TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
NO. 03-12-00189-CV
The City of Austin, Appellant
v.
GHI Investments, LLC f/k/a GHI Partners, LLC, Appellee
FROM THE DISTRICT COURT OF TRAVIS COUNTY, 353RD JUDICIAL DISTRICT
NO. D-1-GN-11-002658, HONORABLE GISELA D. TRIANA, JUDGE PRESIDING
MEMORANDUM OPINION
In this interlocutory appeal, the City of Austin challenges the trial court’s denial of
its plea to the jurisdiction as to the claims for inverse condemnation and nuisance of GHI
Investments, LLC f/k/a GHI Partners, LLC. GHI brought suit alleging that the City inversely
condemned its property when it approved drainage designs that did not comply with its Design
Criteria Manual (DCM) as part of two separate project site plans—a road widening and bike lane
project on Pleasant Valley Road (the PV Project) and an HEB grocery store project (the HEB
Project)—that resulted in flooding on GHI’s property, constituting a taking.1 In its plea to the
jurisdiction, the City argued that GHI’s pleadings did not support claims for inverse condemnation
1
GHI asserted other claims against the City and claims against other parties that are not at
issue in this appeal.
and nuisance and the City therefore retained its governmental immunity. For the reasons that follow,
we affirm the trial court’s order.
FACTUAL BACKGROUND
GHI owns property in the City of Austin on the west side of Pleasant Valley Road
adjacent to and downstream from an HEB grocery store. It appears to be undisputed that for some
time there had been drainage problems in the area, causing water to pool on a recurrent basis and
requiring street closures on nearby Elmont Drive, downstream from GHI’s property. In
approximately 2001, the City initiated the PV Project, a public works project for improvements to
Pleasant Valley Road adjacent to GHI’s property, including widening the road, adding a bike lane,
and modifying the drainage system. An engineer assigned to the PV Project, Mitchell Stein,
expressed concerns about the project, stating in emails that he may be “forced” to design
improvements that are “recognized as not being in complete compliance with City standards.” He
called the project a “‘band-aid’ solution” that was “chosen as a way to get collected water off the
roadway soon after a rainfall . . . which is in contrast to the existing situation in which water will
stand in Elmont for days after moderately heavy rainfall” but was “recognized by all involved as
being inadequate to solve the drainage problems in the area.” He warned that the plan “changes the
drainage pattern,” decreases the conveyance of water across Pleasant Valley Road, and “may even
make the ponding situation on the west side of Pleasant Valley worse,” and he suggested a modified
plan that would not make the situation worse.2
2
Stein initially explained that the plan called for replacing five existing 24 inch culverts that
crossed Elmont Drive with “a single 24" RCP and a 2' x 4' culvert crossing P[leasant] V[alley],”
2
Stein observed that a “large natural area” on the east side of Pleasant Valley Road that
served as a “default detention area” would be eliminated by the drainage plan and “one of the intents
of the ‘band-aid solution’ was to provide a means for collected water to drain off the road . . . so the
hope was that, even if water is not allowed to flow to the ‘default detention area’ on the east side of
PV, at least it may be collected and drained quickly enough from the west side of PV so that the
adjacent property owners won’t be affected any more than they currently are affected during a rain
event.” (Ellipsis in original.) A little more than a year after Stein first expressed his concerns, he
emailed an “Update of Analysis of Drainage Needs at PV and Elmont,” questioning how he could
“demonstrate conveyance” of water for the PV Project in a system that could not even convey the
existing water. He noted that the existing system did not convey existing water, that he could not
demonstrate conveyance for the proposed system, and that “[s]uch a condition would arise on the
west side of PV, in the culverts under Elmont.”3 A separate internal City email exchange indicates
resulting in a reduction in conveyance across Pleasant Valley Road from 15.7 sf to 11.14 sf. He also
observed that “in most cases, an increase in conveyance is sought, and not the decrease shown by
these numbers” and stated that if the five culverts were not removed, the situation would not be made
worse. In subsequent emails, he further explained that grade restrictions and the presence of existing
culverts precluded the use of a 24 inch RCP to cross Pleasant Valley Road, as originally planned,
and that an 18 inch RCP would be used instead. These restrictions also required that the “laterals
from the two proposed inlets” that were to connect to a manhole from which the water then would
feed into the 18 inch RCP would have to be 15 inch instead of the “City desired minimum of 18",”
requiring a waiver from the City’s DCM. In another email, Stein addressed what appears to be a
second waiver for “declaration of no need for detention.” He explained that the PV Project is a
“bond funded rehabilitation project,” the type of project that is usually approved under a “General
Permit” instead of a “full permit,” but that a waiver may be necessary for the PV Project to go
forward under a “General Permit” because, in contrast to most rehabilitation projects that do not
add much impervious cover, the PV Project would add an additional 30,000 square feet of
impervious cover.
3
Stein explained that the “2 18" RCPs can only handle about 19 cfs before overtopping the
edge of the road. Yet [water] being sent to them, even under only [sic] existing conditions, is
3
that the HEB area was “causing most of the runoff.” The email indicates that a planned increased
“time of concentration” on the HEB site was “expect[ed to] reduce the flows and thus stay within
the downstream channels,” but an assessment of the final impact was yet to be made. Apparently,
the City proceeded with the drainage plan without resolving Stein’s concerns and completed the PV
Project in 2006.
At some time in approximately 2008, the City approved an extension of a
previously-approved site plan for redevelopment of an HEB grocery store, including construction
of “an approximately 112,750 square foot HEB discount superstore, 3,900 square foot Burger King
restaurant, HEB fuel station, and the associated demolition, landscape, drainage, utility, parking, and
driveway improvements.” The engineer’s letter requesting the extension stated that “the discharge
from the site at the northeast corner after redevelopment shall not exceed the existing runoff
discharged from the site under existing conditions.” The letter also indicated a “proposed detention
pond [that would] provide more detention volume.” According to GHI’s engineer, modifications
were made to the site plan, but there are no as-built drawings to reflect those changes. Although the
PV and HEB Projects were separate projects, conducted at different times, City emails dated late
2005 indicated that the scope of the PV Project had changed and that the portion of the widening of
Pleasant Valley Road in front of the HEB, which consisted of a center turn lane, was to be done as
approximately 91 cfs. So there is NO DEMONSTRATED CONVEYANCE of the increase in
[water] from the bike lanes. As I see it, what this means is that CONVEYANCE CAN NOT BE
DEMONSTRATED WITHOUT HAVING A SYSTEM THAT CONVEYS THE FULLY
DEVELOPED [WATER] ADEQUATELY.” (Emphasis in original.) He concluded that for the
facilities to handle the proposed water plus the existing water, the culverts under Elmont and the
culverts under the driveways on Elmont would have to be upgraded sufficiently to convey the water
and demonstrate conveyance.
4
part of the HEB Project instead of as part of the PV Project, as originally planned. The HEB Project
was completed in approximately 2009.
PROCEDURAL BACKGROUND
In 2011, GHI filed suit claiming that its property has been repeatedly flooded and
rendered useless since January 2010 and asserting claims for inverse condemnation and nuisance.
GHI alleged that the City had approved an incorrect drainage analysis in connection with the HEB
Project, resulting in a deficient detention pond. GHI further alleged that the PV Project reduced
drainage capacity along Pleasant Valley Road, including the reduction of the drainage ditch. GHI
contended that these actions resulted in diversion of water onto GHI’s property, causing damage that
the City knew was substantially certain to result, thus constituting a taking without adequate
compensation and a nuisance. The City filed a plea to the jurisdiction challenging GHI’s pleadings
and contending that the allegations in the petition concerning the HEB Project “completely negat[ed]
that the City intended in any way for the Property to be flooded” and demonstrated, at most, that the
City negligently relied on an analysis provided to it. The City further argued that because the HEB
Project was not a public use, GHI had failed to allege that the taking was for public use. Thus, the
City argued, the trial court lacked jurisdiction to entertain GHI’s claims regarding the HEB Project.
Regarding the PV Project, the City challenged that there had been a taking, claiming that GHI had
not alleged that the City had taken action “directly to” GHI’s land, but had only complained
of actions around its land, nor had GHI alleged unreasonable interference such as blocking
access or denial of a permit. Therefore, the City contended, GHI had not properly pleaded an
5
inverse condemnation or nuisance claim and had not established a waiver of the City’s
governmental immunity.4
Before the hearing on the City’s plea to the jurisdiction, GHI filed a second amended
petition,5 in which it alleged that the City approved both projects contrary to its DCM; that the
approval of the HEB Project resulted in increased flows upstream from GHI’s property and increased
roadway impervious cover and runoff, imposing a water detention on GHI’s property for the benefit
of the downstream public and resulting in its property being repeatedly flooded and rendered useless
since January 2010; that the approval of the PV Project resulted in increased impervious cover and
runoff and diminished the carrying capacity of the west-side ditch on Pleasant Valley Road, resulting
in flooding GHI’s property, substantially interfering with GHI’s use of the property, and causing
damage; and that the City was aware or substantially certain that its actions would result in
downstream flooding, substantially interfere with GHI’s use of its property, and damage GHI’s
property. Concurrently with its second amended petition, GHI filed a response to the City’s plea to
the jurisdiction. Attached as evidence to GHI’s response were an engineer’s affidavit, internal
emails among City staff, HEB’s request for site plan extension, and emails between the City and
HEB representatives. GHI contended that the City emails warning of inadequate drainage on
Pleasant Valley Road and the impact increased flows would have on the west-side property owners
established that in approving and permitting the projects, the City acted with the knowledge of
4
As discussed more fully below, nuisance is an alternative ground of recovery under the
takings clause, and an exception to governmental immunity may apply if it is interrelated with a
takings claim. See Texas Dep’t of Transp. v. City of Sunset Valley, 8 S.W.3d 727, 733 (Tex.
App.—Austin 1999, no pet.).
5
The appellate record does not contain a first amended petition.
6
obvious risk of flooding to GHI’s property. GHI also argued that the City took GHI’s property to
relieve downstream property from flooding, which is a public use. Finally, GHI argued that it was
not required to prove the merits of the alleged taking as long as it had properly asserted the elements
of a takings claim.
At the hearing on the City’s plea to the jurisdiction, the City agreed to rely on its
“Plea to the Jurisdiction with Respect to Plaintiff’s First Amended Original Petition” even though
GHI filed its seconded amended petition after the City filed its plea to the jurisdiction. The trial
court found that GHI had already amended its petition in response to the City’s assertions of
immunity such that no further amendment was necessary, granted the City’s plea in part, and denied
the plea as to GHI’s takings and nuisance claims. This appeal followed.
STANDARD OF REVIEW AND APPLICABLE LAW
Standard of Review
A plea to the jurisdiction challenges the court’s authority to decide a case. Heckman
v. Williamson Cnty., 369 S.W.3d 137, 149 (Tex. 2012). A plea questioning the trial court’s subject
matter jurisdiction raises a question of law that we review de novo. Westbrook v. Penley,
231 S.W.3d 389, 394 (Tex. 2007). “When reviewing a trial court’s ruling on a challenge to its
jurisdiction, we consider the plaintiff’s pleadings and factual assertions, as well as any evidence in
the record that is relevant to the jurisdictional issue.” City of Elsa v. Gonzales, 325 S.W.3d 622, 625
(Tex. 2010) (per curiam) (citing Bland Indep. Sch. Dist. v. Blue, 34 S.W.3d 547, 555 (Tex. 2000)).
When, as here, a plea to the jurisdiction challenges the pleadings, we must determine if the pleader
7
has alleged sufficient facts to affirmatively demonstrate the trial court’s jurisdiction to hear the cause.
City of El Paso v. Heinrich, 284 S.W.3d 366, 378 (Tex. 2009); Texas Dep’t of Parks & Wildlife
v. Miranda, 133 S.W.3d 217, 226 (Tex. 2004); Creedmoor-Maha Water Supply Corp. v. Texas
Comm’n on Envtl. Quality, 307 S.W.3d 505, 512 (Tex. App.—Austin 2010, no pet.) (“The plaintiff
has the initial burden of alleging facts that demonstrate the trial court’s jurisdiction to hear
the cause.”).
To make this determination, we look to the pleader’s intent, construe the pleadings
liberally in favor of jurisdiction, and accept the allegations in the pleadings as true. Westbrook,
231 S.W.3d at 405; Miranda, 133 S.W.3d at 226. If the pleadings affirmatively negate the existence
of jurisdiction, then a plea to the jurisdiction may be granted without allowing the plaintiff an
opportunity to amend. Miranda, 133 S.W.3d at 227. When the pleadings do not allege sufficient
facts to affirmatively demonstrate the trial court’s jurisdiction but do not affirmatively demonstrate
an incurable jurisdictional defect, the issue is one of pleading sufficiency, and the plaintiff should
be given an opportunity to amend. Id. 133 S.W.3d at 226–27. In determining a plea to the
jurisdiction, the trial court may consider any evidence the parties have submitted and must do so
when necessary to resolve the jurisdictional inquiry. Bland Indep. Sch. Dist., 34 S.W.3d at 555. If
the relevant evidence is undisputed or fails to raise a fact question, the trial court should rule on the
plea as a matter of law. City of Elsa, 325 S.W.3d at 626; Miranda, 133 S.W.3d at 228.
Governmental Immunity and the Takings Clause
Governmental immunity deprives a trial court of subject matter jurisdiction in suits
against a political subdivision of the state, including cities when they are performing govenmental
8
functions, unless the political subdivision consents to suit, and therefore is properly asserted in a
plea to the jurisdiction. Rolling Plains Groundwater Conservation Dist. v. City of Aspermont,
353 S.W.3d 756, 759 n.4 (Tex. 2011) (per curiam); Miranda, 133 S.W.3d at 224, 225–26. There
is a clear and unambiguous limited waiver of immunity for valid claims under article I, section 17
of the Texas Constitution, the “takings clause,” which provides that “[n]o person’s property shall be
taken, damaged or destroyed for or applied to public use without adequate compensation being made
. . . .” Tex. Const. art. I, § 17; Steele v. City of Houston, 603 S.W.2d 786, 791 (Tex. 1980); City of
Midlothian v. Black, 271 S.W.3d 791, 799 (Tex. App.—Waco 2008, no pet.). If the government
appropriates property without paying adequate compensation, the owner may bring an inverse
condemnation claim to recover the resulting damages. Westgate, Ltd. v. State, 843 S.W.2d 448, 452
(Tex. 1992).
To plead a valid inverse condemnation claim and establish waiver of immunity under
the takings clause, a plaintiff must allege that the governmental agency (1) intentionally performed
certain acts in the exercise of its lawful authority (2) that resulted in taking, damaging, or destroying
the plaintiff’s property (3) for public use. General Servs. Comm’n v. Little–Tex Insulation Co.,
39 S.W.3d 591, 598 (Tex. 2001); Steele, 603 S.W.2d at 791. The intent element may be met by a
showing that the governmental entity “(1) knows that a specific act is causing identifiable harm; or
(2) knows that the specific property damage was substantially certain to result from an authorized
government action—that is, that the damage is ‘necessarily an incident to, or necessarily a
consequential result of’ the government’s action.” City of Dallas v. Jennings, 142 S.W.3d 310, 314
(Tex. 2004) (quoting Texas Hwy. Dep’t v. Weber, 219 S.W.2d 70, 71 (Tex. 1949)). “There is
9
no concrete rule for determining whether a use is a public use; each case is usually decided
upon the basis of its own facts and the surrounding circumstances.” Whittington v. City of Austin,
174 S.W.3d 889, 897 n.3 (Tex. App.—Austin 2005, pet. denied) (citing Coastal States Gas Prod.
Co. v. Pate, 309 S.W.2d 828, 833 (Tex. 1958)). Generally, judicial decisions have narrowed the
meaning of the term to situations in which the damages are incident to public works. Steele,
603 S.W.2d at 790. Texas courts have found public use when the public is “‘entitled to share
indiscriminately in the proposed use as a matter of right.’” Whittington, 174 S.W.3d at 897 n.3
(quoting Daniel B. Benbow, Public Use as a Limitation of the Power of Eminent Domain in Texas,
44 Tex. L. Rev. 1499, 1500 n.8 (1966)). Thus, public use occurs when “‘there results to the public
some definite right or use in the business or undertaking to which the property is devoted.’” Pate,
309 S.W.2d at 833; Dyer v. Texas Elec. Serv. Co., 680 S.W.2d 883, 885 (Tex. App.—El Paso 1984,
writ ref’d n.r.e.). Whether particular facts constitute a taking is a question of law. Little-Tex,
39 S.W.3d at 598 (citing Mayhew v. Town of Sunnyvale, 964 S.W.2d 922, 936 (Tex. 1998)).
A claim for nuisance is an alternative ground of recovery under article I, section 17
and is also an exception to sovereign immunity if it rises to the level of a constitutional taking.
Jennings, 142 S.W.3d at 311; City of Abilene v. Downs, 367 S.W.2d 153, 159 (Tex. 1963); Texas
Dep’t of Transp. v. City of Sunset Valley, 8 S.W.3d 727, 733 (Tex. App.—Austin 1999, no pet.).
When, as here, a nuisance claim is interrelated with or in the nature of a takings claim, the elements
of the inverse condemnation and nuisance claims are the same, and a valid claim for inverse
condemnation under the takings clause also establishes a valid interrelated nuisance claim. See City
of Sunset Valley, 8 S.W.3d at 732–33 (waiver of immunity for inverse condemnation claim under
10
article I, section 17 also waived immunity for nuisance claim); cf. Jennings, 142 S.W.3d at 311, 316
(where plaintiff failed to establish requisite intent for waiver of sovereign immunity as to takings
claim and asserted no other basis for waiver of immunity as to nuisance claim, city was also immune
from nuisance claim); Foster v. Denton Indep. Sch. Dist., 73 S.W.3d 454, 460–61 (Tex. App.—Fort
Worth 2002, no pet.) (claim for simple nuisance not interrelated with takings claim did not fall
within exception to sovereign immunity).
DISCUSSION
Intent
In its first issue, the City argues that GHI has not met the intent element of its takings
claim.6 In its plea to the jurisdiction, the City argued that GHI had not stated a valid takings claim
because its pleadings showed negligence at most and negated intent on the part of the City. In its
second amended petition, GHI alleged that the City’s approval of the PV and HEB Projects caused
repeated flooding of GHI’s property, imposing a water detention for the benefit of the downstream
public and interfering with GHI’s use of the property, and that the City was aware or substantially
certain that its actions would cause these results. Construing the pleadings liberally in favor of
jurisdiction, looking to GHI’s intent, and accepting the allegations in the pleadings as true, see
Westbrook, 231 S.W.3d at 405; Miranda, 133 S.W.3d at 226, we conclude that GHI’s pleadings
do not complain of the City’s negligence or omissions but, instead, assert the essential intent
6
Because the parties agree that GHI’s nuisance claim is interrelated with its inverse
condemnation claim under article I, section 17, we address both claims as GHI’s takings claim, as
do the parties. See City of Sunset Valley, 8 S.W.3d at 733.
11
element necessary to state a facially valid takings claim. See Tarrant Reg’l Water Dist. v. Gragg,
151 S.W.3d 546, 555–56 (Tex. 2004) (evidence that damage from increased flooding was inevitable
result of district’s construction of reservoir and its operation as intended sufficient to support trial
court’s finding of taking even though plaintiff offered some evidence of careless operation by
district); Jennings, 142 S.W.3d at 314; Little-Tex, 39 S.W.3d at 598; cf. City of El Paso v. Ramirez,
349 S.W.3d 181, 187 (Tex. App.—El Paso 2011, no pet.) (pleadings alleging omissions by city did
not state claim for inverse condemnation because governmental entity’s failure to act cannot rise to
level of taking); City of Midlothian, 271 S.W.3d at 800 (petition containing no allegation that city
knew damage was substantially certain to occur failed to plead valid inverse condemnation claim);
Bell v. City of Dallas, 146 S.W.3d 819, 825 (Tex. App.—Dallas 2004, no pet.) (pleadings containing
only allegations that damage was caused by negligent omissions and no allegations that city
intentionally performed acts affirmatively negated takings claim); City of Del Rio v. Felton,
No. 04-06-00091-CV, 2007 Tex. App. LEXIS 660, at *25–26 (Tex. App.—San Antonio
Jan. 31, 2007, no pet.) (mem. op.) (allegation that city had notice of water damage to building on
opposite side of park from plaintiff’s property failed to state facially valid takings claim as to water
damage to plaintiff’s structure); Evatt v. Texas Dep’t of Transp., No. 11-05-00031-CV, 2006 Tex.
App. LEXIS 4268, at *12 (Tex. App.—Eastland May 18, 2006, pet. denied) (mem. op.)
(homeowners who did not allege department either knew or was substantially certain their homes
would flood as result of construction methods used by department did not sufficiently allege
takings claim).
12
On appeal, the City, which did not present any jurisdictional evidence, contends that
GHI’s evidence, presented after the City filed its plea, is insufficient to establish the requisite intent.
The City asserts that the emails of Stein, a City engineer, do not demonstrate that the City knew with
substantial certainty that its actions would result in a taking of GHI’s property. The City contends
that the emails show, at most, a difference of opinion among city staff members on DCM standards
and “on the amount of impervious surface increase on the street without corresponding drainage
upgrades.” The City also argues that GHI negated its allegation of increased flooding by presenting
evidence of preexisting drainage problems in the area and failing to present evidence of preexisting
conditions on its property.7 In short, the City does not dispute GHI’s jurisdictional evidence; it
simply argues that the evidence negates, or is insufficient to raise a fact issue as to, the element of
intent. We find this argument unpersuasive.
GHI presented evidence showing the City was aware that inadequate conveyance of
the increase in water from the PV Project on the west side of Pleasant Valley Road, where GHI’s
property was located, “would arise” from the approved projects. Stein, who was assigned to the
project, initially warned that the PV Project altered the drainage pattern, would decrease conveyance
of water across Pleasant Valley Road, and “may even make the ponding situation on the west side
of Pleasant Valley worse” and observed that the City’s “hope” was that west-side property owners
would not be affected any more than they already were. More than a year later, after changes were
made to the drainage plan that reduced some culverts to a size below the City’s desired minimum,
7
The City also contends that GHI’s “real complaint” is that the City did not fix the
preexisting drainage problems, which cannot form the basis of a takings claim. As stated previously,
we do not construe GHI’s pleadings to allege negligent acts or omissions on the part of the City.
13
he predicted that a “condition would arise” on the west side of Pleasant Valley Road in which the
culverts under Elmont could not handle the conveyance of increased water from the proposed
additional impervious cover because they could not handle the conveyance of the existing water.
There is no evidence that the plan was revised to upgrade the culverts on Elmont and under the
driveways on Elmont, as Stein concluded was necessary to adequately convey water from the
proposed impervious cover being added to the existing water.
Stein’s comments, read together, do not merely show that the City did not plan to
correct the drainage problems in the area, as the City contends, but also show the City’s awareness
that approval of the PV Project would increase impervious cover, decrease water conveyance in an
area where conveyance was already inadequate, and likely result in “ponding” on the west side
of Pleasant Valley Road where GHI’s property is located. See City of Borger v. Garcia,
290 S.W.3d 325, 330 (Tex. App.—Amarillo 2009, pet. denied) (citing Norman v. Schaen, Inc. v. City
of Dallas, 536 S.W.2d 428, 429–30 (Tex. Civ. App.—Dallas 1976, no writ)) (only duty imposed on
city in constructing drainage system is not to increase flow of surface water across appellees’
property). Despite the City’s assertion that there was a difference of opinion among city staff, the
City did not present evidence that the City disagreed with Stein regarding his predictions of
inadequate water conveyance and west-side ponding. Further, although there is evidence that steps
were being taken during the PV Project to “reduce the flow and thus stay within the downstream
channels” as to that “30+ acres” composing the HEB site, from which “most of the runoff” in the
area came, there is no evidence of the final impact of the planned corrective steps. Moreover, the
City subsequently approved the addition of a turn lane in connection with the HEB project, which
14
was not part of the original HEB site plan, and there is no evidence that any corresponding steps
were taken to reduce and contain the flow for that portion of the HEB Project, which added even
more impervious cover to Pleasant Valley Road and additional water to an already inadequate
system, while further reducing the capacity of the west-side drainage ditch. See id. In fact,
according to GHI’s engineer, both projects were completed without a provision for detention systems
of increased capacity to west-side downstream conveyance.
Nor is it dispositive that GHI presented evidence of existing flooding in the area and
did not offer evidence establishing conditions on its property prior to the projects. In its response
to the City’s plea to the jurisdiction, GHI asserted that it was undisputed that its property had
experienced increased flooding since the completion of the projects. The supreme court has held that
changes in the “character” of preexisting flooding—whether, for example, the water “‘arrived
sooner, flowed faster, and [was] more forceful, deeper, and longer-lasting’”—may form the basis of
a takings claim. See Gragg, 151 S.W.3d at 555 (quoting trial court’s findings) (brackets in original).
We believe that GHI is not required to establish the full extent of and nature and degree of any
alleged increased flooding to invoke the court’s jurisdiction. See Bland Indep. Sch. Dist., 34 S.W.3d
at 554 (plaintiffs not required to “put on their case simply to establish jurisdiction”); City of El Paso
v. Mazie’s, L.P., No. 08-11-00233-CV, 2012 Tex. App. LEXIS 10540, at *31 (Tex. App.—El Paso
Dec. 19, 2012, pet. filed) (mem. op.) (pleading of recurrence of flooding, which goes to proof of
takings claim, not required to establish jurisdiction in takings claim) (citing Doss v. City of Victoria,
No. 13-07-00306-CV, 2007 Tex. App. LEXIS 9872, at *11 (Tex. App.—Corpus Christi
Dec. 20, 2007, no pet.) (mem. op.)). We express no opinion on the merits of GHI’s claims but
15
conclude that GHI has sufficiently pleaded the intent element of a takings claim and that its evidence
raises a fact issue with regard to the City’s intent. See City of Elsa, 325 S.W.3d at 626; Jennings,
142 S.W.3d at 314; Miranda, 133 S.W.3d at 227–28. We overrule the City’s first issue.8
Public Use
In its second issue, the City argues that GHI has insufficiently pleaded that the alleged
taking of its property was for a public use. The City contends that the HEB is not a public use and,
in the alternative, that to the extent the center turn lane portion of the HEB Project is a public use,
only that portion of the alleged flooding attributable to the turn lane could form the basis of a takings
claim. Regarding the PV Project, which the City does not dispute is a public use, the City argues that
GHI has not shown that the alleged flooding was caused by the PV Project, as opposed to the HEB
Project or preexisting conditions. We address these arguments in turn.
Assuming without deciding that the portion of the HEB Project other than the turn
lane is not a public use, we conclude that the turn lane serves a public use. As part of a roadway
project, the turn lane is in the nature of a public work. See Brantley v. Texas Youth Comm’n,
365 S.W.3d 89, 106 (Tex. App.—Austin 2011, no pet.) (“The Constitution limits compensation to
damages for or applied to a public use, and judicial restraints have narrowed that phrase to damages
which arise out of or as an incident to some kind of public works.”) (quoting Steele, 603 S.W.2d at
789) (Internal quotations omitted.) The public may “share indiscriminately” in the use of the turn
8
Because we find that Stein’s emails are sufficient to raise a fact issue as to intent, we do
not reach the remainder of the City’s arguments challenging GHI’s evidence. See Tex. R. App.
P. 47.1.
16
lane “as a matter of right,” see Whittington, 174 S.W.3d at 897, and thus has “some definite right or
use in” the turn lane, see Pate, 309 S.W.2d at 833; Dyer, 680 S.W.2d at 885. Members of the public
shopping at the HEB Project site will enjoy the benefits of the safety and convenience provided by
a center turn lane. See Dyer, 680 S.W.2d at 885 (power line to serve single customer, Gulf, would
arguably benefit public by increasing oil production of Gulf). Further, it is the character of the use
that determines public use, not the extent of the use. See id. at 885 (citing Housing Auth. of City of
Dallas v. Higginbotham, 143 S.W.2d 79, 84 (Tex. 1940)). “‘It is immaterial if the use is limited to
the citizens of a local neighborhood, or that the number of citizens likely to avail themselves of it
is inconsiderable, so long as it is open to all who choose to avail themselves of it. The mere fact that
the advantage of the use inures to a particular individual or enterprise, or group thereof, will not
deprive it of its public character.’” Higginbotham, 143 S.W.2d at 84 (quoting West v. Whitehead,
238 S.W. 976, 978 (Tex. Civ. App.—San Antonio 1922, writ ref’d)). While we agree with the City
that only that portion of the HEB project attributable to a public use may form the basis of a takings
claim, we believe the degree of the flooding resulting from the turn lane is a matter of proof and need
not be shown for GHI’s pleadings to establish jurisdiction. See Bland Indep. Sch. Dist., 34 S.W.3d
at 554; Mazie’s, 2012 Tex. App. LEXIS 10540, at *31.
Regarding the PV Project, the parties agree it is a public work project that serves a
public use and can form the basis of a takings claim. See Steele, 603 S.W.2d at 789; Brantley,
365 S.W.3d at 106. The City argues, however, that GHI has not demonstrated that the alleged
flooding is the result of the PV Project rather than the HEB Project. The City contends that since
the PV Project was completed in 2006, it is “unlikely” that the flooding GHI alleges has rendered
17
its property useless “since January 2010” is attributable to the PV Project. The only evidence on
causation is the affidavit of GHI’s engineer, who stated that both projects resulted in flooding on
GHI’s property. Morever, as with the City’s argument concerning the HEB Project, the questions
of causation and what portion, if any, of the flooding is attributable to the PV Project and the turn
lane, as opposed to any non-public use portion of the HEB Project, are matters of proof for GHI to
establish in its case on the merits and are not facts that must be proven to establish jurisdiction. See
Bland Indep. Sch. Dist., 34 S.W.3d at 554; Mazie’s, 2012 Tex. App. LEXIS 10540, at *31. We
therefore conclude that GHI has sufficiently pleaded the public use element of a takings claim and
overrule the City’s second issue.
CONCLUSION
Having overruled the City’s issue, we affirm the trial court’s order.
__________________________________________
Melissa Goodwin, Justice
Before Chief Justice Jones, Justices Goodwin and Field
Affirmed
Filed: April 30, 2013
18