In The
Court of Appeals
Sixth Appellate District of Texas at Texarkana
______________________________
No. 06-09-00069-CV
______________________________
SCOTT D. MARTIN, Appellant
V.
RUBEN S. MARTIN, III, Appellee
On Appeal from the 188th Judicial District Court
Gregg County, Texas
Trial Court No. 2008-961-A
Before Morriss, C.J., Carter and Moseley, JJ.
Opinion by Justice Moseley
OPINION
I. FACTS AND PROCEDURAL POSTURE
In the intervening years since R. S. Martin, Jr., founded the company which eventually
became Martin Resource Management Company (MRMC) in 1951, it experienced substantial
growth. In its current situation, MRMC is a privately held company, which is also general partner
of Martin Midstream Limited Partners, a publicly-traded company, valued in the hundreds of
millions of dollars. It had been successfully jointly managed for some twenty years by Ruben S.
Martin, III, and Scott D. Martin, sons of the founders (who owned or controlled all of the voting
shares and both of whom were on the five-member board of directors) in an informal, collaborative
relationship. 1 Formal shareholder and board meetings were infrequent and they regularly
conducted votes through unanimous written consents.
Basically, an internecine power struggle over the control of MRMC arose between the
brothers. Although the nature of the brothers’ dispute is complicated, essentially Ruben contended
that Scott was trying to take control of the company, while Scott took the position that it was
Ruben’s goal to ―freeze‖ Scott out from corporate management. Beginning in 2006, the brothers’
relationship began to deteriorate regarding the general direction of the company and their collegial
1
Ruben was President, Chief Executive Officer, and Chairman of the Board of MRMC, an MRMC shareholder, and
the trustee of the R. S. Martin’s Children Trust No. 1 (Angela’s Trust). Scott was Executive Vice President of
MRMC, a member of the Board of Directors, an MRMC shareholder, and the trustee of the Ruben S. Martin, III,
Dynasty Trust (Dynasty Trust). So long as Ruben was trustee of Angela’s Trust and could control the votes of those
shares, he had a slight voting advantage over Scott. However, the time for the termination of the trust was fast
approaching and the brothers’ mother had the ability to remove Ruben as trustee and name another person in his stead.
2
relationship was finally fractured in 2007 when Ruben decided that MRMC should seek to acquire
a California refinery, while Scott opposed the move. This course of events led Scott to attempt to
stop the purchase by formalizing MRMC’s corporate decision-making process, which would
impose checks on any type of unilateral control of the company by Ruben. Meanwhile, control of
the board of directors remained in flux.
In an effort to settle their dispute over corporate control, Ruben and Scott met together and
hammered out an agreement, which was monumentalized in a nineteen-paragraph document
captioned ―Settlement Agreement‖ drafted by Scott’s attorney and signed on January 29, 2008.2
2
The terms of the ―Settlement Agreement‖ are summarized as follows:
Paragraph one: ―Scott and Ruben will negotiate a shareholder agreement . . . .‖
Paragraph two: ―The parties shall work together to better organize the use of MRMC airplanes.‖
Paragraph three: ―Scott may elect to sell any Colorado house and the proceeds shall be split according to ownership
in such house.‖
Paragraph four: ―Scott and Ruben shall be permitted to invite anyone to the MRMC Board meetings.‖
Paragraph five: ―Upon completion of all of the obligations under this Settlement Agreement (the ―Completion
Date‖), Wes Skelton shall resign as a co-trustee of the ESOP and Ruben and Scott shall remain as the sole co-trustees.‖
Paragraph six: ―Upon the Completion Date, Scott shall resign from all trustee positions relating to any trust of
Ruben’s and a successor trustee shall be appointed at Ruben’s discretion.‖
Paragraph seven: ―On or before the Completion Date, Scott and Ruben shall each be given Employment Agreements
with equal compensation and severance packages.‖
Paragraph eight: ―Upon the Completion Date, Scott, Ruben and the officers and directors of MRMC shall execute
mutual releases from any and all claims related to the issues subject to this Agreement.‖
Paragraph nine: ―Upon the Completion Date, Ruben will transfer one share of common stock of MRMC to Scott.‖
3
Among other things, the agreement required the brothers to negotiate a shareholder agreement in
good faith for sixty days (later extended by agreement to ninety days) and that upon completion of
―all of the obligations under this Settlement Agreement‖ (defined as the ―Completion Date‖),
certain other obligations would arise. Although the parties negotiated, they were unable to agree
on the terms of a shareholder agreement and none of the remaining terms have been fulfilled.
Although he acknowledged the failure to arrive at an agreement concerning the content of a
shareholders’ agreement, Scott characterized Ruben’s failure to perform the other obligations set
Paragraph ten: ―Scott and Ruben will be the MRMC representatives appointed to the Arcadia joint venture board of
directors.‖
Paragraph eleven: ―Upon the Completion Date, Don Neumeyer and Wes Skelton will resign from the MRMC Board.
Ruben and Scott will each have the right to appoint 1 additional Board member . . . . This shall be accomplished
through a Unanimous Consent of Shareholders.‖
Paragraph twelve: ―On the Effective Date, Ruben and Scott shall be appointed as co-investment trustee’s [sic] of
Angela’s Trust.‖
Paragraph thirteen: ―Upon the Completion Date, Ruben and Scott will each receive equal unsecured loans of up to
$2,000,000 from MRMC, subject to Amegy approval on all of the terms and conditions of such loan.‖
Paragraph fourteen: ―Upon the Completion Date, Scott, Ruben and Margaret Martin will be reimbursed by MRMC
for all legal, consulting and other related expenses incurred in connection with the negotiation of the issues that are the
subject of this Settlement Agreement.‖
Paragraph fifteen: ―Upon the Completion Date, any and all outstanding stock options in MRMC shall be converted to
non-voting shares upon exercise.‖
Paragraph sixteen: ―There will be no shareholder votes except by unanimous consent until the Completion Date.‖
Paragraph seventeen: ―Board action for MRMC will only be taken through unanimous consent until the Completion
Date.‖
Paragraph eighteen: ―Scott and Ruben will use their good faith efforts to work through counsel to document the
agreements contained herein within sixty (60) days of the Effective Date.‖
Paragraph nineteen: ―Angela will become employed by MRMC (at a location of her choosing), if she wishes.‖
4
forth in the agreement as a breach of contract. Scott brought suit to enforce the agreement,
seeking specific performance and damages.3 After a ten-day trial, the trial court submitted the
case to the jury on the issues of breach and damages.4 In doing so, the trial court impliedly found
the agreement was an enforceable contract. Holt Atherton Indus., Inc. v. Heine, 835 S.W.2d 80,
83 (Tex. 1992); Burnett v. Motyka, 610 S.W.2d 735, 736 (Tex. 1980) (per curiam) (conclusions of
law that are necessary, but not made, are deemed in support of judgment). The jury found Ruben
breached the agreement and awarded Scott $3.2 million in damages and attorney’s fees of $1.5
million. The judgment awarded Scott $3.2 million in accord with the jury verdict, included
provisions requiring specific performance by Ruben of certain portions of the settlement
agreement, and awarded $13,533.85 in costs to Scott. Ruben filed a motion for judgment
notwithstanding the verdict and alternatively a motion for new trial, contending Scott was not
entitled to judgment because the settlement agreement was unenforceable as a matter of law.
That motion was overruled by operation of law.
3
Scott maintains that because April 30, 2008, marked the end of the ninety-day negotiation period under the
agreement, this was the date upon which all obligations under the agreement were to be fulfilled, i.e., the completion
date. In his third amended original petition, Scott alleged that ―Ruben has failed and refused to perform the
obligations and undertakings required of him under the terms of the Settlement Agreement.‖
4
The jury was also asked to determine whether Ruben and Scott were ultimately able to vote 100% of the voting shares
of MRMC on the date of the agreement, whether Ruben and Scott were ultimately able to vote 67% of the voting
shares on the date of the agreement, and whether by virtue of their shared voting power on the date of the agreement,
Ruben and Scott were able to select and remove officers and directors of MRMC as well as the trustees for the Martin
Resource Management Employee Stock Ownership Trust. The jury’s positive response to these issues, as well as to
the monetary damage question, is not in dispute.
5
In the race to appeal, Scott prevailed. In his sole point of error, Scott claims that he was
entitled to recover $16,028.15 in costs, rather than the $13,533.85 awarded in the judgment,
alleging that the trial court had acted arbitrarily, picking a number between the cost figure proved
up by Scott and the number argued for by Ruben. Ruben filed a cross-appeal. In his reply brief,
Ruben streamlined his issues and argument.5 While his principal brief presented four issues,
Ruben’s basic issues, as joined by Scott on cross-appeal, are whether the January 29, 2008,
settlement agreement is legally enforceable, and if so, whether Scott was entitled to an award of
both money damages and specific performance for breach of the agreement. Because the
settlement agreement is not enforceable as a matter of law, we reverse the judgment of the trial
court and render judgment for Ruben.
II. ANALYSIS
Because resolution of Ruben’s issues is determinative of Scott’s point of error regarding
the award of court costs, the issues raised by Ruben will be considered first.
In his first issue on cross-appeal, Ruben contends the settlement agreement is an
unenforceable agreement to agree. Scott contends that this issue (not having been submitted to
the jury) was abandoned and, thus, waived on appeal. We first address the issue of whether the
agreement’s enforceability was properly preserved and then discuss the merits of the issue.
5
In his sur-reply brief, Scott contends Ruben improperly presented new issues on reply, in violation of Rules 38.1(f)
and 38.3 of the Texas Rules of Appellate Procedure. TEX. R. APP. P. 38.1(f) (―The [initial] brief must state concisely
all issues or points presented for review.‖); TEX. R. APP. P. 38.3 (reply brief should address matters raised in appellee’s
brief). Because Ruben fully briefed the issues regarding the agreement’s legal enforceability and the propriety of the
award of specific performance in addition to monetary damages, these issues are squarely before this Court.
6
A. The Enforceability Issue Was Preserved
The central issue raised in this appeal is whether the parties’ January 29, 2008, settlement
agreement is an unenforceable agreement to agree. Scott contends that Ruben abandoned the
contract formation issue by not submitting a question to the jury on this issue and in failing to
object to the absence of such a question. This contention is based on Ruben’s concession that he
assented to the settlement agreement individually, but his assent to its terms was not in a
representative capacity. On appeal, Ruben places more emphasis on the enforceability of the
settlement agreement than at the trial level and relies less on the issue of the capacity under which
he was operating at the time he signed the settlement agreement. Because he raised this issue in
his motion for directed verdict and in his motion for judgment notwithstanding the verdict, or in
the alternative, motion for new trial, Ruben contends that the issue of the contract’s legal
enforceability has successfully been preserved. We agree.
Black’s Law Dictionary defines a ―contract‖ as ―[a]n agreement between two or more
parties creating obligations that are enforceable or otherwise recognizable at law.‖ BLACK’S LAW
DICTIONARY 365 (9th ed. 2009). According to the Restatement of Contracts, the terms
―agreement‖ and ―contract‖ are not synonymous; ―agreement‖ refers to a ―manifestation of mutual
assent on the part of two or more persons,‖ whereas the term ―contract‖ refers to ―a promise or a set
of promises for the breach of which the law gives a remedy, or the performance of which the law in
some way recognizes a duty.‖ RESTATEMENT (SECOND) OF CONTRACTS §§ 1, 3 (1981); see, e.g.,
7
Wiley v. Bertelsen, 770 S.W.2d 878, 882 (Tex. App.––Texarkana 1989, no writ) (noting that the
term ―agreement‖ is more broad than the term ―contract‖ and that it is possible for parties to enter
into an agreement but still not have a contract). Although it is possible to enter into an agreement
without forming a contract, the converse is not true.
Texas Pattern Jury Charge 101.1 sets forth the basic question regarding the existence of a
contract. TEXAS PATTERN JURY CHARGES, BUSINESS, CONSUMER, INSURANCE & EMPLOYMENT,
PJC 101.1 (2008). The commentary to this basic question of the existence of a contract states that
101.1 ―submits the issue of the existence of an agreement. It should be used if there is a dispute
about the existence of an agreement or its terms and a specific factual finding is necessary to
determine whether the agreement constitutes a legally binding contract.‖ Id. Rather than
contending that a fact issue (which would require resolution by a jury) existed with respect to
whether the contract was legally binding, Ruben maintained that the contract was not enforceable
as a matter of law.
The failure to object to the omission of a question on contract formation, when taking the
position that no contract exists in the first instance, is inconsistent with a waiver of that position.
Ruben’s concession that a fact issue did not exist on the intent to agree does not, however, resolve
the issue of whether the contract is legally enforceable. In essence, Ruben complained that there
was no evidence to warrant the submission of a question of contract formation to the jury because,
as a matter of law, the contract was unenforceable. The question of whether an agreement is an
8
unenforceable agreement to agree is a question of law, not a question for the jury. See Mickens v.
Longhorn DFW Moving, Inc., 264 S.W.3d 875, 880 (Tex. App.––Dallas 2008, pet. denied)
(―Whether a contract is legally enforceable is a question of law for the court—not a fact issue for
the jury.‖); Meru v. Huerta, 136 S.W.3d 383, 390 (Tex. App.––Corpus Christi 2004, no pet.)
(―[W]hether a particular agreement is an enforceable contract is generally a question of law.‖).
Moreover, Ruben properly preserved the issue of whether the contract was legally
enforceable as a matter of law. To preserve an issue of law, the appellant must raise the issue
through one of the following: (1) a motion for directed verdict; (2) a motion for judgment
notwithstanding the verdict; (3) an objection to the submission of the question to the jury; (4) a
motion to disregard the jury’s answer to a vital fact question; or (5) a motion for new trial. See
Cecil v. Smith, 804 S.W.2d 509, 510–11 (Tex. 1991); United Parcel Serv., Inc. v. Tasdemiroglu,
25 S.W.3d 914, 916 (Tex. App.––Houston [14th Dist.] 2000, pet. denied). Ruben filed a motion
for directed verdict on the issue of whether the contract was legally enforceable based on its status
as an executory contract both at the conclusion of the plaintiff’s case-in-chief and at the conclusion
of the evidence. On each occasion, the motion was overruled. In addition, Ruben filed a motion
for judgment notwithstanding the verdict and, alternatively, motion for new trial relying on this
issue. This motion was overruled by operation of law.
Because Ruben raised this issue of law by filing the appropriate motions, the issue of the
agreement’s enforceability was properly preserved.
9
B. The Settlement Agreement Is Unenforceable as a Matter of Law
The primary issue in this case is whether the language expressly set forth in the agreement
was sufficiently definite to be enforceable against Ruben. Whether a particular agreement is an
enforceable contract is a question of law reviewed de novo. Perry Homes v. Cull, 258 S.W.3d
580, 598 (Tex. 2008); Elijah Ragira/VIP Lodging Group, Inc. v. VIP Lodging Group, Inc., 301
S.W.3d 747, 754 (Tex. App.––El Paso 2009, pet. denied). On appellate review, we are not
required to give any particular deference to the trial court’s legal conclusion that the contract was
legally enforceable. See Cap Rock Elec. Co-op., Inc. v. Tex. Utils. Elec. Co., 874 S.W.2d 92, 99
(Tex. App.––El Paso 1994, no pet.). Rather, we are required to independently evaluate the trial
court’s legal determination. Id. Legal conclusions of a trial court are to be reversed only when
they are erroneous as a matter of law. America’s Favorite Chicken Co. v. Samaras, 929 S.W.2d
617, 622 (Tex. App.––San Antonio 1996, writ denied).
Even though Ruben acknowledged (with few qualifications) his assent to every term of the
settlement agreement, he maintains that by its express terms, the agreement is not a final,
enforceable contract; he maintains that it was, rather, a mere listing of areas the two brothers
planned to address over the next few months in an attempt to resolve their disputes. The first
10
paragraph of the agreement calls for the negotiation of a shareholder agreement binding on all
MRMC shareholders.6 It provides that:
(1) Scott and Ruben will negotiate a shareholder agreement (―Shareholder
Agreement‖) that will be applicable to all shareholders. It will provide that Ruben
will continue to be the CEO of Martin Resource Management Corporation
(―MRMC‖) but the authority to conduct the day to day operations of MRMC will
be subject to those responsibilities that are delegated to him by the Board of
Directors of MRMC. Scott shall have the ability to determine what authority the
Board will delegate to Ruben. Scott’s duties will need to be more clearly defined
and delegated by the Board as well. The Shareholders Agreement will contain
provisions typically found in large, complex corporations, including provisions
governing liquidity for all the shareholders. The parties will negotiate in good
faith the provisions of the Shareholders Agreement and try to reach agreement on
some form of buy-sell provisions contained therein. Such buy-sell provision will
be subject to a 1 yr. lockup period. Finally, the Shareholder Agreement will
require at least quarterly Board meetings.
It is undisputed that the parties never arrived at an agreement for the content of a
shareholder agreement and never executed one.7
Paragraphs five through nine, eleven, and thirteen through fifteen each contain provisions
that are triggered by the ―Completion Date,‖ as that term is defined in the agreement.8 The
―Completion Date‖ is defined as the completion ―of all of the obligations under this Settlement
Agreement.‖ The dependent provisions include: (1) Wes Skelton’s resignation as MRMC
6
Shareholder agreements in Texas are subject to the requirements of Chapter 21, Subchapter C of the Texas Business
Organizations Code—and require approval and ratification by all shareholders, among other things, to be effective.
TEX. BUS. ORGS. CODE ANN. § 21.101(b) (Vernon 2010 pamphlet).
7
Paragraphs two, three, and four of the agreement address treatment of MRMC assets, such as use of the MRMC
planes, sale of any ―Colorado house,‖ and Scott’s and Ruben’s ability to invite whomever they wish to attend MRMC
Board meetings.
8
Each of these paragraphs is prefaced by the language, ―Upon the Completion Date,‖ or ―On or before the Completion
Date.‖
11
ESOP Trustee; (2) Scott’s resignation as trustee for Ruben’s family trusts; (3) MRMC’s extension
of employment agreements to Scott and Ruben; (4) Scott’s, Ruben’s, and the MRMC board
members’ execution of mutual releases from any and all claims related to issues subject to the
agreement; (5) Ruben’s transfer of one share of MRMC stock to Scott; (6) Neumeyer’s and
Skelton’s resignations from MRMC’s board, to be replaced by Ruben’s and Scott’s respective
designees; (7) the extension of $2,000,000.00 loans to Scott and to Ruben, respectively, upon
approval of Amegy (MRMC’s financing arm); (8) reimbursement by MRMC of all legal fees
incurred by Scott, Ruben, and Margaret Martin related to the negotiations; and (9) conversion of
all outstanding MRMC stock options to ―non-voting,‖ to last until the termination of Angela’s
Trust.9
The bedrock of the instant dispute is that Ruben and Scott differ over the meaning of
paragraph one of the settlement agreement. The interpretation of this paragraph is central to the
issue of the agreement’s enforceability. Ruben maintains that the plain meaning of the settlement
agreement is that Scott and Ruben would spend sixty days (later extended to ninety days) to
negotiate a shareholder agreement (paragraph one) and other items that would resolve the issues
between them (the remaining provisions of the agreement). Although the parties negotiated for a
period of ninety days, no shareholder agreement was reached, and none of the remaining
9
The remaining paragraphs—ten, sixteen, seventeen, and nineteen—require that the MRMC Board could take action
only by unanimous consent through the ―Completion Date‖; provide that Angela Alexander may be employed by
MRMC at a location of her choosing, and state that both Scott and Ruben will be the MRMC representatives appointed
to the Arcadia joint venture board of directors.
12
agreements were carried out. 10 Ruben thus contends that because the obligations under the
settlement agreement (including the negotiation of a shareholder agreement) were not completed,
the ―Completion Date‖ never occurred. As a result, none of the dependent provisions were
triggered.11
When an agreement leaves material matters open for future adjustment and agreement that
never occur, it is not binding on the parties and merely constitutes an agreement to agree. Fort
Worth Indep. Sch. Dist. v. City of Fort Worth, 22 S.W.3d 831, 846 (Tex. 2000), superseded by
statute on other grounds, Vantage Sys. Design, Inc. v. Raymondville Indep. Sch. Dist., 290 S.W.3d
312, 316 (Tex. App.––Corpus Christi 2009, pet. filed); Sadeghi v. Gang, 270 S.W.3d 773, 776
(Tex. App.––Dallas 2008, no pet.). Said another way, a party cannot accept an offer so as to form
a contract unless the terms of that contract are reasonably certain. Fort Worth Indep. Sch. Dist.,
22 S.W.3d at 846. Contract terms are reasonably certain ―if they provide a basis for determining
the existence of a breach and for giving an appropriate remedy.‖ RESTATEMENT (SECOND) OF
CONTRACTS § 33(2) (1981). If an alleged agreement is so indefinite as to make it impossible for a
10
Ruben points out that many of the provisions of the settlement agreement require MRMC board approval. Darren
Inoff, attorney for Scott, drafted the settlement agreement. Inoff provided Scott with a list of decisions that required
MRMC board approval. Those decisions include: the election or removal of officers from the corporation; entering
into or amending any employment or severance agreement with any officer or employee of the corporation, and all
compensation programs (including base salaries and bonuses) for officers and key employees; the purchase, sale,
lease, transfer or other acquisition or disposition of assets (including equity interests in any entity) in a transaction or
series of transactions in excess of a given amount; any real estate lease or purchase; any commencement or settlement
of any litigation; and approval of any other item specifically required elsewhere in the shareholder’s agreement,
bylaws, or articles of incorporation. These categories of actions requiring board approval apply to paragraphs three,
five, seven, eight, eleven, thirteen, fifteen, sixteen, and seventeen.
11
Paragraph eighteen of the settlement agreement provides that ―Scott and Ruben will use their good faith efforts to
work through counsel to document the agreements contained herein within sixty (60) days of the Effective Date.‖
13
court to fix the legal obligations and liabilities of the parties, it cannot constitute an enforceable
contract. Playoff Corp. v. Blackwell, 300 S.W.3d 451, 455 (Tex. App.––Fort Worth 2009, pet.
denied).
Conversely, enforceable settlement agreements need only ―contain sufficient terms to
determine the parties’ obligations but [are] not required to resolve all disputed issues.‖ W. Beach
Marina, Ltd. v. Erdeljac, 94 S.W.3d 248, 258–59 (Tex. App.––Austin 2002, no pet.). ―Where the
evidence shows that the parties intended to enter into an agreement, the courts should find the
contract to be definite enough to grant a remedy provided that there is a certain basis for
determining the remedy.‖ America’s Favorite Chicken Co., 929 S.W.2d at 623. Parties may
therefore agree upon some contractual terms, understanding them to be an agreement, and leave
other contract terms to be made later. T.O. Stanley Boot Co. v. Bank of El Paso, 847 S.W.2d 218,
221 (Tex. 1992). It is only when an essential term is left open for future negotiation that there is
nothing more than an unenforceable agreement to agree. Id. The parties here disagree regarding
the enforceability of the contract based on (1) whether the completion date, as that term is defined
in the agreement, was reached; and (2) whether the shareholder agreement was an essential term of
the overall agreement.
(1) A Completion Date Was Not Reached
Ruben contends the parties, as a part of their ―obligations‖ under the settlement agreement,
were required to not only negotiate, but to actually reach a shareholder agreement, reduce it to
14
writing, sign it, and adopt it as an antecedent to the other obligations. Without this obligation
being brought to fruition, a ―Completion Date‖ never happens. Without a ―Completion Date,‖
none of the nine dependent provisions take place. In this scenario, the trial court could not
determine what the parties’ rights and obligations would be under the settlement agreement
because the court could not possibly know what agreement the parties would have negotiated.
Scott contends the obligation was simply to negotiate (but not necessarily agree upon and
adopt) a shareholder agreement, and the parties had sixty days in which to do so (later extended to
ninety days). According to Scott, the ―Completion Date‖ is reached by fulfilling the obligation to
negotiate as set out by paragraph number one of the settlement agreement. In support of this
position, Scott relies on Geophysical Micro Computer Applications (Int’l) Ltd. v. Paradigm
Geophysical Ltd., No. 05-98-02016-CV, 2001 WL 1270795, at *6 (Tex. App.––Dallas Oct. 24,
2001, pet. denied) (not designated for publication) (finding an obligation to ―negotiate in good
faith‖ satisfied ―the mutuality of obligation requirement as a matter of law‖).
Paradigm involved a letter of intent regarding the purchase of computer software. The
letter clearly identified the asset to be sold, its price and adjustments to the purchase price,
royalties, a method to calculate the closing date, and the payment of financing terms. The letter of
intent also provided for ―other terms‖ regarding due diligence, responsibility for closing
documents, and other ―necessary commercial terms.‖ There was no evidence in this summary
judgment case that the ―other terms‖ or other ―necessary commercial terms‖ were essential for the
15
contract. The court held that the trial court improperly granted summary judgment because the
evidence was disputed and the language in the document was inconclusive on whether the parties
intended the agreement to be a memorialization of the parties’ agreement or a condition precedent
to the formation of a contract. Id. Paradigm also moved for summary judgment on the basis that
the letters were not enforceable because they lacked mutuality of obligation, i.e., they were subject
to the parties’ corporate approval, and Paradigm’s board had disapproved and rejected the
transaction. Because the letter required the parties to negotiate in good faith, the mutuality of
obligation requirement was satisfied as a matter of law; the issue of whether Paradigm discharged
this obligation in good faith was a question of fact. Id. Because this case focuses on mutuality of
obligations, and not whether an agreement to negotiate in good faith amounts to an enforceable
contract, it is not persuasive. Mutuality of obligation does not render an otherwise unenforceable
contract, lacking essential terms, enforceable.
Ruben maintains that an agreement to negotiate in the future is unenforceable, even if the
agreement calls for a good-faith effort in negotiations, citing John Wood Group USA, Inc. v. ICO,
Inc., 26 S.W.3d 12, 21 (Tex. App.––Houston [1st Dist.] 2000, pet. denied). This case involved a
letter agreement for the sale of corporate assets, which stated that the essential terms of the
proposed sale were ―not binding.‖ The jury awarded damages for breach of contract. On appeal,
the appellant maintained that even if the sale provisions were held to be unenforceable—as they
were—the damages should nevertheless stand because the Wood Group breached the good-faith
16
clause of the letter agreement, by which both parties intended to be bound. In support of that
proposition, appellant relied on Illinois law, under which agreements to negotiate toward the
formation of a contract are themselves enforceable as contracts. The court recognized, however,
that under Texas law, an agreement to negotiate in the future is unenforceable, even if the
agreement calls for a ―good faith effort‖ in the negotiations. Id. at 21 (citing Radford v. McNeny,
129 Tex. 568, 104 S.W.2d 472, 474 (1937); Maranatha Temple, Inc. v. Enter. Prods. Co., 893
S.W.2d 92, 104 (Tex. App.––Houston [1st Dist.] 1994, writ denied) (presence of term ―good faith
effort‖ in agreement not talismanic; its presence does not automatically mean the provision that
contains this phrase is enforceable—an agreement to enter into good-faith negotiations in future
not enforceable)).
Scott’s argument, though creative, does not conform to Texas law. The shareholder
agreement must be executed, not merely negotiated. The agreement itself supports this
conclusion. Paragraph one states that the brothers ―will negotiate a shareholder agreement‖ that
―will be applicable to all shareholders.‖ Since the goal of negotiation is agreement, if the parties
are required to ―negotiate an agreement,‖ they must necessarily and ultimately conclude with a
negotiated agreement. Otherwise, the parties have only attempted to negotiate an agreement.
Additionally, paragraph one contains obligatory language which supports the conclusion that its
terms require the execution of a shareholder agreement. It requires that (the shareholder
agreement) ―will provide,‖ ―will contain,‖ and ―will require.‖ Imperative statements such as
17
these envision the object to be accomplished will, in fact, be accomplished. In failing to negotiate
a shareholder agreement, the parties fell short of accomplishing this goal. Thus, the completion
date—meaning completion ―of all of the obligations under this Settlement Agreement‖—was not
reached because the obligation of executing a shareholder agreement was not completed.
Without a completion date, Ruben contends the agreement is merely an agreement to agree in the
future, which is not legally binding. See Fort Worth Indep. Sch. Dist., 22 S.W.3d at 846.
However, if the shareholder agreement provision of the agreement is not essential, as Scott
contends, the agreement can nevertheless be enforced. See T.O. Stanley Boot Co., 847 S.W.2d at
221 (only when essential term left open for future negotiation is agreement an unenforceable
agreement to agree). We, therefore, must determine whether the shareholder provision is
essential to the overall settlement agreement.
(2) The Shareholder Agreement Is Essential to the Settlement Agreement
Ruben maintains that each provision of the settlement agreement is essential because all
obligations, i.e., each provision of the agreement, must be completed in order to reach the
completion date.12 Even so, Ruben characterizes the shareholder provision as the ―pearl‖ of the
agreement, an essential provision. The issue of essential contractual provisions was recently
addressed in Playoff Corp., 300 S.W.3d 451.
12
The definition of ―Completion Date‖ as the completion of all obligations under the agreement, in light of the nine
provisions to be concluded upon the completion date, creates a never-ending chain of events which cannot, logically,
result in a completion date.
18
In that case, Blackwell brought suit against Playoff, a sports trading-card company, for
breach of contract. Id. at 453. After finding that a breach of contract occurred, the jury found
damages of $6.1 million, but the trial court granted a take-nothing judgment notwithstanding the
verdict, holding that the agreement was ―legally unenforceable.‖ Id. at 454. The Fort Worth
court affirmed. The matters in dispute in Playoff involved an employment agreement, the most
hotly contested provision of which involved the issue of payment by Playoff, the employer, to
Blackwell, the employee. That provision was summarized as follows:
Playoff . . . would pay Blackwell 25% of the proceeds from the sale of Playoff or
entities contemplated to be formed by the parties, if any, after reducing the
proceeds from the sale by $ 5,000,000.00 (Playoff's agreed fair market value at the
time of the alleged employment agreement); or 25% of the fair market value of
Playoff or entities contemplated to be formed by the parties, if any, after reducing
the fair market value by $ 5,000,000.00, on the last day of his employment if
Playoff or any entity contemplated to be formed by the parties terminated
Blackwell's employment.
Id at 453. Because the term ―fair market value‖ was to be determined by ―additional negotiation
and agreement between the parties,‖ the ―alleged agreement left a material matter open for future
adjustment and agreement that never occurred.‖ Id. at 457. Consequently, the agreement was
unenforceable as a matter of law. Id.
In contrast to Playoff, Scott maintains that while the parties contemplated future
negotiations on some issues, including the shareholder provision, future negotiations do not negate
contractual intent as a matter of law. Komet v. Graves, 40 S.W.3d 596, 601–02 (Tex. App.––San
19
Antonio 2001, no pet.). In that case, an employment agreement set out the material terms of the
employee’s salary and benefits, but also provided the following provisions: ―[a] commission
schedule structure shall be created and mutually agreed to and incorporated into this agreement‖
that was ―to be determined by a future document‖ and an ―[e]quity agreement to be determined in
subsequent document.‖ Id. at 599. Because the agreement set out the effective date, salary,
health insurance provisions, and vacation time and other benefits, the parties’ obligations were
sufficiently outlined. In Komet, the court determined that the percentages were not material and
therefore could ―be left open for future negotiations without destroying the contract’s
effectiveness.‖ Id. at 602. Because Komet determined that no essential provision was left to
future negotiation, the contract was enforceable.
Scott makes the same argument in this case. He contends that the shareholder agreement
was not essential to the overall agreement because it was not imperative or indispensible, pointing
out that the installation of a four-member board was not predicated on the existence of a
shareholder agreement 13 (which, according to Scott, was the key essential term to the entire
13
The provision requiring a four-member board is not a part of the shareholder agreement; it is contained in paragraph
eleven of the settlement agreement. Paragraph eleven states:
Upon the Completion Date, Don Neumeyer and Wes Skelton will resign from the MRMC Board.
Ruben and Scott will each have the right to appoint 1 additional Board member, it being assumed
(but not required) that Bob Bondurant will be Ruben’s appointment and Mike Gayler will be Scott’s
appointment. Courtney Stovall and Angela Alexander shall also be appointed as advisory,
non-voting Board members. This shall be accomplished through a Unanimous Consent of
Shareholders. Under no circumstances will these changes constitute a Change of Control under
any employment agreement, retention or severance agreement or any other agreement entered into
by MRMC. The current Board shall execute a written consent authorizing these Board changes to
20
agreement).14 To effectuate the settlement agreement, the four-member board of directors would
come first, and then the other documents would ―fall into place.‖ 15 Therefore, even when
negotiations on the shareholder agreement failed, the remaining provisions of the settlement
agreement were––in Scott’s estimation––enforceable.
What terms are ―material‖ or essential to a contract should be determined on an
agreement-by-agreement basis. T.O. Stanley Boot Co., 847 S.W.2d at 221 (―Each contract should
be considered separately to determine its material terms.‖). A close corporation such as MRMC
may, by statute, be managed either by a board of directors or in the manner provided for in a
shareholders’ agreement. TEX. BUS. CORP. ACT ANN. art. 12.31(A)(2) (Vernon 2003). 16 By
statute, a shareholder agreement may restrict the discretion or powers of the board of directors.
Or, the agreement can eliminate the board of directors and authorize the business and affairs of the
confirm that these changes shall not constitute a Change of Control. The composition of the Board
cannot be changed until The R.S. Martin Jr., Children’s Trust No. One f/b/o Angela Santi Jones
(also known as Angela J. Alexander) (―Angela’s Trust‖) terminates upon which time any
shareholder shall be entitled to call a special meeting for the purpose of proposing a new slate of
directors of the MRMC Board. The Bylaws shall be amended accordingly to permit this Board
composition (since Bylaws currently require seven (7) Board members).
14
After a hard fought battle, Scott and Ruben agreed on a board of Scott and his designee and Ruben and his designee.
It was not Scott’s intention that the four-member board be contingent on or subject to the successful negotiation of a
shareholder agreement. The four-member board provision does appear to be an essential provision of the overall
agreement, given the degree of specificity it contains. That does not, however, resolve the issue of whether the
shareholder provision is essential to the settlement agreement.
15
Both Scott and Ruben testified they could vote 100% of the shares of MRMC. Scott testified, with respect to
paragraph eleven, that if Skelton did not want to resign, he could be made to resign. Scott and Ruben controlled the
MRMC board vote on January 29, 2008, so any provisions requiring action by the board of directors could be
effectuated by their board votes. The MRMC board appoints the trustees of the ESOP as well, so the board could also
effectuate changes to the ESOP.
16
This section of the Business Corporation Act expired on January 1, 2010, but was in effect at the time the settlement
agreement was executed. TEX. BUS. CORP. ACT ANN. art. 11.02 (Vernon Supp. 2010).
21
corporation to be managed by one or more of its shareholders or other persons. TEX. BUS. ORGS.
CODE ANN. § 21.101(b)(1).
Paragraph one of the settlement agreement provides that the shareholder agreement will
delegate responsibility to Scott to determine what authority the board of directors will delegate to
Ruben to conduct the day-to-day operation of the corporation. Scott’s duties are to be more
clearly defined and delegated by the board. Further, the agreement will contain provisions
―typically found in large, complex corporations, including provisions governing liquidity for all
shareholders.‖ The agreement will also include buy-sell provisions, ―subject to a 1 yr. lockup
period.‖ Sufficient detail regarding corporate management and financial governance is built into
paragraph one to convince this Court that the shareholder agreement was essential to the overall
settlement agreement.
Further, the proposed shareholder agreements drafted during the course of the parties’
negotiations are detailed and comprehensive. The most recent (failed) draft of the shareholder
agreement was thirty pages in length with a detailed table of contents. The draft shareholder
agreement addressed restrictions on disposition of shares, voluntary lifetime transfers, involuntary
lifetime transfers, purchase of shares on the death of a shareholder or spouse of a shareholder,
general provisions relating to transfers, voting agreements, covenants of the corporation, and a
number of miscellaneous provisions. Each of these areas covered additional sub-topics in
22
meticulous detail; each of these provisions can be excruciatingly complex and subject to intense
negotiation.
While Scott maintains the shareholder agreement is not essential, a plain reading of the
entire agreement indicates otherwise. The shareholder agreement, as envisioned in the settlement
agreement and as reflected by the drafts produced in negotiations, would be the foundational
document of MRMC and would define the parties’ rights vis-à-vis each other and MRMC.
Moreover, the shareholder agreement was fundamental to the enforcement of nine of the
remaining eighteen paragraphs which, by their express language, are dependent on completion of
all of the obligations under the agreement.
Because the settlement agreement leaves this essential provision open for future agreement
that never occurred, it is not binding and merely constitutes an agreement to agree in the future.
See Fort Worth Indep. Sch. Dist., 22 S.W.3d at 846; Playoff Corp., 300 S.W.3d at 455; Meru v.
Huerta, 136 S.W.3d 383, 391 (Tex. App.––Corpus Christi 2004, no pet.). As such, it cannot be
enforced.
Because we find the settlement agreement to be unenforceable as a matter of law, we need
not address the issue of whether the trial court erred in (1) awarding money damages and specific
performance for a breach of contract and (2) awarding costs.
We reverse the judgment of the trial court and render a take-nothing judgment.
23
Bailey C. Moseley
Justice
Date Submitted: October 13, 2010
Date Decided: November 3, 2010
24