UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
EQUITAS DISABILITY ADVOCATES,
LLC,
Plaintiff,
v. Civil Action No. 15-611 (RDM)
DALEY, DEBOFSKY & BRYANT, P.C.;
JONATHAN FEIGENBAUM,
Defendants.
MEMORANDUM OPINION
Plaintiff Equitas Disability Advocates, LLC was formerly engaged in the practice of law.
Dkt. 2-4 at 23 (Abeles Aff. ¶ 2). Its affairs are being wound up by its only remaining principal,
Brian Abeles. Id. Defendant Jonathan M. Feigenbaum is a Boston lawyer, Dkt. 16-2 at 1
(Feigenbaum Aff. ¶ 3), and Defendant Daley, Debofsky & Bryant, P.C. (“DDB”) was an Illinois
law firm until it was dissolved by the Illinois Secretary of State in 2013, Dkt. 2 at 4. This case
arises out of an arbitration regarding legal fees that Feigenbaum and DDB (“Defendants”)
purportedly owed Equitas based on two fee-sharing agreements.
Presently before the Court are Equitas’s motion to vacate the arbitration award, which
was pending when Defendants removed this action from the D.C. Superior Court, Dkt. 2-4 at 4;
Equitas’s motion to remand the case to the Superior Court, Dkt. 14; and Defendants’ motion to
confirm the arbitration award, Dkt. 17. Equitas contends that this case must be remanded
because the parties’ agreements specify that D.C. law governs and that the arbitration will be
held in D.C., and under D.C.’s Revised Uniform Arbitration Act (“DCRAA”), the Superior
Court has “exclusive jurisdiction” to enter judgment on an arbitration award when the
“agreement to arbitrate provid[es] for arbitration in the District of Columbia.” D.C. Code §§ 16-
4426(b), 16-4401(5); see Dkt. 14-1. Equitas also contends that it is entitled to vacatur of the
arbitration award under the DCRAA because the arbitrator improperly denied a postponement of
the arbitration proceedings. Dkt. 2-4 at 19. Defendants respond that the “choice of [D.C.] law
[in the agreements] was only intended to govern any . . . disputes arising from the underlying
agreements between the parties” and does not affect “the governing law for confirmation of or
challenge to any arbitration award.” Dkt. 15 at 5. In Defendants’ view, the Federal Arbitration
Act (“FAA”), 9 U.S.C. § 1 et seq., governs such proceedings and, under the FAA, Equitas’s
motion to vacate is untimely. Dkt. 16-1 at 3–4. Defendants further contend that irrespective of
whether the FAA or the DCRAA applies, the arbitrator’s denial of a postponement withstands
scrutiny and, accordingly, the motion to confirm must be granted. Id. at 5–17.
For the reasons that follow, Equitas’s motions to remand the case, Dkt. 14, and to vacate
the arbitration award, Dkt. 2-4 at 4, are DENIED, and Defendants’ motion to confirm the
arbitration award, Dkt. 17, is GRANTED.
I. BACKGROUND
A. The Agreements
Brian Abeles previously worked in the disability-insurance industry as an insurance
broker, benefits consultant, and claims consultant, which enabled him to amass over 100,000
pages of industry documents providing insight into theories of recovery for disability-insurance
claimants. Dkt. 2-4 at 31–32. Although Abeles is not a lawyer, id. at 23 (Abeles Aff. ¶ 3), he
believed that access to these documents, known as “the Archive,” could be useful to disability-
insurance lawyers and their clients, id. at 31–32. He thus sought to partner with lawyers who
could use the Archive to pursue recoveries for their clients. Id. at 32. Abeles ultimately co-
2
founded the D.C. law firm Fulcrum Law Group, LLC, with attorney Joshua Rose. 1 Id. at 31.
Fulcrum is the predecessor-in-interest of Plaintiff Equitas. Id. at 34 n.4. Fulcrum entered into
two agreements with Defendants Feigenbaum and DDB in May and June of 2008, to which
Equitas later became a party. See Dkt. 9-2 at 25–63. Pursuant to the Strategic Alliance Co-
Counsel Agreement (“SACCA”) and the Fulcrum-Alliance Archive Sublicense Agreement
(“FAASA”), Defendants obtained access to the Archive and to consultant and/or co-counsel
services in exchange for a percentage of the fees recovered in specified cases. See id.; Dkt. 2-4
at 31, 33. The SACCA included choice-of-law and arbitration clauses:
(g) Governing Law; Dispute Resolution. This Agreement shall be
deemed to have been entered into under the laws of the District of Columbia, and
the rights and obligations of the parties hereunder shall be governed and
determined according to the laws of said state without giving any effect to conflict
of laws. All disputes arising under or in connection with this Agreement or
involving the interpretation, performance or breach of this Agreement will be
finally settled by final and binding arbitration administered by and in accordance
with the then existing [Judicial Arbitration, Mediation, and ADR Services
(“JAMS”)] Streamlined Arbitration Rules and Procedures[] (the “Rules of
Arbitration”) by a single arbitrator appointed in accordance with the Rules of
Arbitration. Any such arbitration shall be held in Washington, DC, unless the
parties hereto mutually agree in writing upon some other location for arbitration.
There shall be no consolidation of this arbitration with any other dispute or
proceeding involving third parties. The provisions of this Agreement shall prevail
in case of inconsistency between the Rules of Arbitration and this Agreement.
Judgment may be entered into in any court of competent jurisdiction to enforce
any final decision by the arbitrators.
Dkt. 9-2 at 39. The FAASA included similar provisions, which are, for purposes of this case,
materially indistinguishable from the SACCA provisions. 2 Id. at 57.
1
The D.C. Rules of Professional Conduct (“DC RPC”) permit non-lawyers to retain a financial
interest or managerial authority in a law firm in certain circumstances. See DC RPC Rule 5.4(b).
2
The FAASA provides as follows:
17.2 Governing Law; Dispute Resolution. This Agreement will be
deemed to have been entered into under the laws of the District of Columbia, and
the rights and obligations of the parties hereunder will be governed and
3
B. Arbitration Proceedings
On December 20, 2013, Equitas, represented by the law firm Zuckerman Spaeder,
demanded arbitration against Defendants pursuant to the SACCA and FAASA, alleging breach
of contract, breach of the implied covenant of good faith and fair dealing, unjust enrichment, and
fraud, and seeking return of all Archive documents. 3 Dkt. 2-4 at 38–39; id. at 24 (Abeles Aff.
¶ 9). Equitas alleged that DDB and Feigenbaum had failed to pay Equitas its share of the fees
earned in cases allegedly covered by the SACCA and FAASA. Id. at 33. An arbitrator was
assigned on February 6, 2014. Id. at 45.
After a hearing on May 20, 2014, the arbitrator dismissed Equitas’s claims for unjust
enrichment and fraud for failure to state a claim. Id. at 8; Dkt. 16-3 at 3. Subsequent to briefing
on the construction of the parties’ agreements, the arbitrator issued a decision on August 6, 2014,
determined according to the laws of the District of Columbia without giving any
effect to conflict of laws. All disputes arising under or in connection with this
Agreement or involving the interpretation, performance or breach of this
Agreement will be finally settled by final and binding arbitration administered by
and in accordance with the then existing JAMS Streamlined Arbitration Rules and
Procedures[] (the “Rules of Arbitration”) by a single arbitrator appointed in
accordance with the Rules of Arbitration. Any such arbitration shall be held in
Washington, DC, unless the parties hereto mutually agree in writing upon some
other location for arbitration. There shall be no consolidation of this arbitration
with any other dispute or proceeding involving third parties. The provisions of
this Agreement will prevail in case of inconsistency between the Rules of
Arbitration and this Agreement. Judgment may be entered into in any court of
competent jurisdiction to enforce any final decision by the arbitrators.
Dkt. 9-2 at 57.
3
Equitas also demanded arbitration against Frederick Daley, Mark DeBofsky, and David Bryant
in their personal capacities, but the arbitrator dismissed the claims against them because they
were not parties to the SACCA and FAASA. Dkt. 2-4 at 8; id. at 24 (Abeles Aff. ¶ 5). Equitas
filed a separate action against the three individuals, which was dismissed by another judge of this
Court on September 29, 2015. See Equitas Disability Advocates, LLC v. Bryant, No. 14-1644,
2015 WL 5728365 (D.D.C. Sept. 29, 2015), appeal dismissed, No. 15-7127, 2015 WL 9310483
(D.C. Cir. Dec. 4, 2015).
4
concluding that there remained material questions of fact with respect to Equitas’s claims for
breach of contract and breach of the covenant of good faith and fair dealing. Dkt. 2-4 at 8. The
arbitrator explained that Defendants were asserting a unilateral-mistake defense based on the
deletion of a key sentence limiting the scope of the cases covered from a prior draft of the
SACCA and that the question of who was responsible for the sentence’s deletion “cannot be
resolved on the papers.” Dkt. 16-3 at 3. He also cautioned that “[t]his matter has already greatly
exceeded the reasonable expectations of the parties when they agreed to proceed under the JAMS
Streamlined Arbitration Rules” and that “[t]he merits hearing of this case must be scheduled and
conducted without further delay.” Id. at 3–4.
On August 15, 2014, by agreement of the parties, a hearing was scheduled for the week
of December 8, 2014. Dkt. 2-4 at 46. At the same time, JAMS informed the parties that “[a]ll
fees must be paid by 10/9/14 to proceed with the . . . hearing;” that “[a]ny cancellation or
continuance must be approved by the arbitrator;” and that if the hearing was canceled or
continued after October 9, “the party canceling or continuing the hearing is responsible for all
fees associated with the reserved time” unless JAMS could otherwise fill it. Id. at 46. On
October 9, 2014, JAMS reminded the parties that payment was due and that it was the last day to
cancel the hearing without incurring cancelation fees. Id. at 47. Equitas paid its share of the fees
that day. Id. at 63. Defendants, however, did not pay their share of the fees at that time. Id. at
62.
According to Abeles, in mid-October 2014, he realized that Equitas’s relationship with
Zuckerman Spaeder “had to end.” Id. at 25 (Abeles Aff. ¶ 13). The relationship had deteriorated
after the lead attorney on the matter left the firm during the preceding summer. Id. Equitas
learned in mid-June 2014 that the lead attorney planned to depart, and she left Zuckerman
5
Spaeder on July 1, 2014. Id. at 61. On October 14, 2014, Abeles notified the JAMS case
administrator that Zuckerman Spaeder was withdrawing from the case and that he “was certain
that Equitas would need a postponement of the hearing.” Id. at 25 (Abeles Aff. ¶ 15). During
the last week of October, the case administrator allegedly told Abeles that the arbitration hearing
would likely be canceled anyway because Defendants had not paid their share of the fees. Id. at
25–26 (Abeles Aff. ¶ 16); see also id. at 62. Abeles replied that Equitas would not advance
Defendants’ share of the fees. Id. at 26 (Abeles Aff. ¶ 16). Under the JAMS Streamlined
Arbitration Rules, “JAMS may order the suspension or termination of the proceedings” if a party
fails to pay and no other party advances the payment owed. 4 Equitas did not, however, move for
a continuance at that time.
On October 30, 2014, JAMS notified the parties that if payment was not received by
November 7, 2014, the hearing would be canceled. Dkt. 2-4 at 48. Defendants then paid their
share of the fees on November 7, and JAMS informed Abeles of this “[a] few days later.” Id. at
26 (Abeles Aff. ¶ 19). On November 11, 2014, Abeles told the case administrator that he had not
retained new counsel and would need a postponement of the hearing. Id. (Abeles Aff. ¶ 20).
The administrator “asked that Equitas put that in writing” but allegedly agreed to inform the
arbitrator and Defendants. Id. at 63. Zuckerman Spaeder provided formal notice of its
withdrawal on November 14, 2014. Id. at 26–27 (Abeles Aff. ¶ 22); id. at 53.
On the evening of November 26, 2014, the day before Thanksgiving, Equitas finally
moved for a postponement of the hearing. Id. at 56. Abeles stated that the postponement was
needed because “Equitas has had to change counsel” which “became necessary when one of the
4
See Rule 6, available at http://www.jamsadr.com/rules-streamlined-arbitration/#Rule6; see
also Dkt. 2-4 at 26 (Abeles Aff. ¶ 16).
6
key members on [its] legal team left Zuckerman Spaeder.” Dkt. 16-3 at 33. He further explained
that “[a]though [they] immediately began exploring the options and conferring with other firms
. . . , that process is not complete and, in any event, [their] new counsel will need additional time
to become familiar with the case.” Id.
Defendants opposed any continuance. Id. at 35. In a November 28, 2014 letter to the
arbitrator, they explained that they had been preparing for the hearing, that they had rearranged
their schedules and bought non-refundable flights, that a witness had rearranged his schedule to
attend, and that Equitas had long been on notice of the need to seek new counsel. Id. at 35–37.
As Defendants explained, Equitas’s lead attorney had left Zuckerman Spaeder in July 2014. Id.
Defendants also represented that Abeles had consented to the withdrawal of the firm’s
representation of Equitas in closely related litigation in D.C. Superior Court on August 26, 2014,
and Equitas had successfully obtained new counsel in that litigation. Id.; see also supra p.4 n.3
(explaining related litigation); Dkt. 16-3 at 20–23 (notice of withdrawal); Equitas Disability
Advocates, LLC v. Bryant, No. 14-1644 (D.D.C. Oct. 7, 2014), Dkt. 3 (notice of appearance).
Although Defendants opposed any continuance, they asserted that if one was granted, Equitas
should be responsible for the costs incurred to reschedule, including the cost of their airline
tickets, hotel rooms, and the arbitrator’s fees. Dkt. 2-4 at 58. The arbitrator denied the request
for a postponement on December 1, 2014. Id. at 59. He explained that Defendants had booked
non-refundable travel, that they had prepared for trial, that they should be permitted to present
their affirmative defense “without further delay,” and that the “proceeding had been anything but
streamlined so far.” Id.
Equitas sought reconsideration of the denial on December 4, 2014, id. at 60, and
Defendants in turn reaffirmed their opposition to a postponement, Dkt. 16-3 at 39. In its motion
7
for reconsideration, Equitas did not dispute that Abeles had prior notice that Zuckerman Spaeder
would withdraw, but argued that “Equitas continued to incur legal expenses with Zuckerman
while [Defendants] withheld payment from JAMS.” Dkt. 2-4 at 62. It further argued that a
postponement was appropriate because Defendants “used their failure to pay JAMS fees to lull
Equitas into thinking that it had time to obtain new counsel.” Id. at 60. Equitas also explained
that Abeles had previously communicated to the JAMS case administrator that Equitas was
seeking new counsel and would need a postponement. Id. at 63. With respect to Defendants’
contention that Equitas should be responsible for the costs of any continuance, Equitas stated
only that “[w]hat [Defendants] have at stake in time and expenses is de minimis when compared
against the damage incurred by Equitas as a result of their wrongful and deceptive practices.” Id.
The arbitrator denied the request for reconsideration on Friday, December 5, 2014, id. at 65–67,
stating that “[i]t is far too late for a continuance” and that they would “begin on Monday
morning with whatever we have.” Id. at 65. He explained that if Equitas had no evidence to
present, the case would proceed with respect to Defendants’ affirmative defense and that “if [he]
agree[d] that [Equitas’s] failure to present evidence [was] excusable, [he] [would] consider
. . . adjourning the proceeding until [Equitas] can proceed.” Id.
The arbitration hearing proceeded as scheduled, and Abeles, without counsel, participated
in it on behalf of Equitas. Dkt. 2-4 at 28 (Abeles Aff. ¶ 28). The parties were given until
December 12, 2014 to present any additional materials, and Equitas did submit further affidavits.
Id. at 8; Dkt. 16-1 at 13. On December 15, 2014, the arbitrator ruled that Defendants had
prevailed on their affirmative defense and that Equitas was not owed any money. Dkt. 2-4 at 10–
12. He also ordered Equitas to reimburse Defendants for their portion of the arbitration fees—
$24,562.06. Id.
8
C. Judicial Proceedings
On February 12, 2015, Feigenbaum and DDB filed a motion to confirm the arbitration
award in Massachusetts Superior Court, which was served on Equitas on February 23, 2015.
Dkt. 16-3 at 46; Dkt. 18-1 at 1. On March 13, 2015, Equitas filed a motion to vacate the
arbitration award in D.C. Superior Court. Dkt. 2-4 at 8. Equitas’s motion was based on the
arbitrator’s allegedly improper denial of a postponement. Id. at 19–21. Two weeks later,
Equitas filed a “Motion to Enlarge Time” in the Massachusetts proceeding, explaining that “the
resolution of the Motion to Vacate by the Superior Court for the District of Columbia will
obviate any basis for [Feigenbaum and DDB] to proceed with their Complaint in this Court.”
Dkt. 9-2 at 76. Feigenbaum and DDB opposed the motion. See id. at 78–85. On May 15, 2015,
after oral argument, the Massachusetts Superior Court entered an order deferring to the D.C.
action, stating that “[w]hile nothing prohibits this court from confirming an arbitration award
from the District of Columbia, that venue is most appropriate to adjudicate confirmation/vacatur
as [the] award was issued there.” Dkt. 16-3 at 46; see also Dkt. 16-1 at 14.
Meanwhile, on April 23, 2015, Defendants removed the D.C. Superior Court action to
this Court based on the Court’s diversity jurisdiction. Dkt. 2 at 3–4. On April 29, 2015, they
filed a motion to stay this action pending the Massachusetts action, which the Court denied in
light of their failure to comply with the meet-and-confer requirements of Local Rule 7(m). Dkt.
9; May 6, 2015 Minute Order. On May 6, 2015, Defendants filed an amended motion to stay this
proceeding, but they withdrew that motion on May 22, 2015, after the Massachusetts court
issued its ruling deferring to this action. Dkts. 12–13; Dkt. 16-3 at 46.
On May 22, 2015, Equitas filed a motion to remand the case to D.C. Superior Court, Dkt.
14, which Defendants opposed, Dkt. 15. On June 8, 2015, Defendants filed a motion to confirm
9
the arbitration award, Dkt. 17, which Equitas opposed, Dkt. 21. The parties’ motions to remand
the action and to vacate or confirm the arbitration award are, accordingly, now ripe for
adjudication.
II. ANALYSIS
A. Subject-matter Jurisdiction
“Although the Federal Arbitration Act (FAA) constitutes federal law, ‘the Supreme Court
has interpreted the statute as not itself bestowing jurisdiction on the federal district courts.’”
Karsner v. Lothian, 532 F.3d 876, 882 (D.C. Cir. 2008) (quoting Kasap v. Folger Nolan Fleming
& Douglas, Inc., 166 F.3d 1243, 1245–46 (D.C. Cir. 1999)). Here, however, 28 U.S.C. § 1332,
which confers diversity jurisdiction on the federal courts, establishes this Court’s jurisdiction to
adjudicate this case. The parties are “citizens of different States” within the meaning of that
statute. 28 U.S.C. § 1332(a)(1); see also id. § 1332(c)(1). It is undisputed that Equitas is a D.C.
LLC whose sole remaining member, Abeles, is a citizen of Florida; that DDB was incorporated
in Illinois and had its principal place of business there; and that Feigenbaum is a citizen of
Massachusetts. Dkt. 2 at 3–4.
Moreover, “the matter in controversy exceeds the sum or value of $75,000, exclusive of
interest and costs.” 28 U.S.C. § 1332(a). The D.C. Circuit follows the “demand approach” to
determining the amount in controversy in an action to confirm or vacate an arbitration award,
Karsner, 532 F.3d at 884, under which “the amount in controversy is the amount sought in the
underlying arbitration rather than the amount awarded,” id. at 882. As a result, even though
Equitas lost the arbitration and was ordered to pay only $24,562.06 to Defendants, Dkt. 2-4 at
94, the amount-in-controversy requirement of § 1332(a) is met because Equitas originally sought
10
damages in excess of $75,000, see Dkt. 2 at 4; Dkt. 2-4 at 35–38 (seeking 20–50% of the legal
fees incurred in a case that settled for $1,000,000, as well as fees incurred in other litigations).
The Court, accordingly, concludes that it has subject-matter jurisdiction over the parties’
dispute.
B. Motion to Remand
Equitas contends that the case must, nonetheless, be remanded to the D.C. Superior Court
because the choice-of-law provisions of the SACCA and FAASA also serve, by operation of
D.C. law, as forum-selection clauses conferring exclusive jurisdiction on that court. See Dkt. 14-
1 at 3–7. To understand Equitas’s argument, a bit of background is required. The SACCA and
FAASA clauses on “Governing Law; Dispute Resolution” state that “the rights and obligations
of the parties hereunder shall be governed and determined according to the laws of” the District
of Columbia “without giving any effect to conflict of laws,” and that any “arbitration shall be
held in Washington, DC, unless the parties hereto mutually agree in writing upon some other
location.” Dkt. 9-2 at 39, 57. Less than six months before the parties entered into the SACCA
and FAASA, the District of Columbia adopted the DCRAA, which includes the following
provision: “An agreement to arbitrate providing for arbitration in the District of Columbia
confers exclusive jurisdiction on the court to enter judgment on an award under this chapter.”
D.C. Code § 16-4426(b); see Dkt 9-2 at 43, 48 (dating agreements to May and June 2008).
“Court” is defined elsewhere in the DCRAA as “the Superior Court of the District of Columbia.”
D.C. Code § 16-4401(5). The DCRAA further provides that “[b]efore a controversy arises that is
subject to an agreement to arbitrate, a party to the agreement may not waive or agree to vary the
effect of” the foregoing provision on “exclusive jurisdiction.” Id. § 16-4404(b)(1).
11
Equitas contends that because the parties selected D.C. law to govern their disputes and
selected D.C. as the location for the arbitration, the DCRAA applies to this case and vests
exclusive jurisdiction in the D.C. Superior Court. As Equitas explains its position, “by virtue of
having agreed to arbitrate in D.C., and to be governed by D.C. law, the parties also agreed that
the D.C. Superior Court would be the exclusive forum for review of any arbitration award.” Dkt.
14-1 at 7. Defendants offer two arguments in response: (1) that the FAA preempts the relevant
provisions of the DCRAA, Dkt. 15 at 2–3; and (2) that Equitas “is asking this Court to rewrite
the agreements and insert a forum[-]selection clause,” id. at 6.
1. Preemption
Defendants’ first contention falls wide of the mark. They assert that “Equitas’[s] motion
to vacate the [a]ward under the D.C. Arbitration Act is preempted under the FAA,” id. at 2, and
that “state arbitration laws must yield to the FAA when the dispute involves interstate
commerce,” id. at 3. The Court agrees that the contracts at issue fall within the scope of the
FAA, which applies to “contract[s] evidencing a transaction involving commerce” and provides
that an arbitration provision in such contracts is “valid, irrevocable, and enforceable, save upon
such grounds as exist at law or in equity for the revocation of any contract.” 9 U.S.C. § 2; see
also Allied-Bruce Terminix Cos., Inc. v. Dobson, 513 U.S. 265, 277 (1995) (interpreting the
phrase “involving commerce” in § 2 as “signal[ing] an intent to exercise Congress’ commerce
power to the full”). That, however, is only the first step in the analysis. The Supreme Court has
recognized three forms of preemption: “express” preemption, “field” preemption, and “conflict”
preemption. See Cipollone v. Liggett Grp., Inc., 505 U.S. 504, 516 (1992). Because the FAA
does not contain an express preemption clause and does not preempt the entire field of
arbitration, see Volt Info. Scis. Inc. v. Bd. of Trs. of the Leland Stanford Junior Univ., 489 U.S.
12
468, 477 (1989), Defendants’ argument comes down to a claim of conflict preemption. Conflict
preemption, in turn, applies in circumstances where it is impossible to comply with conflicting
federal and state rules, see, e.g., Fla. Line & Avocado Growers, Inc. v. Paul, 373 U.S. 132, 142–
43 (1963), or where state law “stands as an obstacle to the accomplishment and execution of the
full purpose and objectives of Congress,” Hines v. Davidowitz, 312 U.S. 52, 67 (1941). “The
question before” the Court, “therefore, is whether application of” D.C. Code § 16-4426(b) to
require that an action to confirm or vacate an arbitration award be brought in D.C. Superior
Court would directly conflict with the terms of the FAA or would “undermine the goals and
policies of” the Act. Volt, 489 U.S. at 477–78. As explained below, the Court concludes that it
would not.
As an initial matter, it is clear that the choice-of-forum rule contained in D.C. Code § 16-
4426(b) does not directly conflict with the FAA. The FAA provides that “the United States court
in and for the district wherein the award was made may make an order vacating the award.” 9
U.S.C. § 10(a). Likewise, the Act provides that the federal district court for the district in which
the award is made “may make an order modifying or correcting the award,” id. § 11, and, “[i]f no
court is specified in the agreement of the parties, then” an application to confirm the award “may
be made to the” federal district court “within which such award was made,” id. § 9. As the
Supreme Court has explained, “the three venue sections of the FAA are best analyzed together,”
and, in light of the legislative history of the Act, it is evident that all three provisions are
permissive, not mandatory. Cortez Byrd Chips, Inc. v. Bill Harbert Const. Co., 529 U.S. 193,
198–204 (2000). Most notably, § 9 expressly contemplates that the parties to an arbitration
agreement may agree to an alternative venue for bringing a confirmation proceeding, and, as the
Supreme Court explained, there is no basis to believe that Congress intended that confirmation
13
proceedings might be brought in one venue, while vacatur proceedings must be brought in
another. Id. at 200–201.
It is possible that a state law mandating that confirmation, vacatur, or modification
proceedings must be brought in a state forum and precluding the parties from contractually
agreeing otherwise might conflict with even the permissive view of the FAA’s venue provisions.
And, at first blush, the language in D.C. Code § 4404(b), which precludes a party to an
arbitration agreement from waiving the applicability of D.C. Code § 16-4426 before a dispute
subject to the arbitration requirement arises, might be seen to cross that line. But that is not how
the parties present the issue, and it is not how the Court understands it. Rather, Equitas’s
contention that D.C. law applies here is premised on the claim that the SACCA and FAASA
affirmatively incorporate DC law into the parties’ agreement; Equitas does not argue that D.C.
law applies of its own force and despite the parties’ agreement, but rather that it applies because
of their agreement. See Dkt. 14-1 at 7. With the issue so framed, Defendants cannot plausibly
claim that the D.C. choice-of-forum rules directly conflict with the permissive venue provisions
contained in the FAA. To the contrary, defense counsel conceded at oral argument that
contractual provisions expressly limiting enforcement of an arbitration award to a particular
forum are enforceable.
Defendants’ claim of “obstacle” preemption fares no better. “Congress enacted the FAA
to replace judicial indisposition to arbitration with a ‘national policy favoring [it] and plac[ing]
arbitration agreements on equal footing with all other contracts.’” Hall St. Assocs., LLC v.
Mattel, Inc., 552 U.S. 576, 581 (2008) (quoting Buckeye Check Cashing, Inc. v. Cardegna, 546
U.S. 440, 443 (2006)) (alterations in Hall St.). It is this policy that informs the preemptive scope
of the Act. As the Supreme Court has affirmed:
14
While the FAA . . . pre-empts application of state laws which render arbitration
agreements unenforceable, “[i]t does not follow, however, that the federal law has
preclusive effect in a case where the parties have chosen in their [arbitration]
agreements to abide by state rules.” To the contrary, because “[t]he thrust of the
federal law is that arbitration is strictly a matter of contract,” the parties to an
arbitration agreement should be ‘at liberty to choose the terms under which they
will arbitrate.” Where . . . the parties have chosen in their agreement to abide by
the state rules of arbitration, application of the FAA to prevent enforcement of
those rules would actually be “inimical to the policies underlying state and federal
arbitration law[] because it would force the parties to arbitrate in a manner
contrary to their agreement.”
Volt, 489 U.S. at 472 (citations omitted) (first, second, and third alterations in original); see also
id. at 478–79. Thus, even if a contract is covered by the FAA, if it “make[s] applicable state [or
D.C.] rules governing the conduct of arbitration,” those local rules are not necessarily preempted.
Id. at 476; see also Hall St. Assocs., 552 U.S. at 590 (“The FAA is not the only way into court
for parties wanting review of arbitration awards: they may contemplate enforcement under state
statutory or common law . . . .”). This is because “[t]here is no federal policy favoring
arbitration under a certain set of procedural rules; the federal policy is simply to ensure the
enforceability, according to their terms, of private agreements to arbitrate.” Volt, 489 U.S. at
476. If the parties in fact agreed to limit judicial review of the award to the D.C. Superior Court,
that private agreement would not conflict with the policies embodied in the FAA, and their
agreement should be enforced. See, e.g., Foulger-Pratt Residential Contracting, LLC v.
Madrigal Condos., LLC, 779 F. Supp. 2d 100, 108–11 (D.D.C. 2011).
Finally, although D.C. Code § 16-4426(b) speaks in terms of the “exclusive jurisdiction”
of the D.C. Superior Court, the Court does not understand that provision—or Equitas’s
argument—to purport to constrain the subject-matter jurisdiction of the federal district courts.
See Dkt. 14-1 at 7. Rather, both the D.C. law and Equitas’s argument are best understood to
pertain to the proper venue or forum for judicial review of an arbitration award. Obviously,
15
neither the states nor private parties may alter the subject-matter jurisdiction of the federal
courts. For the reasons described above, however, parties to an arbitration agreement may either
directly, or through the incorporation of state law, agree that related litigation will be brought in
any forum of their choice, so long as that forum has jurisdiction to decide the dispute.
Accordingly, if the SACCA and FAASA incorporate D.C. Code § 16-4426(b), the venue rule
contained in that provision would not conflict with the FAA.
2. Contract Interpretation
The question, then, is simply whether, as matter of contract interpretation, the SACCA
and FAASA incorporate D.C. Code § 16-4426(b), as Equitas contends. That is, “the case . . .
comes down to what the contract has to say” about the proper forum for judicial review of the
arbitration award. Mastrobuono v. Shearson Lehman Hutton, Inc., 514 U.S. 52, 58 (1995).
Three sentences contained in the “Governing Law; Dispute Resolution” provisions of the
contracts are most relevant to this question. The first sentence states that “[t]his Agreement shall
be deemed to have been entered into under the laws of the District of Columbia, and the rights
and obligations of the parties hereunder shall be governed and determined according to the laws
of said state without giving any effect to conflict of laws.” Dkt. 9-2 at 39 (SACCA); id. at 57
(FAASA). The second sentence provides for the application of the JAMS Streamlined
Arbitration Rules and Procedures. Id. And the final sentence states that “[j]udgment may be
entered into in any court of competent jurisdiction to enforce any final decision by the
arbitrators.” Id. According to Equitas, by incorporating D.C. law, the first sentence incorporates
the DCRAA, including § 16-4426(b). See Dkt. 14-1 at 6. Defendants, in contrast, argue that the
parties were required to expressly opt out of the FAA if they wished to incorporate the DCRAA
and that, in any event, the second and final sentences provide that an action to enforce or to
16
vacate the arbitration award can be brought in any court with jurisdiction, not just the D.C.
Superior Court. The parties agreed at oral argument that there is no parol evidence that would
elucidate the meaning of these provisions and the contracting parties’ intent with respect to the
proper forum for this action.
The Supreme Court’s decision in Mastrobuono v. Shearson Lehman Hutton, Inc., 514
U.S. 52, provides a helpful starting point for construing the SACCA and FAASA. In
Mastrobuono, the Supreme Court construed “a standard-form contract that expressly provide[d]
that it ‘shall be governed by the laws of the State of New York.’” Id. at 53. Although the
contract “contain[ed] no express reference to claims for punitive damages,” id. at 59, under New
York law, “the power to award punitive damages [was] limited to judicial tribunals and [could]
not be exercised by arbitrators,” id. at 55. The arbitration clause of the contract also, however,
“explicitly authorize[d] arbitration in accordance with [National Association of Securities
Dealers (“NASD”)] rules.” Id. at 60. Under those rules, “arbitrators [could] award ‘damages
and other relief,’” which the Court construed as “broad enough at least to contemplate [punitive
damages as] a remedy.” Id. at 61. Thus, as in this case, Mastrobuono involved an arguable
conflict between a general provision incorporating state law and other contractual language.
The Mastrobuono Court concluded that “[a]t most, the choice-of-law clause introduce[d]
an ambiguity into an arbitration agreement that would otherwise [have] allow[ed] punitive
damages awards,” id. at 62, and that, given this ambiguity, “the best way to harmonize the
choice-of-law provision with the arbitration provision [was] to read ‘the laws of the State of New
York’ to encompass substantive principles that New York courts would apply, but not to include
special rules limiting the authority of arbitrators,” id. at 63–64. So understood, the Court
concluded that “the choice-of-law provision cover[ed] the rights and duties of the parties, while
17
the arbitration clause cover[ed] arbitration; neither sentence intrude[d] upon the other.” Id. at 64.
Thus, notwithstanding the inclusion of a provision in the contract incorporating New York law in
general terms, the Court concluded that the contract did not incorporate New York law regarding
arbitral awards of punitive damages. Id. at 55, 64.
Here, the first sentence of the SACCA and FAASA incorporating D.C. law presents a
similar ambiguity, presenting two possible interpretations of the contract. On the one hand, the
first sentence provides that D.C. law governs and, under D.C. contract law, “laws in effect at the
time of the making of a contract form a part of the contract ‘as fully as if they had been expressly
referred to or incorporated in its terms.’” Double H Hous. Corp. v. Big Wash, Inc., 799 A.2d
1195, 1199 (D.C. 2002) (quoting Farmers & Merchs. Bank of Monroe v. Fed. Reserve Bank of
Richmond, 262 U.S. 649, 660 (1923)). But, on the other hand, this generally worded choice-of-
law provision might also be construed, as in Mastrobuono, to incorporate only the “substantive
principles that [D.C.] courts would apply” with respect to the parties’ underlying contractual
dispute, Mastruobuono, 514 U.S. at 64, and not to incorporate local procedural laws, see Dalal v.
Goldman Sachs & Co., Inc., 575 F.3d 725, 726 (D.C. Cir. 2009) (per curiam) (unpub.); Ekstrom
v. Value Health, Inc., 68 F.3d 1391, 1395 (D.C. Cir. 1995), or local laws specific to arbitration
proceedings, Contech Constr. Prods, Inc. v. Heierli, 764 F. Supp. 2d 96, 107–108 (D.D.C. 2011);
Jung v. Ass’n of Am. Med. Colls., 300 F. Supp. 2d 119, 151–54 (D.D.C. 2004). As so construed,
D.C. law would define “the rights and obligations of the parties hereunder,” Dkt. 9-2 at 39, 57
(emphasis added)—that is, their substantive rights and obligations under the SACCA and
FAASA—but not the procedures for enforcing or vacating a future arbitration award. Cf.
Mastruobuono, 514 U.S. at 64.
18
Defendants argue that any ambiguity in the agreements favors their position because
Mastrobuono and its progeny impose a clear-statement rule—a rule that to “opt-out” of the rules
that would otherwise apply under the FAA, and to adopt the D.C. choice-of-forum rule in their
place, the parties would have had to do so expressly. See Dkt. 15 at 3–6 & n.2 (citing Contech,
764 F. Supp. 2d at 108; Jung, 300 F. Supp. 2d at 151–54). It is true that “[n]umerous courts of
appeals have concluded that Mastrobuono requires that the intent of the contracting parties to
apply state arbitration rules or law to arbitration proceedings must be explicitly stated in the
contract and that under Mastrobuono, a general choice of law provision does not evidence such
intent.” Jung, 300 F. Supp.2d at 152. That rule, however, is not as categorical as Defendants
suggest. They are correct that Mastrobuono declined to apply New York arbitration law on
punitive damages, at least in part, because the contract lacked “an unequivocal exclusion of
punitive damages claims.” 514 U.S. at 60 (emphasis added). But the Supreme Court’s
invocation of a clear-statement test was based on the premise that, “when a court interprets [an
ambiguous] provision[] in an agreement covered by the FAA, ‘due regard must be given to the
federal policy favoring arbitration, and ambiguities as to the scope of the arbitration clause itself
[must be] resolved in favor of arbitration.’” Id. at 62; see also Jung, 300 F. Supp. 2d at 153 &
n.21 (relying on “the policies that heavily favor arbitration” to hold that “Mastrobuono requires”
a clear-statement of intent to apply local arbitration law).
Unlike in Mastrobuono, the present dispute does not concern the scope of an arbitration
agreement or the authority of an arbitrator to award relief. Cf. Mastrobuono, 514 U.S. at 62.
Rather, the dispute is which court should decide the pending motions to vacate and to confirm,
and, as explained above, the FAA’s policy in favor of arbitration does not dictate a particular
forum for judicial review of an arbitration award. Because the FAA’s venue provisions are
19
permissive, see Cortez Byrd Chips, 529 U.S. at 198–204, the parties are free to choose any court
with jurisdiction to address post-arbitration motions, and, in construing what they agreed to do,
there is no basis for putting a finger on the scale in favor of a federal forum. Thus, what the
Court takes from Mastrobuono is simply that a generally worded choice-of-law clause in an
arbitration agreement does not resolve the question whether the contract incorporates all relevant
state law or only the rules defining the parties’ substantive rights. Resolution of that question, at
least in the present context, does not turn on the application of a clear-statement rule, but rather
on the language of the contract read “as a whole,” Mastrobuono, 514 U.S. at 59 (quoting
Restatement (Second) of Contracts § 202(2) (1979)), and settled rules of contract interpretation. 5
Here, even in the absence of a clear-statement rule, the better reading of the contract is
the one propounded by Defendants. They contend that the second and final sentences of the
Governing Law provisions of the SACCA and FAASA refute Equitas’s claim of exclusive venue
in the D.C. Superior Court. Dkt. 15 at 4–5. The Court disagrees as to the second sentence, but
agrees with respect to the final sentence. The second sentence states that the arbitration is to be
“administered by and in accordance with the then existing JAMS Streamlined Arbitration Rules
and Procedures.” Dkt. 9-2 at 39, 57. Under those rules, judicial review of an arbitration award is
5
Among these rules, Mastrobuono relied on “the common-law rule of contract interpretation
that a court should construe ambiguous language against the interest of the party that drafted it”
as a tiebreaker. 514 U.S. at 62. Here, however, the parties’ agreements disclaim application of
that doctrine. See Dkt. 9-2 at 41 (SACCA) (“The parties have participated jointly in the
negotiation and drafting of this Agreement . . . . [T]his agreement will be construed as if drafted
jointly . . . .”); id. at 58 (FAASA) (“This Agreement will not be construed more strictly against
any party regardless of who is responsible for its drafting.”); see also Aeroground, Inc. v.
CenterPoint Props. Tr., 738 F.3d 810, 817 (7th Cir. 2013) (declining to construe agreement
against drafter where contract included similar provision). But see Dkt. 2-4 at 10 (arbitrator’s
finding that the SACCA “was drafted by Ed McGinty, a Florida lawyer who was not only
retained by Equitas (or its predecessor) but who also had a financial interest in Mr. Abeles’
enterprise”).
20
available in “any court having jurisdiction thereof”—either in accordance with the FAA or in
accordance with state law. Rule 20, JAMS Streamlined Arbitration Rules & Procedures. 6
Defendants contend that this shows that judicial review of the arbitration award is not confined
to the D.C. Superior Court, but extends to any court with subject-matter jurisdiction. See Dkt 15
at 4–5. As Equitas points out, however, the very next sentence of the Governing Law provision
belies any claim that the JAMS Rules resolve the venue issue. That sentence declares that “[t]he
provisions of this Agreement shall prevail in case of inconsistency between the Rules of
Arbitration and this Agreement.” Dkt. 18 at 3–4 (quoting Dkt. 2-4 at 42, 44). Thus, to the extent
that the first sentence of the Governing Law provisions could be construed to incorporate the
venue rule found in D.C. Code § 16-4426(b), the incorporation of the JAMS Rules does nothing
to undercut that construction.
Defendants’ argument premised on the final sentence of the Governing Law provisions,
however, fares better. That sentence speaks directly to the question in dispute and states in
categorical terms that “[j]udgment may be entered into in any court of competent jurisdiction to
enforce any final decision by the arbitrators.” Dkt. 9-2 at 39, 57 (emphasis added). Although
Defendants acknowledged at oral argument that this language constitutes boilerplate included in
many, if not most, arbitration agreements, it provides in plain—and specific—terms that judicial
review is available in any court of competent jurisdiction. “Read naturally, the word ‘any’ has
6
JAMS Rule 20, available at http://www.jamsadr.com/rules-streamlined-arbitration/#Rule20,
provides in full:
Proceedings to enforce, confirm, modify or vacate an Award will be controlled by
and conducted in conformity with the Federal Arbitration Act, 9 U.S.C. Sec 1, et.
seq., or applicable state law. The Parties to an Arbitration under these Rules shall
be deemed to have consented that judgment upon the Award may be entered in
any court having jurisdiction thereof.
21
an expansive meaning, that is, ‘one or some indiscriminately of whatever kind.’” United States
v. Gonzales, 520 U.S. 1, 5 (1997) (quoting Webster’s Third New International Dictionary 97
(1976)). And, while context matters, see Small v. United States, 544 U.S. 385, 388 (2005),
Equitas offers no reason to give the word anything other than its natural meaning. The final
sentence, accordingly, provides that an arbitration award may be “entered”—that is, confirmed—
in whatever court the moving party might select, so long as that court has jurisdiction. Here,
moreover, there is no dispute that the parties’ dispute falls within this Court’s diversity
jurisdiction, and thus the final sentence of the Governing Law provisions confirms that
Defendants acted within the plain terms of the SACCA and FAASA when they removed the
action to this Court.
To be sure, the final sentence addresses motions to confirm awards, and not motions, like
the one Equitas brought, to vacate an award. But as the Supreme Court suggested in Cortez
Byrd, it would make little sense to designate different tribunals for purposes of enforcing and
vacating an arbitration award. See 529 U.S. at 200–201. Indeed, Equitas does not argue
otherwise, nor could it given the fact that D.C. Code § 16-4426(b) is itself addressed to the
proper court “to enter judgment on an” arbitration award. Nor can Equitas reasonably argue that
this is not a “court of competent jurisdiction” on the theory that D.C. Code § 16-4426(b) grants
“exclusive jurisdiction” to the D.C. Superior Court. As explained above, the Court understands
the D.C. Code’s reference to “exclusive jurisdiction” to refer to venue, not subject-matter
jurisdiction. If that language were construed otherwise, it would directly conflict with 28 U.S.C.
§ 1332, which grants the district courts jurisdiction in diversity cases, and would be preempted
by federal law. See, e.g., United States v. Peters, 9 U.S. 115, 136 (1809).
22
This, then, leaves only the question whether the first and final sentences of the Governing
Law provision conflict, and, if so, how that conflict should be resolved. As in Mastrobuono, the
Court concludes that any potential conflict can, and should, be avoided by construing the first
sentence to identify the source of substantive law for purposes of the contract, but not to specify
the procedures for enforcing or vacating an arbitration award. Cf. Mastrobuono, 514 U.S. at 63–
64. As the Court put it in Mastrobuono, “a document should be read to give effect to all its
provisions and to render them consistent with each other.” Id. at 63; see also Abdelrhman v.
Ackerman, 76 A.3d 883, 891 (D.C. 2013) (“When interpreting a contract, we ‘strive to give
reasonable effect to all its parts and eschew an interpretation that would render part of it
meaningless or incompatible with the contract as a whole.’” (quoting District of Columbia v.
Young, 39 A.3d 36, 40 (D.C. 2012)). If the first provision confers exclusive jurisdiction on the
D.C. Superior Court by operation of D.C. Code § 16-4426(b) as Equitas contends, there is no
way to give the final sentence—and, in particular, the word “any”—a plausible meaning.
Equitas argues that “any court of competent jurisdiction” retains meaning under its
interpretation because, under D.C. law, the parties could have agreed to a forum other than the
Superior Court after the dispute arose. See Dkt. 18 at 4 n.1 (citing D.C. Code § 16-4404(a)). “It
is an axiom of contract interpretation,” however, that “the court should determine ‘what a
reasonable person in the position of the parties would have thought the disputed language
meant.’” Foulger-Pratt, 779 F. Supp. 2d at 110 (quoting Steele Founds., Inc. v. Clark Constr.
Group, Inc., 937 A.2d 148, 154 (D.C. 2007)). Here, Equitas’s construction is a stretch too far.
Although the parties could easily have done so, they did not say that an arbitration award could
be enforced in “any court of competent jurisdiction that the parties agree to after a dispute
arises.” Instead, they simply said “any” court with jurisdiction. Limiting the reach of the final
23
provision to Equitas’s construction might give that sentence some meaning—it might apply in
unusual circumstances to more than a single court—but its construction would not give the
sentence a meaning that comports with its plain terms.
Construing the final sentence to confirm that the parties may enforce or seek to vacate an
award in any court with jurisdiction is also supported by another rule of construction—that
“‘specific terms and exact terms are given greater weight than general language.’” Abdelrhman,
76 A.3d at 891. Equitas relies on the first sentence of the Governing Law provisions, but that
sentence provides for the application of D.C. law in general terms, without any reference to
proceedings to review an arbitration award. The final sentence, in contrast, is addressed to one
topic alone—the choice of forum for purposes of an action to enforce an arbitration award.
Under the Court’s construction of the SACCA and FAASA, “both the specific and general
provisions [are] given reasonable effect, [and] both are . . . retained.” Id. (internal quotation
marks omitted). Even if these provisions were irreconcilable, moreover, the “specific
clause[]”—the final sentence—would “prevail over [the] general clause[]”—the first sentence.
Id. Under either construction, D.C. Code § 16-4426(b) is not incorporated into the contract and
jurisdiction over this action is not limited to the D.C. Superior Court.
Finally, this construction is consistent with the cases relied upon by Equitas. Equitas is
correct that in Volt the Supreme Court upheld the application of the California Arbitration Act’s
procedural provisions regarding stays of arbitration “in a case where the parties . . . agreed that
their arbitration agreement [would] be governed by the law of California.” 489 U.S. at 470. The
question before the Court in Volt, however, was only whether the FAA categorically precludes
parties from choosing state rules to govern an arbitration. See id. The Court, moreover,
expressly stated that it was not reviewing the California Court of Appeal’s finding that the
24
general choice-of-law provision incorporated the California rules of arbitration into the contract.
See id. at 474. Indeed, as the Supreme Court explained, that case came to it on review of a final
judgment rendered by the highest court of a state, see id. at 473 n.4, and, although the proper
interpretation of the FAA presented a question of federal law, “the interpretation of private
contracts is ordinarily a question of state law, which th[e] [Supreme] Court does not sit to
review,” id. at 474. Here, in contrast, the Court must construe the parties’ contracts de novo. See
Mastrobuono, 514 U.S. at 60 n.4 (distinguishing Volt on this basis).
Equitas’s reliance on C & L Enterprises, Inc. v. Citizen Band Potawatomi Indian Tribe of
Oklahoma, 532 U.S. 411 (2011), is similarly misplaced. That case concerned whether the
Potawatomi tribe waived its sovereign immunity “when it expressly agreed to arbitrate disputes
with C & L relating to the contract, to the governance of Oklahoma law, and to the enforcement
of arbitral awards ‘in any court having jurisdiction thereof.”” Id. at 414. In addressing the
sovereign-immunity question, the Court explained that “[t]he contract’s choice of law clause
makes it plain enough that a ‘court having jurisdiction’ to enforce the award in question is the
Oklahoma state court.” Id. at 419. This was because the arbitration provision provided for
“arbitral awards [to] be reduced to judgment ‘in accordance with applicable law in any court
having jurisdiction thereof’” and, under Oklahoma law, the state court had such jurisdiction. Id.
The Court did not decide, and had no reason to decide, whether the arbitration award might also
have been enforced in federal court; indeed, the Tribe’s position was that “[n]o court—federal,
state, or even tribal—ha[d] jurisdiction over [the] suit.” Id. at 421. And it did not decide, and
had no reason to decide, whether the general choice-of-law provision conflicted with some other
contractual provision, like the specific forum-selection clause at issue here.
25
Finally, Equitas points to several district-court cases to support its position, but those
cases are also readily distinguishable because they either expressly designate the D.C. Superior
Court as the proper venue or expressly incorporate the DCRAA. See Dkt. 14-1 at 3–4, 6. In
Carmen Group, Inc. v. Xavier University of Louisiana, for example, Judge Cooper of this Court
held that a forum-selection clause stating that “venue . . . shall be the Superior Court of the
District of Columbia” and that the parties “waive any objection to such venue” was sufficiently
clear to “effect a waiver of the parties’ removal rights.” 41 F. Supp. 3d 8, 10–11 (D.D.C. 2014).
Similarly, in Foulger-Pratt, Judge Kessler concluded that a clause providing that “‘[t]his
[a]greement to arbitrate shall be specifically enforceable pursuant to and interpreted under the
laws of the District of Columbia’” meant what it said, and that, accordingly, review of the
arbitration award was properly conducted under D.C. law. 779 F. Supp. 2d at 110
(distinguishing Mastrobuono and concluding DCRAA applied because “[i]n this case, . . . the
parties included a specific clause” providing for enforcement of the arbitration award under D.C.
law (emphasis added)). Neither conclusion is surprising or at odds with the conclusion that
Equitas and Defendants expressly agreed that a proceeding to review the arbitrator’s award could
be brought in “any court of competent jurisdiction.”
The parties could have included a provision in the SACCA and FAASA expressly
designating the D.C. Superior Court as the exclusive forum for review of the arbitration award,
but they did not. The Court agrees with Defendants that to adopt Equitas’s reading of the general
D.C. choice-of-law provision as vesting exclusive venue in the D.C. Superior Court would be
akin to “rewrite[ing] the agreements.” Dkt. 15 at 6. The Court, accordingly, DENIES Equitas’s
motion to remand this action to the D.C. Superior Court. See Dkt. 14.
C. Motion to Vacate
26
1. Denial of Postponement
Equitas contends that, in any event, it is entitled to vacatur of the arbitration award under
either the DCRAA or the FAA because the arbitrator improperly denied its requests for a
continuance of the arbitration hearing. Dkt. 2-4 at 19–21. For purposes of determining whether
the arbitrator’s denial of a postponement warrants vacatur of the arbitration award, it is
immaterial whether the FAA or the DCRAA applies. Under both statutes, “judicial review of
arbitration awards is extremely limited.” Foulger-Pratt, 779 F. Supp. 2d at 113. “Such
extremely limited review ‘serves to attain a balance between the need for speedy, inexpensive
dispute resolution, on the one hand, and the need to establish justified confidence in arbitration
among the public, on the other.’” Id. at 114 (quoting Bolton v. Bernabei & Katz, PLLC, 954
A.2d 953, 959 (D.C. 2008)).
Both statutes include denial of a postponement as a ground for vacatur. Under the FAA,
the court “may make an order vacating the award . . . where the arbitrators were guilty of
misconduct in refusing to postpone the hearing, upon sufficient cause shown.” 9 U.S.C.
§ 10(a)(3). Under the DCRAA, “the court shall vacate an award . . . if . . . [a]n arbitrator refused
to postpone the hearing upon [a] showing of sufficient cause for postponement.” D.C. Code
§ 16-4423(a)(3). Notwithstanding the differences in language, courts apply the same deferential
standard to determine whether denial of a postponement warrants vacatur under the FAA and the
DCRAA. See Foulger-Pratt, 779 F. Supp. 2d at 118, 120 n.23; Naing Int’l Enterprises, Ltd. v.
Ellsworth Assocs., Inc., 961 F. Supp. 1, 2 (D.D.C. 1997); Capozio v. Am. Arbitration Ass’n, 490
A.2d 611, 615–18 (D.C. 1985); see also Hercules & Co. v. Beltway Carpet Serv., Inc., 592 A.2d
1069, 1073 (D.C. 1991) (“[F]ederal court decisions construing and applying the federal
arbitration act may be regarded as persuasive authority in construing and applying the
27
corresponding provisions of the District of Columbia arbitration act, so long as there is no
material difference in the statutory language between the two acts.”). 7 Under both statutes,
The arbitrary denial of a reasonable request for a postponement may serve as
grounds for vacating an arbitration award. However, arbitrators are to be
accorded a degree of discretion in exercising their judgment with respect to a
requested postponement. Thus, if there exists a reasonable basis for the
arbitrators’ decision not to grant a continuance, the Court will be reluctant to
interfere with the award on these grounds. Nonetheless, if the failure of an
arbitrator to grant a postponement or adjournment results in the foreclosure of the
presentation of “pertinent and material evidence,” it is an abuse of discretion.
Naing Int’l Enterp., 961 F. Supp. at 3 (citations omitted) (applying the FAA); see also Foulger-
Pratt, 779 F. Supp. 2d at 118 (applying the same standard under the DCRAA). The question,
accordingly, is not whether this Court might have exercised its discretion to grant a
postponement under the relevant circumstances, but whether the arbitrator’s decision to deny the
continuance was unreasonable or an abuse of discretion.
Equitas contends that the arbitrator’s denial of a postponement lacked a reasonable basis
because “Mr. Abeles had been diligent in notifying the case administrator of his need for new
counsel and the need for a continuance for well over a month in advance of the hearing.” Dkt. 2-
4 at 20. But the fact that Abeles informally told the case administrator in mid-October 2014 that
counsel for Equitas intended to withdraw and that Equitas would need a postponement, Dkt. 2-4
at 25 (Abeles Aff. ¶ 15), does not explain Equitas’s inability to obtain new counsel in time for
the December hearing. The arbitrator found that “Mr[.] Abeles clearly had prior notice of
counsel’s withdrawal,” Dkt. 2-4 at 8, and this finding was supported by the record. When
7
The D.C. Uniform Arbitration Act, the predecessor to the DCRAA, which some of the cases
cited above interpret, provided for vacatur based on denial of a postponement in terms materially
indistinguishable from the DCRAA: “[T]he Court shall vacate an award where: . . . The
arbitrators refused to postpone the hearing upon sufficient cause being shown therefor . . . .”
D.C. Code § 16-4311(a)(4) (West 2007).
28
Equitas eventually filed a motion for a postponement just before Thanksgiving, it cited the
departure of a “key member[] on [its] legal team” from Zuckerman Spaeder as the reason that it
was necessary to adjourn the previously scheduled hearing. Dkt. 16-3 at 33. But, as Abeles
admits, that person left the firm on July 1, 2014—a month and a half before the December
hearing date was even set with the consent of the parties, and over five months before the
hearing. Dkt. 2-4 at 25 (Abeles Aff. ¶ 13); id. at 46, 61. Moreover, Equitas learned that its lead
attorney would leave in the middle of June 2014, Dkt. 2-4 at 61, and, as early as August 26,
2014, Zuckerman Spaeder withdrew from representing Equitas in closely related litigation, Dkt.
16-3 at 20–23.
In seeking a postponement, Equitas did not provide any description of its efforts since the
summer to retain new counsel, and it did not offer any explanation why those efforts had proven
unsuccessful or any indication of when it anticipated actually retaining new counsel. This was
insufficient to show cause why, having been aware of the need to identify a new lead attorney for
months, Equitas was unable timely to proceed with the hearing. This was not a case, moreover,
where the need for new counsel arose suddenly and to the surprise of the client. To the contrary,
Abeles simply asserts that over time he “became increasingly disenchanted with the attorneys
handling [the] case.” Dkt. 2-4 at 25 (Abeles Aff. ¶ 13). An unexplained “disenchantment” with
one’s counsel on the eve of trial, where the client had months to assess counsel’s performance
and to make a change if appropriate, does not—without more—establish good cause for an
adjournment.
Abeles’s only other explanation for Equitas’s delay in identifying and retaining new
counsel was that Defendants’ “failure to pay JAMS fees . . . lull[ed] Equitas into thinking that it
had time to obtain new counsel” and that “retaining new counsel would have been an unjustified
29
expense while it appeared that the [Defendants] were not willing to pay their share and proceed
with the arbitration.” Dkt. 2-4 at 60, 62. That contention, however, is in tension with Abeles’s
representation to the arbitrator that, “when one of the key members on [Equitas’s] legal team left
Zuckerman Spaeder,” Equitas “immediately began exploring [its] options and conferring with
other counsel” but had “not yet complete[d]” the process by the time it sought the continuance.
Dkt. 16-3 at 33 (emphasis added). And, even more to the point, it is difficult to square with the
timeline. Abeles asserts that he did not learn that Defendants had failed to pay their share of the
arbitration fees until the last week of October, at the same time that he was purportedly told by
the case manager that the hearing would “likely” be canceled.” 8 Dkt. 2-4 at 25–26 (Abeles Aff.
¶ 16), 62. But he also concedes that on October 30, 2014, JAMS informed him that Defendants
would have until November 7, 2014 to pay their share of the fees and that if they failed to do so,
the hearing would be canceled, id. at 48; see also id. at 26 (Abeles Aff. ¶ 17). And there is no
dispute that Defendants did, in fact, pay the required fees on November 7. Id. at 26 (Abeles Aff.
¶ 19).
As a result, (1) any confusion about whether the hearing would be canceled due to non-
payment could not have prevented Equitas from locating new counsel between the middle of
June and the end of October; (2) by the end of October, Equitas was on formal notice that the fee
issue would not prevent the hearing from going forward if Defendants paid their share of the fees
by November 7; and (3) the Defendants, in fact, paid the fee by the November 7 deadline. Thus,
even viewed in the light most favorable to Equitas, the record reflects that it waited months to
locate replacement counsel and that, even if it—briefly—delayed its search for new counsel in
8
In a roughly contemporaneous email that Abeles sent to the case administrator, he describes
her assessment of the situation somewhat less affirmatively, noting that she merely said that “it
was quite plausible the entire Arbitration would be cancelled.” Dkt. 2-4 at 51.
30
late October and early November, it did so with the knowledge that Defendants would not be
precluded from going forward if they paid the fees by November 7. The timeline also provides
no explanation at all for why, after learning that Defendants had paid, Equitas waited until
November 26 (Thanksgiving eve) to ask the arbitrator to postpone the hearing—even though it
was informed at the time that the hearing was scheduled that “[a]ny cancellation or continuance
must be approved by the arbitrator.” Dkt. 16-3 at 14. Under these circumstances, the Court
cannot conclude that the arbitrator acted arbitrarily or unreasonably in finding that Equitas had
not shown “sufficient cause” for a postponement. See Dkt. 2-4 at 8.
Equitas goes on to argue that the arbitrator should have at least “inquir[ed] as to whether
Equitas would pay [the] costs [of a continuance] (including cancellation fees payable to the
Arbitrator himself)” instead of denying outright the request for a postponement. Id. at 20.
Although Defendants opposed a postponement, they argued that if one was granted, Equitas
should be responsible for such costs. Id. at 58. But Defendants never agreed to a postponement,
even on the condition that Equitas pay their costs. Nor did Equitas ever indicate that this
alternative was acceptable to it. To the contrary, it replied only that it was entitled to a
postponement and that Defendants’ costs were “de minimis” relative to the harm caused to it by
Defendants’ alleged breach of its obligations under the SACCA and FAASA. Id. at 63. The
arbitrator was under no obligation to inquire into Equitas’s willingness to pay for the costs
associated with a postponement, particularly after Equitas replied dismissively to Defendants’
contention that it should. And, even if Equitas was willing to pay for a postponement, it was still
reasonable for the arbitrator to conclude that Equitas had not shown sufficient cause to justify
further delay of the proceedings.
31
Finally, Equitas contends that “failure to grant the continuance was exacerbated by the
fact that, during the course of the proceeding, [Defendants] presented false or misleading
testimony, knowing that Mr. Abeles was not in a position to rebut it.” Id. at 21.
Notwithstanding the “degree of discretion” afforded to arbitrators “in exercising their judgment
with respect to a requested postponement,” if a denial “results in the foreclosure of the
presentation of ‘pertinent and material evidence,’ it is an abuse of discretion.” Naing Int’l
Enterp., 961 F. Supp. at 3 (citation omitted). This is because “neither this Court nor the
arbitration panel can allow the pursuit of an expedient adjudication to outweigh its obligation to
ensure a just and fair one.” Id. at 5.
Equitas, however, has not shown that it was prevented from presenting any such
evidence. Abeles asserts that, during the hearing, Defendants’ “witnesses repeatedly made
statements that [he] knew to be untrue,” including statements “relating to whether specific cases
were within the scope of the agreements at issue in the arbitration.” Dkt. 2-4 at 29 (Abeles Aff.
¶ 30). But Abeles did cross-examine the Defendants’ witnesses at the hearing, although,
according to the arbitrator, he did not do so “effectively.” Id. at 9. The arbitrator concluded, at
any rate, that Abeles’s inability to conduct an effective cross-examination did “not devalue or
impeach the testimony of” a key witness, “a non-party witness who was Mr[.] Abeles’ former
business associate in Equitas and who reaffirmed an earlier affidavit that set forth his
understanding that Equitas would not share in the fees earned by [Defendants] on ‘every
disability case they ever had.’” Id. at 9–10. Equitas, in turn, does not rebut this conclusion or,
indeed, offer any description of what further impeachment evidence it was prevented from
presenting, contending only that Abeles “had documents” that would have defeated Defendants’
argument regarding the interpretation of the contracts. Id. at 29 (Abeles Aff. ¶ 30). Without a
32
proffer of the evidence that Equitas would have presented, there is no basis on which the Court
could conclude that Equitas was prevented from presenting “pertinent and material” evidence.
Cf. Laws v. Morgan Stanley Dean Witter, 452 F.3d 398, 400 (5th Cir. 2006) (“Absent even a
representation that the materials [plaintiff sought additional time to review] were important to his
case or that a continuance might have altered the outcome of the arbitration, we cannot conclude
that [plaintiff] was deprived of a fair hearing.”). And, without an explanation of why Abeles
could not himself present those documents at the hearing or afterward, the Court cannot conclude
that the denial of a postponement foreclosed the presentation of any evidence—material or
otherwise. The arbitrator permitted the parties to submit further evidence until December 12,
Dkt. 2-4 at 8, and, as defense counsel conceded at oral argument, Equitas did so.
There is no authority, moreover, for the proposition that an arbitrator must indefinitely
delay proceedings to accommodate a party who dismisses its counsel and then dawdles in
obtaining new counsel. In Fairchild & Co., Inc. v. Richmond, Fredericksburg & Potomac
Railroad Co., for example, the plaintiff alleged that, due to a withdrawal of counsel, it “was
unable to secure adequate legal representation . . . until shortly before” the proceedings were
commenced and that “a postponement [was] necessary to permit it to adequately prepare for the
hearing.” 516 F. Supp. 1305, 1313 (D.D.C. 1981). Another judge of this court affirmed the
arbitrator’s conclusion that the plaintiff “had had ample time to secure adequate legal
representation and prepare” and that its “arguments in support of its request did not justify a
substantial delay in the resolution of the case.” Id. at 1314. Indeed, some courts have even held
that arbitrators do not abuse their discretion in denying a postponement when the result is that the
arbitration hearing is held entirely ex parte. See, e.g., Capozio, 490 A.2d at 614–617; Scott v.
Prudential Secs., Inc., 141 F.3d 1007, 1010, 1017 (11th Cir. 1998). Here, in contrast, the
33
arbitrator had the benefit of briefing on the construction of the parties’ agreements that was
submitted prior to Zuckerman Spaeder’s withdrawal from the case, and Abeles participated in the
hearing on Equitas’s behalf. See Dkt. 2-4 at 8.
“[A]rbitrators are given a great deal of latitude in conducting arbitration proceedings, and
based upon the record, the Court cannot find that the arbitrator[’s] conduct constituted
misconduct nor can the Court find on this record that there was even an abuse of discretion by
the arbitrator[].” Berlacher v. PaineWebber Inc., 759 F. Supp. 21, 24 (D.D.C. 1991). “This is
particularly so in view of the fact that [Equitas] . . . had itself made a formal demand for
arbitration, yet purportedly remained unprepared for a hearing nearly [twelve] months after that
demand.” Fairchild, 516 F. Supp. at 1314. The Court, accordingly, DENIES Equitas’s motion
to vacate the arbitration award.
2. Timeliness
Given this conclusion, the Court need not reach Defendants’ alternative argument that
Equitas’ motion to vacate the arbitration award is untimely under the FAA, which requires that a
motion to vacate an arbitration award “be served upon the adverse party or his attorney within
three months after the award [was] filed.” 9 U.S.C. § 12; Dkt. 16-1 at 3–4. If Defendants’
timeliness defense called the Court’s jurisdiction into question, the Court would, of course, need
to address it, and, indeed, could not have decided the preceding issue in the absence of
jurisdiction. See Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 94 (1998). But it does not.
As the Supreme Court has explained, even though courts “have occasionally described a
nonextendable time limit as ‘mandatory and jurisdictional,’” recent caselaw clarifies that “time
prescriptions, however emphatic, are not properly typed ‘jurisdictional’” in the sense of
restricting courts’ subject-matter jurisdiction. Arbaugh v. Y&H Corp., 546 U.S. 500, 510 (2006)
34
(citations and some internal quotation marks omitted). Rather, “when Congress does not rank a
statutory limitation . . . as jurisdictional, courts should treat the restriction as nonjurisdictional in
character.” Id. at 516. That is the case with § 12 of the FAA. That provision says nothing about
the jurisdiction or the authority of the district courts, but rather—like a statute of limitations—
merely prescribes the time the moving party has to initiate an action challenging an arbitral
award. Given that the Court need not reach the issue to dispose of the pending motion, the Court
declines to decide whether Equitas’s motion to vacate was timely.
D. Motion to Confirm
Under both the FAA and DCRAA, the Court must grant a motion to confirm an
arbitration award once it denies a motion to vacate. See 9 U.S.C. § 9 (“[T]he court must grant
[an application for an order confirming the award] unless the award is vacated, modified, or
corrected as prescribed in sections 10 and 11 . . . .”); D.C. Code § 16-4423(e) (“If the court
denies a motion to vacate an award, it shall confirm the award unless a motion to modify or
correct the award is pending.”). Equitas asserts that, even if the Court denies the motion to
vacate, it should decline to confirm the arbitration award as a sanction for Defendants’ “blatant
forum[] shopping” in filing the Massachusetts action to confirm the arbitration award. Dkt. 21-1
at 2. Equitas’s claim of misconduct is difficult to square with the order of the Massachusetts
court observing that “nothing prohibits this court from confirming an arbitration award from the
District of Columbia.” Dkt. 16-3 at 46. But, even if the Court agreed with Equitas’s
characterization of Defendants’ conduct, Equitas fails to cite any authority for the proposition
that the Court may decline to confirm an arbitration award on this basis. See Hall St. Assocs.,
552 U.S. at 587 (“There is nothing malleable about ‘must grant,’ which unequivocally tells
courts to grant confirmation in all cases, except when one of the ‘prescribed’ exceptions
35
applies.”); A1 Team USA Holdings, LLC v. Bingham McCutchen LLP, 998 A.2d 320, 326 (D.C.
2010) (rejecting argument that DCRAA “broaden[s] judicial review of arbitral awards” beyond
“the traditional limited or extremely limited standard”). Having denied Equitas’s motion to
vacate the arbitration award, the Court, accordingly, GRANTS Defendants’ motion to confirm it.
Dkt. 17.
III. CONCLUSION
For the foregoing reasons, it is hereby ORDERED that Plaintiff’s motion to remand the
case, Dkt. 14, is DENIED; Plaintiff’s motion to vacate the arbitration award, Dkt. 2-4 at 4, is
DENIED; and Defendants’ motion to confirm the arbitration award, Dkt. 17, is GRANTED. A
separate Order will issue.
SO ORDERED.
/s/ Randolph D. Moss
RANDOLPH D. MOSS
United States District Judge
Date: March 29, 2016
36