IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
DIVISION ONE
C & R ELECTRIC, INC., ) No. 73464-4-1 , U)
)
Respondent, )
CD,
) -41 ,
v. ) CD
rr,
) rn
T.R.J. DEVELOPMENT, INC., ) . r-
TERENCE RAYMOND JOHNSON, ) UNPUBLISHED OPINION cp
-rt=,
)
Appellant. ) FILED: March 20, 2017
)
VERELLEN, C.J. — Terence Johnson appeals the grant of summary judgment in
favor of C & R Electric, Inc. for breach of contract and lien foreclosure. Johnson
contends that there are genuine issues of material fact and that the trial court abused its
discretion in granting attorney fees. Because there is no dispute of material fact
whether Johnson entered into a time and materials contract with C & R, we affirm.
Johnson failed to preserve his challenge to attorney fees and may not raise his
objection for the first time on appeal.
FACTS
Terence Johnson owns commercial real property located at 21104 International
Boulevard in SeaTac. C & R, a licensed and bonded electrical contracting company,
performed work on Johnson's property related to electrical power for a paint booth and
other unrelated electrical repairs. When Johnson failed to pay for the work, C & R
No. 73464-4-1/2
recorded a mechanics' lien against the property. Thereafter, C & R filed a lawsuit
against Johnson seeking a monetary judgment based on breach of contract. C & R also
sought to foreclose the lien.
The trial court granted C & R's motion for summary judgment on its breach of
contract claim and entered judgment against Johnson for $7,506.30, the principal
amount of the work completed, plus $1,506.70 in interest. The court also awarded
C & R a lien against the property in the amount of $3,626.01 for the electrical repairs
unrelated to the paint booth project. The court did not award a lien for the work related
to the paint booth because it found an issue of fact existed whether the work constituted
an improvement to real property. The court awarded C & R $20,000 in attorney fees
and $1,883.84 in costs.
Johnson appeals.
ANALYSIS
Motion for Summary Judgment
Johnson argues the trial court erred in granting summary judgment because
there are genuine issues of material fact whether he entered into a contract with C & R.
We disagree.
When reviewing a grant of summary judgment, an appellate court undertakes the
same inquiry as the trial court) We consider the facts and all reasonable inferences in
the light most favorable to the nonmoving party.2 Summary judgment is appropriate "if
1 Beaupre v. Pierce County, 161 Wn.2d 568, 571, 166 P.3d 712(2007).
2 Fulton v. Dep't of Soc. & Health Servs., 169 Wn. App. 137, 147, 279 P.3d 500
(2012).
2
No. 73464-4-1/3
the pleadings, depositions, answers to interrogatories, and admissions on file, together
with the affidavits, if any, show that there is no genuine issue as to any material fact and
that the moving party is entitled to a judgment as a matter of law.m3 "A genuine issue of
material fact exists if reasonable minds could differ about the facts controlling the
outcome of the lawsuit."4
The moving party can satisfy its initial burden under CR 56 by demonstrating that
it is entitled to a judgment as a matter of law.5 Once there has been an initial showing
of the absence of any genuine issue of material fact, the party opposing summary
judgment must respond with more than conclusory allegations, speculative statements,
or argumentative assertions of the existence of unresolved factual issues.6 "An adverse
party may not rest upon mere allegations or denials"7 but must instead set forth
"specific facts which sufficiently rebut the moving party's contentions and disclose the
existence of a genuine issue as to a material fact.'"5
In support of its motion for summary judgment, C & R submitted a declaration
from C & R president Marc Gartin. The Gartin declaration explains that in April 2013,
3 CR56(c); White v. State, 131 Wn.2d 1, 9, 929 P.2d 396(1997)(quoting
Marincovich v. Tarabochia, 114 Wn.2d 1271, 274, 787 P.2d 562(1990)).
4 Barkley v. Greenpoint Mortg. Funding, Inc., 190 Wn. App. 58, 65, 358 P.3d
1204 (2015), review denied, 184 Wn.2d 1036 (2016).
5 Young v. Key Pharms., Inc., 112 Wn.2d 216, 225 n.1, 770 P.2d 182(1989).
6 Rucker v. Novastar Mortg., Inc., 177 Wn. App. 1, 10, 311 P.3d 31(2013)
(quoting Seven Gables Corp. v. MGM/UA Entm't Co., 106 Wn.2d 1, 13, 721 P.2d 1
(1986)).
7 McBride v. Walla Walla County, 95 Wn. App. 33, 36, 975 P.2d 1029(1999);
CR 56(e).
8 Ranger Ins. Co. v. Pierce County, 164 Wn.2d 545, 552, 192 P.3d 886 (2008)
(quoting Meyer v. Univ. of Wash., 105 Wn.2d 847, 852, 719 P.2d 98(1986)).
3
No. 73464-4-1/4
Johnson unexpectedly appeared at C & R's office. Gartin met with Johnson, who
frantically explained that he needed an electrician to complete work on a freestanding
paint booth at the property because the City of Seattle had "red-tagged" it for having no
electrical permit.
Gartin explained that C & R could obtain an electrical permit for Johnson and
perform the work on a "time and materials" basis, meaning it would "charge all the time
for electricians on an hourly basis, as well as all materials used on the project."9 Gartin
informed Johnson that the work "would not be cheap," because Gartin personally knew
the SeaTac electrical inspector, who would "demand absolute strict compliance for any
electrical contractor performing work on the paint booth project."19 According to Gartin,
Johnson agreed to the "terms while he sat in my office."11
After the meeting, C & R sent one of its electricians to the property to meet with
the city electrical inspector "and ascertain specifically all the work and materials
required to perform the job."12 Per Johnson's request, C & R also had a representative
present for each inspection made by the city. C & R completed the work on the paint
booth and successfully obtained an electrical permit and final approval by the city
electrical inspector.
During the course of C & R's work on the paint booth, Johnson's property was
vandalized. Someone apparently stole copper wire, resulting in severe damage to the
9 Clerk's Papers(CP)at 176.
19 CP at 176-77.
11 CP at 177.
12 CP at 177.
4
No. 73464-4-1/5
property's entire electrical service. Johnson asked C & R to replace the stolen copper
wire and perform other necessary electrical repairs. C & R agreed and then completed
the work requested. C & R sent four invoices to Johnson, totaling $7,506.30. Three of
the invoices were for the work performed on the paint booth and totaled $3,880.29.
Gartin expressly stated the fourth invoice "is related only to the work" for the electrical
repairs in the amount of $3,626.01.13
C & R therefore satisfied its initial burden under CR 56 of demonstrating that it
was entitled to judgment as a matter of law.
Johnson submitted two declarations opposing summary judgment: one from
himself and the other from Antonio Miranda, a tenant who leased a portion of the
property to operate his company T&C Auto. The Johnson declaration is narrowly
crafted. It makes no mention of the April 2013 meeting and only vaguely refers to the
electrician who came to the property to determine the scope of the work:
C&R came to the site and met with Antonio and me and looked at
the scope of the work[.] Contrary to Marc Gartin's Declaration that C&R
believed and at some point apprised me that this would be a major project,
they understood they were basically reviewing my work done to power
T&C's paint booth. C&R must have seen the work as a casual, minor job
since Mr. Gartin never presented or discussed any terms of an agreement
or prices for labor and materials. . . .
... As I stated, there had never been any discussion of price,
hourly rates, value of work, or other terms of agreement and there was no
agreement, verbal or written, between C&R and either TR,1[141 or T&C.(151
13 CP at 178.
14 Johnson owned TRJ Development, Inc. before it dissolved in 2014.
15 CP at 91-92(emphasis added).
5
No. 73464-4-1/6
Johnson's vague statements of no discussion of price, hourly rates, value of
work, or other terms of agreement are not adequate cause to create a question of fact.
Johnson does not deny the April 2013 meeting with Gartin, or that he himself reached
an agreement with C & R to obtain the electrical permit and perform the work on a time
and materials basis. Rather, he denies there was a specific agreement as to the hourly
rate for the labor and the specific costs of materials. But "[o]ne common type of
contract between owners and general contractors is called a time and materials
contract. This contract provides for a contract price based on the actual cost of both the
labor and the materials."16 Such a contract for time and materials is an adequate
contract.17 C & R could properly later calculate the reasonable cost of the labor and the
materials.
Likewise, Miranda's declaration did not deny the occurrence of the April 2013
meeting:
C&R became involved in finishing up the work and inspections of
the booth . . . because the electrical inspector had changed and [Johnson]
was unable to get the needed electrical permit. . . to complete the booth
installation work. It became clear that even though there was a right to
such a permit, it would "go much faster" according to the SeaTac City
16 33 MATTHEW KING, WASHINGTON PRACTICE: CONSTRUCTION LAW MANUAL § 9:1,
at 164(2008)(footnote omitted).
17 See 17A Am. JUR. 2D Contracts § 477(2016)("Where a contract makes no
statement as to the price to be paid, the law invokes the standard of reasonableness,
and the fair value of the services or property is recoverable."). See also 1 JOSEPH M.
PERILLO, CORBIN ON CONTRACTS § 4.4, at 581 (rev. ed. 1993)("An agreement is not
unenforceable for lack of definiteness of price or amount if the parties specify a
practicable method by which the amount can be determined by the court without any
new expression by the parties themselves.); id. at 586 ("[T]he fact that one of the parties
reserves the power of fixing or varying the price or other performance is not fatal if the
exercise of this power is subject to prescribed or implied limitations, as that the variation
must be in proportion to some objectively determined base or must be reasonable or in
good faith.").
6
No. 73464-4-1/7
Attorney if an electrical contractor were used to inspect and to make sure
the work already done was adequate and to perform a few remaining
items. C&R Electric was the contractor used and, in a brief meeting on
site, they were shown such work as needed to be done. I was present at
the meeting.. ..
The work on the booth was very minor [in] scope and amount of
work.. . . No contract, verbal or written, nor prices for time and materials
were ever discussed. There was just a general agreement that C&R
would oversee the minor amount of work that remained to be done. C&R
never gave me an owner's notice or contract, discussed price terms with
me, or gave me an estimate of the cost of its work.[191
Although Miranda "felt sure that everyone involved knew they were doing this work to
benefit me, as the building's tenant,"19 there is nothing in either declaration opposing
summary judgment to indicate C & R was ever told that Miranda was solely responsible
for paying for the work.
Both the Johnson and Miranda declarations failed to set forth any specific facts to
sufficiently rebut C & R's contention that Johnson entered into a time and materials
agreement in April 2013.
Johnson also argues the trial court erred in granting C & R summary judgment
because material issues of fact exist "regarding the amount owing for the copper wire
repair."2° But in Gartin's declaration, he explained:
Throughout the course of the work by C&R at the Property, it
provided four invoices to Terry Johnson totaling $7,506.30. It is
noteworthy that the first of the four invoices (i.e., Invoice No. 28502),
outlining the hourly charges for a journeyman electrician as well as costs
of certain materials, was sent on April 26, 2013 (i.e., soon after C&R
started the work). After receiving the invoice, Terry Johnson did not
mention any problem, allowed the work to proceed and as mentioned
18 CP at 65-66.
18 CP at 64.
20 Appellant's Br. at 12.
7
No. 73464-4-1/8
above, even asked C&R to repair the electrical service which was
damaged during the alleged burglary. . . . It should also be mentioned that
one of the four invoices (Invoice No. 28607), is related only to the work for
the above described electric service repair for the entire Property and not
the paint booth project(21J
Johnson speculates that some items listed in the fourth invoice (Invoice 28607) were
related to the paint booth, but failed to rebut Gartin's express statement to the contrary.
Therefore, the trial court correctly granted summary judgment in favor of C & R
for breach of contract and lien foreclosure.
Attorney Fees and Costs
Johnson challenges the trial court's award of attorney fees and costs to C & R.
He argues C & R did not provide the trial court with adequate information to perform the
required lodestar calculation. He also argues the trial court failed to enter any findings
of fact to support the award and failed to segregate the attorney fees between non-lien
and lien claim fees. But none of these objections were raised before the trial court.
In C & R's motion for summary judgment, it sought attorney fees and costs.
C & R attorney Stephan Wakefield submitted a supporting declaration that included his
and his paralegal's hourly rates, a general discussion of the extensive work involved
(including Johnson's chapter 13 bankruptcy), and his statement that $20,000 in total
fees had been incurred. Johnson did not object to the hourly rates, lack of detailed
itemization, or lack of segregation between non-lien and lien claim fees. He raised no
objections in his opposition to summary judgment or during the hearing on the summary
judgment motion.
21 CP at 178(emphasis added).
No. 73464-4-1/9
In moving for reconsideration, Johnson's only objection was to "delete any
mention of attorney fees at this time, as there was no mention of them in the courtns
oral ruling."22 In Johnson's declaration supporting reconsideration, he reiterated that the
written order did not reflect the court's oral ruling: "As the court's oral ruling was silent
regarding attorney's fees, the order should state the issue of fees is reserved for trial,
pending possible settlement, or an agreement to arbitrate."23
Generally, this court will not consider issues not presented to the trial court.24
Specifically, objections related to attorney fees should not be raised for the first time on
appea1.25 Even on reconsideration, Johnson's only suggestion was that an award of
fees was premature, an issue he has not raised on appeal. In the absence of any
objection or argument in the trial court on the grounds raised for the first time on appeal
regarding attorney fees, Johnson has failed to preserve his challenges to the amount of
attorney fees or segregation of fees. Therefore, those issues are not properly before
us.26
22 CP at 144.
23 CP at 150.
24 Washburn v. Beatt Equip. Co., 120 Wn.2d 246, 290, 840 P.2d 860(1992).
25King County v. Guardian Cas. & Guar. Co., 103 Wash. 509, 514-15, 175 P.
166(1918)(question regarding authority for fees should not be considered for the first
time on appeal); Bierce v. Grubbs, 84 Wn. App. 640, 645, 929 P.2d 1142(1997)(fee
issue could not be raised for first time on appeal); Draper Mach. Works, Inc. v. Hagberg,
34 Wn. App. 483, 488,663 P.2d 141 (1983)(challenge to amount of fees could not be
raised for first time on appeal).
26 See RAP 2.5(a).
9
No. 73464-4-1/10
Appellate Fees
C & R requests an award of attorney fees on appeal. Under the lien foreclosure
statute, the court "may allow the prevailing party in the action... as part of the costs of
the action,... attorneys'fees and necessary expenses incurred by the attorney in the
superior court, court of appeals, supreme court, or arbitration, as the court... deems
reasonable."27 Accordingly, C & R is entitled to reasonable attorney fees and costs on
appeal related to the lien foreclosure and subject to compliance with RAP 18.1(d).
Affirmed.
WE CONCUR:
27 RCW 60.04.181.
10