T.C. Memo. 2009-50
UNITED STATES TAX COURT
UNION CARBIDE CORPORATION AND SUBSIDIARIES, Petitioner v.
COMMISSIONER OF INTERNAL REVENUE, Respondent
Docket No. 11119-99. Filed March 10, 2009.
R determined deficiencies in P’s Federal income
tax for 1994 and 1995. Pursuant to a negotiated
agreement, P was allowed research credits under sec.
41, I.R.C., for 1994 and 1995. In an amended petition
P now seeks additional research credits for 106
projects conducted at its manufacturing plants. To
resolve this action expeditiously, P and R agreed to
try five of the largest projects underlying P’s
research credit claim.
Held: Two of the five projects constitute
qualified research under sec. 41(d), I.R.C.
Held, further, P has established that it included
all activities that were similar to the two qualified
research projects in its calculation of its base amount
under sec. 41(c)(4), I.R.C.
Held, further, P has established that it incurred
$1,045 of additional qualified research expenditures
- 2 -
(QREs) for wages paid to specific plant employees for
qualified services performed during the two qualified
research projects. The remaining expenditures for
which P claims additional research credits are not QREs
because they were incurred in the production of goods
for sale, not in the conduct of qualified research.
Held, further, P improperly included production
costs in its base amount. However, because P’s error
caused P to overestimate its base amount, we find P’s
error to be harmless and accept P’s calculation of its
additional base period QREs with several adjustments.
Harold J. Heltzer, Alex E. Sadler, Robert L. Willmore, Peter
B. Work, and Allen D. Madison, for petitioner.
Jill A. Frisch, Daniel A. Rosen, Lyle B. Press, Alex
Shlivko, and Jenny D. Boissonneault, for respondent.
CONTENTS
FINDINGS OF FACT . . . . . . . . . . . . . . . . . . . . . . . 9
I. Overview . . . . . . . . . . . . . . . . . . . . . . . . . 9
A. Petitioner . . . . . . . . . . . . . . . . . . . . . . 9
B. Procedural History . . . . . . . . . . . . . . . . . 11
II. Claim Projects . . . . . . . . . . . . . . . . . . . . . 15
A. The Olefins Production Process . . . . . . . . . . . 16
B. The Amoco Anticoking Project . . . . . . . . . . . . 20
1. Overview of Coking . . . . . . . . . . . . . . 20
2. The Coke Reduction Program and Amoco’s
Technology . . . . . . . . . . . . . . . . . . 22
3. The Amoco Anticoking Project . . . . . . . . . 25
C. The Spuds Project . . . . . . . . . . . . . . . . . 32
1. Overview of the Spuds Project . . . . . . . . . 32
2. Petitioner’s Motion for Leave To Amend
Its Petition . . . . . . . . . . . . . . . . . 37
D. The Sodium Borohydride Project . . . . . . . . . . . 38
1. Overview of the Acid Gas Removal System . . . . 38
2. The Sodium Borohydride Project . . . . . . . . 41
E. UOP GA-155 Project . . . . . . . . . . . . . . . . . 48
1. Overview of Fouling in the C3 Column . . . . . 48
2. Overview of Inhibitors . . . . . . . . . . . . 50
- 3 -
3. The UOP GA-155 Project . . . . . . . . . . . . 52
F. The UCAT-J Project . . . . . . . . . . . . . . . . . 60
1. Overview of Polyethylene Production . . . . . . 60
2. UCAT-J . . . . . . . . . . . . . . . . . . . . 66
3. Overview of the UCAT-J Project . . . . . . . . 70
4. Experimental Runs Before the Credit Years . . . 79
5. Experimental Runs During the Credit Years . . . 79
a. DJM-5265H (UCAT-J Run 1) . . . . . . . . . 81
b. DJM-1810B (UCAT-J Runs 2 and 11) . . . . . 84
c. DJM-1732H (UCAT-J Runs 3 and 15) . . . . . 88
d. DJM-2419H, DJM-1810H, and DJM 2016H
(UCAT-J Runs 4 Through 6) . . . . . . . . . 91
e. DJM-1735H (UCAT-J Runs 7 and 16) . . . . . 95
f. DJL-5264H and DJL-5280H (UCAT-J Runs 8, 9,
18, and 19 . . . . . . . . . . . . . . . . 98
g. DJH-2580H and DJH-2950H (UCAT-J Runs 10 and
12) . . . . . . . . . . . . . . . . . . . . 101
h. DJL-5420H and DJL-5143H (UCAT-J Runs 13 and
14) . . . . . . . . . . . . . . . . . . . . 103
i. DJM-1720H (UCAT-J Run 17) . . . . . . . 104
III. Claimed Costs . . . . . . . . . . . . . . . . . . . . . 106
A. Cost Documentation Used . . . . . . . . . . . . . . 106
1. PCDs and MASs . . . . . . . . . . . . . . . . . 106
2. CMAI Data for Ethylene Byproducts . . . . . . . 107
3. Wage Information . . . . . . . . . . . . . . . 109
4. R&D Budgets . . . . . . . . . . . . . . . . . . 109
B. Costs of the Amoco Anticoking Project . . . . . . . 110
1. Supplies . . . . . . . . . . . . . . . . . . . 110
2. Wages . . . . . . . . . . . . . . . . . . . . . 113
C. Costs of the Spuds Project . . . . . . . . . . . . . 114
D. Costs of the UOP GA-155 Project . . . . . . . . . . 115
1. Supplies . . . . . . . . . . . . . . . . . . . 115
2. Wages . . . . . . . . . . . . . . . . . . . . . 116
E. Costs of the Sodium Borohydride Project . . . . . . 116
F. Costs of the UCAT-J Project . . . . . . . . . . . . 117
1. Supplies . . . . . . . . . . . . . . . . . . . 117
2. Wages . . . . . . . . . . . . . . . . . . . . . 118
IV. Base Period Projects . . . . . . . . . . . . . . . . . . 119
A. Scope of the Trial . . . . . . . . . . . . . . . . . 119
1. Organization of UCC’s Manufacturing Operations
During the Base Period . . . . . . . . . . . . 120
2. Acquisitions and Dispositions Between the
Claim Years and the Base Period . . . . . . . . 122
a. Acquisitions . . . . . . . . . . . . . . . 122
b. Dispositions . . . . . . . . . . . . . . . 124
3. UCC/Shell Polypropylene Business . . . . . . . 125
- 4 -
a. The Cooperative Undertaking . . . . . . . . 125
b. SPC . . . . . . . . . . . . . . . . . . . . 127
c. Petitioner’s Base Amount Recalculation . . 129
B. Base Period Projects . . . . . . . . . . . . . . . . 130
1. UCC’s Focus on R&D During the Base Period and
Credit Years . . . . . . . . . . . . . . . . . 130
2. The Role of R&D and Engineering at UCC’s
Manufacturing Plants . . . . . . . . . . . . . 130
3. Petitioner’s Identification of Plant-Based
Qualified Research Activities Conducted During
the Base Period . . . . . . . . . . . . . . . . 131
a. Dr. Wadia’s Assignment . . . . . . . . . . 131
b. Dr. Wadia’s Methodology . . . . . . . . . . 133
c. Dr. Wadia’s Conclusions . . . . . . . . . . 134
d. Petitioner’s Concessions . . . . . . . . . 136
i. Nalco Inhibitor Antifouling Test (Run
816) . . . . . . . . . . . . . . . . . 136
ii. Wastewater Activity (Run 809) . . . . 137
iii. Rohm & Haas Runs (Runs 813
and 814) . . . . . . . . . . . . . . 138
e. Activities That Were Not Identified Base
Period Activities . . . . . . . . . . . . . 139
i. NOx . . . . . . . . . . . . . . . . . . 139
ii. John Zink Co. Orders . . . . . . . . . 149
iii. Star Pelleting . . . . . . . . . . . 149
iv. Naphtha Analysis . . . . . . . . . . . 150
f. Duration and Quantities of Product
Produced . . . . . . . . . . . . . . . . . 150
i. Natural and Forced Draft Burner Tests
(Runs 1 through 11, 95, and 96) . . . . 153
ii. Nalco 5211 Tests (Run 15) . . . . . . 157
iii. Vinyl Acetate Catalyst Protection
Tests (Runs 47 and 48 and Runs 594
and 596) . . . . . . . . . . . . . . 159
iv. Butyl Acetate Capacity Increase Test
(Run 161) . . . . . . . . . . . . . . . 161
v. MEK Production Test (Run 175) . . . . . 161
vi. Secondary Refining System Test
(Run 178) . . . . . . . . . . . . . . 162
vii. Spanish Fermentation Ethanol Refining
Test (Run 180) . . . . . . . . . . . 162
viii. Ethanol Tertiary Recovery Test (Run
181) . . . . . . . . . . . . . . . 162
ix. Mexican Fermentation Ethanol Refining
Test (Run 184) . . . . . . . . . . . . 163
x. Propionic Acid Hydrogen Peroxide
Treatment Test (Run 190) . . . . . . . 163
- 5 -
xi. Adiabatic Hydrogenation Beds
Rearrangement Test (Run 198 . . . . . 163
xii. Butanol Refining Test (Run 202) . . . 164
xiii. DIBK Recycle to Mixed Keytones
Converters Test (Run 608) . . . . . 164
V. Base Period QREs . . . . . . . . . . . . . . . . . . . . 164
A. Documentation . . . . . . . . . . . . . . . . . . . 166
B. Ms. Toivonen’s Costing Methodology . . . . . . . . . 167
1. Identifying the Lead PCD . . . . . . . . . . . 168
2. Identifying the Materials . . . . . . . . . . . 169
3. Tracing the Materials . . . . . . . . . . . . . 169
4. Determining the Unit Costs of Materials . . . . 170
5. Calculating Total Materials Costs . . . . . . . 172
6. Calculating the Wage Costs . . . . . . . . . . 173
7. Calculating the Total Run Costs . . . . . . . . 175
8. Exceptions to Ms. Toivonen’s General Costing
Methodology . . . . . . . . . . . . . . . . . . 175
C. Ms. Toivonen’s Conclusions . . . . . . . . . . . . . 178
D. Disputed Calculations . . . . . . . . . . . . . . . 178
1. Acrolein Refining System Capacity Test (Run
128) . . . . . . . . . . . . . . . . . . . . 179
2. Propyl Dipropasol Refining Test (Run 171) . . . 179
3. Isophorone Mids Conversion Test (Run 173) . . . 180
4. Secondary Refining System Test (Run 178) . . . 180
5. Naphtha-Sulfur Injection Test (Run 807) . . . . 180
6. Methylmercaptopropanal (MMP) Refrigeration
Tests (Run 810) . . . . . . . . . . . . . . 181
OPINION . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
I. The Experts . . . . . . . . . . . . . . . . . . . . . . . 186
A. Petitioner’s Expert Witnesses . . . . . . . . . . . 187
1. Peter Spitz . . . . . . . . . . . . . . . . . . 187
2. Gilbert Froment . . . . . . . . . . . . . . . . 187
3. Richard Martin . . . . . . . . . . . . . . . . 188
4. Norman Brockmeier . . . . . . . . . . . . . . . 188
5. Ms. Hinojosa . . . . . . . . . . . . . . . . . 188
6. Dr. Wadia . . . . . . . . . . . . . . . . . . . 189
7. Ms. Toivonen . . . . . . . . . . . . . . . . . 189
B. Respondent’s Expert Witnesses . . . . . . . . . . . 189
1. Roy T. Halle . . . . . . . . . . . . . . . . . 189
2. M. Julianne McClung . . . . . . . . . . . . . . 190
3. Gary Allen . . . . . . . . . . . . . . . . . . 190
II. Whether the Claim Projects Constitute Qualified Research 191
A. The Qualified Research Tests . . . . . . . . . . . . 191
1. The Section 174 Test . . . . . . . . . . . . . 194
- 6 -
2. The Technological Information Test . . . . . . 197
3. The Business Component Test . . . . . . . . . . 198
4. The Process of Experimentation Test . . . . . . 198
5. Activities That Are Not Qualified Research . . 203
B. The Claim Projects . . . . . . . . . . . . . . . . . 204
1. Plant-Based Research . . . . . . . . . . . . . 204
2. The Amoco Anticoking Project . . . . . . . . . 207
a. The Section 174 Test . . . . . . . . . . . 208
b. The Technological Information Test . . . . 211
c. The Business Component Test . . . . . . . . 212
d. Process of Experimentation Test . . . . . . 212
e. Funded Research . . . . . . . . . . . . . . 215
f. Research After Commercial Production . . . 216
g. Data Collection and Routine Testing . . . . 217
h. Substantiation Requirement . . . . . . . . 219
3. The Spuds Project . . . . . . . . . . . . . . . 220
a. The Section 174 Test . . . . . . . . . . . 221
b. The Remaining Tests . . . . . . . . . . . . 223
4. The Sodium Borohydride Project . . . . . . . . 223
a. The First Three Tests . . . . . . . . . . . 224
b. The Process of Experimentation Test . . . . 224
5. The UOP GA-155 Project. . . . . . . . . . . . . 227
a. The Section 174 Test . . . . . . . . . . . 228
b. The Remaining Tests . . . . . . . . . . . . 230
6. The UCAT-J Project . . . . . . . . . . . . . . 230
a. The Section 174 Test . . . . . . . . . . . 230
i. Uncertainty . . . . . . . . . . . . . . 232
ii. Discovering Information . . . . . . . 235
b. The Technological Information Test . . . . 238
c. The Business Component Test . . . . . . . . 239
d. The Process of Experimentation Test . . . . 239
e. Research After Commercial Production . . . 242
f. Substantiation Requirement . . . . . . . . 243
III. Base Period Activities . . . . . . . . . . . . . . . . 244
A. Whether Petitioner Must Include Activities Conducted
By the Entire Consolidated Group . . . . . . . . . . 245
B. Acquisitions and Dispositions . . . . . . . . . . . 248
C. Polypropylene Runs . . . . . . . . . . . . . . . . . 250
D. Whether Petitioner Included All Activities Similar
to the Claim Projects on Its List of Identified
Runs . . . . . . . . . . . . . . . . . . . . . . . . 251
1. Petitioner’s Sources of Information . . . . . . 251
a. Whether Petitioner Was Required To Use
FOCRs To Identify Base Period Activities . . 251
b. Whether Petitioner Was Required To Consider
Alternative Sources . . . . . . . . . . . . 255
- 7 -
2. Whether Petitioner Should Include Additional
Activities in Its Base Period Calculation . . . 256
a. NOx . . . . . . . . . . . . . . . . . . . . 257
b. John Zink Co. Products . . . . . . . . . . 257
c. Star Pelleting Line . . . . . . . . . . . . 257
d. Naphtha Analysis . . . . . . . . . . . . . 258
e. Dr. Wadia’s Limitation of Duration . . . . 258
3. Reliability of Dr. Wadia’s Methodology . . . . 260
a. Reliability of Dr. Wadia’s Methodology as
Expert Testimony . . . . . . . . . . . . . 261
i. Whether the Methodology Can Be Tested . 263
ii. Whether the Methodology Is Known or
Accepted in the Community, Has Been
Published, or Has Been Subjected to Peer
Review . . . . . . . . . . . . . . . . 264
iii. Whether the Methodology Is Subject to
Known Rate of Error . . . . . . . . . 264
b. Petitioner’s Definition of “Qualified
Research” . . . . . . . . . . . . . . . . . 268
c. Whether Dr. Wadia Is Biased . . . . . . . . 272
IV. Claimed Costs . . . . . . . . . . . . . . . . . . . . . 273
V. Base Period QREs . . . . . . . . . . . . . . . . . . . . 285
A. Alleged Flaws in Ms. Toivonen’s Costing
Methodology . . . . . . . . . . . . . . . . . . . . 285
B. Alleged Errors in Ms. Toivonen’s
Calculations . . . . . . . . . . . . . . . . . . . . 288
C. Documents Ms. Toivonen Relied Upon . . . . . . . . . 291
D. Consistency Requirement . . . . . . . . . . . . . . 291
1. In General . . . . . . . . . . . . . . . . . . 293
2. Base Case Costs . . . . . . . . . . . . . . . . 294
3. Wage Costs . . . . . . . . . . . . . . . . . . 295
E. Whether Ms. Toivonen Calculated the Cost of
“Qualified Research” Activities . . . . . . . . . . 296
VI. Conclusion . . . . . . . . . . . . . . . . . . . . . . . 296
MEMORANDUM FINDINGS OF FACT AND OPINION
GOEKE, Judge: Respondent determined deficiencies in
petitioner’s Federal income tax of $20,481,520 and $140,732,254
for 1994 and 1995, respectively. In its petition, as amended,
- 8 -
petitioner alleges that it is entitled to additional research
credits under section 411 of approximately $3,656,091 and
$4,726,664 for 1994 and 1995, respectively (claimed credits).2
The claimed credits are based on 106 projects it conducted in
various units within six manufacturing plants during 1994 and
1995 (credit years). For purposes of resolving this action
expeditiously, the parties have agreed to try five of the largest
projects3 underlying petitioner’s affirmative research credit
claims (claim projects).4
The issue before the Court is whether petitioner is entitled
to additional research credits under section 41 for 1994 or
1995.5 Resolution of this issue requires us to determine: (1)
1
Unless otherwise indicated, all section references are to
the Internal Revenue Code in effect for the years at issue, and
all Rule references are to the Tax Court Rules of Practice and
Procedure.
2
In its original petition, petitioner claimed as affirmative
adjustments additional research credits of $4,808,671 and
$5,851,619 for 1994 and 1995, respectively.
After amending its petition, petitioner has conceded that an
additional project does not satisfy the requirements of sec.
41(d). This concession does not affect our discussion of
petitioner’s claims and will be addressed in the parties’ Rule
155 computations.
3
The term “projects” is used for convenience.
4
Petitioner withdrew a sixth project before trial.
5
All other issues in this case were resolved by agreement of
the parties or our previous Opinion in Union Carbide Foreign
Sales Corp. v. Commissioner, 115 T.C. 423 (2000).
- 9 -
Whether any of the claim projects constitute qualified research
under section 41(d); (2) whether any of the claim projects
constitute qualified research, whether petitioner included all
activities that were similar to the claim projects in its
calculation of its base amount under section 41(c)(4); (3) if any
of the claim projects constitute qualified research under section
41(d), whether the claimed costs of supplies and wages
attributable to those projects (claimed costs) are qualified
research expenditures under section 41(b) (QREs); and (4) if any
of the claimed costs are QREs, whether petitioner included all
similar costs in its base amount calculation.
FINDINGS OF FACT
I. Overview
Some of the facts have been stipulated and are so found.
The stipulated facts and the accompanying exhibits are
incorporated herein by this reference.
A. Petitioner
Union Carbide Corp. (UCC) was the parent corporation of a
group of corporations (collectively, petitioner) that filed
consolidated Federal income tax returns for the years ending
December 31, 1994 and 1995. UCC is a corporation organized and
existing under the laws of the State of New York. At the time
the petition was filed, UCC maintained its principal corporate
office in Danbury, Connecticut.
- 10 -
At all relevant times petitioner was a worldwide
manufacturer and marketer of basic chemicals and plastics and
specialty and intermediate chemicals. Petitioner conducted its
operations at large-scale production facilities throughout the
United States and abroad.
Petitioner’s basic chemicals and plastics (C&P) operations
involved the processing of raw hydrocarbon feedstocks--
principally ethane, propane, and naphtha--into basic building-
block chemicals known as olefins. Ethylene and propylene were
the major olefins UCC produced and were key raw materials for
petitioner’s olefins-chain C&P businesses.
Petitioner used process technologies to convert manufactured
and purchased ethylene and polypropylene into first-line
derivatives such as: (1) Polyethylene, which is used for high-
volume applications such as food containers, milk and water
bottles, grocery and trash bags, pipes, and tubing; (2)
polypropylene, which is used for similar high-volume
applications; and (3) ethylene oxide/glycol and derivatives,
which are used for products such as automobile antifreeze,
polyester resin, and film and as raw materials for petitioner’s
specialty and intermediates chemicals business.
Petitioner’s specialty and intermediates chemicals
operations involved the production of a wide variety of specialty
chemical and polymer product lines, as well as solvents and
- 11 -
chemical intermediates. During the credit years petitioner also
licensed its key olefins-based process technologies, such as the
UNIPOL process for manufacturing polyethylene, to third parties
in the oil and gas petrochemical industries.
During the credit years UCC maintained research and
development (R&D) technical centers in South Charleston, West
Virginia (South Charleston); Tarrytown, New York; Bound Brook,
Edison, and Somerset, New Jersey; and Cary, North Carolina. UCC
carried out process and design engineering at the technical
center in South Charleston.
On February 6, 2001, UCC merged into a wholly owned
subsidiary of Dow Chemical Co. (Dow).
B. Procedural History
UCC, as the common parent of petitioner’s consolidated
group, timely filed consolidated Federal income tax returns for
the years at issue on Forms 1120, U.S. Corporation Income Tax
Return.
On its 1994 and 1995 Federal income tax returns (returns),
petitioner claimed research credits of $14,100,887 and $4,053,901
for 1994 and 1995, respectively (original returns research
credits). UCC elected the reduced research credit under section
280C(c)(3) on its 1995 return, but not on its 1994 return.
In computing the original returns research credits,
petitioner included the following amounts as QREs for 1984
- 12 -
through 1988 attributable to UCC (UCC’s original returns base
period QREs):
UCC’s Original Returns
Year Base Period QREs
1984 $68,503,722
1985 64,742,828
1986 48,107,169
1987 52,170,492
1988 70,499,622
Total 304,023,833
UCC’s original returns base period QREs for 1984 through 1987
were drawn exclusively from UCC’s R&D technical centers. UCC’s
1988 original returns base period QREs were drawn from UCC’s R&D
technical centers except for $1.9 million attributable to UCC’s
G-1750 reactor at its Seadrift facility in Texas (Seadrift).
UCC’s annual gross receipts for the base period were as
follows:
UCC’s Annual
Year Gross Receipts
1984 $2,737,545,150
1985 2,440,721,126
1986 2,976,592,778
1987 3,547,163,938
1988 5,033,745,128
Total 16,735,768,120
- 13 -
UCC’s annual gross receipts for 1990 through 1994 were as
follows:
UCC’s Annual
Year Gross Receipts
1990 $4,010,083,913
1991 3,724,913,910
1992 3,608,486,054
1993 3,617,655,799
1994 3,789,545,361
On March 22, 1999, respondent timely mailed a notice of
deficiency to petitioner determining income tax deficiencies of
$20,481,520 and $140,732,254 for 1994 and 1995, respectively.
The parties negotiated an agreement that resolved most of
the issues raised in the notice of deficiency. Respondent
allowed petitioner’s original returns research credits as part of
the negotiated agreement.
Petitioner alleges in its petition, as amended, that it is
entitled to additional claimed credits of approximately
$3,656,091 and $4,726,664 for 1994 and 1995, respectively.6
Petitioner’s claimed credits are based on 106 projects it
conducted in various units within six manufacturing plants during
the claim years.
6
These figures have not been adjusted to reflect the fact
that petitioner has conceded that some of the projects do not
satisfy the requirements of sec. 41(d).
- 14 -
In computing the claimed credits, petitioner claimed
$56,247,556 and $145,435,822 as additional QREs under section
41(b) for 1994 and 1995, respectively (claimed QREs). The amount
of claimed QREs for 1995 is the full-year amount although
petitioner acknowledges that section 41 does not apply to any
amount paid or incurred after June 30, 1995, and before January
1, 1996, and petitioner will disregard such amounts in computing
the amount of additional research credits to which it is
entitled. On its original 1994 and 1995 returns petitioner
reported the claimed QREs as costs of goods sold. The supply
items that are in dispute are raw materials used to produce goods
for sale.
For purposes of resolving this action expeditiously, the
parties have agreed to try five of the largest projects
underlying petitioner’s affirmative research credit claims.7 The
five claim projects are referred to as: (1) The Amoco anticoking
7
The parties have not specified how they will proceed as to
the remaining credit year projects. The Court hopes that this
opinion will provide the parties with sufficient guidance to
determine whether additional research credits are available for
those projects. However, additional proceedings may be necessary
if the parties cannot agree on the final disposition of the
remaining projects.
- 15 -
project; (2) the spuds project;8 (3) the sodium borohydride
project; (4) the UOP GA-155 project; and (5) the UCAT-J project.
The Court held two special trial sessions in connection with
the petition claims. The first addressed the research credit
eligibility of the claim projects, and the second addressed
petitioner’s section 41(c) base amount recomputation. Both
parties introduced fact testimony from former UCC employees (in
some instances, current Dow employees) and opinion testimony from
expert witnesses.
II. Claim Projects
UCC conducted the claim projects at the Taft Plant (Taft)
and the Star Plant (Star), both of which were in Hahnville,
Louisiana.9 UCC conducted its olefins production at Taft’s
hydrocarbons unit, which contained two production subunits
designated Olefins-1 and Olefins-2. During the credit years Taft
was a manufacturing plant that included facilities for the
conversion of raw hydrocarbon feedstocks such as ethane, propane,
and naphtha into basic olefins such as ethylene, propylene, and
butadiene. The Amoco anticoking, spuds, sodium borohydride, and
8
Petitioner now concedes that the spuds project is not
qualified research. However, for reasons discussed below, we
will make an independent determination as to whether the spuds
project constitutes qualified research.
9
Following Dow’s acquisition of UCC in 2001, Taft and Star
were integrated into a single petrochemical complex referred to
as St. Charles Operations.
- 16 -
UOP GA-155 projects related to the olefins production process and
were conducted at Taft.
UCC produced film and molding polyethylene resins using
petitioner’s low pressure UNIPOL process technology at Star. The
UCAT-J project related to UCC’s production of polyethylene resins
and was conducted at Star.
A. The Olefins Production Process
A highly simplified description of the olefins production
process at Taft is that hydrocarbon feedstock is pumped from
storage into pyrolysis furnaces, preheated, and diluted with
steam and then is broken into lighter hydrocarbons through
thermal cracking. Hydrocarbons are any chemical compounds
consisting primarily of carbon and hydrogen. Hydrocarbons may
include 1 to more than 60 carbon atoms and can be gases, liquids,
or solids at normal temperatures depending on the number of
carbon atoms in the compound. Hydrocarbons are found in
petroleum, coal, and natural gas. Hydrocarbons are significant
sources of fuel and raw materials for the production of basic
petrochemicals and derivatives such as plastics, rubbers, and
specialty chemicals.
“Cracking” is the process whereby hydrocarbon molecules are
decomposed and recombined into lighter, commercially useful
molecules through the breaking of carbon-to-carbon or carbon-to-
hydrogen bonds. Cracking can be accomplished through a thermal
- 17 -
or a catalytic process. UCC’s olefins production facilities
employed a thermal process called “steam cracking”, whereby a
gaseous or liquid hydrocarbon feed is diluted with steam and
heated in a fire furnace. The steam cracking reaction requires
temperatures in the range of 1400 to 1650 degrees Fahrenheit and
ordinarily occurs for less than half a second before being
“quenched”, or cooled rapidly, in a heat exchanger or by direct
contact with colder fluid. UCC’s heat exchangers are typically
referred to by the acronym “TLE”, which stands for “transfer line
exchanger”. A TLE tubesheet is a flat, circular sheet
approximately 5 feet in diameter that manifolds together many
double concentric tubes each with an inner diameter of about 1
inch. Water and steam flow through the concentric annulus of
each double concentric tube, and the very high temperature
effluent flows through the center tube. Heat is transferred from
the cracked gas, or “effluent”, to the water and steam to quench
the ethylene furnace reaction products. TLEs use the extremely
hot effluent to boil water into high pressure steam that may be
used to power large steam turbine drivers in the product recovery
section of the plant or for other purposes.
The steam cracking process requires the construction and
maintenance of large, capital intensive, and complex cracking
furnaces to supply the necessary heat. Most of the furnaces at
Olefins-1 and 2 were Lummus SRT (SRT stands for “short residence
- 18 -
time”) furnaces. A Lummus SRT furnace consists of a rectangular
firebox with a row of vertical tubular coils, or “cracking sets”,
located in the center plane between two radiating ceramic
refractory walls.
After the effluent is initially quenched in the furnace’s
TLE to minimize secondary chemical reactions, it is further
quenched through direct contact with water and/or oil in a quench
tower. Heavier hydrocarbons, known as “pyrolysis fuel oil”, are
separated from the effluent during the quenching process. The
cracking, quenching, and pyrolysis fuel oil separation processes
occur in the hot section of UCC’s olefins production units.
After quenching, the effluent enters the recovery section
(or cold section) of the olefins production units. The effluent
is first compressed in a multistage centrifugal compressor to the
pressure required for separation. Acid gasses such as carbon
dioxide and hydrogen sulfide are removed in an acid gas removal
unit during the compression process.
Following compression and acid gas removal, the effluent is
dried, chilled, and partially condensed. It then proceeds
through a separations train whereby ethylene, propylene,
butadiene, and byproducts are fractionated and recovered in a
series of distillation columns and related equipment.
Distillation is performed in a column through the
application of heat from a reboiler at the column’s base and the
- 19 -
removal of components in a condenser at the column’s top. The
lighter fraction in the column feed mixture (the fraction
containing the components of the mixture with the lower boiling
points) is separated according to the lower boiling points
relative to the other chemicals in the mixture and recovered as
overhead vapor at the top of the column. The heavier fractions
in the column feed mixture exit as “bottoms” through the column’s
base.
Olefins-1 and Olefins-2 each had several distillation
columns, including the demethanizer (C1) column, which separated
methane from less volatile components; the deethanizer (C2)
column, which separated ethylene and ethane from less volatile
components; the depropanizer (C3) column, which separated
propylene and propane from less volatile components; and the
debutanizer (C4) column, which separated crude butadiene, butane,
and other four-carbon compounds from less volatile components.
The units also included an ethylene fractionator, which separated
ethylene from ethane, and a propylene fractionator, which
separated propylene from propane, as well as several other
columns.
Recovered methane and hydrogen were used primarily as fuel
gas. UCC typically supplied recovered ethylene, propylene, and
crude butadiene to third parties and/or one of UCC’s dedicated
olefins derivatives units. UCC also recovered and sold certain
- 20 -
byproducts of the olefins production process, such as acetylene,
dripolene (pygas), and fuel oil. Ethane and propane recovered in
the process were recycled through the process to extinction.
B. The Amoco Anticoking Project
1. Overview of Coking
Coke is a heavy, hard, and relatively brittle form of carbon
that gradually forms on the interior walls of cracking set coils
during the cracking process. The cracking reaction produces two
types of coke, “catalytic” and “thermal”.10 Catalytic coking is
caused by the reaction between active metal sites on the inner
furnace tube walls and hydrocarbon molecules in the cracked
furnace gas. Thermal coking gradually forms as a result of the
reaction between catalytic coke and the highly reactive products
in the cracked furnace gas. Time and temperature combine to
remove the hydrogen from the hydrocarbon molecules, forming
thermal coke.
Coke buildup adversely influences furnace performance in a
number of ways. Coke insulates the furnace tubes from the
inside, impeding effective heat transfer from the furnace walls
to the gas within the cracking sets. This gradually increases
the skin temperature of the coils to the mechanical limit,
approximately 2,000 degrees Fahrenheit. Coil coking also closes
10
There are other coke formation theories that are not
relevant here.
- 21 -
off the flow cross-section area within the cracking sets and
thereby causes the hydrocarbon partial pressure (the pressure
exerted by the hydrocarbons within the gas mixture) to increase.
Higher partial pressure in the coils reduces the desired ethylene
yield from the furnace.
Coke also accumulates in the TLEs, located immediately
downstream from the radiant section, and the accumulation can
lead to higher hydrocarbon partial pressures and TLE exit
temperatures. Higher pressure in the TLEs caused by coking also
reduces the desired ethylene yield from the furnace.
Because of these effects of coking on furnace operation, the
cracking sets must be decoked periodically. UCC generally
decoked the furnaces in Taft’s hydrocarbons unit every 30 to 60
days through a process in which air and steam were fed into the
cracking sets at elevated temperatures (hot decokes). After
approximately three to four hot decokes, UCC brought the furnaces
down for an extended “cold turnaround” in which damaged cracking
sets were replaced and coke was manually removed from the TLE
system. Hot decokes and cold turnarounds necessarily resulted in
maintenance costs and lost production. Inhibiting coke formation
could result in reduced maintenance, longer furnace run times,
longer equipment life, and increased productivity.
- 22 -
2. The Coke Reduction Program and Amoco’s Technology
Before and during the credit years UCC’s hydrocarbons R&D
group had in place a coke reduction program aimed at achieving
economic and productivity improvements by implementing
technologies designed to reduce or eliminate coke in UCC’s
ethylene furnaces. Because of the inefficiencies caused by coke,
finding ways to reduce or eliminate coke was an important
objective of UCC’s hydrocarbons business. The goal of the coke
reduction program was to reduce the number of decokes per year by
50 percent and increase productivity by 4 to 4.5 percent per
year. If successful, UCC estimated that this would reduce its
decoking costs by $2.4 million per year and increase revenue by
as much as $20 million.
Many coke mitigation technologies have been proposed and
developed in laboratories over the years, but none have succeeded
commercially. Some failed to mitigate coke or even made it
worse. UCC screened and commercially tested numerous anticoking
technologies in the mid-1980s and later. During the credit years
there was no known, generally accepted, commercial coke
mitigation technology for pyrolysis furnaces. UCC considered at
least four technologies during the credit years but tested only
technology developed by Amoco Chemical Corp. (Amoco) during that
period.
- 23 -
One of UCC’s senior engineering scientists, David Milks,
approached Amoco regarding its anticoking technology in January
1994. Dr. Milks operated out of the South Charleston technical
center. On January 21, 1994, Amoco’s anticoking technology
manager wrote to UCC regarding an Amoco-developed furnace
anticoking technology that would mitigate coke formation and
extend furnace run times between decokings. Amoco’s technology
involved the pretreatment of the interior walls of the cracking
sets with a solution of dithiophosphoric acid derivative. Amoco
claimed that the pretreatment bonded to the sites of the tube
walls that promote catalytic coke formation and “poisoned” these
sites for several furnace runs to prevent coke buildup. Amoco
told UCC that its anticoking technology had been successfully
tested in a pilot plant and two commercial plants and that the
treatment had been shown to survive multiple decokes. After
reading about the science behind the technology, Dr. Milks
believed that it was theoretically sound but not yet proven.
Both Dr. Milks and Amoco were interested in testing the
technology on UCC’s facilities.
Several UCC employees formed the Amoco anticoking technology
test team to evaluate the technology on one of the furnaces at
Olefins-2 and to provide a recommendation as to whether UCC
should license the technology and implement it on all of its
furnaces at Taft and other UCC plants. William Hyde, an
- 24 -
operations improvement engineer at Taft, was the team leader. As
the team leader, Mr. Hyde prepared a charter for the team,
evaluated the technology to determine whether it was worth
testing, and coordinated the testing of the technology.
Amoco’s anticoking technology included the treating chemical
and a specialized method of application. Unlike prior decoking
technologies that UCC had tested, which involved the continuous
injection of an anticoking chemical, Amoco’s technology was a
pretreatment to be applied to a clean furnace before introducing
the feed.
Because of the proprietary nature of the technology, Amoco
required the protection of a secrecy agreement before disclosing
its process to UCC. On or about November 23, 1994, UCC entered
into an agreement with Amoco relating to Amoco’s anticoking
technology (the secrecy agreement). The secrecy agreement was
the only agreement UCC entered into with Amoco regarding Amoco’s
anticoking technology. According to the secrecy agreement, UCC’s
goal in conducting the Amoco anticoking project was to evaluate
the technical and economic feasibility of Amoco’s process and
equipment for inhibiting coking in UCC’s ethylene furnaces. UCC
also wanted to determine whether it was interested in a licensing
arrangement with Amoco. UCC’s rights in Amoco’s technology were
limited to these purposes. The secrecy agreement obligated UCC
to provide Amoco with a nonconfidential summary of the Amoco
- 25 -
anticoking technology’s performance no later than 3 months after
testing was completed. UCC gained no rights in, or licenses to,
any Amoco patent, but the secrecy agreement contemplated that the
parties could enter into a licensing agreement after the testing
was completed.
3. The Amoco Anticoking Project
At the beginning of the Amoco anticoking project UCC was
under the impression that the Amoco technology was fairly
established and beyond early developmental stages but that it
would still require some testing before it was proven technology.
Except for the fact that UCC was testing the Amoco technology,
UCC intended to continue its ethylene production process as usual
without decreasing production during the Amoco anticoking
project.
UCC worked with Amoco to draft a test plan that specified
the number of test runs (runs), the run lengths, what would be
measured, and the method of injecting the inhibitor. The run
lengths would be determined by “furnace cycles”, the amount of
time the furnace would run between hot decokes under normal
operating conditions. The test plan called for the collection of
data over four consecutive furnace cycles. The testing would
begin on furnace 24 in Taft’s Olefins-2 unit. The test plan
provided that Amoco would apply the inhibitor to four of the six
coils in the furnace so that the coke formation could be compared
- 26 -
between the treated cracking sets and the untreated cracking
sets. The test plan provided that treating four of the six coils
would ensure that the test results would not be affected by
differences between furnaces or operating conditions.
The test plan called for the collection of various
measurements during decokes, including furnace coil skin
temperature, pressure drop across the coils, TLE inlet pressure,
carbon monoxide, carbon dioxide, and phosphine. Except for
phosphine, these measurements are affected by coke formation.
Phosphine is a toxic substance that can be produced when
phosphorous-containing materials are used as coke inhibitors.
To prepare for the test, Mr. Hyde prepared a Facility
Operational Change Review (FOCR) for the project. An FOCR is a
document that is prepared by the operations personnel when a
significant operational change is to take place. It generally
addresses technical, quality, health, waste, and safety issues
that must be considered before the change is implemented in order
to minimize any risks involved. Jason Tregre, a Taft hydrocarbon
R&D technology manager, participated in the prestartup safety
review on furnace 24. As part of the test preparation UCC also
manufactured and installed nozzles according to design
specifications provided by Amoco. Among the other final test
preparations were several discussions with Amoco representatives
- 27 -
and a walkthrough at Taft on November 7, 1994, in which Amoco and
UCC personnel reviewed the pretreatment application procedures.
On or about November 28, 1994, after a hot decoke, four of
the six cracking sets were treated. Amoco personnel worked with
UCC’s plant operators to apply the treatment using Amoco’s
equipment. Amoco provided the treatment free of charge and
agreed to pay any overtime for additional time that UCC’s
employees would be required to work. The treatment was completed
on November 30, 1994. After the pretreatment was complete, UCC’s
plant personnel returned the furnace to normal operating
conditions.
UCC paid for the feedstocks and fuel gases used during the
project as well as the normal wages of the UCC employees involved
in the project. The supplies used for the project were the same
supplies that UCC used for normal operations, and UCC sold the
materials produced during the Amoco anticoking project in the
ordinary course of its business. The Amoco anticoking project
did not disrupt UCC’s normal manufacturing processes or products.
After the pretreatment was applied, UCC’s plant personnel
took various measurements, including the following, some of which
were not normally taken and others of which were not normally
taken as frequently:
- 28 -
Measurement Frequency Normal
Taken During Test Frequency
Furnace coil Once per day Once every 1
skin to 3 days
temperature
Radiant coil At least once Not normally
pressure drop per day measured
TLE inlet Continuously Continuously
pressure
Carbon monoxide Not specified Not normally
measured
Carbon dioxide During the Not normally
decoke measured
Hydrocarbon and Every 6 minutes Not specified
steam flows for the first 7
days, hourly
thereafter
Phosphine Not specified Not normally
measured
Some of these measurements were collected on the Olefins-2 unit’s
process computer, and others were collected manually.
UCC took measurements for approximately 45 days, then
performed a hot decoke of furnace 24 in January 1995.
Throughout the project UCC continued to decoke furnace 24
according to the plant’s normal schedule. UCC restarted the
furnace on or about January 15, 1995, without retreating the
furnace and continued to take measurements for about 9 days
thereafter.
Dr. Hyde compiled these measurements and sent them to Dr.
Milks and Dr. Husebye, a researcher in the hydrocarbons R&D group
- 29 -
at the South Charleston technical center. Dr. Husebye
reformatted the data and analyzed them. Dr. Husebye did not
typically perform this type of analysis. UCC did not share the
data it collected with Amoco.11
Dr. Husebye and Dr. Milks documented the results of the
first Amoco pretreatment in a report dated February 21, 1995.
The report covered approximately 7 weeks of furnace 24’s
operation. The results showed that carbon monoxide in the
treated cracking sets was initially reduced, indicating
successful coke inhibition. However, after the first hot decoke
and restart of furnace 24, there was no statistically significant
difference in the amount of carbon monoxide in the treated versus
untreated cracking sets. Dr. Milks and Dr. Husebye hypothesized
that the hot decoke that was performed before the Amoco
pretreatment was applied might have been incomplete and the
pretreatment might not have survived the first hot decoke
following the pretreatment. The results from the other
measurements were either inconclusive or indicated no difference
between the treated and untreated cracking sets.
Because the results from the first pretreatment were
inconclusive, Dr. Milks and Dr. Husebye recommended a second
pretreatment with the Amoco technology after a thorough cold
11
Respondent argues that UCC did share data it collected
with Amoco, and there is conflicting testimony on this point.
However, this fact does not control our decision.
- 30 -
turnaround. Amoco personnel applied the second pretreatment in
April 1995 to four of the six cracking sets. UCC personnel
gathered the same data following the second pretreatment as they
had gathered following the first pretreatment, and Dr. Husebye
analyzed the data. While UCC did not retain its analysis of the
second pretreatment, it did retain archived computer records that
included data collected after the second pretreatment that could
be used to reconstruct the original analysis.
Following the second pretreatment, the initial carbon
monoxide levels in the treated cracking sets were again
significantly lower than the carbon monoxide levels in the
untreated sets. However, after the hot decokes of furnace 24 in
May and June 1995, the carbon monoxide levels in the treated and
untreated cracking sets were nearly identical. The results from
the second pretreatment, as a whole, indicated that the Amoco
technology did not inhibit coke formation in furnace 24’s treated
cracking sets during the runs conducted between April and mid-
August 1995.
On August 21, 1995, a furnace operator participating in a
cold turnaround of furnace 24 observed that the TLE cones
connected to the treated cracking sets had significantly greater
amounts of coke deposits than the TLE cones connected to the
untreated cracking sets. This was unexpected, and UCC believed
- 31 -
that the pretreatment may have contributed to the excess coke in
the TLE cones.
During the cold turnaround UCC removed tube samples and coke
samples from furnace 24 to be tested. UCC’s corrosion and
machinery engineering department evaluated the samples and
documented the results of its analysis in a formal project
report. This report included the results of several tests
performed on the samples, analyses of those tests, and
recommendations for future tests of the Amoco technology. UCC
did not prepare any other formal project reports to specifically
document the results of the second pretreatment. However, UCC
reported the results of the two pretreatments in several informal
reports and memoranda.
UCC considered the Amoco anticoking project to be finished
in August 1995, and UCC never again tested the Amoco technology
in any of its ethylene furnaces. UCC later discovered that the
problem might have been caused by a mistake on Amoco’s part in
establishing the feed rate or the quantity of inhibitor to be fed
to the furnaces. This indicated to UCC that Amoco’s technology
was more developmental than UCC originally believed it to be.
UCC never entered into a licensing agreement with Amoco to use
its technology.
UCC used the information gathered during the Amoco
anticoking project primarily to determine that Amoco’s technology
- 32 -
did not effectively reduce coke formation in its commercial
facilities. UCC also learned about the operation of
thiophosphates (the active ingredients in the Amoco technology),
the relationship between sulfur and carbon monoxide levels, and
the effect of anticoking technology on the ceramic material on
TLE cones. UCC used this information in the course of its
business.
Mr. Hyde spent 35 hours in 1994 and 10 hours in 1995 working
on the Amoco anticoking project. Mr. Tregre spent 5 hours
working on the Amoco anticoking project in 1994.12
C. The Spuds Project
1. Overview of the Spuds Project
The spuds project involved replacing four-hole spuds with
one-hole spuds on furnace 3 in Olefins-1 at Taft. The one-hole
spuds were installed on furnace 3 on or about January 13, 1995.
A burner is a device that provides radiant heat in a
pyrolysis furnace through controlled combustion. In a pyrolysis
furnace, combustion is intended to provide a uniform temperature
to the fired radiant wall, allowing for even heat flux
distribution to the cracking set coils.
12
Petitioner does not claim as QREs any wages paid to Dr.
Milks or Dr. Husebye, who operated out of the South Charleston
technical center. Their wages would have been included in
petitioner’s original returns research credits.
- 33 -
The furnaces in Olefins-1 each had 112 radiant wall burners.
The burners are mounted through the furnace radiant wall and
produced a thin, flat circular disk of flame adjacent to the
wall. The burners were equally spaced in a grid pattern and
radiated heat to the process tubes on the centerline of the
furnace. Each burner had a single spud.
A spud is the orifice or port through which fuel gas flows
into the burner. It resembles a bolt with one or more holes at
the end. Spuds are installed at the piping terminations of each
burner and affect fuel flow and pressure. Spuds function to
equally divide the amount of fuel being injected to each burner
so that the heat released from the burners is evenly and
predictably distributed throughout all of the burners in the
firebox. The size and number of spud orifices determine the
pressure of the fuel gas just upstream of the orifice and the
exit velocity of the fuel gas from the orifice, parameters known
as “flow characteristics”. Flow characteristics of the spuds
help determine the burner firing capacity, which is the British
Thermal Unit (BTU) per hour heat output generated by a single
burner, flame stability, and fuel efficiency. As fuel gas passes
through the spud it produces a high velocity gas jet, which
entrains combustion air and mixes it with the fuel. The amount
of air that mixes with the fuel is critical to the stability of
the flame.
- 34 -
When it was first built in the 1960s, Olefins-1 used one-
hole spuds until it was moth-balled in the 1980s. When it was
restarted in 1989, Olefins-1 switched to four-hole spuds in order
to reduce noise. The four-hole spuds were prone to plugging, and
UCC typically cleaned the spuds during furnace shutdowns by
poking them with pieces of wire. Plugging of spuds may also be
improved or eliminated by cleaning the fuel gas system, removing
contaminants in the fuel gas, setting up a regular maintenance
schedule for removing and cleaning the spuds, or increasing the
size of the orifice(s) in the spuds. Some of these methods may
be costly and/or labor intensive. While replacing multihole
spuds with one-hole spuds without changing the total area of the
holes was a known method of reducing plugging, one-hole spuds
cause significantly more noise than multihole spuds and therefore
cannot always be used.
The Taft hydrocarbons unit identified fuel efficiency as an
area for operational improvement. In October 1994 the John Zink
Co. conducted a combustion survey of Taft’s hydrocarbons unit.
The John Zink Co. is a large ethylene burner manufacturer that
manufactured the burner used on furnace 3. Burner manufacturers
generally use their test furnaces to evaluate new spud designs
because testing new spuds in a commercial furnace can be
hazardous and the costs are unreasonably high. However, once a
spud design is proven, it generally performs better on commercial
- 35 -
furnaces than on test furnaces because the higher heat content in
a commercial furnace results in more stable flames. Testing and
evaluating a new spud on a test furnace takes about a day or
less.
Following the survey, the John Zink Co. recommended using
one-hole spuds instead of four-hole spuds in the Olefins-1
furnaces to reduce plugging. UCC had been using one-hole spuds
in its Olefins-2 furnaces since the late 1970s and noticed that
Olefins-2 had not experienced any plugging problems. However,
UCC was concerned about changing to one-hole spuds because they
might create too much noise. Olefins-1 and 2 were physically
different, and noise was more of a concern at Olefins-1 than at
Olefins-2. However, noise was not a major concern because the
plant personnel already wore hearing protection.
UCC followed the John Zink Co.’s recommendation to try
switching from four-hole spuds to spuds with one hole with the
same total hole area. UCC decided to purchase enough spuds for
three furnaces, which would cost $3,400 to $3,700 per furnace.
UCC believed that this was a relatively inexpensive way to solve
the plugging problem. UCC intended to test the new spuds on one
furnace; and if the test was successful, then UCC would
immediately begin replacing the spuds on two other furnaces.
To test the new spuds, UCC planned to monitor performance
data such as: (1) The fuel-to-feed ratio (BTUs of fuel per point
- 36 -
of feed), (2) excess oxygen in the fuel gas, (3) the amount of
combustibles in the fuel gas, and (4) fuel pressure. UCC
intended to evaluate the fuel efficiency improvements by
measuring BTUs in a process computer, measurements that were
available regardless of whether a test was being performed. The
goals of the test were to determine whether the new spuds would:
(1) Stop or reduce plugging; (2) increase efficiency, and if so
by how much; and (3) increase noise, and if so by how much. Mr.
Tregre was involved in this planning.
UCC did in fact take the above test data on furnace 3 for
about 90 days. Mr. James Gorenflo, a furnace technician, was
involved in testing furnace 3. UCC monitored plugging by
checking fuel pressure gauges. The results showed that pressure
was not increasing, which indicated that the new spuds solved the
plugging problem. UCC also evaluated fuel efficiency by
analyzing measurements of fuel gravity and the fuel-to-feed
ratio. Mr. Tregre was involved in this evaluation. The results
showed that fuel efficiency improved, although not as
dramatically as UCC had hoped.
Because the one-hole spuds solved the plugging problem, UCC
installed one-hole spuds on all of its furnaces at Olefins-1
after the 90-day test period was over. While UCC hoped that the
change would increase fuel efficiency more, the fact that the
- 37 -
one-hole spuds solved the plugging problem was sufficient
justification for changing the spuds.
Mr. Tregre spent 70 hours in 1994 and 10 hours in 1995
working on the spuds project. Mr. Gorenflo spent 10 hours in
1995 working on the spuds project.
2. Petitioner’s Motion for Leave To Amend Its Petition
On January 19, 2007, petitioner filed a motion for leave to
amend its petition. If filed, the amended petition would have:
(1) Withdrawn petitioner’s affirmative claim for additional
research credits under section 41 to the extent it was based on
the spuds project, (2) adjusted the claimed QREs to reflect the
withdrawal of the spuds project, and (3) applied the correct
credit rate for 1994. Respondent opposed this motion because the
Court had already held a trial on the claim projects, including
the spuds project. Given the substantial cost of litigation,
respondent argued that he would be prejudiced if the Court was
prevented from rendering a decision on whether the spuds project
satisfied the criteria for qualified research. In addition, to
the extent that petitioner claimed additional research credits
for projects similar to the spuds project that were not litigated
in the claim year trial, respondent argued that he would be
prejudiced by the absence of a decision on whether the spuds
project constituted qualified research.
- 38 -
Following a hearing on this motion on August 29, 2007, we
denied petitioner’s motion because we found that it would be
unfair to allow petitioner to unilaterally alter its agreement
with respondent to hold a trial on the five claim projects.
D. The Sodium Borohydride Project
1. Overview of the Acid Gas Removal System
The sodium borohydride project involved the injection of a
sodium borohydride solution into the Olefins-2 caustic scrubber.
The Olefins-1 and Olefins-2 acid gas removal systems remove
carbon dioxide and hydrogen sulfide from cracked furnace gas.
Acid gases are impurities that can cause operational problems in
downstream plant equipment. Acid gas removal is also necessary
to meet product specifications.
The acid gas removal system consists of a regenerative
monoethanolamine (MEA) system followed by a caustic scrubber.
Cracked furnace gas is fed into the MEA system, where it is
washed with a countercurrent flow of amine solution that removes
the bulk of acid gases. As an incidental benefit the MEA system
removes the impurity acetaldehyde from the cracked furnace gas.
Acetaldehyde is a highly reactive compound created in trace
quantities during the thermal cracking of hydrocarbons in the
presence of steam. It is formed in the furnaces through the
interaction of free radicals from steam and ethane or other raw
materials. Acetaldehyde can polymerize and foul plant equipment.
- 39 -
After being treated by the MEA system, the cracked furnace
gas passes through a two-stage caustic scrubber for removal of
residual acid gases. The caustic scrubber is sized so that it
can reduce acid gases to specification levels even when the MEA
system is shut down.
The MEA systems in both Olefins-1 and Olefins-2 had to be
periodically shut down and manually cleaned because of the
fouling of heat transfer surfaces partially caused by
acetaldehyde polymerization. Fouling is the deposition of heavy
organic solids that were dissolved in process fluid. When one of
the MEA systems is down, the cracked furnace gas passes through
only the caustic scrubber for acid gas removal. The caustic
scrubber, however, does not remove acetaldehyde. Taft’s MEA
systems ordinarily ran from 3 to 6 months between shutdowns,
depending on the feedstocks used and furnace cracking conditions.
Cleaning the MEA system normally took about 14 days.
In the early 1990s UCC produced at its Taft plant a
hydrocarbon product called crude butadiene. Crude butadiene is
highly reactive and is a major contributor to fouling in the
olefins process equipment. When the MEA system was shut down and
only the caustic scrubber was used to remove acid gases, some
acetaldehyde would leave the process with the crude butadiene.
In 1994 Shell Oil Co. (Shell) was Taft’s primary customer
for crude butadiene. At the time, Taft stored crude butadiene in
- 40 -
two storage tanks and transported it in barges to Shell, which
operated a plant directly across the Mississippi River from Taft.
Shell had a product specification limiting the amount of
acetaldehyde in Taft’s crude butadiene to 100 parts per million
(ppm) because acetaldehyde would foul Shell’s processing
equipment. On one occasion in the summer of 1994, UCC
manufactured crude butadiene that did not meet Shell’s
acetaldehyde specification. Shell refused to accept a barge
shipment of that crude butadiene and returned it to Taft.
When the MEA system was in service, acetaldehyde levels in
Taft’s crude butadiene were well below 100 ppm. However,
acetaldehyde levels reached between 500 and 800 ppm when the MEA
system was shut down. One method that UCC used to bring off-
specification crude butadiene within specification levels was
called “blending”. UCC would store off-specification crude
butadiene and then blend it with on-specification crude butadiene
when the MEA system was restarted.
However, when the amount of off-specification crude
butadiene exceeded UCC’s available storage capacity, UCC would
have to attempt to recycle the crude butadiene or find a
purchaser who would accept it as it was. Another problem of
blending was that it was difficult to calculate the amount of on-
specification product needed to blend with the off-specification
product. UCC was also considering building a pipeline directly
- 41 -
from Taft to the Shell plant, which would reduce or eliminate the
need for storage tanks and make blending impractical. Therefore,
UCC did not view blending as a permanent solution to the problem
of off-specification crude butadiene.
2. The Sodium Borohydride Project
Because of the shortcomings of blending, UCC sought a way to
remove acetaldehyde from crude butadiene during the periods that
the MEA system was shut down for maintenance. UCC decided that a
possible solution was to add sodium borohydride to the caustic
scrubber to remove acetaldehyde when the MEA system was shut down
for maintenance.
In February 1995 UCC considered using sodium borohydride
regularly to remove acetaldehyde if using sodium borohydride
proved to be effective. UCC knew that sodium borohydride was
effective in removing aldehydes, including acetaldehyde, as UCC
had been testing sodium borohydride in laboratories for such
purposes as early as 1961. UCC and its competitors had
successfully used sodium borohydride in commercial processes to
remove acetaldehyde and other carbonyl compounds from products.
However, UCC did not know how effectively sodium borohydride
could remove acetaldehyde in the caustic scrubber. Liquid sodium
borohydride was often used to remove acetaldehyde from other
liquids, but in the caustic scrubber UCC would need to use liquid
sodium borohydride to remove acetaldehyde from a gas. The
- 42 -
interaction of a liquid with a gas is much more difficult to
predict than the interaction of a liquid with other liquids.
UCC also knew that sodium bisulfate could be used to remove
acetaldehyde. However, UCC would have had to use a higher
concentration of sodium bisulfate than sodium borohydride to
effectively remove acetaldehyde, and sodium bisulfate was more
difficult to work with than sodium borohydride.
On October 10, 1994, Mr. George Brandon, a senior production
specialist at Taft, initiated an FOCR for injecting sodium
borohydride into the caustic scrubber in Olefins-2. According to
the FOCR, the purpose of the project was to run a test to
determine whether sodium borohydride could be used to remove
acetaldehyde when the MEA system was shut down.
An R&D report dated January 9, 1995, prepared by Robert
Manyik, a consultant in the hydrocarbons R&D group, was attached
to the FOCR. In the R&D report Dr. Manyik proposed a plant test
to add sodium borohydride to the caustic scrubber when the MEA
system was down in order to remove acetaldehyde to on-
specification levels. UCC would use a sodium borohydride
solution called VenPure, sold by Morton Performance Chemicals
(Morton). The R&D report addressed whether such a test was
feasible, identified potential hazards that could arise during a
test, and provided the necessary technical information that would
be needed to conduct the test. The R&D report specified the
- 43 -
equipment that was available, how much sodium borohydride UCC
would purchase, the rate at which the sodium borohydride would be
added, and the benefits and drawbacks of diluting the sodium
borohydride. The FOCR also included a diagram illustrating how
the sodium borohydride would be injected and a memorandum setting
out, in question and answer format, the duration of the test, the
controls that would be monitored, whether the sodium borohydride
would be diluted, the physical configuration of the injection
equipment, operation temperatures and pressures for the injection
equipment, and UCC’s plan to prevent the buildup of salt
precipitates.
One of the departments that reviewed the FOCR was Taft’s
Environmental Pollution Department (EPD). The EPD endorsed the
sodium borohydride project provided that certain conditions were
met. These conditions were that the EPD would sample and monitor
the plant’s wastewater for the presence of boron 2 weeks before,
during, and 2 weeks after the test, and the use of sodium
borohydride would be immediately terminated if the monitoring
indicated that the wastewater quality was beginning to
deteriorate. The EPD was concerned that large amounts of boron
might enter the wastewater system and disrupt the wastewater
treatment. Another condition that the EDP imposed was that the
injection rate would not exceed 5 pounds per hour; and if the
- 44 -
plant was required to increase this rate, it would seek approval
from the EPD at that time.
Approval from UCC’s R&D department was also necessary before
beginning the project because it involved the introduction of a
new chemical to the process. UCC wanted to ensure that the
change was safe and that there would be no adverse consequences
to the plant process from the injection of sodium borohydride.
The R&D department approved the sodium borohydride project on
January 13, 1995, and the engineering department approved the
sodium borohydride project on February 20, 1995.
UCC believed that a plant test was necessary to determine
whether sodium borohydride would effectively remove acetaldehyde
in an actual caustic scrubber. UCC was uncertain how well the
sodium borohydride would mix with the acetaldehyde because of the
difficulty in modeling liquid-gas interactions. Therefore, while
it was known that sodium borohydride would react with
acetaldehyde in a laboratory or pilot plant setting, UCC was not
sure how well sodium borohydride and acetaldehyde would react in
a full-scale plant given the plant’s size, gas flow, and
configuration. Because cracked furnace gas travels quickly
through the caustic scrubber, UCC was unsure whether the
residence time of the sodium borohydride in the caustic scrubber
would give the sodium borohydride sufficient time to react with
the acetaldehyde and bring the crude butadiene within
- 45 -
specification levels. UCC was also unsure of the appropriate
rate to inject the sodium borohydride and of the effect the
sodium borohydride would have on the boron concentration of the
wastewater. Because of these uncertainties as to how sodium
borohydride would interact with acetaldehyde, UCC referred to the
sodium borohydride project as a “test run”.
After injecting the sodium borohydride, UCC intended to
monitor the acetaldehyde content of crude butadiene extracted
from the caustic scrubber. The EPD also planned to monitor the
wastewater for boron content.
The equipment for the sodium borohydride project was
initially installed at Olefins-1 on June 11, 1995, but the crude
butadiene remained within specification levels when the Olefins-1
unit’s MEA system was shut down for maintenance. Accordingly,
UCC moved the equipment to Olefins-2 and conducted the test
there. UCC had a limited amount of sodium borohydride and did
not want to waste it on crude butadiene that was already on-
specification. The sodium borohydride project began in the
Olefins-2 unit on or about June 12, 1995, and ran for
approximately 2 weeks.
During the test, UCC injected the sodium borohydride
solution into the Olefins-2 caustic scrubber. To inject the
sodium borohydride UCC used a small tote tank (owned by Morton)
to hold the solution, a small metering pump to inject the
- 46 -
solution, and tubing to connect the tank and the pump to the
process. Morton recommended an amount for UCC to inject, and UCC
followed that recommendation initially but then made adjustments
as the project progressed. UCC did not regularly record the
amount of sodium borohydride that was injected during the test.
Taft employees monitored the crude butadiene production from
the Olefins-2 unit’s C4 column during the sodium borohydride
project. UCC measured the acetaldehyde content of the crude
butadiene every 12 hours. UCC normally took these measurements
about three times a week. To take the measurements, plant
operators took samples of crude butadiene to Taft’s central
quality control laboratory for testing. In addition, Mr. Brandon
measured acetaldehyde levels in the cracked furnace gas entering
and exiting the caustic scrubber. To take these measurements,
Mr. Brandon used a device called a “drager pump and tube system”.
The tubes would indicate how many ppm of acetaldehyde the cracked
gas contained. Mr. Brandon took these measurements at least
daily for the duration of the project. Mr. Brandon did not
normally take such measurements. As planned, the EPD also
monitored the wastewater approximately every 12 hours. The EPD
normally monitored the wastewater weekly unless a special test
was being run.
Mr. Brandon collected and recorded the results of the crude
butadiene analyses and drager tube tests and reported the results
- 47 -
to Terry Swindle, a Taft engineer assisting with the sodium
borohydride project. Mr. Brandon devoted approximately 200 hours
to the sodium borohydride project. The EPD collected and
recorded the results of the wastewater monitoring and reported to
Mr. Swindle that the boron was within acceptable limits.
However, the data collected from the sodium borohydride project
were not documented in a final project report. UCC treated the
January 9, 1995, R&D report prepared by Dr. Manyik as the
functional equivalent of a project report even though the report
was prepared before the test of sodium borohydride occurred.
UCC considered the sodium borohydride project to be a
success because the sodium borohydride effectively kept the
acetaldehyde in the crude butadiene production below the 100 ppm
specification level. Accordingly, Taft began to use sodium
borohydride regularly to reduce acetaldehyde levels when an MEA
system was shut down.
Several years later, UCC discovered that using sodium
borohydride to remove acetaldehyde caused unacceptably high
levels of ethanol, a byproduct of the reaction, in the crude
butadiene. During the credit years UCC believed that ethanol
would leave the system with the spent caustic and therefore did
not consider whether ethanol would be a problem and did not
measure it. However, the ethanol remained in the crude butadiene
and later caused it to fail Shell’s new specifications.
- 48 -
Therefore, UCC began using a new product to remove acetaldehyde
instead of sodium borohydride.
E. UOP GA-155 Project
1. Overview of Fouling in the C3 Column
The UOP GA-155 project involved the injection of an
inhibitor, UOP GA-155, into the C3 column line at Olefins-1 in an
attempt to reduce fouling in the C3 column trays and reboilers.
Fouling is a major problem for petrochemical plants.
Consequences of fouling may include declining performance,
frequent shutdowns of process equipment, loss of operation time,
and increased maintenance costs for cleaning or replacement of
equipment.
Fouling is a particular problem in distillation column
services. Deposit buildup in distillation columns can reduce
capacity and efficiency by blocking the flow path and by impeding
the performance of heat exchangers. An ethylene unit can
experience polymer fouling in the C2, C3, and C4 distillation
columns. The C3 column typically has the worst fouling problem.
The main function of the C3 column was to separate the
propylene and propane (C3 molecules) and heavier hydrocarbons.
The liquid hydrocarbon steam entered the C3 column at the
column’s midpoint and fell to the bottom where it was heated by
one of the two reboilers mounted on the column’s base. The
lighter C3 molecules were vaporized and captured at the top of
- 49 -
the column, while the remaining heavier components exited the
bottom of the column and traveled on to the C4 column. The C3
column contained approximately 40 trays that held the liquid
hydrocarbon stream being processed so that it could be exposed to
the vapor generated by the reboiler.
Column fouling is typically greatest within the reboiler and
also occurs in the trays. One cause of fouling in distillation
columns is the polymerization of reactive components in the
liquid phase of distillation. Polymerization is the linking of
double bonds to form long chain molecules. Most of the
polymerization is due to the reaction of diolefins and reactive
species such as styrenics.
In the mid-1990s Olefins-1 was experiencing high levels of
fouling in the C3 columns, reboilers, and internal trays caused
by the formation of polybutadiene polymer, a rubbery black
substance that adhered to the insides of the column. There were
two reboilers mounted to the base of the C3 column, but only one
operated at a time. The polybutadiene polymer fouled the tubes
in the operating reboiler and restricted the liquid flow. When
the reboiler fouled to the point that it became inoperable, it
was taken out of service and cleaned, and the clean reboiler was
placed in service. Typically, it took about 2 weeks to clean a
fouled reboiler and cost about $25,000. In 1994 and 1995 the
- 50 -
ideal run time for a reboiler between cleanings was 2 to 3
months.
The polybutadiene polymer also accumulated on the trays to
the point that the vapors rising from the bottom of the column
could not pass through the holes in the tray. This fouling
created a high differential pressure in the column, causing the
column to flood with liquid and become inoperable. At this
point, plant employees would have to shut down the column and
clean it. In 1994 and 1995 the ideal run time for a C3 column
was approximately 3 years but, depending on the feedstock,
cracking, and operating conditions, the column would not always
run that long. It would typically take about a month to clean a
fouled C3 column and cost about $50,000. Occasionally the entire
olefins unit needed to be shut down when a column cleaning
occurred.
2. Overview of Inhibitors
An inhibitor is a chemical that is added to a chemical plant
to reduce fouling and increase the time that a particular piece
of equipment will operate before it needs to be cleaned or shut
down. Olefins plants use two types of inhibitors (1)
polymerization/oxidation inhibitors and (2) dispersants.
Polymerization/oxidation inhibitors are added to stabilize
certain products that can polymerize or break down when exposed
to air. Dispersants are added to products to keep impurities
- 51 -
suspended in the liquid hydrocarbon stream from depositing on
plant surfaces and fouling them. An effective inhibitor will
improve column and reboiler run length times and will not cause
any additional problems in the plant.
UCC used about 12 different inhibitors in its olefins
manufacturing processes at any particular time in the early
1990s. In 1994 and 1995 UCC used different inhibitors in its
olefins manufacturing units because an inhibitor that works well
in one olefins plant may not necessarily work well in another
olefins plant. Because equipment differs from plant to plant, an
inhibitor might have a different residence time or different
contact times in different columns. In addition, flow rates,
pressures, and temperatures, which all affect the operation of an
inhibitor, differ from plant to plant.
The vendors from whom UCC purchased inhibitors tested the
inhibitors in laboratories to verify that they would in fact
inhibit polymerization or oxidation. However, UCC could not
determine how well the inhibitors would work in one of its plants
without testing them in the plant. UCC generally gathered data
when using a new inhibitor and compared that data to baseline
data to determine whether the inhibitor worked as expected. The
purpose of inhibitors is to extend the time equipment can be used
before it must be shut down and cleaned. Therefore, one way to
know whether an inhibitor is effective is to compare the run time
- 52 -
of a compressor, reboiler, or column operating with the inhibitor
against the preinhibitor run time of the same equipment. UCC
believed that the test of a new inhibitor should last for about
as long as the vendor claims the equipment will run with the use
of the inhibitor. UCC also generally used inhibitor tests to
determine the proper dosage. While UCC believed it was important
to use enough of an inhibitor for it to be effective, excessive
use of an inhibitor can have adverse effects on the production
process or on the plant’s products. Furthermore, because
inhibitors are expensive, using a higher dosage than is necessary
will reduce the economic benefit of using the inhibitor.
The hydrocarbons R&D group was generally involved in
decisions to test process inhibitors at UCC’s plants because the
tests would involve the introduction of a new chemical into the
plant and could have environmental, health, and safety
consequences. R&D was familiar with the chemistries and
processes of the plants and could provide input on whether a new
inhibitor might be effective in the plant, what dosage levels to
use, how to set up the test plan, and how to measure the results
of the inhibitor use.
3. The UOP GA-155 Project
Dripolene was a byproduct of Taft’s olefins production
process that flowed out the bottom of the C4 column, the final
column in the olefins separations train. UCC could not ship
- 53 -
dripolene unless it was stabilized with a certain amount of
polymerization/oxidation inhibitor. Without the inhibitor, the
dripolene could react with oxygen and present an explosion
hazard.
Before undertaking the UOP GA-155 project, Taft’s
hydrocarbons unit had been injecting a stabilizer known as UOP-5
into the dripolene as it flowed out of the C4 column. The active
ingredient of UOP-5 was phenylenediamine. The dripolene from
Olefins-1 and 2 was blended and stored in the same tank, so the
Olefins-1 dripolene was stabilized by the inhibitor injected into
the Olefins-2 dripolene.
Because cleaning the reboilers and shutting down the columns
was very expensive, UCC was always looking for ways to decrease
operating costs by reducing fouling. Mr. Brandon discussed the
problem with members of Taft’s hydrocarbons R&D group to try to
find ways to reduce fouling in the C3 column. Mr. Brandon
approached UOP, a supplier to the petrochemical industry, to
determine whether UOP had a product that could be fed directly
into the Olefins-1 C3 column to both reduce fouling and stabilize
the dripolene. UOP reviewed UCC’s process stream, operation,
equipment, and operating conditions. On the basis of those
observations, UOP recommended that UCC use UOP GA-155, which
contains phenylenediamine (the active ingredient used in UOP-5)
as well as a dispersant. UOP told UCC the approximate
- 54 -
percentages of UOP-5 and the dispersant contained in UOP GA-155.
UOP maintained that UOP GA-155 would operate as an oxidation
inhibitor in the C3 column, the phenylenediamine would stabilize
the dripolene, and the dispersant would mitigate fouling in the
C3 column. UOP represented to UCC that UOP GA-155 was effective
in extending process run length.
UCC had not previously used UOP GA-155 in any of its
facilities and was not aware of any other olefins plants in the
country that had used UOP GA-155. However, UOP told UCC that
some of the ingredients in UOP GA-155 were industry-wide standard
materials that were being used in olefins plants. UCC did not
consider other possible inhibitors or chemicals because their
cost was excessive because they were bundled with the purchase of
services that UCC did not want.
UCC wanted to test UOP GA-155 in its plant because
successful laboratory tests do not guarantee that an inhibitor
will be effective enough in a full-scale plant to justify its
cost. While manufacturers often made representations to UCC
regarding the inhibitors that they were selling, the inhibitors
did not always work as represented.
To test the UOP GA-155, UCC planned to inject UOP GA-155
into the C3 column feed instead of into the dripolene product as
it had done with UOP-5. The UOP GA-155 would then flow out of
- 55 -
the bottom of the C3 column, flow into the C4 column feed, and
flow out of the C4 column and the plant with the dripolene.
Mr. Brandon initiated an FOCR, numbered 94-80 (FOCR 94-80),
for moving the equipment that was being used to inject UOP-5 into
the Olefins-2 dripolene product over to Olefins-1 in order to
inject the inhibitor into the C3 column feed. UCC hoped that
injecting the inhibitor into the C3 column feed instead of
injecting it into the dripolene as it flowed out of the C4 column
would inhibit fouling in the depropanizer system. Mr. Brandon
initiated another FOCR, numbered 94-61 (FOCR 94-61), for changing
the inhibitor from UOP-5 to UOP GA-155 and injecting UOP GA-155
into the C3 column feed. FOCRs were generally required when
introducing new inhibitors because the introduction of a new
inhibitor is a process change. According to FOCR 94-61, the
purpose of the change was to reduce fouling in the C3 and C4
columns and their reboilers. The FOCR listed as concerns that
needed resolution (1) whether the customers would approve of the
change and (2) whether UCC had a pump that had a high enough
discharge pressure.
Mr. Brandon’s supervisor instructed Mr. Brandon to keep the
UOP GA-155 project on hold until the necessary approvals had been
obtained from the hydrocarbons R&D group, the EPD, and UCC’s
customers. UCC informed its customers that UOP GA-155 would be
injected into Taft’s Olefins-1 production process, and its
- 56 -
customers did not object. The FOCRs were finally approved on
September 22, 1994.
While Mr. Brandon hoped that UOP GA-155 would increase the
C3 column’s run time, he was not certain how effective UOP GA-155
would be. Mr. Brandon was also concerned that UOP GA-155 could
actually harm UCC’s production process. Specifically, he was
concerned that adding a dispersant to the column could cause
existing polymers to loosen from the column walls and trays and
plug the column. If that happened, UCC would have to shut down
the column and possibly the entire Olefins-1 unit. In addition,
Mr. Brandon was concerned about the effect that UOP GA-155 might
have on Taft’s commercial products because the UOP GA-155 would
flow out with the crude dripolene. Because UOP GA-155 would be a
new ingredient in the product, it was possible that it could
adversely affect the downstream olefins products or cause
problems when fed into customers’ production processes.
The injection of UOP GA-155 into the C3 column feed line in
Olefins-1 began soon after the final approvals were obtained for
FOCR 94-61 and FOCR 94-80 on September 22, 1994. The
hydrocarbons R&D group asked the plant personnel to collect data
during the test. Accordingly, Mr. Brandon collected daily all of
the pertinent data that were regularly recorded on the process
computer system in the Olefins-1 control room, including
differential column pressure, feed flows, throughput rate, steam
- 57 -
temperatures, and steam flows. Differential column pressure is
the measurement of the different pressures across the column
trays from top to bottom. When polybutadiene polymer accumulates
on the trays, the trays plug and the differential pressure
increases. While UCC did not normally review these measurements
daily, UCC did monitor reboiler chest pressure when there were
problems. It was also typical in the industry to measure column
differential pressure when equipment is prone to fouling.
During the test Mr. Brandon also measured and recorded
condensate pressure of the reboiler every day. Neither Mr.
Brandon nor any of UCC’s other employees had monitored the
condensate pressure daily before the UOP GA-155 project. An
increase in condensate pressure is a primary indicator of
reboiler fouling.
Mr. Brandon and other employees also took samples of
dripolene and analyzed the inhibitor levels once per 12-hour
shift. Before the UOP GA-155 project, UCC’s employees had
analyzed the inhibitor levels in the dripolene once a week for
quality control. Mr. Brandon took measurements for approximately
90 days during the UOP GA-155 project. Mr. Brandon also kept
track of reboiler run lengths both before and during the test
period. Mr. Brandon spent approximately 200 hours in 1994 and
200 hours in 1995 working on the UOP GA-155 project.
- 58 -
It would take approximately 3 years to determine whether UOP
GA-155 substantially extended the run length of the C3 column.
UCC could determine whether UOP GA-155 was reducing fouling in
the column by opening the column, but that was not practical.
Therefore, UCC relied on indicators such as differential column
pressure to determine whether UOP GA-155 was reducing fouling in
the column.
It would take at least 3 months for UCC to assess whether
UOP GA-155 would increase the run length of the reboiler because
the normal run length of a reboiler without the addition of an
inhibitor is about 2 to 3 months. UCC believed that a successful
inhibitor could extend the run length of a reboiler to about 6
months. Therefore, while Mr. Brandon recorded data only for
about 90 days, UCC treated the project as beginning on September
22, 1994, and lasting for 6 months. During this time the
Olefins-1 unit operated normally except for the addition of the
activities described above. UCC sold the products produced
during the UOP GA-155 project in the ordinary course of its
business.
UCC considered the UOP GA-155 project to be a success
because it reduced fouling and increased the run length of the
reboiler to 6 months.
Mr. Brandon recorded the results of the project and shared
them with Mr. Swindle. However, Mr. Brandon did not prepare a
- 59 -
formal project report after the project was completed or save the
data for use when fouling of Olefins-2 was discovered in 1997 or
1998. However, the results of the project would have been
reported in the quarterly reports that the hydrocarbons R&D group
prepared. The results of the UOP GA-155 project were also
included in a memorandum prepared for a conference call to be
held on July 27, 1995. The memorandum did not include data from
the project but reported the results as follows:
UOP Inhibitor Project: Recall that in the beginning of
the second half last year, the UOP-5 inhibitor was
replaced with the UOP GA-155 inhibitor and it was
injected earlier in the system in order to reduce
fouling of the C3 Column Reboilers in Ole-1. In
January of this year, the east kettle [reboiler] had to
be taken out of service due to tube leaks which were
not caused by the inhibitor or fouling - it was due to
attack from carbonic acid in the steam condensate. The
newly purchased kettle, which was installed last
October, was then put in service and is still in
service. We feel that the success of the kettle - six
month life - is primarily due to the use of the new
inhibitor. In addition, the new inhibitor is now also
being used in Ole-2.
UCC did not always prepare formal project reports when an
inhibitor test such as the UOP GA-155 project was performed.
Although it was preferable for a project report to be prepared to
summarize the results of an inhibitor test, this did not always
happen because it was not always a top priority.
On or about October 28, 1994, about a month after the UOP
GA-155 project began, Mr. Brandon began preparing an FOCR for a
project to begin using UOP GA-155 in Olefins-2. On November 29,
- 60 -
1994, Mr. Swindle recommended that UOP GA-155 be used at Olefins-
2. On or about June 14, 1995, after the completion of the UOP
GA-155 project, UCC began injecting UOP GA-155 into Olefins-2’s
C2 column tail. The purpose of this change was to reduce fouling
in the C2, C3, and C4 columns in Olefins-2 and simultaneously
stabilize the dripolene. However, during a plant shutdown in
1997 or 1998, UCC discovered that the dispersant in UOP GA-155
caused severe fouling in the Olefins-2.
F. The UCAT-J Project
1. Overview of Polyethylene Production
The UCAT-J project involved a series of runs using a new
polyethylene (PE) catalyst referred to as UCAT-J conducted at
Star. PE is a plastic made by reacting ethylene with other
materials to form polymers, or molecular chains, of ethylene.
The PE production process generally involves a reaction between a
polymerization-initiating catalyst (as relevant here, M-1 or
UCAT-J13), a cocatalyst, a monomer (usually ethylene), a
comonomer (hexene or butene), triethylaluminum (TEAl), and
hydrogen. Once polymerization begins, monomer molecules diffuse
to the growing polymer chains and resin is formed. Following
polymerization, the resin is discharged into a separate vessel
known as a product purge bin. Purging removes the residual
13
The UCAT-J and M-1 catalysts are described in greater
detail below.
- 61 -
hydrocarbons in the resin and deactivates the catalyst and
cocatalyst. The resin is then fed into a pelletizer, which
converts the resin into pellets. The pelleted PE resin is the
finished product. UCC typically shipped pelleted PE in hopper
cars (which each hold about 185,000 pounds of PE resin) to
customers who used it to make items such as grocery and trash
bags, packaging, thin-walled containers, and industrial liners.
Star was dedicated to the commercial production of linear
low-density film and molding resins (LLDPE) and medium density
(MDPE) and high density (HDPE) molding resins using UCC’s low-
pressure UNIPOL process technology. “UNIPOL” is the trade name
for a low-pressure gas phase fluidized bed process that UCC
developed and licensed to third parties. Star’s Low Pressure 3
Unit (LP-3) operated two UNIPOL reactors: Reactor 1, which was
used primarily for HDPE molding resins, and Reactor 2, which was
used primarily for LLDPE film resins. Although used for
different purposes, the two reactors were physically and
technologically identical. Reactor 1 and Reactor 2 operated
continuously 24 hours a day except for limited downtime
maintenance, transitions, and unforeseen problems such as
electrical outages.
In the early 1990s UCC began to plan the design of another
UNIPOL manufacturing facility, Low Pressure 6 Unit (LP-6). LP-6
was designed to produce PE using UCAT-J as the catalyst, but UCC
- 62 -
decided to install two different sets of catalyst feeders so that
M-1 could be used at the plant if UCC could not commercialize
UCAT-J by the time LP-6 was complete. UCC believed that it was
likely that it would be able to use UCAT-J at LP-6 once it was
constructed, but also knew that beginning the design of LP-6
before UCAT-J was ready for commercial production was a risk.
UCC did not want to wait until UCAT-J was commercialized before
building LP-6 because it takes years to design and build a
manufacturing facility and UCC wanted LP-6 to be completed close
to the time that UCAT-J was commercialized. LP-6 began producing
PE in June of 1995 using UCAT-J.
A UNIPOL reactor is referred to as a “fluidized bed” because
the circulating gas flow in the reactor causes the solid granular
resin to fluidize. The catalyst is fed directly into the side of
the fluidized bed through an injection system. A cocatalyst is
also fed into the bottom of the UNIPOL reactor to activate the
catalyst and promote catalyst activity.
“Reactor operability” refers to a wide range of potential
reactor operating issues, including catalyst stability,
reproducibility (whether the reactor consistently produces the
same responses), reactor control, production rate control,
product discharge, and downstream equipment operation. Reactor
operability is affected by a number of factors such as the
history of the reactor since it was last cleaned (i.e., how often
- 63 -
it has been exposed to oxygen and moisture), the mix of products
run on the reactor, the purity of the feed streams, and the
catalysts and cocatalysts used on the reaction system.
A significant UNIPOL operability issue is the formation of
sheets and agglomerates caused by static in the reactor. Sheets
and agglomerates are often referred to as continuity problems
because they interrupt the continuous operation of the reactors.
Sheets are formed when resin continues to react in a stagnant
zone (a zone with poor fluidization) next to the walls of the
reactor. Without fluidization to remove the heat of reaction,
the resin fuses together and forms sheet-like blocks ranging from
paper thin to several inches in thickness and several feet in
length. Agglomerates are formed when granular resin fuses
together forming solid or tightly adhered chunks ranging from
popcorn sized to several feet in diameter. These chunks can be
caused by sheets folding or rolling in the fluidizing bed, poor
catalyst distribution, localized poor heat transfer, or areas of
poor fluidization on the reactor distributor plate. Sheets and
agglomerates interfere with fluidization and plug the product
purge bin valve, requiring UCC to shut down and clean the
reactors.
Another operability issue is the formation of small, dust-
like particles called “fines”. Fines can create static (which
- 64 -
can lead to sheeting), cause continuity problems in the reactor,
and foul the cycle gas system.
The occurrence of operability problems might require a
reactor to be “killed”. A reactor kill (or CO kill) is typically
accomplished by the injection of carbon monoxide into the
reaction cycle gas to either reduce the rate of reaction (a
minikill) or stop all reaction as quickly as possible.
PE material meeting all applicable product specifications is
referred to as “aim-grade”. PE material that does not meet all
applicable product specifications is referred to as “off-grade”.
The production of off-grade material was not unusual, and UCC
sold both aim-grade and off-grade resin to third parties but at
different prices. Specific product properties of PE resins
include the average particle size (APS), density (for solid
molded resin), bulk density (for loose resin powder), film
appearance rating (FAR), hexane extractables (relating to the
stickiness of the resin), melt flow index, melt flow ratio (MFR),
and resin morphology.
The specific properties of the PE products made in a UNIPOL
reactor are determined by a variety of factors, including the
catalyst used and reactor operating conditions. The key reactor
operating conditions that determine the properties of the PE
resin are reactor temperature, ethylene partial pressure,
- 65 -
hydrogen-to-ethylene ratio, comonomer ratio, TEAl cocatalyst
ratio (Al/Ti), and residence time.
Star’s reactors made a variety of PE base resins. UCC
identified base resins using a three-letter prefix followed by a
four-number code and either an “H” or a “B”. The prefix of all
base resins begins with a “D”, followed by a “J” if UCAT-J is
used as the catalyst or a “G” if M-1 is used as the catalyst,
followed by an “H”, “M”, or “L” depending on the melt index
range. The four-number code identifies the density and melt
index designation. The final “H” or “B” identifies the comonomer
as hexene or butene, respectively.
A transition is the period when reactor conditions are
changed from one product’s specifications to a new product’s
specifications. A transition typically takes three to four bed
turnovers to complete, and each bed turnover lasts about 2 hours.
A bed turnover is the average amount of time material stays in
the reactor before flowing out of the product stream. The resin
made during transitions is either intermediate-grade material
that can be recycled into aim-grade resin or off-grade material
sold for scrap uses such as picnic tables and barrels. Once a
reactor is transitioned into a new product it takes a number of
additional bed turnovers to “line out” the reactor. Lining out
the reactor involves increasing the production rate back to the
normal level after slowing down for the transition and returning
- 66 -
operation conditions back to their normal steady state. After a
transition from M-1 to UCAT-J, it takes at least 12 hours to line
out the reactor.
2. UCAT-J
In a chemical reaction, a catalyst is a substance that
increases the rate of the reaction or causes the reaction to
occur under different conditions than otherwise possible.
Polymerization cannot occur in a UNIPOL reactor without a
catalyst. The catalyst provides the site on which the polymer
chain grows. A PE catalyst “precursor” refers to the catalyst
state before the incorporation of aluminum alkyl catalyst
modifying agents.
From Star’s startup in 1981 through the beginning of the
UCAT-J runs at Star in 1992, Reactor 1 and Reactor 2 at the LP-3
unit operated exclusively on a catalyst called M-1. UCC
continued to use M-1 at Star during the credit years during
normal production runs occurring between UCAT-J runs. Despite
its extensive experience using M-1, UCC occasionally experienced
operability and continuity problems with M-1, particularly
sheeting.
UCC developed UCAT-J as a superior catalyst alternative to
M-1. The primary advantage of UCAT-J is that UCAT-J is over four
times more “active” than M-1, meaning that the same amount of
catalyst makes over four times as much PE resin as can be made
- 67 -
with M-1. This, in turn, significantly reduces both capital
outlays for catalyst manufacturing facilities and the cost of
catalysts used in manufacturing PE. UCAT-J also requires less
hydrogen and TEAl than M-1, thereby reducing manufacturing costs
further, and improves some properties of PE resin such as FAR.
However, UCC used about the same amount of ethylene, hexene, and
butene regardless of whether it used M-1 or UCAT-J. Although UCC
had not commercialized UCAT-J during the credit years, UCC knew
of these advantages during the credit years and described them to
its licensees in anticipation of UCAT-J’s commercialization.
M-1 and UCAT-J are both Ziegler-Natta catalysts, a general
category of PE catalysts made from a transition metal such as
titanium and requiring a cocatalyst to initiate polymerization.
Both catalysts are based on a chemical solution of magnesium
chloride, titanium trichloride, and tetrahydrofuran, although the
proportions of these materials in M-1 and UCAT-J are different.
Most significantly, UCAT-J has a higher titanium loading and
magnesium-to-titanium ratio than M-1, both of which give UCAT-J
superior activity. Both M-1 and UCAT-J use titanium to provide
the catalyst active site and TEAl as the co-catalyst.
To create M-1, a chemical solution is added to small
particles of treated silica, which absorb the solution. Most of
the tetrahydrofuran is then evaporated to produce a free-flowing
solid, which is the M-1 precursor. The M-1 precursor is then
- 68 -
reduced with aluminum alkyls, diethylaluminum chloride (DEAC) and
tri-n-hexylaluminum (TnHAl), to produce the M-1 catalyst.
Catalyst reduction refers to the treatment of the catalyst
precursor with aluminum alkyl modifying agents to moderate
catalyst activity and ensure acceptable product properties such
as bulk density and particle size. The aluminum alkyl reduction
agents used for both M-1 and UCAT-J were DEAC and TnHAl. In its
final form, M-1 is a dry powder resembling sand.
UCAT-J is spray dried instead of being silica based. The
chemical solution is transformed into a fine droplet spray in a
spray dryer. As these droplets pass through a drying chamber,
the tetrahydrofuran evaporates, leaving only the solid catalyst.
The catalyst is then added to mineral oil to create a slurry (a
mixture of liquid and insoluble solids) of UCAT-J precursor. The
UCAT-J precursor is then reduced with aluminum alkyls. Although
Star made its own M-1 catalyst precursor, UCC made UCAT-J
precursor at a separate catalyst manufacturing facility in South
Charleston and shipped it to Star.
Because of the different methods by which they are made, M-1
and UCAT-J have different “catalyst morphology”, a term used to
describe the size, shape, and surface texture of a catalyst
particle. M-1 catalyst particles have a substantially larger APS
than those of UCAT-J. M-1 particles are typically rounder and
smoother than UCAT-J particles. UCAT-J’s morphology creates some
- 69 -
problems that were not present with M-1, particularly increased
fines and resin flowablity problems. These problems created
operating uncertainties that had not been resolved by the
beginning of 1994. UCAT-J and M-1 also respond differently to
other chemicals present during polymerization, respond
differently to reactor conditions, and create differences in PE
product properties.
M-1 precursor is reduced in the catalyst manufacturing unit
before the catalyst is delivered for use in the reactor. UCAT-J
precursor, in contrast, requires “in-line” catalyst reduction,
meaning that the DEAC and TnHAl modifying agents are injected
into the catalyst stream immediately before it is fed into the
UNIPOL reactor.
Before the first UCAT-J run at Star, which occurred in May
1992, UCC installed new equipment at Star to allow the in-line
reduction of UCAT-J precursor. The in-line precursor
modification system was a new unit operation installed
specifically for use with UCAT-J. In this system, UCAT-J
precursor was placed into a slurry feed tank, agitated to
maintain good dispersion, and pumped at a controlled rate. DEAC
and TnHAl were pumped into the catalyst stream at a specific
ratio to the catalyst feed. Following the injection of the
aluminum alkyls, the precursor flowed into a static mixer to
- 70 -
ensure adequate contacting and then into a residence time pot to
provide time for the in-line modification to occur.
The UCAT-J in-line reduction system presented several
operating uncertainties not present with M-1. When the system
was first used, it created catalyst consistency problem that were
due in part to the absence of static mixers and in part to the
fact that the original design contacted the UCAT-J precursor with
DEAC first and then with TnHAl, as was customary with M-1. UCC
later discovered that consistency improved when the order was
reversed. UCC also had difficulty controlling flow rates,
keeping control consistent and accurate, and injecting UCAT-J
because a slurry does not disburse as easily as a dry catalyst
like M-1. These uncertainties were not resolved by 1994.
3. Overview of the UCAT-J Project
The UCAT-J commercialization program involved the
development of UCAT-J to the point where it could be
commercialized. UCC’s UNIPOL licensing business wanted to
commercialize UCAT-J in order to: (1) Derive revenues from
selling UCAT-J to existing UNIPOL licensees; (2) be able to tout
the superior qualifies of UCAT-J to prospective UNIPOL licensees;
(3) avoid the capital costs associated with constructing plants
to manufacture the less-productive M-1 catalyst; and (4) reduce
Star’s manufacturing costs as a result of UCAT-J’s superior
productivity. The UCAT-J commercialization program took place at
- 71 -
Star from 1992 to 1996. References to the “UCAT-J project” are
only to those runs that occurred during the credit years.
Once UCC made the decision to commercialize UCAT-J, members
from process R&D, product R&D, and catalyst R&D formed an
interdisciplinary UCAT-J technology task force. The members met
monthly or bimonthly, usually in person, to review the status of
the commercialization effort and develop strategies for
overcoming problems with UCAT-J implementation.
During 1993 through 1995 UCC’s process R&D group conducted
what it called “experimental runs” of UCAT-J on a small-scale
UNIPOL reactor at a pilot plant at the South Charleston technical
center. UCC defined an experimental run as a run of a product
that UCC deemed noncommercial.14 During the credit years UCC’s
manufacturing business required that a commercial facility
conduct at least two, but preferably three, objective-meeting
experimental runs of new PE products, including products made
with a new catalyst, for the products to be considered
commercial. The successful completion of two to three objective-
meeting runs would demonstrate the operability of a new
technology to the satisfaction of the UNIPOL R&D and
manufacturing organizations. A customer’s qualification of a PE
resin depended on an independent inquiry related to the
14
We use the term “experimental run” for convenience and
consistency with UCC’s terminology.
- 72 -
suitability of the product produced and did not establish that
the product could be produced consistently enough to be
considered commercial. UCC was not required to advise customers
that they were receiving base resins produced with UCAT-J unless
a specific contractual term required such a disclosure.
The South Charleston pilot plant’s UNIPOL reactors were used
strictly for R&D purposes, and one reactor was dedicated to UCAT-
J. UCC ran UCAT-J on the pilot plant reactor to evaluate
catalyst performance, estimate optimal operating conditions for
the commercial reactors, and make PE resin for evaluation by the
product R&D group in Bound Brook. After experimenting with new
technologies on the pilot plant, UCC generally experimented with
the technologies on its mid-size UNIPOL reactors at Seadrift
before experimenting with the technology on the larger reactors
at Star. However, UCC took some UCAT-J products from the pilot
plant directly to Star or did not test them on smaller reactors
at all.
Successful commercialization of UCAT-J required UCC to
conduct experimental runs at UCC’s commercial plants to evaluate
whether UCAT-J could be used with reactor operability and resin
properties at least equivalent to, and hopefully better than,
those achieved using M-1. While UCC was often able to achieve at
least the same level of reactor operability and continuity using
UCAT-J as it had achieved with M-1 at pilot plants, commercial-
- 73 -
scale plant tests were also necessary because there were
significant differences between the pilot plants and commercial
reactors. For example, the bed volume of Star’s commercial
reactors was about 825 times the size of the bed volume of the
pilot plant reactor. Because of this difference, UCC’s pilot
plant and commercial reactors use different methods of
fluidization. These differences affect the amount of sheeting
and static in a reactor. Accordingly, a successful run at the
pilot plant did not indicate that sheeting and static would not
cause significant problems when a similar run was conducted at a
commercial plant.
The first commercial-scale run using UCAT-J was conducted on
UCC’s smallest commercial-scale reactor, the G-1750 reactor at
Seadrift, in 1991. UCC continued the UCAT-J commercialization
program at Star until 1996. UCC did not consider UCAT-J fully
commercial before the program was completed because UCC did not
know with certainty how UCAT-J would affect reactor operability
and continuity, how it would affect product quality and how much
off-grade material it would produce, whether there would be
problems feeding the catalyst into the reactor, and how it would
respond to CO kills. UCC was also concerned about reactor feed
stability, fines creation, production rate control, resin
properties, sheeting, and agglomeration. Such reactor
operability and continuity issues could develop at any time
- 74 -
during an experimental run, so process R&D representatives
remained on site for the duration of the runs, even after the
reactor had been successfully transitioned into UCAT-J. Process
R&D preferred longer experimental runs because they afforded more
opportunities to evaluate reactor operability and continuity.
UCAT-J experimental runs were initiated by the completion of
an experimental run request by the appropriate business manager,
R&D group leader, inventory planning and control (IPAC) manager,
and plant department head. IPAC controlled the scheduling of the
experimental runs and the duration of each run. When scheduling
the runs, IPAC considered existing customer orders and the risks
posed by experimental runs so that the experimental runs would
fit UCC’s commercial requirements. Once an experimental run
request was completed and the experimental run was scheduled,
representatives from process R&D in South Charleston would
prepare a strategic run plan with input from the UCAT-J
technology task force. The principal purpose of a strategic run
plan was to communicate to all interested parties the run
objectives, key operating parameters, analytical requirements,
and run coverage. After receiving the strategic run plan, a Star
engineer would prepare a tactical run plan. The purpose of the
tactical run plan was to give detailed run instructions to the
plant operators responsible for reactor operation. Strategic run
plans and tactical run plans were not prepared for routine
- 75 -
commercial production runs. The operations improvement group
would also complete a “New Product Introduction/Commercialization
Procedure Checklist” showing whether all required documentation
was in place.
The function of process R&D representatives during
experimental runs was to evaluate what was happening in the
reactor, identify problems, create hypotheses for how to solve
those issues or improve the process, and test those hypotheses by
conducting experiments. Process R&D representatives conducted
experiments by adjusting operating ratios, modifying catalyst
properties, and introducing new reactor control technologies.
Process R&D generally did not address minor problems that could
be solved by troubleshooting, which were addressed by the
production group at the plant.
During the UCAT-J project process R&D regularly collected
various measurements of reactor operability and continuity and
product properties. While many of these measurements were
collected during nonexperimental runs, process R&D
representatives collected some data that were not normally
collected and took other measurements more frequently than they
normally would. For example, process R&D measured residual
aluminum and titanium to monitor for TEAl starvation during the
UCAT-J project but did not normally take these measurements.
TEAl starvation occurs when there is an inadequate amount of TEAl
- 76 -
cocatalyst in the reactor. This lowers hydrogen and comonomer
response and catalyst productivity, which cause a loss of control
over the reactor and product properties. Process R&D also
measured hexane extractables more frequently than normal during
the UCAT-J project. The process R&D representatives recorded
their observations in R&D notebooks. At least every other day
process R&D sent an e-mail update to the members of the UCAT-J
technology task force and UCC’s management. This was not done
for normal commercial production runs. Process R&D
representatives were also called upon to address significant
production problems with products made using the M-1 catalyst
during the credit years.
Representatives from catalyst R&D and product R&D, both
based in Bound Brook, were available as needed. Samples of PE
resins made during UCAT-J experimental runs were shipped to the
product R&D group for testing to ensure that the resin was
equivalent to or better than that made with M-1. Any remaining
aim-grade resin made during the experimental runs was sold to
UCC’s customers. Product R&D did not provide coverage or test
resin samples for routine commercial production runs with M-1.
The run team, comprising representatives from process R&D
and Star’s management and operations staff, met before each run
to discuss the run objectives and transition into UCAT-J. The
run team also met regularly during the course of the UCAT-J runs
- 77 -
to assess the status of the run objectives and develop strategies
for resolving any operating problems that had surfaced. At the
end of each run the run team met to discuss the extent to which
the run objectives had been met. The run team presented these
findings at meetings of the UCAT-J technology task force. In
addition, process R&D representatives prepared a run notebook for
each run containing the strategic run plan, the tactical run
plan, the R&D monthly report description of the run, the
presentation to the UCAT-J technology task force, e-mails and
other communications regarding the run, and lab data. Process
R&D also described the UCAT-J runs in monthly reports issued by
the process R&D group, but these reports did not provide
technical details concerning the runs. Process R&D did not
generally mention normal production runs in these reports.
4. Experimental Runs Before the Credit Years
UCC conducted nine UCAT-J run campaigns on reactor 2 at Star
from May 1992 to November 1993. The UCAT-J runs conducted at
Star in 1992 and 1993 involved only hexene LLDPE film resins made
on reactor 2. These were the principal products made at Star and
UNIPOL licensee plants and tended to have tighter product
requirements than molding resins. At the end of 1993 UCC had
conducted no UCAT-J runs on reactor 1 or on reactor 2 with either
molding or butene film resins.
- 78 -
About 6 percent of the PE resin UCC made at Star in 1993 was
made with UCAT-J. By the end of 1993, UCC had resolved some
uncertainties related to UCAT-J such as an issue related to
catalyst particle size. The plant personnel at Star also gained
experience operating the plants using UCAT-J and were at ease
using UCAT-J and in transitions. Furthermore, a number of UCAT-J
runs had produced no off-grade product.
However, the UCAT-J runs conducted at Star in 1992 and 1993
suffered from numerous operability problems. Many were
unresolved as of the end of 1993, including: (1) Gas channeling
(resin becomes stagnant and nitrogen is channeled through the
resin instead of mixing with it, causing inadequate resin
purging); (2) TEAl starvation; (3) sticky stretch LLDPE resins
(resins that agglomerated and did not flow properly); (4)
sheeting; and (5) poor control over product properties such as
melt index, density, and hexane extractables caused by
differences in UCAT-J and M-1 catalyst morphology. UCC was
confident that many of these issues could be resolved but was
unsure when or how it would be able to resolve them.
Following a UCAT-J run campaign on LLDPE film resins in
November 1993, a moratorium was imposed on further experimental
runs on film resins to allow R&D to work out various problems,
some related to UCAT-J and others that were general plant
- 79 -
problems. UCC did not believe that UCAT-J was ready to be
commercialized by the end of 1993.
5. Experimental Runs During the Credit Years
At the beginning of 1994 some of the major outstanding
issues with UCAT-J were: (1) Obtaining acceptable product
properties in fractional melt index film resins; (2) resolving
butene film bulk density problems; (3) determining the cause of
and preventing resin stickiness; (4) establishing operating
parameters for UCAT-J film resins; (5) developing UCAT-J for
molding resins; and (6) ensuring that UCAT-J met operational
requirements. UCC believed it needed to conduct additional
experimental runs to resolve these issues.
UCC seeks research credits for the expenses incurred in 19
UCAT-J runs (UCAT-J runs 1 through 19) conducted at Star during
the credit years. The base resins produced, types of resin
produced (low-density film or high-density molding), start and
end dates of the runs, and pounds of base resin produced
according to UCC’s product cost detail reports (PCDs) are
included in the chart below:
- 80 -
Aim-Grade Off-Grade
Resin Resin
Run Base Start Produced Produced
No. Resin Resin Type Date End Date (pounds) (pounds)
1 DJM-5265H HDPE Molding 2/16/94 2/17/94 958,968 -
2 DJM-1810B LLDPE Film 10/22/94 10/26/94 4,832,092 771,350
1 2
3 DJM-1732H LLDPE Film 11/14/94 11/15/94 188,068 1,162,650
4 DJM-2419H LLDPE Film 12/11/94 12/13/94 1,632,872 765,700
5 DJM-1810H LLDPE Film 12/13/94 12/17/94 5,254,885 455,700
6 DJM-2016H LLDPE Film 12/17/94 12/18/94 703,691 -
3 4
7 DJM-1725H LLDPE Film 12/18/94 12/18/94 731,842 137,100
8 DJL-5264H HDPE Molding 1/26/95 1/27/95 6,135,634 797,750
9 DJL-5280H HDPE Molding 1/27/95 1/28/95 1,864,465 -
10 DJH-2580H LLDPE Film 3/3/95 3/6/95 2,601,861 578,450
11 DJM-1810B LLDPE Film 3/4/95 3/13/95 8,707,791 1,058,450
12 DJH-2950H LLDPE Film 3/6/95 3/6/95 132,324 148,750
13 DJL-5420H HDPE Molding 3/25/95 3/26/95 696,181 -
14 DJL-5143H HDPE Molding 3/26/95 3/27/95 1,006,947 -
5 6
15 DJM-1732H LLDPE Film 5/16/95 5/22/95 4,091,446 2,430,700
16 DJM-1725H LLDPE Film 5/22/95 5/26/95 3,653,813 966,350
17 DJM-1720H LLDPE Film 5/26/95 5/27/95 886,625 520,100
8
19 DJL-5280H HDPE Molding 6/22/95 6/23/95
1
This amount was found on a PCD for DJM-1734H. UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product.
2
This amount was found on a PCD for DJM-1734H. UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product.
3
This amount includes base resin produced during both run 7
and another experimental run that took place in November 1994.
4
This amount includes base resin produced during both run 7
and another experimental run that took place in November 1994.
5
This amount was found on a PCD for DJM-1734H. UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product.
- 81 -
6
This amount was found on a PCD for DJM-1734H. UCC could
not find a PCD for DJM-1732H, so it used the PCD for a similar
product.
7
The resin that petitioner claims UCC produced during run 18
is included in the amount of resin petitioner claims UCC produced
during run 8.
8
The resin that petitioner claims UCC produced during run 19
is included in the amount of resin petitioner claims UCC produced
during run 9.
a. DJM-5265H (UCAT-J Run 1)
UCAT-J run 1 was the first UCAT-J run at Star with a molding
resin and the first UCAT-J run conducted on reactor 1. The base
resin, DJM-5265H, was selected to be the first molding resin made
with UCAT-J at Star because it was a basic cornerstone product
that Star made in large quantities and UCC considered it to be a
low-risk product. UCC had made aim-grade DJM-5265H at the pilot
plant using UCAT-J and found UCAT-J to be equivalent to M-1 with
respect to operability and continuity on that scale.
Before UCAT-J run 1, two short runs of DJM-5265H had been
conducted at the UNIPOL facility of a licensee, Hanwa Chemical
Corp. (Hanwa), in Korea. While the runs at Hanwa were generally
successful, they lasted only a few days, and the second run was
aborted when the second transition failed. These results were of
limited value to UCC because Hanwa’s reactors were different from
Star’s reactors. Hanwa’s reactors were just over half the size
of Star’s reactors and so were less prone to static.
Furthermore, Hanwa’s reactors had a purification system for raw
materials that was considerably better than UCC’s purification
- 82 -
system. As a result, Hanwa’s reactor feed was much cleaner than
UCC’s and the catalyst had better productivity.
The objectives of UCAT-J run 1 were to: (1) Successfully
scale up production (adjust production to take into account the
differences in reactor size) of DJM-5265H from the South
Charleston pilot plant to reactor 1; (2) produce aim-grade resin
for customer qualification; and (3) establish reactor operability
and continuity on reactor 1. As to the third objective, UCC was
not merely confirming that reactor operability and continuity
were as expected. UCC wanted to evaluate how well reactor 1
worked with UCAT-J.
UCC’s primary concerns before UCAT-J run 1 were that: (1)
The differences between the pilot plant and reactor 1 at Star
could cause the product to go off grade; (2) TEAl starvation
could cause operability and continuity problems; (3) difficulties
with CO kills could occur if any kills were necessary; and (4)
resin clumpiness could cause operability and continuity problems.
As with all of the UCAT-J runs discussed below (although not
specifically mentioned below for brevity), representatives from
process R&D and product R&D provided coverage for UCAT-J run 1
and process R&D collected data, some of which were not normally
collected or was not normally collected as frequently.
Additionally, samples of resin were collected during and
- 83 -
following the run and were sent to product R&D in Bound Brook for
evaluation.
UCAT-J run 1 was aborted after 17 hours because of sheeting
caused by the use of M-1 before the transition to UCAT-J and the
formation of a spongy material that resembled Styrofoam. UCC
analyzed the spongy material and determined that it formed
because of the use of UCAT-J. But because the sheeting was
caused by M-1, UCC was unable to determine the extent to which
the use of UCAT-J contributed to the shutdown.
UCC also discovered a discrepancy between the Ti/Al ratio
calculated by flow rate and the measured Ti/Al ratio that
correlated with catalyst feed rate. UCC was unable to explain
this discrepancy and was concerned about TEAl starvation. UCC
also discovered more fines than expected.
UCAT-J run 1 did not last long enough for UCC to draw any
conclusions from the run. It remained uncertain following the
run whether UCAT-J could be used on reactor 1 with operability,
continuity, and resin properties equivalent to those achievable
with M-1. Because of the formation of the spongy material, TEAl
starvation concerns, and increased fines, UCC had serious doubts
as to its ability to make further product. Therefore, it did not
attempt to make another molding resin run again until 1995.
According to a PCD for DJM-5265H, UCC produced 958,968
pounds of aim-grade base resin for customer evaluation during
- 84 -
UCAT-J run 1.15 Petitioner claims as QREs costs associated with
producing 960,150 pounds of aim-grade base resin during UCAT-J
run 1.
b. DJM-1810B (UCAT-J Runs 2 and 11)
UCAT-J run 2 was the first UCAT-J run conducted at Star
using butene, as opposed to hexene, as the comonomer. UCC wanted
its plant operators to gain production experience using butene
comonomers in anticipation of the startup of LP-6. There had
been successful runs of DJM-1810B at Seadrift, the pilot plant,
and a licensee’s facility, which encouraged UCC to believe that
it would be able to use butene as a comonomer at Star. However,
process R&D had encountered significant difficulties producing
butene film resins using UCAT-J with acceptable bulk density
because of particle morphology differences between UCAT-J and
M-1.
The principal objective for UCAT-J run 2 was to successfully
scale up UCAT-J on the butene film resin from the pilot plant to
Star. A successful scale-up would require that the run: (1)
Demonstrate operability using UCAT-J equivalent to that
achievable using M-1; (2) reach aim-grade production within a
15
As discussed below, PCDs were produced monthly and
annually, not for specific projects. However, no base resin
produced with UCAT-J was made in more than one run in any given
month during the credit years. Accordingly, the PCD for the
month in which a UCAT-J run occurred would include information
only for that particular run.
- 85 -
specified period; (3) produce no significant off-grade material
once the transition was complete; and (4) produce resin with
acceptable bulk density. UCC was uncertain before the run
whether any of these requirements would be met or whether the
scale-up would be successful. UCC also hoped to produce 10 to 12
million pounds of aim-grade resin to sell to customers during
UCAT-J run 2.
To achieve acceptable bulk density, process R&D planned to
change the catalyst reduction ratios and increase the amount of
isopentane in the reactor during the run. Process R&D regarded
both changes as experimental and was uncertain whether they would
improve bulk density without adversely affecting reactor
productivity.
Additional objectives of UCAT-J run 2 were to demonstrate a
closed reactor restart with UCAT-J following a CO kill on M-1 and
to demonstrate the ability to kill the reactor while it contained
UCAT-J. UCC had never attempted a closed reactor restart at Star
with UCAT-J. UCC had had some experience with CO kills using
UCAT-J, but the results had been mixed. In particular, mini-
kills had been much less effective when using UCAT-J as compared
with M-1.
UCC was also concerned about several other risks, including:
(1) TEAl starvation; (2) resin carryover (a negative effect of
- 86 -
low resin APS, which may result from steps taken to improve bulk
density); and (3) resin clumpiness.
UCAT-J Run 2 began well and met some of the objectives,
including the first successful reactor startup with UCAT-J, no
significant off-grade material produced, and unexpectedly high
bulk density. However, UCC experienced operating problems a few
days into the run that required the reactor to be shut down and
the run aborted. The most significant of these problems were
unexplained production rate swings and the formation of “cue
balls” of PE resin that were about the size of softballs. UCC
hypothesized that the cause of the cue balls was poor catalyst
dispersion, and accordingly it planned to change the injection
tube for the next run of DJM-1810B to improve catalyst dispersion
and determine whether that would solve the problem.
According to a PCD for DJM-1810B, UCC produced 4,832,092
pounds of aim-grade and 771,350 pounds of off-grade base resin
during UCAT-J run 2. Petitioner claims as QREs costs associated
with producing 4,954,150 pounds of aim-grade and 771,350 pounds
of off-grade base resin during UCAT-J run 2.
UCAT-J run 11 was the second run of DJM-1810B. UCC’s
primary objective was to make DJM-1810B without the problems
experienced in UCAT-J run 2.
UCAT-J run 11 lasted from March 4 to 13, 1995, the longest
run for a single product during the UCAT-J project. A long run
- 87 -
is usually evidence that the run was successful. However, the
transition to DJM-1810B was unusually long and difficult, and a
significant amount of off-grade resin was produced. Once UCAT-J
was introduced into the reactor, the resin bulk density
unexpectedly dropped significantly, causing the product purge bin
to plug. This resulted in significant off-grade material and
required the production rate to be lowered. UCC did not
anticipate the bulk density problem because UCAT-J run 2 produced
resin with unexpectedly high bulk density. There were also
problems with catalyst stability, sheeting, poor hydrogen
control, and melt index swings. These problems were all specific
to UCAT-J and were not anticipated before the run.
Because of the bulk density and operability problems, UCC
decided to return the testing of DJM-1810B to Seadrift. While
UCAT-J run 11 provided valuable operating data, it did not
establish that reactor 1 at Star could produce UCAT-J butene
LLDPE film resins with operability and continuity equivalent to
that achieved using M-1.
According to a PCD for DJM-1810B, UCC produced 8,707,791
pounds of aim-grade and 1,058,450 pounds of off-grade base resin
during UCAT-J run 11. Petitioner claims as QREs costs associated
with producing 8,941,350 pounds of aim-grade and 1,058,450 pounds
of off-grade base resin during UCAT-J run 11.
- 88 -
c. DJM-1732H (UCAT-J Runs 3 and 15)
UCAT-J run 3 produced DJM-1732H, a low-density, high-melt-
index LLDPE film resin. UCAT-J run 3 was the first UCAT-J
experimental run of an LLDPE film resin with a hexene comonomer
conducted at Star since November 1993. UCC experienced so many
problems during the November 1993 run and the run had such a
negative impact on manufacturing that R&D wanted to do more work
on smaller reactors before attempting the run again at Star. UCC
had conducted runs of DJM-1732H at Star in January and March 1993
for 1 day each, but these runs were too short to establish that
the process could be used with sufficient operability and
continuity.
The objectives of UCAT-J run 3 were to: (1) Produce
sufficient product for customer qualification; (2) run reactor 2
at normal Star rates with operability and continuity equivalent
to or better than M-1; (3) reach aim-grade production within a
specified period; and (4) produce no significant off-grade
material. UCC was uncertain whether any of these objectives
could be met or whether the run would be successful.
Because low-density, high-melt-index LLDPE film resin is
sticky by design, resin flowability was a primary concern before
UCAT-J run 3. UCC was also concerned about: (1) TEAl
starvation; (2) resin carryover; (3) difficulties with CO kills,
if they were necessary; and (4) resin clumpiness. Resin
- 89 -
clumpiness had also been a problem when using M-1 to make DJM-
1732H but tended to be worse with UCAT-J.
UCAT-J run 3 had several successes: (1) UCC was able to use
CO mini-kills, which produced a rapid and significant effect; (2)
no fines were produced; and (3) a hopper car of resin was
produced. However, the run as a whole was considered a failure
and several problems occurred: (1) There was extensive formation
of clumpy resin that plugged the product purge bin; (2) there was
poor melt index control; and (3) there was TEAl starvation in the
reactor. Process R&D evaluated these problems, identified their
potential causes, and developed possible solutions for future
runs. UCC determined that the next run might be more successful
if it: (1) Lowered the ethylene partial pressure in the reactor
to reduce the amount of hexane; (2) controlled the cycle gas
composition and flow ratio; and (3) doubled the TEAl feed into
the reactor for 20 minutes (known as giving the reactor a “TEAl
shot”) periodically even if starvation was not expected and more
frequently during upset conditions. UCAT-J run 3 did not
establish that UCAT-J could be used with operability and
continuity equivalent to that achieved using M-1.
According to a PCD for DJM-1734H, not DJM-1732H, UCC
produced 188,068 pounds of aim-grade and 1,162,650 pounds of off-
grade DJM-1734H in 1994. No PCD was available for DJM-1723H for
1994. Petitioner claims as QREs costs associated with producing
- 90 -
188,850 pounds of aim-grade and 1,162,650 pounds of off-grade
base resin during UCAT-J run 3. However, other postrun
documentation indicates that UCC produced 743,987 pounds of aim-
grade base resin during UCAT-J run 3.
In addition to the objectives stated for UCAT-J run 3, a
goal of UCAT-J run 15, the next run of DJM-1732H, was to
implement measures developed by process R&D to control resin
stickiness and TEAl levels and to demonstrate acceptable
operability and continuity using UCAT-J in reactor 2. To control
resin stickiness, process R&D recommended that ethylene partial
pressure be lowered below 90 psi, which had never been done
before at Star with UCAT-J. This change to reactor conditions
was considered experimental and had two drawbacks: (1) Lowering
the ethylene partial pressure could lower the productivity of the
catalyst, which would lower resin APS and increase fines, causing
fouling; and (2) if the reactor transitioned back to M-1, it
would be necessary to increase the ethylene partial pressure by a
greater amount. UCC also planned to give the reactor periodic
TEAl shots to minimize TEAl starvation, which UCC began using in
run 4 (discussed below). However, UCC was unsure whether these
steps would be successful.
UCC hoped to produce 23 hopper cars of DJM-1732H for
customer qualification and consumption. Other run objectives
were to: (1) Run reactor 2 at normal production rates; (2) reach
- 91 -
aim-grade production within a specified period; and (3) produce
no significant off-grade material.
UCAT-J run 15 was generally successful. UCC was able to
control resin stickiness by lowering the ethylene partial
pressure, and UCC was able to maintain good catalyst productivity
even though it is more difficult to maintain at low ethylene
partial pressure. Overall, operability and continuity were good
throughout the run. However, while flowability improved, it was
still slightly worse than flowability that had been achieved
using M-1. Furthermore, there was some TEAl starvation due to
the TEAl feed system, though less than had occurred during
previous runs. Therefore, the information gained was valuable to
UCC but process R&D still had some concerns.
A PCD for DJM-1734H, not DJM-1732H, shows that UCC produced
4,091,446 pounds of aim-grade DJM-1734H in 1995. No PCD was
available for DJM-1732H for 1995. Petitioner claimed as QREs
costs associated with producing 4,108,850 pounds of aim-grade and
2,430,700 pounds of off-grade base resin during UCAT-J run 15.
d. DJM-2419H, DJM-1810H, and DJM 2016H (UCAT-J
Runs 4 Through 6)
UCAT-J runs 4 through 6 were all runs of hexene LLDPE film
resins. With the exception of DJM-1810H (UCAT-J run 5), which
had been used as an experimental bed resin for various types of
reactor testing, Star had limited experience with the UCAT-J
resins to be made in these runs.
- 92 -
UCC designed UCAT-J run 4 to make DJM-2419H, which UCC had
previously made at Star only during a 1-day run in 1993. UCC
produced approximately 600,000 pounds of DJM-2419H in 1993 and
UCC’s customers had accepted DJM-2419H made with UCAT-J.
However, UCC was still uncertain whether it would be able to
produce DJM-2419H at Star consistently with satisfactory
operability.
UCC designed UCAT-J run 5 to make DJM-1810H. UCC had used
DJM-1810H as an experimental bed resin and had produced it in 11
runs at Star during 1992 and 1993. UCC experienced significant
problems during the earlier runs. During the later runs UCC used
DJM-1810H as an experimental bed for catalyst reduction tests,
order of reduction tests, and similar tests. UCC made about 170
hopper cars of DJM-1810H in 1993. DJM-1810H produced with UCAT-J
had already been accepted by customers. However, UCC still
considered DJM-1810H to be an experimental resin at this point,
primarily because it had flowability problems.
UCC designed UCAT-J run 6 to produce DJM-2016H, which UCC
had never made at Star. However, UCC had produced DJM-2016H at
other plants during earlier experimental runs and customers had
qualified resin produced during those runs. UCC expected results
similar to those that had been obtained during runs of DJM-1810H
(UCAT-J run 5).
- 93 -
The overarching goal of these runs was to demonstrate
sustained operability of UCAT-J with hexene LLDPE film resins.
The specific run objectives listed on the strategic run plan were
to: (1) Produce sufficient product for customer qualification;
(2) further commercial experience through the extended production
run of DJM-2419H (UCAT-J run 4) and DJM-1810H (UCAT-J run 5)
(among other runs not claimed); (3) run reactor 2 at normal Star
rates with operability equivalent to that achieved using M-1; (4)
reach aim-grade production within a specified period; and (5)
produce no significant off-grade material outside product
transitions.
In response to a recommendation made at the UCAT-J
technology task force meeting following UCAT-J run 3, UCC decided
to run reactor 2 at a lower than normal ethylene partial pressure
during UCAT-J runs 4 through 6 to improve resin flowability. UCC
considered this change to be an experiment because it was
uncertain whether the change would successfully eliminate
flowability problems and there was a risk that the change could
significantly reduce catalyst productivity. UCC also decided to
use production rate control, which is an automated system to
control the catalyst feed rate and the ethylene partial pressure
in the reactor. The goal of this system was to maximize
production rate by allowing production rate to run closer to the
constraints of the reactor system.
- 94 -
Because of the problems with TEAl starvation in UCAT-J run
3, UCC decided to experiment with TEAl shots during UCAT-J runs 4
through 6. However, UCC was concerned that increasing the Ti/Al
ratio would also increase hexane extractables.
In addition to TEAl starvation, UCC identified several other
risks related to UCAT-J runs 4 through 6: (1) Resin carryover;
(2) difficulties with CO kills, if they were necessary; and (3)
resin clumpiness.
Process R&D representatives evaluated the ethylene partial
pressure and TEAl shot experiments during UCAT-J runs 4 through 6
in addition to the support that R&D provided to all of the UCAT-J
runs.
UCAT-J runs 4 through 6 were generally successful. Reducing
the ethylene partial pressure and using production rate control
reduced the stickiness problem and giving the reactor TEAl shots
reduced TEAl starvation. UCC viewed this as a substantial
achievement. The only significant problem was a decrease in FAR,
which occurs when there are gels or foreign matter in the film.
UCC took samples of the resin to try to determine the potential
causes and solutions for the decreased FAR. UCC hypothesized
that the decrease in FAR was caused by the use of wet hexene.
Process R&D concluded that it had gained confidence that
Star could produce DJM-1810H (UCAT-J run 5) and DJM-2016H (UCAT-J
run 6) with sufficient operability and continuity. However, UCC
- 95 -
believed that additional experiments were necessary to reach this
conclusion with respect to DJM-2419H (UCAT-J run 4).
According to a PCD for DJM-2419H, UCC produced 1,632,872
pounds of aim-grade and 765,700 pounds of off-grade base resin
during UCAT-J run 4. Petitioner claims as QREs costs associated
with producing 1,640,950 pounds of aim-grade and 765,700 pounds
of off-grade base resin during UCAT-J run 4.
According to a PCD for DJM-1810H, UCC produced 5,254,885
pounds of aim-grade and 455,700 pounds of off-grade base resin
during UCAT-J run 5. Petitioner claims as QREs costs associated
with producing 5,270,050 pounds of aim-grade and 455,700 pounds
of off-grade base resin during UCAT-J run 5.
According to a PCD for DJM-2016H, UCC produced 703,691
pounds of aim-grade base resin during UCAT-J run 6. Petitioner
claims as QREs costs associated with producing 704,600 pounds of
aim-grade base resin during UCAT-J run 6.
e. DJM-1735H (UCAT-J Runs 7 and 16)
UCAT-J run 7 was an experimental run of DJM-1725H, another
hexene LLDPE film resin that is very sticky and had shown poor
flowability. UCAT-J run 7 began and ended on December 18, 1994.
UCC also produced DJM-1725H in November 1994, but there were so
many problems with clumpy resin, melt index control, and TEAl
starvation that UCC did not use that resin for customer
qualification.
- 96 -
As in UCAT-J runs 4 through 6, the overarching objective of
UCAT-J run 7 was to demonstrate sustained operability of UCAT-J
with hexene LLDPE film resins. The specific run objectives were
to: (1) Produce sufficient product for customer qualification;
(2) run reactor 2 at normal Star rates with operability
equivalent to that achieved with M-1; (3) reach aim-grade
production within a specified period; and (4) produce no
significant off-grade material outside of product transitions.
UCC implemented the recommendation of the UCAT-J technology
task force to run reactor 2 at a lower than normal ethylene
partial pressure to improve resin flowability. UCC also gave the
reactor TEAl shots to reduce TEAl starvation but was still
concerned that increasing the TEAl ratio would also increase
hexane extractables. In addition to the support R&D provided to
all of the UCAT-J runs, process R&D representatives evaluated the
ethylene partial pressure and TEAl shots experiments.
UCAT-J run 7 was generally successful. The only significant
problem was a decrease in FAR caused by gels or foreign matter in
the film, which had also occurred during UCAT-J runs 4 through 6.
UCC took samples of the resin to try to determine the potential
causes and solutions for the decreased FAR. UCC believed that
additional experiments were necessary to gain confidence that it
could produce DJM-1725H with sufficient operability and
continuity.
- 97 -
According to the summary report of the UCAT-J experimental
runs conducted at Star, UCC produced 480,461 pounds of aim-grade
and 177,821 pounds of off-grade base resin during UCAT-J run 7.
According to a PCD for DJM-1725H, UCC produced 541,866 pounds of
aim-grade and zero pounds of off-grade base resin. Petitioner
claims as QREs costs associated with producing 737,200 pounds of
aim-grade and 137,100 pounds of off-grade base resin, which
includes total production for 1994 (both UCAT-J run 7 and the run
that took place in November 1994).
UCC produced DJM-1725H again in UCAT-J run 16 because UCAT-J
run 7 did not establish that DJM-1725H could be made without
continuity problems during longer runs. TEAl starvation remained
another significant operating issue.
In addition to the objectives for UCAT-J run 7, the goals of
UCAT-J Run 16 were to implement measures developed by process R&D
to control resin stickiness and TEAl levels and to demonstrate
acceptable operability and continuity of UCAT-J in reactor 2. As
in UCAT-J run 15, to control resin stickiness process R&D
recommended that ethylene partial pressure be lowered below 90
psi. UCC also planned to use periodic TEAl shots to minimize
TEAl starvation. However, UCC was unsure whether these steps
would be successful.
UCAT-J run 16 was generally successful. UCC controlled
resin stickiness by lowering the ethylene partial pressure below
- 98 -
90 psi, and UCC was able to maintain good catalyst productivity.
Overall, operability and continuity were good throughout the run.
However, while flowability improved, it was still slightly worse
than the flowability that could be achieved using M-1.
Furthermore, there was some TEAl starvation due to the TEAl feed
system, though less than had occurred during previous runs.
Therefore, the information gained was valuable to UCC but process
R&D still had some concerns.
According to a PCD for DJM-1725H, UCC produced 3,653,813
pounds of aim-grade and 966,350 pounds of off-grade base resin
during UCAT-J run 16. Petitioner claims as QREs costs associated
with producing 3,665,150 pounds of aim-grade and 966,350 pounds
of off-grade base resin during UCAT-J run 16.
f. DJL-5264H and DJL-5280H (UCAT-J Runs 8, 9,
18,and 19
UCAT-J runs 8 (DJL-5264H) and 9 (DJL-5280H) were the next
experimental runs of HDPE molding resins after UCAT-J run 1,
which UCC aborted before it could draw any meaningful
conclusions. Following UCAT-J run 1, process R&D took a year to
evaluate UCAT-J molding resins in the pilot plant before
conducting another experimental run at Star. UCC determined that
UCAT-J was equivalent to M-1 with respect to reactor operability
and continuity when making DJL-5264H and DJL-5280H at its pilot
plant, but UCC was still uncertain whether UCAT-J would perform
as well at Star. UCC had not yet determined that it could make
- 99 -
DJL-5264H or DJL-5280H consistently on full-scale commercial
reactors before UCAT-J runs 8 and 9.
The objectives of UCAT-J runs 8 and 9 were to: (1) Produce
sufficient product for customer qualification; (2) run reactor 1
at normal Star rates with operability equivalent to that achieved
using M-1; (3) reach aim-grade production within a specified
period; and (4) produce no significant off-grade material.
The primary risks UCC identified for UCAT-J runs 8 and 9
were: (1) TEAl starvation; (2) resin carryover; and (3)
difficulties with CO kills, if they were necessary. To reduce
the risk of TEAl starvation, UCC measured aluminum and titanium
during the run and gave the reactor periodic TEAl shots. Since
TEAl starvation had not been a problem with M-1, these
measurements were not taken during commercial runs using M-1.
Although resin carryover was listed as a risk on the strategic
run plan for UCAT-J runs 8 and 9, according to the strategic run
plan UCC did not actually expect resin carryover to be a problem.
UCAT-J runs 8 and 9 were generally successful. Reactor 1
demonstrated acceptable operability and continuity and all other
run objectives were met. There was some melt index variation
(resin in some hopper cars had a higher melt index than the resin
in others), but this was not significant problem. Some TEAl
starvation also occurred, but it did not cause the resin to go
off grade; and UCC determined that it could most likely fix the
- 100 -
problem by implementing a different TEAl system. Because UCAT-J
runs 8 and 9 each lasted only 1 day, UCC did not have time to
fully evaluate operability and continuity. However, the
information UCC gained was valuable, and one or two more
successful experimental runs would establish to UCC’s
satisfaction that the process was ready for commercialization.
UCAT-J runs 18 and 19 were the next experimental runs of
DJL-5264H and DJL-5280H. The operability and continuity of
reactor 1 in making these products remained uncertain before
these runs, as only a few short HDPE molding resin runs had been
conducted up to this point with mixed results.
The primary objectives of UCAT-J run 18 were to operate at
normal Star rates with operability equivalent to that achieved
using M-1 and to make a maximum of 250,000 pounds of off-grade
material.
UCAT-J run 18 yielded 825,000 pounds of off-grade material,
which indicated poor operability, particularly poor control of
the resin properties in the reactor. There were also problems
with the product purge bin, poor flowability, and poor melt index
control. However, UCAT-J run 19 was generally successful.
According to a PCD for DJL-5264H, UCC produced 6,135,634
pounds of aim-grade and 797,750 pounds of off-grade base resin
during 1995, including both UCAT-J runs 8 and 18. Postrun
documentation indicates that UCC produced 933,000 pounds of aim-
- 101 -
grade base resin during run 8 and 5,313,000 pounds of aim-grade
and 825,000 pounds of off-grade base resin during UCAT-J run 18.
Petitioner claims as QREs costs associated with producing
6,143,300 pounds of aim-grade and 797,750 pounds of off-grade
resin during UCAT-J runs 8 and 18 combined.
According to a PCD for DJL-5280H, UCC produced 1,864,465
pounds of aim-grade base resin in 1995, including both UCAT-J
runs 9 and 19. Postrun documentation indicates that UCC produced
851,844 pounds and 1,331,804 pounds of aim-grade base resin
during UCAT-J runs 9 and 19, respectively. Petitioner claims as
QREs costs associated with producing 1,750,532 pounds of aim-
grade base resin during UCAT-J runs 9 and 19 combined.
g. DJH-2580H and DJH-2950H (UCAT-J Runs 10 and
12)
UCC made DJH-2580H (UCAT-J run 10) in two short runs in 1992
and 1993. The run in 1993 produced about 17 hopper cars of base
resin that customers accepted. However, the 1992 and 1993 runs
of DJH-2580H presented significant operability problems. DJH-
2950H (UCAT-J run 12) was a difficult product to run and had
never been made at Star.
The primary objectives of UCAT-J runs 10 and 12 were to
produce these resins with acceptable product properties,
particularly fractional melt index, and to demonstrate acceptable
reactor operability and continuity.
- 102 -
UCAT-J run 10 ran for 3 days and then transitioned to DJH-
2950H (UCAT-J run 12). Significant sheeting problems developed
after the transition. The reactor was mini-killed and restarted,
but the sheeting continued and became worse. As a result,
Reactor 2 had to be shut down so that the sheets could be
physically removed with a suction truck and chainsaws. Opening
the reactor to remove sheets exposes the reactor to oxygen and
can cause problems in subsequent runs. As a result of the
sheeting, UCC aborted the runs and reactor 2 was restarted with
M-1 because resuming operation with UCAT-J was considered to be
too risky in the light of UCC’s overall business considerations.
However, some aim-grade resin was produced during the runs and
was sold to customers.
Process R&D suspected that the sheeting that first developed
after the transition to DJH-2950H (UCAT-J run 12) was due to the
high molecular weight of the DJH-2950H resin, and the sheeting
that developed after the mini-kill was due to static. Because of
the significant sheeting problems experienced during these runs,
process R&D moved testing of DJH-2580H and DJH-2950 to Seadrift
before returning the testing to Star. UCC imposed a moratorium
restricting fractional melt index products from operation at
Star.
According to a PCD for DJH-2580H, UCC produced 2,601,861
pound of aim-grade and 578,450 pounds of off-grade base resin
- 103 -
during UCAT-J run 10. Petitioner claims as QREs costs associated
with producing 2,668,500 pounds of aim-grade and 578,450 pounds
of off-grade base resin during UCAT-J run 10.
According to a PCD for DJH-2950H, UCC produced 132,324
pounds of aim-grade and 148,750 pounds of off-grade base resin
during UCAT-J run 12. Petitioner claims as QREs costs associated
with producing 132,800 pounds of aim-grade and 148,750 pounds of
off-grade base resin during UCAT-J run 12.
h. DJL-5420H and DJL-5143H (UCAT-J Runs 13 and
14)
Although UCC had successfully produced high density molding
base resins in the pilot plant using UCAT-J, it had never made
DJL-5420H (UCAT-J run 13) or DJL-5143H (UCAT-J run 14) at Star
before these runs.
UCC’s objectives for UCAT-J runs 13 and 14 were to: (1)
Produce requested quantities of each resin for customer
qualification (about four hopper cars for each product); (2) run
reactor 1 at normal Star rates with operability equivalent to
that achieved using M-1; (3) reach aim-grade production within a
specified period; and (4) produce no significant off-grade
material.
UCC was concerned about the risks of: (1) TEAl starvation;
(2) resin carryover; and (3) difficulties with CO kills, if they
were necessary. UCC planned for both of these runs to be short
because of the risk associated with UCAT-J.
- 104 -
Several operability issues occurred during the runs,
particularly minor sheeting during UCAT-J run 13, cold bands
after the transition to DJL-5143H, and the formation of spongy
agglomerates. A cold band is an area where the reactor wall is
cold and it indicates that there is enough static to cause resin
to stick to the walls and create sheeting. The spongy
agglomerates that formed were similar to the substances that
formed during UCAT-J run 1.
Despite these problems, UCC considered the runs to be a
success. However, because these were short runs, UCC would need
to continue to evaluate the resins to determine whether
continuity issues would arise on longer runs.
According to a PCD for DJH-5420H, UCC produced 696,181
pounds of aim-grade base resin during UCAT-J run 13. Petitioner
claims as QREs costs associated with producing 696,981 pounds of
base resin during UCAT-J run 13.
According to a PCD for DJL-5143H, UCC produced 1,006,947
pounds of aim-grade base resin during UCAT-J run 14. Petitioner
claims as QREs costs associated with producing 1,008,181 pounds
of aim-grade base resin during UCAT-J run 14.
i. DJM-1720H (UCAT-J Run 17)
DJM-1720H had never been made at Star before UCAT-J run 17.
Two of the goals of this run were to implement measures developed
by process R&D to control resin stickiness and TEAl levels (first
- 105 -
implemented in UCAT-J runs 15 and 16, discussed above) and to
demonstrate acceptable operability and continuity of UCAT-J in
reactor 2 with these products. The other run objectives
identified in pre-run documentation were to: (1) Produce the
requested quantities of resin for customer qualification (four
hopper cars); (2) run reactor 2 at normal production rates; (3)
reach aim-grade production within a specified period; and (4)
produce no significant off-grade material attributable to UCAT-J.
DJM-1720H is an LLDPE resin, which tends to be very sticky
and had shown poor flowability in previous runs. TEAl starvation
remained another significant operating issue. As in UCAT-J runs
15 and 16, to control resin stickiness process R&D recommended
that ethylene partial pressure be lowered below 90 psi. UCC
still considered this change to reactor conditions to be
experimental. UCC also planned to give the reactor periodic TEAl
shots to minimize TEAl starvation.
UCAT-J run 17 was generally successful. UCC controlled
resin stickiness through ethylene partial pressure, and UCC was
able to maintain good catalyst productivity. Overall,
operability and continuity were good throughout the run.
However, while flowability improved, it was still slightly worse
than the flowability achieved using M-1. Furthermore, there was
some TEAl starvation due to the TEAl feed system, though less
than during previous runs. Therefore, the information gained was
- 106 -
valuable to UCC, but process R&D still had some concerns.
Following UCAT-J runs 16 and 17 UCC planned to implement a new
TEAl feed system for all of Star. Ultimately this alleviated the
TEAl starvation issues.
According to a PCD for DJM-1720H, UCC produced 866,625
pounds of aim-grade and 520,100 pounds of off-grade base resin
during UCAT-J run 17. Petitioner claims as QREs the costs
associated with producing 895,700 pounds of aim-grade and 520,800
pounds of off-grade base resin.
III. Claimed Costs
One of petitioner’s expert witnesses, Wendi Hinojosa,16 was
responsible for costing the claim projects. Ms. Hinojosa was
qualified as an expert in the accounting systems and
documentation used by UCC in the credit years and the base
period. Petitioner claims as QREs incurred by UCC in connection
with the claim projects $23,356,600 for 1994 and $32,114,800 for
1995.
A. Cost Documentation Used
1. PCDs and MASs
The primary cost accounting records that Ms. Hinojosa used
to calculate the cost of the supplies used in the claim projects
were PCDs and material accounting summary reports (MASs). PCDs
16
Ms. Hinojosa’s qualifications are set out in the Opinion
section, below.
- 107 -
and MASs were part of UCC’s material accounting system used to
track variable costs (costs that vary with production) such as
raw materials, catalysts, and other materials used in the
manufacturing process. UCC used the material accounting system
during both the credit years and the base period. There were no
significant differences in UCC’s material accounting system and
related documentation during these two timeframes.
The PCD was UCC’s official cost accounting record for
products that it manufactured. PCDs contained detailed cost
information for every product that UCC manufactured, including
the materials and quantities used in production. PCDs were
produced monthly and annually, not for particular projects. The
PCD for any given year consisted of approximately 3,000 pages.
MASs are inventory control reports containing a transaction
summary for every material UCC manufactured or purchased, each of
which was assigned a unique product code. Material production
and consumption information was contained in both PCDs and MASs.
However, PCDs were organized by manufactured product, whereas
MASs were organized in numerical order by product code and listed
all transactions for each product code by location.
2. CMAI Data for Ethylene Byproducts
Additional products made during the manufacturing process of
the primary product were listed as byproducts on PCDs. UCC’s
- 108 -
material accounting system treated the cost of byproducts as a
reduction in the cost of the primary product.
Taft’s hydrocarbons unit made several ethylene byproducts
such as propylene, butadiene, dripolene, hydrogen, methane, and
acetylene. Because these byproducts are made from the same
starting materials as ethylene, it is difficult to separately
allocate the supply costs attributable to each byproduct. For
this reason, Ms. Hinojosa used historical 1994 and 1995 market
values of ethylene byproducts as a proxy for their supply costs.
These market values were provided by Chemical Market Associates,
Inc. (CMAI), a leading petrochemical industry consulting and
research firm.
Ms. Hinojosa used the byproduct values provided by CMAI to
calculate the supply costs incurred in conducting the UOP GA-155
project on the Olefins-1 unit’s C3 column, which produced
ethylene byproducts (such as propylene, butadiene, and dripolene)
as opposed to ethylene, which had already been separated off in
the C2 column. In addition, Ms. Hinojosa deducted these
byproduct values from Taft’s total ethylene production cost, from
which she calculated the supply costs for the Amoco anticoking
and sodium borohydride projects. This treatment of byproducts
avoided double-counting the supply costs incurred in conducting
the claim projects.
- 109 -
3. Wage Information
UCC’s accounting system tracked budgeted and actual period
costs (fixed costs, costs that do not fluctuate with production)
such as labor. UCC’s accounting system generated accounting
records known as account levels. Account levels are the best
source of information for calculating wage costs. However,
account levels were not available for the credit years.
Therefore, for the claim projects conducted in Taft’s
hydrocarbons unit (the Amoco anticoking, spuds, UOP GA-155, and
sodium borohydride projects), Ms. Hinojosa used the annual
salaries found on Forms W-2, Wage and Tax Statement, for specific
employees involved in the projects. For the UCAT-J project, Ms.
Hinojosa used Star budget reports that provided the total wage
cost during the claim years and allocated that cost using the
percentage of PE pounds produced during the UCAT-J runs relative
to Star’s total PE production during the same period. Wages
represented 1 percent of the total cost of all of the claim
projects.
4. R&D Budgets
Ms. Hinojosa did not refer to budgets prepared by UCC during
the credit years. UCC’s hydrocarbons R&D department did not
prepare formal budget proposals specific to individual projects,
but it did prepare an overall R&D budget that referenced various
projects that would occur during the year. The R&D budget
- 110 -
generally included wages, laboratory materials, travel, and
extraordinary expenses. Plant materials were generally included
in the plant budget, not the R&D budget. Accordingly, R&D did
not account for feedstock or fuel when estimating how much of its
budget would be allocated to projects conducted on commercial
plants.
B. Costs of the Amoco Anticoking Project
1. Supplies
Ms. Hinojosa calculated the supply costs of the Amoco
anticoking, spuds, and sodium borohydride projects on the basis
of the total ethylene manufacturing cost of Taft’s hydrocarbons
unit in 1994 and 1995. Ms. Hinojosa identified the materials as
material quantities used to manufacture ethylene at Taft from the
relevant PCDs and MASs.
In calculating Taft’s total ethylene production cost for
1994 and 1995, Ms. Hinojosa included only major components of
supplies that were supported by available accounting records.
Specifically, Ms. Hinojosa included certain materials purchased
from third-party vendors and certain internally produced
materials.
Ms. Hinojosa did not include any general plant utilities
such as electricity, treated water, nitrogen, or compressed air
in her calculations. However, Ms. Hinojosa did include the cost
of the fuel gases (such as natural gas, methane, and hydrogen)
- 111 -
used to fire Taft’s ethylene furnaces and the refrigeration used
in the cold section of the ethylene production process. Ms.
Hinojosa included these costs because it was necessary to rapidly
reduce the temperature of the raw material stream at various
points in the production process in order to maximize the
production of ethylene. To the extent that these costs are
considered utilities, Ms. Hinojosa considered them to be
extraordinary costs, different from general plant utilities,
because of the energy-intensive nature of the ethylene production
process relative to UCC’s other manufacturing units.
Ms. Hinojosa used the relevant pages from the 1994 and 1995
MASs to calculate UCC’s actual per-unit cost for both materials
purchased from third parties and internally produced materials.
She multiplied these actual unit costs by the quantities used (as
shown on the relevant PCDs and MASs) to derive the total cost of
materials used in manufacturing ethylene at Taft.
UCC was a net ethylene purchaser as it did not produce
sufficient amounts of ethylene to meet the raw material
requirements of its downstream products. UCC made up the
difference by purchasing ethylene from third-party suppliers.
Accordingly, to determine UCC’s ethylene cost, Ms. Hinojosa
calculated a pooled ethylene price based on the weighted average
of Taft’s ethylene production cost (derived from PCDs and MASs)
- 112 -
and the price that UCC paid for ethylene supplied by third
parties as reported in a hydrocarbons business report.
After calculating the total cost of materials used to
manufacture ethylene, Ms. Hinojosa subtracted the cost of
ethylene coproducts and byproducts to isolate the supply costs
attributable specifically to ethylene. Ms. Hinojosa obtained the
quantities of coproducts and byproducts from the relevant PCDs
and MASs. As discussed above, the unit costs of the deducted
byproducts were based on historical 1994 and 1995 market value
data provided by CMAI.
Using this methodology, Ms. Hinojosa determined that Taft’s
total ethylene production cost was $96,947,718 in 1994 and
$97,479,242 in 1995. Ms. Hinojosa calculated the supply costs
for the Amoco anticoking, spuds, and sodium borohydride projects
by allocating Taft’s total ethylene production costs in 1994 and
1995 according to (1) the duration of the projects and (2) the
percentage of the production capacity of Taft’s hydrocarbons unit
employed in the projects. Ms. Hinojosa did not add the cost of
any extraordinary supplies that were purchased specifically for
the claim projects. If UCC increased the supplies it used during
the projects or altered its production rate while conducting the
projects, these facts are not reflected in Ms. Hinojosa’s
calculations.
- 113 -
For the Amoco anticoking project, Ms. Hinojosa calculated
the supply costs by multiplying Taft’s average daily ethylene
production cost ($265,610 in 1994 and $267,066 in 1995) by (1)
the project duration (30 days in 1994, 173 days in 1995) and (2)
the fraction of the production capacity of Taft’s hydrocarbons
unit employed in the project (one-seventeenth). Petitioner
claims that the Amoco anticoking project lasted from the start of
the first pretreatment on November 29, 1994, until a furnace cold
turnaround in mid-August of 1995. Petitioner included the
materials cost for producing ethylene in all six (four treated
and two untreated) cracking sets.
To avoid double-counting of supplies used in conducting both
the Amoco anticoking project and the sodium borohydride project,
Ms. Hinojosa eliminated the supplies used during the 1-week
sodium borohydride project from her supply cost calculation for
the Amoco anticoking project.
Ms. Hinojosa calculated UCC’s supply QREs for the Amoco
anticoking project as $468,723.86 and $2,717,793.54 for 1994 and
1995, respectively.
2. Wages
For the projects conducted at Taft’s hydrocarbons unit, Ms.
Hinojosa determined wage rates for the employees who were
primarily involved in the projects and multiplied those rates by
the number of hours that the employees estimated they had worked
- 114 -
on the project. For the Amoco anticoking project, Ms. Hinojosa
determined that Mr. Hyde, Mr. Tregre, and Mr. Gorenflo spent 35,
5, and 2 hours working on the project in 1994 and that Mr. Hyde
spent 10 hours working on the project in 1995. Mr. Hyde’s wage
rate was $21 per hour, Mr. Tregre’s wage rate was $20 per hour,
and Mr. Gorenflo’s wage rate was $19 per hour. Ms. Hinojosa
derived the wage rates from the employees’ annual salaries,
decreased by estimated overtime and profit-sharing.
Ms. Hinojosa calculated petitioner’s wage QREs for the Amoco
anticoking project as $873 and $210 for 1994 and 1995,
respectively.
C. Costs of the Spuds Project
Petitioner’s claimed amount for supplies used during the
spuds project was also based on UCC’s total manufacturing costs
for 1995, which were then prorated between Olefins-1 and Olefins-
2 according to production capacity. Petitioner claims as QREs
one-seventeenth of its production costs for the 89 days after UCC
changed the spuds on furnace 3. Ms. Hinojosa calculated as QREs
$1,188,445.55 for supplies attributable to the spuds project in
1995.
Ms. Hinojosa calculated the wage costs for the spuds project
using the same methodology she used to calculate wage costs for
the Amoco anticoking project, discussed above. Ms. Hinojosa
determined that Mr. Tregre spent 70 hours in 1994 and 10 hours in
- 115 -
1995 on the project and that Mr. Gorenflo spent 10 hours in 1995
on the project. Ms. Hinojosa calculated as QREs $1,400 and $390
for wages attributable to the spuds project in 1994 and 1995,
respectively.
However, petitioner no longer claims any QREs attributable
to the spuds project.
D. Costs of the UOP GA-155 Project
1. Supplies
UCC conducted the UOP GA-155 project in the Olefins-1 unit’s
C3 column, downstream of the C2 column where ethylene was
separated from the process flow. The C3 column processed the
ethylene byproducts (propylene, butadiene, and dripolene). The
supply costs for the UOP GA-155 project are based on the cost of
the materials running through the C3 column during the test. Ms.
Hinojosa calculated this cost by multiplying the CMAI material
values for each of the byproducts by their respective feed rates
into the C3 column and the project duration. The claimed supply
costs include costs for plant feed, energy, and other costs of
manufacturing products in Olefins-1 for 179 days (from September
22, 1994, through March 21, 1995). Ms. Hinojosa also included
the costs of the UOP GA-155 additive, which were $14,077 and
$24,534 for 1994 and 1995, respectively.
- 116 -
Ms. Hinojosa calculated UCC’s supply QREs for the UOP GA-155
project as $20,707,920 and $23,117,359.20 for 1994 and 1995,
respectively.
2. Wages
Ms. Hinojosa calculated the wage costs for the UOP GA-155
project using the same methodology she used to calculate the wage
costs for the Amoco anticoking project, discussed above. Ms.
Hinojosa determined that Mr. Brandon spent 220 hours working on
the UOP GA-155 project during each of the credit years. Mr.
Brandon’s wage rate was $21 per hour. Ms. Hinojosa calculated
UCC’s wage QREs for the UOP GA-155 as $4,620 for each of the
credit years.
E. Costs of the Sodium Borohydride Project
Ms. Hinojosa calculated the claimed supply costs of the
sodium borohydride project using the same methodology she used to
calculate the claimed costs for the Amoco anticoking project,
discussed above.
Ms. Hinojosa calculated the supply costs for the sodium
borohydride project by multiplying Taft’s average daily ethylene
production cost in 1995 ($267,066) by (1) the project duration (7
days) and (2) the percentage of the production capacity of Taft’s
hydrocarbons unit employed in the project (approximately 67
percent). Accordingly, Ms. Hinojosa calculated UCC’s supply QREs
for the sodium borohydride project as 1,248,300.86 for 1995. The
- 117 -
production cost included $55,583 for the sodium borohydride
additive.
Ms. Hinojosa calculated UCC’s wage QREs as $4,620 for the
sodium borohydride project using the methodology she used to
calculate wage costs for the Amoco anticoking project, discussed
above. Ms. Hinojosa determined that Mr. Brandon spent 220 hours
working on the sodium borohydride test in 1995.
F. Costs of the UCAT-J Project
1. Supplies
For the UCAT-J project, Ms. Hinojosa used the PCDs for the
PE base resins made in the UCAT-J experimental runs to identify
the materials and material quantities used in the runs. For
UCAT-J runs 3 and 15, Ms. Hinojosa did not have a PCD for the
specific product that was made (DJM-1732H), and she accordingly
used a PCD for a similar product (DJM-1734H). Ms. Hinojosa did
not include any costs classified on the PCDs as utilities or the
costs of additives incorporated into base resins during
postreaction pelleting. Ms. Hinojosa then used 1994 and 1995
MASs to calculate the actual per-unit cost of purchased materials
used in the UCAT-J project. Because UCC used both purchased and
internally produced ethylene to manufacture PE, Ms. Hinojosa used
a pooled ethylene price.
Ms. Hinojosa used the 1994 and 1995 MASs to calculate the
unit costs of the UCAT-J reduction agents (DEAC and TnHAl) and
- 118 -
hydrogen mix used in UCAT-J runs. For the internally produced
UCAT-J precursor, Ms. Hinojosa used 80 percent of the standard
cost shown on the PCDs.
Petitioner claims as QREs for supplies $2,006,700 and
$4,670,900 for 1994 and 1995, respectively, for the UCAT-J
project.
2. Wages
The UNIPOL reactors in Star’s LP-3 unit operated
continuously during the UCAT-J credit year experimental runs,
with production staff supporting the reactors 24 hours per day on
12-hour rotating shifts. According to Ms. Hinojosa, the amount
of time spent by plant operators and other support staff did not
vary significantly for experimental UCAT-J runs as compared to
normal production runs.
Ms. Hinojosa calculated the wage QREs attributable to the
UCAT-J project by allocating Star’s total wages in 1994 ($8.92
million) and 1995 ($9.72 million) according to the percentage of
Star’s total PE production made during the UCAT-J experimental
runs in 1994 (2.1 percent) and 1995 (4.18 percent), adjusted for
reactor downtime.17
17
Ms. Hinojosa reduced wages for downtime in response to a
comment from Mr. Allen, one of respondent’s expert witnesses. In
response to another comment from Mr. Allen, Ms. Hinojosa also
calculated wages using an allocation based on the duration of the
runs instead of production. Ms. Hinojosa believes that the
impact of this change was insignificant and therefore did not
(continued...)
- 119 -
Petitioner claims as QREs for wages $167,839 and $351,040
for 1994 and 1995, respectively, for the UCAT-J project.
IV. Base Period Projects
The second special trial session focused on petitioner’s
revised base period computations (base period trial).18
Petitioner arrived at a revised base amount by identifying
additional activities that it believes constitute qualified
research within the meaning of section 41(d) (identified runs)
and calculating the cost of those identified runs.
A. Scope of the Trial
On September 15, 2006, petitioner filed a motion for partial
summary judgment seeking to: (1) Limit the scope of the evidence
at the base period trial to QREs incurred by UCC, as opposed to
petitioner’s entire consolidated group; and (2) shift the burden
of proof on the base period issues to respondent.
By an order dated January 17, 2007, the Court granted
petitioner’s motion in part and denied it in part, informing the
parties in pertinent part that: (1) Petitioner would bear the
burden of production with respect to its revised base period
computations; (2) for purposes of conforming the base period
computations to the methodology petitioner employed to compute
17
(...continued)
alter her methodology.
18
The “base period” includes the years beginning after Dec.
31, 1983, and before Jan. 1, 1989. See sec. 41(c)(3)(A).
- 120 -
the claimed credits, only evidence of the revised base period
computations for the legal entity for which additional credits
are claimed would be necessary; (3) in the above-described legal
entity computations, it would be necessary to produce evidence to
revise the base amount for businesses acquired by the legal
entity after December 31, 1983, and not disposed of before
January 1, 1994; and (4) if petitioner could show that any
dispositions that occurred before 1994 played no role in the
computation of QREs of the legal entities in the return as filed,
then petitioner would not have to account for dispositions of
those trades or businesses in conforming the base period
computations to the methodology used to claim additional credits
for the years at issue.
Because petitioner’s claimed credits all relate to alleged
QREs incurred by UCC as a single legal entity, the scope of the
base period portion of the trial was limited to research that UCC
conducted, including research conducted by any businesses that
UCC acquired after December 31, 1983, and did not dispose of
before January 1, 1994.
1. Organization of UCC’s Manufacturing Operations
During the Base Period
During the base period UCC operated its C&P business segment
as well as various other business segments, including consumer
products, carbon products, and industrial gases. As a result of
a divestiture policy that UCC pursued in the late 1980s and early
- 121 -
1990s, the C&P business segment was the only UCC business segment
remaining during the credit years. Accordingly, when petitioner
revised UCC’s base amount for QREs incurred at UCC’s
manufacturing plants during the base period, petitioner included
only QREs that were incurred within UCC’s C&P business segment.
During the base period UCC’s C&P business consisted of four
divisions that corresponded to product groupings: (1) The
industrial chemicals division; (2) the polyolefins division; (3)
the solvents and coatings materials division; and (4) the
specialty chemicals division.
The industrial chemicals division encompassed 19 separate
manufacturing units that collectively produced ethylene and other
olefins, ethylene oxide/ethylene glycol, various ethylene oxide
derivatives, and other products at Taft; Seadrift; UCC’s Texas
City, Texas plant (Texas City); UCC’s Institute, West Virginia,
plant (Institute); and UCC’s Washougal, Washington, plant
(Washougal).
The polyolefins division encompassed six manufacturing units
that collectively manufactured commodity and specialty PE
products at Seadrift and Star as well as a wire and cable
compounding plant in Bound Brook. UNIPOL was a part of the
polyolefins division during the base period and was the largest
consumer of R&D funding within the division.
- 122 -
The solvents and coatings materials division encompassed 21
manufacturing units that collectively manufactured glycol ethers,
acrylates, and various other solvents and coatings at UCC’s Taft,
Seadrift, Texas City, Institute, and South Charleston plants, as
well as latex products at several small production facilities
across the country.
The specialty chemicals division encompassed 13
manufacturing units that collectively manufactured a variety of
low-volume, high-performance specialty chemicals, including
acrolein derivatives, alkyl alkanolamines, Cellosize, and Polyox
at Taft, Institute, and South Charleston.
2. Acquisitions and Dispositions Between the Claim
Years and the Base Period19
a. Acquisitions
On November 16, 1990, UCC acquired particular assets of Rohm
& Haas Co. (Rohm & Haas). The acquired assets included chemical
formulas and other intellectual property associated with Rohm &
Haas’s worldwide surfactant and alkylphenol business under the
trade name Triton (Triton assets). Surfactants are a family of
organo-silicone molecules, including detergents and hard-surface
cleansers. Following the sale of the Triton assets, all
associated technical data and intellectual property were
transferred to UCC.
19
Acquisitions and dispositions that do not affect
petitioner’s revised research credit computations are omitted.
- 123 -
During the base period the Triton business represented a
mature technology. Rohm and Haas had not performed any work to
improve or add products to its portfolio in many years. During
the base period and until the sale of the Triton assets to UCC,
it was Rohm & Haas’s practice to manage the Triton business as a
“cash cow”, harvesting substantial amounts of cash from the
business while investing only limited resources for research and
growth.
Rohm & Haas treated its sale of the Triton assets and its
obligations under various agreements made in connection with the
sale as a disposition of a major portion of a trade or business
for purposes of the research credit computation. Likewise, UCC
treated its purchase of the Triton assets and its obligations
under the various agreements as an acquisition of a major portion
of a trade or business for purposes of the research credit
computation.
In 1990 UCC acquired the Norkool business from Quantum
Chemical Corp. The Norkool products included industrial coolants
and antifreeze formulations, corrosion inhibitor packages, and
cooling system cleaners. During the base period one person was
assigned to provide R&D support for most of the Norkool business,
although additional R&D support analyzed Norkool’s fluids to
- 124 -
ensure that they were properly balanced. In addition, there were
engineers available to provide assistance if necessary.20
In 1990 UCC acquired the worldwide Polyphobe thickeners
business and assets from De Soto, Inc. The Polyphobe thickeners
were used in the formulation of latex paints.21
b. Dispositions
UCC’s original base period QREs reflected allowable
adjustments under section 41(f)(3)(B) attributable to
dispositions by UCC of the major portion of a trade or business
or the major portion of a separate unit of a trade or business.
During the credit years there were no dispositions by UCC of the
major portion of a trade or business or the major portion of a
separate unit of a trade or business for which petitioner must
adjust its base period QREs or gross receipts under section
41(f)(3)(B) other than the dispositions reflected in the base
period QREs and gross receipts reported on UCC’s original
returns.
UCC divested itself of its home and automotive, agricultural
products, film packaging, engineering polymers and advanced
composites, worldwide metals, and battery products businesses in
1986. UCC sold a 50-percent interest in its carbon products
20
None of petitioner’s original base period QREs were
attributable to the Norkool business.
21
None of petitioner’s original base period QREs were
attributable to the Polyphobe thickeners business.
- 125 -
business in 1991. UCC spun off its industrial gases business in
1992. Before January 1, 1994, UCC divested itself of the
following additional businesses: Primary alcohol ethoxylates,
polycrystalline silicon, urethane polyether polyols and propylene
glycol, silicones and urethane catalysts, coatings service,
phenolic resins, and phenoxy resins.
3. UCC/Shell Polypropylene Business
a. The Cooperative Undertaking
On December 22, 1983, UCC and Shell formed a tax partnership
called the Cooperative Undertaking, pursuant to a legal agreement
entitled the “Cooperative Undertaking Agreement” (CUA). UCC and
Shell each contributed goods and services in return for a 50-
percent interest in the Cooperative Undertaking. According to
the CUA, the purpose of the Cooperative Undertaking was to
develop and adapt UCC’s UNIPOL technology to incorporate Shell’s
catalyst technology and create a combined commercial process for
the manufacture of polypropylene (combined commercial process).
The Cooperative Undertaking planned to license the combined
commercial process to third parties. Shell was also interested
in producing polypropylene using the combined commercial process.
The CUA envisioned a three-phase process.22 In phase I, UCC
and Shell would develop acceptable pilot plant operating
22
As discussed below, some of the activities envisioned by
the CUA were not actually performed by the Cooperative
Undertaking.
- 126 -
conditions and produce acceptable polypropylene resin. In Phase
II, UCC would construct a demonstration plant at Seadrift and
scale up manufacture of polypropylene resin from the pilot plant
to the demonstration plant. In addition, Shell would develop
preliminary commercial markets for the sale of cooperatively made
polypropylene resin using the combined commercial process. In
phase III, certain limited licenses between UCC and Shell would
become effective; UCC and Shell would operate the demonstration
plant to produce cooperative polypropylene resin using the
combined commercial process; UCC would solicit, grant, and
administer third-party licenses with Shell’s assistance; and UCC
and Shell would continue to cooperate to improve the combined
commercial process. On January 29, 1987, phase II ended and
phase III began.
Under the CUA, UCC and Shell each paid their own costs for
R&D covered by the CUA and retained sole intellectual property
rights for information they developed separately during phases I
and II. However, UCC and Shell would share all net licensing
revenue equally during phase III. UCC and Shell would jointly
own any intellectual property jointly developed during any phase.
UCC and Shell agreed that the Cooperative Undertaking was a
partnership solely for tax purposes. The Cooperative Undertaking
accordingly filed Federal and State partnership tax returns with
UCC serving as the tax matters partner. However, the CUA
- 127 -
expressly excluded from the CUA tax partnership: (1) All
research activities conducted individually by UCC and Shell
during phases I and II; and (2) all activities conducted by
Seadrift Polypropylene Co. (SPC). As discussed below, SPC was to
conduct all manufacturing activities using the combined
commercial process and the Cooperative Undertaking would not
engage in any manufacturing activities or plant-based
experiments.
b. SPC
On March 21, 1984, UCC and Shell formed SPC as a partnership
under the laws of the State of Texas. UCC and Shell each
contributed goods and services in return for a 50-percent
interest in SPC. SPC filed Federal and State partnership tax
returns, with Shell serving as the tax matters partner and
providing accounting services.
The purpose of SPC was to construct and operate a
demonstration manufacturing plant, the P-1 unit, which would be
used to commercialize the combined commercial process developed
by the Cooperative Undertaking, demonstrate the combined
commercial process to licensees and potential licensees, and
produce polypropylene. Only SPC, not the Cooperative
Undertaking, would conduct polypropylene manufacturing
operations.
- 128 -
Also on March 21, 1984, SPC retained and designated UCC as
an independent contractor to design and construct the P-1 unit.
SPC leased existing plant facilities and land from UCC so that
UCC could build the P-1 unit within the confines of Seadrift.
Under the contract signed with SPC (the engineering and
construction contract), SPC paid UCC a fixed price for the design
and construction work on the P-1 unit. Under the engineering and
construction contract, UCC would own any intellectual property
that it developed in the course of designing and constructing the
plant under the contract. Petitioner did not include any
activities that occurred under the engineering and construction
contract during the base period in either its original or revised
base period calculations.
Pursuant to another agreement between UCC and SPC (the
operating agreement) dated March 21, 1984, SPC retained UCC as an
independent contractor to serve as the operator of the P-1 unit.
In this capacity, UCC initially incurred the costs of SPC’s
polypropylene manufacturing operations, including variable costs
such as raw materials and period costs such as plant labor. UCC
purchased polypropylene and catalysts directly from Shell. UCC
submitted monthly invoices for these costs to SPC, and, pursuant
to the operating agreement, SPC reimbursed UCC for these costs.
The operating agreement provided that any intellectual property
discovered or developed by UCC in the course of performing its
- 129 -
duties would be governed by the CUA, not the operating agreement
or any other SPC agreement.
SPC did not maintain a separate set of books and records.
However, in its capacity as an independent contractor UCC
maintained SPC’s accounting records and identified SPC as a
separate business.
In the mid-1990s UCC sued Shell and various other entities,
claiming, inter alia, that Shell had violated its fiduciary duty
with respect to the joint venture. The litigation settled, and
on January 18, 1996, UCC acquired Shell’s polypropylene business
assets, including Shell’s interest in SPC, as part of the
settlement.
c. Petitioner’s Base Amount Recalculation
Petitioner did not include the cost of any research
conducted at P-1 during the base period in its base amount
because petitioner believes that SPC, not UCC, incurred the costs
of that research. However, petitioner identified 138 runs that
occurred at P-1 during the base period that it would treat as
qualified research in the event that the Court finds that UCC,
not SPC, incurred the costs of these runs (polypropylene runs).23
Petitioner determined that the 138 runs that occurred at P-1
during the base period cost $29,508,628.41.
23
The criteria used to identify the research that petitioner
believes constitutes qualified research within the meaning of
sec. 41(d) are discussed below.
- 130 -
B. Base Period Projects
1. UCC’s Focus on R&D During the Base Period and
Credit Years
UCC viewed manufacturing process improvements as important
during both the base period and the credit years. UCC’s
manufacturing process was continuously evolving throughout these
years. In particular, in the early 1990s William Joyce, the
president of UCC’s polyolefins division, implemented a new
process improvement program designed to lower costs. Mr. Joyce
implemented this program as part of a program to increase UCC’s
licensing business.
2. The Role of R&D and Engineering at UCC’s
Manufacturing Plants
During the base period, R&D provided plant support to all
four C&P divisions. R&D supported the operation and safety of
the plants and monitored the quality of the products. UCC’s
engineering and manufacturing departments also helped to develop
UCC’s manufacturing process. Plant-based experiments were
typically carried out through multifunctional teams.
There was no formal rule during the base period regarding
how many successful runs of a new product must be conducted
before the product is deemed to be commercial. However, in the
polyolefins division UCC generally preferred to conduct at least
three runs on a new product before deeming it commercial.
- 131 -
3. Petitioner’s Identification of Plant-Based
Qualified Research Activities Conducted During the
Base Period
a. Dr. Wadia’s Assignment
Parvez H. Wadia, one of petitioner’s expert witnesses, was
qualified in the base period trial as an expert in conducting R&D
related to the manufacturing of chemicals and plastics.24 Dr.
Wadia’s task was to identify all activities that UCC conducted at
its domestic C&P manufacturing facilities during the base period
that Dr. Wadia believed constituted “qualified research” as
defined by petitioner’s counsel. The criteria that Dr. Wadia
used to select the identified runs are referred to as the
“qualified research criteria”, and the activities that Dr. Wadia
believes satisfy the qualified research criteria are referred to
as the “identified runs”.25 Another of petitioner’s expert
witnesses, Sheri L. Toivonen, calculated the costs of the
identified runs.26
Dr. Wadia was not familiar with the claim projects before
beginning his task. At petitioner’s request Dr. Wadia later
compared the identified runs with the spuds project. However,
24
Dr. Wadia’s qualifications are set out in the Opinion
section, below.
25
We make no finding at this time whether the identified
runs constituted qualified research within the meaning of sec.
41(d).
26
Ms. Toivonen’s qualifications are set out in the Opinion
section, below.
- 132 -
Dr. Wadia was not asked to opine whether the claim projects
satisfy the qualified research criteria or to identify activities
similar to the claim projects that occurred during the base
period.
Dr. Wadia was assisted by five other professionals from Mid-
Atlantic Commercial Research, a subsidiary of the Mid-Atlantic
Technology, Research & Innovation Center (MATRIC) (collectively,
MATRIC team27). MATRIC’s largest client is the United States
Government. The MATRIC team had more than 224 years of
experience in the chemicals and plastics industry and 171 years
of experience with UCC. None of the MATRIC team members
testified as fact witnesses during the trial.
The qualified research criteria closely tracked the
definition of qualified research under section 41(d) and section
1.41-4, Income Tax Regs.28 The criteria required Dr. Wadia to
consider five key questions: (1) Does the research activity seek
to eliminate an uncertainty concerning the development or
improvement of a business component, which can be either a
product or a process? (2) Does the research activity seek
technological information? (3) Does substantially all of the
27
Although the company that petitioner retained was a
subsidiary of MATRIC, the parties generally refer to the team as
being from MATRIC. We adopt that designation for convenience.
28
As we explain infra note 42, respondent concedes that
petitioner may rely on sec. 1.41-4, Income Tax Regs., even though
it is effective for years ending on or after Dec. 31, 2003.
- 133 -
research activity involve elements of a process of
experimentation? (4) Does the research activity relate to a
qualified purpose? (5) Is the activity an “excluded activity”?
Dr. Wadia was provided with a list of excluded activities that
tracked section 41(d)(4). To be consistent with petitioner’s
selection of the claim projects, petitioner asked Dr. Wadia to
identify only plant-based experiments that occurred at UCC’s
domestic manufacturing facilities.
b. Dr. Wadia’s Methodology
Dr. Wadia and his team spent approximately 5,650 hours
selecting the identified runs. This time was spent reviewing
over 120,000 pages of technical documents, conducting electronic
searches, interviewing 157 current and former Dow and UCC
employees, and visiting 42 of Dow’s unit libraries and 69
satellite libraries. The technical documents that the MATRIC
team reviewed included, but were not limited to, R&D project
reports and project memoranda, definition of technology reports,
technology manager’s reports, UNIPOL strategic run plans and
tactical run plans, and latex process and commercial product
information. Dr. Wadia reviewed a few FOCRs, but most of the
FOCRs that had been produced during the base period were no
longer available. Dr. Wadia’s project identification
investigation was highly interactive and often complex,
nonlinear, and iterative.
- 134 -
For each of the identified runs, Dr. Wadia defined the
activity by providing: (1) A run description; (2) the
manufacturing plant locations and specific manufacturing units;
(3) the product(s) made during the activities and their
production volumes; (4) the raw materials and catalysts used to
make the product(s); (5) the start and end dates of the
activities; (6) any other relevant scientific information; and
(7) the documents related to the identified runs.
Dr. Wadia used a somewhat modified process with respect to
UCC’s crystal products business based at Washougal, which UCC
sold to an unrelated third party in 1999. Dr. Wadia used a “top-
down” approach to estimate how much UCC spent on plant-based
experimentation for this business. To make this estimation, Dr.
Wadia assumed that: (1) Annual sales for the business ranged
from $9 to $10 million per year; (2) manufacturing cost as a
percent of sales was 60 percent; and (3) about 5 to 10 percent of
the crystal growth stations for manufacturing products were
dedicated to experimental work. The plant manager for the
Washougal crystal products plant confirmed that he believed that
these were reasonable estimates.
c. Dr. Wadia’s Conclusions
Dr. Wadia identified a total of 793 separate plant-based
activities that he believes satisfy the qualified research
- 135 -
criteria.29 Dr. Wadia originally identified 764 runs in his
opening expert report dated August 3, 2007. After receiving and
reviewing additional information, Dr. Wadia identified 29
additional runs that he listed in his supplemental expert report
dated October 26, 2007. Dr. Wadia also revised the duration and
production of runs 408, 574, and 777 at that time.
The MATRIC team considered thousands of projects. Dr. Wadia
rejected some projects at the outset because they occurred
outside the base period, were not conducted at a manufacturing
facility, or otherwise clearly did not satisfy the qualified
research criteria. The MATRIC team then discussed the remaining
potential projects, and Dr. Wadia decided whether they satisfied
the qualified research criteria. The MATRIC team did not retain
a list of potential projects that were discussed but not included
on the list of identified runs. Dr. Wadia was satisfied that the
MATRIC team had sufficiently analyzed each project and did not
feel that such a list was necessary.
Dr. Wadia listed the identified runs as runs 1 through 806
on the exhibits to his initial and supplemental expert reports.30
Dr. Wadia later produced a table of identified runs that includes
29
These runs are listed as runs 1 through 806. Dr. Wadia
did not identify any runs as run 121, 278, 524, 525, 526, 527,
679, 687, 688, 689, 690, 691, or 775.
30
As discussed above, Dr. Wadia has not identified any runs
as Run 121, 278, 524, 525, 526, 527, 679, 687, 688, 689, 690,
691, or 775.
- 136 -
comments on the runs. In his expert report Dr. Wadia discusses
the specific manufacturing units that conducted the runs and
provides additional narrative information regarding many of the
runs.
d. Petitioner’s Concessions
As a result of fact witness testimony at trial, petitioner,
with the assistance of Dr. Wadia, conceded that 14 additional
plant-based research activities conducted during the base period
satisfy the qualified research criteria (runs 807 through 820).
Ms. Toivonen summarized each of the conceded activities, provided
references to pertinent testimony and documents, and provided
calculations of the cost of the research activities on the basis
of the referenced information and relevant accounting records.
The pertinent conceded runs are discussed below.31
i. Nalco Inhibitor Antifouling Test (Run
816)
Dr. Wadia did not include the Nalco inhibitor antifouling
test among the first 793 identified runs, but petitioner later
conceded that this test satisfies the criteria for qualified
research and added this test as run 816.
31
As discussed in the Opinion section, respondent argues
that the fact that Dr. Wadia did not initially include runs 807
through 820 illustrates a flaw in his methodology. While we
state no opinion on respondent’s argument at this time, we
provide pertinent facts regarding the runs that respondent
addresses in his argument.
- 137 -
During the base period UCC worked with Nalco Chemical
(Nalco) to develop a type of antioxidant or fouling inhibitor to
inject into the C2 column, which would then enter the C3 column
and prevent fouling in that column. If successful, this would
minimize the number of times the reboiler had to be cleaned and
extend the number of months the reboiler could operate without
being shut down.
Nalco approached UCC with a fouling inhibitor for UCC to
test. UCC most likely would have prepared an FOCR for the
installation of the pumping facilities to inject the inhibitor
and for the addition of a new chemical into the plant.
UCC tested the Nalco inhibitor for 5 to 6 months. UCC
personnel monitored the steam pressure on the C3 column reboiler
and checked the reboiler for fouling during the test.
The inhibitor extended the length of time the reboiler ran
without being cleaned and the steam pressure was reduced. As a
result of these findings, UCC determined that the Nalco inhibitor
worked as it was intended to work and did not perform additional
testing.
Ms. Toivonen determined that the Nalco inhibitor antifouling
test cost $7,192,670.85.
ii. Wastewater Activity (Run 809)
Another activity that Dr. Wadia did not include as an
identified run in his original or supplemental report was a plant
- 138 -
test performed at Taft’s wastewater treatment facility. UCC
received a tank truck of wastewater from another plant and
processed the tank through the wastewater treatment facility at
Taft.
A technology highlights memorandum describes the activity as
a “plant test” that would be run in mid-November of 1985. The
activity would involve dumping half of the tank into the
wastewater facility at a rate of 2 gallons per minute and
monitoring for odor. UCC would rapidly dump the remaining 2,900
gallons in two stages. In the first stage UCC would dump 1,450
gallons into the acrylics sump. If that caused odor problems,
UCC would dump the remaining 1,450 gallons into a different sump.
If the dumping of the first 1,450 gallons did not cause odor
problems, UCC would also dump the remaining 1,450 gallons into
the acrylics sump.
Ms. Toivonen calculated the QREs associated with this
activity to be $8,441.65.
iii. Rohm & Haas Runs (Runs 813 and 814)
Dr. Wadia included two runs associated with the Triton
assets in his expert witness report as identified runs. Ms.
Toivonen calculated the cost of these two runs as $1,489.06 and
$39,630.61, respectively. Petitioner later conceded that two
additional runs (runs 813 and 814) associated with the Triton
asset should have been included in its base amount calculation.
- 139 -
In her second supplemental expert witness report Ms. Toivonen
calculated the costs of these runs as $21,826.32 and $345,683.94,
respectively. This concession doubled the number of identified
runs associated with the Triton assets and increased the costs of
the identified runs associated with the Triton assets nearly
tenfold.
e. Activities That Were Not Identified Base
Period Activities
Respondent argues that Dr. Wadia should have included the
following additional activities on the list of identified runs.
i. NOx
Dr. Wadia did not include as identified runs any activities
related to NOx. “NOx” refers to various compounds of nitrogen
and oxygen that can be contained in catalytically cracked
refinery gases that are sometimes fed to ethylene units. NOx can
accumulate in the cryogenic sections of commercial ethylene
units. These cryogenic sections, called “cold boxes”, separate
very low boiling point materials in the cracked furnace gas as
part of the ethylene recovery process. Nitric oxide (NO), a
compound of NOx, has very low boiling and freezing points.
Therefore, nearly all of the NO in the ethylene unit cracked gas
stream enters the cold box. NO may be oxidized to NO2 in the
cold box by the presence of oxygen, and NO2 can react with
additional NO to form N2O3.
- 140 -
Some NOx compounds (NO2 and N2O3 in particular) freeze and
boil at significantly higher temperatures than NO. Therefore,
NOx compounds can freeze in the cold box and accumulate. The
accumulation of NOx compounds in the cold box can present a
significant safety hazard. Some NOx compounds are highly
reactive and can combine with other materials, in particular
butadiene, in the cold box to form NOx gums. NOx compounds also
react with ammonia to form ammonium nitrate and nitrite (NOx
salts). While stable at the very low cold box temperatures, NOx
gums and NOx salts can become unstable and explosive when the
cold box is warmed. NOx gums may explode at temperatures well
below ambient, while NOx salts require warmer temperatures to
explode. Even small amounts of explosive gums can be a serious
safety hazard.
UCC was aware of the potential safety hazards of NOx
accumulation in cold boxes long before the base period. UCC had
not had an NOx-related explosion before the base period, but it
had been aware of NOx-related explosions in other cryogenic gas
processing units in the chemical industry.
By 1982 it was generally known that thawing a cold box would
remove NOx that had accumulated in the cold box. A controlled
thaw involves shutting off the cracked furnace gas feed,
gradually warming the cold box to ambient temperature, and
injecting purge gas through the piping to flush out the NOx
- 141 -
compounds. It was also generally known how fast to warm the cold
box and to what temperature to warm the cold box to minimize the
risk of explosion. Furthermore, it was generally known that
after a thaw a cold methanol wash could be used to remove NOx
gums from the cold box equipment and at what temperature the cold
methanol wash should be used.
During the base period it was industry practice to thaw cold
boxes periodically. UCC thawed its cold boxes approximately once
per year during the 1980s but had not used a methanol wash until
July 1985. Before the base period UCC had never quantified the
amount of accumulated NOx or the rate of NOx accumulation in any
of its olefins units’ cold boxes.
By late November 1984 operations personnel at Texas City had
determined that they did not have enough information to define a
safe run length for the cold box. During several earlier thaws
UCC had checked the effluent from the Texas City cold box for
NOx. UCC found NOx in the effluent on every occasion but never
quantified the amount or determined the form or type of NOx
compounds present in the Texas City cold box. UCC used a
chemical method called the Griess-Saltzman method to detect the
presence of NOx. UCC also used Draeger tubes (another analytical
technique) to measure NOx concentrations in the cold box vent
gas. UCC thought that the NOx that was accumulating might be NOx
gums.
- 142 -
In December 1984 Luis Batiz, an engineer in Texas City’s
olefins unit, sent a letter to the hydrocarbons R&D technology
manager expressing concern about the potential accumulation of
NOx compounds in the Texas City cold box and requesting
assistance in developing a standard philosophy and general
procedure that could be implemented in Texas City to thaw the
cold box. The Texas City olefins unit was particularly
susceptible to NOx accumulation because it used refinery gas,
which was known to contain NOx, as a raw material. At that point
the Texas City cold box had been operating continuously for about
1 year without a thaw. UCC had no way to estimate how much NOx
had accumulated because UCC had not previously quantified the
accumulation of NOx.
Mr. Batiz’s request was assigned to Dr. Henstock, a project
scientist in UCC’s hydrocarbons R&D group, in early 1985. Dr.
Henstock was based at the technical center in South Charleston.
Dr. Henstock researched the issue, reviewed the situation at
Texas City, and concluded that the Texas City personnel did not
have enough information to determine a safe run length or set
their own operating guidelines. In February of 1985 Dr. Henstock
informed his supervisors that while the hazards of NOx had been
known for some time, the formation of NOx deposits and their
removal was still not well understood. Dr. Henstock decided to
conduct a controlled thaw as soon as was practical and measure
- 143 -
the amount of NOx that was liberated from the cold box to
determine the rate at which it was accumulating. UCC intended to
use this information to determine how frequently the cold box
must be thawed.
In order to better analyze the amount of NOx that came out
of the cold box, UCC’s South Charleston technical center built a
prototype of a photoionization analyzer. The photoionization
analyzer gave readings every 2 to 3 minutes, recorded data
automatically, and could be left unattended. UCC believed that
this method for analyzing NOx was superior to the Griess-Saltzman
method because the Griess-Saltzman method did not give readings
frequently, was very time consuming, required skill to operate,
and could not be operated unattended.
The first Texas City thaw began on February 19 and ended on
February 24, 1985. This was UCC’s first attempt to measure
accumulated NOx. During the thaw an operator noticed a bright
blue liquid leaking from a cold box valve, which was not
expected. Dr. Henstock discussed this phenomenon with some of
his colleagues in South Charleston, and they determined that the
material was N2O3, which is not the form of NOx compound that Dr.
Henstock had expected. Dr. Henstock then vented the material
into the atmosphere while measuring the concentration and total
flow rate in order to calculate the total amount. Dr. Henstock
estimated that about 100 pounds of material had built up in the
- 144 -
cold box. Much of the NOx that had entered the system was from
purchased refinery gas. Dr. Henstock did not determine whether
NOx gums had formed. The rest of the cold box thaw was completed
uneventfully and the cold box was returned to normal operation.
Dr. Henstock documented the February 1985 cold box thaw in a
project report dated August 13, 1985. The project report
summarized what occurred during the thaw and documented the
results. Dr. Henstock was surprised and concerned about the
amount of NOx that he found. Accordingly, Dr. Henstock
recommended that the thaw be repeated in a few months to see how
much NOx would accumulate in that time. Dr. Henstock also
recommended that a methanol wash be performed to determine
whether NOx gums had formed. UCC decided to have an external
consultant perform laboratory work to understand the hazards of
N2O3.
Recognizing the potential safety implications of the
significant quantities of NOx found during the February 1985
thaw, UCC made the results of the thaw available to the olefins
industry during the summer of 1985. The findings of the February
1985 thaw resulted in the formation of the Task Group on Nitrogen
Oxides in Ethylene plans, which met four times from October 1985
to October 1986. The task group issued a report of its findings
that identified potential problems regarding NOx and made
suggestions on how to safely handle equipment likely to contain
- 145 -
NOx. Dr. Henstock also wrote a paper on NOx that was presented
at an American Institute of Chemical Engineers (AIChE) meeting in
the spring of 1986.
Following Dr. Henstock’s recommendations, UCC performed
another thaw of the Texas City cold box in July 1985, followed by
a methanol wash. This was the first methanol wash that UCC had
performed at any of its olefins facilities. UCC determined that
less than 3 pounds of NOx had accumulated and that no NOx gums
had formed.
Dr. Henstock wrote another project report to document the
results of the July 1985 thaw. Because of the small amount of
NOx accumulation found and the absence of NOx gums during this
thaw, Dr. Henstock regarded the NOx issue as a manageable safety
hazard at Texas City. Dr. Henstock postulated that much of the
NOx passed through the cold box and flowed out in the fuel
stream. Dr. Henstock recommended that a method should be
developed for monitoring the NOx balance around the Texas City
cold box, such as the installation of a permanent NOx analyzer.
Dr. Henstock also recommended that future thaws at all locations
be monitored closely to determine the amount of NOx accumulation.
In the meantime, Dr. Henstock recommended that the Texas City
cold box be thawed at least every 12 months. Dr. Henstock did
not believe that methanol washes would be necessary at Texas City
- 146 -
in the future, but he recommended methanol washes at locations
where NOx and butadiene could both enter the cold box.
In January 1986 UCC performed a thaw and methanol wash of
the cold box and one of the two methane columns at Seadrift.
Seadrift did not use refinery gas as a raw material. Therefore,
UCC assumed that NOx accumulation at Seadrift was less likely
than at Texas City. However, UCC had detected NOx at several
points within the process, which indicated that there might be
NOx present. UCC also believed that NOx and butadiene
occasionally contacted one another, which could potentially cause
the formation of NOx gums. UCC was concerned about an incident
at Seadrift in which thaw gas flowing out of piping was found to
be unexplainably warm during a cold box thaw in 1979. UCC had
never quantified the accumulation of NOx or NOx gums or used a
methanol wash at Seadrift before this thaw.
During the January 1986 thaw at Seadrift, UCC used the same
general procedures it had used at Texas City. UCC did not find
any NOx accumulation or NOx gums in the cold box. Dr. Henstock
documented the results of the January 1986 thaw in a project
report dated June 16, 1986. Dr. Henstock concluded that the warm
thaw gas outlet pipe incident during the 1979 thaw was probably
not related to NOx. Dr. Henstock also developed guidelines for
future management of potential NOx hazards at Seadrift. Dr.
Henstock determined that future Seadrift cold box thaws should be
- 147 -
closely monitored for NOx in the outflowing warmup gas but that
methanol washes would not be required unless evidence of NOx gum
formation developed.
UCC followed the plans recommended after the July 1985 thaw
at Texas City and conducted another thaw at Texas City in January
1987. UCC improved the procedure it had previously used at Texas
City by using a drain vaporizer when NOx levels were very low.
UCC purged less than 1 pound of NOx during the January 1987 thaw.
Dr. Henstock documented the results of the January 1987 thaw
in a project report dated March 11, 1987. Dr. Henstock concluded
that the smaller accumulation was probably due to decreases in
the level of NOx in the refinery gas. Dr. Henstock recommended
careful monitoring of the refinery gas NOx concentrations once
the permanent analyzer was installed later in 1987. Dr. Henstock
also recommended that it was safe to increase the time between
thaws to 24 months as long as the low NOx concentrations in the
feed streams persisted, but he suggested reevaluating the time
interval between thaws according to the results of the next thaw.
In March 1988 UCC measured NOx accumulation during a normal
plant shut down and cold box thaw at Taft. Taft’s Olefins-2 unit
had run continuously for over 3 years at that point. UCC had
never attempted to quantify the accumulation of NOx or NOx gums
at Taft before this thaw. Taft did not use refinery gas as a raw
material, but the design of the separations system at Taft
- 148 -
allowed some butadiene (known to form NOx gums) to enter the cold
box. UCC analyzed the process streams feeding and leaving the
cold box at Taft on three different occasions before the March
1988 thaw but found no measurable NOx.
During the March 1988 thaw UCC monitored the effluent for
NOx and detected less than a pound of NOx. UCC did not detect
any NOx gums or polymers on a visual inspection of the cold box
and methane column feed separators. Dr. Henstock concluded that
future monitoring of the Taft cold box by the hydrocarbon R&D
group would not be necessary. However, Taft personnel would
continue to check the cold box streams for NOx with Draeger tubes
at any future shutdowns.
None of the thaws discussed above involved the changing of
any variables before the NOx accumulation was measured. During
each thaw UCC collected data for the purpose of determining how
fast NOx was accumulating under normal conditions and how long
the cold boxes could safely operate without being thawed. Dr.
Henstock continued to study NOx into the 1990s and still
considered NOx accumulation to be a safety issue at least as late
as 2002.32
32
A serious NOx gum explosion occurred at the Shell Olefins
plant in Berre, France, in 1990. A second industry task group
was formed in response to this explosion. However, these events
did not occur during the base period or the credit years, and
accordingly we do not address them in detail here. A minor NOx-
related explosion also occurred at Texas City in 1994. However,
(continued...)
- 149 -
Dr. Wadia did not include any NOx-related activities on the
list of identified runs because the MATRIC team concluded that
they did not involve a process of experimentation but merely
constituted data collection and monitoring. Accordingly, Ms.
Toivonen did not include the cost of any NOx-related activities
in her expert witness report.
Roy T. Halle, one of respondent’s expert witnesses,
estimated that the cost of the ethylene that UCC produced at
Texas City, Seadrift, and Taft during the periods leading up to
the cold box thaws was about $443 million.33
ii. John Zink Co. Orders
UCC purchased equipment from the John Zink Co. during the
base period. UCC conducted tests on equipment purchased from the
John Zink Co. during the base period that Dr. Wadia did not
include on his table of identified runs. These tests generally
consisted of testing the products to see whether they functioned
properly.
iii. Star Pelleting
In 1986 UCC installed one of the industry’s largest and most
effective pelleting lines at Star. UCC tested the new equipment
32
(...continued)
none of the claim projects relate to this explosion.
Accordingly, we need not discuss the event further.
33
Mr. Halle’s qualifications are set out in the Opinion
section, below.
- 150 -
to validate that everything functioned as was expected. However,
UCC did not take any steps to further develop the new pelleting
line. UCC did not have any significant difficulties with the
startup of the new pelleting line.
iv. Naphtha Analysis
In 1987 UCC’s R&D department analyzed virtually every
naphtha shipment that arrived at Taft to determine the
composition of the naphtha. Naphtha is not a standard chemical,
and different batches of naphtha could lead to different yields
of ethylene and different degrees of coking. R&D analyzed the
naphtha with a gas chromatograph and entered the results into a
computer to predict the naphtha’s yields, and this information
was given to UCC’s economics department to determine which
naphtha shipments had the highest value.
f. Duration and Quantities of Product Produced
The MATRIC team provided Ms. Toivonen with the duration of
the identified runs and the amount of products produced during
the runs so that Ms. Toivonen could calculate the costs incurred
in conducting those runs. As discussed in more detail below, Ms.
Toivonen used duration to calculate the wage costs and the amount
of product produced to calculate the material costs.
Where there was no explicit statement of the duration or the
production quantity in the documentary evidence, the MATRIC team
determined the amounts using a number of different methods. In
- 151 -
some cases the documents stated the pounds of material made
during the run, and the MATRIC team calculated the duration by
dividing the material by the operating rate in terms of pounds
per hour. The MATRIC team determined the production rate from a
number of different sources. If the operating rate was not
known, the MATRIC team made estimates by looking at analogous
tests or experiments.
Where neither the duration nor the quantity produced was
explicitly stated on supporting documentation, the MATRIC team
looked at similar runs and talked to people who actually
conducted the experiments to obtain additional information. The
MATRIC team then used its technical judgment to determine when a
particular experiment began and ended. However, this was
necessary for only a small percentage of the identified runs.
If the amount of product produced was not explicitly stated
on the documentation but the raw materials were mentioned, the
MATRIC team made estimates on yields or efficiencies based on
information in the documents, its own knowledge, or information
from interviewees. The MATRIC team used the data on the raw
materials and its estimates on yields or efficiencies to
calculate the amount of product made and then calculated duration
using the amount of product made and the operating capacity or
operating rate.
- 152 -
If the MATRIC team found a strategic run plan but not a run
report, then it estimated the length of the run. The MATRIC team
made these estimates on the basis of interviews with people who
worked on the projects and data from analogous runs with the same
technology. The names of the people who assisted the MATRIC team
are not documented in the table of identified runs but are
included in the interview notes. Other than with respect to the
cable and wire business, Dr. Wadia did not check his production
estimates against PCDs because the annual PCDs would show the
entire quantity of the product produced in the year, not the
quantity produced during the duration of the experiments.
In some cases the MATRIC team reported the duration of an
identified run as shorter than the total duration of the
activity. In those cases the MATRIC team included only the
portion of the run that it determined related to experimentation.
For example, if UCC personnel conducted experiments only between
the time a run started and the time the unit reached a steady
state, the MATRIC team included only the time required to reach a
steady state in the duration of the identified run. If a run was
conducted for the purpose of determining whether it would produce
a product of acceptable quality, the MATRIC team treated the
experimental portion of the run as ending when that determination
was made. However, if the researchers continued to experiment
after the unit reached a steady state, the MATRIC team would also
- 153 -
include the time when experimentation occurred in the total
duration. In a small number of cases it was not clear when the
experimental portion began or ended, and in those cases the
MATRIC team made an estimate based on its knowledge, similar
runs, and information from interviewees. The MATRIC team used
the total run duration for most of the identified runs conducted
in the polyolefins area because of the complexity of that area,
but it frequently used a partial run duration for identified runs
conducted in the industrial chemicals area where the systems are
more predictable. The MATRIC team noted when it used a partial
run duration in the comments section of the table of identified
runs.
The MATRIC team also noted in the comments section of the
table of identified runs when it made assumptions about run
duration. According to the comments section, the MATRIC team
made assumptions with respect to about 225 identified runs. We
find that most of these assumptions were reasonable. However,
the parties dispute the duration of the identified runs discussed
below.
i. Natural and Forced Draft Burner Tests
(Runs 1 through 11, 95, and 96)
Runs 1 through 11 involved tests on natural draft burners.
Runs 95 and 96 involved tests on forced draft burners. UCC
prepared a report for the natural draft burner tests and another
report for the forced draft burner tests.
- 154 -
UCC conducted the tests on natural draft burners to
determine the most energy efficient operating parameters for the
furnaces. UCC collected data for runs 1 through 11 from January
to October 1985.
UCC conducted runs 1 through 11 on nine furnaces equipped
with natural draft burners (furnaces 1, 4, 5, 7, 9, 14, 15, 18,
and 2434). UCC conducted an 11-point test on each of nine
burners and also conducted additional tests on furnaces 9 and 15.
It appears that Dr. Wadia determined that there were 11 runs by
including one run for each of the nine furnaces and two
additional runs for the second tests conducted on furnaces 9 and
15. However, Dr. Wadia did not distinguish between the 11 runs
in his expert report.
The duration of each of the natural draft burner tests was
reported in the natural draft burner report as 1 to 1-1/2 days.
Dr. Wadia used the midpoint, 30 hours, as the duration of each of
these runs. This was a conservative estimate because each of the
11 test points lasted about an hour, so the tests most likely
occurred over 1-1/2 work days, not 24-hour days.
UCC also tested the effects of fuel specified gravity on
energy use on furnace 9. UCC ran a 13-point test at three
34
As discussed below, natural draft burner tests were also
conducted on furnaces 10 and 12, but those tests were conducted
to collect baseline data for the forced draft burner tests in
1983, not as part of the natural draft burner tests that took
place in 1985.
- 155 -
different gravities. The extra test points added approximately 2
hours to this test, but UCC could still reasonably complete the
test within 30 hours.
The natural draft burner report refers to two separate 11-
point tests conducted on furnace 15. During one test UCC
collected data over a 23-hour period, and during the second UCC
collected data over a 25-hour period. However, the engineer
conducting the test would not typically collect data continuously
over the entire test period.
The natural draft burner report also refers to the
implementation of a new measurement technique called the Bunker-
Ramo control technique. However, the technique was already well
understood at that point, and UCC did not test or experiment with
this technique as part of the natural draft burner tests.
Runs 95 and 96 were conducted on forced draft burners on
furnaces 10 and 12 in 1984.35 UCC installed the forced draft
burners in early 1984 or late 1983. Before installing the new
burners, UCC collected data from the natural draft burners on
furnaces 10 and 12 to compare with data that UCC would collect
after installing the new burners. We find that the tests on the
natural draft burners on furnaces 10 and 12 occurred in late
1983. The natural draft burner tests conducted on Furnaces 10
35
Dr. Wadia originally determined that runs 95 and 96
occurred in 1985 but corrected the date in his supplemental
report. Respondent agrees that these runs occurred in 1984.
- 156 -
and 12 are not included in runs 1 through 11, 95, or 96 (or
elsewhere on the table of identified runs).
The purpose of runs 95 and 96 was to measure the energy
efficiency of the forced draft burners and compare the results
with the tests on Furnaces 10 and 12 before the new burners were
installed. UCC conducted two 11-point tests and one 7-point test
on Furnace 10 during Run 95 and three 11-point tests on Furnace
12 during Run 96. Dr. Wadia determined that the durations of
Runs 95 and 96 were 20 and 24 hours, respectively. Dr. Wadia
believed this was a reasonable estimate because each point would
take at least half an hour. The test data collected on Furnaces
10 and 12 with both the natural and forced draft burners were
reported in the forced draft burner report.
The forced draft burner report also included data taken to
measure NOx in order to aid UCC in complying with environmental
regulations. The data was collected from Furnaces 10 and 12,
which were fitted with forced draft burners at the time, and
furnaces 3, 5, 6, 7, and 8, which were natural draft burners. To
collect the data, UCC put an analyzer on the stack gas portion of
the furnaces, which detected the amount of NOx floating up in the
furnace. UCC did not make any changes to the furnaces outside
the normal operating window. The purpose of collecting these
data was to verify representations made by the burner vendors
- 157 -
regarding NOx production. Dr. Wadia did not include these data
collection activities on the table of identified runs.
ii. Nalco 5211 Tests (Run 15)
Dr. Wadia identified two tests of a coke inhibitor known as
Nalco 5211 as runs 15 and 566.36 Run 15 was conducted on furnace
23 in Taft’s Olefins-2 unit in 1986 and 1987. The overall
purpose of the test was to determine the effectiveness of Nalco
5211 as a coking inhibitor. One objective of the test was to
gather enough information to determine whether Nalco 5211
improved operations enough to justify the inhibitor’s cost.
Dr. Wadia determined that run 15 lasted for 110 days, which
is the amount of time that the furnace ran after Nalco 5211 was
injected before the furnace was shut down. The test run ended
prematurely because the furnace was upset. UCC predicted that
the furnace would run for about 150 to 220 days if no upsets
occurred.
According to the project report, the data collected after
Nalco 5211 had been injected were compared to data collected from
five base case runs on furnace 23 when no inhibitor had been
injected and furnace 23 operated normally. A “base case” refers
to the collection of data during normal operations to serve as a
reference to compare to data collected during an experiment or
36
The parties only dispute the duration of run 15.
Accordingly, references to the Nalco 5211 test are only to run
15.
- 158 -
after an operational change has occurred. The five base case
runs spanned 292 days from January to December 1985. The base
case data were the same data normally collected by computer and
would have been collected even if UCC did not intend to test
Nalco 5211 on Furnace 23. An analysis of the base case data
indicated that UCC’s furnaces could run for 60 to 90 days between
decokings under normal conditions without an inhibitor instead of
30 to 45 days as previously believed.
Following the test, UCC concluded that there was little
economic incentive at Taft to justify the use of Nalco 5211 and
that savings could be realized by extending the furnace run times
without adding an inhibitor.
Dr. Wadia did not include the base case runs in his expert
report because UCC did not change any process variables before
the base case runs. Therefore, Dr. Wadia did not believe that
they involved a process of experimentation. Ms. Toivonen, in her
expert witness report, determined that the Nalco 5211 test cost
$1,419,392.24 excluding the cost of the base case runs. Mr.
Halle, one of respondent’s expert witnesses, estimated that the
base case runs would have cost about $5.4 million using Ms.
Hinojosa’s methodology for costing the Amoco anticoking project.
- 159 -
iii. Vinyl Acetate Catalyst Protection
Tests (Runs 47 and 48 and Runs 594 and
596)
The vinyl acetate catalyst protection tests (runs 47 and 48)
involved runs in the vinyl acetate unit. The goal of these runs
was to protect the expensive catalyst from low levels of iodine,
which comes in as an impurity with acetic acid. In run 47, a
small (about a quarter of an inch) pilot tube was installed in
the process stream to divert some of the feedstock to create a
slipstream. UCC would then test the performance of a silver-
containing resin for removing iodine from the acetic acid feed.
The purpose of the run was to test the physical strength of the
resin, which was being used as a trap bed for iodine, over a
period of 2,400 hours to determine whether minor components in
the acetic acid feed would have a deleterious effect on the
resin.
For run 47 Dr. Wadia treated the experiment as having a
duration of 12 hours, which was the time it took to set up and
take down the apparatus and determine whether the material had
maintained its physical integrity. Dr. Wadia did not count the
2,400 hours that the tube was in place as part of the test
because there was no monitoring during that time. Furthermore,
Dr. Wadia treated the product quantity as zero because the amount
of feedstock going through the tube was so small compared to what
- 160 -
was going through the main process and it would be very difficult
to quantify.
Run 48 was very similar to run 47 except that run 48
involved a larger tube and full-scale trap bed made of the same
material. The purpose of Run 48 was similar to that of run 47
except that UCC also wanted to determine whether there would be
other issues with scaling up the channeling.
For run 48 Dr. Wadia treated the duration as 720 hours,
which was the time it would take to get a good indication of
stability. The comment section on the table of identified runs
does not provide any additional details as to how Dr. Wadia
concluded that the duration of the run was 720 hours. Dr. Wadia
did not include the entire duration of the run because the plant
would have continued to operate as normal even if the experiment
never happened.
Dr. Wadia again treated the production quantity as zero
because the same materials that were used during run 48 were also
being used in a simultaneous plant test of a new catalyst in the
unit (Run 153) and Dr. Wadia did not believe that it was
appropriate to double count the materials.
Dr. Wadia used the same methodology (including only the
feedstock material flowing through the parts of the process in
which the tests were being conducted) for runs 594 and 596, which
also used a slipstream. Dr. Wadia used a duration of 216 and 96
- 161 -
hours for runs 594 and 596, respectively. Dr. Wadia determined
that 3,000 and 3,800 pounds of products were produced during runs
594 and 596, respectively.
iv. Butyl Acetate Capacity Increase Test
(Run 161)
UCC conducted the butyl acetate capacity increase test (run
161) to test an increase in butyl acetate production by
increasing the number of refining column trays in the esters
batch still. The trays were installed in January 1987 and
removed in February 1987. Dr. Wadia treated the run as lasting 4
days even though the trays may have been in place for up to 2
months. Nothing in Dr. Wadia’s expert reports explains how he
determined this duration.
v. MEK Production Test (Run 175)
The MEK production test (run 175) involved the production of
methyl ethyl keytone (MEK) at Institute from August 27 to October
5, 1988 (6 weeks). The production campaign responded to a severe
market shortage of MEK. This run was UCC’s first attempt to make
MEK. According to the project report, UCC collected data for the
first 914 hours of the run.
Dr. Wadia assumed that the startup and experimentation
involved in the project took 2 weeks, and accordingly treated the
duration as 336 hours. Nothing in Dr. Wadia’s expert reports
explains how Dr. Wadia arrived at the conclusion that the startup
and experimentation took only 2 weeks.
- 162 -
vi. Secondary Refining System Test (Run 178)
The secondary refining system test (Run 178) involved a
plant test conducted on the secondary refining system for the
purpose of optimizing the ethanol refining system. The test
involved feeding the primary extractive column overheads directly
to the lights column to immediately separate acetaldehyde and
ether from ethanol. The lights column tails were then fed to the
secondary extractive column. The secondary refining system
project lasted 2 weeks. However, Dr. Wadia assumed a duration of
1 week. Nothing in Dr. Wadia’s expert reports explains how he
arrived at this conclusion.
vii. Spanish Fermentation Ethanol Refining
Test (Run 180)
The Spanish fermentation ethanol refining test (run 180)
involved the refining of Spanish fermentation ethanol with a goal
of producing 200 proof ethanol. Dr. Wadia assumed a 4-day
duration although about 11 days of testing were reported.
Nothing in Dr. Wadia’s expert reports explains how he arrived at
this conclusion.
viii. Ethanol Tertiary Recovery Test (Run
181)
The ethanol tertiary recovery test (run 181) was conducted
for the purpose of optimizing the separation of propanol and the
recovery of ethanol in the ethanol residue column. Dr. Wadia
assumed a 4-day duration even though about 15 days of testing
- 163 -
were reported. Nothing in Dr. Wadia’s expert reports explains
how he arrived at this conclusion.
ix. Mexican Fermentation Ethanol Refining
Test (Run 184)
The Mexican fermentation ethanol refining test (run 184)
involved the refining of Mexican fermentation ethanol with the
goal of producing specification ethanol. Dr. Wadia assumed a 4-
day duration although a 1-week test was reported. Nothing in Dr.
Wadia’s expert reports explains how he arrived at this
conclusion.
x. Propionic Acid Hydrogen Peroxide
Treatment Test (Run 190)
The propionic acid hydrogen peroxide treatment test (run
190) involved the addition of small quantities of hydrogen
peroxide to the process for making propionic acid. It began on
February 18, 1987, and lasted 10 days. Dr. Wadia assumed a test
period of 4 days. Nothing in Dr. Wadia’s expert reports explains
how he arrived at this conclusion.
xi. Adiabatic Hydrogenation Beds
Rearrangement Test (Run 198)
The adiabatic hydrogenation beds rearrangement test (run
198) involved rearranging the order of the adiabatic
hydrogenation beds used to make butanol in order to improve
product quality. The order was changed on February 29, 1984, and
data were collected on March 21, 1984. Dr. Wadia determined that
- 164 -
the duration of run 198 was 4 days. Nothing in Dr. Wadia’s
expert reports explains how he arrived at this conclusion.
xii. Butanol Refining Test (Run 202)
The butanol refining test (run 202) involved adjusting the
base temperature on the butanol refining forecolumn. A 2-week
test was reported, but Dr. Wadia determined a 4-day duration.
Nothing in Dr. Wadia’s expert reports explains how he arrived at
this conclusion.
xiii. DIBK Recycle to Mixed Keytones
Converters Test (Run 608)
The DIBK recycle to mixed keytones converters test (run 608)
was a process enhancement test to suppress the formation of
diisobutyl ketone (DIBK). The test was conducted between October
25 and November 23, 1988. However, Dr. Wadia determined that the
portion of the test from November 1 to 8 demonstrated the
catalyst performance and trends. Dr. Wadia does not explain in
his expert reports how he chose November 1 and 8.
V. Base Period QREs
Ms. Toivonen, one of petitioner’s expert witnesses,
calculated the supply and wage costs UCC incurred in conducting
the identified runs, including runs 807 through 820, which
petitioner concedes occurred during the base period and
constitute qualified research under section 41(d). Ms. Toivonen
is a partner with the public accounting firm of Ernst & Young LLP
- 165 -
(E&Y). In performing her assignment Ms. Toivonen led a team of
E&Y accounting professionals ranging from 10 to 75 people.
In addition, four current or former Dow/UCC cost accountants
(including Ms. Hinojosa) assisted Ms. Toivonen in the costing
process. Ms. Hinojosa and her colleagues identified the lead
PCDs (the page of the PCD that is tied to the product produced in
a specific run) and the MASs relating to the products Ms.
Toivonen costed. Ms. Hinojosa also consulted on other issues.
As discussed above, Ms. Toivonen obtained the production
quantities and run durations from the MATRIC team for runs 1
through 806. In situations where Dr. Wadia’s production quantity
exceeded the production quantity reflected on the lead PCD, Ms.
Toivonen used Dr. Wadia’s production quantity to calculate the
cost of the run, to be conservative. Ms. Toivonen did not
independently verify the MATRIC team’s conclusions regarding run
duration or production quantity, and the MATRIC team did not
review Ms. Toivonen’s costing of the identified runs.
Ms. Toivonen determined the run durations and production
quantities for runs 807 through 820 using UCC’s accounting
records, not information provided by Dr. Wadia. Petitioner’s
counsel provided Ms. Toivonen with the accounting records that
related to these runs. Ms. Toivonen did not have access to all
of the technical documents produced in this case. However, when
Ms. Toivonen felt that she needed additional documents, she asked
- 166 -
petitioner’s counsel to see whether more information was
available. Ms. Toivonen did not conduct an independent search
for information relating to these runs because the Court directed
Ms. Toivonen to rely on the factual record that existed at the
end of the base period trial. Ms. Toivonen used historical UCC
cost accounting records to calculate the costs of runs 807 to
815, 818, and 819. Ms. Toivonen used cost information supplied
by CMAI to calculate the costs of runs 816, 817, and 820.
A. Documentation
During the base period, as in the credit years, UCC used the
material accounting system for production, inventory, and product
costing. Ms. Toivonen relied primarily upon PCDs and MASs to
calculate the supply costs of the identified runs, which are the
same types of documents that Ms. Hinojosa used to calculate the
claimed QREs for the claim projects. Ms. Toivonen also used
other records such as reports of UCC’s third-party purchases and
documents from UCC’s latex business. Ms. Toivonen primarily used
account levels and Star’s performance history report to calculate
wage costs. More than 90 percent of the base period cost
calculations were based upon historical UCC accounting records.
Ms. Toivonen and her team also used the MATRIC team’s table of
identified runs, a separate table prepared by the MATRIC team
that listed the materials and material quantities used in the 140
latex runs identified by Dr. Wadia, historical pricing
- 167 -
information from CMAI regarding ethylene byproducts, and
information provided by Dow/UCC cost accountants and Dow
technical personnel.
Petitioner was unable to find its R&D budgets for 1984,
1985, 1986, 1988, 1994, or 1995. However, petitioner provided
its R&D budgets for 1987.
B. Ms. Toivonen’s Costing Methodology
To develop a methodology to calculate the costs UCC incurred
in conducting the identified runs, Ms. Toivonen reviewed Ms.
Hinojosa’s expert report for the credit years and designed her
methodology to be consistent with Ms. Hinojosa’s methodology.
Ms. Toivonen included the same types of costs and used the same
types of records that Ms. Hinojosa used when it was possible.
Ms. Toivonen’s methodology involved:37 (1) Identifying the lead
PCDs for the runs; (2) identifying the materials that required
costing; (3) tracing the materials through UCC’s accounting
records; (4) determining the unit costs of materials; (5)
calculating the total materials costs; (6) calculating the wage
costs; and (7) calculating the total run costs.
Following this process, Ms. Toivonen and her team prepared
detailed cost calculations for each identified run. With certain
37
As discussed above, some of these activities were
performed by Ms. Hinojosa and her colleagues or the MATRIC team.
In particular, Ms. Hinojosa identified the lead PCDs, and the
MATRIC team determined the duration and production quantities for
most of the identified runs.
- 168 -
exceptions discussed below, each identified run is supported by:
(1) A lead PCD for the product or the closest match if the lead
PCD was unavailable; (2) secondary PCDs and MASs used to derive
the per-unit costs of internally produced materials used in the
production of the lead PCD product; (3) an E&Y-generated unit
cost calculation worksheet showing the actual unit cost
calculation for each material used in the identified run; (4) an
E&Y-generated material detail report showing the total cost of
the materials used in producing the final product made in the
identified run; (5) an E&Y-generated wage detail report showing
the wage cost calculation for the identified run; and (6) an E&Y-
generated summary report showing the total material and wage
costs for the identified run. The supporting documentation was
substantially similar for the identified runs conducted in UCC’s
latex business although the latex business did not use the same
accounting records as the rest of UCC’s C&P business.
1. Identifying the Lead PCD
As discussed above, Ms. Hinojosa identified the lead PCDs
for the identified runs. A lead PCD provides the materials and
material quantities used in manufacturing the final product(s) in
a given year and essentially provides the “recipe” for making the
product. Lead PCDs were not found for all of the products
produced in the identified runs. If a lead PCD was not found for
a specific product, Ms. Toivonen used a PCD for a similar
- 169 -
product. In other cases, Ms. Hinojosa identified more than one
lead PCD that could have been a match for a run. In those cases,
Ms. Toivonen selected the PCD that was the closest match.
2. Identifying the Materials
In a few cases Dr. Wadia identified materials used in a run
that were different from the materials listed on the PCD. In
such cases Ms. Toivonen relied on the PCD because it was UCC’s
official cost accounting record. As a result, Ms. Toivonen
either would not cost the material identified by Dr. Wadia or
would cost a material listed on the PCD that was different from
the material identified by Dr. Wadia. Ms. Toivonen did not keep
a list of materials that were identified by Dr. Wadia but that
were not listed on the PCDs she used because she believed that
materials would be omitted from UCC’s cost accounting records
only if their costs were immaterial.
Ms. Toivonen generally did not include utilities when she
identified the materials that required costing. However, Ms.
Toivonen did include the costs of the furnace gases and
refrigeration used in the ethylene production process because Ms.
Hinojosa included those costs when costing the claim projects
that involved the ethylene production process.
3. Tracing the Materials
To calculate the unit cost of purchased materials, Ms.
Toivonen divided the total material cost for the year by the
- 170 -
quantity received. The unit cost for internally produced
materials was more complex. For internally produced materials
the E&Y team identified the applicable secondary PCDs and traced
all of the materials listed on the secondary PCDs. This tracing
process was continued until the E&Y team reached the originating
material purchases from third-party vendors. Internally produced
materials frequently required multiple levels of tracing.
Ms. Toivonen and the E&Y team developed practical approaches
to simplify the tracing process for internally produced
materials. For example, where multiple levels of tracing were
required, the tracing process was repeated until at least 80
percent of the total material quantity had been reached. The
actual unit cost calculated from this material quantity was
applied to the entire amount for the material used in an
identified run. In some cases where an internally produced
material accounted for less than 5 percent of the total cost
shown on a lead PCD, Ms. Toivonen used UCC’s annually updated
material standard cost. These approaches did not materially
affect the calculated cost of internally produced materials
because the standard cost reasonably approximated UCC’s actual
per-unit cost.
4. Determining the Unit Costs of Materials
Transfer costs shown on lead PCDs represented materials
transferred to the manufacturing site from another UCC division
- 171 -
or location. E&Y used MASs to determine the UCC division or
location where the materials were originally purchased or
produced. Other than the addition of freight or other charges,
the unit cost calculation for transfer costs was the same for
purchased and internally produced materials.
Consistent with Ms. Hinojosa’s treatment of byproducts in
calculating the costs of the claim projects, Ms. Toivonen and her
team treated the costs of byproducts as reductions in the unit
cost calculations. Actual per-unit byproduct costs were used
where these costs had been previously determined. Otherwise, Ms.
Toivonen used historical values from CMAI because that was the
source of information that Ms. Hinojosa used for her claim
project calculations. In a few instances where CMAI data were
not available, Ms. Toivonen used UCC’s standard cost. Where
byproducts represented less than 5 percent of the total cost on a
lead PCD, no reduction was taken because the impact on overall
cost was immaterial.
During the base period, UCC both purchased and internally
produced ethylene, which was a major raw material for many
chemicals and plastics. Additional calculations were necessary
to determine the actual unit cost of ethylene consumed in
downstream products. Consistent with the methodology that Ms.
Hinojosa used for the claim projects, Ms. Toivonen calculated a
“Gulf Coast Weighted Average Pooled Price for Ethylene” using the
- 172 -
weighted average cost of UCC’s ethylene purchases and internal
production for each base period year.
Ms. Toivonen used a different approach to derive the unit
costs of materials used in the 140 identified runs from UCC’s
latex business. The latex business did not use PCDs or MASs, and
there were no accounting records for the base period for the
latex business. Accordingly, Ms. Toivonen derived unit costs of
the materials used in the latex runs from available latex
business documents from other periods with adjustments for
inflation where appropriate. For deionized water, which is a
high-volume, low-dollar raw material, Ms. Toivonen used the UCC
standard cost. Collectively, the 140 latex runs accounted for
less than 1 percent of the total cost of the identified runs.
5. Calculating Total Materials Costs
Once Ms. Toivonen calculated the unit cost for each of the
materials used to make the product produced during a run, Ms.
Toivonen calculated the total materials cost for the product by
multiplying the per-unit costs by the quantities of each material
shown on the lead PCD (or on the MATRIC team’s “Latex Run Batch
Components Table” for the latex runs). This calculation
generated the total production cost for the year for the product
manufactured in the run. Ms. Toivonen then divided this total
production cost for the product by the total quantity of the
product produced in the year to generate a per-unit cost of the
- 173 -
product manufactured. Ms. Toivonen and the E&Y team then
multiplied this per-unit cost by the quantity of product made
during the identified run to determine the total material cost
for the run. As discussed above, Ms. Toivonen obtained the
production quantities from Dr. Wadia for runs 1 through 806.
6. Calculating the Wage Costs
Ms. Toivonen determined wage costs for each identified run
by multiplying the run duration (supplied by Dr. Wadia) by a
calculated hourly wage rate for the UCC manufacturing unit in
which the run was conducted. Ms. Toivonen derived the hourly
wage rates from account levels, which reported both budgeted and
standard labor cost information for the budget accounts within
UCC locations. Ms. Toivonen then adjusted the standard labor
costs to actual costs by an allocation of the deviation accounts,
which represent the differences between standard and actual labor
costs. To calculate the hourly wage rates, Ms. Toivonen created
“wage groups” based on common manufacturing areas at UCC plants.
Ms. Toivonen then calculated “wage group dollars” based on the
actual direct labor costs of each wage group as well as the
allocable portion of shared laboratory and shift administration
labor costs. Wage group dollars represented an aggregate cost of
all employee-related wages and benefits associated with a UCC
manufacturing unit. Ms. Toivonen calculated “wage group dollars
- 174 -
per production unit hour” by dividing wage group dollars by the
wage group’s total production unit hours.
The above methodology for calculating wages was used for all
identified runs except for the latex runs and the runs conducted
at Star between 1985 and 1988. Because account levels were not
available for these runs, Ms. Toivonen estimated hourly wage
rates on the basis of the best available information.
Ms. Toivonen determined that the total wage cost for all
identified runs was approximately $7.937 million, or about 5.87
percent of the total run costs. For the claim projects, Ms.
Hinojosa determined that wages accounted for only 1 percent of
the total project costs. Furthermore, the wage rates for
approximately 98 percent of the identified runs were higher than
the wage rates used by Ms. Hinojosa. The reason for these
differences was that Ms. Toivonen’s approach to costing the
identified runs was much more comprehensive than that used by Ms.
Hinojosa and the records available for the base years were more
detailed than those available for the credit years. In
particular, budget reports were not available for the credit
years. However, since Ms. Toivonen did not have data for wages
paid at the Star plants for 1985 through 1988, she used the Star
plant performance history report that was consistent with what
Ms. Hinojosa used for the credit years. Furthermore, since Ms.
Toivonen did not have accounting records for the latex business,
- 175 -
she estimated the wages for that business using information
provided by the MATRIC team. The MATRIC team also calculated the
run costs for the crystal products business because there were no
accounting records available for that facility.
7. Calculating the Total Run Costs
Ms. Toivonen and the E&Y team then added the total materials
cost to the total wage cost for each identified run to calculate
the total cost of each identified run.
8. Exceptions to Ms. Toivonen’s General Costing
Methodology
Certain identified runs involved extraordinary situations
requiring Ms. Toivonen and the E&Y team to develop and apply
special costing rules.
The first exception was for sequential runs. When the
manufactured product of an initial run was used as a material in
a subsequent run, the costs of the manufactured product from the
initial run were excluded from the second run calculation to
avoid double counting.
Different treatment was also required for runs where third
parties contributed materials at no charge. In these cases no
cost was assigned to the contributed materials.
The next exception occurred when materials used to produce
the manufactured product included some quantity of the same
manufactured product that was treated as a work-in-process, such
as recycled materials. In these cases the material quantity was
- 176 -
netted against the production quantity as shown on the lead PCD
and the cost of the work-in-process material was excluded from
the total cost on the PCD.
Ms. Toivonen calculated the cost of materials used in some
ethylene furnace tests differently. The MATRIC team did not
provide production quantities for some identified runs performed
on ethylene furnaces because the ethylene was mass produced in
multiple furnaces. In those cases, Ms. Toivonen calculated an
hourly production rate for one furnace and multiplied the rate by
the run duration as shown on the MATRIC table of identified runs.
Another exception was necessary when the PCDs for certain PE
products made at Seadrift did not specify a nomenclatured resin
but instead identified a generic “fluff” product. To identify
the correct lead PCD for runs making these products, Ms. Toivonen
used run-specific information such as the unit, density,
comonomer, catalyst, and cocatalyst. Where there were multiple
PCDs involving fluff resins with run-specific characteristics,
Ms. Toivonen calculated a weighted average per-unit cost for the
identified run from the PCDs.
Ms. Toivonen made an exception for the Oxo-12 LPO vaporizer
capacity test (run 193) because the lead PCD reflected three
manufactured products with two different units of measure. In
addition, one manufactured product had a work-in-process material
adjustment. Calculating a per-unit cost for the relevant
- 177 -
manufactured product required the quantity of the relevant
product to be isolated on the PCD as a production quantity. One
of the other manufactured products had to be recategorized as a
byproduct, and the other had to be netted as a work-in-process
material adjustment.
Ms. Toivonen also made an exception for identified runs
where the lead PCD reported significant negative material
quantities, resulting in a negative per-unit material cost. A
negative per unit material cost was typically the result of UCC’s
reclassification of a material or some other adjustment. Ms.
Toivonen corrected these quantities based on the forecasted
contribution of the material to the standard cost shown on the
PCD.
The next exception was for the crystal products business.
UCC accounting records were not available for the crystal
products business in Washougal, which was sold in the late 1990s.
Accordingly, Ms. Toivonen and the E&Y team did not compute the
cost of plant-based R&D activities for this business. The MATRIC
team estimated that the cost of the identified runs conducted as
part of the crystal products business (runs 687 through 691) was
$472,000 per year.
Ms. Toivonen also used a different methodology for the runs
conducted by Rohm & Haas before UCC acquired the Triton assets.
Ms. Toivonen and the E&Y team determined material and labor costs
- 178 -
for the runs using Rohm & Haas documentation and made adjustments
based on the Consumer Price Index, as published by the U.S.
Department of Labor, Bureau of Labor Statistics.
The last exception was for identified runs where the table
of identified runs did not report any production for the run.
For those runs Ms. Toivonen obtained the materials and quantities
consumed from the MATRIC team and then used the general costing
methodology discussed above.
C. Ms. Toivonen’s Conclusions
Ms. Toivonen concluded that, in her opinion, the total cost
of all of the identified runs (the initial 793 identified runs
and runs 807 through 820) for each base period year was as
follows:
Cost of
Year Identified Runs
1984 $17,433,643
1985 22,837,583
1986 38,870,319
1987 22,396,571
1988 33,574,796
Total 135,112,912
D. Disputed Calculations
The parties dispute Ms. Toivonen’s calculations of the
following runs.38 Accordingly, we discuss them below.
38
Respondent also questions Ms. Toivonen’s reliance on Dr.
(continued...)
- 179 -
1. Acrolein Refining System Capacity Test (Run
128)
Dr. Wadia determined that UCC produced 1.8 million pounds of
product in the acrolein refining system capacity test (run 128).
However, Ms. Toivonen treated the production quantity as 90,000
pounds. Ms. Toivonen determined that the unit cost per pound was
$0.16588 and accordingly calculated the total run material cost
to be $14,929.27. Had Ms. Toivonen treated the run production
quantity as 1.8 million pounds, the total run material cost would
have been $298,584, a difference of $283,654.73. Ms. Toivonen
testified that the discrepancy might be attributable to a unit of
measure conversion, but she did not explain the discrepancy in
her expert report.
2. Propyl Dipropasol Refining Test (Run 171)
Dr. Wadia listed sodium hydroxide as the catalyst for the
propyl dipropasol refining test (run 171) on the table of
identified runs. However, the PCD that Ms. Toivonen used to cost
the run does not reference sodium hydroxide. Instead, the PCD
lists sodium propylate as a raw material. Accordingly, Ms.
Toivonen calculated the cost of sodium propylate instead of
sodium hydroxide when costing the run.
38
(...continued)
Wadia’s determinations of the durations and production quantity
for the runs discussed in sec. IV.B.3.f., above. However,
because we have already discussed the facts relating to those
runs, we need not address them again here.
- 180 -
Ms. Toivonen determined that the unit cost of sodium
propylate for 1988 was $1.04607. For the cellosolve solvent test
(run 576) Ms. Toivonen determined that the unit cost of sodium
hydroxide pellets in 1985 was $0.2375 per pound.
3. Isophorone Mids Conversion Test (Run 173)
Dr. Wadia listed potassium carbonate as the catalyst for the
isophorone mids conversion test (run 173) on the table of
identified runs. Because potassium carbonate was not listed on
the lead PCD for this run, Ms. Toivonen did not include the cost
of potassium carbonate when she costed the run. According to a
project report for the run, UCC used 15 gallons of potassium
carbonate. Ms. Toivonen determined that potassium carbonate cost
34 cents to 95 cents per pound for other identified runs.
4. Secondary Refining System Test (Run 178)
Dr. Wadia’s report states that part of the secondary
refining system test (run 178) included a 2-day test with a
caustic addition. However, Ms. Toivonen did not list any caustic
additives as materials used in this run. The cost of caustic
solutions in other runs ranged from 6 cents to 25 cents per
pound.
5. Naphtha-Sulfur Injection Test (Run 807)
The naphtha-sulfur injection test involved the injection of
naphtha into the production process. The purpose of the run was
to determine whether the normal diethyl sulfide (DES) injection
- 181 -
could be replaced with naphtha in the gas feed to the cracking
furnaces without causing problems to furnace operations or
increasing carbon monoxide levels.
In costing the naphtha-sulfur injection test Ms. Toivonen
did not include the costs of the equipment required to inject the
naphtha. The equipment cost approximately $2,500 per furnace.
Ms. Toivonen did not include the costs of the equipment because
she considered those to be capital costs, not supplies or wages.
Ms. Toivonen also did not calculate the cost of naphtha as a
separate material for the naphtha-sulfur injection test because
the lead PCD did not list naphtha. However, the cost of the
naphtha may have been captured on a secondary PCD which Ms.
Toivonen used to calculate the costs of materials listed on lead
PCDs. It is also possible that Ms. Toivonen included the cost of
DES instead of naphtha, although DES is not listed on the lead
PCD as a material used in the production of ethylene.
Ms. Toivonen determined that the naphtha-sulfur injection
test lasted 35 days. The technical report for the test, written
on January 20, 1986, states that the test began on December 16,
1985. Ms. Toivonen allowed 1 day for preparation of the report.
6. Methylmercaptopropanal (MMP) Refrigeration
Tests (Run 810)
Run 810 consisted of two MMP refrigeration capacity tests.
The first test was designed to evaluate transfer chiller control
at negative 10 degrees Centigrade instead of negative 17 degrees
- 182 -
Centigrade as a means to minimize super-cooling, which could
cause MMP to freeze or hydrates to form. The second test was
designed to estimate the ambient heat gain of the day tanks and
storage tanks as a means to verify assumptions that UCC’s
engineering division used in calculations.
Ms. Toivonen did not include any utility costs in the cost
of the MMP refrigeration tests. Ms. Toivonen determined that
utility costs should not be included in the cost of the run
because Ms. Hinojosa generally excluded utility costs unless they
were extraordinary. Ms. Hinojosa found utility costs to be
extraordinary only in the production of ethylene. Accordingly,
Ms. Toivonen considered electricity to be an extraordinary cost
only when a run involved the production of ethylene. In other
situations, Ms. Toivonen did not calculate the cost of
electricity because it was not captured in UCC’s accounting
records. Accordingly, Ms. Toivonen had no basis for determining
whether the cost of electricity was extraordinary.
OPINION
The research credit was introduced with the enactment of the
Economic Recovery Tax Act of 1981, Pub. L. 97-34, sec. 221(a), 95
Stat. 241.39 Congress enacted the research credit to “stimulate
a higher rate of capital formation and to increase productivity”,
S. Rept. 97-144, at 76-77 (1981), 1981-2 C.B. 412, 438-439; H.
39
The research credit was originally included in sec. 44F.
- 183 -
Rept. 97-201, at 111 (1981), 1981-2 C.B. 352, 358, and “to
encourage business firms to perform the research necessary to
increase the innovative qualities and efficiency of the U.S.
economy.” S. Rept. 99-313, at 694 (1986), 1986-3 C.B. (Vol. 3)
1, 694; H. Rept. 99-426, at 177 (1985), 1986-3 C.B. (Vol. 2) 1,
177. Congress found research to be essential to America’s
economic progress and competitiveness. H. Conf. Rept. 100-1104,
at 88 (1988), 1988-3 C.B. 473-578.
However, in 1986 Congress became concerned that taxpayers
were interpreting the research credit too broadly and that “some
taxpayers * * * claimed the credit for virtually any expenses
relating to product development.” S. Rept. 99-313, supra at 694-
695, 1986-3 C.B. (Vol. 3) at 694-695; see also H. Rept. 99-426,
supra at 178, 1986-3 C.B. (Vol. 2) at 178. Therefore, Congress
amended the research credit by the Tax Reform Act of 1986, Pub.
L. 99-514, sec. 231(b), 100 Stat. 2173, to provide a definition
of “qualified research”.
The research credit was intended to apply to incremental
research and experimental expenditures in order to overcome the
resistence of businesses to bearing the costs that must be
incurred to initiate or expand research programs. H. Rept. 97-
201, supra at 111, 1981-2 C.B. at 358; see also Staff of Joint
Comm. on Taxation, General Explanation of the Economic Recovery
Tax Act of 1981, at 119-120 (J. Comm. Print 1981) (“The new
- 184 -
credit applies only to increases in qualified research
expenditures, in order to encourage enlarged research efforts by
companies which already may be engaged in some research
activities.”). The goal of the research credit was to encourage
research activity that would not otherwise have been undertaken.
135 Cong. Rec. S13114, S13125 (daily ed. Oct. 12, 1989) (Senate
Finance Committee Report on Title VI, Revenue Reconciliation Act
of 1989, Subtitle A., Extensions of Certain Expiring Tax
Provisions).
Section 41(a)(1) allows taxpayers a credit against income
taxes in an amount equal to 20 percent of the excess (if any) of
the taxpayer’s QREs for the year over the base amount.40 To
determine the amount of a taxpayer’s QREs, the taxpayer must
determine whether any of its activities constitute “qualified
research” as defined in section 41(d), and then determine which
costs attributable to the qualified research constitute QREs
under section 41(b). QREs include in-house research expenses and
contract research expenses. Sec. 41(b)(1).
The base amount is generally the product of the fixed-base
percentage and the average annual gross receipts of the taxpayer
for the 4 years preceding the credit year. Sec. 41(c)(2). The
fixed-base percentage is normally the lesser of 16 percent or the
40
Sec. 41(a)(2) does not apply in this case. Sec. 41(a)(3)
was added in 2005. Energy Policy Act of 1985, Pub.L. 109-58,
sec. 1351(a)(1), 119 Stat. 594, 1056.
- 185 -
percentage that the aggregate QREs of the taxpayer for the
taxable years beginning in the years 1984 through 1988 (the base
period) is of the aggregate gross receipts of the taxpayer for
those years. Sec. 41(c)(3)(A). However, the base amount may not
be less than 50 percent of the QREs for the credit year. Sec.
41(c)(2). The parties do not dispute the amount of UCC’s annual
gross receipts for the 4 years preceding the credit years or for
the base period. Accordingly, we need only determine the amount
of UCC’s additional QREs for the base period to be able to
recalculate the base amount.
A taxpayer must determine its QREs to be taken into account
in computing its fixed-base percentage “on a basis consistent
with” its determination of QREs for the credit year (the
consistency requirement). Sec. 41(c)(4).41 Accordingly, the
taxpayer must include the same types of activities from the
credit year and the base period when identifying qualified
research activities and include the same types of costs as QREs
for the credit year and the base period.
Respondent argues that petitioner has failed to prove that
any of the claim projects constitute qualified research within
the meaning of section 41(d). Even if some of the claim projects
41
In 1996 the consistency requirement was redesignated
subsec. (c)(5). Small Business Job Protection Act of 1996, Pub.
L. 104-188, sec. 1204(c), 110 Stat. 1774. In 2006 the
consistency rule again was redesignated subsec. (c)(6). Tax
Relief and Health Care Act of 2006, Pub. L. 109-432, div. A, sec.
104(c)(1), 120 Stat. 2935.
- 186 -
constitute qualified research, respondent also argues that
petitioner has not satisfied the consistency requirement because
it has not proved that it included all similar activities in its
base period computations. Respondent further argues that even if
petitioner has satisfied these requirements, it has not
established that it incurred any additional QREs not already
taken into account for the credit years because petitioner is
claiming production costs as QREs. To the extent that petitioner
has incurred additional credit year QREs, respondent argues that
petitioner failed to establish that it used a consistent method
to calculate its revised base period QREs. Respondent also
argues that petitioner failed to substantiate its credit year and
base period activities, made unreliable assumptions and
estimations to calculate its claimed credits, and asks the Court
to rely on conclusory opinions of its expert. We address these
arguments in turn.
I. The Experts
Both parties rely on expert opinions to support their
arguments. We evaluate expert opinions in the light of all of
the evidence in the record, and we are not bound by the opinion
of any expert witness. Helvering v. Natl. Grocery Co., 304 U.S.
282, 295 (1938); Shepherd v. Commissioner, 115 T.C. 376 (2000),
affd. 283 F.3d 1258 (11th Cir. 2002). We may reject, in whole or
- 187 -
in part, any expert opinion. Estate of Davis v. Commissioner,
110 T.C. 530, 538 (1998).
A. Petitioner’s Expert Witnesses
1. Peter Spitz
Petitioner introduced expert testimony by Peter Spitz
regarding the role of plant-based research. Mr. Spitz is a
chemical engineer who has written two books on the petrochemical
industry, consulted for petrochemical companies for several
decades, and testified as an expert witness regarding the role of
plant-scale R&D for petrochemicals.
2. Gilbert Froment
Petitioner introduced expert testimony by Gilbert Froment
regarding the Amoco anticoking project. Dr. Froment is a
professor of chemical engineering at Texas A&M University with
about 50 years of experience teaching and consulting in the field
of thermal cracking for olefins production. He has written at
least 70 scientific papers dedicated to issues in olefins
production, and several of these papers specifically related to
coke formation and its consequences. Dr. Froment is a member of
several professional associations and has designed thermal
cracking pilot plants in which he has led studies of coke
formation and its consequences.
- 188 -
3. Richard Martin
Petitioner introduced expert testimony by Richard Martin
regarding the spuds project. Dr. Martin has over 30 years of
experience developing, designing, and testing combustion
equipment for the refining and petrochemical industries. Dr.
Martin was previously employed by the John Zink Co. and was
involved in the development and testing of the radiant wall
burners that are currently installed in the furnaces used in
Taft’s Olefins-2 unit.
4. Norman Brockmeier
Petitioner introduced expert testimony by Norman Brockmeier
regarding the UCAT-J commercialization program conducted at Star
in general and the UCAT-J project that took place during the
credit years in particular. Dr. Brockmeier is a licensed
professional engineer, president of Oakwood Consulting, Inc., and
a Fellow of the AIChE. He has more than 40 years of industrial
experience. His specialty is polyolefin process design and
catalysis, and he has many publications and design projects in
this field.
5. Ms. Hinojosa
Ms. Hinojosa, a former cost accountant for UCC and currently
an accountant for Dow, calculated the costs of the supplies and
wages that petitioner claims as QREs in conducting the claim
projects. At trial Ms. Hinojosa was qualified as an expert in
- 189 -
the accounting systems and documentation employed by UCC during
the credit years and the base period.
6. Dr. Wadia
Dr. Wadia was qualified in the base period trial as an
expert in conducting R&D related to the manufacturing of
chemicals and plastics. Dr. Wadia has a doctorate of science and
a master’s degree in chemical engineering from the Massachusetts
Institute of Technology. Dr. Wadia held a variety of technical
and senior management positions in business and corporate R&D,
technology licensing, and engineering over approximately 30 years
with UCC and Dow.
7. Ms. Toivonen
Ms. Toivonen is a certified public accountant and partner
with E&Y. During the base period trial Ms. Toivonen was
qualified as an expert in accounting. Ms. Toivonen’s specialty
is forensic accounting, a practice that involves the application
of accounting, auditing, and investigative skills to analyze a
company’s financial records.
B. Respondent’s Expert Witnesses
1. Roy T. Halle
Respondent introduced expert testimony by Roy T. Halle
regarding the Amoco anticoking, sodium borohydride, and UOP GA-
155 projects as well as some of the identified runs that occurred
during the base period. Mr. Halle has over 45 years of
- 190 -
experience in the petrochemical and petroleum industries, mostly
in the olefins industry. For the past 10 years, Mr. Halle has
worked as an independent consultant on olefins manufacturing
process issues. Mr. Halle is an affiliate of LECG, L.L.C.
(LEGC), in the area of petroleum and petrochemicals.
2. M. Julianne McClung
Respondent introduced expert testimony by M. Julianne
McClung regarding the spuds project. Ms. McClung, like Mr.
Halle, is an affiliate of LECG. Ms. McClung has over 11 years of
experience working with the steam-cracking area of an ethylene
plant, during which she was involved in all areas of maintaining,
operating, and designing a steam-cracking furnace.
3. Gary Allen
Respondent introduced expert testimony by Gary Allen
regarding the UCAT-J project. Dr. Allen is an affiliate of the
petroleum and chemicals practice of LECG. He has over 30 years
of experience in the chemicals and plastics industry. Dr. Allen
led the development and commercialization of several different
polymer technologies. Respondent introduced Dr. Allen as an
expert in scaling up chemical and process technologies to
commercial operations. While Dr. Allen conceded that he has less
experience with PE, polyolefins, and UNIPOL than petitioner’s
fact witnesses, Dr. Allen has extensive experience scaling up
- 191 -
products and processes from laboratories through pilot plants to
commercial manufacturers.
II. Whether the Claim Projects Constitute Qualified Research
A. The Qualified Research Tests
To be eligible for a credit under section 41(a)(1) a
taxpayer must show that it has performed “qualified research”
during the years at issue. Sec. 41(a)(1)(A), (b)(2). To be
qualified research, the research must satisfy four tests. First,
expenditures connected with the research must be eligible for
treatment as expenses under section 174 (the section 174 test).
Sec. 41(d)(1)(A). Second, the research must be undertaken for
the purpose of discovering technological information (the
technological information test42). Sec. 41(d)(1)(B)(i). Third,
42
We have previously called this test the “discovery test”.
See Norwest Corp. & Subs. v Commissioner, 110 T.C. 454, 491
(1998); Eustace v. Commissioner, T.C. Memo. 2001-66, affd. 312
F.3d 905 (7th Cir. 2002). Before the promulgation of sec. 1.41-
4(a)(3)(ii), Income Tax Regs., we held that this test had a
“discovery” component that was to be construed more narrowly than
the discovery test of sec. 174 and required that the taxpayer
discover information that went beyond the current state of
knowledge in the relevant field. Norwest Corp. & Subs. v.
Commissioner, supra at 493; Eustace v. Commissioner, supra.
However, the current regulations provide that “A determination
that research is undertaken for the purpose of discovering
information that is technological in nature does not require the
taxpayer be seeking to obtain information that exceeds, expands
or refines the common knowledge of skilled professionals in the
particular field of science or engineering in which the taxpayer
is performing the research.” While these regulations apply to
years ending on or after Dec. 31, 2003, sec. 1.41-4(e), Income
Tax Regs., respondent has taken the position that he will not
challenge return positions that are consistent with these final
regulations and therefore that the current regulation should
(continued...)
- 192 -
the taxpayer must intend that the information to be discovered
will be useful in the development of a new or improved business
component of the taxpayer (the business component test). Sec.
41(d)(1)(B)(ii). Fourth, substantially all of the research
activities must constitute elements of a process of
experimentation for a purpose relating to a new or improved
function, performance, reliability, or quality (the process of
experimentation test). Sec. 41(d)(1)(C), (3).
The Department of the Treasury (Treasury) and the Internal
Revenue Service (IRS) promulgated regulations to clarify the
definition of “qualified research” under section 41(d) that are
effective for taxable years ending on or after December 31, 2003.
Because the Treasury Decision implementing these regulations
states that “the IRS will not challenge return positions that are
consistent with these final regulations” for taxable years ending
before the effective date of this regulation, T.D. 9104, 2004-1
C.B. 406, 410, and respondent conceded that petitioner may rely
on the current regulations, we will not hold petitioner to a
higher standard than the regulations require.
42
(...continued)
govern the outcome of this case, see T.D. 9104, 2004-1 C.B. 406,
410. Accordingly, respondent concedes that petitioner satisfies
the “technological in nature” test as long as the information
sought to be discovered is in fact technological, and we accept
this concession. In light of the change to the test, we find
that it is more appropriate to refer to this test as the
“technological information test”.
- 193 -
The above tests are applied separately to each business
component. Sec. 41(d)(2)(A). A “business component” includes,
in pertinent part, a product or process that the taxpayer either
holds for sale, lease, or license or uses in its trade or
business. Sec. 41(d)(2)(B). In the case of a production
process, section 41(d)(2)(C) provides that “Any plant process,
machinery, or technique for commercial production of a business
component shall be treated as a separate business component (and
not as part of the business component being produced).”
The claim projects all relate to UCC’s processes for
commercial production of ethylene, PE, or related products.
Accordingly, each of the claim projects includes two business
components: (1) The production process and (2) the product being
produced. Petitioner argues that for each claim project it is
one of UCC’s processes, not the product produced, that is the
relevant business component. Therefore, in order to analyze the
discrete business components at issue, for each project we must
separate the activities that relate to the improvement of the
production process from the activities that relate to the product
being produced. Sec. 1.41-4(b)(1), Income Tax Regs. The fact
that activities that relate to the product being produced do not
satisfy the qualified research tests of section 41(d) will have
no impact on whether the activities that relate to the
improvement of the production process satisfy those tests.
- 194 -
If a business component as a whole fails the qualified
research tests, we may apply the “shrinking-back rule”, which
allows us to apply the qualified research tests to subsets of the
business component if doing so will allow the subset to satisfy
those tests. Sec. 1.41-4(b)(2), Income Tax Regs. The shrinking-
back rule provides that if the qualified research tests are not
satisfied at the level of the discrete business component, they
are then applied to the most significant subset of elements of
the business component. The shrinking-back continues until
either a subset of the business component satisfies the tests or
the most basic element of the business component is reached and
fails to satisfy the tests. The shrinking-back rule applies only
if the overall business component does not satisfy the qualified
research tests set out in section 41(d)(1) and is not itself a
reason to exclude activities from credit eligibility. Id.
1. The Section 174 Test
The section 174 test requires that expenditures connected
with the research activities must be eligible for treatment as
expenses under section 174. Section 174 provides alternative
methods of accounting for “research or experimental expenditures”
that taxpayers would otherwise capitalize. Sec. 1.174-1, Income
Tax Regs. The regulations define “research or experimental
expenditures” as “expenditures incurred in connection with the
taxpayer’s trade or business which represent research and
- 195 -
development costs in the experimental or laboratory sense.” Sec.
1.174-2(a)(1), Income Tax Regs.43 The parties do not dispute
that costs of the claim projects were incurred in connection with
UCC’s trade or business. As relevant here, an activity is
“research and development * * * in the experimental or laboratory
sense” if: (1) The information available to the taxpayer does
not establish the capability or method for developing or
improving a product or process or the appropriate design of a
product or process (i.e., an uncertainty exists); and (2) the
activity is intended to discover information that would eliminate
this uncertainty. Sec. 1.174-2(a)(1) and (2), Income Tax Regs.
Because the taxpayer need only be uncertain as to “the capability
or method * * * or the appropriate design” of the improvement, an
uncertainty may exist even if the taxpayer knows that it is
technically possible to achieve a goal but is uncertain of the
method or appropriate design to use to reach that goal. Sec.
1.174-2(a)(1), Income Tax Regs. (emphasis added). Whether an
43
While the current version of these regulations applies to
years beginning after Oct. 3, 1994, the Treasury Decision
accompanying the current regulations states: “Because the
amendments merely clarify the existing definition of research or
experimental expenditures, retroactive application of the
amendments is unnecessary. Return positions consistent with the
amendments will be consistent with the existing regulations and
will be recognized as such by the IRS.” T.D. 8562, 1994-2 C.B.
30, 31. Respondent concedes that petitioner may rely on the
current version of the regulations to determine whether the claim
projects carried out in 1994 constitute qualified research.
- 196 -
uncertainty exists is an objective test that depends on the
information available to the taxpayer. See Mayrath v.
Commissioner, 41 T.C. 582, 590-591 (1964), affd. 357 F.2d 209
(5th Cir. 1966). These guidelines apply to the nature of the
activity examined, not the nature of or the level of
technological advancement represented by the product or process.
Sec. 1.174-2(a)(1) and (2), Income Tax Regs.
However, deductions are allowed under section 174 only to
the extent that they are reasonable. Sec. 174(e). Furthermore,
deductions under section 174 are limited to “expenditures of an
investigative nature expended in developing the concept of a
model or product”, as opposed to the construction or manufacture
of the product itself. Mayrath v. Commissioner, supra at 590;
Glassley v. Commissioner, T.C. Memo. 1996-206; Kollsman
Instrument Corp. v. Commissioner, T.C. Memo. 1986-66, affd. 870
F.2d 89 (2d Cir. 1989). Therefore, if a project involves both
the development of the concept of a new or improved process and
the use of the process in production, only the activities related
to the development of the concept of the process satisfy the
section 174 test.
The regulations under section 174 exclude expenditures for
certain activities, including, as relevant here, the ordinary
testing or inspection of materials, products, or processes for
quality control (quality control testing). Sec. 1.174-2(a)(2)
- 197 -
and (3), Income Tax Regs. Quality control testing includes
testing or inspecting to determine whether particular units of
materials, products, or processes conform to specified
parameters. Sec. 1.174-2(a)(2) and (3), Income Tax Regs.
However, quality control testing does not include testing to
determine whether the design of the product or process is
appropriate. Sec. 1.174-2(a)(2), (3), and (4), Income Tax Regs.
Because section 174 refers to research and experimental
expenditures, not research and experimental activities, we
interpret section 41(d)(1)(A) as requiring only that qualified
research activities constitute research and development within
the meaning of section 174. However, as discussed below, to
determine which costs of those activities constitute QREs under
section 41(b), the reference to section 174 in section
41(d)(1)(A) requires us to consider whether those costs may be
treated as expenses under section 174. See Norwest Corp. & Subs.
v. Commissioner, 110 T.C. 454, 491 (1998).
2. The Technological Information Test
The technological information test requires that the
research be undertaken for the purpose of discovering information
that is “technological in nature”. Sec. 41(d)(1)(B)(i).
Information is “technological in nature” if it “fundamentally
relies on principles of the physical or biological sciences,
engineering, or computer science”. H. Conf. Rept. 99-841 (Vol.
- 198 -
II), at II-71 through II-72 (1986), 1986-3 C.B. (Vol. 4) 1, 71-
72. Therefore, discovery of information related to the social
sciences, arts, or humanities would not satisfy this test.
Norwest Corp. & Subs. v. Commissioner, supra at 492.
3. The Business Component Test
The business component test requires that the taxpayer
intend that the information to be discovered be useful in the
development of a new or improved business component of the
taxpayer. Sec. 41(d)(1)(B)(ii). To be useful within the meaning
of this test, the research need only provide some level of
functional improvement to the taxpayer. Norwest Corp. & Subs. v.
Commissioner, supra at 495.
4. The Process of Experimentation Test
The process of experimentation test has three elements: (1)
Substantially all of the research activities must constitute (2)
elements of a process of experimentation (3) for a qualified
purpose. Sec. 41(d)(1)(C).
The “substantially all” element means that 80 percent or
more of the taxpayer’s research activities for each business
component, measured on a cost or other consistently applied
reasonable basis, must constitute a process of experimentation
for a qualified purpose. Norwest Corp. & Subs. v. Commissioner,
supra at 497; sec. 1.41-4(a)(6), Income Tax Regs. A taxpayer
does not fail this requirement even if the remaining 20 percent
- 199 -
(or less) of its research activities with respect to the business
component do not constitute elements of a process of
experimentation for a purpose described in section 41(d)(3) as
long as the remaining research activities satisfy the
requirements of section 41(d)(1)(A) (the section 174 test) and
are not otherwise excluded under section 41(d)(4). Sec. 1.41-
4(a)(6), Income Tax Regs. If a business component fails the
process of experimentation test because of the “substantially
all” requirement, the taxpayer may apply the shrinking-back rule,
discussed above, until an element that satisfies the test is
reached. Norwest Corp. & Subs. v. Commissioner, supra at 497.
A process of experimentation is “a process designed to
evaluate one or more alternatives to achieve a result where the
capability or the method of achieving that result, or the
appropriate design of that result, is uncertain as of the
beginning of the taxpayer’s research activities.” Sec. 1.41-
4(a)(5)(i), Income Tax Regs. The “uncertainty” element of this
test is essentially the same uncertainty as is required by the
section 174 test,44 and the test may be satisfied even if the
taxpayer is certain of either the capability or method of
achieving the desired goal if the appropriate design of the
desired result is uncertain at the outset. Sec. 1.41-4(a)(5)(i),
44
Sec. 1.174-2(a)(1), Income Tax Regs., provides that
“Uncertainty exists if the information available to the taxpayer
does not establish the capability or method for developing or
improving the product or the appropriate design of the product.”
- 200 -
Income Tax Regs.; cf. Norwest Corp. & Subs. v. Commissioner,
supra at 496.45
However, this test also imposes a more structured method of
discovering information than section 174 requires and may not
include all actions a taxpayer takes to resolve uncertainty. See
Norwest Corp. & Subs. v. Commissioner, supra at 496; see also
Eustace v. Commissioner, 312 F.3d 905, 907 (7th Cir. 2002), affg.
T.C. Memo. 2001-66. The process of experimentation test was
added to section 41 because Congress was concerned that taxpayers
had been claiming the credit “for virtually any expenses relating
to product development” as opposed to high technology. S. Rept.
99-313, supra at 694-695, 1986-3 C.B. (Vol. 3) at 694-695; see
also H. Rept. 99-426, supra at 178, 1986-3 C.B. (Vol. 2) at 178.
The process of experimentation test is not necessarily satisfied
just because a taxpayer takes steps to improve a business
component. The legislative history explains:
The term process of experimentation means a
process involving the evaluation of more than one
alternative designed to achieve a result where the
means of achieving that result is uncertain at the
outset. This may involve developing one or more
hypotheses, testing and analyzing those hypotheses
(through, for example, modeling or simulation), and
refining or discarding the hypotheses as part of a
sequential design process to develop the overall
component.
45
As discussed above, we shall apply the more generous rule
of the final regulations where it differs from our prior
holdings.
- 201 -
Thus, for example, costs of developing a new or
improved business component are not eligible for the
credit if the method of reaching the desired objective
(the new or improved product characteristics) is
readily discernible and applicable as of the beginning
of the research activities, so that true
experimentation in the scientific or laboratory sense
would not have to be undertaken to develop, test, and
choose among viable alternatives. On the other hand,
costs of experiments undertaken by chemists or
physicians in developing and testing a new drug are
eligible for the credit because the researchers are
engaged in scientific experimentation. Similarly,
engineers who design a new computer system, or who
design improved or new integrated circuits for use in
computer or other electronic products, are engaged in
qualified research because the design of those items is
uncertain at the outset and can only be determined
through a process of experimentation relating to
specific design hypotheses and decisions as described
above. [H. Conf. Rept. 99-841 (Vol. II), supra at II-
72, 1986-3 C.B. (Vol. 4) at 72.]
This requires the use of the scientific method sense, not merely
taking steps to resolve uncertainty or to improve a product. See
Black’s Law Dictionary (8th ed. 2004) (defining the “scientific
method” as “An analytical technique by which a hypothesis is
formulated and then systematically tested through observation and
experimentation.”). To satisfy the process of experimentation
test, the taxpayer should develop a hypothesis as to how a new
alternative might be used to develop a business component, test
that hypothesis in a scientific manner, analyze the results of
the test, and then either refine the hypothesis or discard it and
develop a new hypothesis and repeat the previous steps.
It is not sufficient that the taxpayer use a method of
simple trial and error to validate that a process or product
- 202 -
change meets the taxpayer’s needs. See id. While the
Commissioner concedes in the regulations that a “systematic trial
and error methodology” can be a process of experimentation, sec.
1.41-4(a)(5)(i), Income Tax Regs., the term “systematic” suggests
that the project must involve a methodical plan involving a
series of trials to test a hypothesis, analyze the data, refine
the hypothesis, and retest the hypothesis so that it constitutes
experimentation in the scientific sense. Testing and refining a
hypothesis may involve determining the strengths and weakness of
the alternative tested, whether and how the process could be
further refined and improved, and whether other alternatives
might be better suited for achieving the taxpayer’s goal. While
the process of experimentation need identify only one
alternative, it generally should be capable of evaluating more
than one alternative. Sec. 1.41-4(a)(5)(i), Income Tax Regs. If
only one alternative is tested, for that alternative to
constitute a process of experimentation the taxpayer should
conduct a series of experiments with the alternative in order to
develop the business component. See H. Conf. Rept. 99-841 (Vol.
II), supra at II-72, 1986-3 C.B. (Vol. 4) at 72.
In response to commentary that “in the industrial or
commercial setting, the recording of results is not necessarily
inherent in a bona fide process of experimentation”, Treasury and
the IRS acknowledged that the regulations in place during the
- 203 -
years at issue did not impose any rules regarding the recording
of experiment results. T.D. 8930, 2001-1 C.B. 433, 437.
However, even if the results are not actually recorded, the
taxpayer should perform a sufficient analysis of the alternative
tested so that the taxpayer could meaningfully compare one
alternative to another. Furthermore, section 1.41-4(d), Income
Tax Regs., requires a taxpayer to “retain records in sufficiently
usable form and detail to substantiate that the expenditures
claimed are eligible for the credit.”
The qualified purposes are purposes relating to a new or
improved function, performance, reliability, or quality. Sec.
41(d)(3). By contrast, style, taste, cosmetic, or seasonal
design factors are not qualified purposes. Sec. 41(d)(3)(B).
5. Activities That Are Not Qualified Research
Section 41(d)(4) lists certain activities that do not
constitute qualified research, including, as relevant here: (1)
Research after commercial production, (2) routine data
collection, (3) foreign research, and (4) funded research.
Research conducted after the beginning of commercial
production is not qualified research. Sec. 41(d)(4)(A). A
business component is ready for commercial production when it is
developed to the point where it: (1) Meets the basic functional
and economic requirements of the taxpayer; or (2) is ready for
commercial sale or use. H. Conf. Rept. 99-841 (Vol. II), supra
- 204 -
at II-74, 1986-3 C.B. (Vol. 4) at 74. Typical examples of
activities conducted after commercial production include: (1)
Preproduction planning for a finished business component; (2)
tooling-up for production; (3) trial production runs; (4)
trouble-shooting involving detecting faults in production
equipment or processes; (5) accumulation of data relating to
production processes; and (6) debugging product flaws. Id. at
II-74 through II-75, 1986-3 C.B. (Vol. 4) at 74-75. The
exclusion for research after commercial production applies
separately to the activities relating to the development of the
product and the activities relating to the development of the
process. Sec. 1.41-4(c)(2)(iii), Income Tax Regs. Therefore,
even after a product is ready for commercial sale, activities
relating to the development of the manufacturing process may
constitute qualified research.
Funded research refers to research to the extent it is
funded by any grant, contract, or otherwise by another person or
governmental entity. Sec. 41(d)(4)(H).
B. The Claim Projects
1. Plant-Based Research
All of the claim projects took place at UCC’s manufacturing
plants during the production process. Petitioner argues that as
a general matter, plant-based research can be “qualified
research”. Mr. Spitz, one of petitioner’s expert witnesses,
- 205 -
testified that petrochemical chemical companies carry out plant-
scale R&D for many reasons, such as developing new process
technologies and products, enhancing the performance of existing
process technologies and products, and attempting to resolve
operational problems. Mr. Spitz believes that it is essential
for petrochemical companies to conduct research at commercial
plants to obtain meaningful test data. In Mr. Spitz’s opinion,
experiments conducted in laboratories or pilot plants cannot
simply be “scaled-up” to full-sized plants without additional
testing because of the differences in size, dimensions, and fluid
dynamics of plant equipment and the inherent unpredictability of
chemical reactions and chemical plant operations.
Petitioner argues that making plant-based research eligible
for the research credit comports with Congress’ intent to promote
business research in order to spur economic growth. Furthermore,
petitioner argues that Congress could not have intended to
foreclose availability of the credit for research that is helpful
to a taxpayer’s trade or business because the research was
conducted in a plant environment and the research resulted in
salable products.
Respondent agrees that plant-based research satisfying
section 41(d) is eligible for the research credit. However,
respondent argues that all of the claim projects fail the
qualified research tests because the activities involved in the
- 206 -
claim projects were primarily production activities, not
investigative activities related to developing the concept of the
process, and therefore fail the section 174 test under Mayrath v.
Commissioner, 41 T.C. at 590. Respondent argues that the claim
projects also fail the section 174 test because they were
designed to produce products for sale, not to eliminate any
uncertainties. Furthermore, respondent argues that all of the
claim projects fail the process of experimentation test because
substantially all of the activities for which petitioner is
claiming QREs constituted production activities, not elements of
a process of experimentation. Respondent also argues that the
claim projects involve research after the beginning of commercial
production and therefore are excluded under section 41(d)(4)(A).
Petitioner argues that respondent incorrectly identified the
end products produced by UCC, not the techniques and processes
UCC employed to produce those products, as the “business
component” to which the research relates. While the products
produced during the claim projects already met UCC’s basic
functional and economic requirements, petitioner argues that the
processes were still experimental and had not yet been proven.
As discussed above, under section 41(d)(2)(C) plant
processes for commercial production are treated as a separate
business component from the product being produced. Accordingly,
where a taxpayer seeks research credits for plant processes but
- 207 -
not for the products produced, we apply the qualified research
tests only to activities related to the development of the
process without taking into account the activities related to the
production or development of the product. Sec. 1.41-4(b)(1),
Income Tax Regs. While each of the claim projects in its
entirety necessarily involves production activities because the
goal of each of the claim projects was to improve UCC’s
production process, we find that for each of the claim projects
there are two business components: (1) A process business
component and (2) a product business component. The activities
that relate primarily to the improvement of UCC’s processes are
part of the process business component, and the activities that
relate primarily to the production of products are part of the
product business component. Therefore, respondent’s arguments
that petitioner’s production activities do not satisfy the
section 174 test or the process of experimentation test have no
bearing on whether the activities that relate primarily to the
development of UCC’s processes satisfy the qualified research
tests.
2. The Amoco Anticoking Project
Petitioner claims that the Amoco anticoking project
constitutes qualified research and the specific business
component at issue is the olefins production process. As
discussed above, under section 41(d)(2)(C) and section 1.41-
- 208 -
4(b)(1), Income Tax Regs., we find that only activities that
relate to the improvement of UCC’s olefins production process,
not production activities, are part of this business component.
a. The Section 174 Test
In the opinion of Dr. Froment, one of petitioner’s expert
witnesses, the Amoco anticoking project was designed to eliminate
several uncertainties, in particular whether the pretreatment
would: (1) Inhibit, reduce, or increase coke formation; (2)
extend run lengths between furnace turnarounds; and/or (3)
adversely affect the downstream manufacturing processes or
properties of finished olefins products. While the Amoco
technology had shown promise in tests in laboratories and pilot
plants, petitioner argues that UCC believed that it had not yet
been proven and UCC was unsure whether it would work on its
commercial-scale ethylene furnaces.
Respondent argues that the Amoco anticoking project fails
the section 174 test because petitioner did not show that UCC
undertook the project for the purpose of eliminating an
uncertainty. Respondent argues that UCC believed that the Amoco
technology’s capabilities were already well established because
Amoco told UCC that its technology had been successfully tested
in two commercial plants. Accordingly, respondent believes that
UCC was merely testing the Amoco technology to validate that it
worked as Amoco claimed. Respondent argues that UCC did not
- 209 -
realize that Amoco’s technology was still developmental until
just before it abandoned the project.
Petitioner argues that the technology was promising but far
from proven. There is some conflicting evidence in the record as
to how well established UCC believed Amoco’s technology to be at
the time it agreed to test the technology.46 However, it is
clear that neither UCC nor Amoco regarded the technology as
proven or established to the point where it could be licensed
commercially. The fact that Amoco applied the treatment at no
cost to UCC supports petitioner’s argument that the technology
was not fully established. When UCC decided to undertake the
Amoco anticoking project, the information available did not
establish that Amoco’s technology was capable of preventing or
reducing coking on UCC’s furnaces. See sec. 1.174-2(a)(1),
Income Tax Regs.
Section 174 does not require that the technology be in the
very beginning stages of development, only that the taxpayer be
uncertain as to whether the technology will improve its product
or process. The record supports petitioner’s argument that UCC
was uncertain as to whether the Amoco anticoking technology would
work in UCC’s facilities. Therefore, we find that at the time of
46
Dr. Milks testified that he believed that the Amoco
technology was experimental and definitely not proven. Jack
Marchio, the technology manager for hydrocarbons R&D at the South
Charleston technical center, testified that he thought the Amoco
technology was established technology.
- 210 -
the test UCC was uncertain as to whether coke formation could be
reduced in its commercial facility and, if so, whether Amoco’s
technology would reduce it.
Respondent also argues that the Amoco anticoking project is
not qualified research because it does not satisfy the test of
Mayrath v. Commissioner, 41 T.C. at 590. Respondent argues that
most of the claimed costs associated with the Amoco anticoking
project relate primarily to production activities, not the
development of the concept of the Amoco anticoking technology.
We agree with respondent that many of the activities
involved in the Amoco anticoking project did not relate to the
development of the concept of using the Amoco technology to
reduce coke formation but instead constituted production
activities, such as the basic operation of furnace 24 and all
downstream activities. These production activities relate
primarily to the production of ethylene, not the improvement of
UCC’s production process. Accordingly, they are part of the
product business component, not the process business component at
issue, and do not affect our analysis. To the extent that
petitioner has included production activities as part of the
business component, we may apply the shrinking-back rule and
apply the qualified research tests to the most significant subset
of elements of the process that satisfies the qualified research
tests, which we find to be the subset of activities that relate
- 211 -
primarily to the testing of the Amoco technology. See sec. 1.41-
4(b)(2), Income Tax Regs.
We find that the following activities relate primarily to
the testing of the Amoco technology and are therefore the focus
of our inquiry: (1) Reviewing research of prior testing of the
Amoco technology; (2) preparing a test plan; (3) designating
reference and experimental cracking sets; (4) preparing for the
test; (5) applying the pretreatment; (6) collecting test data;
(7) analyzing the data; (8) forming of a conclusion; (9) refining
the hypothesis; and (10) repeating steps 4 through 8 for the
refined hypothesis (collectively, Amoco anticoking research
activities). We find that these activities related to the
development of the concept of using the Amoco anticoking
technology and therefore are not excluded under Mayrath.
Accordingly, the Amoco anticoking research activities, as defined
above, satisfy the section 174 test.
b. The Technological Information Test
Petitioner argues that the Amoco anticoking project
satisfies the technological information test because the
information it sought to discover was based on organic chemistry,
chemical engineering, and other sciences. We agree that the
Amoco anticoking research activities satisfy this test.
- 212 -
c. The Business Component Test
Petitioner argues that the Amoco anticoking project
satisfies the business component test because it was designed to
improve the performance of its olefins production processes by
reducing coke formation. We agree that the Amoco anticoking
research activities, as defined in part a., satisfy this test.
d. Process of Experimentation Test
In the opinion of Dr. Froment, the Amoco anticoking project
consisted of a process of experimentation in the scientific sense
because UCC: (1) Researched and considered a variety of
anticoking technologies; (2) developed and implemented a detailed
test plan by designating reference versus experimental cracking
sets, applying the pretreatment, and recording test data; (3)
analyzed the results; (4) refined the process after results from
the first test were not satisfactory; (5) retested the product;
and (6) drew a conclusion. Petitioner argues that substantially
all of the activities involved in the Amoco anticoking project
were part of this process of experimentation and that the project
was conducted for a qualified purpose--the evaluation of whether
the Amoco pretreatment would improve the olefins production
process by inhibiting coke formation.
Respondent argues that UCC’s activities did not constitute a
process of experimentation because UCC was merely validating
Amoco’s claim that the technology worked.
- 213 -
We find that the Amoco anticoking research activities
constitute a process of experimentation. UCC did not merely
determine whether the Amoco technology inhibited coke formation
but instead collected and analyzed data that could be used to
compare the technology with alternatives. When the first
pretreatment proved to be unsuccessful, UCC considered that the
problem might have been the fact that the pretreatment was
applied over coke remaining after a hot decoke. UCC refined the
process by applying the second pretreatment to the furnace after
a cold turnaround. After UCC applied the second pretreatment in
April 1995, it continued to collect and analyze data until August
1995, and it used the data analysis to evaluate the technology.
While UCC did not continue to refine its hypothesis as to the
effectiveness of the Amoco technology and test it for four
consecutive furnace cycles as it had planned, satisfaction of the
process of experimentation test does not require a taxpayer to
continue testing a hypothesis that has no possibility of success.
Such a requirement would be contrary to the purpose of section
41. Accordingly, we find that UCC used a process of
experimentation to evaluate the Amoco technology and did not
merely change its process and decide whether the change satisfied
its basic needs.
Petitioner argues that this project was undertaken for a
qualified purpose–-to evaluate the efficiency of the Amoco
- 214 -
technology at inhibiting coke formation in order to improve the
function, reliability, and performance of the ethylene production
process. Successful coke inhibition would have resulted in
significantly longer furnace runs, reduced maintenance, longer
equipment life, and increased ethylene productivity, yielding
significant cost savings and increased profits. We agree that
this was a qualified purpose.
Respondent counters that even if the Amoco anticoking
project exhibits some characteristics of research, it fails the
“substantially all” test. See Norwest Corp. & Subs. v.
Commissioner, 110 T.C. at 497. Respondent argues that
substantially all of the activities for which petitioner is
claiming QREs do not constitute elements of a process of
experimentation but instead constitute production activities.
We agree that the ordinary production activities that would
have occurred even if UCC was not conducting an experiment do not
constitute elements of a process of experimentation. However, as
discussed above with regard to the section 174 test, we find that
the qualified research tests should be applied solely to the
Amoco anticoking research activities. Accordingly, we consider
only whether these activities satisfy the process of
experimentation test. We find that when we limit the project to
only the Amoco anticoking research activities, “substantially
- 215 -
all” of those activities satisfy the process of experimentation
test.
Respondent argues that even if the Amoco anticoking project
satisfies the qualified research tests, it is excluded from the
definition of qualified research because it constitutes funded
research, research after commercial production, or data
collection and routine testing.
e. Funded Research
Section 41(d)(4)(H) provides that research is not qualified
research “to the extent funded by any grant, contract, or
otherwise by another person”. The evidence shows that Amoco and
UCC each paid their own costs during the Amoco anticoking
project. While Amoco covered the cost of applying the
pretreatment and was contractually obligated to pay for any
overtime worked by UCC employees, petitioner did not include any
of these costs in its QRE calculations.
Respondent argues that under section 1.41-4A(d)(2), Income
Tax Regs., as made applicable by section 1.41-4(c)(9), Income Tax
Regs., research is treated as fully funded “If a taxpayer
performing research for another person retains no substantial
rights in research under the agreement providing for the
research”. Furthermore, under section 1.41-4A(d)(3), Income Tax
Regs., “A taxpayer does not retain substantial rights in the
- 216 -
research if the taxpayer must pay for the right to use the
results of the research.”
However, petitioner is not seeking credit for research
conducted for the benefit of Amoco or that Amoco would purchase
from UCC. It would clearly violate Congress’s intent in enacting
section 41 if a taxpayer could seek a tax credit for research
that it did not ultimately pay for. Petitioner is also not
seeking credit for the costs that Amoco incurred to develop the
technology. Petitioner is seeking credit for research that UCC
performed for its own benefit and at its own cost. While UCC did
not gain any rights to Amoco’s technology by conducting the Amoco
anticoking project, UCC retained all rights to its own research.
Petitioner produced credible evidence at trial that the
information that UCC gained during the Amoco anticoking project
was valuable regardless of whether it licensed Amoco’s technology
or not. Accordingly, we find that the Amoco anticoking research
activities do not constitute funded research.
f. Research After Commercial Production
Respondent argues that the Amoco anticoking project is
research after commercial production because UCC’s olefins
process already met its functional and economic requirements.
Respondent points out that the Amoco anticoking project did not
disrupt UCC’s normal production process and resulted in a salable
- 217 -
product. Respondent argues that UCC was simply tweaking its
existing process.
Petitioner argues that the Amoco anticoking project was not
merely research after commercial production but was a process of
experimentation that UCC had to conduct before deciding whether
to license Amoco’s technology. As discussed above, it is only
the Amoco anticoking research activities that we must examine,
not UCC’s entire olefins process, which we agree already met
UCC’s basic functional and economic requirements and was used
commercially. We conclude that the Amoco technology was not yet
ready for commercial use at the time UCC undertook the Amoco
anticoking project. The fact that Amoco’s technology ultimately
failed is a clear indication that it did not meet UCC’s needs.
Petitioner further argues that the Amoco anticoking project was
not a “trial production run” because it was conducted before the
potential process improvement, the Amoco technology, was
satisfactorily tested and proven. We agree with petitioner that
the Amoco anticoking research activities were not merely research
after commercial production and are not excluded from the
definition of qualified research by section 41(d)(4)(A).
g. Data Collection and Routine Testing
Respondent next argues that the Amoco anticoking project is
specifically excluded from the definition of qualified research
because it constitutes routine data collection, routine or
- 218 -
ordinary testing, or inspection for quality control. Respondent
argues that after the initial results from the first pretreatment
suggested failure, the activities occurring during the remaining
period were primarily the accumulation of data. Respondent
points out that some of the data that UCC collected were
routinely collected in its normal operations and was available to
UCC regardless of whether a test were being conducted.
Petitioner counters that during the Amoco anticoking project
UCC collected some data that it did not normally measure and took
other measurements more frequently than it normally took them.
Furthermore, petitioner points out that UCC analyzed the
collected data, which UCC did not normally do. While UCC did
take some measurements during the normal olefins production
process, petitioner argues that the purpose of those measurements
was to ensure that furnace was operating normally. By contrast,
petitioner argues that during the Amoco anticoking project UCC
took many more measurements for the purpose of determining
whether Amoco’s anticoking technology actually reduced the
formation of coke and whether the technology could improve UCC’s
production process. We agree that UCC’s activities went beyond
routine data collection and that the Amoco anticoking research
activities are not excluded from the definition of qualified
research by section 41(d)(4)(D).
- 219 -
h. Substantiation Requirement
Respondent finally argues that even if the Amoco anticoking
project would otherwise satisfy the qualified research tests,
petitioner has not substantiated its claim after the 10th week of
testing. While the activities that occurred from the first
pretreatment to the cold turnaround in January 1995 were
documented in the project report dated February 21, 1995,
respondent points out that there is no comparable project report
to corroborate UCC’s argument that the Amoco anticoking project
continued with a second pretreatment in April 1995 and additional
testing until the August 1995 cold turnaround. Respondent argues
that petitioner was unable to find any data or analysis of data
collected after February 21, 1995. Therefore, respondent argues
that petitioner has failed to substantiate any activities after
the February 21, 1995, project report was written. See sec.
6001; Boyd v. Commissioner; 122 T.C. 305, 320 (2004); Tyson
Foods, Inc. & Subs. v. Commissioner, T.C. Memo. 2007-188; Eustace
v. Commissioner, T.C. Memo. 2001-66; sec. 1.6001-1, Income Tax
Regs.
Petitioner argues that there is sufficient evidence to show
that UCC continued to run the test and evaluate data until August
1995. Petitioner offered four witnesses who corroborated that
the second test occurred, two of whom confirmed that the test
lasted until August 1995. Furthermore, petitioner submitted
- 220 -
documentary evidence that confirms the testimony and shows that
some analysis was performed on the data collected from the second
test. One of respondent’s own expert witnesses, Mr. Halle,
concluded that the Amoco anticoking project lasted 8 to 9 months.
Accordingly, on the basis of the entire record, we conclude that
petitioner sufficiently substantiated its claim that the Amoco
anticoking project included a second test that ran from April to
August 1995.
On the basis of the foregoing, we hold that the Amoco
anticoking research activities were qualified research.
3. The Spuds Project
Petitioner originally claimed that the spuds project was
qualified research but now concedes that it does not satisfy the
requirements of section 41(d). Dr. Wadia testified that, in his
opinion, the spuds project did not constitute research or
experimentation in the scientific sense. Dr. Wadia believes that
the spuds project was a standard mechanical design change
followed by routine plant troubleshooting. Dr. Wadia also
believes that the spuds project presented a low level of
uncertainty because UCC had been using one-hole spuds at Olefins-
2 for 18 years.
Petitioner originally argued that the relevant business
component was the olefins production process. As discussed
above, under section 41(d)(2)(C) and section 1.41-4(b)(1), Income
- 221 -
Tax Regs., we find that only activities that relate to the
improvement of UCC’s olefins production process, not production
activities, are part of this business component.
a. The Section 174 Test
In the opinion of Dr. Martin, another of petitioner’s expert
witnesses, the purpose of the spuds project was to eliminate
uncertainties concerning improvements that might be achieved in
the operation of the Olefins-1 furnaces by replacing the four-
hole spuds with one-hole spuds. Dr. Martin’s opinion is that it
would be impossible to determine the impact of the change on all
of the various operating conditions in the furnace by calculation
or by testing in a small test facility similar to the test
facilities operated by burner vendors. Petitioner originally
argued that the specific uncertainties that the spuds project was
designed to eliminate were whether the new spud design would:
(1) Reduce plugging, carbon monoxide levels, and erratic burner
flame patterns; (2) increase furnace fuel efficiency; and/or (3)
adversely affect furnace operations or downstream processes.
Specifically, UCC was concerned that using the one-hole spuds
would increase the level of noise from the furnaces above
acceptable levels.
Respondent argues that the spuds project fails the section
174 test because the project was not designed to eliminate any
uncertainties. Ms. McClung, one of respondent’s expert
- 222 -
witnesses, testified that the one-hole spud design maintained the
same design flow area as the four-hole spuds and did not
necessitate testing to validate performance. In Ms. McClung’s
opinion, changing the number of spud holes without changing the
total area of the holes would not be expected to significantly
affect anything concerning the furnace or burner operation other
than to reduce or eliminate the plugging problem. Furthermore,
Ms. McClung believes that UCC’s experience with one-hole spuds on
its Olefins-2 furnaces eliminated any uncertainties that may have
otherwise existed. Accordingly, respondent argues that UCC was
certain that replacing four-hole spuds with one-hole spuds would
result, at a minimum, in the improvement of the plugging problem
on the basis of its use of the one-hole spuds at Olefins-2 and
common sense.
Petitioner’s fact witnesses testified that they hoped that
the one-hole spuds would improve the process, but they were not
certain. However, the section 174 test requires that an
objective uncertainty exist as to the capability or method for
developing or improving a product or process or the appropriate
design of a product or process. See Mayrath v. Commissioner, 41
T.C. at 590-591. We find that regardless of whether some of
UCC’s employees were not certain that the one-hole spuds would
improve UCC’s production process at Olefins-1, UCC had sufficient
information available to it, both information gathered from its
- 223 -
own experiences using one-hole spuds and information provided by
the John Zink Co., to be certain that the one-hole spuds were
capable of improving UCC’s production process.
Furthermore, UCC was certain that changing the four-hole
spuds to one-hole spuds was the appropriate method for reducing
plugging. UCC knew that changing the spuds would be an effective
and relatively inexpensive way to solve the problem.
Finally, there was no uncertainty as to the appropriate
design of the improvement. The John Zink Co. designed the one-
hole spud, and there is no evidence that UCC ever considered
adapting the John Zink Co.’s design.
b. The Remaining Tests
Because the spuds project fails the section 174 test, we
need not address whether it satisfies the remaining tests.
4. The Sodium Borohydride Project
Petitioner claims that the sodium borohydride project is
qualified research. Petitioner identified the olefins production
process as the relevant business component. As discussed above,
under section 41(d)(2)(C) and section 1.41-4(b)(1), Income Tax
Regs., we find that only activities that relate to the
improvement of UCC’s olefins production process, not production
activities, are part of this business component.
- 224 -
a. The First Three Tests
As explained below, we find that the sodium borohydride
project fails the process of experimentation test. Accordingly,
we need not discuss whether it satisfies the section 174,
technological information, or business component test.
b. The Process of Experimentation Test
Petitioner argues that the sodium borohydride project
satisfies the process of experimentation test because
substantially all of the activities involved constitute a process
of experimentation designed to determine whether UCC could
effectively use sodium borohydride to remove acetaldehyde to
below 100 ppm while the MEA system was out of service.
Petitioner argues that the process involved: (1) Considering
alternatives, most notably sodium bisulfate; (2) preparing a
detailed project memorandum and an FOCR; (3) posing and answering
a series of questions about the proposed sodium borohydride
injections; (4) determining test dosages and injection rates; (5)
injecting the sodium borohydride; (6) sampling the cracked gas
stream and crude butadiene product for acetaldehyde; (7) sampling
the wastewater for boron; (8) analyzing the results; and (9)
evaluating the results and drawing the conclusion that sodium
borohydride had successfully removed acetaldehyde to below
specification levels. Furthermore, petitioner argues that the
process of experimentation was for qualified purposes–-improved
- 225 -
function and performance of Taft’s ethylene production process
and improved quality of the consumer product.
Respondent argues that the sodium borohydride project did
not involve a process of experimentation but was merely a method
of reducing the acetaldehyde in UCC’s crude butadiene.
Respondent argues that UCC was not evaluating alternatives but
was simply validating that injecting sodium borohydride could be
used to remove acetaldehyde and troubleshooting any problems that
came up. Respondent argues that while sodium bisulfate could
have been used as an alternative to sodium borohydride, UCC never
seriously considered using sodium bisulfate because it knew that
sodium borohydride would work better. In respondent’s opinion,
the occurrence of operating issues or the collection of data does
not make a process one of experimentation. Respondent argues
that the sodium borohydride project lacked any analysis of the
data collected or evaluation of the process change beyond
validating that the change satisfied UCC’s needs.
We agree with petitioner that the sodium borohydride
research activities were designed to resolve uncertainty. Even
if the capability of using sodium borohydride to remove
acetaldehyde was generally known, UCC was not certain whether (1)
sodium borohydride was the appropriate method for removing
acetaldehyde from crude butadiene while the MEA system was out of
- 226 -
service given its high cost and unknown efficiency or (2) UCC’s
design for injecting sodium borohydride was appropriate.
However, to constitute a process of experimentation, the
sodium borohydride project research activities must have been
designed not only to test whether sodium borohydride satisfied
UCC’s needs but to evaluate the use of sodium borohydride through
a sequential process of experimentation. Such a process would
include not only planning the test, implementing the test, and
collecting data, but would also include analyzing of the data
collected, refining and discarding hypotheses, and progressively
developing the process. There is no evidence to support UCC’s
assertion that it actually analyzed the data it collected beyond
determining that sodium borohydride reduced acetaldehyde below
100 ppm. While petitioner argues that UCC was uncertain about
the appropriate dosages or injection rates, there is no evidence
that UCC experimented with dosages or injection rates or
determined the optimal dosage and injection rate. UCC was merely
validating that injecting sodium borohydride into the caustic
scrubber would reduce acetaldehyde to on-specification levels.
There is also no evidence that the results of the test were
sufficiently analyzed so that UCC could compare them with the
results of tests of other alternatives. UCC’s data collection
alone, no matter how extensive, does not constitute a process of
experimentation if it is not followed by meaningful analysis.
- 227 -
While Dr. Manyik prepared an R&D report for the sodium
borohydride project that UCC considered to be the functional
equivalent of a project report, Dr. Manyik prepared the R&D
report before the test of sodium borohydride occurred.
Therefore, it could not have included any analyses of the project
that were not available before the project began. The fact that
UCC found Dr. Manyik’s R&D report and other prerun reports
sufficient to document the sodium borohydride project indicates
that UCC did not find it necessary to analyze the results of the
project and was not interested in developing or refining its
process. Accordingly, we find that the sodium borohydride
research activities fail the process of experimentation test and
were not qualified research. We need not address respondent’s
remaining arguments relating to this project.
5. The UOP GA-155 Project
Petitioner argues that the UOP GA-155 project is qualified
research and that the relevant business component is the olefins
production process. As discussed above, under section
41(d)(2)(C) and section 1.41-4(b)(1), Income Tax Regs., we find
that only activities that relate to the improvement of UCC’s
olefins production process, not production activities, are part
of this business component.
- 228 -
a. The Section 174 Test
Petitioner argues that the UOP GA-155 project satisfies the
section 174 test because it was designed to eliminate
uncertainties as to: (1) Whether UOP GA-155 would reduce
butadiene polymer fouling in the C3 column and reboilers; (2) the
proper dosage of UOP GA-155 to both reduce C3 column fouling and
stabilize the dripolene; and/or (3) whether UOP GA-155 would
adversely affect Taft’s downstream processes and commercial
products. Petitioner argues that these uncertainties could not
have been resolved without a plant test because laboratory tests
would not translate well to the plant.
Respondent argues that the UOP GA-155 project fails the
section 174 test because any uncertainties with respect to
injecting UOP GA-155 had been resolved before the project began.
Respondent believes that the only question that remained was how
much UOP GA-155 to use, and UCC intended to resolve this issue by
obtaining advice from UOP, not through its own testing.
Respondent argues that there were no issues with respect to the
capability or method for developing or improving the process or
the appropriate design of the process but that UCC was merely
verifying UOP’s claims that UOP GA-155 would reducing fouling.
If there were any uncertainties with respect to the UOP GA-155
project, respondent argues that they would have been reflected in
the FOCR.
- 229 -
While UCC’s employees testified that they were uncertain
whether UOP GA-155 would reduce fouling, we find that the
information available to UCC established that UOP GA-155 would be
effective. The evidence shows that UOP, not UCC, performed the
research to determine UOP GA-155’s effectiveness. The fact that
UCC desired to confirm UOP’s assertions with its own testing does
not create an uncertainty within the meaning of section 174. The
section 174 test is an objective test, and a taxpayer may not
turn its back on the available information in order to create
uncertainty.
Furthermore, there is no evidence that UCC was uncertain as
to the appropriate method for reducing fouling. UCC had
significant experience using inhibitors before beginning the UOP
GA-155 project and there is no evidence that UCC had any doubt
that injecting an inhibitor into the C3 column was the
appropriate method to reduce fouling in the C3 column.
Finally, UCC had sufficient information available to it to
eliminate any uncertainties as to the appropriate design of using
UOP GA-155 to reduce fouling in the C3 column. It was UOP that
developed UOP GA-155, studied UCC’s process, and recommended the
design that UCC should use to inject UOP GA-155. There is no
evidence that UCC intended to use the UOP GA-155 project to
discover information to improve upon or change the design
suggested by UOP.
- 230 -
b. The Remaining Tests
Because the UOP GA-155 project fails the section 174 test,
we need not address whether it satisfies the remaining qualified
research tests.
6. The UCAT-J Project
Petitioner claims that the UCAT-J project is qualified
research and that the relevant business component is the PE
production process. Respondent argues that each of the
individual UCAT-J runs constitutes a separate project. We find
that the UCAT-J runs were separate tests in the same project to
develop the use of UCAT-J in UCC’s PE production process and
should be treated as a single business component. However, as
discussed above, under section 41(d)(2)(C) and section 1.41-
4(b)(1), Income Tax Regs., we find that only activities that
relate to the improvement of UCC’s PE production process, not
production activities, are part of this business component.
a. The Section 174 Test
In the opinion of Dr. Brockmeier, one of petitioner’s expert
witnesses, the UCAT-J project was designed to discover
information that would eliminate several uncertainties relating
to whether UCC could use UCAT-J to produce PE base resins in
Star’s UNIPOL reactors with reactor operability and continuity
and product properties equivalent to or better than those that
could be achieved using M-1. For example, Dr. Brockmeier
- 231 -
believes that UCC was uncertain whether using UCAT-J as the
catalyst would increase the amount of static in the reactor and
cause operability problems. Static was a greater problem with
UCAT-J than with M-1 because of the dielectric properties of the
UCAT-J system. In Dr. Brockmeier’s opinion, UCC could not
discover how to solve this problem at the pilot plants or smaller
commercial reactors because static was less of a problem in
smaller reactors. Petitioner argues that other examples of
operability issues related to UCAT-J were UCC’s ability to: (1)
Control bulk density when producing butene film resins; (2)
reduce resin stickiness without reducing catalyst productivity;
and (3) prevent TEAl starvation. Petitioner argues that these
issues created uncertainties regarding UCC’s capability of using
UCAT-J to produce base resin and/or uncertainties regarding the
design for using UCAT-J to develop or improve its UNIPOL process
technology used at Star. Petitioner argues that the UCAT-J
project was intended to discover information that would eliminate
these uncertainties.
In the opinion of Dr. Brockmeier, the “rule of three”
followed at Star was reasonable and one or even two problem-free
experiments does not provide a manufacturer with sufficient
assurance that the technology can be used without R&D supervision
and involvement. Dr. Brockmeier also believes that the duration
of the UCAT-J runs was scientifically reasonable and that UCC was
- 232 -
continuing to discover information about UCAT-J’s operability
after the reactor was lined out and reached a steady state. In
Dr. Brockmeier’s opinion, the UCAT-J runs were not merely trial
production runs because UCC had not yet eliminated the
uncertainties associated with the new technology.
Respondent’s analysis of the UCAT-J project relies on the
report of one of his expert witnesses, Dr. Allen. Respondent
argues that the UCAT-J project fails the section 174 test
because: (1) UCC was certain that it could produce aim-grade base
resin using UCAT-J; and (2) the UCAT-J project was conducted for
the purpose of producing products for sale to customers, not for
the purpose of discovering information.
i. Uncertainty
Respondent argues that the UCAT-J project fails the section
174 test because UCC was certain that it could produce aim-grade
base resin using UCAT-J. Respondent argues that UCC gained this
certainty because it had successfully used UCAT-J on the UNIPOL
pilot plant as well as at Star and Seadrift. Respondent believes
his argument is supported by the fact that UCC had enough
confidence to begin designing LP-6, which was designed to use
UCAT-J, and to tout the benefits of UCAT-J to UNIPOL licensees
before it began the UCAT-J project.
Respondent argues that the Court should consider
petitioner’s arguments and testimonial evidence against the
- 233 -
documentary evidence made contemporaneously with the runs. In
support of his argument, respondent cites United States v. United
States Gypsum Co., 333 U.S. 364, 395-396 (1948), where the
Supreme Court stated:
Both on direct and cross-examination counsel were
permitted to phrase their questions in extremely
leading form, so that the import of the witnesses’
testimony was conflicting. * * * Where such testimony
is in conflict with contemporaneous documents we can
give it little weight, particularly when the crucial
issues involve mixed questions of law and fact. * * *
Respondent points to documents dated before the UCAT-J project
began indicating that UCC had produced aim-grade resin on its
smaller reactors without significant operability or continuity
problems and that UCAT-J performed better than M-1 on the pilot
plant. Respondent also argues that the pre-run documentation
does not identify the uncertainties that petitioner claims
existed before the runs.
We agree with respondent that some of the documentary
evidence indicates that UCC was confident that at some point it
would be able to produce base resin using UCAT-J on a commercial
scale and sell UCAT-J to licensees. Furthermore, we find that
UCC generally found UCAT-J to work as well as or better than M-1
in its pilot plants. However, this not end our inquiry. Even if
UCC was certain that it was capable of using UCAT-J commercially,
the section 174 test may also be satisfied “if the information
available to the taxpayer does not establish the * * *
- 234 -
appropriate design of the product.” Sec. 1.174-2(a)(1), Income
Tax Regs. The documentary evidence indicates that UCC was
confident that it would eventually be able to use UCAT-J with
satisfactory operability and continuity, but it does not indicate
that UCC knew how to design its process so that (1) using UCAT-J
would be an improvement over using M-1 in its full-size
commercial reactors and (2) UCC could fully use UCAT-J’s superior
qualities. Many of the documents in evidence list the objectives
and the risks involved in the runs, and petitioner confirmed
through testimony that each of the runs was conducted for the
purpose of discovering information that would help eliminate
uncertainties as to how UCC could improve its PE production
process using UCAT-J. Therefore, we find that the testimony does
not conflict with the documentary evidence.
Furthermore, we find that at the beginning of 1994 UCC did
not have enough information available to establish how it should
design its process so that using UCAT-J would be an improvement
over using M-1 on a full-scale commercial reactor. UCC may have
been satisfied with the design of its process using UCAT-J in the
pilot plant and the smaller reactor at Seadrift, but UCC could
not use the same design on Star’s reactor because Star’s larger
size caused problems that did not occur at the smaller plants
such as static and sheeting. UCC was still experiencing
significant operability and continuity problems at Star that
- 235 -
negated many of the benefits of using UCAT-J. The purpose of
testing a process on a pilot plant is to eliminate any
uncertainties that can be eliminated at the pilot plant level
before moving the experiment to a commercial-scale reactor, but
any uncertainties that arise only on larger reactors cannot be
eliminated without testing on a commercial-scale reactor. We
agree with petitioner that because of the differences between a
commercial-scale reactor and a pilot plant reactor there were
additional uncertainties relating to the design of the process
that could not be eliminated through testing on smaller reactors.
Petitioner’s argument that testing on smaller reactors would not
eliminate all uncertainties regarding the design of a commercial-
scale PE production process using UCAT-J is further supported by
the fact that UCC decided to install two different sets of
catalyst feeders on its LP-6 plant so that M-1 could be used at
the plant if UCC was unable to commercialize UCAT-J by the time
the plant was completed.
ii. Discovering Information
Respondent argues that even if there were uncertainties as
to the design of UCC’s process, the UCAT-J runs were not
conducted for the purpose of eliminating those uncertainties. In
the opinion of Dr. Allen, all of the runs of the UCAT-J project
were conducted for commercial reasons. Respondent points out
that: (1) UCC sold most of the resin it produced during the
- 236 -
UCAT-J runs; (2) an objective for most of the runs was to produce
resin for customer qualification; and (3) many of the runs lasted
longer than the time necessary to achieve a steady state in the
reactor.
We agree that some of UCC’s objectives were commercial as we
would expect, considering that UCC’s ultimate goal was to
commercialize the use of UCAT-J and the UCAT-J project included
both process and product business components. However, we find
that the record supports petitioner’s argument that the primary
goal of UCC’s activities that related to the process business
component was to discover information to eliminate uncertainties
as to the appropriate design of UCC’s PE production process when
UCAT-J was used as the catalyst. UCC’s production activities, by
contrast, are part of the product business component of the UCAT-
J project and are outside the scope of our inquiry.
Respondent also points out that UCC wanted its plant
operators to gain experience making products with UCAT-J in
anticipation of the completion of LP-6. While this may have been
an additional objective of the UCAT-J project, we do not believe
that it was the primary objective.
Respondent next argues that the even if the UCAT-J project
otherwise satisfies the section 174 test, it fails the test of
Mayrath v. Commissioner, 41 T.C. 582 (1964). Respondent argues
that most of the claimed costs associated with the UCAT-J project
- 237 -
related to production activities, not activities related to the
development of the concept of the project.
We agree that the activities that related primarily to the
production of PE base resin were not related to the development
of the concept of using UCAT-J and may not be treated as expenses
under section 174. See Mayrath v. Commissioner, supra at 590.
However, we conclude that these production activities are part of
the product business component, not the process business
component at issue. To the extent that petitioner has included
production activities as part of the business component, we may
apply the shrinking-back rule and apply the qualified research
tests to the most significant subset of elements of the process
that satisfies the qualified research tests, which we find to be
the subset of activities that relate primarily to the development
of the production process using UCAT-J. See sec. 1.41-4(b)(2),
Income Tax Regs.
The activities that relate primarily to the development of
the production process using UCAT-J are part of the process
business component, and we find that they satisfy the Mayrath
test. These activities include: (1) Preparing run
documentation, including identifying objectives and risks of each
run; (2) monitoring reactor performance; (3) responding to
unexpected operating problems; (4) conducting experiments during
the runs; (5) collecting resin and catalyst samples; (6)
- 238 -
reporting run performance both during and following each run; (7)
analyzing the results of each run; (8) identifying ways to
improve subsequent runs; and (9) implementing improvements in
subsequent runs (collectively, UCAT-J research activities).
Respondent finally argues that the UCAT-J project fails the
section 174 test because the duration of many of the runs far
exceeded the duration necessary to discover information to
resolve uncertainties. We disagree, and we find that activities
that relate primarily to the development of the process, as
opposed to the production of base resin, may satisfy the section
174 test regardless of when they occurred as long as they were
performed for the purpose of discovering information to eliminate
the uncertainties discussed above. We find that the UCAT-J
research activities were performed for this purpose.
b. The Technological Information Test
Petitioner argues that the UCAT-J project satisfies the
technological information test because it was designed to
discover information based upon numerous principles of chemistry
and engineering including: (1) Catalytic chemistry; (2)
polymerization; (3) heat and mass transfer; (4) reaction
kinetics; (5) statistics; (6) fluid dynamics and solubility; (7)
chemical engineering; and (8) process engineering. We agree that
the UCAT-J research activities satisfy this test.
- 239 -
c. The Business Component Test
Petitioner argues that the UCAT-J project satisfies the
business component test because the project was intended to
discover information that would be useful for improving UCC’s PE
production process. We agree that the UCAT-J research activities
satisfy this test.
d. The Process of Experimentation Test
Petitioner claims that substantially all of the activities
involved in the UCAT-J project constitute elements of a process
of experimentation for a qualified purpose. In Dr. Brockmeier’s
opinion, the UCAT-J project involved a constant process of
evaluation and experimentation including: (1) Preparing run
documentation that identified the objectives and risks of each
run; (2) monitoring reactor performance; (3) responding to
unexpected operating problems; (4) conducting experiments during
the runs; (5) collecting resin and catalyst samples; (6)
reporting run performance both during and following each run; (7)
analyzing the results of the runs; and (8) developing ways to
improve the process during subsequent runs.
Dr. Brockmeier believes that the run team’s activities--
meeting regularly to discuss objectives, identifying obstacles,
proposing alternative remedies, and evaluating reaction system
responses to the experimental remedies–-indicate that the project
was conducted using a process of experimentation in the
- 240 -
scientific sense. Dr. Brockmeier also noted various experiments
that UCC conducted during the UCAT-J project, including: (1)
Adjusting operating ratios and chemicals; (2) adjusting ethylene
partial pressure; (3) modifying catalyst properties; (4)
introducing new reactor control technologies; and (5) giving the
reactor TEAl shots. Dr. Brockmeier concluded in his report:
“Viewed in its entirety, the UCAT-J Project is a textbook example
of the R&D-driven process of experimentation that is required in
order to implement a catalyst change in a large-scale PE
production process.”
Petitioner also claims that the UCAT-J project was performed
for a qualified purpose–-to improve the function and performance
of the PE production process and to improve the quality of the
consumer product. UCAT-J, if successfully commercialized,
offered many process-related advantages over M-1 because it was
more active than M-1 and therefore could produce more base resin.
Furthermore, if UCAT-J worked properly, it would improve PE
product properties.
Respondent argues that the UCAT-J project fails the process
of experimentation test because respondent believes that UCC had
already eliminated all uncertainties related to the use of UCAT-J
before the credit years and accordingly no experimentation was
necessary. As discussed above with respect to the section 174
test, we find that UCC had not eliminated all uncertainties
- 241 -
relating to the design of its PE production process using UCAT-J
on a commercial scale before completing the project.
Respondent also argues that petitioner failed to produce any
formal project reports that analyzed the results of the UCAT-J
project. While such formal project reports would indicate a
process of experimentation, we are satisfied that UCC
sufficiently analyzed the results through discussion and informal
documentation. Petitioner presented credible testimony that
process R&D collected data during the UCAT-J runs, process R&D
representatives and members of the run team analyzed and
discussed the results, and UCC used these analyses to further
refine the PE production process using UCAT-J. The fact that UCC
was able to compare its production process using UCAT-J with its
production process using M-1 in terms of reactor operability and
continuity issues indicates that UCC could use the same process
to compare UCAT-J with other catalysts.
We find that the UCAT-J research activities constitute a
process of experimentation. Unlike the sodium borohydride
project, the UCAT-J project was not a simple change to a process
followed by verification that the change would work. UCC
conducted a series of trials using UCAT-J and analyzed the
results of each trial to develop and improve its process. UCC
was testing hypotheses and forming new hypotheses based on each
succeeding run in order to solve some of the chemical and
- 242 -
physical problems it had experienced using UCAT-J. Throughout
the UCAT-J project UCC was comparing UCAT-J’s performance to M-
1’s performance on a variety of criteria related to reactor
operability, reactor continuity, and product properties.
While many of the activities that were conducted during the
UCAT-J project as a whole did not constitute a process of
experimentation but were ordinary production activities, as
discussed above we find it appropriate to separate the production
activities and the research activities into separate business
components for the nonexperimental product and the experimental
process, respectively. Therefore, the occurrence of
nonexperimental production activities does not cause the UCAT-J
research activities to fail the “substantially all” portion of
the process of experimentation test. Furthermore, we find that
the improvement of UCC’s PE production process is a qualified
purpose under section 41(d)(3). Accordingly, we find that the
UCAT-J research activities satisfy the process of experimentation
test.
e. Research After Commercial Production
Respondent next argues that the UCAT-J project is excluded
from the definition of qualified research because it constituted
research after commercial production, specifically trial
production runs, troubleshooting, or debugging. Respondent
- 243 -
argues that the UCAT-J runs occurred after the preproduction
planning and trial production runs had occurred.
We disagree that the UCAT-J research activities constituted
research after commercial production. While the aim-grade base
resin that UCC produced satisfied UCC’s basic functional and
economic requirements, the business component at issue is the
process business component, not the product business component.
UCC’s production process using UCAT-J did not satisfy its basic
functional and economic requirements during the credit years.
UCC was not yet licensing the use of UCAT-J and was not using
UCAT-J as its primary catalyst for production. UCC was still
experimenting to eliminate significant problems that counteracted
the benefits of using UCAT-J instead of M-1. Accordingly, we
find that the UCAT-J research activities are not excluded from
the definition of qualified research under section 41(d)(4)(A).
f. Substantiation Requirement
Respondent finally argues that petitioner has not produced
sufficient documentary evidence to corroborate the testimony of
its fact witnesses in support of its argument that the UCAT-J
project was qualified research. See sec. 6001; sec. 1.6001-1,
Income Tax Regs.; see also Boyd v. Commissioner, 122 T.C. at 320;
Tyson Foods, Inc. & Subs. v. Commissioner, T.C. Memo. 2007-188;
Eustace v. Commissioner, T.C. Memo. 2001-66.
- 244 -
Petitioner argues that there is sufficient evidence to show
that the UCAT-J project occurred and satisfies the qualified
research tests. Petitioner produced three fact witnesses to
discuss the UCAT-J project and argues that their testimony is
corroborated by sufficient documentary evidence that provides the
objectives, risks, and results of the runs.
Considering the record in its entirety, we find that
petitioner substantiated its claim that the UCAT-J research
activities satisfy the qualified research tests. Accordingly,
these research activities, but not ordinary production
activities, constitute qualified research.
III. Base Period Activities
We next address whether petitioner included all activities
similar to the activities that we find constitute qualified
research in making its revised base period computations. A
taxpayer must determine its QREs to be taken into account in
computing its fixed-base percentage “on a basis consistent with”
its determination of QREs for the credit year. Sec. 41(c)(4).47
Accordingly, the taxpayer must include the same types of
activities as qualified research and include the same types of
costs as QREs for the credit years and the base period. The
legislative history explains:
if a taxpayer includes (or excludes) certain
expenditures in determining its qualified research
47
See supra note 41.
- 245 -
expenses for the current year, it must provide the same
treatment for all such expenditures incurred during any
year taken into account in computing the taxpayer’s
fixed-base percentage * * *. [H. Rept. 101-247, at
1202-1203 (1989).]
A. Whether Petitioner Must Include Activities Conducted By
the Entire Consolidated Group
In its order dated January 17, 2007, the Court ordered that
for purposes of conforming the base period computations to the
methodology petitioner employed to compute the claimed credits,
only evidence of the revised base period computations for the
legal entity for which additional credits are claimed would be
necessary. Because petitioner claimed additional credits only
for activities conducted by UCC, the base period trial was
limited to UCC’s base period computations.
In response to petitioner’s motion for partial summary
judgement dated September 15, 2006, respondent argued48 that
petitioner was required to calculate its QREs for the base period
for the entire controlled group on a consistent basis with its
QRE calculation for the claim projects. This would require
petitioner to include in its revised research credit computations
the QREs incurred not only by UCC, but also the other members of
petitioner’s controlled group. Respondent pointed to section
41(f)(1), which provides:
48
Respondent did not repeat these arguments on brief and
acknowledges that the Court has already decided this issue.
However, respondent reserves his arguments with respect to this
issue. Accordingly, we address his arguments here.
- 246 -
(1) Aggregation of expenditures.--
(A) Controlled group of corporations.--In determining
the amount of the credit under this section–-
(i) all members of the same controlled group of
corporations shall be treated as a single taxpayer, and
(ii) the credit (if any) allowable by this section
to each such member shall be its proportionate shares
of the qualified research expenses and basic research
payments giving rise to the credit.
However, we decided that the consistency rule applies to the
determination of QREs for each member of the controlled group
while the aggregation rule of section 41(f)(1) refers to the
determination of the overall credit. The rule for aggregation of
expenditures exists “To ensure that the new credit will be
allowed only for actual increases in research wage expenditures”.
S. Rept. 97-144, supra at 83, 1981-2 C.B. at 442. Congress
intended for these rules to prevent artificial increases in
research expenditures by shifting expenditures among commonly
controlled or otherwise related persons. Id. The rules for
aggregation were already in place when the consistency rule was
enacted as part of the Omnibus Budget Reconciliation Act of 1989,
Pub. L. 101-239, sec. 7110(b)(1), 103 Stat. 2323, yet the
legislative history does not provide any guidance as to whether
the consistency rule applies at the entity level or the
consolidated group level. See H. Rept. 101-247, supra at 1202-
1203; H. Conf. Rept. 101-386, at 542 (1989). Section 41(c)(4)(B)
refers to the “taxpayer”, not the controlled group, and there is
- 247 -
no indication in the statute or the legislative history that all
members of a consolidated group must calculate their QREs in the
same way.
Section 41(c)(4) undercuts the logic of the argument that
the consistency rule is to be applied to the controlled group as
a whole. Section 41(c)(4)(B) gives the Secretary authority to
issue regulations to prevent “distortions” caused by a “change in
accounting methods used by such taxpayer”. Taxpayers that are
part of a commonly controlled group may have different methods of
accounting. Because the statute refers only to a single
accounting method, it makes no sense to conclude that the
consistency rule applies to the controlled group as a whole.
Respondent’s attempt to read the consistency rule in the light of
section 41(f) creates an anomaly.
Respondent argued that petitioner’s interpretation of the
consistency rule contradicts “unambiguous congressional intent.”
Respondent asked us to consider the following example:
A and B are members of a controlled group of
corporations. During the base years, A but not B
incurred a certain type of QRE. In the credit year,
the AB controlled group shifts this type of QRE to B in
order to avoid including this item of A’s base period
QRE in the group credit computation under the
consistency requirement.
Respondent argued that petitioner’s interpretation of the
consistency rule would permit the result in the example. In
support of his position, respondent cited the legislative purpose
- 248 -
for the aggregation rules: “to prevent artificial increases in
research wage expenditures by shifting expenditures among
commonly controlled or otherwise related persons.” See S. Rept.
97-144, supra at 83, 1981-2 C.B. at 442. However, the
regulations already address respondent’s concern. Section 41(f)
and the legislative history direct the Secretary to issue
regulations to ensure that artificial shifting of research
expenditures will not occur. Section 1.41-6(i), Income Tax
Regs., addresses the concern of shifting artificial expenditures
among members of a controlled group by providing that because all
members of a group under common control are treated as a single
taxpayer for purposes of determining the research credit,
transfers between members of the group are generally
disregarded.49
There is no support in the statute or the legislative
history for the application of the consistency rule at the
controlled group level. Accordingly, because petitioner is now
seeking additional research credits for activities conducted only
by UCC, petitioner properly included base period QREs for only
UCC in its fixed-base percentage.
B. Acquisitions and Dispositions
Section 41(f)(3) provides for adjustments to QREs in the
event of an acquisition or disposition by the taxpayer. If the
49
During the credit years this regulation was found under
sec. 1.41-8(e), Income Tax Regs.
- 249 -
taxpayer acquires a major portion of a trade or business, then
the taxpayer must increase the amount of the QREs it incurred
before the acquisition by the amount of QREs incurred by the
acquired trade or business during that time. Sec. 41(f)(3)(A).
Likewise, in the case of a disposition of a major portion of its
trade or business, the taxpayer must decrease the amount of the
QREs it incurred before the disposition by the amount of QREs
attributable to the trade or business sold. Sec. 41(f)(3)(B).
Section 41(d)(4)(F) excludes from the definition of
“qualified research” any research conducted outside the United
States, the Commonwealth of Puerto Rico, or any possession the
United States. Accordingly, we need not consider any
acquisitions or dispositions of businesses that conducted
research solely outside the United States during the base period.
UCC’s C&P business segment was UCC’s only domestic business
segment operating during the base period that remained a part of
the UCC legal entity during the credit years. Accordingly, we
need not consider any of the other business segments that were
part of UCC during the base period.50 We find, and respondent
does not dispute, that petitioner has properly accounted for the
acquisitions and dispositions that occurred during the relevant
periods.
50
UCC disposed of its consumer products, carbon products,
and industrial gases segments before January 1, 1994.
- 250 -
C. Polypropylene Runs
Dr. Wadia contends that the 138 identified polypropylene
runs that occurred at Seadrift’s P-1 unit satisfy the qualified
research criteria. Ms. Toivonen costed the polypropylene runs at
$29.5 million. However, petitioner did not include these runs in
its base period calculations because petitioner claims that UCC
conducted these runs as an independent contractor for SPC and SPC
ultimately bore the cost of these runs.
Respondent argues that petitioner should have included the
polypropylene runs in its base period calculations because UCC
initially bore the costs of the runs, petitioner failed to
substantiate that UCC was compensated by SPC, SPC did not
maintain separate books and records apart from UCC’s books and
records, and UCC was required to bear its own costs of conducting
R&D under the CUA.
Under the operating agreement between UCC and SPC, SPC
agreed to reimburse UCC for any operating expenses it incurred.
Petitioner presented testimony at trial that SPC did in fact
reimburse UCC for these expenses, and we find the testimony to be
credible. Furthermore, while UCC provided accounting services
for SPC, petitioner provided credible evidence that UCC kept its
records separate from those of SPC.
While we agree that the CUA provides that UCC would bear the
costs of R&D it conducted as part of the Cooperative Undertaking,
- 251 -
the polypropylene runs were conducted by SPC, not the Cooperative
Undertaking. The polypropylene runs all involved plant-based
experimentation, and the Cooperative Undertaking was not involved
in any experimentation that occurred during the production
process. While the agreements between UCC and Shell relating to
SPC provided that any intellectual property discovered or
developed by UCC in the course of performing its duties under
those agreements would be governed by the CUA, not the SPC
agreements, we find that the costs of the polypropylene runs were
costs treated as the costs of polypropylene production, not the
development of intellectual property, and they would not have
been governed by the CUA. Accordingly, the CUA provisions are
irrelevant.51 We see no other reason why SPC should not be
respected as a tax partnership, and we accordingly find that
petitioner was correct to exclude the polypropylene runs from its
base period computations.
D. Whether Petitioner Included All Activities Similar to
the Claim Projects on Its List of Identified Runs
Respondent argues that the methodology that petitioner used
to identify plant-based research for the claim projects is
completely different and fundamentally inconsistent with its
methodology for identifying plant-based research that occurred
51
Respondent does not argue that petitioner failed to
include additional QREs not identified by Ms. Toivonen that UCC
incurred as part of the Cooperative Undertaking. It appears that
UCC treated these costs as QREs on its original return.
- 252 -
during the base period. We address each of respondent’s
arguments in turn.
1. Petitioner’s Sources of Information
a. Whether Petitioner Was Required To Use FOCRs
To Identify Base Period Activities
Respondent points out that the claim projects were largely
documented by FOCRs, but UCC destroyed its FOCRs from the base
period before performing its revised base period calculations.
Accordingly, petitioner was unable to review all of the FOCRs
produced during the base period to see whether they identified
additional qualified research activities. Respondent argues that
because Dr. Wadia could not review the FOCRs from the base
period, petitioner cannot prove that it identified all of the
base period activities that were similar to the claim projects.
As an example, respondent argues that Dr. Wadia “missed” the
Nalco inhibitor antifouling test (run 816), which petitioner
later conceded and costed at $7 million. Respondent argues that
this process change would have been documented by an FOCR, so Dr.
Wadia might not have missed this project had the FOCRs from the
base period been available. Respondent argues that FOCRs were
the key document indicating manufacturing process changes during
both the base period and the credit years. Accordingly,
respondent argues that petitioner needed to analyze and produce
its FOCRs from the base period in order to meet the consistency
- 253 -
requirement and capture all base period activities similar to the
claim projects.
Neither section 41(c)(4) nor section 1.41-4(d), Income Tax
Regs., imposes any requirement that a taxpayer use the same types
of documents to identify qualified research in the base period as
it used to identify qualified research in the claim year if the
taxpayer can otherwise show that it has satisfied the consistency
requirement. While it is true that Dr. Wadia did not include the
Nalco inhibitor antifouling test in his original list of
identified runs, we do not view this as evidence that Dr. Wadia
“missed” any projects because he did not review FOCRs from the
base period. We find that the Nalco inhibitor antifouling test
fails the process of experimentation test. UCC was not
experimenting with the Nalco inhibitor or conducting research to
better understand inhibitors; it was merely testing Nalco’s
product to see whether it worked as promised. While UCC
monitored the reboiler after injecting the Nalco inhibitor, as it
did with the UOP GA-155 project, there is no evidence that UCC
analyzed the results of the test or intended to refine its
hypothesis and conduct additional tests. Such verification,
without more, does not constitute a process of experimentation.
Accordingly, Dr. Wadia’s exclusion of the Nalco inhibitor
antifouling test from his list of identified runs does not cause
us to doubt his reliability.
- 254 -
Furthermore, while petitioner did rely heavily on FOCRs to
establish that the claim projects constitute qualified research,
we do not find that FOCRs are as important to identifying
qualified research as respondent advocates. FOCRs were used for
any process change, regardless of whether the change involved
experimentation. Accordingly, even if all of the FOCRs from the
base period were available to Dr. Wadia, we do not believe that
this would significantly change Dr. Wadia’s conclusions.
Respondent also argues that petitioner chose an ad hoc
methodology to identify base period activities and relied on
documents that were highly variable in completeness and
usefulness. Respondent argues that the absence of any summary
documents, such as lists of new products introduced during the
base period or R&D budgets, makes it impossible to confirm that
Dr. Wadia captured all of the qualified research activities that
occurred during the base period. Furthermore, because the
documents did not always provide conclusive evidence of the
duration or production quantities of the identified runs, Dr.
Wadia relied upon estimates and assumptions for a large number of
runs. Respondent argues that estimates are legally
impermissible.
Section 1.41-4(d), Income Tax Regs., does not require that a
taxpayer substantiate its research credit claim with any
particular types of documents but requires that the taxpayer
- 255 -
“retain records in sufficiently usable form and detail to
substantiate that the expenditures claimed are eligible for the
credit.” We find that the documents that petitioner produced
were sufficient to substantiate its claim that the MATRIC team
identified all of the scientific research projects that occurred
during the base period and were sufficiently detailed to allow
the MATRIC team to make reasonable determinations as to the
duration and production quantities of the identified runs.
b. Whether Petitioner Was Required To Consider
Alternative Sources
Respondent argues that petitioner should have examined
alternative sources to correct defects in its methodology. As an
example, because two of the claim projects (the UOP GA-155 and
sodium borohydride projects) involved the injection of additives
into the olefins production process, respondent argues that
petitioner should have sought documents from third parties from
whom UCC purchased additives during the base period to see
whether they would show whether UCC experimented with different
additives during the base period. Respondent argues that the
documents produced by the John Zink Co. show that UCC conducted
additional plant testing during the base period that was not
addressed by Dr. Wadia’s report.
Petitioner argues that respondent was unable to obtain any
significant documents from third-parties from whom UCC purchased
additives during the base period, so any attempt that petitioner
- 256 -
would have made to obtain the same documents would have been
fruitless. Furthermore, petitioner argues that the third-party
documents that are available, those produced by the John Zink
Co., did not identify any experimental activities.
We agree that section 41 does not require petitioner to seek
documents from third-party sources to determine whether they
contain evidence of experimentation. Furthermore, we find that
the documents from third-party sources that were available, those
from the John Zink Co., do not indicate that additional research
occurred during the base period that petitioner failed to
consider. Those documents show that UCC tested the products it
purchased, but not that it experimented with them. Considering
that we do not find the UOP GA-155 project or the sodium
borohydride project to be qualified research, we find it unlikely
that documents from UCC’s additive vendors or other third parties
would be useful in identifying additional qualified research
activities conducted during the base period.
2. Whether Petitioner Should Include Additional
Activities in Its Base Period Calculation
Respondent argues that petitioner failed to capture all of
the qualified research activities that occurred during the base
period, specifically: (1) The NOx project, (2) testing on
products that UCC purchased from the John Zink Co., (3) testing
of the Star pelleting line, and (4) UCC’s analysis of naphtha on
its list of identified runs. According to respondent,
- 257 -
petitioner’s failure to include these projects or tests in its
base period calculations is evidence that petitioner’s
identification of qualified research activities was incomplete.
Respondent also argues that Dr. Wadia improperly omitted portions
of the identified runs.
a. NOx
The NOx project does contain some elements of qualified
research to the extent that UCC was attempting to discover
information that would allow it to determine whether it was
thawing its cold boxes frequently enough to reduce the safety
hazard caused by NOx accumulation. However, we find that the NOx
project does not satisfy the process of experimentation test
because UCC was not conducting an experiment in the scientific
sense but was merely performing maintenance on its cold boxes,
collecting data, and using the collected data to set operating
guidelines.
b. John Zink Co. Products
We also find that UCC did not conduct any qualified research
activities related to purchases from the John Zink Co. As with
the spuds project, any testing that UCC performed on products
purchased from the John Zink Co. was merely quality control
testing to ensure that the products worked as promised.
- 258 -
c. Star Pelleting Line
Similarly, while UCC most likely tested the pelleting line
it installed at Star in 1986, there is no indication that UCC
performed any experimentation associated with the new pelleting
line, much less qualified research. Any tests that UCC performed
were most likely quality control tests to ensure that the
pelleting line did in fact work.
d. Naphtha Analysis
We find that UCC’s analysis of naphtha in 1987 was routine
data collection or routine or ordinary inspection. There is no
indication that UCC performed any experiments when it was
determining the composition of the naphtha it purchased.
e. Dr. Wadia’s Limitation of Duration
Respondent also argues that even if Dr. Wadia included all
of the projects that constitute qualified research on his list of
identified runs, Dr. Wadia’s interpretation of the definition of
“qualified research” was narrower than the definition petitioner
used during the claim years. Respondent argues that petitioner
treated the entire duration of all of the claim projects as
qualified research regardless of whether only part of a run was
experimental, while Dr. Wadia limited the run durations to the
experimental portions of the identified runs.
For some of the identified runs, Dr. Wadia defined qualified
research as including only the portion of a run that he believed
- 259 -
was experimental, not the entire run. Accordingly, Dr. Wadia
treated the duration of many identified runs as including only
the portion of the run where experimentation occurred. For
example, if a run was conducted for the purpose of determining
whether it would produce a product of acceptable quality, Dr.
Wadia would treat the duration of the run as lasting only until
the point at which that determination was made unless the
researchers continued to experiment after the unit reached a
steady state.
In the MEK production test (run 175), UCC collected data for
the first 914 hours of the run, but Dr. Wadia included only the
first 336 hours in the duration of run 175. Similarly, for the
first vinyl acetate catalyst protection test (runs 47), Dr. Wadia
treated the run as lasting only 12 hours even though the resin
was in place for 2,400 hours and one of the goals of the test was
to test the strength of the resin over a period of 2,400 hours.
Dr. Wadia used partial durations for many other runs as well.
Respondent argues that this approach is inconsistent with
petitioner’s treatment of the UCAT-J runs because petitioner did
not limit the duration of those runs to the time it took the
reactor to reach a steady state even if no experimentation
occurred after that point. Respondent argues that Dr. Wadia’s
approach is also inconsistent with the UOP GA-155 project, where
UCC collected data for only 90 days but treated the project as
- 260 -
lasting 6 months. Respondent also argues that the duration of
the Amoco anticoking project would have been much shorter if
petitioner limited the duration to the time it should have taken
UCC to realize that the Amoco technology was not working.
Respondent argues that petitioner did not attempt to divide any
of the other claim projects into their “experimental” and “non-
experimental” parts.
Even assuming respondent is correct, we find that our
limitation of the claim projects to only the activities that
relate to the experimental process business component is at least
as narrow as Dr. Wadia’s approach. As discussed with respect to
the claim projects, under section 41(d)(2)(C), where research is
conducted to improve a taxpayer’s production process, activities
that relate to the product being produced are part of a separate
nonexperimental product business component. Production
activities that do not involve experimentation are properly
excluded from the definition of qualified research. Therefore,
petitioner’s reliance on Dr. Wadia’s definition of which
activities constitute qualified research does not run afoul of
section 41(c)(4). Accordingly, we find that there are no
additional activities that are similar to the claim year projects
that satisfy section 41(d).
- 261 -
3. Reliability of Dr. Wadia’s Methodology
Respondent argues that even if the Court does not find that
petitioner omitted any particular projects from its list of
identified runs, the Court cannot rely on Dr. Wadia’s testimony
to prove that it identified all of the qualified research
activities that occurred during the base period because Dr.
Wadia’s methodology is flawed. Respondent argues that Dr.
Wadia’s methodology is unreliable because: (1) It does not meet
the standards set out in Daubert v. Merrell Dow Pharms., Inc.,
509 U.S. 579, 593-594 (1993), and Kumho Tire Co. v. Carmichael,
526 U.S. 137, 149-150 (1999); (2) Dr. Wadia’s interpretation of
the qualified research criteria for the base period differs from
the definition that petitioner used to identify the claim
projects; and (3) Dr. Wadia is biased by MATRIC’s relationship
with Dow.
a. Reliability of Dr. Wadia’s Methodology as
Expert Testimony
Respondent argues that the Court should not rely on Dr.
Wadia’s opinion because it is unreliable under the standards set
out in Daubert v. Merrell Dow Pharms., Inc., supra at 593-594,
and Kumho Tire Co. v. Carmichael, supra at 149-150. Respondent
argues that to evaluate the reliability of Dr. Wadia’s
methodology, the Court should consider the following factors:
(1) Whether the methodology has been or can be tested; (2)
whether the methodology has been published or subjected to peer
- 262 -
review; (3) whether the methodology is subject to potential or
known errors; and (4) whether the methodology is generally known
and accepted within the relevant community. Daubert v. Merrell
Dow Pharms., Inc., supra at 593-594.
Petitioner argues that respondent is merely reasserting the
challenges he previously made to the admissibility of Dr. Wadia’s
testimony and recasting them as challenges to the reliability of
his testimony. While we decided before trial that Dr. Wadia’s
testimony was admissible under rule 104(a) of the Federal Rules
of Evidence, to the extent that the Daubert factors also pertain
to the weight that we should give to Dr. Wadia’s testimony we
consider them here.
However, the Daubert factors are not necessarily pertinent
in all cases, and their relevance depends upon the nature of ths
issue, the expert’s particular expertise, and the subject of his
testimony. Kumho Tire Co. v. Carmichael, supra at 150. Dr.
Wadia’s testimony is helpful because of his specialized knowledge
of UCC’s production processes and of how research and
experimentation is conducted from a scientific point of view.
Because of his years of experience working for UCC, Dr. Wadia is
familiar with the way UCC conducted plant-based experimentation
during the base period. While UCC’s production processes rely on
many principles of the physical sciences and the Court is
assisted by Dr. Wadia’s view of research and experimentation from
- 263 -
a scientist’s perspective, Dr. Wadia’s task in identifying
activities that satisfy the qualified research criteria is not
itself founded on principles of science. See Tuf Racing Prods.,
Inc. v. Am. Suzuki Motor Corp., 223 F.3d 585, 591 (7th Cir. 2000)
(stating that “The principle of Daubert is merely that if an
expert witness is to offer an opinion based on science, it must
be real science, not junk science”, and finding that Daubert is
not applicable when the expert does not “purport to be doing
science”). Accordingly, an analysis of the Daubert factors is of
limited value.
i. Whether the Methodology Can Be Tested
Respondent argues that Dr. Wadia’s methodology cannot be
tested because Dr. Wadia’s opinions are merely general,
conclusory statements. Respondent argues that Dr. Wadia’s
descriptions of the runs are sparse and do not refer to any
specific facts to support his conclusions. Furthermore,
respondent argues that Dr. Wadia does not set forth any reasons
for his conclusion that the projects that he did not list as
identified runs did not satisfy the qualified research criteria.
Respondent contrasts Dr. Wadia’s practices with those of Ms.
Toivonen, who maintained workpapers that documented her decisions
for the purpose of permitting her results to be checked and
verified.
- 264 -
We disagree that Dr. Wadia’s methodology cannot be tested.
While it would be difficult for another person to duplicate Dr.
Wadia’s efforts exactly, Dr. Wadia’s method of reviewing
documents, interviewing people familiar with events that occurred
during the base period, and discussing each project with the
MATRIC team is a relatively simple methodology that could be
repeated by others. Furthermore, because each project that Dr.
Wadia included as an identified run is essentially a concession
by petitioner, we do not find that Dr. Wadia’s failure to explain
in greater detail why those projects satisfy the qualified
research criteria detracts from his reliability. While it would
have been more helpful to the Court if Dr. Wadia had explained
why he rejected the projects that he did not list as identified
runs, given petitioner’s concession of runs 807 through 820
(discussed below), we have sufficient information to conclude
that runs 1 through 820 include all of the additional qualified
research activities that occurred during the base period.
ii. Whether the Methodology Is Known or
Accepted in the Community, Has Been
Published, or Has Been Subjected to Peer
Review
Respondent also argues that Dr. Wadia’s methodology was not
known or accepted in the community, was not published, and was
not subject to peer review. Respondent argues that there are no
accepted standards or controls for applying Dr. Wadia’s
methodology.
- 265 -
Petitioner responds that this factor is simply not
applicable to Dr. Wadia’s task, and we agree. We find it highly
unlikely that there are any published methodologies in the
scientific world on how to identify research or experimentation
performed by a company for a given set of years, but clearly
Congress did not intend for the research credit to be
unattainable because of the absence of a peer-reviewed
methodology.
iii. Whether the Methodology Is Subject to
Known Rate of Error
Respondent further argues that there is no known rate of
error in applying Dr. Wadia’s methodology. However, respondent
believes that Dr. Wadia’s methodology was subject to errors as
evidenced by (1) Dr. Wadia’s supplemental report, which added 29
identified runs that Dr. Wadia did not include in his original
report, and (2) petitioner’s concession of runs 807 through 820.
Respondent points out that petitioner’s concession doubled the
number of runs associated with the Triton Assets from 2 to 4. As
evidence of Dr. Wadia’s lack of thoroughness, respondent argues
that Dr. Wadia should not have missed the wastewater activity
test (run 809), which is described as a “plant test” in its
supporting documentation. Respondent also argues that Dr. Wadia
erroneously treated the forced draft burner tests (runs 95 and
96) as occurring in 1985 instead of 1984 in his original expert
report; erroneously treated natural draft burner tests on
- 266 -
furnaces 10 and 12 as occurring in 1985 instead of 1984 or
earlier; and incorrectly determined the duration of the forced
draft burner tests, the natural draft burner tests on furnaces 10
and 12, and the natural draft burner tests (runs 1 through 11) on
furnace 9.
Petitioner argues that Dr. Wadia’s methodology is not the
type of methodology that can be assigned a known rate of error
because it is not the type of research that is generally the
subject of statistical studies. We agree that whether a project
or test satisfies the qualified research criteria from a
scientific point of view is not a question that can be
scientifically verified to a certainty. While Dr. Wadia’s
experience as a scientist was central to his task, reasonable
scientists could disagree as to whether some projects satisfy the
qualified research criteria; and it is the duty of the Court to
determine whether any particular project does in fact satisfy
section 41(d). We find that it is unlikely that any method of
identifying qualified research has been assigned a rate of error,
but Congress clearly intended for some taxpayers to be eligible
for the research credit. Accordingly, the absence of a known
rate of error does not affect the weight we will give to Dr.
Wadia’s testimony.
Furthermore, we do not find that Dr. Wadia’s “failure” to
include the wastewater activity test on his list of identified
- 267 -
runs indicates that Dr. Wadia was not thorough because we find
that the wastewater activity was not qualified research. While
referred to as a “plant test” in the supporting documentation,
this project did not involve any experimentation but was merely
odor testing. Even if UCC did form a hypothesis before
conducting this activity, there is no evidence that UCC performed
any analysis of the results.
Regarding Dr. Wadia’s mistake of concluding that the forced
draft burner tests occurred in 1985 instead of 1984, we find that
this mistake was immaterial and it was sufficient that Dr. Wadia
corrected the mistake in his supplemental expert report.
Furthermore, respondent’s arguments regarding natural draft
burner tests on furnaces 10 and 12 are contrary to our findings
of fact–-we find that the tests on those furnaces occurred before
the base period and Dr. Wadia correctly excluded them from his
list of identified runs. We also find that Dr. Wadia’s
determination of the duration of the forced draft burner tests
and the tests on furnace 9 during the natural draft burner tests
do not understate the duration of those runs.
While we do not accept Dr. Wadia’s testimony as an opinion
as to which activities satisfy section 41(d), we find that he
interpreted the qualified research criteria using his knowledge
of scientific research and experimentation, and we find his
identification of runs that satisfy the qualified research
- 268 -
criteria from a scientific point of view to be helpful to the
Court. We find that any errors in Dr. Wadia’s methodology have
been cured by petitioner’s concession of runs 807 through 820,
which we believe constitute the activities that may not
constitute qualified research but that bear enough marks of
qualified research that they must be considered to ensure that
petitioner has not omitted any qualified research activities from
its base period calculations. Considering that (1) petitioner
conceded the Nalco inhibitor test and the wastewater activity,
which we find do not constitute qualified research, and (2)
respondent has not identified any projects that petitioner failed
to include that do constitute qualified research, we find it
unlikely that there are other projects that do satisfy the
qualified research criteria that petitioner has failed to
identify and concede.
b. Petitioner’s Definition of “Qualified
Research”
Respondent argues that even if he has not identified other
activities that should have been included in petitioner’s base
period calculation, the burden is on petitioner to prove that it
has included in its base period calculations all of the
activities that are similar to the claim projects, and that
petitioner has not satisfied that burden. Respondent argues that
petitioner cannot use Dr. Wadia’s expert testimony to prove that
it identified all of the activities that occurred during the base
- 269 -
period that are similar to the claim projects because Dr. Wadia
did not use the claim projects as models when applying the
qualified research criteria or give any consideration to whether
he identified all activities that were similar to the claim
projects when carrying out his task. Furthermore, respondent
argues that Dr. Wadia’s interpretation of the qualified research
criteria was narrower than petitioner’s credit year position.
As evidence, respondent again points to the Nalco inhibitor
antifouling test, which involved an activity that was very
similar to petitioner’s largest claim project, the UOP GA-155
project. Had Dr. Wadia been charged with identifying all
projects that were similar to the claim projects, respondent
argues that Dr. Wadia would have included the Nalco inhibitor
antifouling test on his original list of identified runs.
Respondent also argues that Dr. Wadia did not rely on the
“rule of three” when determining whether activities satisfied the
qualified research criteria even though petitioner relied upon
the rule of three for including some of the UCAT-J runs as
qualified research. Accordingly, respondent argues that Dr.
Wadia may have excluded some activities from his list of
identified runs even though the technology tested in those runs
had been proven in only one or two successful runs.
Petitioner argues that it satisfied the consistency
requirement because the qualified research criteria that Dr.
- 270 -
Wadia relied upon mirror the requirements of section 41 and the
regulations promulgated thereunder, and these were the same
criteria that petitioner used for its credit year claims.
Petitioner argues that using the same selection criteria for both
the credit years and the base period indicates that it complied
with the consistency requirement.
We agree that the Nalco inhibitor antifouling test closely
resembles the UOP GA-155 project and that the fact that Dr. Wadia
did not include the Nalco inhibitor antifouling test on his list
of identified runs suggests that he interpreted the qualified
research criteria more narrowly than petitioner interpreted the
criteria when selecting the claim projects. However, as
discussed above, we find that neither the UOP GA-155 project nor
the Nalco inhibitor antifouling test was qualified research. We
find that Dr. Wadia’s failure to include projects similar to
those claim projects that fail the qualified research tests is
not sufficient basis for denying petitioner an additional
research credit. As petitioner correctly argues, the consistency
requirement does not alter the definition of qualified research
under section 41(d). Accordingly, petitioner’s failure to adhere
to section 41(d) when selecting some of the claim projects does
not necessarily indicate that Dr. Wadia failed to identify all of
the qualified research activities that occurred during the base
period.
- 271 -
Furthermore, we find that the fact that Dr. Wadia did not
rely on the rule of three does not detract from his reliability.
The evidence indicates that the rule of three applied only to the
PE production process during the credit years, not to the entire
C&P division. Furthermore, we find that Dr. Wadia is qualified
to determine whether UCC considered its technology to be
experimental or commercial during the base period.
Respondent also argues that because Dr. Wadia kept no
records of the projects that he rejected, there is no way to
verify his conclusions or consider whether he was correct to
reject those projects. Accordingly, respondent argues that Dr.
Wadia’s statement that he identified virtually all of the
qualified research activities that occurred during the base
period is a conclusory opinion that cannot be verified.
We agree that this is a flaw in Dr. Wadia’s methodology.
However, we find that petitioner’s concession of runs 807 through
820 cures Dr. Wadia’s failure to identify the group of base
period projects that failed the qualified research criteria in
Dr. Wadia’s opinion but might have satisfied the Court’s
interpretation of section 41(d) because runs 807 through 820
constitute that group of projects. While we find it unnecessary
to analyze all of the conceded runs in the light of petitioner’s
concession that they do satisfy section 41(d), the fact that the
two runs that respondent specifically criticizes Dr. Wadia for
- 272 -
missing do not satisfy the requirements of section 41(d) suggests
that petitioner’s concession of these runs sufficiently broadens
petitioner’s definition of “qualified research” for the base
period so that it is at least as broad as, if not broader than,
the Court’s interpretation of section 41(d). Accordingly, under
the reasoning in Cohan v. Commissioner, 39 F.2d 540, 543-544 (2d
Cir. 1930), we accept petitioner’s list of identified runs,
including concessions, as a close approximation of all of the
qualified research activities that occurred during the base
period. It is highly unlikely that Dr. Wadia failed to include
any projects that would materially alter petitioner’s base period
computations. Our view is supported by the 17 fact witnesses who
testified they were not aware of any plant experiments that
occurred during the base period that were not included on the
list of identified runs except for the experiments that
petitioner subsequently conceded. While we agree with respondent
that the memories of the fact witnesses may be faulty, we find
that when taken together as a whole the evidence shows that
petitioner has satisfied its duty to identify all of the
activities that occurred during the base period that it was
required to take into account in calculating its base amount.
While including all of the conceded runs may overstate
petitioner’s base amount, petitioner failed to provide the Court
with any other way to ensure that it has identified all of the
- 273 -
additional qualified research activities that occurred during the
base period and must bear the consequences of its own
inexactitude. See id.
c. Whether Dr. Wadia Is Biased
Respondent argues that Dr. Wadia’s methodology is flawed
because Dr. Wadia is biased by MATRIC’s relationship with Dow and
Dr. Wadia’s reliance on petitioner’s counsel to conduct document
searches. Respondent argues that Dr. Wadia’s failure to include
the wastewater activity (run 809) on his list of identified runs
is evidence of Dr. Wadia’s bias.
As discussed above, we do not think that Dr. Wadia was
mistaken in failing to include the wastewater activity on his
list of identified runs. Respondent has failed to offer any
other evidence that indicates that Dr. Wadia was biased or that
his expert testimony was compromised because of MATRIC’s
relationship with Dow.
IV. Claimed Costs
To be eligible for the research credit under section
41(a)(1), a taxpayer must incur QREs during the credit year.
QREs are generally defined as the sum of the taxpayer’s in-house
research expenses and contract research expenses that are paid or
incurred during the taxable year in carrying on the taxpayer’s
business. Sec. 41(b). Petitioner does not claim as QREs any
contract research expenses and the parties do not dispute that
- 274 -
the claimed costs were incurred during the taxable year in
carrying on UCC’s business.
In relevant part, section 41(b)(2)(A) defines in-house
research expenses as:
(i) any wages paid or incurred to an employee for
qualified services performed by such employee, [and]
(ii) any amount paid or incurred for supplies used
in the conduct of qualified research * * *
Section 41(b)(2)(C) defines the term “supplies” as any
tangible property other than:
(i) land or improvements to land, and
(ii) property of a character subject to the
allowance for depreciation.
Supplies must be used in the conduct of qualified research for
their costs to constitute QREs. Sec. 41(b)(2)(A)(ii). Amounts
incurred for supplies or property used only indirectly for
qualified research or for general and administrative expenses are
not QREs. Sec. 1.41-2(b)(1), Income Tax Regs.
Wages paid to an employee constitute QREs to the extent that
they are paid or incurred for qualified services performed by the
employee. Section 41(b)(2)(B) provides that the term “qualified
services” means services consisting of:
(i) engaging in qualified research, or
(ii) engaging in the direct supervision or direct
support of research activities which constitute
qualified research.
- 275 -
Engaging in qualified research “means the actual conduct of
qualified research (as in the case of a scientist conducting the
laboratory experiments).” Sec. 1.41-2(c)(1), Income Tax Regs.
Section 1.41-2(c)(2), Income Tax Regs., defines “direct
supervision” as follows:
(2) Direct supervision.--The term “direct
supervision” as used in section 41(b)(2)(B) means the
immediate supervision (first-line management) of
qualified research (as in the case of a research
scientist who directly supervises laboratory
experiments, but who may not actually perform
experiments). “Direct supervision” does not include
supervision by a higher-level manager to whom first-
line managers report, even if that manager is a
qualified research scientist.
The regulations define “direct support” as services in the direct
support of either (1) persons engaging in actual conduct of
qualified research or (2) persons directly supervising persons
engaged in actual conduct of qualified research. Sec. 1.41-
2(c)(3), Income Tax Regs.
As discussed above, the Amoco anticoking research activities
and the UCAT-J research activities constitute “qualified
research”. However, we find that the production activities
associated with both projects are not part of the experimental
process business component and do not satisfy the process of
experimentation test. Production activities are associated with
the separate, nonexperimental, product business components.
Accordingly, only the costs of supplies and wages that relate to
- 276 -
UCC’s research activities, not production activities, may be
QREs.
Petitioner argues that the costs of all supplies and wages
that were incurred during the Amoco anticoking and UCAT-J
projects are QREs because the projects could not have occurred
without the supplies, particularly the raw materials, that were
used to make the products or without the employees who were
operating the plant, and the costs of these supplies and wages
are not otherwise excluded from the definition of QREs in section
41(b).
We agree that the Amoco anticoking and UCAT-J projects could
not have occurred if UCC had not purchased the raw materials it
used in its production process, raw materials that UCC previously
treated as inventory and deducted as costs of goods sold.
However, this does not make the costs of these raw materials
QREs. The definition of supplies QREs includes only amounts
“paid or incurred for supplies used in the conduct of qualified
research”. Sec. 41(b)(2)(A)(ii) (emphasis added). Petitioner
now seeks to include as QREs amounts incurred during the
production process upon which the qualified research was
conducted, not during the conduct of qualified research itself.
These costs are, at best, indirect research costs excluded from
the definition of QREs under section 1.41-2(b)(2), Income Tax
Regs.
- 277 -
Petitioner argues that section 41 does not further define
the phrase “used in the conduct of” and the regulations provide
only that supplies are “used in the conduct of qualified research
if they are used the performance of qualified services”. Sec.
1.41-2(b)(1), Income Tax Regs. Accordingly, petitioner argues
that the phrase “used in the conduct of” should be interpreted in
its ordinary, everyday sense, citing Commissioner v. Brown, 380
U.S. 563, 571 (1965).
We find that petitioner’s argument fails to recognize the
precise definition of “qualified research” found in section
41(d). Section 41(d)(2)(C) provides that when a taxpayer seeks a
research credit related to its production process, the production
process must be divided into two business components, one that
relates to the process and another that relates to the product.
This indicates that Congress intended to allow taxpayers research
credits for research performed to improve their production
processes, but Congress did not intend for all of the activities
that were associated with the production process to be eligible
for the research credit if the taxpayer was performing research
only with respect to the process, not the product. See sec.
1.41-4(b)(1), Income Tax Regs. Here, the disputed supplies were
raw materials used in the commercial production and sale of
finished products. They were used to make products for sale, not
for experimentation.
- 278 -
The limited congressional intent is also expressed in the
shrinking-back rule, which permits taxpayers to divide a business
component into activities that do and do not satisfy the
qualified research tests when a project would otherwise be
disqualified when considered in its entirety. See sec. 1.41-
4(b)(2), Income Tax Regs. Taxpayers may not circumvent the
narrow definition of qualified research that Congress intended by
including as QREs costs of a project that are not incurred
primarily as a result of the qualified research activities. Raw
materials used to make finished goods that would have been
purchased regardless of whether a taxpayer was engaged in
qualified research are not “used in the conduct of qualified
research”. See sec. 41(b)(2)(A)(ii).
Similarly, the costs of wages constitute QREs only if they
are paid for services consisting of engaging in or supervising
qualified research. Sec. 41(b)(2)(B). Services performed by
employees for activities that would occur regardless of whether
the taxpayer was engaged in qualified research are not qualified
services. See sec. 41(b)(2)(A)(i).
When section 41(d)(2)(C) applies and the relevant business
component is the process, and production of the product alone
would not constitute qualified research, we find that the costs
of supplies that would be purchased and wages attributable to
services that would have been provided regardless of whether
- 279 -
research was being conducted are costs associated with the
product business component and are not incurred in the conduct of
qualified research. However, additional supplies costs incurred
because qualified research is being performed on the process or
wages attributable to services that would not normally have been
provided are attributable to the process business component and
are allowable as QREs if they otherwise satisfy section 41(b).
Petitioner argues that Fudim v. Commissioner, T.C. Memo.
1994-235, requires a different result because in that case the
Court treated as QREs the costs of materials that the taxpayer
used to make plastic objects as part of his research on a process
known as “rapid modeling”. These costs included the cost of the
photopolymers that were fabricated into the plastic objects.
However, in Fudim the taxpayer’s rapid modeling process was
not a “plant process * * * for commercial production” of a
product that he himself fabricated and sold within the meaning of
section 41(d)(2)(C). The Court found that the taxpayer was not
in the business of producing the plastic objects for sale but
“derived only a minimal amount of income on the models he made
during those years.” Accordingly, there was no need to allocate
costs between the process business component and a product
business component. Id. Unlike the supplies UCC used in its
claim projects, which would have been purchased for production
even if no research had been performed, the supplies the taxpayer
- 280 -
in Fudim purchased were “devoted to research.” Id. (emphasis
added). For these reasons, we find Fudim to be distinguishable.
Petitioner also argues that Lockheed Martin Corp. v. United
States, 49 Fed. Cl. 241 (2001), supports its position because it
implicitly holds that a “component part” of a product to be
delivered to a customer can constitute a “supply” within the
meaning of section 41(b). In that case, the court rejected the
Government’s motion for summary judgment that component parts
used to make Supersonic Low Altitude Target (SLAT) devices could
not be “supplies”. Id. at 247.
We disagree that Lockheed Martin supports petitioner’s
argument. In that case the court explicitly declined to consider
whether the component parts were used in the conduct of qualified
research. Id. at 245-246. Furthermore, Lockheed Martin is
distinguishable from the case before us because in that case the
relevant business component was the SLAT device, not the process
used to make the SLAT devices.
Petitioner also cites a Canadian tax case, Consoltex Inc. v.
R, [1997] 2 C.T.C. 2846, in support of its position. In
Consoltex, the court held that the cost of yarn used by a textile
producer during research conducted to develop improved textile
products was eligible for a scientific research and experimental
development credit. Consoltex addressed a provision of Canadian
law, not the section 41 research credit. In any event, Consoltex
- 281 -
is distinguishable because, as in Lockheed Martin, the research
conducted related to an experimental product and not the process
of producing the product.
Petitioner argues that at many times during the conduct of
the claim projects UCC did not know whether the product produced
would meet customer specifications. However, this does not
indicate that UCC was conducting qualified research on its
products. To the contrary, petitioner has argued that for
purposes of determining whether the claim projects constitute
qualified research we should focus our analysis on the process,
not the product. In any event, the evidence clearly indicates
that to the extent that UCC was conducting research on its end
products its activities would be excluded from the definition of
qualified research under section 41(d)(4)(A) as research after
commercial production because all of the products UCC produced
during the claim projects satisfied UCC’s functional and economic
requirements. The fact that UCC occasionally produced off-
specification products does not change the fact that UCC had
already commercialized those products.
Even if we were to include production activities as part of
the relevant business components, the production costs petitioner
claims are QREs would not be eligible for the research credit
under Mayrath v. Commissioner, 41 T.C. at 590, which limits
deductions under section 174 “to those expenditures of an
- 282 -
investigative nature expended in developing the concept of a
model or product.” Section 41(d)(1)(A) incorporates section 174
into the definition of qualified research. Petitioner cannot
avoid the restrictions of section 174 by arguing that section 174
is relevant only for determining whether activities constitute
qualified research and has no bearing on whether the costs of
those activities may be QREs. See Norwest Corp. & Subs. v.
Commissioner, 110 T.C. at 491; H. Conf. Rept. 99-841 (Vol. II),
supra at II-71, 1986-3 C.B. (Vol. 4) at 71 (“the conference
agreement limits research expenditures eligible for the
incremental credit to ‘research or experimental expenditures’
eligible for expensing under section 174.”).
Furthermore, the fact that petitioner first sought the
research credit for the claimed costs in its petition is strong
evidence that petitioner did not view these costs as research
costs and that UCC would have incurred these costs without the
incentive of the research credit. Production costs that UCC
would have incurred without the incentive of the research credit
are not the types of costs that Congress sought to target when it
enacted the research credit.
Petitioner bears the burden of proving its entitlement to
the additional research credits claimed in the petition. See
Rule 142; New Colonial Ice Co v. Helvering, 292 U.S. 435, 440
- 283 -
(1934); Norwest Corp. & Subs. v. Commissioner, supra at 488-489
n.34; Eustace v. Commissioner, T.C. Memo. 2001-66.
Petitioner’s claimed costs for supplies for both the Amoco
anticoking and UCAT-J projects include only costs of production.
Instead of calculating the cost of supplies that UCC used
specifically to perform experiments during production or analyze
data, petitioner’s calculations are founded on the assumption
that UCC did not increase its supplies costs during the claim
projects above its normal raw materials costs used in its plant
cost system to compute cost of goods sold. It does not appear
that petitioner had any additional supplies QREs to claim because
petitioner claims as QREs only the raw material costs of the
finished products and not any additional supplies. This
indicates that petitioner has not allocated its claimed QREs
between the experimental process business components and the
nonexperimental product business components of those projects.
Furthermore, petitioner did not distinguish between activities
that constitute elements of a process of experimentation and
ordinary production activities. We find that the claimed
supplies costs are ordinary production costs that were properly
included in inventory and petitioner has not satisfied its burden
of proving that the costs it claims as supplies QREs were used in
the conduct of qualified research as required by section
41(b)(2)(A)(ii). Petitioner has had ample opportunity to
- 284 -
establish that it incurred additional supply QREs for the claim
projects and has not carried its burden. Accordingly, we find
that petitioner is not entitled to claim any additional supply
QREs for the claim projects, and we need not address respondent’s
remaining arguments that relate to the costs of these projects.52
The research credits claimed on petitioner’s original
returns and allowed by respondent included the wages of UCC’s R&D
scientists and engineers at its technical centers. Petitioner
now seeks to treat as additional QREs amounts paid to operators
at Taft and Star for the Amoco anticoking and UCAT-J projects,
respectively.
For the Amoco anticoking project, petitioner treated as wage
QREs the wages paid to Mr. Hyde, Mr. Tregre, and Mr. Gorenflo
according to the number of hours each spent working on the
project. Mr. Hyde and Mr. Tregre both credibly testified that
they spent a combined total of 50 hours working on the Amoco
anticoking project. We find that the services that Mr. Hyde and
Mr. Tregre provided in connection with the Amoco anticoking
52
Respondent also argues that: Petitioner should not have
included the costs of utilities in its supplies costs because
utilities are generally excluded from the definition of qualified
research unless they are extraordinary, and they were not
extraordinary for the claim projects, see sec. 1.41-2(b)(1) and
(2), Income Tax Regs.; petitioner’s claimed supplies costs are
unreasonable and are therefore excluded under secs. 174 and
41(d)(1)(A); petitioner has failed to substantiate its supplies
costs; and Ms. Hinojosa erred in her allocation of one-
seventeenth of Taft’s ethylene supply costs to the Amoco
anticoking project.
- 285 -
project, including planning the tests, participating in the
pretreatments, and sending the data to the technical center to be
analyzed, constitute qualified services. While respondent argues
that petitioner has not substantiated its claimed QREs, we find
that the testimonies of Mr. Hyde, Mr. Tregre, and Ms. Hinojosa
were credible and sufficiently substantiated the wages paid to
these employees. We find that petitioner has satisfied its
burden and may treat as wage QREs $835 and $210 for 1994 and
1995, respectively.53 However, Mr. Gorenflo did not testify as
to how much time, if any, he spent on the Amoco anticoking
project. Accordingly, petitioner has not satisfied its burden of
proving that Mr. Gorenflo spent 2 hours engaged in qualified
research with respect to the Amoco anticoking project in 1994 and
may not claim his wages as QREs.
For the UCAT-J project, petitioner treated as additional
QREs a percentage of all wages paid to Star plant personnel
during 1994 and 1995 without determining which employees worked
on the UCAT-J project or how many hours they dedicated to the
project. Petitioner has not provided any evidence that shows how
53
Mr. Hyde spent 35 and 10 hours working on the Amoco
anticoking project in 1994 and 1995, respectively, and his wage
rate was $21 per hour. Mr. Tregre spent 5 hours working on the
Amoco anticoking project in 1994 and his wage rate was $20 per
hour.
The parties agree as to the operation of sec. 280C(c) and
any adjustments that may be required as a result of our decision.
Accordingly, we do not discuss it here.
- 286 -
much time Star’s plant employees actually spent on the UCAT-J
project, and there is no way to determine whether petitioner’s
estimate is accurate. It appears that petitioner has already
received a credit under section 41 for the wages of most of the
employees who engaged in qualified research during the claim
years--the R&D scientists and engineers. Accordingly, petitioner
is not entitled to any additional QREs attributable to wages paid
for the UCAT-J project.
V. Base Period QREs
A. Alleged Flaws in Ms. Toivonen’s Costing Methodology
Petitioner claims that it incurred $135,112,912 of QREs
during the base period on the basis of Ms. Toivonen’s costing
calculations of the runs identified by Dr. Wadia. Respondent
argues that Ms. Toivonen’s methodology is flawed for the same
reasons respondent argues that Dr. Wadia’s methodology is flawed
because Ms. Toivonen failed to review or verify Dr. Wadia’s
determinations of the run durations and production quantities.
However, as discussed above, we find that any flaws in Dr.
Wadia’s methodology have been cured by petitioner’s concessions,
and accordingly Ms. Toivonen’s reliance on Dr. Wadia was
justified.
Respondent also argues that Ms. Toivonen’s methodology is
flawed because she relied on Ms. Hinojosa and other Dow employees
to identify the lead PCDs and MASs relating to the products
- 287 -
produced. However, respondent does not argue that Ms. Hinojosa
or the other Dow employees were unqualified to identify the lead
PCDs and MASs or that they performed their task poorly. To the
contrary, we find that Ms. Hinojosa and other Dow employees were
in the best position to correctly identify the lead PCDs and MASs
because they were familiar with the products that UCC produced
during the base period.
Respondent next argues that Ms. Toivonen was forced to use
cost accounting information for similar products when the actual
accounting information for a product was unavailable. Respondent
believes that in some situations this caused Ms. Toivonen to omit
supplies that were used in the production process. As an
example, respondent points to the propyl dipropasol refining test
(run 171), where Dr. Wadia listed sodium hydroxide as the
catalyst but Ms. Toivonen calculated the cost of sodium propylate
instead because it was listed on the PCD. Similarly, for the
isophorone mids conversion test (run 173) and secondary refining
system test (run 178), Dr. Wadia stated that certain materials
were used that Ms. Toivonen did not include in the cost of the
runs because they were not listed on the PCDs.
Ms. Toivonen testified that in her expert opinion any
discrepancies that may have occurred because she used accounting
information that did not exactly match the products produced or
Dr. Wadia’s descriptions of the runs are immaterial. Regarding
- 288 -
Ms. Toivonen’s method of costing the propyl dipropasol refining
test, we find that Ms. Toivonen did not understate the cost of
the propyl dipropasol refining test because the cost of sodium
propylate was most likely higher than the cost of sodium
hydroxide.54 While a more conservative calculation of the cost
of the isophorone mids conversion and secondary refining system
tests would have included the cost of materials that were used
but omitted from the PCDs, we find that the omissions were
immaterial given the small amount of materials that were used.
We find Ms. Toivonen to be a credible expert witness, and in the
absence of any evidence to the contrary we find that any errors
in her conclusions that may have been caused by the accounting
records she used are immaterial.
B. Alleged Errors in Ms. Toivonen’s Calculations
Respondent also argues that Ms. Toivonen made errors in her
report even when she used the correct documentation. As an
example, respondent argues that Ms. Toivonen incorrectly
calculated the cost of 90,000 pounds of acrolein for the acrolein
refining system capacity test (run 128) instead of 1,800,000
pounds, the production quantity reported by Dr. Wadia. Ms.
Toivonen testified that the discrepancy might be attributable to
54
Petitioner also argues that sodium propylate is the
chemical product of reacting sodium hydroxide with proponal, and
accordingly Ms. Toivonen’s calculation did in fact include the
cost of sodium hydroxide. However, given our finding, we need
not decide whether it is appropriate to take judicial notice of
this fact.
- 289 -
a unit of measure conversion, but she did not explain the
discrepancy in her expert report and could not be certain when
questioned about the discrepancy at trial.
In the absence of any clear explanation as to why she did
not use the production quantity that Dr. Wadia provided, we find
that Ms. Toivonen should have calculated the cost of producing
1,800,000 pounds of acrolein, which would increase the base
period QREs by $283,654.80.55 However, we do not agree with
respondent that all of Ms. Toivonen’s base period calculations
should be disregarded because of this error and find it would be
more appropriate to increase petitioner’s QREs for 1987 by
$283,654.80.
Respondent also argues that Ms. Toivonen lacked the
technical expertise to calculate the cost of runs 807 through
820. As evidence, respondent points out that on cross-
examination Ms. Toivonen could not answer the question of whether
the cost of naphtha was captured as one of the costs for the
naphtha-sulfur injection test (run 807). Ms. Toivonen believes
that the cost of the naphtha may have been captured on secondary
PCDs, which she used to calculate the costs of materials listed
on lead PCDs, but she could not be sure.
55
Ms. Toivonen calculated the supply cost per pound of
acrolein as $0.16588.
- 290 -
Respondent also argues that Ms. Toivonen incorrectly
determined that the naphtha-sulfur injection test lasted for 35
days because other documents indicate that it lasted much longer
than 35 days. As evidence, respondent points to two industrial
chemicals division monthly reports, one for December 1985, dated
January 13, 1986, and a second for July 1986, dated August 11,
1986. The report for December 1985 states that the test began on
December 16, which is the date that Ms. Toivonen determined the
test began. The report for July 1986 does not mention the test
at all.
We do not think that the naphtha-sulfur injection test is
evidence that Ms. Toivonen lacked the technical expertise to
calculate the cost of runs 807 through 820. Ms. Toivonen
captured the costs of the materials listed on the lead PCD for
the product, and we find the lead PCD to be a reliable document
to use to calculate the cost of producing a finished product.
While, as discussed below, this test does highlight a different
flaw in petitioner’s costing methodology because it includes only
the cost of ordinary production activities, we find that the fact
that naphtha was not listed on the lead PCD suggests that its
cost would not materially affect the cost of producing the
product made in the naphtha-sulfur injection test.
Furthermore, the evidence that respondent argues indicates
that the naphtha-sulfur injection test likely lasted much longer
- 291 -
than 35 days does not so indicate. To the contrary, it indicates
that it started on the date that Ms. Toivonen determined it
started and had not been completed as of 3 days before the date
that Ms. Toivonen determined that it ended.
Respondent also believes that Ms. Toivonen mistakenly failed
to include the cost of refrigeration when costing the MMP
refrigeration test (run 810). Section 1.41-2(b), Income Tax
Regs., provides that general and administrative expenses do not
qualify as QREs, and section 1.41-2(b)(2)(i)(1), Income Tax
Regs., provides that utilities are generally treated as general
and administrative expenses. However, section 1.41-2(b)(2)(ii),
Income Tax Regs., provides that utilities may constitute QREs if
they are extraordinary. Respondent argues that the cost of
refrigeration in the MMP refrigeration test was extraordinary.
We find that refrigeration was not an extraordinary
expenditure in the refrigeration capacity tests. In the first
test, in which UCC evaluated transfer chiller control at negative
10 degrees Centigrade instead of negative 17 degrees Centigrade,
UCC actually used less refrigeration than it would have during
the ordinary production of MMP. In the second test, in which UCC
estimated the ambient heat gain of the day tanks and storage
tanks, any refrigeration used was not above the normal amount
that UCC would have used had it not been performing a test.
Accordingly, we do not find the cost of refrigeration to have
- 292 -
been an extraordinary expenditure during either of these tests.
C. Documents Ms. Toivonen Relied Upon
Respondent argues that Ms. Toivonen’s methodology is flawed
because Ms. Toivonen relied on petitioner’s counsel to provide
her with the accounting records related to runs 807 through 820
instead of conducting an independent search of all of the
documents in the record. Furthermore, respondent argues that Ms.
Toivonen looked only at accounting records to identify costs
instead of identifying technical documents to see whether they
provided additional information as to the duration or production
quantity of the runs.
We find that the fact that Ms. Toivonen did not personally
find the necessary accounting records she needed to cost runs 807
through 820 is irrelevant. There has been no suggestion, nor is
there any evidence, that petitioner’s attorneys were not
competent to provide Ms. Toivonen with the documents she needed
or that they withheld or tampered with any information. Given
the large number of documents produced in this controversy, it
would have been impractical to require Ms. Toivonen to search
through all of the documents in the record without the assistance
of petitioner’s counsel.
We also find that respondent’s argument that Ms. Toivonen
looked only at accounting records to calculate the cost of Runs
807 through 820 is inaccurate. Ms. Toivonen’s supplemental
- 293 -
expert report cites numerous technical documents and trial
testimony to support her findings. For each run, Ms. Toivonen
provided a reasonable explanation as to how she determined the
duration and production quantity and included citations of
technical documents and testimony where appropriate. While, as
discussed above, respondent argues that Ms. Toivonen failed to
review technical documents that contradict her findings regarding
the duration of the naphtha-sulfur injection test, we find that
the technical documents at issue are consistent with Ms.
Toivonen’s determinations for that test. Furthermore, because
the refrigeration used in the MMP refrigeration tests was not
extraordinary, there was no need for Ms. Toivonen to review
additional documents to determine the cost of the refrigeration
used. Accordingly, we find that Ms. Toivonen committed no error
in relying upon the documents that she relied upon.
D. Consistency Requirement
Respondent argues that Ms. Toivonen’s methodology for
costing the identified runs was inconsistent with Ms. Hinojosa’s
methodology for calculating the cost of the claim projects.
Specifically, respondent disputes Ms. Toivonen’s treatment of
base case costs and wage costs.
1. In General
Respondent argues that the fact that petitioner claimed QREs
of $43 million for the UOP GA-155 project indicates that
- 294 -
petitioner failed to satisfy the consistency requirement because
the largest base period project before the trial was costed as
$5.1 million and the most QREs petitioner claims in 1 base period
year are $33 million.
Respondent’s argument is contrary to the purpose of the
research credit. The research credit was designed to encourage
taxpayers to increase their spending on qualified research. If
the fact that a taxpayer incurred more QREs in a credit year than
in the base period could be treated as dispositive that the
taxpayer ran afoul of section 41(c)(4), this would thwart the
purpose of the research credit.
Furthermore, we find that as a general matter, petitioner
used the same methodology to calculate its credit year and base
period QREs. In the opinions of Ms. Toivonen and Ms. Hinojosa,
petitioner’s accounting expert witnesses, the costing methodology
Ms. Toivonen applied in calculating UCC’s base period costs is
consistent with Ms. Hinojosa’s methodology. In arriving at this
conclusion, each expert witness reviewed the methodology used by
the other. We find both expert witnesses to be credible on this
matter and find that Ms. Toivonen’s costing methodology was
generally consistent with Ms. Hinojosa’s costing methodology.
2. Base Case Costs
Respondent argues that petitioner’s treatment of base case
costs for the base period differs from its treatment of base case
- 295 -
costs for the credit years. Respondent argues that for the Amoco
anticoking project petitioner treated the cost of testing the
untreated cracking sets as QREs but for the Nalco 5211 test (run
15) petitioner did not treat the cost of the base case runs as
QREs. Respondent argues that both the Amoco anticoking project
and the Nalco 5211 test used base cases and that petitioner
should have treated both base cases the same.
We agree that it is possible that UCC conducted some
qualified research before the start date petitioner determined
for the Nalco 5211 test. However, as discussed above, we find
that none of the supply costs that petitioner claimed with
respect to the Amoco anticoking project constituted QREs.
Similarly, we find that it would be inappropriate to treat the
costs of raw materials that were used during the base case runs
as QREs. While we allowed petitioner to treat $1,045 that UCC
paid to two of its employees as wage QREs, this was less than
one-tenth of 1 percent of the total QREs that petitioner claimed
for the Amoco anticoking project. Accordingly, even if
petitioner improperly omitted wages paid to UCC plant employees
to conduct qualified research before the date on which petitioner
believes the Nalco 5211 test began, given petitioner’s expansive
reading of section 41(b) we find it highly unlikely that
petitioner’s calculation of the Nalco 5211 test understates the
amount of QREs that were actually incurred. Accordingly, under
- 296 -
the principles provided in Cohan v. Commissioner, 39 F.2d at 543-
544, we find it more appropriate to accept petitioner’s
calculation of the Nalco 5211 test than to reject petitioner’s
efforts as a whole.
3. Wage Costs
Respondent next argues that Ms. Toivonen’s method of
calculating wage costs was inconsistent with the method Ms.
Hinojosa used for the credit years, specifically the wage costs
for the UCAT-J project. Ms. Hinojosa calculated the wage costs
for the UCAT-J project by multiplying the total wages incurred
for all Star employees by the ratio of UCAT-J production pounds
to total production pounds in each of the credit years.
Respondent argues that when calculating the wages incurred at
Star for the base period, Ms. Toivonen inconsistently excluded a
number of groups of personnel that were included in the credit
year wage costs.
As discussed above, we find that none of the costs that
petitioner claims as QREs with respect to the UCAT-J project
constitute QREs. Ms. Hinojosa determined that the amount of time
spent by plant operators and other support staff during the UCAT-
J runs was not significantly different when compared to normal
production runs. This indicates that the employees whose wages
Ms. Hinojosa calculated were not involved in the conduct of
qualified research but were engaged in ordinary production
- 297 -
activities. Even if those employees were involved in the conduct
of qualified research, petitioner has offered no way of
distinguishing the wages UCC it paid for its employees to engage
in qualified research and to engage in ordinary production
activities. Accordingly, petitioner did not violate section
41(c)(4) by excluding similar costs from its base period
calculations.
E. Whether Ms. Toivonen Calculated the Cost of “Qualified
Research” Activities
We find Ms. Toivonen’s methodology to be flawed for the same
reason that Ms. Hinojosa’s methodology is flawed. In calculating
the cost of the identified runs, Ms. Toivonen identified only
ordinary production costs, not the costs of performing research.
The naphtha-sulfur injection test (run 807) highlights the
flaw in petitioner’s costing methodology that we discussed with
regard to the claim projects. Ms. Toivonen calculated the cost
of the naphtha-sulfur injection test as being the cost of
producing ethylene, which is not an experimental product.
However, if the naphtha-sulfur injection test constitutes
qualified research,56 the activities that constitute process of
experimentation would be limited to the planning of the test,
injecting naphtha into the process stream, testing the results,
and analyzing the results. The ordinary production activities
that would occur during the production of ethylene regardless of
56
We accept petitioner’s concession that this run
constitutes qualified research.
- 298 -
whether an experiment was being conducted would fail the process
of experimentation test, although most likely naphtha would be
considered a supply used in the experiment. However, in costing
the naphtha-sulfur injecting test, Ms. Toivonen included all of
the ordinary production costs and excluded the cost of naphtha.
Ms. Toivonen similarly calculated the cost of all of the
other identified runs as if they were ordinary production runs.
Ms. Toivonen did not calculate the cost of any additional
supplies that may have been purchased for the tests or calculate
the wages paid to any specific plant employees who worked on the
projects.
However, we find Ms. Toivonen’s error to be harmless because
it causes petitioner to overestimate its base amount, thereby
reducing the research credit. Ms. Toivonen concluded that the
total cost of all of the identified runs was $135,112,912.
Because petitioner has provided us with no way to divide these
costs between costs incurred in the conduct of qualified research
and costs incurred as ordinary production costs, we shall treat
the entire amount as additional base period QREs, adjusted
according to our findings.57
VI. Conclusion
We find that petitioner has established that it incurred
additional wage QREs of $835 and $210 for 1994 and 1995,
57
We find that Ms. Toivonen improperly calculated the cost
of the acrolein refining system capacity test.
- 299 -
respectively, but no additional supplies QREs for the claim
projects. Furthermore, we accept petitioner’s calculations for
the base period, adjusted according to our findings, as UCC’s
additional base period QREs. We shall instruct the parties to
resolve any issues regarding the remaining credit year projects
in a manner consistent with this opinion.
On the basis of the foregoing,
An appropriate order will
be issued.