepted $26,011 for "settlement expenses" subject to Dellew's
submission of invoices supporting all costs incurred. The CO denied Dellew's claim
for $253,630 for proposed termination costs "for the contract performance period of
1April2012 - 30 September 2012 and termination period of 1 October 2012 -
31 March 2013." Concerning the performance period of 1 April 2012 - 30 September
2012, the CO stated:
7
[Dellew] received full payment for the six months of
performance via Modification POOOlO .... The Government
rejects Dellew's proposed termination cost for the
performance period because full compensation was paid to
Dellew on the firm-fixed-price contract.
Regarding the "Termination Period of 1October2012 - 31March2013," the CO
stated:
The Government rejects Dellew's proposed termination
costs for the non-performance period .... Anticipatory and
projected total costs, including G&A and profit, are denied
consistent with FAR Part 12.403(d)(l) ....
(R4, tab 10)
18. The COFD was received on 13 November 2012 and on 4 February 2013
Dellew filed a timely notice of appeal from the COFD (R4, tab 11 ).
19. Dellew submitted a revised termination settlement proposal dated
5 September 2013 in the amount of $297,558. The letter advised:
[O]ur updated proposal [is] based on Dellew['s] actual
costs for additional costs related to the termination of
contract Option Year IV as of September 30, 2012, in the
amount of $297,558.
Our original proposal dated July 9, 2012, was of necessity
based on projected costs and company operations
subsequent to May 31, 2012, both through the termination
date of September 30, 2012, and through the expiration of
the full Option IV period ending March 31, 2013. This
proposal is an update of our original submittal based on
actual costs incurred on the terminated contract.
(Gov't mot., attach. 3)
8
20. The revised proposal included the following costs:
Unrecovered Amount-Contract Performance Period
PACAF Actual Cost 4/1/12 to 9-30-12 $706,036
G&A Expense (Audited 2012 Rate) 25.97% Page4 $183,358
Subtotal $889,394
Profit Markup-As Estimated 30.00% $266,818
Total Cont[r]act Value Including Overhead and Profit $1, 156,212
Less: Earned Contract Amount $(1, 119,049)
Unrecovered Cost-Contract Performance Period $37,163
Unrecovered Home Office Overhead
Unrecovered Mitigated Home Office Overhead-
10/ 1112-3/31/13 $168,582
Profit 30. 00%_ _-"$'-"-5-"-'0'=-5-'-74-'------'$"-"2~1~9'""-15"--"-6
Total Amounts Requested Before Settlement Expenses $256,319
Settlement & Proposal Preparation Costs
Settlement & Proposal Preparation Costs $32,738
G&A Expense (Audited 2012 Rate) 25. 97%_ _--=$-=..;8,=-50=2:;___-"$;_;_4..=...;1,=-24~0
TOTAL AMOUNT REQUESTED BASED ON ACTUAL COSTS $297.558
(Gov't mot., attach. 3)
DECISION
The government filed a motion for summary judgment arguing that pursuant to
the termination for convenience clause in the contract, appellant is not entitled to any
termination settlement costs as a matter of law (gov't mot. at 17, 4 7). Appellant .
opposes the government's motion for summary judgment in the entirety, and has filed
a cross-motion for summary judgment asking this Board to hold that "Dellew is
entitled to recovery under each element of cost in its termination settlement proposal -
including its claim for post-termination overhead" (app. opp'n at 2).
Summary judgment is appropriate where, drawing all inferences in the
nonmovant's favor, there is no genuine dispute as to any material fact and the movant
is entitled to judgment as a matter of law. Mingus Constructors, Inc. v. United States,
812 F.2d 1387, 1390 (Fed. Cir. 1987). Substantive law dictates the parties' relative
burdens, and defines "material" facts as those that may affect the outcome of a
particular cause of action. HTA Aviation, LLC, ASBCA No. 57891 et al., 14-1 BCA
~ 35,556 at 174,237 (citing Osborne Constr. Co., ASBCA No. 55030, 09-1 BCA
~ 34,083 at 168,512).
9
The fact that both parties have moved for summary judgment and assert that
there are no genuine issues of material fact regarding their respective legal positions
does not mean that the tribunal must grant judgment as a matter of law for one side or
the other. Mingus Constructors, 812 F .2d at 1391. Each motion is evaluated
separately on its merits, and all reasonable inferences are drawn in favor of the
defending party. Osborne Constr., 09-1 BCA ~ 34,083 at 168,513. "Merely because a
party has moved for summary judgment and avers there are no genuine issues of fact
precluding its recovery does not mean that it 'concede[ s] that no issues remain in the
event [that its] adversary's theory is adopted."' Id. (quoting Mingus Constructors,
812 F.2d at 1391).
Contract Interpretation
A major element of the parties' dispute is an issue of contract interpretation.
The parties disagree about what portion of the contract controls appellant's TSP.
The government argues that Dellew's TSP "is governed by FAR 52.212-4(1) because
the subject contract is a FAR Part 12 commercial services contract" (gov't mot. at 16).
Appellant argues that DFARS 252.232-7007 addresses the scope of a contractor's right
to recovery in the event of a termination and that FAR 52.212-4 and DFARS
252.232-7007 must be read together (app. opp 'n at 11 ). Specifically, appellant argues
that although the government's right to terminate lies in the termination for
convenience clause, FAR 52.212-4(1), "DF ARS 252.232-7007 provides guidance on
when to terminate for convenience and the categories of recovery to which contractors
are entitled" (id. at 12) (emphasis in original).
"Contract interpretation begins with the plain language of the written
agreement." Hercules Inc. v. United States, 292 F.3d 1378, 1380 (Fed. Cir. 2002);
see also LAI Services, Inc. v. Gates, 573 F.3d 1306, 1314 (Fed. Cir. 2009); Gould, Inc.
v. United States, 935 F.2d 1271, 1274 (Fed. Cir. 1991) (citing Fort Vancouver
Plywood Co. v. United States, 860 F.2d 409, 413 (Fed. Cir. 1988)). The "language of
a contract must be given that meaning that would be derived from the contract by a
reasonable intelligent person acquainted with the contemporaneous circumstances."
Hol-Gar Mfg. Corp. v. United States, 351F.2d972, 975 (Ct. Cl. 1965) (citations
omitted).
Examining the plain language of the contract, the termination for convenience
clause, FAR 52.212-4(1), controls appellant's entitlement to a termination settlement
amount. FAR 52.212-4(1) states that in the event that the contract is terminated for the
convenience of the government:
Subject to the terms of this contract, the Contractor shall be
paid a percentage of the contract price reflecting the
IO
percentage of the work performed prior to the notice of
termination, plus reasonable charges the Contractor can
demonstrate to the satisfaction of the Government using its
standard record keeping system ....
DFARS 252.232-7007, Limitation of Government's Obligation, states that "the total
amount payable by the Government in the event of termination of applicable contract
line item(s) for convenience includes costs, profit, and estimated termination
settlement costs for those item(s)." DFARS 252.232-7007(b). The use of the word
"shall" in FAR 52.212-4(1) establishes that the entitlement formula in the termination
clause is mandatory. By comparison, the DFARS clause language is less definitive.
It states that, in ascertaining whether the government has reached or is approaching the
85% limit, the "total amount payable .. .includes" certain items but makes no mandatory
statement of entitlements and references "estimated termination settlement costs."
DFARS 252.232-7007(b) (emphasis added). On its face, where FAR 52.212-4(1)
includes mandatory language and contemplates actual rather than estimated costs, the
contract's termination for convenience clause controls entitlement to termination
settlement amounts.
Further examination of the pertinent language in the context of the full clauses
in which they appear supports the conclusion that the termination clause, not the
DFARS funding clauses, controls appellant's entitlement to recovery in the event of
termination for convenience. FAR 52.212-4(1) reserves the government's right to
terminate a contract for the government's sole convenience and is a required contract
clause for commercial items contracts. FAR 12.30l(b)(3). The purpose ofDFARS
252.232-7007 is to act as a limitation on government obligation for contract
expenditures. It controls when the contractor must notify the government that the
"work will reach the point at which the total amount payable by the Government,
including any cost for termination for convenience, will approximate 85 percent of the
total amount then allotted to the contract." DFARS 252.232-7007(c). In this context,
the language appearing at DFARS 252.232-7007(b) acts to provide the contractor with
categories of termination for convenience costs to be considered when making the
projections required by DFARS 252.232-7007(c).
Appellant's argument that DFARS 252.232-7007 in some way alters or amends
the termination clause in the contract and allows for an additional avenue of recovery
is unpersuasive. The clause is not a guarantee of reimbursement if the contract is
terminated for the government's convenience, and is deferential to the termination
clause in the contract. See DF ARS 252.232-7007(h) ("Nothing in this clause affects
the right of the Government to terminate this contract pursuant to the clause of this
contract entitled 'Termination for Convenience of the Government."'). There is only
one instance in which the DFARS clause affects the parties' rights under the contract's
termination for convenience clause; in that instance, it places further limits on the
11
government's payment obligation in the event of termination for government
convenience. See DFARS 252.232-7007(b) ("The Government will not be obligated
in any event to reimburse the Contractor in excess of the amount allotted to the
contract for those item( s) regardless of anything to the contrary in the clause entitled
'Termination for Convenience of the Government.'"). None of the language in
DFARS 252.232-7007 indicates that it is a remedy granting clause of the contract that
would entitle a contractor to recovery of particular items in the event of a convenience
termination. Ultimately, any entitlement to termination settlement expenses due
appellant must be established through the process prescribed by FAR 52.212-4(1).
Recovery under FAR 5 2. 212-4 (l)
Resolving the parties' contract interpretation dispute with respect to the effect
ofDFARS 252.232-7007 vis-a-vis FAR 52.212-4(1) does not result in fully granting or
denying either party's motion for summary judgment. We next examine Dellew's TSP
to identify items of recovery under the termination for convenience clause in the
contract, FAR 52.212-4(1).
The third sentence of FAR 52 .212-4(1) "sets forth a procedure or process for the
government to compensate fairly a contractor whose contract has been terminated for
convenience." SWR, Inc., ASBCA No. 56708, 15-1BCA~35,832 at 175,223 (citing
Vazquez-Claudio v. Shinseki, 713 F.3d 112, 115 (Fed. Cir. 2013)). In its entirety, the
third sentence of FAR 52.212-4(1) provides:
Subject to the terms of this contract, the Contractor shall be
paid a percentage of the contract price reflecting the
percentage of the work performed prior to the notice of
termination, plus reasonable charges the Contractor can
demonstrate to the satisfaction of the Government using its
standard record keeping system, have resulted from the
termination.
(Emphasis added) The Board has previously segregated this clause into two prongs
allowing for the recovery of monetary amounts: "(I) a 'percentage of the contract
price reflecting the percentage of work performed' and (2) 'reasonable charges'
that...'have resulted from the [contract] termination."' See SWR, 15-1BCA~35,832
at 175,221; Alkai Consultants, LLC, ASBCA No. 56792, 10-2 BCA ~ 34,493 at
170, 134. This clause sets up a different method for determining fair compensation for
the contractor in the event of termination for convenience of a commercial items
contract than the methods set forth in termination for convenience clauses prescribed
in FAR Part 49. See SWR, 15-1 BCA ~ 35,832 at 175,224.
12
By regulation and as explained by the Board in SWR, there are three general
categories of recovery available to a contractor terminated for convenience pursuant to
FAR 52.212-4(1). A commercial items contractor terminated for the government's
convemence may recover:
( 1) [T]he price of work performed under the contract prior
to notice of termination, under the first prong of the
termination clause;
(2) settlement expenses, under the second prong of the
termination clause; and
(3) also under the second prong of the termination clause,
costs resulting from the termination. l61
The first prong of FAR 52.212-4(1) addresses how a contractor shall be paid for
work performed under the contract prior to the notice of termination. See SWR, 15-1
BCA ~ 35, 83 2 at 17 5,223. While firm-fixed-price contracts containing the FAR Part
49 termination clause are essentially converted into cost-reimbursement contracts
when terminated for government convenience, FAR 52.212-4(1) specifies "instead that
recovery for work performed prior to termination be calculated based on contract
price, i.e., as a percentage of contract price reflecting percentage of work performed
prior to notice of termination." Id. at 175,224. This is not to say appellant would be
foreclosed from recovery of reasonable expenses incurred between 1 April 2012 and
30 September 2012 in preparation for the terminated portion of the contract. See id. at
175,227-28 (holding that the contractor was entitled, under the second prong of FAR
52.212-4(1), to recover a deposit of $75,000 made prior to the termination for
convenience while preparing to perform the contract where no percentage of the
contract was ever performed).
As discussed by the Board in SWR, the second prong of FAR 52.212-4(1)
provides for the recovery of settlement expenses. SWR, 15-1 BCA ~ 35,832 at
175,231. Settlement expenses include those expenses incurred by the contractor for
the preparation and presentation of settlement claims to the CO. FAR 31.205-42(g).
It is well established that settlement expenses, including legal expenses, are generally
allowable. Id. However, a contractor is only entitled to those settlement expenses that
are reasonably necessary for the preparation and presentation of the termination
6
During submission and review of Dellew's TSP and subsequent claim, the parties
appear to refer to this third category as termination costs (separate from
settlement costs) (see SOF ~ 17). For the purposes of consistency oflanguage,
we adopt the parties' terminology.
13
settlement proposal. See, e.g., Contract Maintenance, Inc., ASBCA No. 20689, 77-1
BCA ~ 12,446 at 60,293-94; see also FAR 31.205-42(g).
The second prong of FAR 52.212-4(1) also provides for recovery of
termination-associated costs, which are those reasonable costs, other than settlement
costs, which are incurred by a contractor as a result of the termination. "Contract
terminations generally give rise to the incurrence of costs or the need for special
treatment of costs that would not have arisen had the contract not been terminated."
FAR 31.205-42. The FAR provides an explanation of types of costs that are generally
allowable in a termination for convenience situation. See, e.g., FAR 3 l .205-42(b)
("costs which cannot be discontinued immediately after the effective date of
termination [despite all reasonable efforts] are generally allowable. However, any
costs continuing after the effective date of the termination due to the negligent or
willful failure of the contractor to discontinue the costs shall be unallowable."). These
costs could similarly be recoverable in a commercial items contract termination for
convenience provided that the contractor can demonstrate that these resulted from the
termination and are reasonable. As discussed by the Board, the second prong of FAR
52.212-4(1) provides for the "recovery of those charges incurred that 'do not relate to
work completed' but should be reimbursed to fairly compensate the contractor whose
contract has been terminated." SWR, 15-1 BCA ~ 35,832 at 175,223. The contractor
bears the burden of "proving the costs it incurred in performance of items of work that
were terminated." Id. at 175,229 (citing, e.g., Del. Tool & Die Works, Inc., ASBCA
No. 14033, 71-1BCA~8860 at 41,183). A contractor must "prov[e] the amount of
loss with sufficient certainty so that the determination of the amount of damages will
be more than mere speculation." Lisbon Contractors, Inc. v. United States, 828 F.2d
759, 767 (Fed. Cir. 1987) (quoting Willems Indus., Inc. v. United States, 295 F.2d 822,
831 (Ct. Cl. 1961)).
It is under this basic framework that we examine appellant's claim for
termination settlement costs. Appellant's TSP seeks recovery of cost and profit, which
it has divided into three general areas: ( 1) cost and profit for the period of contract
performance from 1 April 2012 through 30 September 2012; (2) G&A/overhead costs 7
and profit for the terminated period of the contract from 1 October 2012 to 31 March
2013; and (3) settlement expenses (SOF ~ 14).
The Board is not adequately informed as to how the costs claimed by Dellew
for each time period relate to the categories of recovery available pursuant to
FAR 52.212-4(1). To some extent, the categories of recovery available pursuant to
FAR 52.212-4(1) correspond to the timeline of the contract's life. The first prong
addresses how a contractor shall be paid for work performed prior to the notice of
7
Dellew's TSP refers to these costs as G&A (SOF ~ 14). Appellant's cross-motion
refers to these costs as overhead (app. opp'n at 17-19).
14
termination. See SWR, 15-1BCA~35,832 at 175,223. Settlement expenses cannot be
incurred until after the notice of termination. However, particularly when examining
charges incurred that relate to the terminated portion of the work, a timeline is not
useful in determining whether the appropriate termination nexus is met, that is,
whether the costs were incurred by the contractor as a result of the termination.
With respect to the first prong of FAR 52.212-4(1), there is no dispute
concerning what contract work was performed by Dellew, nor what the contract price
was. The relevant clause, however, instructs that the contract price be used in the
convenience termination settlement with respect to the "percentage of work performed
prior to the notice of termination." As the undisputed facts develop in this appeal,
virtually none of the option four work was performed prior to the notice of
termination. Neither party addresses this anomaly nor its impact on what recovery, if
any, should be had respecting the first prong, the basis upon which such recovery
should be calculated, or if any of the other reasonable charges claimed are properly
included in the first prong by reason of this anomaly.
Additionally, we are unable to determine ifthe G&A costs claimed from
1 October 2012 to 31 March 2013 resulted from the termination. The record provides
little to no information about what, if any, activities Dellew had to undertake after
1 October 2012 as a result of the termination. While the government argues that
appellant's claim for G&A/overhead costs are categorically unallowable as a
continuing cost of doing business, the second prong of FAR 52.212-4(1) may allow for
recovery of indirect costs of G&A or home office overhead provided appellant can
demonstrate that they resulted from the termination and are otherwise appropriate.
SWR, 15-1BCA~35,832 at 175,231-32. We are hampered by a lack of explanation in
Dellew's TSP and such a determination is not possible based upon the record as it is
currently developed.
Dellew's TSP does segregate its settlement costs. Appellant asks this Board to
hold that it is entitled to settlement expenses on summary judgment (app. opp'n at 19).
The government argues that these costs are unallowable or unreasonable because they
were incurred while Dellew pursued an invalid approach to the TSP (gov't mot. at 44).
Determination of whether appellant is entitled to settlement expenses, requires an
examination of whether those costs were reasonable. See FAR 3 l .205-42(g)(i).
Furthermore, to qualify as settlement expenses the costs must have been necessarily
incurred for "(t]he preparation and presentation ... of settlement claims to the
contracting officer." FAR 31.205-42(g)(i)(A). The reasonableness of the claimed
settlement expenses and their relation to the preparation of the TSP remain outstanding
questions of fact requiring further evidence.
Appellant also seeks approximately 35% profit. Although the Board has held
that under the second prong of FAR 52.212-4(1), fair compensation of a contractor in a
15
convenience termination settlement may include a "reasonable allowance for profit"
(SWR, 15-1 BCA ~ 35,832 at 175,232-33 (citing General Dynamics Land Sys., Inc.,
ASBCA No. 52283, 02-1BCA~31,659 at 156,411)), the government is not "liable for
the contractor's anticipatory profits." SWR, 15-1 BCA ~ 35,832 at 175,222 (citing
Torncello v. United States, 681F.2d756, 759 (Ct. Cl. 1982)). There remains an
outstanding question of fact as to whether the 35% profit sought by Dellew is
reasonable under this contract. Furthermore, profit on work otherwise compensable
under FAR 52.212-4(1) can only apply to costs which are recoverable by the
contractor. We have yet to determine if appellant is entitled to any termination
settlement costs which allow for recovery of a reasonable profit. Accordingly, a
determination of whether appellant may be entitled to profit and if so, how much, is
premature.
CONCLUSION
We grant the government's motion for summary judgment to the extent that we
agree that FAR 52.212-4(1) governs a contractor's right of recovery when a
commercial items contract is terminated by the government for convenience and that
this right is not expanded by DFARS 252.232-7007. In all other respects, the
government's motion is denied. Appellant's cross-motion for partial summary
judgment is denied.
Dated: 1 May 2015
REBA PAGE
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
~~
Administrative Judge
RICHARD SHACKLEFORD
Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
16
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 58538, Appeal ofDellew
Corporation, rendered in conformance with the Board's Charter.
Dated:
JEFFREY D. GARDIN
Recorder, Armed Services
Board of Contract Appeals
17