STATE OF VERMONT
ENVIRONMENTAL COURT
}
Glebe Mountain Wind Energy, LLC } Docket No. 234‐11‐05 Vtec
(Appeal of JO #2‐227) }
}
Revised
Decision on Cross‐Motions for Summary Judgment
Glebe Mountain Wind Energy, LLC (“Appellant” or “GMWE”) appealed from
Jurisdictional Opinion (JO) #2‐227 of the Acting District 2 Environmental Coordinator,
issued on October 6, 2005, concluding that a “proposed wind energy project
represent[s] material and substantial changes to existing Act 250 permits and thus
require[s] an [Act 250 permit] amendment.” Appellant is represented by Christopher
D. Roy, Esq.; Interested Person Glebe Mountain Group, Inc. (GMGI) is represented by
Robert E. Woolmington, Esq.; Interested Person Vermont Electric Power Co. (VELCO) is
represented by Stephen A. Reynes, Esq.; Interested Person Central Vermont Public
Service (CVPS) is represented by Carolyn Brown Anderson, Esq.; Interested Person
Town of Windham and Intervenor Town of Windham Planning Commission are both
represented by David Grayck, Esq.; Intervenor Department of Public Service (DPS) is
represented by Aaron Adler, Esq.; Intervenor Natural Resources Board is represented
by Melanie Kehne, Esq.; and Intervenor Windham Regional Planning Commission is
represented by Richard D. Perra, Esq.
Now pending before this Court are cross‐motions for summary judgment filed
by Appellant, by Interested Person Glebe Mountain Group, Inc., and jointly by
Interested Person Town of Windham and Intervenor Town of Windham Planning
Commission. Intervenor Windham Regional Commission also filed a motion for
summary judgment, advising that it joined in the motion filed on behalf of Glebe
1
Mountain Group, Inc. Memoranda in support of Appellant’s motion for summary
judgment have been filed on behalf of VELCO and DPS.
Factual Background
The parties have stipulated to the material facts in this case, which are as follows:
1. Appellant is developing plans for a wind power generation facility on
Glebe Mountain in the Towns of Londonderry and Windham (the “Project”).
2. The Project includes the construction of up to twenty‐seven wind turbines
and associated roads and accessory structures.
3. The Project is proposed to be located on two parcels of land (the “Tract”)
owned by the McGraw Family Partnership and Magic Mountain, LLC. The Tract, or
portions of it, is encumbered by a number of Act 250 permits and amendments
previously issued to other projects on the same parcels. There are five sets of permits
and amendments thereto, dating back to 1971. The various permits are referenced in JO
#2‐227, at ¶¶ 12–36.
4. Appellant has installed one temporary wind measurement tower on the
Project site. This tower was approved by the Vermont Public Service Board (PSB)
pursuant to 30 V.S.A. § 248(j) on January 29, 2004, in PSB Docket No. 6786. In that
proceeding, on October 8, 2004, the PSB also approved the installation of two additional
temporary wind measurement towers on the Project site. These two additional towers
have not yet been installed.
5. The Project is an “electric generation facility” subject to review by the PSB
pursuant to 30 V.S.A. § 248.
6. Appellant has not finalized the project’s design, and has not yet filed a
petition for a certificate of public good with the PSB pursuant to 30 V.S.A. § 248.
7. Appellant sent the Windham Regional Planning Commission and the
Towns of Londonderry and Windham a formal notice of intent to file a petition for a
certificate of public good with the PSB pursuant to 30 V.S.A. § 248.
2
8. The Parties have agreed by stipulation, for the purposes of this appeal
only, that if the analysis typically employed under Environmental Board Rule 34 were
to apply to the Project as currently planned, it can be assumed that the Project would
constitute a material and/or substantial change to the previously approved
development on the Project site under one or more Act 250 criteria found in 10 V.S.A. §
6086.
Discussion
At issue in this appeal is a jurisdictional conflict between Act 250 review under a
concept known as “amendment jurisdiction,” see former Environmental Board Rule 341
(EBR 34), and PSB jurisdiction over power generation facilities under 30 V.S.A. § 248.
The conflict arises because a power generation facility is being proposed on lands that
are already encumbered by multiple Act 250 permits, amendments thereto and the
many conditions contained therein.2
It is undisputed that if the wind power generation facility were proposed on land
unencumbered by Act 250 permit conditions, then jurisdiction over the proposed
facility would rest solely with the PSB. Electric generation or transmission facilities that
require a certificate of public good under 30 V.S.A. § 248 are defined out of the term
1 The former Environmental Board Rules have been supplanted by the Act 250 Rules promulgated by the
Natural Resources Board, effective May 1, 2006. We look to the former Environmental Board Rules as
they existed on October 6, 2005, because we are required to apply the substantive standards that were
applicable before the tribunal appealed from, pursuant to 10 V.S.A. § 8504(h). The Legislature ratified
former EBR 34, along with all other Environmental Board rules pertaining to the administration of Act
250, by Public Act 52, § 5 (1985), and the Rule therefore “has the same effect as would any law passed by
the Legislature in the first instance.” In re Spencer, 152 Vt. 330, 336 (1989).
See Vermont Commission on Wind Energy Regulatory Policy: Findings and Conclusions, Attach. A to
2
Appellant’s Mot. for Summ. J., at § 4.2.1(7):
There are conflicting opinions and there is currently no definitive answer for how to deal
with the potential for overlapping jurisdiction between Section 248 and Act 250 (e.g., on
land that already falls under an existing Act 250 permit). For example, some wind
turbines may be proposed on lands that are already subject to the jurisdiction of Act 250
with permit conditions that may be difficult to resolve without going through two
regulatory processes. Section 248 should have jurisdiction in these cases but provide for
consideration of the existing Act 250 permit conditions.
3
“development” by 10 V.S.A. § 6001(3)(D)(ii), and therefore do not trigger Act 250
jurisdiction.
The question before the Court is not whether the Project constitutes
“development” under Act 250 (as it clearly does not), but whether the Project will cause
material or substantial changes to previously permitted development, and thus require
the holders of the pre‐existing permits to seek a permit amendment under EBR 34. EBR
34(A), effective January 12, 2004, required a permit amendment “for any material or
substantial change in a permitted project.”
Appellant argues that, although EBR 34 would require a permit amendment “if
the analysis typically employed . . . were to apply,” Stipulation of Facts at 2, that
requirement would be at odds with the Legislature’s grant to the PSB of exclusive
jurisdiction over § 248 projects. Appellant reasons that since power generation facilities
do not constitute development in the context of Act 250, the construction of such
facilities cannot trigger amendment jurisdiction under EBR 34 because “material or
substantial change,” as that term is used in EBR 34, is a subset of “development.” See
EBR 2(A)(1)(e) (“‘Development’ means . . . (e) Any construction of improvements which
will be a substantial change of a pre‐existing development, and any material or
substantial change to an existing development over which the board or a district
commission has jurisdiction”). Intervenor DPS offered its concurrence at the motion
hearing by asserting that amendment jurisdiction is a derivative of development
jurisdiction and not an independent source of jurisdiction.
The consequence of the argument expounded by Appellant and the DPS is that if
the District Commission is deprived of development jurisdiction over power generation
facilities, then the Commission is likewise deprived of amendment jurisdiction over
those facilities.
Interested Person GMGI opposes Appellant’s interpretation. GMGI agrees that
Act 250 jurisdiction is not triggered by the construction of power generation facilities,
4
but argues that when the construction of those facilities creates a material or substantial
change to an existing development encumbered by an Act 250 permit, then Act 250
review of the changes to the pre‐existing development is required.
The plain language of EBR 34 and § 248 do not provide an answer. Neither
statutory provision specifically addresses the situation at bar: that is, construction of a
§ 248 project on lands already encumbered by Act 250 permit conditions. In resolving
this jurisdictional conflict, our task is to “discern and implement the intent of the
Legislature.” In re MacIntyre Fuels, Inc., 2003 VT 59, ¶ 7. District Commission
jurisdiction over development and PSB jurisdiction over power generation facilities are
both in derogation of common law property rights, and therefore both must be strictly
construed. See Committee to Save Bishop’s House, Inc., 137 Vt. 142, 152 (1979) (“The
court’s true function is to give effect to the legislative intent, and in this endeavor, we
are guided by rules of general applicability, evolved through long judicial experience.
One of these is that legislation in derogation of common law property rights will be
strictly construed.”).
We conclude that EBR 34 represents an explanation of and not an expansion
from the statutory jurisdiction granted to District Commissions. The “amendment
jurisdiction” set out in EBR 34 is the lawful interpretation of existing Act 250
jurisdiction, which does not extend to the “construction of improvements for an electric
generation or transmission facility that requires a certificate of public good under
section 30 V.S.A. § 248.” 10 V.S.A. § 6001(3)(D)(ii).
Interested Person the Town of Windham and Intervenor the Town of Windham
Planning Commission argue in their joint motion for summary judgment that “where
land is subject to an Act 250 permit, a permit amendment is required under Board Rule
34 for otherwise exempt activity—such as logging3 or farming—where such activity is a
The site preparation and construction for the proposed facility would involve tree‐cutting on the top of
3
Glebe Mountain.
5
substantial or material change to the permit or permitted project,” This argument by the
Town and its Planning Commission relies upon the Environmental Board’s analysis in
Re: Keith Van Buskirk d/b/a/ American Wilderness Resources, Inc., Declaratory Ruling
No. 302, Findings of Fact, Conclusions of Law, and Order (Aug. 15, 1995).4 In Van
Buskirk, the Environmental Board, noting that logging activities below the elevation of
2,500 feet are excluded from the definition of development, went on to state that the
“[a]pplication of the logging exclusion to Van Buskirk’s operations does not end the
jurisdictional inquiry. The logging exclusion does not absolutely prohibit the assertion
of Act 250 jurisdiction over the cutting of trees [below 2,500 feet] . . . . A competing
consideration is the Board’s (or district commission’s) authority to impose conditions
when granting Act 250 permits.” Id. at 8. The Environmental Board found an exception
to the logging exclusion, ruling that:
Where findings of fact or conditions regarding tree cutting or logging are
included in a permit, or a representation is made that no tree cutting or
logging will take place, tree cutting or logging which constitutes a
material or substantial change to that permitted development or
subdivision will only be allowed if the permit holder applies for a[n
amendment to their] permit under EBR 34.
Id. at 9.5
The situation in Van Buskirk is distinguished from the case before this Court by
the fact that in Van Buskirk, the timber harvesting would come under Act 250
amendment jurisdiction, or under no jurisdiction whatsoever. The Board stated that
“[t]he policy behind the exception to the logging exclusion is that logging and tree
cutting associated with a development or subdivision has adverse effects with respect to
4
In a recent decision, In re Green Crow Corp., 2006 VT 14, our Supreme Court stressed the “specialized
expertise of the Environmental Board in determining whether it has jurisdiction over a particular
development proposal.” Id. at ¶ 7 (internal quotation omitted), citing In re Denio, 158 Vt. 230, 235 (1992).
5 The Board did not order that Van Buskirk apply for a permit under EBR 34, but only because it found
that no such findings, conditions, or representations were present in the case.
6
the ten criteria of 10 V.S.A. § 6086(a).” Id. An absolute exclusion for logging, then,
could cause harm to the very values sought to be protected by Act 250. Here, however,
it is not a question of “Act 250 jurisdiction or nothing.” The excluded activity,
construction of an electric generation facility, is subject to the jurisdiction of the PSB,
which is required to conduct an environmental review, with due consideration to the
applicable Act 250 criteria, pursuant to 30 V.S.A. § 248.
Section 248(a)(2) states that “(A) no company . . . and no person . . . may begin
site preparation for or construction of an electric generation facility or electric
transmission facility within the state which is designed for immediate or eventual
operation at any voltage, . . . (B) . . . unless the public service board first finds that the
same will promote the general good of the state and issues a certificate to that effect.”
30 V.S.A. § 248(a)(2). When a petitioner files an application for a certificate of public
good with the PSB, the PSB “shall hold a nontechnical public hearing” under 30 V.S.A.
§ 248(a)(4)(A), and one or more technical hearings under 30 V.S.A. § 248(a)(4)(B). The
statute requires further that copies of the application:
shall be given by the petitioner to the attorney general and the department
of public service, and, with respect to facilities within the state, the
department of health, agency of natural resources, historic preservation
division, scenery preservation council, state planning office, agency of
transportation, the agency of agriculture, food and markets and to the
chairperson or director of the municipal and regional planning
commissions and the municipal legislative body for each town and city in
which the proposed facility will be located.
30 V.S.A. § 248(a)(4)(C).
Pursuant to 30 V.S.A. § 248(a)(4)(E), the Agency of Natural Resources:
shall appear as a party in any proceedings held under this subsection,
shall provide evidence and recommendations concerning any findings to
be made under subdivision (b)(5) of this section, and may provide
evidence and recommendations concerning any other matters to be
determined by the board in such a proceeding.
7
Section 248(b)(5) provides the basis for Appellant’s claim here that the PSB has
exclusive jurisdiction over all electric power generation projects. Section 248(b) requires
the PSB to make a number of findings before issuing a certificate of public good.
Prior to 1987, § 248(b)(5) required the PSB to find that the construction of an in‐
state electric power generation facility “will not have an undue adverse effect on
aesthetics, historic sites, air and water purity, the natural environment and the public
health and safety.” In 1987, the Legislature amended § 248(b)(5)6 by adding the phrase
“with due consideration having been given to the criteria specified in 10 V.S.A.
§ 1424a(d).”7 In 1988, the Legislature again amended § 248(b)(5)8 by adding the phrase
“and § 6086(a)(1) through (8) and (9)(K).”
As it exists now, and at the time of the appealed‐from JO, § 248(b)(5) reads as
follows:
Before the public service board issues a certificate of public good as
required under subsection (a) of this section, it shall find that the
purchase, investment or construction: . . . with respect to an in‐state
facility, will not have an undue adverse effect on esthetics, historic sites,
air and water purity, the natural environment and the public health and
safety, with due consideration having been given to the criteria specified
in 10 V.S.A. § 1424a(d) and § 6086(a)(1) through (8) and (9)(K)[.]
The phrase “due consideration” also appears in § 248(b)(1), requiring that due
consideration be given to the recommendations of municipal and regional planning
commissions, recommendations of municipal legislative bodies, and the land
conservation measures contained in Town Plans.
6 1987, No. 67 (Adj. Sess.), An Act Relating to Establishing a Comprehensive State Rivers Policy (H. 339).
7 Section 1424a(d) provides a non‐exclusive list of fourteen criteria that may be considered by the water
resources panel (at that time the water resources board) when deciding whether particular waters should
be designated as outstanding resource waters.
8 1988, No. 273, An Act Relating to Act 250 Jurisdiction over Waste‐Burning Electricity Generating
Facilities (H. 681).
8
The “due consideration” language of § 248(b)(1) was interpreted by our Supreme
Court to mean that those recommendations and land conservation measures were
“advisory rather than controlling.” City of South Burlington v. Vermont Electric Power
Co., 133 Vt. 438, 447 (1975) (“‘Due consideration’ for municipal legislative bodies . . . at
least impliedly postulates that municipal enactments, in the specific area, are advisory
rather than controlling . . . . Any attempt at municipal regulation is pre‐empted.”).
The Legislature was presumably aware of the meaning ascribed to the phrase
“due consideration” when it added that phrase to § 248(b)(5) in 1987 and 1988, see
Heffernan v. Harbeson, 2004 VT 98, ¶9 (“When we interpret statutes, we presume that
the Legislature was mindful of relevant precedents and prior legislation.”). It is
abundantly clear that the Legislature intended that the PSB have exclusive jurisdiction
over electric generation facilities proposed on previously unencumbered land, as
evidenced by the language excluding electric generation facilities from the definition of
development, combined with the language empowering the PSB to grant certificates of
public good “with due consideration” to Act 250 Criteria 1–8 and 9(K). It is less clear,
however, that the Legislature intended that pre‐existing Act 250 jurisdiction would
disappear when an electric generation facility is proposed on land encumbered by Act
250 permit conditions.
Where the plain statutory language is not clear, the Court endeavors to give
effect to the legislative intent underlying the statute by looking at “the legislative
history and circumstances surrounding its enactment, and the legislative policy it was
designed to implement.” MacIntyre at ¶ 7 (internal quotation and citation omitted).
The pertinent legislative history includes a meeting of the Senate Natural Resources and
Energy Committee held on March 13, 1988, at which the Committee heard testimony
relating to H. 681, which was enacted later that year as 1988, No. 273, An Act Relating to
9
Act 250 Jurisdiction over Waste‐Burning Electricity Generating Facilities (H. 681).9 This
Act added the phrase “and § 6086(a)(1) through (8) and (9)(K)” at the end of § 248(b)(5).
The hearing began with the testimony of Representative Emmons, who
explained that questions regarding environmental review of waste‐to‐energy plants,
wood‐fired plants, and gas pipelines were raised during discussions on H. 681:
Rep. Emmons: When we started working on this, we were dealing
with the Act 250 and the Environmental Board and also the Public
Service Board . . . . Environmental issues would be covered under
the Environmental Board in their Act 250 review. We had the
chairman of the Environmental Board, Lon Wilson, and the Public
Service Board, Rich Cowart, in our committee discussing this,
and they worked out a compromise which seemed to be more
workable, that under Public Service Board review—the 248
process—the environmental aspects of that would be expanded to
include Act 250 criteria 1–9.
Appellant’s Attach. D at 2–3. Representative Emmons then outlined the structure of the
House bill, and answered questions posed by Senator Racine, the Chairman of the
Natural Resources and Energy Committee:
Rep. Emmons: [Subsection 5] on page 5 is where we include the Act
250 review. 10 V.S.A. Section 1424[a] and Section 6086, 1–8 and 9,
that’s your criteria 1–10 of Act 250 and that’s where . . . . the
compromise was between the Environmental Board and the Public
Service Board—to include Act 250 review and 248 review. . . .
Sen. Racine: Would they need an Act 250 permit?
Rep. Emmons: No. The certificate of public good is what
they’re going for and that’s exactly the reason, Mr. Chairman, that
we did incorporate the Act 250 process for our 248 review so it
would not be duplicative.
9
A transcript of the hearing was provided to the Court as Attach. D to Appellant’s Mot. for Summ. J.
10
Sen. Racine: I don’t understand what you’re saying, you’re
incorporating the process. You aren’t requiring a 250 permit, but
you’re requiring a 250 review? How will that work?
At this point there is a gap in the transcript with the notation “break to turn tape
over.” Some testimony, including Rep. Emmons’ answer, appears to be missing. When
the transcript resumes, PSB Chair Rich Cowart and Senator Carter have joined in the
dialog:
. . .
Mr. Cowart: It10 would apply to any Section 248 permit which
would include electric transmission lines as well—electric
generating station, electric transmission lines, gas line, anything
that needed Section 248 review.
. . .
Sen. Carter: Can I go back and ask a question which ties in? I
notice that you’ve got NEPA involved here as well. Why do we
exclude Criterion 10 on laterals which deals with compliance with
local and regional plans?
Mr. Cowart: I’ll be glad to answer that. There’s already a section
in 248 which requires the [Public Service] Board to give due
consideration to local and regional plans.
Sen. Carter: I realize you have to give due consideration to it, but
you don’t have to make a finding that it complies.
Mr. Cowart: Correct.
Sen. Carter: I guess I’m asking the question still why you phrased
it that way.
Mr. Cowart: Why did we choose to go with due consideration
rather than compliance with local plans?
Sen. Carter: Yes.
Mr. Cowart: The chief reason for doing that is that—first of all, the
history of it in 248 was that the facilities that provide those utility
services to the state are an integrated network, and it has always
Presumably, the compromise by which the PSB would undertake the environmental review normally
10
conducted by the Environmental Board.
11
been thought to be unwise to allow a single jurisdiction (inaudible)
to put up a roadblock as part of a network.
Sen. Carter: I understand that. Is this a sign that the state, in fact,
is pre‐empting local and regional jurisdiction with respect to
control of the location of these pipelines?
Mr. Cowart: That has always been the case.
Sen. Carter: Does this extend to secondary impacts?
Mr. Cowart: No.
Appellant’s Attach. D at 4–8.
It is not absolutely clear what Senator Carter meant by “secondary impacts,”11
but it is at least plausible that he was referring to situations like that discussed one year
later by our Supreme Court in In re Southview Associates, 153 Vt. 171 (1989), where the
Court upheld the Environmental Board’s denial of a permit application to build a
residential development in a deeryard, stating that the “proposed project would destroy
ten acres of critical habitat and, through the secondary impacts of people living in the
homes, imperil the remaining 34 acres.” Id. at 178. It is also not clear whether Mr.
Cowart was stating that PSB § 248(b) jurisdiction did not extend to secondary impacts
prior to the proposed amendment, but would so extend if H. 681 were enacted, or
11 There is some evidence that the Legislature intended that the PSB have exclusive jurisdiction over
secondary impacts. Mr. Cowart testified that a “fact of life we have to deal with is that we don’t have
statewide or regional comprehensive land use planning to reassure us that we have the capability to
manage the secondary effects of infrastructure as significant as the pipeline. So what can we do? Well,
this bill attempts to do the best we can with what we’ve got right now.” Appellant’s Attach. D at 23.
More to the point, the testimony of Mr. Parenteau, then the Commissioner of the Department of
Environmental Conservation, includes this statement: “The logic of [the shift in control to the PSB] is that
you will have an expert board who will understand the full picture of the pipeline, the laterals, the
mainline, secondary impacts, environmental concerns, growth concerns and all the rest. But I do want to
stress that I have not looked at this language or these criteria with a view towards could they be
improved from the standpoint of secondary impacts. It may well be that they could. I don’t know if the
language needs to be changed, though.” Id. at 40. The legislative record presented to the Court in this
appeal does not reveal an adoption or a rejection by House and Senate members of the witness testimony
offered by Messrs. Cowart and Parenteau.
12
whether he was stating that PSB jurisdiction would not extend even if H. 681 were
enacted.
Later in the hearing on H. 681, the testimony turns to the concept of “one‐stop
shopping” for permit approval. Mr. Cowart continues his testimony as follows:
Question: where should review lie? And this goes back to the beginning
of Act 250, and as you all know, the Legislature determined—and I think
it was a good decision—that electric generating facilities and transmission
facilities would not be subject to Act 250 review because the Public Service
Board was going to review, and they did not want two‐stop shopping.
They wanted one‐stop shopping. And everybody knew that the Public
Service Board was going to have to review the financing of the facility, the
way it’s located and connected to the network, the system reliability issues
that are related to the location of the network, whether transmission
facilities are adequate to service a generating station, whether the
company is going to have adequate catch [sic “cash”] flow and its effect on
rates. The Public Service Board is going to be reviewing all of those
things, and it didn’t make any sense to the Legislature to have the
Environmental Board or the district environmental commission on a
different track doing environmental review. Consequently, there was
language added to Section 248—very broad language—that required the
Public Service Board to conduct an environmental review of those
facilities at the same time that they were conducting these other reviews,
the financial and system reviews.
Appellant’s Attach. D at 16–17.
The “broad language” to which Mr. Cowart was referring is the first portion of
§ 248(b)(5), which establishes the following standard of review: “with respect to an in‐
state facility, [the project] will not have an undue adverse effect on esthetics, historic
sites, air and water purity, the natural environment and the public health and
safety . . . .” Mr. Cowart went on to state that the PSB viewed this language as giving it
an environmental mandate “as broad and more flexible” than the mandate in Act 250,
and that the PSB “looked at the criteria of Act 250 in order to be informed as to what the
broad language of Section 248 meant.” Appellant’s Attach. D at 17. Mr. Cowart then
13
noted that the phrase “due consideration having been given to the criteria specified in
10 V.S.A. § 1424a(d)” had been added in the previous year (1987), and stated that “we
proposed [the language in the House bill] adding specifically the cross references to the
appropriate sections of Act 250.” Id. at 18.
It appears from the record presented to us that Mr. Cowart viewed the addition
of the phrase “and § 6086(a)(1) through (8) and (9)(K)” as merely codifying the existing
practice of the PSB, as he stated that “I view this as an improvement because it will
codify what has been the unspoken practice in most cases that come before the PSB,
which is that the PSB will look at Act 250 in order to determine whether the general
umbrella language about the natural environment and the public health and safety has
been met.” Id. at 20.
Mr. Cowart then returned to the concept of one‐stop as opposed to two‐stop
permit shopping:
At one point I was discussing one‐stop versus two‐stop shopping and
why I think that it is preferable to keep this review at the PSB rather than
having an Environmental Board review and a PSB review. First, as I said,
all on the system stability and economic factors, we’re going to have that
review in any event so you would have a dual track. You’d have the
environmental review going off over here and the financial review going
on over here. Now that raises an immediate coordination problem, not
just in timing. It’s a burden on everybody. It’s a burden on citizens who
want to oppose a facility. It’s a burden on local select boards and
planning commissions who have got to go to two sets of hearings. It’s a
burden on the applicant. It takes longer. I don’t think it’s worth it. But
there’s an even more fundamental problem. As you’ve seen with Vicon,
over on the environmental side every time you change the litigation [sic
“mitigation”] requirement, you change the economics of the project. You
better install a new scrubber. You’ve got to change your ash disposal
methods; you’ve got to do something over here. All of a sudden your
finances are different, and the terms of any contract that you’ve got for the
sale of your power is going to be different. So the idea that you can
somehow segregate these things in their two different worlds is just not
reality. I think it’s a lot more sensible to keep them in the same place.
14
Id. at 20–21.
Interested Person VELCO asserts that “[b]ecause [10 V.S.A.] § 6001(3)(D)(ii)
excludes electric generation and transmission facilities that require a [certificate of
public good], Act 250 jurisdiction does not apply to such facilities regardless of whether
they would constitute a material or substantial change to existing development.”
VELCO Mem. in Support of Appellant’s Mot. for Summ. J. at 11. We agree. Such
facilities are carved out of Act 250 jurisdiction by the plain language of the statute.
There are strong policy arguments, upon which the record establishes that the
Legislature relied, supporting the sole jurisdiction of the PSB over such facilities, chief
among them is the wisdom of having one statewide board handle the integrated electric
generation and transmission network, so that no single local body can put up a
roadblock. Also, the PSB has an institutional memory and an ever‐growing body of
knowledge regarding the cases it oversees, in contrast to local or regional boards which
would have to reinvent the wheel with every case.
We would like to minimize any confusion or misinterpretation that our decision
here may create, but are concerned that any further comments on “secondary impacts,”
would cause this Court to breach its jurisdictional limits. We therefore leave the
consideration of possible future scenarios to a future proceeding, as they are not a case
or controversy before us here.
Accordingly, based on the foregoing, it is hereby ORDERED and ADJUDGED
that Appellant’s motion for summary judgment is GRANTED as to Question 1 in
Appellant’s Revised Statement of Questions. In so ruling, we conclude that Act 250
jurisdiction under ERB 34 does not attach to electric generation facilities that are located
on lands encumbered by pre‐existing Act 250 permits. For these same reasons,
Interested Person GMGI’s motion for summary judgment is DENIED as to Question 1
in Appellant’s Revised Statement of Questions.
15
As to Question 2 in Appellant’s Revised Statement of Questions, Appellant’s
motion is GRANTED to the extent that it refers to the PSB’s exclusive jurisdiction over
all impacts within the boundaries of the subject facility. However, Appellant’s motion
is DENIED to the extent that it refers to secondary impacts beyond the established
boundaries of the proposed § 248 facility. We deny that part of Appellant’s motion for
the reason that such impacts are not properly before this court and therefore do not
constitute a case or controversy for which this court has authority to rule. See Cupola
Golf Course, Inc. v. Dooley, 2006 VT 25, ¶ 11 (stating that “the judiciary is not
empowered to render advisory opinions. Courts are not permitted to dispose of the
merely hypothetical.”). For these same reasons, the various summary judgment
motions filed on behalf of Interested Persons GMGI and Town of Windham and
Intervenors Town of Windham Planning Commission and Windham Regional Planning
Commission are also DENIED as to Question 2.
Because we have adjudicated all of Question 1, and that part of Question 2 that
presents an actual case or controversy to us, and because no other Questions are
contained in Appellant’s Statement of Questions, this decision concludes the
proceedings before this Court in this appeal. A Judgment Order accompanies this
decision.
Done at Berlin, Vermont this 3rd day of August, 2006.
__________________________________________
Thomas S. Durkin, Environmental Judge
16