STATE OF VERMONT
ENVIRONMENTAL COURT
}
In re: Appeal of Ben Kernan } Docket No. 121-6-00 Vtec
}
Decision and Order on Motion to Reconsider and Motion to Strike
Appellant appealed from a decision of the Planning Commission of the City of
Burlington granting a Certificate of Appropriateness to Main Street Landing Company for a
project at 50 Lake Street. Appellant is represented by Carl H. Lisman, Esq.; Appellee Main
Street Landing Company is represented by Gordon C. Gebauer, Esq.; Interested person
Jack Long, Esq., an attorney, has appeared and represents himself; the City is
represented by Kimberlee J. Sturtevant, Esq.
Motion to Reconsider December 4, 2000 Order
After the order issued on December 4, 2000, Appellee-Applicant elected to proceed
by a V.R.A.P. 5.1 collateral final order appeal because the ruling conclusively determines
the disputed question of Appellant=s standing and resolves that important issue completely
separate from the merits of the action, and the issue of Appellant=s standing could be
effectively unreviewable on appeal from a final judgment, if the final judgment is in
Appellee-Applicant=s favor. Appellant objected to Appellee-Applicant=s being allowed to
pursue a collateral final order appeal while the remainder of the merits of the case goes
forward in this Court, instead of being required to take the V.R.A.P. 5(b) interlocutory
appeal route for which it had asked. However, the route of appeal should be determined
by the nature of the question and the most expeditious way of resolving the entire case.
Therefore, the Court declines to change its December 4, 2000 order. Appellee-Applicant
has elected to pursue its appeal as a V.R.A.P. 5.1 collateral final order appeal; Appellant
will be free under that rule to ask the Supreme Court to reject it as improvidently granted.
Motion to Strike
Appellee-Applicant has also moved to strike Questions 1, 2, 4 and 5 of the
Statement of Questions. As the hearing on the merits of this appeal is now set for January
1
4 and January 11, it is necessary to resolve this motion so that the parties may prepare for
the hearing.
Appellant failed to appeal the Zoning Board of Adjustment=s grant of approval of this
project as a Amajor impact development@ under Articles 3, 5, 13 and 17 of the Zoning
Ordinance. Therefore, any issues resolved by the ZBA=s decision and not independently
within the purview of the Planning Commission are precluded from consideration under 24
V.S.A. '4472(d).
Question 1, regarding whether sufficient notice was given of the Planning
Commission=s hearings on this application, might have been suitable for summary
judgment, as it seems to be primarily a legal issue. However, the motion to strike that
question is DENIED (without prejudice to the legal issue=s being litigated in the merits of
the proceeding), because nothing in the ZBA=s decision addressed the adequacy of notice
for the Planning Commission hearings, and therefore it has no preclusive effect on this
issue.
Question 2, regarding whether the project complies with the 50-foot height limit in
'5.3.18(c)(2), is precluded by the unappealed ZBA ruling that the project satisfies the
criteria in Articles 3, 5, 13, and 17 of the Zoning Ordinance. The motion to strike Question
2 is GRANTED. The Planning Commission, and hence this Court in this proceeding, has
no jurisdiction over Article 5. We note, however, that the Planning Commission had
responsibility under Article 6 (both under the general design review criteria of '6.1.10 and
the special waterfront design review criteria of '6.1.11) to determine whether the building
meets those criteria, and that issue remains before the Court in Question 3. That is, a
building which meets the height limitations of Article 5 may nevertheless in a particular
instance fail to meet certain of the view protection criteria of Article 6.
Question 4, regarding whether the parking waiver was properly granted, is also
precluded by the unappealed ZBA ruling, and therefore the motion to strike Question 2 is
GRANTED. While the Planning Commission had responsibility under '7.1.6(b) to examine
the adequacy of parking independently of the propriety of the waiver, we note that that
issue was not raised by the Statement of Questions.
Question 5, regarding whether the project complies with the criteria in Article 13, is
precluded by the unappealed ZBA ruling that the project satisfies the criteria in Articles 3,
2
5, 13, and 17 of the Zoning Ordinance. The motion to strike Question 5 is GRANTED. The
Planning Commission, and hence this Court in this proceeding, has no jurisdiction over
Article 13.
The merits hearing will begin on January 4, 2001, as scheduled, and remains
scheduled to continue on January 11 if necessary. However, in light of the present ruling, if
the parties agree that the hearing will not exceed one full day and if they prefer to hold the
hearing only on January 11, 2001, they may so inform the Court, preferably on or before
December 28, 2000. If they wish another pretrial conference, it can be scheduled by
phone for December 27, 2000, or in person at the Chittenden District Court on December
28, 2000.
Done at Barre, Vermont, this 18th day of December, 2000.
_________________________________________________
Merideth Wright
Environmental Judge
3