In the United States Court of Federal Claims
No. 16-950C, 17-2017C, 18-80C, 18-522C, 18-677C, 18-691C, 18-921C
(consolidated)
(Filed: November 9, 2018)
***************************************** *
*
CB&I AREVA MOX SERVICES, LLC, *
*
Plaintiffs, * Motion for Summary
* Judgment; Rule 56;
v. * Notice of Intent to
* Disallow Costs; Remand
THE UNITED STATES, * to Agency.
*
Defendant. *
*
***************************************** *
Mark J. Linderman, with whom were Dennis J. Callahan, and Stephen L. Bacon, Rogers
Joseph O’Donnell, P.C., San Francisco, California, W. Brad English, J. Andrew Watson,
III, Jon D. Levin, Noah M. Hicks, II, Emily J. Chancey, and Michael W. Rich, Maynard,
Cooper & Gale, P.C., Huntsville, Alabama, and Paul A. Debolt, Emily A. Unnasch,
Christopher G. Griesedieck, and Chelsea B. Knudson, Venable LLP, Washington, D.C.,
for Plaintiff.
Joseph Ashman and P. Davis Oliver, Senior Trial Counsel, with whom were Chad A.
Readler, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, Allison
Kidd-Miller, Assistant Director, Sosun Bae and Anthony Schiavetti, Trial Attorneys,
Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington,
D.C., and Mary-Ellen Noone, Site Counsel, Savannah River Field Office, National Nuclear
Security Administration, Aiken, South Carolina, for Defendant.
OPINION AND ORDER
WHEELER, Judge.
Plaintiff CB&I AREVA MOX Services, LLC (“MOX Services”) seeks payment for
withheld costs after Defendant discovered that certain subcontractor employees received
salary increases, thereby increasing their billing rates to the Government under the contract
at issue. Currently before the Court is Plaintiff’s motion for partial summary judgment in
case number 18-921C, one of the consolidated actions arising from the same contract and
construction project near Aiken, South Carolina. MOX Services claims that the
Government’s withholdings are arbitrary and punitive, and did not follow proper
procedure. The Government argues that its withholdings were reasonable because it never
received sufficient information to justify the salary increases, and that it gave proper notice
of its intent to disallow these costs. For the reasons explained below, the Court GRANTS
Plaintiff’s motion for partial summary judgment because the undisputed facts show that
the Government failed to follow mandatory procedures for noticing a disallowance, and
REMANDS this dispute to the Agency to determine the total additional costs to be paid to
Plaintiff.
Background
Nearly two decades ago, the Department of Energy, National Nuclear Security
Administration (“NNSA” or “the Agency”) awarded a contract for the design, construction,
and operation of a Mixed-Oxide Fuel Fabrication Facility at the Savannah River Nuclear
Site located near Aiken, South Carolina to MOX Services’ predecessor in interest, Duke,
Cogema, Stone & Webster, LLC. The contract follows a “cost reimbursement” model
where NNSA pays MOX Services for allowable costs that MOX Services incurs in
performing its contractual obligations. However, MOX Services itself is an unpopulated
entity. It has no employees and does not directly perform any services. All of its services
are performed by subcontractors. CB&I Project Services Group (“CPSG”) is a principal
subcontractor as well as MOX Services’ parent company. MOX Services is CPSG’s only
client; this contract is CPSG’s only project.
In 2015, CPSG engaged in an employee “re-slotting” process, an extensive overhaul
of its employees’ titles, duties, and, in some cases, compensation. CPSG first created new
titles and position descriptions, then placed nearly all of its “non-craft” (non-union)
workforce of 863 employees into one of these new positions. Second, CPSG reviewed
compensation for these re-slotted employees, and it chose to increase salaries for 55 of the
863 employees. In line with this pay increase, CPSG increased these 55 employees’
billable rates charged to the Government.
Billing under the contract involves two steps. For each billing period, CPSG
forwards vouchers to MOX Services that detail which employees worked during that
period, their number of hours worked, and their billing rate. MOX Services then submits
CPSG’s vouchers (along with those from all other subcontractors) to NNSA as part of
MOX Services’ bi-weekly billing package. Therefore, while NNSA had the rates and hours
from which it could calculate the increases, CPSG did not notify NNSA that it re-slotted
and increased salaries for certain employees at the time those changes were made.
2
In April 2016, the Agency conducted a non-craft labor verification for this project
and noticed that the billing rates for two employees had changed. NNSA asked MOX
Services to explain and justify the billing rate increases. MOX Services told the Agency
about the re-slotting and salary increases, and by May 2017, MOX Services had forwarded
information to NNSA that MOX Services believed would confirm the scope of the re-
slotting and support the decision to re-slot and increase pay for certain employees. NNSA
thought otherwise. On October 6, 2017, the Agency notified MOX Services through the
invoice review process that the previously presented information was insufficient and that
further supporting materials needed to be submitted to facilitate a cost-allowability
decision. NNSA alerted MOX Services that if this additional documentation was not
provided by October 12, 2017, the Agency would take “appropriate action . . . to protect
the Government’s interest.” This protection ultimately came in the form of withholding 2
percent of the total direct non-craft labor expenses starting with those costs beginning on
October 16, 2017 and continuing through the May 27, 2018 billing cycle. The Agency
withheld $1,142,112.00 as of the May 27 cycle. It has withheld additional costs since that
period.
Procedural History
On March 1, 2018, MOX Services submitted a certified claim to NNSA for payment
of withheld costs and requested that a final decision be issued within 60 days.
Approximately two months later, the Agency notified MOX Services that its failure to
provide the requested records constituted a breach of the contract and made a decision
within 60 days impossible. In response, MOX Services filed its first appeal with this Court
on May 18, 2018. That claim was voluntarily dismissed on June 19, 2018, predicated on
the understanding that the Agency would issue a decision shortly after dismissal. On June
26, 2018, the Agency denied MOX Services’ claim. MOX Services’ appeal of that decision
is now before the court.
Plaintiff filed its complaint for case number 18-921C in this Court on June 27, 2018.
Plaintiff then moved for partial summary judgment on July 13, 2018. Defendant filed its
response on August 10, 2018, and Plaintiff filed its reply on August 24, 2018. The Court
heard oral argument on Plaintiff’s motion on September 11, 2018. Believing that the
parties over time had exchanged enough information to resolve this dispute voluntarily, the
Court directed counsel to attempt to reach an agreement on this matter without the Court’s
involvement. However, these efforts were not successful, and counsel recently informed
the Court that the parties had reached an impasse.
3
Discussion
I. Standard of Review
a. Motion for Summary Judgment
Summary judgment is appropriate where “there is no genuine issue as to any
material fact and that the movant is entitled to judgment as a matter of law.” RCFC 56(a).
A fact is “material” if it might significantly alter the outcome of the case under the
governing law. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The
moving party bears the initial burden of showing that there exists no genuine dispute as to
any material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). Summary judgment
will not be granted if the “evidence is such that a reasonable [trier of fact] could return a
verdict for the nonmoving party.” Anderson, 477 U.S. at 248. The Court’s function is not
to weigh the evidence and determine the merits of the case presented, but to determine
whether there is a genuine issue of material fact for trial. Id. at 249; see Matsushita Elec.
Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587-88 (1986).
b. Disallowance Procedure
Disallowance is the official process by which a contracting officer challenges the
allowability of costs that a contractor submits for payment. 48 C.F.R. § 42.801. The
Department of Energy mandates that in reviewing cost-allowability, the contracting officer
must first “[h]old informal discussion[s] with the contractor as appropriate.” 48 C.F.R. §
942.803(a)(1). In order to disallow costs, a contracting officer must provide the contractor
with some official notice of his or her intent to disallow the disputed amount. §
942.803(a)(2) (“the contracting officer, shall: . . . Issue a notice (letter, memo, etc.) to the
contractor advising of cost disallowed or to be disallowed”) (emphasis added). Notice can
come either before the deduction is made or at the time of disallowance. § 942.803(a)(2)-
(3).1 Agencies must follow such regulations in administering contracts. See Spherix, Inc.
v. United States, 58 Fed. Cl. 351, 355-56 (2003).
II. Analysis
a. Notice of the Agency’s Intent to Disallow
MOX Services argues that the Agency never issued proper notice of its intent to
disallow. NNSA disagrees. The Agency claims that notice was given on October 6, 2017
1
The Court agrees with Plaintiff that 48 C.F.R. § 42.801 also requires a contracting officer to issue notice.
Section 42.801’s use of “may” does not provide the contracting officer with the discretion to issue a notice
of intent to disallow. Rather, it affords the contracting officer discretion whether to initiate the disallowance
process. Once the contracting officer heads down this path, notice must be afforded. However, resolution
of this ambiguity is not essential to the judgment in light of 48 C.F.R. § 942.803’s clearer language.
4
when NNSA “notified MOX Services in writing through the invoice review process that
supporting data to facilitate NNSA’s determination of cost allowability . . . was required .
. . or appropriate action would be taken to protect the Government’s interest.” Nyman
Decl. at ¶ 18. Curiously, neither party submitted this writing to the Court.
MOX Services successfully argues that this writing merely warned MOX Services
that the Agency intended to withhold costs pending further investigation, and it did not
constitute notice of NNSA’s intent to disallow costs as required by section 942.803. NNSA
establishes only that it told MOX Services that the Agency would take “appropriate action
. . . to protect the Government’s interest.” The imprecise phrase “appropriate action” does
not convey to MOX Services that NNSA intended to disallow costs. Indeed, the word
“disallow” or other language indicating an intent to disallow does not appear in that writing.
The writing instead seems more characteristic of what one might expect to see during the
pre-notice “informal discussion” period. The Agency points to no other written
communication as constituting notice of its intent to disallow costs.
Moreover, the Agency has not offered any evidence that this October 6 writing
contained any of the other required elements of notice outlined in subsections
942.803(a)(2)(i)-(ii). Since this writing did not meet the required conditions outlined in
section 942.803, it is not a notice of disallowance. As MOX Services points out, no notice
was ever issued, and therefore NNSA cannot be said to have disallowed these costs.
b. Remand Authority
The Tucker Act grants this Court jurisdiction to remand a dispute back to an agency.
See 29 U.S.C. § 1491(a)(2). Pursuant to Rule 52.2 of the Court’s Rules, this matter shall
be remanded to the Agency for a period of 32 days. During this time, the Agency shall
determine the remainder of costs withheld from MOX Services since the May 27, 2018
billing period and shall pay MOX Services that amount in addition to the $1,142,112.00
awarded herein. The Agency shall notify the Court of its decision and payment on or before
December 11, 2018.
Conclusion
For the reasons stated above, the Court GRANTS Plaintiff’s motion for partial
summary judgment in case 18-921C and REMANDS this case to the Agency. Plaintiff is
awarded $1,142,112.00 plus the additional amount determined on remand.
IT IS SO ORDERED.
s/ Thomas C. Wheeler
THOMAS C. WHEELER
Judge
5