FOURTH DIVISION
January 11, 2007
No. 1-06-0086
TIMOTHY JOYCE, ) Appeal from
) the Circuit Court
Plaintiff-Appellant, ) of Cook County.
)
v. )
)
JAY J. MASTRI, JAY’S HVAC, INC., an )
Illinois Corporation, and MADISON SERVICES, INC., )
a Mississippi Corporation, ) Honorable
) Cheryl A. Starks,
Defendants-Appellees. ) Judge Presiding.
PRESIDING JUSTICE QUINN delivered the opinion of the court:
Plaintiff, Timothy Joyce, an employee of an independent contractor, suffered injuries
when he fell off a ladder at a construction site. Plaintiff filed a complaint at law with two counts
against defendant, Madison Services, Inc. (Madison Services), the general contractor of the site,
alleging common-law negligence. Plaintiff appeals from orders of the circuit court granting
summary judgment in defendant’s favor.1 Plaintiff contends that defendant had a duty to prevent
his injuries in light of its contract with plaintiff’s employer, its retention of control over certain
aspects of the construction site, its contract with the federal government and nondelegable duty to
comply with applicable safety regulations, and as the possessor of the land where his injury
occurred. For the following reasons, we affirm.
1
Defendants Jay J. Mastri and Jay’s HVAC, Inc. are not parties in this appeal.
1-06-0086
I. Background
Plaintiff’s injuries occurred on April 16, 2001, at a construction site at the United States
Army Reserve Base in Arlington Heights, Illinois. Madison Services acted as the general
contractor at the construction project to demolish and install air handling systems. Madison
Services hired plaintiff’s employer, Elk Grove Mechanical, Inc. (EGM), to perform certain
demolition and construction work at the site. EGM contracted to work on demolishing air
handling units and their appurtenances in mechanical rooms 110 and 115 at the site.
Pursuant to section 8.1 of the contract between Madison Services and EGM, EGM was
required to execute the work contracted for and provide “all labor, materials, equipment, services
and other items required to complete such portion of the Work.” Section 3.2.2 of the contract
provided that Madison Services “shall not give instructions or orders directly to employees or
workmen of [EGM], except to persons designated as authorized representatives of [EGM].”
Under section 2.1, Madison Services and EGM agreed to be “mutually bound by the terms of
[the] Agreement and, to the extent that provisions of the Prime Contract apply to the Work of the
Subcontractor, the Contractor apply to the Work of the Subcontractor all obligations and
responsibilities that the Owner, under the Prime Contractor assumes toward the Owner and the
Architect.” Also, under section 4.3.1, EGM agreed that it “shall take reasonable safety
precautions with respect to performance of this Subcontract, shall comply with safety measures,
initiated by [Madison Services] and with applicable laws, ordinances, rules, regulations and
orders of public authorities for the requirements of the Prime Contract [between Madison
Services and the United States Government]. [EGM] shall report within three days an injury to
-2-
1-06-0086
an employee or agent of [EGM] which occurred at the site.”
Additionally, section 4.4.1 of the contract provided that “[EGM] shall keep the premises
and surrounding area free from accumulation of waste materials or rubbish caused by operations
performed under this Subcontract. [EGM] shall not be held responsible for unclean conditions
caused by other contractors and subcontractors.” Section 4.6.1 provided:
“To the fullest extent permitted by law, [EGM] shall indemnify and hold
harmless the Owner, Contractor, Architect, Architect’s consultants, and agents
and employees of any of them from and against claims, damages, losses and
expenses, including but not limited to attorney’s fees, arising out of or under this
Subcontract, provided that such claim, damage, loss or expense is attributable to
bodily injury, sickness, disease or death, or to injury to or destruction of tangible
property (other than the Work itself) including loss of use resulting therefrom, but
only to the extent caused in whole or in part by negligent acts or omissions of
[EGM], [EGM’s] Sub-subcontractor, anyone directly or indirectly employed by
them or anyone for whose acts they may be liable, regardless whether or not such
claim, damage, loss or expense is caused in part by a party indemnified
hereunder.”
Plaintiff testified at his deposition that on April 16, 2001, he arrived at the work site on
the Army Reserve Base at approximately 8 a.m. Plaintiff testified that after first arriving at the
work site, he set up extension cords to plug in saws and swept the larger mechanical room. At
approximately 9:20 a.m., plaintiff testified that he began setting up in the smaller mechanical
-3-
1-06-0086
room where he was injured. Plaintiff testified that his employer, EGM, was contracted to tear out
several 15-ton air handlers at the time. Plaintiff was attempting to remove duct work at the time
of his fall.
Plaintiff testified that in order to set up for the removal of duct work, he used a ladder that
was brought to the work site by defendant Jay Mastri, from Jay’s HVAC. Plaintiff testified that
he set up the ladder near the west wall of the mechanical room and extended it to approximately
15 feet. Plaintiff testified that the feet of the ladder were four feet from the wall. Plaintiff
testified that when he climbed about 10 to 12 feet up the ladder to begin working, the ladder
started to retract back to its normal position. Plaintiff testified that he heard part of the locking
mechanism flapping against the rungs of the ladder as it retracted. Plaintiff testified that the
noise sounded like “tick, tick, tick, tick” that one would hear when the locking mechanism on a
ladder is unlatched and the ladder is retracting. Plaintiff testified that he held on to the ladder
and rode the ladder down. Plaintiff testified that when he neared the bottom of the ladder, his
wrist became caught in the rungs and his wrist was shattered. Plaintiff testified that he then fell
to the ground. Plaintiff testified that in his opinion the ladder retracted because there was a
problem with the locking mechanism.
Plaintiff testified that no one told him to use the particular ladder in question. Plaintiff
testified that the ladder was available, so he picked it up and began using it. Plaintiff testified
that Rich Olson was his supervisor at EGM, and that he only saw Olson once to go over things.
Plaintiff testified that Jay Mastri, of Jay’s HVAC, was his day-to-day supervisor, who then
reported to Rich Olson. Plaintiff testified that he had no contact with any employee or anyone
-4-
1-06-0086
related to Madison Services. Plaintiff testified that Madison Services did not provide any of the
equipment for the work project.
Michael Reinersman testified at his deposition that he was employed by Madison
Services, as a project or site manager, at the time of plaintiff’s injury. In April 2001, Reinersman
was responsible for overseeing Madison Services’ projects in the Midwestern region, which
included six states and between 20 to 25 jobs. Reinersman was the only Madison Services
employee performing that job in the Midwestern region, at the time of plaintiff’s injury.
Reinersman testified that his responsibilities were to bid a job out to subcontractors, make
recommendations to Madison Services, and define the scope of the job to the government and the
subcontractor. Reinersman testified that he was responsible for learning what the government
wanted done at its facility and then passing that scope on to the subcontractor. Reinersman
testified that on the work site in question and in all the projects it did, Madison Services had no
self-performed work because it had no tradesmen. Reinersman explained that since Madison
Services’ contracts were written as prime contracts for the government, it viewed them as more
of a contract management point, wherein Madison Services handled the paperwork between the
government and the subcontractors.
Reinersman testified that he visited the work site, during the course of EGM’s work,
approximately five times. Reinersman testified that he was present on at least one occasion when
EGM was performing its work. Reinersman testified that none of the work he observed was
being performed in an unsafe manner, or in violation of OSHA standards. Reinersman testified
that Madison Services had the right to stop a subcontractor’s work at the Army Reserve Base if
-5-
1-06-0086
there was some type of safety hazard, but Reinersman did not have any occasion where he had to
exercise that right. Reinersman testified that he was not present on the day of plaintiff’s injury
and did not conduct a postaccident investigation. Reinersman testified that he was not aware of
plaintiff’s injury until December 2002. Reinersman testified that during a preconstruction
meeting, the issue of dust protection was raised to protect the rest of the facility during EGM’s
demolition work. Reinersman testified that EGM put in place dust protection procedures.
Reinersman testified that Madison Services’ prime contract with the government did not
call for daily site supervision and Madison Services had no role in enforcing safety rules on the
work site. Madison Services did not have a safety person assigned to the work site at the Army
Reserve Base. Reinersman testified that subcontractors, such as EGM, were to comply with
OSHA, based on their contract with Madison Services. Subcontractors were made aware that
they were responsible for safety when they contracted with Madison Services.
Reinersman also testified that he never instructed EGM employees as to what tools to use
or how to go about doing their work. Reinersman testified that Madison Services did not provide
any equipment to be used on the work site, did not direct EGM employees as to the operative
details as to how to perform their work, and did not give any job assignments to EGM
employees.
Richard Olson testified that he was employed as superintendent for EGM at the time of
plaintiff’s injury. Olson testified that he was responsible from the start to the finish of a job, that
he ran everything, and that nothing happened unless it went through him. Olson testified that he
was responsible for 60% to 70% of EGM’s bidding, reviewed and signed contracts, hired and
-6-
1-06-0086
fired employees, did job walk-throughs, and took care of the punch list. Olson testified that he
was responsible for holding safety meetings at EGM’s shop, overseeing the repair of broken
ladders and tools, and providing workers with safety glasses and hard hats. Olson testified that at
safety meetings, ladders would be checked to make sure they had a sound structural base. Olson
testified that EGM inspects its ladders, the locking mechanisms on the ladders, and the ropes on
the ladders.
Olson testified that his contact with Madison Services was Michael Reinersman, who was
the project manager for Madison Services. Olson testified that EGM’s scope of work with
Madison Services involved EGM removing air-handling units at the Army Reserve Base. Olson
testified that Reinersman was the only individual from Madison Services to visit the work site,
and that Reinersman visited the work site about every three days or every other day. Olson
testified that when Reinersman was at the work site, no safety issues came up and no safety
meetings were conducted with Reinersman present. Olson testified that Reinersman did not
express the manner in which he wanted EGM employees to perform work. Olson testified that
Madison Services did not provide any of the equipment, but provided the scope of work for the
project. Olson testified that EGM had a lead man on the work site who supervised the work,
made sure that EGM employees worked eight hours and monitored job progress. Olson testified
that if Adam Blau and Jerry Johansen were at the work site, Jerry Johansen had more experience
and would have been EGM’s lead man. Olson testified that Madison Services did not supervise
EGM’s work and that EGM workers would go to him if they had any type of problems. Olson
testified that EGM workers would have no reason to go to Reinersman.
-7-
1-06-0086
Olson also testified that Jay Mastri, of Jay’s HVAC, was at the work site and was a
subcontractor of EGM. Olson testified that Mastri performed the same work as EGM and also
reported to him. Olson testified that plaintiff’s coworkers stated that plaintiff had the ladder at a
bad angle and that the ladder was backwards. Olson testified that he had no other information as
to what may have caused plaintiff to fall. Olson indicated that the floor was dry and that he did
not see any skid marks on the floor after plaintiff’s injury.
Jay Mastri testified that his company, Jay’s HVAC, had subcontracted with EGM on
various jobs for about one year prior to working at the Army Reserve Base. Mastri testified that
he did not have a written contract with EGM to work on the demolition project at the Army
Reserve Base, but just filled in when needed. Mastri testified that he performed work, then billed
EGM for his time worked at the Army Reserve Base.
Mastri testified that he met with Reinersman from Madison Services and Olson to discuss
the scope of work prior to the project. Mastri testified that he did not see anyone else from
Madison Services visit the work site. Mastri testified that he began working on the work site
three weeks prior to plaintiff’s injury. Mastri testified that the room had cinderblock walls and a
poured concrete floor that was painted. Mastri testified that he did not know how long plaintiff
was on the ladder prior to his fall and that he did not see plaintiff fall. Mastri testified that the
room was almost done with demolition and almost empty at the time of plaintiff’s injury. He
indicated that there was nothing on the ground that would have caused a problem for the ladder
itself gripping the ground, and that there were no foreign substances or broken concrete on the
floor. Mastri testified that there was “maybe just dust” on the floor but that plaintiff could have
-8-
1-06-0086
swept the floor.
Mastri testified that Jerry Johansen was the lead man for EGM, but all of the workers
knew what to do on the work site. Mastri testified that no one from Madison Services came to
the work site to supervise EGM and Jay’s HVAC workers. Mastri also testified that he spoke
with plaintiff after plaintiff’s injury, and plaintiff complained that the ladder was missing a rope
and caused his fall.
Adam Blau testified that he worked as an EGM employee on and off the Army Reserve
Base project prior to the time of plaintiff’s accident. Blau testified that Olson was the foreman
for EGM and ran the job. Blau testified that he received his instructions from Olson and
everyone else also took their instructions from Olson. Blau testified that if Olson was not at the
work site, Jerry Johansen was in charge. Blau testified that he had no discussions with
Reinersman from Madison Services about how work should be done. Reinersman only told Blau
to “be careful.” Blau testified that he never had any specific conversations with Reinersman
about safety or equipment at the work site. Blau also testified that when Reinersman was at the
work site, he did not tell Blau how to do his demolition work and Madison Services did not
provide any of the equipment that Blau used on the work site.
Blau testified that he did not see plaintiff fall from the ladder. Blau indicated that the
floor in the mechanical room was a regular concrete floor and that it was smooth. Blau testified
that there was dust on the floor at the work site. Blau testified that he had no information as to
what caused plaintiff to fall from the ladder.
Scott Curatti testified that he was the owner of EGM at the time of plaintiff’s injury.
-9-
1-06-0086
Curatti testified that plaintiff was an EGM employee on the date of his injury. Curatti testified
that Olson ran the job for EGM and that Olson sold the job, set it up, ran the workers, and told
them what to do. Curatti testified that Olson hired Jay’s HVAC to help on the work site. Curatti
testified that Olson had the skill to conduct the work on the Army Reserve Base. Curatti would
expect Olson to work safely on the project and see that EGM employees also worked safely.
Curatti had no information that Madison Services directed any of EGM’s work.
John Lange testified that he is president of Madison Services and that Reinersman was
the project manager for Madison Services at the time of plaintiff’s injury. Lange testified that
Reinersman ran between 15 to 20 jobs in multiple states. As project manager, Reinersman would
coordinate with the government, oversee branch operations and have overall responsibility for
the coordination of work, inspection and invoicing all delivery orders. Lange testified that he
was never at the Army Reserve Base project.
Lange testified that Madison Services’ personnel did not perform work on the project in
question. Lange testified that the work would be contracted out to various subcontractors and
then supervised by the subcontractor’s managers. Lange testified that Reinersman’s primary
responsibility was to meet with the government personnel, who would issue delivery orders and
ensure that the scope of the delivery order was understood by Madison Services and Madison
Services’ subcontractors. Reinersman would then issue a subcontract and report back to the
government and Madison regarding the status of the job. Reinersman would ascertain the status
of the job by phone and occasional visits to the site and visits with government officials. Lange
testified that Reinersman had no supervisory relationship with any of the people performing
-10-
1-06-0086
demolition work at the Army Reserve Base and Reinersman was the only Madison Services’
employee at the work site.
On March 24, 2005, plaintiff filed his third-amended complaint at law, including two
counts against Madison Services. Count II of the complaint, entitled “Duty under Prime
Contract/OSHA,” alleged that Madison Services owed plaintiff a duty of care based on its
retention of control at the work site under section 414 of the Restatement (Second) of Torts
(Restatement (Second) of Torts §414 (1965)); and count III, entitled “Premises Liability,” alleged
that Madison Services owed plaintiff a duty of care as possessor of the land under section 343 of
the Restatement (Second) of Torts. On December 29, 2004, the circuit court granted partial
summary judgment in Madison Services’ favor and dismissed count II, finding that Madison
Services did not owe plaintiff a duty of care under section 414 of the Restatement (Second) of
Torts. On December 30, 2005, the circuit court denied plaintiff’s motion to reconsider and
granted summary judgment in favor of Madison Services and dismissed count III, finding that
plaintiff could not sustain its premises liability claim under section 343 of the Restatement
(Second) of Torts. Plaintiff appeals the summary dismissal of counts II and III.
II. Analysis
In a negligence action, a plaintiff must present sufficient evidence to establish that the
defendant owed a duty to the plaintiff. Downs v. Steel & Craft Builders, Inc., 358 Ill. App. 3d
201, 204 (2005). The existence of a duty is a question of law to be decided by the court; if no
duty exists there is no recovery. Downs, 358 Ill. App. 3d at 204. Summary judgment is
-11-
1-06-0086
appropriate where the pleadings, depositions, admissions and affidavits on file, viewed in the
light most favorable to the nonmovant, show that no genuine issue of material fact exists and that
the moving party is entitled to judgment as a matter of law. Cochran v. George Sollitt
Construction Co., 358 Ill. App. 3d 865, 872 (2005). This court reviews the grant of summary
judgment de novo. Cochran, 358 Ill. App. 3d at 872.
Plaintiff presents three bases for the existence of a duty of care: (1) Madison Services’
contractual right to control and actual retention of control under section 414 of the Restatement
(Second) of Torts; (2) Madison Services’ responsibility under its prime contract with the
government and applicable safety regulations; and (3) Madison Services’ status as possessor of
the land under section 343 of the Restatement (Second) of Torts. We will address each of these
bases in turn.
A. Section 414 of the Restatement (Second) of Torts
Plaintiff first contends that Madison Services owed him a duty of care pursuant to section
414 of the Restatement (Second) of Torts, because Madison Services retained contractual and
actual control over EGM’s employees at the work site.
Generally, one who employs an independent contractor is not liable for the latter’s acts or
omissions. Downs, 358 Ill. App. 3d at 204-05. In Illinois, a recognized exception to this rule is
found in section 414 of the Restatement (Second) of Torts, which provides:
"One who entrusts work to an independent contractor, but who retains the control
of any part of the work, is subject to liability for physical harm to others for whose
-12-
1-06-0086
safety the employer owes a duty to exercise reasonable care, which is caused by
his failure to exercise his control with reasonable care." Restatement (Second) of
Torts §414 (1965).
Comment c to section 414 explains the "retained control exception":
"In order for the rule stated in this Section to apply, the employer must
have retained at least some degree of control over the manner in which the work
is done. It is not enough that he has merely a general right to order the work
stopped or resumed, to inspect its progress or to receive reports, to make
suggestions or recommendations which need not necessarily be followed, or to
prescribe alterations and deviations. Such a general right is usually reserved to
employers, but it does not mean that the contractor is controlled as to his methods
of work, or as to operative detail. There must be such a retention of a right of
supervision that the contractor is not entirely free to do the work in his own way."
Restatement (Second) of Torts §414, Comment c, at 388 (1965).
Whether a contractor retained such control over a subcontractor’s work so as to give rise
to liability is an issue reserved for a trier of fact, unless the evidence presented is insufficient to
create a factual questions. Bokodi v. Foster Wheeler Robbins, Inc., 312 Ill. App. 3d 1051, 1059
(2000). The best indicator of whether a contractor has retained control over the subcontractor’s
work is the parties’ contract, if one exists. The interpretation of a contract is a question of law
and therefore may be decided on a motion for summary judgment. Downs, 358 Ill. App. 3d at
205. When interpreting a contract, we must consider the entire document to give effect to the
-13-
1-06-0086
parties’ intent, as determined by the plain and ordinary meaning of the language of the contract.
Downs, 358 Ill. App. 3d at 205. We find that the contract between Madison Services and EGM
did not evidence an intent by Madison Services to retain control over safety at the construction
site, which would give rise to a duty of care owed by Madison Services to plaintiff.
Generally, in a construction negligence case involving a contract between a defendant
general contractor and an independent contractor that employed the plaintiff, summary judgment
is improperly granted to a general contractor that had agreed to retain control over safety at a
construction site (Downs, 358 Ill. App. 3d at 205-06, citing Moorehead v. Mustang Construction
Co., 354 Ill. App. 3d 456, 461 (2004) (where general contractor had agreed to be “ ‘fully and
solely responsible for the jobsite safety’ ”), or where a general contractor goes to great lengths to
control safety at the construction site (Bokodi, 312 Ill. App. 3d at 1063-64). However, summary
judgment in favor of the general contractor is appropriate where an independent contractor is
contractually responsible for jobsite safety and the defendant general contractor takes no active
role in ensuring safety (Fris v. Personal Products Co., 255 Ill. App. 3d 916, 924-25 (1994))
(defendant retained authority to stop unsafe work but did not actively inspect for safety or
employ a safety plan), or where the general contractor reserves the general right of supervision
over the independent contractor but does not retain control over the incidental aspects of the
independent contractor’s work (Rangel v. Brookhaven Constructors, Inc., 307 Ill. App. 3d 835,
839 (1999)).
In this case, Madison Services neither controlled the safety measures employed at the
construction nor retained control over the incidental aspects of the work done by EGM. Pursuant
-14-
1-06-0086
to section 8.1 of the contract, EGM was required to provide all labor, materials, and equipment
needed to complete the work. Section 3.2.2 provided that Madison Services would not give
orders or instructions directly to EGM’s employees. Under section 2.1, Madison Services and
EGM agreed to be “mutually bound by the terms of [the] Agreement.” Also, under section 4.3.1,
EGM agreed to take reasonable safety precautions with respect to the performance of the
contract. In addition, section 4.4.1 required EGM to keep the premises and surrounding area
clean and specifically stated that EGM shall not be held responsible for unclean conditions
caused by other contractors or subcontractors. These provisions indicate that Madison Services
intended that EGM would be responsible for directing the work and safety of its own employees
and responsible for only those unclean conditions it created on the premises.
During construction, Madison Services’ representative, Reinersman, visited the site to
look only at the construction’s progress, and he never observed any safety violations or directed
EGM’s employees regarding the manner of their work. Madison Services relied on EGM for
safety. Madison services did not provide safety classes, inspectors, or equipment at the work
site. Rather, EGM conducted safety meetings with employees, provided the equipment,
inspected the equipment and ensured its employees had hard hats and safety glasses.
Furthermore, the rights retained by Madison Services to stop work and inspect progress are
general rights of supervision and not a retention of control over the incidental aspects of EGM’s
work.
While we find that the contract did not grant Madison Services sufficient control over
EGM’s work to create a duty to plaintiff, our analysis of section 414 does not end here. It is
-15-
1-06-0086
possible that a duty to a subcontractor’s employee may be created by the contractor’s actions
where the contractor retains control over the incidental aspects of the independent contractor’s
work. See Bieruta v. Klein Creek Corp., 331 Ill. App. 3d 269, 271-72 (2002).
In Bieruta, this court considered a case where the contractor and subcontractor had not
agreed on the scope of the contractor’s control over the subcontractor’s work. Applying section
414, this court held that the defendant general contractor was not liable for injuries sustained by
an independent contractor’s employee, because the defendant did not retain control over the
“incidental aspects” of the independent contractor’s work. This court found that there was no
evidence that the defendant contractor exerted control over the work site or directed its
“operative details,” or that the subcontractor was not entirely free to perform the work in its own
way. Bieruta, 331 Ill. App. 3d at 276.
Similarly, in this case, the facts indicate that Madison Services did not control EGM’s
work. There is no evidence that Madison Services directed the “operative details” of the work
site or that EGM was not free to perform the demolition work in its own way. The evidence
showed that Madison Services did not participate in or supervise any of the demolition work.
Reinersman, on behalf of Madison Services, visited the work site at the beginning of the project
merely to inform EGM of the scope of the work and any subsequent visits were to monitor the
progress of the work. Reinersman did not direct EGM employees as to the operative details as to
how to perform their work and did not give any job assignments to EGM’s employees. The
evidence showed that Olson, EGM’s superintendent, ran the job and that EGM’s workers were
supervised by its lead man, Jerry Johansen. Olson himself testified that Madison Services did
-16-
1-06-0086
not supervise EGM’s work and that EGM workers would go to him if they had any type of
problems. Accordingly, we find that Madison Services contractually and actually removed
itself from the incidental aspects of the construction and safety work done by EGM, and that
summary judgment for Madison Services was appropriate on plaintiff’s section 414 claim.
B. The Prime Contract and Federal Safety Regulations
Plaintiff further contends that because the Prime Contract between Madison Services and
the United States Government imposed nondelegable safety standards under OSHA and its
regulations, Madison Services owed a duty of care to plaintiff. We disagree.
The Occupational Safety and Health Act of 1970 (OSHA) creates a government program
to enforce compliance with federal occupational safety and health standards by employers in the
private sector. 29 U.S.C. §§651, 654 (2000); Downs, 358 Ill. App. 3d at 208. Part 1926 of Title
29 of the Code of Federal Regulations sets forth the specific construction standards. 29 C.F.R.
§1926 (2004). OSHA explicitly declares that it shall not be construed to supersede, to enlarge, to
diminish, or to affect in any manner “the common law or statutory rights, duties, or liabilities of
employers and employees under any law with respect to injuries *** of employees arising out of
or in the course of, employment.” 29 U.S.C. §653(b)(4) (2000).
In Downs, this court held that OSHA and its accompanying regulations did not impose a
nondelegable duty on the general contractor to maintain safety at the construction site by virtue
of the fact that the contract between the general contractor and independent contractor that
employed the plaintiff required the independent contractor to comply with OSHA. Downs, 358
-17-
1-06-0086
Ill. App. 3d 201. In that case, this court determined that the defendant general contractor could
not be held liable under plaintiff’s section 414 claim, as governed by Illinois law. Therefore,
liability would have resulted only from affecting the defendant’s right to contract away private
liability for injuries, or from enlarging defendant’s liabilities to plaintiff under section 414 by
declaring that, via OSHA, defendant retained control of the independent contractor’s work. This
court explained that “[d]oing so would create an exception that would swallow the rule, because
no matter what steps defendant would take to shield itself from liability, the OSHA inevitably
would pierce defendant’s armor, striking a fatal blow that otherwise would be blocked under the
theories advanced by plaintiff.” Downs, 358 Ill. App. 3d at 209. We find no reason to depart
from our previous determination that a nondelegable duty does not arise under OSHA, because
OSHA creates only a governmental program to enforce compliance and does not deal with the
assignment of liability among contractors.
Plaintiff, nonetheless, argues that certain provisions in the prime contract between
Madison Services and the federal government prohibited Madison Services from delegating its
responsibilities for safety and control of the work site. Plaintiff points to the following portions
of the prime contract in support of his position:
“SUPERINTENDENCE BY THE CONTRACTOR
At all times during the performance of this contract and until the work is
completed and accepted, the Contractor shall directly superintend the work or
assign and have on the work site a competent superintendent who is satisfactory
-18-
1-06-0086
to the Contracting Officer and has authority to act for the Contractor.
***
ACCIDENT PREVENTION
(a) The Contractor shall provide and maintain work environments and
procedures which will (1) safeguard the public and Government personnel,
property, materials, supplies, and equipment exposed to Contractor operations and
activities; (2) avoid interruptions of Government operations and delays in project
completion dates; and (3) control costs in the performance of this contract.
(b) For these purposes on contracts for construction or dismantling,
demolition, or removal of improvements, the Contractor shall–
(1) Provide appropriate safety barricades, signs, and signal lights;
(2) Comply with the standards issued by the Secretary of Labor at 29
C.F.R. Part 1926 and 29 C.F.R. Part 1910; and
(3) Ensure that any additional measures the Contracting Officer determines
to be reasonably necessary for the purposes are taken.
(c) If this contract is for construction or dismantling, demolition or
removal of improvements with any Department of Defense agency or component,
the Contractor shall comply with all pertinent provisions of the latest version of
U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-
1-1, in effect on the date of the solicitation.
(d) Whenever the Contracting Officer becomes aware of any
-19-
1-06-0086
noncompliance with these requirements or any condition which poses a serious or
imminent danger to the health or safety of the public or Government personnel,
the Contracting Officer shall notify the Contractor orally, with written
confirmation, and request immediate initiation of corrective action. This notice,
when delivered to the Contractor or the Contractor’s representative at the work
site, shall be deemed sufficient notice of the noncompliance and that corrective
action is required. After receiving the notice, the Contractor shall immediately
take corrective action. If the Contractor fails or refuses to promptly take
corrective action, the Contracting Officer may issue an order stopping all or part
of the work until satisfactory corrective action has been taken. The Contractor
shall not be entitled to any equitable adjustment of the contract price or extension
of the performance schedule on any stop work order issued under this clause.
(e) The Contractor shall insert this clause, including this paragraph (e),
with appropriate changes in the designation of the parties, in subcontracts.
***
Compliance with regulations: All work, including the handling of hazardous
materials or the disturbance of dismantling of structures containing hazardous
materials shall comply with the applicable requirements of 29 C.F.R. 1926/1910.
*** Where there is a conflict between applicable regulations the most stringent
shall apply.
Contractor Responsibility: The contractor shall assume full responsibility and
-20-
1-06-0086
liability for compliance with all applicable regulations pertaining to the health and
safety of personnel during the execution of work, and shall hold the Government
harmless for any action on his part or that of [his] employees or subcontractors,
which results in illness, injury or death." (Emphasis added.)
Contrary to plaintiff’s assertion, nothing in these provisions prohibited Madison Services from
delegating its duty to maintain safety at the work site to its subcontractor, EGM. Plaintiff cites
no authority for its argument that Madison Services was prohibited from delegating its safety
responsibilities because the project was federally funded and on federal property. As previously
discussed, Madison Services, through its contract with EGM, contractually and actually removed
itself from the incidental aspects of the construction and safety work performed by EGM.
Accordingly, we conclude that summary judgment was appropriate on plaintiff’s section 414
claim.
C. Section 343 of the Restatement (Second) of Torts
Finally, plaintiff contends that Madison Services owed him a duty of care under the
premises liability theory of section 343 of the Restatement (Second) of Torts.
Illinois has adopted the rules set forth in sections 343 and 343A of the Restatement
(Second) of Torts regarding the duty of possessors of land to their invitees. Section 343
provides:
"A possessor of land is subject to liability for physical harm caused to his invitees
by a condition on the land if, but only if, he
-21-
1-06-0086
(a) knows or by the exercise of reasonable care would discover the
condition, and should realize that it involves an unreasonable risk of harm to such
invitees, and
(b) should expect that they will not discover or realize the danger, or will
fail to protect themselves against it, and
(c) fails to exercise reasonable care to protect them against the danger."
Restatement (Second) of Torts §343 (1965).
This duty does not extend to risks created by "open and obvious" conditions. Bucheleres v.
Chicago Park District, 171 Ill. 2d 435, 447-48 (1996).
Plaintiff argues that Madison Services failed to exercise reasonable care and make
adequate inspections to discover accumulated dust on the floor of the work site and the unsafe
ladder condition. Plaintiff argues that even if the dust on the floor and ladder condition were
"open and obvious" conditions, the deliberate encounter exception applies to impose liability on
Madison Services. Comment f to section 343A describes the deliberate encounter exception:
"There are *** cases in which the possessor of land can and should
anticipate that the dangerous condition will cause physical harm to the invitee
notwithstanding its known or obvious danger. In such cases the possessor is not
relieved of the duty of reasonable care which he owes to the invitee ***. ***
***[A] reason [to expect harm] may also arise where the possessor has
reason to expect that the invitee will proceed to encounter the known or
obvious danger because to a reasonable man in his position the advantages
-22-
1-06-0086
of doing so would outweigh the apparent risk." Restatement (Second) of
Torts §343A, Comment f, at 220 (1965).
In this case, we find that plaintiff's premises liability argument under sections 343 and
343A fails because no evidence was presented that Madison Services knew or should have
known of a dangerous condition where plaintiff was working. See Restatement (Second) of
Torts § 343 (1965); Cochran, 358 Ill. App. 3d at 873. Plaintiff himself testified that at the time
of his injury, he was using a ladder that he set up and that no one told him to use the particular
ladder in question. Plaintiff testified that in his opinion the ladder retracted due to a problem
with the locking mechanism. Plaintiff also testified that he had no contact with any employee or
anyone related to Madison Services and that Madison Services did not provide any of the
equipment for the work project. Mastri, owner of Jay’s HVAC, another subcontractor, testified
that there was “maybe just dust” on the floor but that plaintiff could have swept the floor before
he began working. The evidence also showed that Reinersman, Madison Services’ project
manager, visited the work site on several occasions and that no safety issues arose during those
visits. The evidence showed that Reinersman was not present on the day of plaintiff’s injury and
did not conduct a post-accident investigation. Reinersman also testified that during a
preconstruction meeting, the issue of dust protection was raised to protect the rest of the facility
during EGM’s demolition work and that EGM put in place dust protection procedures. The
evidence further showed that Madison Services had no role in enforcing safety rules on the work
site and that subcontractors were responsible for cleaning up after themselves. Therefore there is
no evidence to show that Reinersman, or anyone else from Madison Services, was aware or
-23-
1-06-0086
should have been aware of any allegedly dangerous condition at the time of plaintiff's injury.
Accordingly, no genuine issue of material fact as to Madison Services' lack of knowledge exists
in this case.
III. Conclusion
For the above stated reasons, we affirm the circuit court’s determination where Madison
Services owed no duty of care under the theories advanced by plaintiff.
Affirmed.
NEVILLE and MURPHY, JJ., concur.
-24-