In The
Court of Appeals
Seventh District of Texas at Amarillo
No. 07-16-00029-CV
PAT WOOD AND JOHNNY WOOD, APPELLANTS
V.
CARPET TECH, LTD., APPELLEE
On Appeal from the 72nd District Court
Lubbock County, Texas
Trial Court No. 2013-509,583, Honorable Ruben Gonzales Reyes, Presiding
November 2, 2016
MEMORANDUM OPINION
Before QUINN, C.J., and CAMPBELL and HANCOCK, JJ.
Pat and Johnny Wood (the Woods) appeal from a judgment denying them
recovery against Carpet Tech, Ltd. (Carpet Tech).1 Their two issues implicate the legal
and factual sufficiency of various fact findings executed by the trial court. Through the
first they contend that neither legally nor factually sufficient evidence supports the trial
court’s decision to reject their claim of usury. Through the second they assert that the
decision to deny them damages similarly lacks evidentiary support. We affirm.
1
Carpet Tech filed a cross-appeal. It has since been dismissed per Carpet Tech’s motion.
Background
The dispute arose from a house fire experienced by the Woods. They hired
Carpet Tech to conduct remediation efforts. Those efforts included both the salvaging
of personalty and the demolition and reconstruction of various parts of the house. The
combined bill for doing those tasks exceeded $200,000 and much of it was paid by the
Woods as the work proceeded. However, they withheld a final payment approximating
$25,860 because they believed the work done was deficient in several respects. Carpet
Tech eventually assessed an interest charge on the outstanding sum at 1.5 % per
month or 18% per annum. So too did it sue to recover the debt. In turn, the Woods
filed their counterclaim against Carpet Tech, alleging multiple causes of action including
one sounding in breached contract and another in usury.
Trial was to the court. Thereafter, judgment was entered denying recovery to all
the parties. Findings of fact and conclusions of law were also executed by the trial court
in support of its judgment.
Issue One — Usury
In denying the claim of usury, the trial court found that “Carpet Tech did not
improperly charge interest on the amounts it contended were due and owing by the
Woods.” The Woods now “challenge[] the legal and factual sufficiency of the trial
court’s finding that Carpet Tech’s charge of at least 18% on the contents job invoice
was legal.” Allegedly, they established as a matter of law the elements of usury, which
elements consisted of proof that “(a) Carpet Tech loaned money to Wood by extending
credit for the contents remediation services it rendered, (b) Wood had an absolute
obligation to repay the contents invoice, and (c) Carpet Tech charged interest that
2
exceeded the maximum allowed by law.” The maximum, according to them, was 6%
per annum. We overrule the issue.
As argued by the Woods, they had to prove 1) the existence of a loan of money
or extension of credit, 2) an absolute obligation to repay the principal, and 3) the
exaction of greater compensation than that allowed by law for the borrower’s use of the
money or credit.2 First Bank v. Tony’s Tortilla Factory, 877 S.W.2d 285, 287 (Tex.
1994). It is the second element that we address.
An absolute obligation to pay connotes the absence of any contingency. See
Anglo-Dutchman Petroleum Int’l, Inc. v. Haskell, 193 S.W.3d 87, 96-97 (Tex. App.—
Houston [1st Dist.] 2006, pet. denied) (stating that “appellees’ right to recover their
principal and any return on their investment was contingent upon Anglo-Dutch’s cash
recovery, if any, in the Halliburton lawsuit” which meant that “[p]er the unambiguous
terms of the agreements, Anglo-Dutch did not have an absolute obligation to repay the
principal amounts that appellees invested.”). In other words, if the obligation to pay is
contingent, it is not an absolute one. Id.; Wagner v. Austin Sav. & Loan Ass’n, 525
S.W.2d 724, 730-31 (Tex. Civ. App.—Beaumont 1975, no writ) (holding that there was
no usury since repayment was dependent upon the occurrence of various
contingencies, one of which encompassed the installation of the utilities in accordance
with governing ordinances); Pansy Oil Co. v. Federal Oil Co., 91 S.W.2d 453, 457 (Tex.
Civ. App.—Texarkana 1936, writ ref’d) (holding that there was no usurious transaction
because repayment of any amount under said contract or the arrangement rested on
contingencies of, first, drilling and, second, producing minerals in paying quantities).
2
We make no comment on whether such elements must be established in every claim of usury.
Because the Woods argued that they applied here and attempted to show that those elements were
proven, we address whether they met the burden.
3
The record before us shows that the Woods executed a “Repair & Pay
Authorization” provided by Carpet Tech before initiation of the work. The document
apparently reflects aspects of the agreement between the parties. A portion of it
specified that the Woods understand “that the full amount for the services provided will
be due upon completion.” (Emphasis added). The record further reveals that they
made payments to Carpet Tech as the work progressed. However, those payments
eventually stopped. They did so, according to the trial court, “. . . because [they]
maintained that several parts of the jobs were improperly performed or not completed.”
The trial court also found that Carpet Tech had “failed to fully perform under the
agreement. . . .” No one disputes those findings. Nor do the Woods question the
verbiage of the “Repair & Pay Authorization.” And, looking at that language again, it is
clear that the Woods’ obligation to pay Carpet Tech was contingent upon Carpet Tech
completing, or performing, its duties. So, there is some evidence of record upon which
a rational factfinder could conclude that the Woods had no absolute obligation to pay
monies demanded by Carpet Tech, especially when they and the trial court actually
believed Carpet Tech did not fully perform. So, they did not prove their claim of usury,
as a matter of law, as argued. See Torres v. McCann, No. 13-15-00187-CV, 2016 Tex.
App. LEXIS 6079, at *15 (Tex. App.—Corpus Christi June 9, 2016, no pet.) (mem. op.)
(stating that “[i]f sufficient evidence was presented such that ‘reasonable minds could
differ about the fact determination to be made by the jury,’ then appellants are not
entitled to judgment as a matter of law”). And, when the entire record is considered, we
cannot say that the trial court’s decision to reject the usury claim was contrary to the
overwhelming weight of the evidence so as to render the decision manifestly wrong or
4
unjust. See Hardwick v. Smith Energy Co., No. 07-15-00083-CV, 2016 Tex. App.
LEXIS 6805, at *4-5 (Tex. App.—Amarillo June 27, 2016, no pet.) (stating that when a
party raises the claim of factual insufficiency, we consider all the evidence and set aside
the finding only if the evidence supporting the finding is so weak or so against the
overwhelming weight of the evidence that the finding is clearly wrong and unjust).
Issue Two — Damages
Next, the Woods aver that the trial court’s finding of no damages lacks the
support of both legally and factually sufficient evidence. We disagree.
The trial court entered a factual finding and legal conclusion directly pertaining to
the damages. In the former, it ruled that with respect to the “estimated amounts to
repair or complete the construction portion of the agreement,” the Wood’s expert “failed
to provide any evidence that these amounts were reasonable or necessary.” Although
the witness “recited that the amounts were customary or reasonable,” neither he nor the
Woods “offer[ed] additional evidence to show any basis or support for the
reasonableness of [the] amounts.” Through the conclusion of law, it held that the
Woods “failed to provide legally sufficient evidence to support any damage.” Our effort
to assess whether this finding and conclusion are accurate begins with a brief
discussion about the law of damages applicable to the breach of construction contracts.
There are two ways to measure damages for breaching such an agreement.
One involves remedial damages which are determined by “the cost to complete or
repair less the unpaid balance on the contract price.” McGinty v. Hennen, 372 S.W.3d
625, 627 (Tex. 2012); CCC Group, Inc. v. South Cent. Cement, Ltd., 450 S.W.3d 191,
200 (Tex. App.—Houston [1st Dist.] 2014, no pet.). The other measure is known as the
5
“difference-in-value damages” or damages represented by the difference between the
value of the building as constructed and its value had it been constructed according to
the contract. McGinty v. Hennen, 372 S.W.3d at 627.
Where the first measure (i.e. remedial damages) is used, as here, the party
seeking relief must prove that the damages sought were reasonable and necessary. Id.
To do so demands more than merely proffering evidence illustrating the nature of the
injuries, the character of and need for the services rendered, and the amounts charged
for the services. Id. “Instead, some other ‘evidence showing that the charges are
reasonable’ is required.” Id., quoting, Dallas Ry. & Terminal Co. v. Gossett, 156 Tex.
252, 294 S.W.2d 377, 383 (Tex. 1956). While one need not have a witness utter the
buzzwords “reasonable and necessary” to satisfy the test, CCC Group, Inc. v. South
Cent. Cement, Ltd., 450 S.W.3d at 200, simply uttering those words is not enough
either. See Nigalye v. Orr, No. 11-12-00003-CV, 2013 Tex. App. LEXIS 11247, at *10-
11 (Tex. App.—Eastland August 30, 2013, no pet.) (mem. op.) (stating that “we do not
agree that the evidence conclusively proves that $2,479,220.89 was the reasonable and
necessary cost to complete the construction of the home” because the party seeking
damages presented no evidence “of what work had to be performed . . . to complete the
construction of the home as originally designed . . . [and] . . . other than Orr’s and
Simpson’s conclusory testimony that the costs were reasonable and necessary,
Appellants did not present any specific evidence explaining how [they] determined that
the costs were reasonable and necessary.”); see also Dilston House Condo Ass’n v.
White, 230 S.W.3d 714, 718 (Tex. App.—Houston [14th Dist.] 2007, no pet.) (involving
an award of attorney’s fees and stating that general statements of reasonableness are
6
insufficient); Silverberg v. Texas Commerce Bank, N.A., No. 01-95-00564-CV, 1996
Tex. App. LEXIS 3348, at *21 (Tex. App.—Houston [1st Dist.] 1996, no pet.) (involving
an award of attorney’s fees and holding that conclusory statements in an affidavit are
insufficient to defeat summary judgment and a general statement that the fee amount
sought is reasonable and necessary will not support a finding of reasonableness). As
indicated in Nigalye, there must be evidence explaining how or why the expense was
reasonable and necessary. Nigalye v. Orr, supra. Requiring the latter is no more than
heeding the directive in Houston Unlimited, Inc. v. Mel Acres Ranch, 443 S.W.3d 820
(Tex. 2014). There we were told that if the basis for an expert opinion is missing or the
basis actually provides no support for the opinion, then the opinion is a mere conclusory
statement lacking in evidentiary value. Id. at 829. This is so because the evidentiary
value of an expert’s testimony comes “from the basis [of his opinion], not from the mere
fact that the expert said it.” Id.
With the foregoing in mind, we turn to the record before us. No doubt it contains
testimony from an expert explaining what repairs or construction he thought needed to
be done due to the breach by Carpet Tech. They included 1) “[r]emoval and
replacement of exterior siding per foot of ‘pine or equal’ siding and paint and caulk at
$8.50 @ 1,581 sq. ft.= $13,438,” 2) “[w]idening of the garage opening and installation of
18 foot door, paint and finish out $4,200,” 3) “[r]einstall interior 21 foot glass wall $8,000-
$12,000,” 4) “[i]nterior repairs including paint, repair of paneling, repair cigarette
damage on the mantle, close open space under sink, and miscellaneous $1,500-
$3,000,” 5) “[r]eplace or repair windows $1,500-$3,000,” 6) “[r]oof repair $1,000-$5,000,”
7) “[f]loor vents $500-$1,000,” 8) “[d]emolition of existing area and re-install kitchenette
7
in 4th bedroom $10,000,” and 9) “[o]verhead and profit = 20%.” When asked, the
witness also testified that the charges or range of costs mentioned were “reasonable
and customary.” And, when asked about the price range applicable to the listed tasks,
he said normally if the work to be done was not as extensive as he may have thought,
then the lower number would be appropriate or the cost would be less. That alone may
lead a factfinder to reasonably deduce that some of the work factored into his estimate
may not be necessary or that the expert may not have known about the extent of work
actually needed.
Nor can one easily ignore the difference between the sum depicting the lower
range and that depicting the higher. In many cases the higher amount was twice that of
the lower. That again could be viewed, by the factfinder, as casting doubt on what
repairs were actually needed.
Most importantly, though, is the general absence of information regarding how he
derived either the lower or higher number or any number between them. Whether they
generally reflected the average costs of materials or labor in the area or anywhere else
is unknown. Nor was their evidence explaining (or providing a reasonable estimate of)
the amount of materials needed to complete the work, the cost of the materials
themselves, the quantum of manpower needed, and the cost of that manpower.3 In
3
For instance, the estimate for removing and replacing exterior siding was $13,438, according to
the expert. The sum was derived by multiplying 1,581 sq. ft by $8.50 a sq. ft. One would think that the
$8.50 a foot charge encompassed the cost of materials and labor. But, the expert did not explain what
portion of the sum constituted the materials and what constituted labor. Nor did he explain why the costs
of materials and labor implicit in the amount was reasonable. The same is true regarding the $1500-
$3000 estimate for interior repairs. While he may have mentioned various components factored into the
sum (e.g. 3 people working for 3 days at $50 and hour), he did not describe why or explain how the
number of hours to be expended or the charge was reasonable. Nor did he discuss the materials to be
used, their cost, and why that cost is reasonable. As acknowledged in McGinty, explaining how the figure
was derived does not itself necessarily make the figure reasonable. McGinty v. Hennen, 372 S.W.3d
625, 628 (Tex. 2012).
8
other words, the basis for the dollar figures to which the expert opined is missing. Like
the situation in Nigalye, no one explained “how [the expert] determined that the costs
were reasonable and necessary.” Consequently, the expert’s opinions about the sums
being “reasonable and customary” are mere conclusions and, therefore, no evidence,
and no other evidence fills the void.4
The trial court did not err in finding that no evidence illustrated that the damages
sought by the Woods were reasonable and necessary. There being no evidence of the
matter, it cannot be said that the evidence contradicting the trial court’s finding was so
overwhelming as to merit a new trial. So, the Woods satisfied neither burden imposed
by the standards of review applicable to claims of legal and factual insufficiency.
Each issue is overruled, and the judgment is affirmed.
Brian Quinn
Chief Justice
4
This is not a situation where proof of damage was tendered via affidavit provided by § 18.001 et.
seq of the Texas Civil Practice and Remedies Code. Our decision is not intended to address those cases
holding that a mere statement that damages are reasonable and necessary is enough when the
statement is uncontroverted. See e.g. Cactus Well Serv., Inc. v. Energico Prod., No. 02-13-00186-CV,
2014 Tex. App. LEXIS 12573, at *22 (Tex. App.—Fort Worth November 29, 2014, pet. denied) (mem. op.)
(holding that “Knight’s affidavit, which was uncontroverted and verified that Cactus’s charges and services
were reasonable and necessary, was ‘sufficient evidence to support a finding of fact by judge or jury that
the amount charged was reasonable or that the service was necessary” per § 18.001(b) of the Texas Civil
Practice and Remedies Code).
9