NOT RECOMMENDED FOR FULL-TEXT PUBLICATION
File Name: 08a0606n.06
Filed: October 8, 2008
No. 07-3169
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
HOLLY A. CHANDLER,
Plaintiff-Appellee,
v. ON APPEAL FROM THE UNITED
STATES DISTRICT COURT FOR THE
THE VILLAGE OF CHAGRIN FALLS, et al., NORTHERN DISTRICT OF OHIO
Defendant-Appellant.
/
BEFORE: COLE and CLAY, Circuit Judges; and Russell, District Judge *
CLAY, Circuit Judge. Defendant-Appellant, the Village of Chagrin Falls, appeals from
an order entered by the United States District Court for the Northern District of Ohio denying its
motion for summary judgment and its renewed motion for a judgment as a matter of law in this 42
U.S.C. § 1983 suit initiated by Plaintiff, Holly Chandler. In her complaint, Chandler alleged that the
Village violated her procedural due process rights when it revoked a permit authorizing the
construction of a new garage for her home. For the reasons that follow, we REVERSE the
judgment of the district court.
*
The Honorable Thomas B. Russell, United States District Judge for the Western District of
Kentucky, sitting by designation.
No. 07-3169
BACKGROUND
The facts of this case are largely undisputed. Plaintiff, Holly Chandler (“Chandler”), is a
homeowner and resident of the Village of Chagrin Falls, Ohio (“the Village”). The Village is a small
municipality governed by a mayor, “seven members of a Village Council, various committees,
commissions and boards as well as Administrative Officials.” (J.A. at 28)
In March of 2003, Chandler sought to tear down her garage and construct a larger structure
because her garage was “in poor repair” and could not accommodate the size of her sports utility
vehicle. (J.A. at 208) The parameters of a permissible size for a garage were outlined in §
1125.04(A)(6) of the Village of Chagrin Falls Codified Ordinances. Section 1125.04(A)(6) stated
Garages and Other Accessory Buildings. Each residential building shall be served by a
garage located on the same lot. Garages and other accessory buildings must be in accordance
with the following standards:
***
(6) No accessory building shall exceed one story. The maximum height above finished
grade shall be limited to fifteen feet. The Architectural Review Board may approve
a height of up to but not exceeding twenty-two feet for detached garages to allow roof
pitches that are architecturally compatible with the main building on that lot.
(J.A. at 237) As noted by the district court, the Architectural Review Board (“ARB”) is
“responsible for the oversight, review and approval of all architectural building issues that arise
within the Village. Chandler is a member of the ARB.” (J.A. at 498)
In May of 2003, pursuant to § 1125.04(A)(6), Chandler submitted her plans to the ARB and
requested a building permit to authorize the construction of a new garage. According to the plans
submitted to the ARB, Chandler’s garage was to stand at approximately twenty-two feet and
included a permanent interior staircase.
2
No. 07-3169
On May 20, 2003, the ARB heard testimony regarding Chandler’s garage and approved the
proposed structure for up to twenty-two feet.1 However, the ARB expressed concerns that the garage
constituted a two-story structure in violation of the Ordinance because of its interior staircase. Thus,
Chandler was required to obtain a variance for the installation of the staircase from the Village Board
of Zoning Appeals (“BZA”).
On July 7, 2003, the BZA heard Chandler’s request for a variance from the Ordinance
permitting her to construct a two story structure with a permanent interior staircase. During the
hearing, several of Chandler’s neighbors objected to the approval of the variance for the garage.
According to the BZA meeting minutes, the neighbors “spoke in opposition to the granting of the
variance because of the large size of the structure. Another concern was that because plumbing is
allowed in accessory structures, the second floor might be used as an office residence.” (J.A. at 74)
One neighbor also argued that the actions of the ARB were inappropriate because “the roof pitch of
the garage is higher than that of the house.” (J.A. at 75) The BZA, however, did not pass on the
variance request or the concerns raised by Chandler’s neighbors but instead remanded the matter to
the ARB for an explanation regarding its rationale for approving a structure that exceeded 15 feet.
On July 8, 2003, before the ARB could provide the requested explanation, however, Chandler
withdrew her variance request and instead planned to install a “pull-down” stair case. (J.A. at 230)
On July 14, 2003, with no further action required because the variance request was moot, the Village
1
Chandler did not participate in the deliberations regarding her application for the approval
of her garage plans.
3
No. 07-3169
Chief Administrative Officer issued a building permit to Chandler. Chandler demolished her garage
on the next day and began construction of her new garage.
On July 15, 2003, a neighbor wrote to the Village Administrator to appeal the decision of the
ARB authorizing Chandler to construct a new garage. In a letter dated July 16, 2003, the Village
Chief Administrative Officer advised Chandler that her neighbor filed an appeal regarding the
issuance of her building permit and that the appeal would be heard on August 4, 2003. Chandler was
further advised that, because the outcome of the appeal had not yet been determined, she could
“proceed with construction at [her] own risk under the building permit . . . issued on July 14, 2003.”
(J.A. at 393)
On August 4, 2003, the BZA considered the appeal seeking to reverse the ARB’s decision
to grant a permit to Chandler. According to the meeting minutes, the BZA considered whether the
neighbor had standing to file an appeal and whether the appeal was timely filed. Based on two
pertinent Village Ordinances, §§ 1111.03 and 1111.02, the BZA answered both questions in the
affirmative. The BZA determined that under § 1111.02, which authorized appeals based on
“decision[s] made by the Administrator . . . including the . . . granting of permits,” the neighbor had
standing to appeal. Moreover, it was also determined that the appeal was timely filed under §
1111.03 because it was dated within 30 days of the issuance of the permit by the Administrator.
Thus, the BZA determined that it had jurisdiction to consider the actions of both the ARB and the
Administrator in issuing a building permit for the twenty-two foot structure. At all relevant hearings
and proceedings, Chandler was represented by counsel and objected to any further action by the ARB
4
No. 07-3169
or the BZA regarding her building permit. After hearing arguments from both sides, the appeal
failed and was forwarded to the Village Council for further review.
On September 8, 2003, the Village Council met and considered the actions of the BZA with
respect to the appeal raised by Chandler’s neighbors. During the meeting, the Council heard
testimony regarding the ARB’s authority to approve permits for structures up to twenty-two feet and
whether such a discretionary decision was properly reviewable by the Council. The Council did not
resolve that question but instead revoked the permit issued by the Administrator and remanded the
matter back to the ARB for further consideration. Consistent with the directions of the Council, the
Village Administrator issued a stop work order on September 9, 2003. Under the terms of the stop
work order, Chandler was permitted to continue “caulking, priming and other weather sealing
necessary to protect the elements of the structure so far erected.” (J.A. at 385)
On September 16, 2003, the ARB reconsidered the issuance of the permit, clarified its basis
for approval and affirmed its May 20, 2003 approval of Chandler’s building permit. On September
22, 2003, the Village Council reviewed the ARB’s determination but once again remanded the matter
back to the ARB because of insufficient notice regarding its meeting to surrounding property owners.
On October 6, 2003, the Council and the ARB held a joint meeting to resolve the matter.
On October 6, 2003, apparently frustrated with the protracted permit proceedings, Chandler
filed suit against the Village, her neighbors and several Village council members in federal district
court alleging a number of federal and state claims. In particular, Chandler asserted that Defendants
violated her right to procedural due process and equal protection when it revoked her permit.
Chandler also alleged that she was deprived of her right to “protect one’s property,” her right to
5
No. 07-3169
“liberty, health, safety, privacy and welfare,” and that the permit revocation constituted an unlawful
taking of property. (J.A. at 38-39) Approximately one week after the complaint was filed, the
Village Council reissued a building permit to Chandler.
Before the district court, the Village moved for summary judgment, arguing, in relevant part,
that they were entitled to judgment as a matter of law because the procedures employed to review
the permit in question were consistent with municipal ordinances and Ohio law. Although the
district court agreed that the Village was entitled to summary judgment with respect to most of
Chandler’s claims, the court concluded that Chandler raised a disputed issue of material fact with
respect to her due process claim.2 Relying on Banks v. City of East Cleveland, 1997 WL 35572 (6th
Cir. 1997), the district court found that Chandler could proceed on a theory of due process
deprivation based on “the government’s failure to follow its own ordinances or regulations . . . .”
(J.A. at 505)
Following a trial, the jury found that the Village violated Chandler’s due process rights and
awarded her $10,000 in damages. After judgment in favor of Chandler was entered by the district
court, the Village filed a motion for a judgment as a matter of law, and in the alternative, a new trial.
Both motions were denied. Chandler also sought, and was awarded, $132,733.33 in legal fees, plus
costs and expenses, as the prevailing party pursuant to 42 U.S.C. § 1988. This timely appeal
followed.
2
The district court also dismissed Chandler’s claims against her neighbors and the Village
councilpersons.
6
No. 07-3169
DISCUSSION
I. Procedural Due Process
A. Preservation of the Issue
Chandler argues that the Village did not properly preserve this issue for appeal because it has
framed the legal issue before this Court differently than the argument advanced before the district
court.3 Before the district court, the Village defended against Chandler’s due process allegation by
arguing that it did not violate its own ordinances when it considered her neighbor’s appeal of the July
14, 2003 building permit. Before this Court, however, the Village argues that even if it did violate
its ordinances, it did not violate Chandler’s due process rights inasmuch as she did not have a
protected property interest and was ultimately provided notice and an opportunity to be heard
regarding the issuance of her permit. Thus, Chandler contends, the Village has waived the argument.
Chandler cites Liberte Capital Group, LLC v. Capwill, 462 F.3d 543 (6th Cir. 2006), in
support of this contention. Liberte Capital Group, however, is inapposite. In Liberte Capital
Group, this Court refused to consider a due process claim raised by a party for the first time on
appeal. Id. at 556. In the instant case, the sole issue before the district court concerned procedural
due process and whether Chandler had established the requisite elements necessary to prevail.
Although the Village has changed its framing of the argument, this does not undermine the basic fact
3
Chandler also argues that this Court lacks jurisdiction over the denial of summary judgment
because the district court’s order denying summary judgment was not specifically referenced in the
Village’s notice of appeal. We disagree. It is well established that “an appeal from a final judgment
draws into question all prior non-final rulings and orders.” Crawford v. Roane, 53 F.3d 750, 752
(6th Cir. 1995). Here, the district court entered a final judgment after the jury trial concluded and
attorney’s fees were awarded. Thus, this Court has jurisdiction to consider the Village’s appeal of
the denial of summary judgment.
7
No. 07-3169
that it challenged Chandler’s due process claim before the district court by asserting that Chandler
was afforded due process as required by its ordinances and by the Constitution. Thus, this issue is
properly before this Court.
B. Standard of Review
This Court reviews a district court's denial of summary judgment de novo. Monette v.
Electronic Data Sys. Corp., 90 F.3d 1173, 1176 (6th Cir. 1996). Summary judgment is appropriate
if, pursuant to Rule 56(c) of the Federal Rules of Civil Procedure, the pleadings, depositions,
answers to interrogatories, and admissions on file, together with the affidavits, if any, “show that
there is no genuine issue as to any material fact and that the movant is entitled to a judgment as a
matter of law.” Fed. R. Civ. P. 56(c). As the moving party, the Village bears the burden of showing
the absence of a genuine issue of material fact as to at least one essential element on each of
Chandler’s claims. See Celotex Corp. v. Catrett, 477 U.S. 317, 324 (1986). Chandler, as the non-
moving party, must then present sufficient evidence from which a jury could reasonably find for her.
See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 252 (1986). This Court must then determine
“whether the evidence presents sufficient disagreement to require submission to a jury or whether
it is so one-sided that one party must prevail as a matter of law.” Id. at 251-52. In making this
determination, this Court must draw all reasonable inferences in favor of Chandler. See Nat’l
Enters., Inc. v. Smith, 114 F.3d 561, 563 (6th Cir. 1997).
Similarly, this Court “review[s] a district court's denial of a Rule 50(b) motion de novo,
applying the same deferential standard as the district court: ‘The motion may be granted only if in
viewing the evidence in the light most favorable to the non-moving party, there is no genuine issue
8
No. 07-3169
of material fact for the jury, and reasonable minds could come to but one conclusion, in favor of the
moving party.’” Radvansky v. City of Olmsted Falls, 496 F.3d 609, 614 (6th Cir. 2007) (quoting
Gray v. Toshiba Am. Consumer Prods., Inc., 263 F.3d 595, 598 (6th Cir.2001)). “Neither the district
court nor the reviewing court may reweigh the evidence or assess the credibility of witnesses.” Gray,
263 F.3d at 600. “For [the Village] to succeed, it must overcome the substantial deference owed a
jury verdict.” Radvansky, 496 F.3d at 614.
C. Analysis
On appeal, the Village contends that the district court erred as a matter of law in denying its
motions for summary judgment and judgment as a matter of law. First, the Village contends that the
district court erroneously determined that Chandler presented sufficient evidence of a protected
property interest in the building permit. Second, even if Chandler had established a protected
property interest, the Village contends that Chandler did not establish that the procedure employed
by the Village in reviewing the building permit ran afoul of Chandler’s procedural due process
rights. We examine each point of contention in turn.
The Fourteenth Amendment provides that a State may not “deprive any person of life, liberty
or property, without due process of law.” U.S. Const. amend XIV § 2. Indeed, “the Due Process
Clause provides that certain substantive rights–life, liberty, and property–cannot be deprived except
pursuant to constitutionally adequate procedures.” Cleveland Bd. of Educ. v. Loudermill, 470 U.S.
532, 541 (1985). See also Mullane v. Cent. Hanover Bank & Trust Co., 339 U.S. 306, 313 (1950)
(noting that the Due Process Clause “require[s] that deprivation of life, liberty or property by
adjudication be preceded by notice and opportunity for hearing appropriate to the nature of the
9
No. 07-3169
case”). Thus, to establish a procedural due process claim pursuant to § 1983, Chandler must
establish three elements: (1) that she has a life, liberty, or property interest protected by the Due
Process Clause; (2) that she was deprived of this protected interest within the meaning of the Due
Process Clause; and (3) that the state did not afford her adequate procedural rights prior to depriving
her of her protected interest. Hahn v. Star Bank, 190 F.3d 708, 716 (6th Cir. 1999).
1. Protected Property Interest and Deprivation of Interest
As a threshold matter, to establish a cognizable claim of a violation of procedural due
process, Chandler must establish that she possessed a protected property interest. Matthews v.
Eldridge, 424 U.S. 319, 332 (1976). “Only after identifying such a right do[es this Court] continue
to consider whether the deprivation of that interest contravened the notions of due process.” Wojcik
v. City of Romulus, 257 F.3d 600, 609 (6th Cir. 2001). “Even though individuals often claim
property interests under various provisions of the Constitution, such interests are not created by the
Constitution; nor may individuals manufacture a property interest.” Id. Rather, “[r]esolution of the
federal issue begins . . . with a determination of what it is that state law provides.” Town of Castle
Rock, Colo. v. Gonzales, 545 U.S. 748, 757 (2005). “‘To have a property interest in a benefit, a
person must clearly have more than an abstract need or desire’ and ‘more than a unilateral
expectation to it.’” Id. at 756 (quoting Bd. of Regents of State Colleges v. Roth, 408 U.S. 564, 577
(1972)).
In the instant case, the parties suggest two sources for Chandler’s property interest: the
Village’s procedure for evaluating requests for building permits and the building permit itself. Of
the two possible sources for the property interest at stake, only the latter is cognizable. This Court
10
No. 07-3169
has held that processes mandated by municipal ordinances or state law are insufficient to establish
a property interest. See, e.g., Richardson v. Twp. of Brady, 218 F.3d 508, (6th Cir. 2000). See also
Olim v. Wakinekona, 461 U.S. 238, 250-51 (1983). Indeed, as the Supreme Court noted in
Loudermill, “‘[p]roperty’ cannot be defined by the procedures provided for its deprivation any more
than can life or liberty.” 470 U.S. at 541.
Nevertheless, we find that Chandler has a protected property interest in the building permit
issued to her by the Village Administrator. On July 14, 2003, the Village Administrator issued a
building permit to Chandler which authorized her to demolish her existing garage and construct a
new garage as approved by the ARB. This Court has held that the holder of a building or zoning
permit has a constitutionally protected interest and is therefore entitled to proper proceedings prior
to a final determination regarding revocation. See Tri-Corp Management Co. v. Praznik, 33 F.
App’x 742, 747-48 (6th Cir. 2002) (unpublished). Contrary to the Village’s assertions, it does not
appear that the permit issued was conditional or that the Administrator had the discretion to revoke
or deny the permit absent the direction of the ARB. See Kentucky Department of Corrections v.
Thompson, 490 U.S. 454, 462 (1989) (noting that “a State creates a protected liberty interest by
placing substantive limitations on official discretion.”). Cf. Town of Castle Rock, Colo., 545 U.S.
at 756 (“Our cases recognize that a benefit is not a protected entitlement if government officials may
grant or deny it in their discretion.”); Silver v. Franklin Township Bd. of Zoning Appeals, 966 F.2d
1031, 1036 (6th Cir. 1992) (finding that plaintiff did not have a protected property interest in a
11
No. 07-3169
conditional zoning certificate). Thus, Chandler had a protected property interest in the building
permit once it was issued by the Administrator.4
2. Procedural Rights Prior to Deprivation of Property Interest
“[O]nce it is determined that the Due Process Clause applies, the question remains what
process is due. The answer to that question is not to be found in the [Village ordinance]. ”
Loudermill, 470 U.S. at 541. Rather, the Constitution defines what procedures are sufficient to
satisfy due process. Morrissey v. Brewer, 408 U.S. 471, 489 (1972) (noting that to determine
whether a constitutional violation occurred, this Court’s “task is limited to deciding the minimum
requirements of due process”). In interpreting the constitutional requirements of due process, the
Supreme Court has held that the hallmark of due process is that a deprivation of a property interest
must be “preceded by notice and opportunity for hearing appropriate to the nature of the case.”
Loudermill, 470 U.S. at 542 (quoting Mullane , 339 U.S. 306, 313 (1950)); Matthews, 424 U.S. 319,
333 (1976) (noting that the Supreme Court “consistently has held that some form of hearing is
4
The Village argues that Chandler’s permit was conditional because she took the permit
subject to the rules and regulations established by the Village, including appellate procedures. This
argument is wholly without merit. First, the building permit was issued prior to the letter of appeal
written by Chandler’s neighbor and there was no indication that the permit was conditional at the
time it was issued. Second, the Village cites no authority for the proposition that oversight or
regulation negates a property interest in a license or permit. Were this Court to adopt such a rule,
a whole class of regulated benefits, licenses and permits would be excluded from the protection of
the Due Process Clause. Moreover, this directly contravenes the prior precedent of this court finding
that holders of liquor licenses have a property interest in such licenses, despite the fact that liquor
licenses are pervasively regulated by most states. See, e.g., Wojcik, 257 F.3d at 609 (observing that
this Court has recognized that the holder of a liquor license has a constitutionally protected interest);
George-Khouri Family Ltd. Partnership v. Ohio Dept. of Liquor Control, No. 04-3782, 2005 WL
1285677, at *5 (6th Cir. 2005) (unpublished) (citing Brookpark Entm’t, Inc. v. Taft, 951 F.2d 710,
716 (6th Cir. 1991)).
12
No. 07-3169
required before an individual is finally deprived of a property interest”). In evaluating whether a
particular process comports with the requirements of due process, this Court must weigh a number
of factors:
First, the private interest that will be affected by the official action; second, the risk
of an erroneous deprivation of such interest through the procedures used, and the
probable value, if any, of additional or substitute procedural safeguards; and finally,
the Government’s interest, including the function involved and the fiscal and
administrative burdens that the additional or substitute procedural requirements
would entail.
Id. at 335. “Applying this test, the Court has usually held that the Constitution requires some kind
of a hearing before the State deprives a person of liberty or property.” Zinermon v. Burch, 494 U.S.
113, 127 (1990). “In some circumstances, however, the Court has held that a statutory provision for
a post-deprivation hearing, or a common-law tort remedy for erroneous deprivation, satisfies due
process.” Id. at 128.
The Village asserts that the district court, in denying their motion for summary judgment,
erroneously concluded that the violation of local ordinances that establish the procedure for the
issuance and review of building permits could constitute a violation of due process. Based on this
erroneous conclusion, the Village contends that the district court improperly found that Chandler had
established a genuine issue of material fact for trial and therefore denied its motion for summary
judgment. We agree.
Before the district court, Chandler vociferously contended that the Village’s violation of its
permit review ordinances constituted a violation of her Fourteenth Amendment procedural due
process rights. To overcome summary judgment and the Village’s motion for judgment
notwithstanding the verdict, Chandler argued that § 1125.04(A)(6) did not allow for further review
13
No. 07-3169
of the ARB’s decision to approve her construction plans, either by the BZA or the Village Council.
Additionally, Chandler argued that § 1111.025 of the Village’s Codified Ordinances did not permit
appeals from decisions made by the ARB, but rather allowed for appeals from decisions made by an
Administrator or an Administrative Officer. Lastly, Chandler asserted that the Village lacked
authority to remand the matter of her permit back to the ARB for further consideration under §
1111.116. (Chandler Br. at 32-36) The Village, although maintaining that it complied with §§
1125.04(A)(6), 1111.02 and 1111.11 in entertaining the appeal of Chandler’s permit, contends that
whether it violated its ordinances is irrelevant to the constitutional due process inquiry. Rather, it
5
Section 1111.02 of the Village Ordinances provides, in relevant part, that:
The Board of Zoning appeals shall adopt such rules and regulations, provided they
are not in conflict with this Zoning Code or other ordinances of the Village, as may
be necessary to carry into effect the powers and jurisdiction conferred upon it as
follows:
(a) To hear appeals on decisions made by the Administrator, or by any administrative
officer on matters relating to this Zoning Code for relief from any order, requirement,
decision or determination, including the refusal, granting or revocation of permits,
and may thence decide appeals by reversing or affirming, wholly or in part, or
modifying such order, requirement, decision or determination.
(J.A. at 96)
6
Section 1111.11 provides authority for the Village Council to review the decisions of the
BZA:
Following a decision by the Board of Zoning appeals, each case shall be referred to
Council. After reviewing the Board’s decision, Council may confirm, amend or
reverse a decision by a majority vote of its membership. Immediately following
Council’s decision, record of such decision, including notice of the expiration date
of the proposed variance, shall be mailed to the applicant.
(J.A. at 99)
14
No. 07-3169
contends, the dispositive question is whether the actual process employed in reviewing Chandler’s
permit comported with the minimum constitutional protections required by due process.
Indeed, it appears that the Village’s position is supported by long standing Supreme Court
precedent. In Cleveland Bd. of Educ. v. Loudermill, 470 U.S. 532 (1985), the Supreme Court noted
that the question regarding “what process is due” is not answered by state law or local ordinances
but by constitutional benchmarks. Id. at 541-42. In DePiero v. City of Macedonia, 180 F.3d 770,
788 (6th Cir. 1999), and Eaton v. Charter Twp. of Emmett, No. 06-1542, 2008 WL 78051 (6th Cir.
2008), this Court applied Lourdermill to find that violations of state law did not suffice to establish
a due process violation. In DePiero, this Court held that the “[f]ailure to comply with state law does
not . . . automatically translate into a deprivation of procedural due process under the United States
Constitution. To satisfy due process under the Constitution, notice must be ‘reasonably calculated,
under all of the circumstances, to apprise interested parties of the pendency of the action and afford
them an opportunity to present their objections,’ and ‘must afford a reasonable time for those
interested to make their appearance.’” Id. at 788 (quoting Mullane v. Central Hanover Bank and
Trust Co., 339 U.S. 306, 314 (1950)).
Similarly, in Eaton, a panel of this Court rejected a plaintiff’s contention that a district court
was obliged to instruct a jury that a municipality’s failure to follow its own notice and hearing
ordinances constituted a violation of due process. Instead, this Court held that “[t]he requirements
of procedural due process are measured against constitutional standards. Thus, a violation of [a
local] ordinance violates the Due Process Clause to the extent that the procedures afforded appellants
were also constitutionally deficient.” Id. at *4.
15
No. 07-3169
Although the violation of the Village ordinances may not itself violate procedural due
process, we must examine the actual process applied during the review of Chandler’s permit to
determine if it afforded her meaningful “notice and opportunity for hearing appropriate to the nature
of the case.” Loudermill, 470 U.S. at 542. In the instant case, we find that the district court erred
in denying summary judgment or a judgment notwithstanding the verdict to the Village inasmuch
as Chandler was provided constitutionally adequate pre- and post-deprivation notice and opportunity
to be heard. On appeal, Chandler does not contend that the processes provided by the Village were
inadequate to meet the minimum constitutional requirements of due process or that additional
procedures were required under the test established by the Supreme Court in Matthews. Here,
Chandler was given constitutionally adequate notice and opportunity to be heard both before and
after her permit was revoked by the Village Council in September of 2003. At all pertinent hearings,
Chandler was represented by counsel and expressed her opposition to her neighbor’s appeal. Even
assuming all of the facts alleged by Chandler to be true, that in fact the Village violated its
ordinances and that she was required to expend time and money to secure her building permit, she
has not established, nor does she argue, that process afforded her was insufficient to meet the
constitutional mandates of due process. Rather, like Depiero and Eaton, the sole basis of Chandler’s
due process claim is that the Village failed to comply with its own ordinances. Like Depiero and
Eaton, such a basis is insufficient to establish that the Village provided insufficient procedural due
process when Chandler was otherwise provided notice and an opportunity to be heard. See Kratt v.
Garvey, 342 F.3d 475, 485 (6th Cir. 2003) (finding that a pilot was provided adequate procedural
due process prior to the suspension of his license where he was provided “notice and an opportunity
16
No. 07-3169
for a pre-revocation evidentiary hearing on the record”); Broady v. City of Mason, 250 F.3d 432,
437-38 (6th Cir. 2001) (finding that plaintiffs challenging the grant of a special use permit to a hair
salon were afforded meaningful notice and opportunity to be heard, despite city’s failure to follow
all internal procedures, inasmuch as the plaintiffs were noticed of meetings and had an opportunity
to voice their objections). See also 3883 Connecticut LCC v. District of Columbia, 336 F.3d 1068,
1074-75 (D.C. Cir. 2003) (finding that the District’s issuance of a stop work order did not violate
procedural due process where building permit holder was entitled to challenge the order under an
“appeals process with three levels of review”).
Had Chandler raised a substantive due process claim, perhaps our analysis would be
different. In the context of substantive due process, “governmental deprivations of life, liberty or
property are subject to limitations regardless of the adequacy of the procedures employed . . . .”
Pearson v. City of Grand Blanc, 961 F.2d 1211, 1216 (6th Cir. 1992); see also Zinnermon, 494 U.S.
at 125 (“[T]he Due Process Clause contains a substantive component that bars certain arbitrary,
wrongful government actions “regardless of the fairness of the procedures used to implement
them.”). In the context of zoning and land use determinations, we have held that substantive due
process protects against “arbitrary or capricious” action by a state either by legislative or
administrative action . . . .” Id. To prevail under the “arbitrary or capricious” standard, a litigant
must show “that there is no rational basis for the administrative decision.” Id. at 1221. It certainly
appears that the Village Council lacked a rational basis for subjecting Chandler to numerous hearings
and rescinding her building permit. The Village Council rescinded Chandler’s permit despite the
fact that the matter had been approved by the ARB with an accompanying rationale on at least two
17
No. 07-3169
occasions and despite the fact that the Village Council had no new information regarding Chandler’s
compliance with the Village ordinance. Nevertheless, Chandler has not raised a substantive due
process claim on appeal and we must therefore rest our disposition on the merits of her procedural
due process claim. See United States v. Hayes, 218 F.3d 615, 620 (6th Cir. 2000) (noting that this
Court will not entertain issues raised for the first time on appeal).
As noted above, Chandler has not demonstrated that she received constitutionally inadequate
notice or opportunity to be heard regarding the appeal of the issuance of her building permit. Thus,
we find that the Village is entitled to judgment as a matter of law with respect to Chandler’s
procedural due process claim. Additionally, inasmuch as Chandler cannot be deemed a prevailing
party in this matter, she is not entitled to attorney’s fees pursuant to 42 U.S.C. § 1988.
CONCLUSION
For the reasons stated above, we REVERSE the judgment of the district court.
18