NOTICE: This opinion is subject to motions for reargument under V.R.A.P. 40 as well as formal
revision before publication in the Vermont Reports. Readers are requested to notify the Reporter
of Decisions by email at: JUD.Reporter@vermont.gov or by mail at: Vermont Supreme Court, 109
State Street, Montpelier, Vermont 05609-0801, of any errors in order that corrections may be made
before this opinion goes to press.
2018 VT 39
No. 2017-133
In re Korrow Real Estate, LLC Supreme Court
Act 250 Permit Amendment Application
(State of Vermont, Appellant) On Appeal from
Superior Court,
Environmental Division
November Term, 2017
Thomas S. Durkin, J.
Thomas J. Donovan, Jr., Attorney General, and Kyle H. Landis-Marinello, Assistant
Attorney General, Montpelier, for Appellant.
L. Brooke Dingledine of Valsangiacomo, Detora & McQuesten, P.C., Barre, and
David L. Grayck of Law Office of David L. Grayck, Montpelier, for Appellee.
PRESENT: Reiber, C.J., Robinson, Eaton and Carroll, JJ., and Wesley, Supr. J. (Ret.),
Specially Assigned
¶ 1. EATON, J. The District 5 Commission denied Korrow Real Estate LLC’s as-built
application for an Act 250 permit to construct a barn on property alongside the Dog and Stony
Brook Rivers, finding the project failed to comply with Act 250 Criteria 1(D) and 1(F). In doing
so, the Commission construed key terms as defined by the Agency of Natural Resources (ANR).
On appeal, the Environmental Division reversed the decision and remanded the matter to the
Commission with instructions to grant an as-built permit for the project. The Vermont Natural
Resources Board now appeals the court’s decision, asserting that the court failed to accord proper
deference to the ANR’s statutory authority and expertise, and that the project fails to comply with
the necessary Act 250 permitting criteria. We affirm in part, and reverse and remand in part.
I. Facts and Procedural History
¶ 2. By way of background, appellee, Korrow Real Estate LLC (Korrow), owns
properties off Vermont Route 12A in the Town of Northfield, on either side of Stony Brook Road.
On the northerly side of Stony Brook Road is an improved parcel of land that hosts offices for
Gillespie Fuels and Propane, a business related to Korrow. In 2011, Korrow began constructing a
large barn on a parcel of land on the southerly side of Stony Brook Road. Korrow intended to use
the barn to house Gillespie propane trucks. As built, the barn is roughly 8000 square feet, and sits
at the confluence of the Dog River and the Stony Brook River. After the project was complete in
the summer of 2012, Korrow brought dry pack onto the property to level the parking area inside
the barn. Korrow also brought a small amount of earthen fill to level areas outside the barn.
Portions of this fill were placed in proximity to the nearby rivers. Prior to building the barn and
bringing in the fill, Korrow sought and received a municipal zoning permit. However, Korrow
constructed these improvements without first obtaining an Act 250 permit, which is required for
development of this kind. It was not asserted this omission was intentional.
¶ 3. In 1970, the Vermont Legislature passed Act 250 to protect and conserve
Vermont’s lands and environment, and to ensure that land use would not be detrimental to the
public welfare and interests. 1969, No. 250, § 1 (Adj. Sess.); see generally 10 V.S.A. §§ 6001-
6111. Act 250 requires a land-use permit before certain development can occur. 10 V.S.A.
§ 6081(a) (“No person shall . . . commence development without a permit.”). “Development”
means, in relevant part, “[t]he construction of improvements for commercial or industrial purposes
on more than one acre of land within a municipality that has not adopted permanent zoning and
subdivision bylaws.” Id. § 6001(3)(A)(ii). Korrow’s project is a “development” subject to Act
250 because it is a commercial project constructed on a 6.5-acre parcel in a municipality that has
2
not adopted permanent zoning and subdivision bylaws. As such, the Korrow project requires an
Act 250 permit to remain as built on the property site.
¶ 4. When Act 250 applies to development, a permit can only issue if the project
complies with all ten Act 250 criteria. Id. § 6086(a)(1) (outlining conditions and criteria necessary
for project development). These criteria specifically address development on or near waterways
and rivers. Id. On appeal, the parties dispute whether the Korrow project complies with Act 250
Criterion 1(D), pertaining to development within the “floodway” and “floodway fringe” of nearby
waters, and Criterion 1(F), pertaining to development on “shorelines.” Id. § 6086(a)(1)(D), (F).
These provisions of Act 250 aim to protect Vermonters from the hazards of flooding and erosion,
and to preserve the scenic and recreational features of rivers and their shorelines. Id. An applicant
for an Act 250 permit, such as Korrow, bears the burden of proving compliance with both Criterion
1(D) and Criterion 1(F). Id. § 6088(a).
¶ 5. To determine project compliance with Criterion 1(D), the threshold question is
whether the project is in the “floodway” or “floodway fringe” of a nearby waterway; if it is, then
the applicant must prove that the project will not “restrict or divert the flow of flood waters,” and
“significantly increase the peak discharge of the river,” and “endanger the health, safety and
welfare of the public or of riparian owners during flooding.” Id. § 6086(a)(1)(D)(i), (ii).
¶ 6. Similarly, Criterion 1(F) requires a threshold determination as to whether the
project is located on a “shoreline.” Id. § 6086(a)(1)(F). If so, shoreline development “must of
necessity be located on a shoreline” and must be conducted in a manner that “will, insofar as
possible and reasonable”: (1) retain shorelines and waters “in their natural condition”; (2) allow
continued and recreational access to the waters; (3) provide screening between the development
and the river; and (4) “stabilize the bank from erosion, as necessary, with vegetation cover.” Id.
§ 6086(a)(1)(F)(i)-(iv).
3
¶ 7. Act 250 provides definitions for the terms “floodway, “floodway fringe,” and
“shoreline”:
(6) “Floodway” means the channel of a watercourse which is
expected to flood on an average of at least once every 100 years and
the adjacent land areas which are required to carry and discharge the
flood of the watercourse, as determined by the Secretary of Natural
Resources with full consideration given to upstream impoundments
and flood control projects.
(7) “Floodway fringe” means an area which is outside a floodway
and is flooded with an average frequency of once or more in each
100 years as determined by the Secretary of Natural Resources with
full consideration given to upstream impoundments and flood
control projects.
....
(17) “Shoreline” means the land adjacent to the waters of lakes,
ponds, reservoirs, and rivers. Shorelines shall include the land
between the mean high water mark and the mean low water mark of
such surface waters.
10 V.S.A. § 6001(6), (7), (17) (emphases added). These provisions expressly grant the ANR
authority to define the scope of the “floodway” and “floodway fringe.” Id. § 6001(6), (7). If the
ANR determines that a project falls within the “floodway” or “floodway fringe,” then the project
must also comply with additional Criterion 1(D) specifications to receive permit approval. 10
V.S.A. § 6086(a)(1)(D)(i)-(ii) (requiring project will not “restrict or divert the flow of flood
waters,” and “significantly increase the peak discharge of the river,” and “endanger the health,
safety and welfare of the public or of riparian owners during flooding”).
¶ 8. The Natural Resources Board (NRB) has statutory authority to adopt rules
pertaining to Act 250 permit applications. 10 V.S.A. § 6025(b) (“The Board may adopt substantive
rules . . . that establish criteria under which applications for permits under this chapter may be
classified in terms of complexity and significance of impact under the standards of subsection
6086(a) of this chapter.”). The NRB has adopted such a rule defining “shoreline” for the purpose
of determining compliance with Criterion 1(F). Act 250 Rules, Rule 2(C)(20),
4
http://nrb.vermont.gov/sites/nrb/files/documents/2015%20Adopted%20Rules.pdf [https://perma.
cc/4G79-LLZY] [hereinafter NRB Rule]. NRB Rule 2(C)(20) defines “shoreline” as follows:
For purposes of 10 V.S.A. § 6086(a)(1)(F), a project involves the
“development or subdivision of shorelines,” if:
(a) the project involves construction on or the use of “the land
between the mean high water mark and the mean low water mark of
such surface waters.” 10 V.S.A. § 6001(17), or
(b) the project, or an element of the project which is adjacent to the
shoreline, has the potential for significant impact on any of the sub
criteria specified in 10 V.S.A. § 6086(a)(1)(F)(i)-(iv).
¶ 9. With these definitions in mind, we return to Korrow’s application to the District
Commission for an as-built Act 250 permit. Applications for an Act 250 permit are filed with the
District Commission to determine compliance with Act 250 criteria, including Criterion 1(D) and
Criterion 1(F) discussed above. 10 V.S.A. § 6083(a) (“An application for a permit shall be filed
with the District Commission as prescribed by the rules of the [Natural Resources] Board . . . .”).
In the application at issue, Korrow indicated the project involved “development or subdivision on
or near a river, lake, pond or reservoir shoreline.” The Commission heard testimony from an ANR
expert regarding the project’s potential impacts on the Dog and Stony Brook Rivers, and evaluated
the project’s compliance with Act 250 Criteria 1(D) and 1(F).
¶ 10. Regarding Criterion 1(D), the ANR calculated the scope of the “floodway” and
“floodway fringe” and determined that the Korrow project fell within the Act 250 “floodway.” To
calculate the scope of the “floodway,” the ANR adhered to its “Technical Guidance for
Determining Floodway Limits Pursuant to Act 250 Criterion 1(D).” Agency of Nat. Res.,
Technical Guidance for Determining Floodway Limits Pursuant to Act 250 Criterion 1(D)
(October 9, 2009), http://www.docket7970.com/ANR/Attachment%20A.ANR.VGS.RTP.1-
3%20(Nelson)/VT%20Technical%20Guidance%20for%20Determining%20Floodway%20Limit
s%20Pursuant%20to%20Act%20250%20Criterion%201(D).pdf [https://perma.cc/3YXE-
5
NQAL]. These guidelines, originally issued in 2003, were updated in 2009 to “enhance
understanding of the ANR Floodway Procedure” and ensure “clear, consistent, and broadly
accepted [ANR] floodway determinations.” Id. at 1. The document is public and provides general
background on how the ANR determines the “floodway” and “floodway fringe” when considering
Criterion 1(D). The guidelines recognize the role of erosion hazards in defining the Act 250
“floodway,” and require the ANR to “consider both inundation and fluvial erosion hazards . . . in
the Act 250 regulatory process.” Id. The ANR has stated that the guidelines’ procedure for
determining the Act 250 “floodway” surrounding an area “strikes an acceptable balance between
having a consistent set of guidelines to reduce inundation and erosion hazards while allowing
consideration of existing and future development . . . [and] remaining consistent with the science-
based stream equilibrium objective.” Id. at 2.
¶ 11. The guidelines state:
For the purpose of determining the inundation floodway under 10
V.S.A. § 6001(6), and the impacts of a project built in a floodway
under Criterion 1(D), Agency technical staff will consider the
regulatory floodway as defined by the Federal Emergency
Management Agency (FEMA) and [the National Flood Insurance
Program (NFIP)] regulatory standards.
Id. at 4. The guidelines clarify that the ANR may separately assess the geomorphology and erosion
hazards of a project site to determine the “fluvial erosion hazard” (FEH) area. The ANR may also
conclude that the FEH area applies “to lands that lie outside” the NFIP and FEMA designations.
Id. at 3-4. Since publishing the updated guidelines in 2009, the ANR has also issued a “River
Corridor Protection Guide,” which provides a more detailed description of the methodology and
data used to create the ANR FEH area. Both of these guidelines are instructive in understanding
how the ANR calculates the FEH area for a project. Notably, the FEH area can be within, or less
wide, than the inundation area mapped by the NFIP or FEMA, or it can be broader. “Upon
comparison” of these measurements—the ANR’s assessment of the FEH area and the NFIP/FEMA
6
designated area—“the Act 250 floodway limit shall be whichever laterally extends further from
the stream.” Id. at 4. Thus, the guidelines permit the ANR to expand the scope of the Act 250
“floodway” to align with the FEH area—even if the FEH area is broader than the NFIP or FEMA
measurements.
¶ 12. Pursuant to these guidelines, the ANR construes the Act 250 “floodway” as
encompassing the agency’s assessment of the FEH area, the NFIP-mapped areas, and FEMA-
designated portions of the Special Flood Hazard Area.
¶ 13. This construction by the ANR was critical to evaluating whether the Korrow project
was within the Act 250 “floodway.” Here, the ANR determined that “[m]uch of the existing barn,
fill, and proposed drainage . . . are located within the Act 250 Floodway” because these portions
of the project were constructed within the ANR’s FEH area. The ANR determined the project was
within the FEH area based on a geomorphic assessment of the project area, the project’s proximity
to the Dog and Stony Brook Rivers, and the potential for physical adjustments in the area. As
noted above, the guidelines allow the Act 250 “floodway” to expand to match the ANR’s definition
of the FEH area. Therefore, although the barn was located outside the NFIP-mapped area and the
FEMA-designated area, the Korrow project was within the ANR’s FEH area, and thereby within
the Act 250 “floodway.” Id. § 6001(6). After making the preliminary finding that the project was
within the “floodway,” the Commission assessed project compliance with § 6086(a)(1)(D)(i)-(ii),
and determined the project could not meet the Criterion 1(D) requirements as built. The
Commission ordered that the project be removed and relocated to comply with Criterion 1(D).
¶ 14. The Commission reached a similar conclusion regarding Criterion 1(F). Based on
recommendations from the ANR and the Department of Fish and Wildlife regarding the
preservation of riparian buffers—naturally vegetated areas bordering waterways—along the Dog
River and Stony Brook River, the Commission found the Project was located on a “shoreline,” id.
7
§ 6001(17), and required that the project be removed and relocated to comply with Criterion 1(F).
Id. § 6086(a)(1)(F). Korrow appealed the Commission’s order to the Environmental Division.
¶ 15. While recognizing the deferential standard generally applied to agency
interpretations of statutory provisions within their area of expertise, the Environmental Division
found the ANR’s construction of the “floodway” to be unreasonable in light of the project location
and testimony presented at the evidentiary hearing. The court determined the project was not
within a “floodway.” Despite this determination, the court made additional findings that the
project would not cause the adverse impacts for development within a floodway prohibited by
Criterion 1(D) even if the project was within the floodway. The court also found that the project
was not constructed on a “shoreline” and complied with the criteria listed in 10 V.S.A.
§ 6086(a)(1)(F)(i)-(iv). Ultimately, the court found that the project complied with Criteria 1(D)
and 1(F), reversed the Commission’s determinations, and remanded the proceedings to the
Commission to issue Korrow’s as-built Act 250 permit. This appeal followed.
¶ 16. On appeal, we address two issues: (1) whether the Korrow project complies with
Act 250 Criterion 1(D), pertaining to the project’s impact on the “floodway” and the “floodway
fringe”; and (2) whether the project complies with Criterion 1(F), pertaining to development on a
“shoreline.” 10 V.S.A. § 6086(a)(1)(D), (F). The parties dispute whether the ANR appropriately
calculated the scope of the “floodway” and “floodway fringe”; to what extent the court should
defer to the ANR’s definition of these terms; and whether the project was constructed on a
shoreline and, if so, whether the construction “of necessity” occurred on the shoreline. We
consider project compliance with Criteria 1(D) and 1(F) below.
II. Standard of Review
¶ 17. We review the court’s factual findings for clear error and its findings of law de
novo. In re Vill. Assocs. Act 250 Land Use Permit, 2010 VT 42A, ¶ 7, 188 Vt. 113, 998 A.2d 712
(“Under our standard of review, the Environmental Court determines the credibility of witnesses
8
and weighs the persuasive effect of evidence, and we will not overturn its factual findings unless,
taking them in the light most favorable to the prevailing party, they are clearly erroneous. We
review issues of law or statutory interpretation de novo.” (quotations and citations omitted)). We
will determine that a court’s factual findings are clearly erroneous in limited circumstances—“only
if they are supported by no credible evidence that a reasonable person would rely upon to support
the conclusions.” In re Zaremba Gr. Act 250 Permit, 2015 VT 88, ¶ 6, 199 Vt. 538, 127 A.3d 93.
In contrast, the court’s legal conclusions will be upheld “if they are reasonably supported by the
findings.” Id. (quotation omitted).
¶ 18. Thus, we review the court’s findings of fact—whether the project was within a
“floodway” and/or on a “shoreline”—for clear error, and its legal conclusions—whether the
project complied with Criteria 1(D) and 1(F) in light of its placement—de novo.
III. Project’s Compliance with Criterion 1(D)
¶ 19. Act 250 Criterion 1(D) requires applicants who are proposing project development
within the “floodway” or the “floodway fringe” of a body of water to demonstrate compliance with
certain requirements. See 10 V.S.A. § 6086(a)(1)(D)(i) (explaining that applicant must show
development within floodway “will not restrict or divert the flow of flood waters, and endanger
the health, safety and welfare of the public or of riparian owners during flooding”); id.
§ 6086(a)(1)(D)(ii) (explaining that applicant must demonstrate development within floodway
fringe “will not significantly increase the peak discharge of the river or stream within or
downstream from the area of development and endanger the health, safety, or welfare of the public
or riparian owners during flooding”). Determining whether a project triggers analysis under
Criterion 1(D) requires a preliminary finding that the project is located within a “floodway” or
“floodway fringe.” Id. § 6001(6), (7). Notably, the ANR has specific statutory authority to
determine the area comprising a “floodway” or “floodway fringe” pursuant to 10 V.S.A. § 6001(6)
and (7), and thus whether a project falls within those areas. See Zaremba Gr. Act 250 Permit, 2015
9
VT 88, ¶ 7 (“ANR has authority, pursuant to Act 250, to determine whether a particular project
will fall within a floodway. Moreover, at an Environmental Division trial, ANR may, as
intervenor, present evidence relevant to its expertise, which the Environmental Division may rely
upon in deciding the case.” (citation omitted)). Here, the parties dispute whether the Korrow
project was within the “floodway” or “floodway fringe,” and whether the Environmental Division
accorded the ANR proper deference in interpreting these terms.
¶ 20. Even when conducting an evidentiary hearing, the court owes deference to agency
interpretations of policy or terms when: (1) that agency is statutorily authorized to provide such
guidance; (2) complex methodologies are applied; or (3) such decisions are within the agency’s
“area of expertise.” See Plum Creek Me. Timberlands, LLC v. Vt. Dept. of Forests, Parks & Rec.,
2016 VT 103, ¶ 25, 203 Vt. 197, 155 A.3d 694 (explaining agency determinations regarding “the
proper interpretation of policy or methodology within the agency’s expertise are entitled to
deference, even where there is a de novo hearing within the superior court”); In re Woodford
Packers, Inc., 2003 VT 60, ¶ 12, 175 Vt. 579, 830 A.2d 100 (mem.) (deferring to agency
interpretation of “floodway” and “floodway fringe” in Act 250 permit proceeding because ANR
had authority to define terms based on plain language of statute).
¶ 21. While “[d]ecisions made within the expertise of such agencies are presumed
correct, valid, and reasonable,” the deference owed to agency determinations is not absolute. Plum
Creek Me. Timberlands, LLC, 2016 VT 103, ¶ 31. An agency’s authority to define terms within
its statutory purview will be given deference unless that authority is applied “arbitrarily and
capriciously” such that it “give[s] rise to a violation of due process.” Woodford Packers, Inc.,
2003 VT 60, ¶ 17. Agency determinations regarding complex methodologies are similarly entitled
to deference by the court, unless the opposing party can demonstrate the agency decision was
“wholly irrational and unreasonable in relation to its intended purpose.” Plum Creek Me.
Timberlands, LLC, 2016 VT 103, ¶ 28 (quotation omitted).
10
¶ 22. Here, the ANR had broad statutory authority and the relevant expertise to define
the “floodway” and “floodway fringe” surrounding the Dog and Stony Brooks Rivers, and the
ANR applied complex methodologies to define the scope of these areas. For these reasons, the
court owed deference to the ANR’s definitions of these terms. First, “[t]he plain language of the
statute states that the Secretary of ANR is authorized to make determinations as to what constitutes
a floodway or a floodway fringe.” Woodford Packers, Inc., 2003 VT 60, ¶ 12; 10 V.S.A.
§ 6001(6), (7). This statutory grant of authority alone signals that the court owed deference to the
ANR interpretations of these terms under our caslaw. Second, calculating the scope of these areas
requires the application of complex methodologies within the ANR’s area of expertise, as
demonstrated by the Technical Guidance document and River Corridor Protection Guide, to which
the court also owed deference. See Plum Creek Me. Timberlands, LLC, 2016 VT 103, ¶¶ 29-30
(explaining that, even in context of de novo hearing, “deference is due [when] the methodology
for determining compliance is an area over which [the agency] has broad statutory authority and
the relevant expertise”). Therefore, the Environmental Division owed deference to the ANR’s
interpretation of the terms “floodway” and “floodway fringe” in conducting its evidentiary hearing
unless the ANR’s construction of these terms was “arbitrarily and capriciously applied” such that
it “[gave] rise to a violation of due process.” Woodford Packers, Inc., 2003 VT 60, ¶ 17. A mere
disagreement with the ANR’s interpretation of those terms is insufficient to allow the
Environmental Division to substitute its own interpretation, especially in light of the broad
statutory authority given to the ANR in applying those terms. Plum Creek Me. Timberlands, LLC,
2016 VT 103, ¶ 30.
¶ 23. In this case, the ANR determined the Korrow project was within the Act 250
“floodway” based on the project’s location relative to the FEH area surrounding the Dog and Stony
11
Brook Rivers.1 This ANR determination was based on established practice derived from the
agency’s Technical Guidance document, which requires the ANR to conduct complex calculations
regarding the likelihood of flooding and erosion near the rivers at issue and the project site, and
the project’s potential impact on the area. The ANR presented detailed maps, exhibits, and expert
testimony to explain its methodology and outcomes. On appeal, the trial court found the ANR’s
interpretation of the “floodway” to be unreasonable because it disagreed with the ANR’s methods
for calculating the FEH area. Applying its own methodology, the court construed the term
“floodway” to encompass a smaller area, which did not include the Korrow project. Because the
court determined the project was not within a “floodway,” the court did not deem it necessary to
evaluate the project’s compliance with Act 250 Criterion 1(D).
¶ 24. The Environmental Division erred when it determined that the methodology
applied by Korrow’s expert, or the methodology of the court, was superior to that employed by the
ANR. Plum Creek Me. Timberlands, LLC, 2016 VT 103, ¶ 30. “We have cautioned that courts
are not a higher environmental agency entrusted with the power to make environmental law and
policy, but rather exercise a narrow role in ensuring that the decisions of ANR are made in
accordance with law.” Id. (quotations omitted). Where “questions about complicated
methodologies within the agency’s expertise” arise, “a reviewing court, even in the context of a de
novo hearing, must give deference to the agency’s decision.” Id. (quotation omitted).
¶ 25. Here, the Legislature granted the ANR express authority to construe “floodway”
under the relevant Act 250 provisions, this task is within the ANR’s area of expertise, and the ANR
measured the project’s compliance with Criterion 1(D) using complicated methodologies for
determining the “floodway” that are established practice within the agency. Absent a violation of
due process or evidence that the agency decision was arbitrary and capricious, the court should
1
See, supra, ¶¶ 12-14.
12
have deferred to the agency’s interpretation of the terms at issue and applied them when assessing
the project. There is no such violation or evidence here.2 The court’s failure to afford deference
to the ANR’s interpretation of terms that the Legislature expressly placed within the agency’s
statutory purview, were within the ANR’s area of expertise, and required complex methodologies
to discern, was error. Accordingly, we apply the ANR definitions of “floodway” and “floodway
fringe” on appeal.
¶ 26. In applying the ANR definition, we find that Korrow’s project was within the
“floodway” under 10 V.S.A. § 6001(6)—triggering analysis of project compliance with Act 250
Criterion 1(D).3 10 V.S.A. § 6086(a)(1)(D). Criterion 1(D)(i) specifies: “A permit will be granted
whenever it is demonstrated by the applicant that . . . development . . . within a floodway will not
restrict or divert the flow of flood waters, and endanger the health, safety and welfare of the public
2
The Environmental Division determined that the ANR definition of “floodway” was
unreasonable because the ANR’s calculation of the FEH area and stream sensitivity assessment
did not comport with the court’s view of the “natural lay” of the land adjacent to the Dog and
Stony Brook Rivers. The court used this rationale to delve into lengthy analysis under Chevron.
Chevron, U.S.A., Inc. v. Nat. Res. Def. Council, Inc., 467 U.S. 37 (1984). The fact that the court
disagreed with the ANR’s assessment is insufficient to demonstrate the ANR’s methodology was
unreasonable. In Woodford Packers, we explained that the ANR has the authority to define the
“floodway” and “floodway fringe” for the purpose of Act 250 Criterion 1(D), even when the ANR
alters its methodology for doing so. Woodford Packers, Inc., 2003 VT 60, ¶¶ 12-14 (“An agency
is not required to adopt rules or regulations to carry out what its authorizing statute specifically
directs it to do. While ANR’s alteration of its methodology for determining floodways may have
been a surprise to WPI—apparently the first applicant to undergo ‘fluvial geomorphology’
analysis—we cannot conclude that it lacked authority to do so.” (citation omitted)). The court
noted that, while “[s]tandardless alteration of ANR’s practice of determining floodways may give
rise to a violation of due process if arbitrarily and capriciously applied,” reliance on ANR
methodology is appropriate when such methods are “soundly grounded and supported by the
evidence.” Id. ¶ 17. Here, the ANR’s methodology for calculating the FEH area was an
established practice—it was not arbitrarily or capriciously applied to the Korrow project.
Moreover, the ANR provided ample support, including testimony, maps, and exhibits, to support
its interpretation of the Act 250 “floodway.” The ANR was well within its statutory bounds when
calculating the “floodway” here, and its authority should not have been usurped by the court.
3
Because the project is within the “floodway” under § 6001(6), it is not necessary to
address whether it is also within the broader scope of the “floodway fringe” under § 6001(7) or
analyze its compliance with § 6086(a)(1)(D)(ii), regarding development within the floodway
fringe.
13
or of riparian owners during flooding.” Id. § 6086(a)(1)(D)(i). Here, the court made findings of
fact sufficient to support its conclusion that the project’s construction within the floodway would
not “restrict or divert the flow of flood water” or “endanger the health, safety and welfare of the
public or riparian owners during flooding.”
¶ 27. The court does not owe deference to the Commission regarding its findings of fact
when conducting its own evidentiary hearing, and we will defer to the trial court’s findings of fact
unless they are clearly erroneous. Zaremba Gr. Act 250 Permit, 2015 VT 88, ¶ 6.
¶ 28. Even though the court erroneously found that the project was located outside the
“floodway,” there was sufficient evidence to support the trial court’s conclusion that the project
complied with Criterion 1(D). The court based this conclusion on “undisputed evidence at trial,”
which was put into context for the court by a site visit conducted prior to trial, that the Korrow
project was on “a significant upward slope” and therefore would not restrict or divert floodwater
movement in a manner that would endanger others. The court found that “the land rises” from a
“relatively flat area beside the river” up to the Korrow property. Witnesses at trial further testified
that the Korrow parcel had not flooded in the past fifty years, despite significant storms that have
caused recent flooding in the area, such as Tropical Storm Irene in 2011. One witness, who lives
downstream from the project, expressly stated that the barn did not “endanger” his safety due to
the project’s location:
[Attorney:] Q. Do you have any concern that there could be a flood
event that would cause you concern, danger, would endanger your
safety because that barn is located where it is?
[Neighbor:] A. No. Absolutely not.
The court noted “the historical significance of the Korrow parcel has been that it is where residents
have parked their vehicles and congregated to witness flooding events, without fear of being
washed away.” Additionally, a licensed professional engineer and land surveyor who visited and
evaluated the project site testified that the project would not divert or restrict the flow of
14
floodwaters or “endanger the health, safety, and welfare of the public or of riparian owners, during
flooding.”
¶ 29. Taking the evidence in the light most favorable to the prevailing party, Korrow, the
court’s factual findings that project construction will not “restrict or divert the flow of flood
waters” or “endanger the health, safety and welfare of the public or riparian owners during
flooding” are supported by “credible evidence that a reasonable person would rely upon to
support” the court’s conclusions. 10 V.S.A. § 6086(a)(1)(D)(i); Zaremba Gr. Act 250 Permit, 2015
VT 88, ¶ 6; Vill. Assocs. Act 250 Land Use Permit, 2010 VT 42A, ¶ 7. Based on these factual
findings, we conclude that, although the Korrow project was constructed within a “floodway,” the
project conforms with the requirements under Act 250 Criterion 1(D). 10 V.S.A. § 6086(a)(1)(D).
IV. Project’s Compliance with Criterion 1(F)
¶ 30. For the Korrow project to remain as developed, compliance with Criterion 1(D) is
not enough; if this project is within a shoreline, the project must also comply with Criterion 1(F),
which regulates development within shorelines. Under 10 V.S.A. § 6086(a)(1)(F):
A permit will be granted whenever it is demonstrated by the
applicant that . . . the development . . . of shorelines must of
necessity be located on a shoreline in order to fulfill the purpose of
the development or subdivision, and the development . . . will,
insofar as possible and reasonable in light of its purpose:
(i) retain the shoreline and the waters in their natural condition;
(ii) allow continued access to the waters and the recreational
opportunities provided by the waters;
(iii) retain or provide vegetation which will screen the development
or subdivision from the waters; and
(iv) stabilize the bank from erosion, as necessary, with vegetation
cover.
(Emphases added.)
¶ 31. Our first task is to clarify the definition of “shoreline.” Act 250 provision
§ 6001(17) defines “shoreline” as “the land adjacent to the waters of lakes, ponds, reservoirs, and
15
rivers. Shorelines shall include the land between the mean high water mark and the mean low
water mark of such surface waters.” Id. § 6001(17) (emphasis added).4 The Legislature also
authorized the NRB to adopt additional rules interpreting Act 250 provisions. Id. § 6025(b).
Pursuant to this enabling language, the NRB adopted rules which provide further interpretation of
“shoreline.” NRB Rule 2(C)(20) specifies that “[f]or purposes of 10 V.S.A. § 6086(a)(1)(F), a
project involves the ‘development or subdivision of shorelines’ ” if: “(a) the project involves
construction on or the use of ‘the land between the mean high water mark and the mean low water
mark of such surface waters,’ ”5 or “(b) the project, or an element of the project which is adjacent
to the shoreline, has the potential for significant impact on any of the subcriteria specified in 10
V.S.A. § 6086(a)(1)(F)(i)-(iv).” NRB Rule 2(C)(20)(a), (b) (emphasis added).
¶ 32. Under the definitions of “shoreline” provided in § 6001(17) and NRB Rule
2(C)(20), a project constructed on land “adjacent” to a river is on a “shoreline,” and it will be
subject to the stringent requirements of § 6086(a)(1)(F). Thus, determining whether the Korrow
project is “adjacent” to the Dog and Stony Brook Rivers is essential to finding whether the project
is or is not on a shoreline and whether further analysis regarding project compliance with Criterion
1(F) is necessary. With this in mind, we turn to two remaining questions: (1) whether the Korrow
project is on a “shoreline” pursuant to the definitions provided in § 6001(17) and NRB Rule
2(C)(20); and (2) if so, whether the project complies with Criterion 1(F), § 6086(a)(1)(F).
4
Unlike “floodway” and “floodway fringe” under § 6001(6) and (7), the ANR is not
statutorily tasked with defining shorelines under § 6001(17). The parties do not dispute, and we
do not consider, the level of deference the court owes to the agency construction of “shoreline.”
5
The parties do not dispute that the Korrow project is outside the scope of “land between
the mean high water mark and the mean low water mark” of the Dog River and Stony Brook
River—that element of both provisions is inapplicable to our analysis. 10 V.S.A. § 6001(17); NRB
Rule 2(C)(2)(a).
16
¶ 33. Whether the Korrow project is on a “shoreline” is a finding of fact that this Court
reviews for clear error. The court’s determination will stand unless there is “no credible evidence
that a reasonable person would rely upon to support the conclusion[].” Zaremba Group Act 250
Permit, 2015 VT 88, ¶ 6.
¶ 34. There are two flaws in the court’s findings. First, although interpreting the scope
of land “adjacent” to the rivers is essential to determining whether a project is on a “shoreline,” no
definition of “adjacent” is provided by the trial court. Second, even applying the court’s
contextual, rather than distance-based, analysis of the project’s location in relation to the Dog and
Stony Brook Rivers, the court’s conclusion that the project was not on the “shoreline” is based on
insufficient evidence.
¶ 35. First, the court’s failure to construe the term “adjacent” leaves a hole in the analysis
of the issue before us—whether the Korrow project was on a “shoreline.” While this Court has
not defined “adjacent” in the context of an Act 250 proceeding, the Environmental Division has
evaluated this term in the context of town zoning bylaws, which restricted project development on
public waters. In re Irish Constr. Application, No. 44-3-08 Vtec. (Vt. Envtl. Ct. Nov. 2, 2009),
https://www.vermontjudiciary.org/sites/default/files/documents/Irish%20Construction%20Appli
cation%20%20Docket%2044-3-08%20Vtec.pdf [https://perma.cc/CR7Z-794R]. In that case, the
Environmental Division appears to have applied a distance-based approach to determine
adjacency. The court explained that the plain meaning of “adjacent” was “close to; next to; lying
near; [or] adjoining” a body of water. Id. at 5 (quotation omitted). The proposed project in Irish
Construction Application was eighteen feet from the waterway at issue and was deemed “adjacent”
to public water for the purposes of the zoning ordinance. Id.
¶ 36. In contrast here, the court seems to be applying a functional application of
“adjacent” by looking to the project’s location within the riparian buffers of the Dog and Stony
Brook Rivers and evaluating the project’s impact on the four Criterion 1(F) subcriteria to
17
determine whether the project is on a “shoreline.” Considering the parties do not dispute the
definition of “adjacent” and the court does not engage with the issue, we decline to sua sponte
construe the term here. Rather, we look to the record below to support the court’s finding that the
project was not on a “shoreline.”
¶ 37. Second, based on the record below, even applying the court’s functional, rather than
distance-based, application of “shoreline,” there was insufficient evidence for the court to
determine that the Korrow project was not on a shoreline. The court never clearly defined the
scope of the shoreline; instead, the court measured the project’s compliance with Criterion 1(F)
based on evidence and testimony regarding the project’s proximity to the riparian buffers along
the Dog and Stony Brook Rivers and its compliance with the four subcriteria outlined in
§ 6086(a)(1)(F)(i)-(iv).
¶ 38. Riparian buffers are undeveloped, vegetated areas bordering waterways, which “are
important for [protecting] adjacent waters as well as downstream reaches.” The ANR recommends
that permit conditions require undisturbed, naturally vegetated buffers be maintained along
streams, and “the Department of Fish and Wildlife recommends maintenance of a minimum 50-
foot undisturbed riparian buffer along Stony Brook . . . [and] a 100-foot minimum undisturbed
riparian buffer between the development and the top of the Dog River riverbank.” The Korrow
project placed a small amount of fill within the Stony Brook River’s 50-foot buffer during
construction. Although the project’s “as-built location” is “approximately 130 feet” from the Dog
River, a small amount of fill was also placed within the Dog River’s 100-foot buffer during
construction.
¶ 39. The evidence regarding the project’s location in relation to riparian buffers between
the Korrow project and the rivers does not justify the court’s finding that the project was not on a
shoreline. To the contrary, this evidence indicates that part of the fill associated with the project
was within the riparian buffers of the Dog and Stony Brook Rivers. The court appears to apply
18
the following logic: A project is on a shoreline if it is developed on land adjacent to a river; land
is adjacent to a river if it is within the riparian buffer; the project here is only partially within the
riparian buffer; therefore, the project is not adjacent to the river and is not on the shoreline. Even
if we accept this logic and construe the term “adjacent” as synonymous with “within the riparian
buffer,” as the trial court seems to have done, then the undisputed fact that portions of the project
were within the riparian buffers of both rivers and the impact that fact has on the “shoreline”
determination are not addressed in the court’s findings. Thus, the findings are insufficient to
determine that the project was not on a shoreline.
¶ 40. The court further states that, even if the project was on a shoreline, it complies with
the four subcriteria in § 6086(a)(1)(F)(i)-(iv) and thus meets the shoreline requirements of Act 250.
However, the court fails to consider the full requirements of § 6086(a)(1)(F)(i)-(iv) by not
assessing, if the project is within the shoreline, whether the project was “of necessity” located
within a “shoreline.”
¶ 41. Criterion 1(F) requires the Environmental Division to “make its own determination
that a development need be located on the shoreline.” In re McShinsky, 153 Vt. 586, 591, 572
A.2d 916, 919 (1990). NRB Rule 2(C)(21) defines “of necessity” for the purposes of 10 V.S.A.
§ 6086(a)(1)(F):
[T]he project or a portion of the project must serve a water-related
purpose and . . . the project’s location on the shoreline serves such
an integral part of the developmental scheme that the inability to
locate the project, or a portion of the project, on the shoreline would
make the project impossible[.]
If this project is within a “shoreline,” the court must determine compliance with the “of necessity”
requirement in addition to evaluating whether the project meets the four subcriteria outlined in 10
V.S.A. § 6086(a)(1)(F). The court did not do so here.
¶ 42. Considering the court’s failure to adequately define the scope of the “shoreline”
along the Dog and Stony Brook Rivers, the court’s analysis of the project’s compliance with
19
Criterion 1(F), even when viewed in the light most favorable to the prevailing party, is insufficient
to justify its conclusions. Further, should the project fall within the “shoreline,” the court must
then further consider whether it must, of necessity, be located there.
¶ 43. Based on the record below, we cannot determine whether the project is constructed
on a “shoreline” as defined in § 6001(17), an assessment that may or may not require ANR
expertise, and, if so, whether the project complies with the subcriteria required by § 6086(a)(1)(F).
As such, the Environmental Division’s conclusion that the project complied with Criterion 1(F) is
reversed and this issue is remanded to the court for further findings consistent with this opinion.
Because the question of what is meant by “adjacent” is critical to the shoreline determination and
has thus far not been briefed or argued, the parties are directed upon remand to brief this issue for
the court.
We reverse the Environmental Division’s ruling defining the term “floodway,” but affirm
its conclusion that the project complied with Criterion 1(D). We reverse and remand to the
Environmental Division for further proceedings to determine whether this project involves a
“shoreline” and, if so, the project’s compliance with Criterion 1(F).
FOR THE COURT:
Associate Justice
20