This is an appeal by plaintiff from judgments in favor of the defendants American Bonding Company and J. W. Rapple, after the separate demurrers of each of said defendants had been sustained, the plaintiff declining to further amend his complaint.
The facts as presented by the record are these: In the month of December, 1909, the defendants E. B. Lennig and J. W. Rapple, as copartners, under the firm name of Lennig-Rapple Engineering Company, entered into a contract with the city and county of San Francisco for the installation of a heating and ventilating system in the Hall of Justice, and in connection therewith the said firm, as principal, and the American Bonding Company, as surety, executed and delivered to the proper officials of said city a statutory bond as security against any failure on the part of the said firm to pay for any of the materials or labor furnished for said work, as required by the provisions of the act of the legislature entitled "An act to secure the payment of the claims of materialmen, mechanics or laborers employed by contractors upon state, municipal or other public work," ap. proved March 27, 1897 (Stats. 1897, p. 201). The foregoing act was in effect at the time said bond was given; and it provided that any materialman furnishing materials or supplies to a contractor to be used in the performance of such public work, whose claim had not been paid by the contractor, shall, within thirty days from the time such work is completed, file with the proper officials by whom the work was awarded a verified statement of his claim, and that the same had not been paid; and at any time within ninety days after the filing of said claim the person filing the same might commence an action upon the bond.
The plaintiff herein furnished certain materials for the installation of said heating and ventilating system in the Hall of Justice under said contract. Before said materials were so furnished but after said bond had been given, the foregoing act was amended so as to provide that the materialman's claim might be filed within ninety days after the completion of the work, and that the claimant might have six months thereafter within which to commence his *Page 687 action. (Stats. 1911, p. 1422.) The plaintiff herein filed his claim in due form more than thirty days but within ninety days after the completion of the work. The respondent, American Bonding Company, urged upon demurrer that the statute as it existed at the time its bond was given, and not the statute as it stood at the time the plaintiff's materials were furnished, controlled; and that the latter's claim not having been filed within thirty days after the completion of the work, cannot be made the subject of a recovery upon the bond. The trial court adopted this view in sustaining the demurrer of the bonding company.
That it was in error in so doing is settled by the recent decision in the case of Asbestos Mfg. Supply Co. v. AmercanBonding Co., 25 Cal.App. 641, [145 P. 107], wherein this court for the third appellate district, upon the authority ofNational Surety Co. v. Architectural Dec. Co., 226 U.S. 276, [57 L.Ed. 221, 33 Sup. Ct. Rep. 17], holds that the change in a statute enlarging the time within which claims of this character may be filed and actions thereon begun, amounts merely to a modification of the remedy, and is not to be construed to be a material interference with the obligation of the bond. It follows that the judgment entered in favor of the American Bonding Co. must be reversed.
As to the judgment herein rendered upon the order of the court sustaining the demurrer of the defendant Rapple, we are of the opinion that it should be affirmed. The obligation of the Lennig-Rapple Engineering Co., the principal upon the bond upon which this suit was brought, was, according to the averments of the plaintiff's complaint, a partnership obligation, and not the individual bond of the members of the firm. The mere fact that after the execution of the bond the members of the firm had entered into certain understandings with each other, having for their object the dissolution of the copartnership, and the further carrying on of all work upon the firm contracts by Lennig, which agreements did not reach the point or have the effect of a novation, cannot affect the liability of the defendant Rapple upon the bond of the firm, nor entitle the plaintiff to sue him individually upon that bond. His liability is the statutory liability upon judgments obtained against the copartnership and not otherwise, according to the views expressed by the supreme court in the case ofRedwood City Salt *Page 688 Co. v. Whitney, 153 Cal. 421, [95 P. 885], and of this court for the third appellate district in the case of Asbestos Mfg. Supply Co. v. Lennig-Rapple Engineering Co., 26 Cal.App. 177, [146 P. 188].
Upon these authorities the judgment in favor of Rapple should be affirmed.
The judgment in favor of the American Bonding Co. is reversed and the cause remanded. The judgment in favor of J. W. Rapple is affirmed.
Kerrigan, J., and Richards, J., concurred.