UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
_________________________________________
)
IOAN MICULA, et al., )
)
Petitioners, )
)
v. ) Case No. 17-cv-02332 (APM)
)
GOVERNMENT OF ROMANIA, )
)
Respondent. )
_________________________________________ )
MEMORANDUM OPINION
I. INTRODUCTION
Petitioners Viorel Micula, Ioan Micula, and three entities they control have asked this court
to confirm an arbitration award entered in their favor against Respondent Government of Romania
(“Romania”) by a tribunal convened under the International Convention on the Settlement of
Investment Disputes between States and Nationals of Other States. Confirming the award would
render it an enforceable judgment in the United States. Romania raises a host of objections to
confirming the award, including a challenge to the court’s subject matter jurisdiction. The
European Commission, appearing as amicus curiae, also advocates against confirming the award.
For the reasons that follow, the court grants the petition to confirm the arbitration award
and enters judgment in favor of Petitioners.
II. BACKGROUND
A. Factual Background
1. The ICSID Convention
The International Convention on the Settlement of Investment Disputes between States and
Nationals of Other States (“Convention”) is “a multilateral treaty aimed at encouraging and
facilitating private foreign investment in developing countries.” Mobil Cerro Negro, Ltd. v.
Bolivarian Republic of Venezuela, 863 F.3d 96, 100 (2d Cir. 2017). The Convention carries out
that purpose by providing a legal framework and procedural mechanism to resolve disputes between
private investors and governments. See Convention on the Settlement of Investment Disputes
between States and Nationals of Other States Preamble, Mar. 18, 1965, T.I.A.S. No. 6090, 17 U.S.T.
1270. The Convention establishes the International Centre for Settlement of Investment Disputes,
or “ICSID,” as an international institution that operates under the auspices of the World Bank.
See Mobil Cerro Negro, 863 F.3d at 101. ICSID convenes arbitration panels “to adjudicate disputes
between international investors and host governments in ‘Contracting States.’” Id. Romania and
Sweden are signatories to the ICSID Convention. So, too, is the United States.
“Any Contracting State or any national of a Contracting State” may ask ICSID to convene
an arbitral tribunal to resolve a dispute. Convention art. 36. The tribunal is tasked with adjudicating
the dispute and, if warranted, issuing a written award that addresses “every question submitted to
the Tribunal” and “state[s] the reasons upon which [the award] is based.” Id. art. 48. A party may
contest the tribunal’s decision, consistent with the procedures set forth in the Convention. See id.
arts. 51–52. But critically, “except to the extent that enforcement [is] stayed,” the tribunal’s ruling
is “binding on the parties and shall not be subject to any appeal or to any other remedy” other than
2
those afforded under the Convention. Id. art. 53. In other words, the domestic courts of member
countries lack the authority to review the merits of a decision by an ICSID tribunal.
The Convention does not, however, confer upon ICSID the power to enforce arbitral awards.
It left that function to its Contracting States. Article 54(1) of the Convention provides: “Each
Contracting State shall recognize an award rendered pursuant to this Convention as binding and
enforce the pecuniary obligations imposed by that award within its territories as if it were a final
judgment of a court in that State.” Id. art. 54(1). Contracting States that, like the United States,
have a federal system of government “may enforce such an award in or through [their] federal courts
and may provide that such courts shall treat the award as if it were a final judgment of the courts of
a constituent state.” Id.
The ICSID Convention also is not self-executing. See Medellin v. Texas, 552 U.S. 491,
505–06 (2008) (explaining when a treaty obligation requires legislation to become domestic law).
Contracting States must “take such legislative or other measures as may be necessary for making
the provisions of this Convention effective in [their] territories.” Convention art. 69. In the United
States, Congress gave the ICSID Convention domestic effect by passing the Convention on the
Settlement of Investment Disputes Act of 1966. See Convention on the Settlement of Investment
Disputes Act of 1966, Pub. Law 89–532, 80 Stat. 334 (1966) (codified at 22 U.S.C. §§ 1650 and
1650a). Section 3 of the Act addresses the enforcement of ICSID arbitration awards in the United
States. It provides in relevant part: “The pecuniary obligations imposed by [an ICSID] award shall
be enforced and shall be given the same full faith and credit as if the award were a final judgment
of a court of general jurisdiction of one of the several States.” 22 U.S.C. § 1650a(a). Federal courts
are vested with “exclusive jurisdiction over actions and proceedings” to enforce ICSID awards.
Id. § 1650a(b).
3
2. Events Leading to the ICSID Arbitration
This case arises out of a dispute between Swedish investors and Romania. Following the
overthrow of the communist regime of Nicolae Ceausescu in December 1989, the country of
Romania found itself in dire economic and social circumstances. See Ioan Micula, et al. v.
Romania, ICSID Case No. ARB/05/20 (Dec. 11, 2013), ECF No. 1-1–1-4 [hereinafter Final
Decision], ¶ 137. In response to these problems, Romania adopted a series of measures designed
to attract and promote investment. Id. ¶¶ 138–144. Among the measures was Emergency
Government Ordinance No. 24/1998 (“EGO 24”), which established a framework for granting
incentives to invest in “disfavored” regions of Romania. Id. ¶ 145.
The petitioners in this case are Swedish nationals Viorel and Ioan Micula, along with three
companies they control, S.C. European Food S.A., S.C. Starmill S.R.L., and S.C. Multipack S.R.L.
See Petition to Confirm ICSID Award, ECF No. 1 [hereinafter Pet.], ¶¶ 8–12. Starting in 1998, in
reliance on the incentives offered by EGO 24, Petitioners began to build an integrated food platform
designed to produce consumer products and beverages for the Romanian market. Final Decision
¶¶ 166–172.
In August 2004, Romania thwarted Petitioners’ plans when it announced that it would repeal
EGO 24, effective February 22, 2005. Id. ¶ 241. Romania made the repeal decision as part of the
process of becoming a member of the European Union (“EU”). Id. ¶¶ 234–239. The action
followed Romania’s receipt of advice from the European Commission—an institution of the
European Union that is responsible for ensuring the proper application of EU treaties—that the
incentives constituted “state aid” that was incompatible with the EU’s prohibition of such
anticompetitive schemes. Id. The incentives’ repeal caused Petitioners to suffer cash constraints
4
that prevented them from completing the projects they had planned in reliance on EGO 24. Id.
¶ 172.
2. The ICSID Arbitration
In 2002, Romania entered a bilateral investment treaty (“Sweden-Romania BIT”) with the
Kingdom of Sweden, which entered into force on April 1, 2003. Final Decision ¶ 226. That treaty
granted certain protections to each country’s investors who invested in the other country, including
the right to arbitrate investment disputes. See Agreement between the Government of the Kingdom
of Sweden and the Government of Romania on the Promotion and Reciprocal Protection of
Investments art. 2, Swed.-Rom., May 29, 2002, Law No. 541/2002 (Rom.) [hereinafter Sweden-
Romania BIT]. Pertinent to the parties’ dispute is Article 7 of the Sweden-Romania BIT.
See generally Ioan Micula, et al. v. Romania, ICSID Case No. ARB/05/20 (Sept. 24, 2008), ECF
No. 62-2. It provides that disputes concerning investments are to be settled by international
arbitration, before either an ICSID arbitral tribunal or an ad hoc tribunal established under the
Arbitration Rules of the United Nations Commission on International Trade Law. See id. ¶ 57;
Sweden-Romania BIT art. 7.
In response to Romania’s decision to revoke financial incentives, Petitioners initiated
arbitration proceedings against Romania before an ICSID tribunal on August 2, 2005. Final
Decision ¶ 10. Petitioners claimed that they had made investments in certain regions of Romania
in reliance on the economic incentives. Id. ¶ 131. The revocation of those incentives, Petitioners
alleged, caused them to suffer significant financial losses, for which Romania was liable. Id. ¶¶ 131,
262. The ICSID tribunal agreed. In December 2013, the tribunal ruled for Petitioners and awarded
monetary damages of 376,433,229 Romanian Leu (RON)—the equivalent of $116,317,868—plus
5
interest at the rate of the three-month Romanian Interbank Offer Rate, plus 5%, compounded on a
quarterly basis with respect to certain amounts and periods (“the Award”). Id. ¶ 1329.
3. Romania Joins the European Union
Meanwhile, in parallel with the ICSID arbitral tribunal proceedings, Romania continued
taking steps necessary to join the EU. Id. ¶¶ 246–47. Romania formally joined the EU on January
1, 2007—after Petitioners invoked their right to arbitration under the Sweden-Romania BIT but
before the ICSID tribunal ruled in favor of Petitioners. Id. ¶¶ 247–49.
Shortly after the ICSID tribunal issued the award, the European Commission advised
Romania that implementing or executing the Award would constitute impermissible new state aid,
about which Romania would be required to notify the Commission. See Commission Decision
(EU) 2015/1470 of 30 March 2015, ECF No. 51-2 [hereinafter State Aid Decision], ¶ 2. Three
months later, in May 2014, the Commission issued a “suspension injunction,” prohibiting Romania
from taking any action to fulfill any part of the Award not yet paid until the Commission reached
a final decision on whether the Award constituted state aid. Id. ¶ 6.
As a result of the suspension injunction, Romania returned to ICSID. Invoking Article 52
of the Convention, Romania asked ICSID to convene an ad hoc tribunal for the purpose of annulling
the Award. Id. ¶ 28. ICSID did so, and on August 7, 2014, the tribunal agreed to stay enforcement
of the Award. Id. It conditioned the stay, however, on Romania’s committing, without
qualification, to pay the full Award if the ICSID tribunal decided not to annul the Award. Id.
Romania declined to provide the unconditional commitment to pay. Id. ¶ 29. The tribunal then
lifted the stay of enforcement on September 7, 2014. Id.
Nearly a year after issuing the suspension injunction, on March 30, 2015, the Commission
issued its decision on whether the Award constituted state aid in violation of EU law (“the State
6
Aid Decision”). The Commission found that it did. Id. ¶ 125. The Commission concluded that,
because the benefits generated by Romania’s incentive law was unlawful state aid, so too was the
Award, which sought to compensate Petitioners for the advantages negated by the incentives’
repeal. Id. ¶¶ 95, 109–24. The Commission rejected Petitioners’ view that the ICSID Convention
controlled, reasoning that EU law superseded the Sweden-Romania BIT. Id. ¶¶ 126–29. The State
Aid Decision concluded by ordering Romania not to pay any further amounts on the Award and
to recover any amounts already paid. Id. at 33, art. 2. Petitioners filed an appeal of the State Aid
Decision with the General Court of the Court of Justice of the European Union, a constituent court
of the EU’s highest court, the Court of Justice of the European Union (CJEU).
In the meantime, the annulment proceedings before the ICSID ad hoc tribunal continued.
Almost a year after the State Aid Decision, the ad hoc tribunal issued its final decision on February
26, 2016. It rejected Romania’s effort to annul the Award. See Ioan Micula, et al. v. Romania,
ICSID Case No. ARB/05/20 (Feb. 26, 2016), ECF No. 1-5. In so doing, the tribunal summarily
rejected the argument put forward by the European Commission, which had intervened, that the
Award was incompatible with EU law on state aid. See id. ¶¶ 308–28. The ICSID ad hoc tribunal’s
decision thus created a direct conflict with the Commission’s State Aid Decision.
B. Petitioners’ Efforts to Confirm the Award in the United States
As Petitioners and Romania duked it out before the Commission and ICSID over the
validity of the Award, Petitioners came to the United States to attempt to “confirm” the Award
under 22 U.S.C. § 1650a. 1 A confirmed Award would render it an enforceable judgment in United
1
To be clear, the court uses the verb “confirm” in this Memorandum Opinion to mean the judicial act of “enforcing”
an Award under § 1650a. As the Second Circuit and this court have held, § 1650a does not contemplate a
“confirmation” or “recognition” procedure that is separate from “enforcing” an ICSID award. See Mobil Cerro Negro,
863 F.3d at 118–20 & 118 n.18; Micula v. Gov’t of Romania, 104 F. Supp. 3d 42, 49 (D.D.C. 2015). Nevertheless,
because Petitioners repeatedly use the term “confirm,” for sake of consistency the court does as well.
7
States courts. See generally Micula v. Gov’t of Rom., 104 F. Supp. 3d 42, 44 (D.D.C. 2015)
[hereinafter Micula I]. Petitioners’ efforts to confirm the Award, and Romania’s corresponding
efforts to resist confirmation, have proceeded on a long, winding road over five years along the I-
95 corridor from Washington, D.C., to New York City, and back to Washington, D.C.
The opening act took place here, before this court. On April 11, 2014, Petitioner Viorel
Micula, proceeding only on his own behalf, filed a petition to confirm the Award. Citing the
practice of the federal District Courts in the Southern District of New York (“SDNY”), Viorel
urged this court to confirm the Award though an ex parte, summary proceeding. See id. at 46. For
that reason, Viorel never served the Government of Romania, and Romania did not formally
appear. See id. at 47. This court, however, refused to confirm the Award in an ex parte proceeding.
See id. at 52. The court held that § 1650a did not permit ex parte confirmation of an ICSID award,
but instead required a petitioner to “file a plenary action, subject to the ordinary requirements of
process under the Foreign Service Immunities Act [“FSIA”].” Id. Viorel elected not to file such
an action and voluntarily dismissed his petition.
Five days after this court ruled, the other Petitioners, later joined by Viorel, sought a
presumably more favorable legal terrain and filed a petition for confirmation in the SDNY. They
initially found success. On April 21, 2015, the court confirmed the Award in an ex parte, summary
proceeding, thereby converting the Award to a judgment. See Micula v. Gov’t of Rom., No. 15
MISC. 107, 2015 WL 4643180, at *2 (S.D.N.Y. Aug. 5, 2015) (allowing proceeding to move
forward ex parte). Romania later appeared and asked another judge in the SDNY to vacate the
judgment on the ground that the ex parte proceeding violated the FSIA. See id. at *3. Also, the
European Commission filed an amicus brief in those proceedings, and it urged the court either to
abstain from exercising jurisdiction or vacate the judgment on the grounds of foreign comity, the
8
act of state doctrine, and the foreign compulsion doctrine, each argument premised on the ongoing
proceedings in Europe. See id. at *2, *6–8. The court in the SDNY rejected all of these arguments
and re-affirmed the judgment against Romania. See id. at *3–8; see also Micula v. Gov’t of Rom.,
No. 15 Misc. 107 (LGS), 2015 WL 5257013 (S.D.N.Y. Sept. 3, 2015) (rejecting second motion
for reconsideration by Romania). Romania appealed.
Petitioners’ victory proved to be fleeting. At the same time Romania was prosecuting its
appeal, another sovereign, the Bolivarian Republic of Venezuela, was also fighting an SDNY
District Court’s ex parte confirmation of an ICSID award in the Second Circuit. On July 11, 2017,
the Second Circuit issued its decision in Mobil Cerro Negro, Ltd. v. Bolivarian Republic of
Venezuela. The case involved three key holdings. The first was that the FSIA provides the sole
basis for subject matter jurisdiction for proceedings under § 1650a, and that § 1650a does not itself
confer such jurisdiction. 863 F.3d at 112–15. Second, the court held the FSIA controls the manner
of obtaining personal jurisdiction over a sovereign, and therefore confirming an ICSID award
pursuant to a summary, ex parte proceeding was improper. See id. at 116–21. Finally, the court
found that a proceeding pursuant to § 1650a must be initiated like a procedure to enforce a state
court judgment—by way of a plenary action with service upon the foreign sovereign. See id. at
121–24.
Based on these rulings in Mobil Cerro Negro, another panel of the Second Circuit on
October 23, 2017, vacated the judgment against Romania. See Micula v. Gov’t of Romania, 714
Fed. App’x 18, 21–22 (2d Cir. 2017). The panel also made clear that, under the FSIA’s venue
provision, venue was proper only in the District of Columbia, see id., thereby forcing Petitioners
to return to this District Court.
9
C. Proceedings Before this Court: To Stay or Not to Stay?
If this case were a hypothetical in a law school class on Civil Procedure, Romania would
get a failing grade. Its procedural maneuvers have caused confusion and unnecessary delay, and
no doubt increased expenses for Petitioners.
On November 6, 2017, Petitioners initiated this action once more before this court, filing
their Petition to Confirm ICSID Arbitration Award and Enter Judgment. See Pet. After
overcoming Romania’s numerous objections to the validity of service under the FSIA—a process
that took nearly a year 2—the court entered an Order setting November 6, 2018, as the deadline for
Romania to answer the Petition. See Order, ECF No. 50 at 3. It also set November 20, 2018, as
the due date for Petitioners’ renewed motion to confirm the arbitral award, and December 11,
2018, as the due date for Romania’s opposition. See id.
Romania never answered the Petition. Instead, on November 6, 2018, it filed a lengthy
memorandum of law in “Opposition” to the Petition. See Resp.’s Mem. of Law in Opp’n to Pet.,
ECF No. 51 [hereinafter Resp’t Opp’n]. Its Opposition asserted that Romania had satisfied the
Award and that the act of state and the foreign sovereign compulsion doctrines required the court
to deny the Petition. See generally id. Romania did not dispute the court’s subject matter
jurisdiction. See id. Petitioners timely filed their Motion for Judgment on the Pleadings or, In the
Alternative, Summary Judgment on November 20, 2018. See Pet’rs Mot. for J. on the Pleadings
or, In the Alternative, Summ. J., ECF No. 55. This is the operative motion before the court. 3 But
Romania did not file an opposition to the Petition, as ordered. Instead, it moved to stay the
2
See Order, ECF No. 15; Order, ECF No. 16; Order, ECF No. 23; Order, ECF No. 50.
3
But it is not Petitioners’ first dispositive motion. Petitioners filed an initial Motion for Judgment and Confirmation
of Arbitral Award, ECF No. 26, on June 28, 2018. Romania opposed the Motion, see ECF No. 29, and it became ripe
on July 19, 2018, see ECF No. 34. As of that date, the status of proper service on Romania remained uncertain. As a
result, Petitioners agreed to re-serve process on Romania, in a manner to which it did not object. See Notice, ECF No.
36. Petitioners renewed service operated as a reset of the proceedings. On October 31, 2018, the court deemed moot
the Motion filed on June 28, 2018, by Petitioners. See Order, ECF No. 50.
10
proceedings and asked the court to extend time to file a “responsive pleading” to the Petitioners’
Motion for Judgment. See Resp’t Motion to Stay Proceedings, ECF No. 57 [hereinafter Resp’t
Mot. to Stay]; Resp’t Mot. for Extension of Time to File Responsive Pleading, ECF No. 58. The
reasons for Romania’s requested stay were Petitioners’ pending appeal of the State Aid Decision
to the General Court of the Court of Justice of the European Union, as well as bankruptcy
proceedings in Romania involving the entity Petitioners. See Resp’t Mem. of Law in Support of
Resp’t Mot. to Stay, ECF No. 57-1. On December 26, 2018, Petitioners filed oppositions to these
motions, as well as a reply in support of its Motion for Judgment, even though Romania had not
filed an opposition to their motion. See ECF Nos. 61, 63, 64. Romania moved to strike Petitioners’
reply, setting off yet another series of briefings. See ECF Nos. 65, 66, 69. To date, Romania has
yet to formally oppose Respondents’ Motion for Judgment.
The European Commission entered these proceedings as amicus curiae on December 11,
2019. See Br. of Amicus Brief the European Commission in Support of Romania, ECF No. 60
[hereinafter EC Amicus Br.]. The Commission took the position that the court must deny the
Petition. It argued that the court lacked subject matter jurisdiction under the FSIA and,
correspondingly, lacked authority under § 1650a to confirm the Award. Of particular note, the
Commission drew the court’s attention to a recent decision of the European Court of Justice in
Slovak Republic v. Achmea BV. See id. at 7–8 (citing Slovak Republic v. Achmea, Case C0284/16
(6 March 2018), ECLI:EU:C:108:158, ECF No. 51-3). More on Achmea below. But for present
purposes it suffices to say that the Commission argued that the decision in Achmea rendered the
arbitration agreement in the Sweden-Romania BIT invalid and unenforceable and, for that reason,
the court lacked subject matter jurisdiction under the FSIA. See id. at 7–8, 10–12. In addition to
this jurisdictional argument, the Commission also contended, as it had in the SDNY proceedings,
11
that the act of state doctrine and the foreign compulsion doctrine barred confirmation.
See generally id. Petitioners opposed the Commission’s arguments. See Pet’rs Mem. of Law in
Response to Br. of Commission, ECF No. 62.
The Commission’s brief apparently triggered a eureka moment for Romania. In its reply
brief in support of its Motion for Stay, Romania asserted for the first time that the court lacks
subject matter jurisdiction to confirm the Award. See Resp’t Reply Mem. in Support of Resp’t
Mot. to Stay, ECF No. 68 [hereinafter Resp’t Reply], at 14–17. Like the European Commission,
Romania rooted its jurisdictional argument in the Achmea decision. See id. at 16–17. 4 Romania
also reasserted that a stay was needed to allow the European court to resolve the appeal of the State
Aid Decision. See id. at 17–21.
This is where the case stood as of June 2019. And then came one more unexpected turn.
D. The General Court Rules
On June 18, 2019, the General Court of the European Court of Justice issued its ruling on
Petitioners’ appeal of the State Aid Decision. See Pet’rs Notice of Suppl. Auth., ECF No. 74;
European Food S.A. et al. v. European Commission, Ioan Micula v. European Commission, and
Viorel Micula et al. v. European Commission, Case Nos. T-624/15, T-694/15, and T-704/15 (June
18, 2019), ECF No. 74-1 [hereinafter General Court Decision]. It held that the State Aid Decision
“must be annulled in its entirety.” Id. ¶ 111. The General Court’s decision turned on its
determination that EU law became applicable to Romania only upon its accession to the EU on
January 1, 2007. Id. ¶¶ 66–67. Based on that premise, the court concluded the Commission lacked
the “competence” to declare that the investment incentives—which Romania offered before
4
To be fair, Romania did cite to Achmea repeatedly in its opposition brief, see Resp’t Opp’n at 1–3, 16–17, 24, 27–
28, but only in connection with its arguments under the act of state and foreign sovereign compulsion doctrine
doctrines. It did not challenge subject matter jurisdiction based on Achmea.
12
acceding to the EU—violated EU rules on state aid. Id. ¶¶ 67, 79. The General Court also found
that, because the ICSID tribunal’s Award compensated Petitioners for Romania’s pre-EU-
accession repeal of the incentives, satisfying the Award would not constitute illegal state aid, even
though it was entered after accession. See id. ¶¶ 74–75, 80, 90-93, 95.
As a result of the General Court’s decision, this court denied as moot Romania’s request
for a stay. See Order, ECF No. 75. It also denied Romania’s motion for additional time to respond
to Petitioners’ Motion for Judgment. See id. The court indicated that it would consider the
arguments made by Romania in its prior filings to collectively comprise its opposition to
Petitioners’ Motion. See id. The court also ordered further briefing on the impact of the General
Court’s nullification of the State Aid Decision. See id. The parties and the European Commission
filed their supplemental briefs in July 2019, 5 and the Commission subsequently advised that it had
lodged an appeal of the General Court’s decision with the CJEU. See European Comm’n’s Notice
of Suppl. Auth., ECF No. 84 [hereinafter EC Not. of Suppl. Authority].
At long last, five years after this matter first arrived in this District, the court now turns to
the merits of whether to confirm the Award.
III. LEGAL STANDARD
A federal court’s role in enforcing an ICSID award is limited. As discussed, the ICSID
Convention vests the power to enforce ICSID awards in the domestic courts of Contracting States.
In the United States, Congress granted federal courts exclusive jurisdiction to enforce ICSID
awards. See 22 U.S.C. § 1650a(b). Such awards “shall be enforced and shall be given the same
full faith and credit as if the award were a final judgment of a court of general jurisdiction of one
5
In yet another instance of Romania not adhering to a court order, its supplemental response rehashed procedural
history and arguments that had little or nothing to do with the General Court’s decision. The court struck Romania’s
response and allowed Romania to re-file a brief responsive to the court’s request, see Minute Order, July 9, 2019,
which it did on July 26, 2019, ECF No. 82.
13
of the several States.” 22 U.S.C. § 1650a(a). A federal court is “not permitted to examine an ICSID
award’s merits, its compliance with international law, or the ICSID tribunal’s jurisdiction to render
the award.” Mobil Cerro Negro, 863 F.3d at 102, 118 (stating that an “ICSID-award debtor would
be a party to the action . . . but would not be permitted to make substantive challenges to the
award”); TECO Guatemala Holdings, LLC v. Republic of Guatemala, Civ. No. 17-102 (RDM),
2018 WL 4705794, at * 2 (D.D.C. Sept. 30, 2018) (citing Mobil Cerro Negro). Instead, the court
“may do no more than examine the judgment’s authenticity and enforce the obligations imposed
by the award.” Mobil Cerro Negro, 863 F.3d at 102, 121 (stating that the ICSID-award debtor can
make “non-merits challenges” to an award, such as “the authenticity of the award presented for
enforcement, the finality of the award, or the possibility that an offset might apply to the award
that would make execution in the full amount improper”). This limited role “reflects an
expectation [under the Convention] that the courts of a member nation will treat the award as
final.” Id.
IV. DISCUSSION
With these principles in mind, the court turns to the challenges raised by Romania.
It advances four arguments. Romania asserts: (1) the court lacks subject matter jurisdiction under
the FSIA, (2) it has fully satisfied the Award, (3) the act of state doctrine prohibits the Award’s
enforcement, and (4) so, too, does the foreign sovereign compulsion doctrine. See Resp’t Opp’n.
at 17–29; Resp’t Mot. to Stay; Resp’t Reply. The European Commission joins in each of these
arguments, except Romania’s contention that it has satisfied the Award. See EU Amicus Br. at
10–20.
14
A. Subject Matter Jurisdiction
The court begins, as it must, with its subject matter jurisdiction to enforce the Award. The
FSIA is “the sole basis for obtaining jurisdiction over a foreign state in the courts of the [United
States].” Belize Soc. Dev. Ltd. v. Gov’t of Belize, 794 F.3d 99, 101 (D.C. Cir. 2015) (quoting
Argentine Republic v. Amerada Hess Shipping Corp., 488 U.S. 428, 443 (1989)); see also
28 U.S.C. §§ 1605–1607. Pursuant to the FSIA, “a foreign state is presumptively immune from
the jurisdiction of the United States courts[,] unless a specified exception applies.” Saudi Arabia
v. Nelson, 507 U.S. 349, 355 (1993). Because “subject matter jurisdiction in any such action
depends on the existence of one of the specified exceptions to foreign sovereign immunity” laid
out in the FSIA, as a “threshold” matter in every action against a foreign state, a district court
“must satisfy itself that one of the exceptions applies.” Verlinden B.V. v. Cent. Bank of Nigeria,
461 U.S. 480, 493–94 (1983); see 28 U.S.C. § 1605(a). Once a plaintiff establishes as a threshold
matter that an exception applies, “the burden of proof in establishing the inapplicability of these
exceptions is upon the party claiming immunity.” Transamerican S.S. Corp. v. Somali Democratic
Republic, 767 F.2d 998, 1002 (D.C. Cir. 1985).
1. Arbitration Exception and the Achmea decision
Here, Petitioners rest jurisdiction primarily on the FSIA’s arbitration exception. See Pet’rs
Resp. to EC Br., ECF No. 62 [hereinafter Pet’rs Resp. to EC].6 That exception provides:
A foreign state shall not be immune from the jurisdiction of courts
of the United States or of the States in any case . . . in which the
6
Petitioners also assert in a footnote that the court has jurisdiction over this matter under the FSIA’s “implied waiver”
exception, because Romania did not challenge the court’s subject matter jurisdiction either in its motion opposing
confirmation of the Award or its motion to stay proceedings. See Pet’rs Resp. to EC at 4 n.3 (“Because Romania did
not raise subject matter jurisdiction under the FSIA in its responsive pleading, the ‘implied waiver’ exception under
Section 1605(a)(1) also applies here.”). The court rejects this assertion for two reasons. First, the court need not
“consider cursory arguments made only in a footnote.” Hutchins v. District of Columbia, 188 F.3d 531, 539 n.3 (D.C.
Cir. 1999). Second, the implied waiver doctrine applies only “narrowly” and includes an “implicit . . . requirement
that the foreign state have intended to waive its sovereign immunity.” Creighton Ltd. v. Gov’t of State of Qatar, 181
F.3d 118, 122 (D.C. Cir. 1999). “[C]ourts rarely find that a nation has waived its sovereign immunity . . . without
15
action is brought[ ] . . . to confirm an award made pursuant to such
an agreement to arbitrate, if . . . the agreement or award is or may be
governed by a treaty or other international agreement in force for the
United States calling for the recognition and enforcement of arbitral
awards.
28 U.S.C. § 1605(a)(6). Courts consistently have held that the FSIA’s arbitration exception
confers subject matter jurisdiction over petitions to enforce ICSID awards. See Blue Ridge Invs.,
L.L.C. v. Republic of Argentina, 735 F.3d 72, 85 (2d Cir. 2013) (“[E]very court to consider whether
awards issued pursuant to the ICSID Convention fall within the arbitral award exception to the
FSIA has concluded that they do.”). Petitioners thus have satisfied their initial burden of
identifying an applicable exception under the FSIA to sovereign immunity. See Phoenix
Consulting, Inc. v. Republic of Angola, 216 F.3d 36, 40 (D.C. Cir. 2000).
Romania says this case is different than those finding the arbitration exception applicable.
It contends that the arbitration exception does not confer jurisdiction “because the arbitration
clause in the Sweden-Romania BIT has been declared invalid.” Resp’t Reply at 15. This argument
rests on the European Court of Justice’s decision in Achmea. Specifically, Romania points to that
part of the Achmea opinion stating that EU law “preclud[es] a provision in an international
agreement concluded between Member States . . . under which an investor from one of those
Member States may, in the event of a dispute concerning investments in the other Member State,
bring proceedings against the latter Member State before an arbitral tribunal.” Resp’t Reply at 16
(quoting Achmea ¶ 60). Applying that principle here, Romania contends that the arbitration clause
in the Sweden-Romania BIT is “invalid as of Romania’s accession to the E.U.” Id. The European
strong evidence that this is what the foreign state intended.” Foremost-McKesson, Inc. v. Islamic Republic of Iran,
905 F.2d 438, 444 (D.C. Cir. 1990). Such “strong evidence” is lacking here. Since appearing in this matter, Romania
has resisted this court’s jurisdiction, at first on the ground that Petitioners failed to secure jurisdiction through proper
service of process under the FSIA. See Mot. to Dismiss for Insufficient Service of Process, ECF No. 7. Once served,
Romania again contested the court’s subject matter jurisdiction under the arbitration exception, albeit belatedly in a
reply brief. See Resp’t Reply at 14–17. Though Romania should have raised its arbitration-exception challenge in an
opening brief, the record lacks the “strong evidence” required to make a finding of implied waiver.
16
Commission shares this view of the effect of Achmea. See EC Amicus Br. at 11 (arguing that
Achmea “applies foursquare to the arbitration agreement in the Romania-Sweden BIT”).
Petitioners, on the other hand, insist that Achmea is not controlling. Pet’rs Resp. to EC at
5–7. They argue that Achmea is materially distinguishable from this case on the facts. See id.
Specifically, Petitioners maintain that Achmea does not apply to the Sweden-Romania BIT
because: (1) the Slovak Republic in Achmea had joined the EU before the arbitral tribunal
commenced in that case, whereas here Romania acceded two years after the ICSID proceedings
began, and (2) Achmea involved an arbitration under another treaty, not the ICSID Convention.
Id. They also assert that the General Court’s decision overturning the State Aid Decision confirms
the inapplicability of Achmea and the continuing validity of the Sweden-Romania BIT’s arbitration
agreement. See Pet’rs Reply in Support of Notice of Suppl. Auth., ECF No. 82, at 6.
At issue in Achmea was a 1992 bilateral investment treaty between the Netherlands and the
Czech and Slovak Republic (“Slovak Republic”). That treaty, like the one at issue here, contained
a provision providing for dispute resolution through international arbitration. Achmea ¶ 4. In May
2004, the Slovak Republic joined the EU. See id. ¶ 6. That same year, in response to the country’s
liberalization of its private medical insurance market, Achmea, a subsidiary of a Netherlands
insurance group, set up a company in the Slovak Republic to sell private medical insurance. See id.
¶ 7. A mere two years later, the Slovak Republic began to partially roll back the market reforms.
See id. ¶ 8. Asserting financial harm as a result of these actions, Achmea invoked the bilateral
investment treaty’s arbitration clause and filed arbitration proceedings against the Slovak Republic
in October 2008. Id. ¶ 9. In December 2012, the arbitral tribunal awarded Achmea damages in
the amount of EUR 22.1 million. Id. ¶ 12.
17
The case eventually made its way to the CJEU, where the court was presented with the
following question:
Does [EU law] preclude the application of a provision in a bilateral
investment protection agreement between Member States . . . under
which an investor of a Contracting State, in the event of a dispute
concerning investments in the other Contracting State, may bring
proceedings against the latter State before an arbitral tribunal where
the investment protection agreement was concluded before one of
the Contracting States acceded to the European Union but arbitral
proceedings are not to be brought until after that date?
Id. ¶ 23. 7 To address the question, the court turned first to the Treaty on the Functioning of the
European Union, which sets forth the EU’s authority to legislate and key principles of EU law.
The court explained that among the Treaty’s aims was to establish the primacy of European law
over the law of the Member States, see id. ¶¶ 32–34, and a judicial system that operates through
national courts and tribunals and the CJEU to “ensure consistency and uniformity in the
interpretation of EU law,” id. ¶ 35. In resolving the issue posed, the CJEU asked three questions.
First, it inquired whether the dispute before the arbitral tribunal related to the interpretation or
application of EU law. It did. See id. ¶¶ 39–42. Next, the court asked whether the arbitral tribunal
“is situated within the judicial system of the EU.” It was not. See id. ¶¶ 43–49. Finally, the court
questioned whether the arbitral award was subject to review by a court of a Member State. It was
not—the bilateral investment treaty at issue provided that the decision of the arbitral tribunal was
final. See id. ¶¶ 50–56. In view of these considerations, the CJEU ruled that the bilateral
investment treaty’s arbitration provision was inconsistent with EU law because permitting
arbitration outside of the EU system could prevent disputes “from being resolved in a manner that
7
Achmea arrived at the CJEU by a process analogous to a federal court in the United States certifying a question of
state law to a state supreme court. The Slovak Republic had filed an action in the domestic courts of Germany to
nullify the award, and the German court then referred the question presented to the CJEU. See id. ¶¶ 12–13.
18
ensures the full effectiveness of EU law, even though they might concern the interpretation of
application of that law.” Id. ¶ 56. The CJEU thus held:
[EU law] must be interpreted as precluding a provision in an
international agreement concluded between Member States . . .
under which an investor from one of those Member States may, in
the event of a dispute concerning investments in the other Member
State, bring proceedings against the latter Member State before an
arbitral tribunal whose jurisdiction that Member State has
undertaken to accept.
Id. ¶ 60.
Having carefully considered the Achmea decision, this court finds that Romania has failed
to carry its burden of showing that Achmea forecloses this court’s jurisdiction under the FSIA’s
arbitration exception. The CJEU’s reasoning in Achmea turned on protecting the “the autonomy
of EU law.” Id. ¶ 59. The court there deemed the arbitration provision invalid because, in short,
the dispute called upon the arbitral tribunal to interpret or apply EU law and the tribunal’s ultimate
resolution of any question of EU law was not subject to review by a court or tribunal within the
EU’s judicial system. Here, Romania has not shown that the concern that animated Achmea—the
un-reviewability of an arbitral tribunal’s determination of EU law by an EU court—is present in
this case. The court so concludes for three reasons.
First, the facts here are materially different than Achmea. The applicability of EU law to
the dispute in Achmea was clear, as both the challenged government action occurred, and the
arbitration proceeding therefore commenced, after the Slovak Republic entered the EU. See ¶¶ 6,
8, 9. Here, on the other hand, all key events to the parties’ dispute occurred before Romania
acceded to the EU on January 1, 2007. See General Court Decision ¶ 13. The Sweden-Romania
BIT entered into force nearly four years earlier on July 1, 2003. See id. ¶ 14. Romania repealed
the incentives upon which Petitioners relied in making their investments the following year, in
19
August 2004. See id. ¶ 12. That revocation took legal effect on February 22, 2005, see id., thereby
“giving rise to the damage for which the compensation at issue was awarded,” id. ¶ 72. And, five
months later, on July 28, 2005, Petitioners invoked their right to convene an ICSID arbitral tribunal
pursuant to Article 7 of the BIT. See id. ¶ 15. Thus, unlike in Achmea, in which the contested
government action occurred when the Slovak Republic was already an EU Member State and
governed by EU law, Romania’s challenged actions occurred when it remained outside the EU and
subject, at least primarily, to its own domestic law. 8
Second, a close inspection of the Final Decision shows that the dispute before the ICSID
arbitral tribunal did not “relate to the interpretation or application of EU law” in the sense that
concerned the court in Achmea. Achmea ¶ 39. Before the ICSID tribunal, Petitioners and Romania
agreed that the claims put forward were based on the Sweden-Romania BIT and that the BIT’s
“substantive rules” supplied the “applicable law.” Final Decision ¶¶ 288, 318 (“There is no dispute
among the Parties that the primary source of law for this Tribunal is the BIT itself.”). Insofar as
EU law was concerned, the tribunal held, Romania had not yet acceded to the EU at the time it
repealed the economic incentives and so “EU law was not directly applicable to Romania.”
Id. ¶ 319. The tribunal did determine, however, that “EU law forms part of the ‘factual matrix’ of
the case.” Id. ¶ 328. “The overall context of EU accession in general and the pertinent provisions
of EU law in particular may be relevant to the determination of whether, inter alia, Romania’s
8
The court uses the word “primarily” for a reason. The Commission points out that, on February 1, 1993, Romania
signed the Europe Agreement, which established an association between the EU and Romania and provided a legal
framework for the accession process. See Resp. of Amicus Curiae the European Commission to Pet.’s Notice of Suppl.
Authority, ECF No. 76 [hereinafter EC Resp. to Suppl. Authority], at 7 n.; Final Decision ¶ 179. The Europe
Agreement came into force on February 1, 1995, long before the dispute at issue here arose. Final Decision ¶ 185.
According to the Commission, the Europe Agreement “forms part of E.U. law.” EC Resp. to Suppl. Authority at 7 n.
The suggestion is that, because Romania was subject to the Europe Agreement, the arbitral tribunal passed on
questions of European law. But, as discussed below, although the tribunal considered EU law as part of its decision-
making, it did not make the kind of pronouncements about EU law that would invite the type of autonomy concerns
expressed in Achmea.
20
actions were reasonable in light of all the circumstances, or whether Claimants’ expectations were
legitimate.” Id. Thus, in resolving the dispute before it, the ICSID arbitral tribunal considered EU
law, but it did so for factual context, not as a source of controlling law. Indeed, the tribunal
expressly passed on deciding whether “any payment of compensation arising out of this Award
would constitute illegal state aid under EU law and render the Award unenforceable within the
EU.” Id. ¶¶ 330, 340. The tribunal therefore did not decide a question of EU law in a way that
implicates the core rationale of Achmea. See Achmea ¶ 58 (expressing concern that an arbitral
tribunal’s application or interpretation of EU law would “call into question not only the principle
of mutual trust between the Member States but also the preservation of the particular nature of the
law established by the [governing EU] Treaties”).
Finally, the General Court’s ruling overturning the State Aid Decision confirms that the
ICSID arbitral tribunal did not tread upon substantive EU law and, for that reason, Achmea does
not affect the Award’s validity. The General Court held that “EU law became applicable in
Romania only as from its accession to the European Union on 1 January 2007.” General Court
Decision ¶ 67. It found that the events giving rise to the Award occurred before January 1, 2007,
and that “the arbitral tribunal confined itself to determining the exact damage suffered by the
applicants on the basis of the infringements committed by Romania in 2005.” Id. ¶ 77. The
Commission thus lacked the competence to review Romania’s pre-accession actions and the
Award’s compatibility with EU state aid law. See id. ¶ 86. Based on these determinations, the
General Court distinguished the present case from Achmea: “[I]t must be pointed out that, in the
present case, the arbitral tribunal was not bound to apply EU law to events occurring prior to the
accession before it, unlike the situation in the case which gave rise to the judgment of 6 March
2018, Achmea (C-284/16, EU:C:2018:158, paragraphs 38 to 41).” Id. ¶ 87. Romania fails to
21
acknowledge this key passage in the General Court’s ruling. See Resp’t Resp. to Pet’rs Notice of
Suppl. Authority, ECF No. 79 [hereinafter Resp’t Resp. to Suppl. Authority], at 5–6. The General
Court’s ruling therefore explicitly refutes Romania’s position that the CJEU’s decision in Achmea
nullified the arbitration agreement contained in the Sweden-Romania BIT.
Accordingly, this court possesses subject matter jurisdiction over this matter under the
FSIA’s arbitration exception.
B. The Act of State and Foreign Sovereign Compulsion Doctrines
Having satisfied itself of jurisdiction, the court turns to Romania’s other arguments.
Romania contends that two related doctrines—the act of state and foreign sovereign compulsion
doctrines—require the court to reject confirming the Award and to dismiss the Petition. See Resp’t
Opp’n at 25–30. The Commission supports Romania’s position. See EC Amicus Br. at 18–22.
Under the act of state doctrine, “the courts of one state will not question the validity of public acts
(acts jure imperii) performed by other sovereigns within their own borders, even when such courts
have jurisdiction over a controversy.” Republic of Austria v. Altmann, 541 U.S. 677, 700 (2004).
Similarly, the foreign sovereign compulsion doctrine “shields from . . . liability the acts of parties
carried out in obedience to the mandate of a foreign government.” See Mannington Mills, Inc. v.
Congoleum Corp., 595 F.2d 1287, 1293 (3d Cir. 1979). The court accepts, for present purposes,
that the Commission qualifies as a “sovereign” under these doctrines. Cf. European Cmty. v. RJR
Nabisco, Inc., 764 F.3d 129, 144 (2d Cir. 2014), rev’d and remanded on other grounds, 136 S. Ct.
2090, 195 L. Ed. 2d 476 (2016) (holding that the European Community “is an organ of a foreign
state” for purposes of the FSIA).
The original rationale for invoking these doctrines has been overtaken by events. Romania,
at first, argued that the State Aid Decision required the court to deny relief. See Resp’t Opp’n at
22
25–30. But the General Court’s decision then “annulled” the State Aid Decision. General Court
Decision ¶ 111. Following this development, Romania pivoted and asserted that, notwithstanding
the General Court’s ruling, the doctrines still require not confirming the Award, because
Petitioners never challenged either the Commission’s decision to open a state aid investigation
against Romania or the suspension injunction issued during the investigation. See Resp’t Resp. to
Suppl. Authority at 6. Because the General Court’s decision does not purport to affect these
“preparatory acts,” Romania claims, it remains barred under EU law from paying any portion of
the Award. Therefore, the act of state and foreign sovereign compulsion doctrines carry the same
force and effect as they did before the General Court’s ruling. See id. Romania cites no more than
a single case—Spain v. Commission, Case C-415/96, ECLI:EU:C:1998:533—to support its
position, Resp’t Resp. to Suppl. Authority at 6.
Petitioners answer Romania by submitting a declaration on EU law from Sir Nicholas
Forwood Q.C., a barrister of the Bars of England and Wales and of Ireland. See Pet’rs Reply in
Support of Suppl. Authority, ECF No. 82, Decl. of Sir Nicholas Forwood, ECF No. 82-1. Forwood
explains that in his view of EU law, when, as here, a Commission ruling is declared void, the
Commission “cannot take any steps that would be incompatible with the Court’s findings,” and
must in fact “take account of the grounds of the judgment which have [led] to the finding of
illegality.” Id. ¶¶ 13–14. Applying that principle here, Forwood posits, the General Court’s
decision not only directly annulled the State Aid Decision, but by its rationale it also makes
“untenable” the view that the decision to open the investigation and the suspension injunction
remain effective. Id. ¶ 16. The General Court’s decision was premised on the legal determination
that Romania was not subject to EU law until it acceded to the EU and therefore the Commission
lacked the “competence” to declare payment of the Award to be unlawful state aid. See id. ¶ 15.
23
By that logic, Forwood explains, the Commission also lacks the “competence” to open an
investigation or to issue a suspension injunction with regard to Romania’s acts that are not subject
to EU law. See id. ¶¶ 17–19. So, in his view, by virtue of the General Court’s ruling, neither the
decision to open the investigation nor the suspension injunction bars Romania from making
payment on the Award.
The court finds Forwood’s interpretation of EU law persuasive. The authority that
Forwood relies upon for the proposition that the “Commission must take account of the grounds
of the judgment which have [led] to the finding of illegality” is Société Nationale Maritime Corse
Méditerranée (SNCM), Case T-1/15, ECLI:EU:T:2017:470. Id. ¶ 14. In that case, a General Court
acknowledged that, under EU law,
annulment of a Community act does not necessarily affect
preparatory acts. The annulment of an act terminating an
administrative procedure consisting of different phases does not
necessarily entail the annulment of the entire procedure prior to the
adoption of the contested act, regardless of the grounds, the
substance or the procedure, the annulment judgment.
SNCM ¶ 66. 9 Yet, the court also stated that, “[i]n order to comply with a judgment of annulment
and to give it full effect, the institutions are required to respect not only the operative part of the
judgment but also the reasons which led to it and which constitute its support necessary, in that
they are indispensable for determining the exact meaning of what has been judged in the device.”
Id. ¶ 64. As Forwood correctly notes, taking account of the reasons for the General Court’s
judgment means that the Commission’s “preparatory acts” in this case are equally as invalid as the
final State Aid Decision. Again, the logic of the General Court’s decision is that Romania was not
subject to EU law at the time it repealed the economic incentives and therefore an Award intended
9
Available at https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:62015TJ0001 (English translation
electronically generated).
24
to remedy that harm cannot be incompatible with EU state aid rules, as those rules did not apply
at the relevant time. The same logic applies to the Commission’s acts of opening an investigation
and issuing the suspension injunction. They, too, were premised on the Commission’s belief that
it had the authority to scrutinize Romania’s actions under EU law. The General Court’s decision
makes clear that the Commission lacked the power to undertake even such preparatory steps. The
court therefore finds that, as a consequence of the General Court’s decision, the Commission’s
preparatory acts of opening an investigation and issuing a suspension injunction do not bar
Romania’s payment of the Award.
The sole decision upon which Romania relies—Spain v. Commission 10—is not to the
contrary. There, the court said that the “annulment of a Community measure does not necessarily
affect the preparatory acts.” Spain ¶ 32 (emphasis added). The court annulled the Commission’s
decision in Spain because the Commission had not fully analyzed the matter before it in the manner
required by EU law. The court did not, however, foreclose the Commission from correcting its
error. Instead, because the reliability of the Commission’s findings were not challenged, the court
left it open for the Commission to resume its inquiry. See id. ¶ 34. In other words, the Commission
was permitted to pick up from the point of error, leaving the preparatory acts intact. See id. ¶¶ 33–
34. This case, obviously, is quite different than Spain. Here, the Commission lacked
“competence” from the start to investigate a state aid violation by Romania because Romania’s
disputed acts all took place before it acceded to the EU. The decision to open the investigation
and the suspension injunction were as beyond the Commission’s competence as the final State Aid
Decision. So, the Commission cannot now simply pick up where it left off, as was the case in
Spain. Accordingly, there is no extant sovereign act that Romania would risk defying if it were
10
Available at https://perma.cc/JA7U-V8K2.
25
ordered to pay the Award. The court thus finds that Romania has not made a sufficient showing
that either the act of state or foreign sovereign compulsion doctrine forecloses confirming the
Award.
For its part, the Commission, which has appealed the General Court’s decision, see EC Not.
of Suppl. Authority, points out that the General Court’s decision is “merely a judgment of the
lower of two courts in the EU judicial system” and is thus subject to reversal, see EC Resp. to
Suppl. Authority at 4. That may be, but this court’s task is simply to consider whether to grant the
pending petition and convert the Award to a judgment under § 1650a based on the legal landscape
as it presently stands. As the Second Circuit has explained, the text of § 1650a “suggest[s] an
expectation” on the part of Congress “that actions to enforce ICSID awards would not be
protracted.” Mobil Cerro Negro, 863 F.3d at 121; id. at 117 (“Litigation on actions to enforce
awards need not be protracted.”). Nearly six years have passed since the ISCID tribunal entered
the Award for Petitioners, and almost two years have elapsed since Petitioners re-initiated these
enforcement proceedings. Moreover, the Commission in taking an appeal to the CJEU did not
seek to suspend the General Court’s decision pending appeal. See Pet’rs Resp. to European
Comm’n’s Not. of Suppl. Authority, ECF No. 85. The court is not prepared to delay confirmation
any longer based on the mere possibility that the CJEU, at some undefined time in the future, might
reverse the General Court’s decision.
C. Romania’s Claimed Satisfaction of the Award
Romania’s final argument is that the court should deny the Petition because it has satisfied
the Award in full. See Resp’t Opp’n at 17–25; Resp’t Mot. to Stay at 7–11. Romania contends
that it has done so through a series of tax setoffs and forced executions on accounts held by the
26
Romanian Ministry of Public Finance, and that the court must recognize the validity and effect of
these actions taken under Romanian law. See Resp’t Opp’n at 19–25.
As a threshold matter, Petitioners contend that, in these proceedings, the court cannot
consider Romania’s argument that it has satisfied the Award. See Pet’rs Mem. in Support of Pet’rs
Mot. [hereinafter Pet’rs Mem.], ECF No. 55-1, at 16–18. Petitioners insist that “Romania’s
contention that it has ‘satisfied’ the Award is no defense to the confirmation of a binding, final
ICSID Award.” Id. at 18. That assertion is wrong. It rests on the mistaken understanding that,
under § 1650a, there is a “confirmation” proceeding that is separate and distinct from an
enforcement proceeding. There is not. See supra n.1. Section 1650a speaks only of “enforcement”
of an ICSID award. See Mobil Cerro Negro, 863 F.3d at 118 n.18; Micula I, 104 F. Supp. 3d at
49. In such a proceeding, the defense of setoff or satisfaction is available. See Mobil Cerro Negro,
863 F.3d at 121 (identifying as a defense in a proceeding under § 1650a the “possibility that an
offset might apply to the award that would make execution in the full amount improper”); see also
Restatement (Second) of Conflict of Laws § 116 (1971) (“A judgment will not be enforced in other
states if the judgment has been discharged by payment or otherwise under the local law of the state
of rendition.”).
A second threshold consideration concerns the choice of law. What law must the court
apply in deciding whether a claimed payment actually discharges the Award? Neither side
meaningfully addresses this issue. Romania assumes that its domestic law applies. See Resp’t
Opp’n at 18–20. Petitioners cite District of Columbia law for general legal principles, see Pet’rs
Mem. at 18, but do not squarely challenge Romania’s assertion that Romanian law controls the
legal effect of its claimed payments, see id. at 18–24. The court therefore assumes that the law of
Romania governs whether a claimed payment satisfies a portion of the Award.
27
With these threshold matters resolved, the court turns to Romania’s arguments on the
merits. Romania first claims that a “de jure offset” occurred between Romania and Petitioner
European Food on December 11, 2013. See Resp’t Opp’n at 17. On January 14 and 15, 2014, the
Romanian Ministry of Finance issued setoff decisions in the amount of RON 337,492,864 (EUR
76 million) against tax debts owed by European Foods to Romania. Id. Romania asserts that,
“[u]nder Romanian law, the satisfaction of the Award, occurred when the conditions for the legal
setoff were met: the first date that European Food owed back taxes and when it, and the other
Petitioners, won the Award in arbitration, December 11, 2013.” Id. But Romania fails to
acknowledge that a Romanian court declared the asserted tax setoffs to be unlawful under
Romanian law. See Decl. of Oana Popa, ECF No. 55-12, ¶¶ 15–16 and Ex. L, ECF No. 55-24.
The Romanian court reasoned that the setoff violated Romanian law because (1) the setoff law
relied upon by the Romanian finance authorities can be used to offset the state’s fiscal obligations,
but not civil liabilities, such as the Award, and (2) the setoff improperly applied only to one of the
Petitioners, European Foods, and not the others. See id. Apparently, Romania appealed the court’s
ruling, but the appeal was stayed pending the outcome of the General Court review of the State
Aid Decision. See Popa Decl. ¶ 17. The parties have not alerted this court of any developments
related to the stayed appeal since the General Court issued its decision. With the claimed tax
setoffs at present annulled, Romania cannot rely on them to satisfy the Award. 11
Next, Romania asserts that, on March 9, 2015, the Romanian Ministry of Public Finance
transferred RON 472,788,675 (EUR 106.5 million) into a specially created, legislatively
authorized Treasury account in Petitioners’ names to satisfy the Award. See Resp’t Opp’n at 21.
11
Petitioners also respond to various assertions made by Romania’s Romanian law expert, Professor Radu Bufan,
concerning the legal effect of the Romanian court’s decision. See Pet’rs Mem. at 20–22. But because Romania itself
does not advance those arguments in its legal briefs, the court does not consider them.
28
But as Petitioners point out, and Romania does not dispute, Romania actually controlled the
account, Petitioners never had access to it, and Romania subsequently withdrew the funds from
the account after the State Aid Decision. See Popa Decl. ¶¶ 23–25. Petitioners therefore have not
received any of the money from the Treasury account in satisfaction of the Award. Under
Romanian law, absent actual receipt of payment, a judgment is not deemed satisfied. See Popa
Decl., Ex. O, Legal Op. of Adriana Almasan, ECF No. 55-27, ¶¶ 11–17. The funds transferred on
March 9, 2015, therefore cannot be applied against the Award.
The last set of payments Romania identifies as satisfying the Award are certain seizures of
funds from the Romanian Ministry of Public Finance’s account. See Resp’t Opp’n at 20.
Petitioners do not dispute that they have received some money from Romania through these forced
executions and that such sums are appropriately offset against the Award. See Pet’rs Mem. at 26.
Petitioners estimate the total amount obtained to be slightly more than $11.2 million. See id. This
amount therefore is properly reduced from the final judgment.
Before concluding, the court addresses a handful of other arguments that Romania makes
concerning satisfaction of the Award. First, Romania contends that the General Court’s decision
“acknowledges that Romania has paid the Award.” Resp’t Resp. to Suppl. Authority at 2. The
General Court did no such thing. The paragraphs that Romania cites from the General Court’s
decision—paragraphs 78, 80, and 82, see Resp’t Resp. to Suppl. Authority at 2—merely refer to
historic events leading up to the court’s ruling. The General Court nowhere acknowledged that
Romania had satisfied the Award.
Romania also contends that the court should not convert the Award into a judgment,
because the General Court’s decision “creates confusion as to the amount of the Award that
qualifies as state aid, and any amount Romania had the right to recoup per the Decision.” Id. at 3.
29
The argument is premised on a suggestion made by the General Court that some portion of the
Award might be subject to EU state aid rules because it constitutes compensation for the period
after Romania’s accession to the EU, when no one disputes it was subject to EU law. See id. at 3–
4. The General Court, however, declined to make any division of the Award, because “the
Commission did not draw a distinction between the periods of compensation for the damage
suffered by the applicants before or after accession.” General Court Decision ¶ 91. In other words,
the Commission forfeited any such argument. Romania cannot convert the General Court’s non-
holding into a basis to decline to confirm the Award. The contention that some portion of the
Award violates EU law goes to the merits of the ICSID panel’s determination. That argument
must be taken to the ICSID arbitral panel, and it is not a valid ground on which to reject converting
the Award in full to a judgment. See Convention art. 53 (“The award shall be binding on the
parties and shall not be subject to any appeal or to any other remedy except those provided for in
this Convention.”).
Finally, Romania claims that the doctrine of international comity requires the court to
recognize that Romania has fully satisfied the Award. See Resp’t Resp. to Suppl. Authority at 7.
But international comity concerns play no role here. See Société Nationale Industrielle
Aérospatiale v. U.S. District Court for the Southern District of Iowa, 482 U.S. 522, 543 n.27 (1987)
(“Comity refers to the spirit of cooperation in which a domestic tribunal approaches the resolution
of cases touching the laws and interests of other sovereign states.”). At Romania’s suggestion, the
court has applied Romanian law to assess whether Romania has satisfied the Award. It has not.
Accordingly, international comity provides no ground to decline to enforce the Award.
30
V. CONCLUSION AND ORDER
For the foregoing reasons, the court grants the Petition to Confirm Arbitration Award,
ECF No. 1, as well as Petitioners’ Motion for Judgment on the Pleadings, ECF No. 55.
It is further ordered that judgment shall be entered in favor of Petitioners and against
Romania in the amount of $331,557,687, 12 which reflects the sum total of the Award net payments
made by Romania, in addition to pre-judgment interest as of November 2, 2018, at the rate
identified in the Award. See Pet’rs Mem. at 13–15 (setting forth calculations for final judgment).
Petitioners shall submit by September 18, 2019, a draft Final Judgment that reflects the
foregoing amount plus all additional prejudgment interest accrued between November 3, 2018,
and September 18, 2019.
Dated: September 11, 2019 Amit P. Mehta
United States District Court Judge
12
Petitioners asked the court to convert the Award to U.S. Dollars as of the date of the Award. See Pet’rs Mem. at
11–12. Romania has not objected to that request. In any event, conversion of ICSID awards is the norm in proceedings
under § 1650a. See Belize Bank Ltd. v. Gov’t of Belize, 191 F. Supp. 3d 26, 39–40 (D.D.C. 2016).
31