UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLUMBIA
WATERKEEPER ALLIANCE, INC., et al.,
Plaintiffs,
v. Civil Action No. 18-2230 (JDB)
ANDREW WHEELER, Acting Administrator,
U.S. Environmental Protection Agency, et al.,
Defendants.
MEMORANDUM OPINION
Three environmental groups challenge EPA’s approval of an Oklahoma program
regulating the disposal of coal combustion residuals (“coal residuals” or “coal ash”). Plaintiffs
bring two sets of claims: first, a citizen suit alleging that EPA failed to perform its statutory duty
to develop and publish minimum guidelines for public participation in the program’s approval;
and second, claims under the Administrative Procedure Act (“APA”) alleging that EPA’s approval
of the program was arbitrary, capricious, or otherwise unlawful. The State of Oklahoma, as well
as various utility companies, moved to intervene to defend EPA’s approval of the program, and
the Court granted their motions. Before the Court are plaintiffs’ motion for summary judgment
and defendants’ and intervenors’ cross-motions for summary judgment. For the reasons stated
herein, the Court will grant in part and deny in part each of the parties’ motions, granting summary
judgment for defendants and intervenors on all but one claim.
BACKGROUND
A. Statutory and Regulatory Landscape
In 1976, Congress passed and President Ford signed into law the Resource Conservation
and Recovery Act of 1976 (“RCRA”), Pub. L. 94-580, 90 Stat. 2795 (codified at 42 U.S.C. § 6901),
1
as an amendment to the Solid Waste Disposal Act, Pub. L. No. 89-272, 79 Stat. 992 (1965). RCRA
established a comprehensive framework for regulating the treatment, storage, and disposal of
hazardous and non-hazardous waste. See Util. Solid Waste Activities Grp. v. EPA, 901 F.3d 414,
420 (D.C. Cir. 2018) (per curiam) [hereinafter USWAG].
Subtitle D of RCRA “calls on the EPA to promulgate criteria distinguishing ‘sanitary
landfills,’ which are permissible under the statute, from ‘open dumps,’ which are prohibited.” Id.
(quoting 42 U.S.C. § 6944(a)). In 2015, EPA promulgated federal regulations governing disposal
of coal residuals under Subtitle D. See Hazardous and Solid Waste Management System: Disposal
of Coal Combustion Residuals from Electric Utilities (“2015 Rule”), 80 Fed. Reg. 21,302 (Apr.
17, 2015) (codified at 40 C.F.R. § 257.50). Coal residuals, or coal ash, “are generated from the
combustion of coal . . . for the purpose of generating steam for powering a generator.” See
Oklahoma: Approval of State Coal Combustion Residuals Permit Program (“Final
Authorization”), 83 Fed. Reg. 30,356, 30,356 (June 28, 2018). Although coal residuals may be
put to beneficial use, many are shipped to off-site disposal facilities like landfills or surface
impoundments. Id.
In 2016, Congress passed the Water Infrastructure Improvements for the Nation Act
(“WIIN Act”), Pub. L. No. 114-322, 130 Stat. 1628 (2016) (codified at 42 U.S.C. § 6945(d)). The
WIIN Act “amended RCRA . . . to allow the EPA to approve State permitting programs ‘to operate
in lieu of [EPA’s federal] regulation of coal . . . residuals units in the State,’ provided those
programs are at least as environmentally protective as the existing (or successor) EPA regulations.”
USWAG, 901 F.3d at 426 (quoting 42 U.S.C. § 6945(d)(1)(A)). EPA issued non-binding guidance
“as a technical resource to States that may be useful in developing and submitting a State Coal
Combustion Residuals . . . Permit Program to EPA for approval.” See U.S. Envtl. Prot. Agency,
2
EPA-HQ-OLEM-2017-0613-0006, Coal Combustion Residuals State Permit Program Guidance
Document; Interim Final, (“Interim Final Guidance”) at ii (Aug. 2017). The Guidance Document
encourages States to include in their applications a description of their “public participation
procedures for permit issuance and post-permit actions,” and notes that “EPA . . . believes that an
adequate permit program provides for public participation.” Id. at 2-3.
In August 2018, the D.C. Circuit vacated and remanded parts of the 2015 Rule, holding
inter alia that “EPA acted arbitrarily and capriciously and contrary to RCRA in failing to require
the closure of unlined surface impoundments.” USWAG, 901 F.3d at 449. Such unlined
impoundments, the court determined, failed to meet “RCRA’s baseline requirement that any solid
waste disposal site pose ‘no reasonable probability of adverse effects on health or the
environment.’” Id. at 427 (quoting 42 U.S.C. § 6944(a)). The court vacated and remanded that
provision, along with two others that it determined were arbitrary and capricious. Id. at 449.
B. Oklahoma’s Program
Oklahoma developed and submitted a proposed permitting program under the amended
RCRA on August 3, 2017. See Final Authorization, 83 Fed. Reg. at 30,357. On January 18, 2018,
EPA proposed approval of Oklahoma’s program by notice in the Federal Register. See Oklahoma:
Approval of State Coal Combustion Residuals State Permit Program, 83 Fed. Reg. 2100 (Jan. 16,
2018). Waterkeeper submitted comments opposing the approval. See Earthjustice, Grand
Riverkeeper, LEAD Agency, Sierra Club, Tar Creekkeeper, and Waterkeeper Alliance, Comment
Letter on Oklahoma: Approval of State Coal Combustion Residuals State Permit Program
(“Environmental Comments”) at 20–22, 28–32, 35–36, 41–43 (Mar. 19, 2018),
https://www.regulations.gov/document?D=EPA-HQ-OLEM-2017-0613-0044. EPA then
approved Oklahoma’s program on June 28, 2018, with an effective date of July 30, 2018. See
3
Final Authorization, 83 Fed. Reg. at 30,356. Oklahoma codified those regulations in law. See
Okla. Admin. Code § 252:517-1-1.
C. Procedural History
Waterkeeper filed its complaint on September 26, 2018. Compl. for Declaratory &
Injunctive Relief (“Compl.”) [ECF No. 1]. It brought two types of claims against EPA. Count 1,
under the citizen-suit provision of RCRA, claims that EPA failed to perform a nondiscretionary
statutory duty under RCRA, codified at 42 U.S.C. § 6974(b)(1), to develop and publish minimum
guidelines for public participation in the design, implementation, and approval of state CCR
programs. See Compl. ¶¶ 64–72. Waterkeeper’s second set of claims, brought under the APA and
set forth in Counts 2 through 7, alleges that EPA’s approval is invalid because (1) it permits the
continued use of unlined impoundments, which the D.C. Circuit determined to be unlawful in
USWAG, id. ¶¶ 73–78; (2) EPA failed to perform its duty to publish guidelines for public
participation under 42 U.S.C. § 6974(b)(1), id. ¶¶ 79–88; (3) EPA’s approval of the Oklahoma
program is inconsistent with the WIIN Act because the Oklahoma program provides for “permits
for life,” id. ¶¶ 89–98; and (4) EPA failed to respond adequately to two comments raised during
the administrative process, id. ¶¶ 99–113.
The Oklahoma Gas and Electric Company (“OG&E”), the State of Oklahoma and the
Oklahoma Department of Environmental Quality (“Oklahoma”), and the Public Service Company
of Oklahoma (“PSO”) and the Utility Solid Waste Activities Group (“USWAG”) moved to
intervene. See Mem. in Supp. of Mot. of OG&E to Intervene [ECF No. 12-2] (“OG&E Mot.”);
Mem. in Supp. of Mot. of USWAG and PSO to Intervene [ECF No. 18-2] (“USWAG & PSO
Mot.”); The State of Oklahoma’s Mot. to Intervene [ECF No. 14] (“Okla. Mot.”). USWAG is an
electric utility association that represents over 150 electric utilities, including PSO, and OG&E
4
and PSO are electric utility companies with coal residuals facilities in Oklahoma. See OG&E Mot.
at 1; USWAG & PSO Mot. at 2–3. The Court granted the three motions to intervene but cabined
intervenors’ argument “to the existing claims in this action.” Waterkeeper All., Inc. v. Wheeler,
330 F.R.D. 1, 10 (D.D.C. 2018).
On March 15, 2019, Waterkeeper moved for summary judgment. Mot. of Pls. Waterkeeper
Alliance, Inc., LEAD Agency, Inc., & Sierra Club for Summ. J., and Mem. in Supp. (“Pls.’ Mem.”)
[ECF No. 42]. EPA and intervenors each filed a cross-motion for summary judgment. Defs.’
Cross-Mot. for Summ. J. & Resp. in Opp’n to Pls.’ Mot. for Summ. J. (“Defs.’ Opp’n”) [ECF No.
45]; Defs.-Intervenors’ Cross-Mot. for Summ. J. & Resp. to Pls.’ Mot. for Summ. J. (“Intervenors’
Opp’n”) [ECF No. 48]. The motions are fully briefed and ripe for resolution.
LEGAL STANDARD
Summary judgment is appropriate when “there is no genuine dispute as to any material fact
and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “[A] party
seeking summary judgment always bears the initial responsibility of informing the district court
of the basis for its motion, and identifying those portions of ‘the pleadings, depositions, answers
to interrogatories, and admissions on file, together with the affidavits, if any,’ which it believes
demonstrate the absence of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477 U.S.
317, 323 (1986). When considering a motion for summary judgment, “[t]he evidence of the non-
movant is to be believed, and all justifiable inferences are to be drawn in his favor.” Anderson v.
Liberty Lobby, Inc., 477 U.S. 242, 255 (1986).
“[W]hen a party seeks review of agency action under the APA, the district judge sits as an
appellate tribunal.” Am. Bioscience, Inc. v. Thompson, 269 F.3d 1077, 1083 (D.C. Cir. 2001).
While courts will usually review cross-motions for summary judgment “with an eye toward finding
5
genuine dispute[s] as to any material fact[s] that might make summary judgment inappropriate,”
the function of the district court under APA review “is to determine whether or not as a matter of
law the evidence in the administrative record permitted the agency to make the decision it did.”
Ass’n of Private Sector Colls. & Univs. v. Duncan, 110 F. Supp. 3d 176, 184 (D.D.C. 2015)
(internal quotation marks omitted), aff’d, 640 Fed. App’x 5 (D.C. Cir. 2016). “And that question
of law is: based on the record, did the agency act in an ‘arbitrary’ or ‘capricious’ manner or
otherwise violate the law?” Id. The Court must “hold unlawful and set aside agency action,
findings, and conclusions found to be . . . arbitrary, capricious, an abuse of discretion, or otherwise
not in accordance with law.” 5 U.S.C. § 706(2)(A).
ANALYSIS
I. Citizen Suit
In assessing a citizen suit, “[t]he court has jurisdiction only if the EPA has failed to fulfill
a nondiscretionary duty.” Defs. of Wildlife v. Jackson, 284 F.R.D. 1, 4 (D.D.C. 2012). A
“nondiscretionary duty” is an obligation whose requirements, such as the deadline for completion,
are clearly set forth by law and not left to the discretion of an agency. See, e.g., Zook v. EPA, 611
Fed. App’x 725, 726 (D.C. Cir. 2015) (per curiam) (“An individual may bring an action against
the EPA Administrator under the Clean Air Act’s citizen-suit provision ‘where there is alleged a
failure of the Administrator to perform any act or duty under [the Act] which is not discretionary
with the Administrator.’” (quoting 42 U.S.C. § 7604(a)(2)).
Waterkeeper argues that EPA has failed to satisfy its statutory duty under 42 U.S.C.
§ 6974(b)(1) to publish minimum guidelines for public participation in state coal residuals
programs. Pls.’ Mem. at 22–26. Waterkeeper contends that “EPA’s failure to discharge its
nondiscretionary duty . . . is in derogation of public participation rights” and necessitates
6
invalidating the Final Program Approval as a matter of law. Id. at 21, 25.
EPA responds that the language of § 6974(b)(1) does not set out a nondiscretionary duty
to establish guidelines for public participation before approving state coal residuals programs;
rather, the statute affords EPA discretion in when and how to implement this requirement. Defs.’
Opp’n at 8–10. In order to bring suit under the RCRA citizen-suit provision, EPA contends,
plaintiffs “must identify a date-certain deadline for EPA to act.” Id. at 8. For this proposition,
EPA cites case law explaining the requirements for bringing suit under the identically worded
citizen-suit provision of the Clean Air Act. Id. at 8. Compare 42 U.S.C. § 6972(a)(2) (allowing
suit, under RCRA, “where there is alleged a failure of the Administrator to perform any act or duty
under this chapter which is not discretionary with the Administrator”), with 42 U.S.C. § 7604(a)(2)
(allowing suit, under the Clean Water Act, “where there is alleged a failure of the Administrator
to perform any act or duty under this chapter which is not discretionary with the Administrator”).
In one of the cases cited, Sierra Club v. Thomas, 828 F.2d 783 (D.C. Cir. 1987), the D.C. Circuit
held that, “[i]n order to impose a clear-cut nondiscretionary duty” of timeliness, the Clean Air Act
needed to “categorically mandat[e] that all specified action be taken by a date-certain deadline,”
id. at 791 (internal quotation marks omitted) (alteration in original).
The Court is persuaded that the Clean Air Act cases are sufficiently analogous to the
present case to provide persuasive authority. As EPA notes, § 6974(b)(1) contains no apparent
dates or timelines for action:
Public participation in the development, revision, implementation, and enforcement
of any regulation, guideline, information, or program under this chapter shall be
provided for, encouraged, and assisted by the Administrator and the States. The
Administrator, in cooperation with the States, shall develop and publish minimum
guidelines for public participation in such processes.
42 U.S.C. § 6974(b)(1); see also Defs.’ Opp’n at 9. But the absence of specific dates is not the
7
end of the inquiry. Under Thomas, a date-certain deadline “may exist, even though not explicitly
set forth in the statute, if it is readily-ascertainable by reference to a fixed date or event,” Thomas,
828 F.2d at 791 n.58; see also Pls.’ Reply in Supp. of Mot. for Summ. J. & Opp’n to Defs.’ &
Intervenor-Defs.’ Cross-Mots. for Summ. J. (“Pls.’ Reply”) [ECF No. 49] at 2. Waterkeeper
argues that “dates certain may be clearly discernable in or inferable from the statutory scheme, and
need not be explicitly labeled as deadlines.” Pls.’ Reply at 2. RCRA sets out such a “clearly
discernable” deadline, the argument goes, by providing that EPA “‘shall develop and publish
minimum guidelines for public participation’ in the ‘development, revision, implementation, and
enforcement of any regulation, guideline, information, or program.’” Id. (quoting 42 U.S.C.
§ 6974(b) (emphasis added)).
The Court finds this reading of § 6974(b)(1) persuasive. For this provision to have any
effect, EPA must “develop and publish minimum guidelines” at least before the agency authorizes
a state program, lest they have no practical effect. At the same time, the Court faces a further
question: whether the discernable deadline established by § 6974(b)(1) and the WIIN Act is for a
state’s submission of its application to run its own permitting program or instead for EPA’s final
approval of that application. While the latter event is clearly discernable, the publication of these
guidelines seems designed not for EPA’s benefit in reviewing state applications, but for states’
advantage in formulating their applications. If states’ submissions of their applications is the
“discernible event,” however, then the mandate under § 6974(b)(1) risks again becoming rather
amorphous.
The Court need not decide this question, however, for even assuming that Waterkeeper is
correct that § 6974(b) does impose on EPA a nondiscretionary duty to issue guidelines for public
participation, EPA satisfied this requirement through its publication of Interim Final Guidance in
8
August 2017. See Release of Interim Final Guidance for State Coal Combustion Residuals Permit
Programs; Comment Request, 82 Fed. Reg. 38,685 (Aug. 15, 2017); see also Defs.’ Opp’n at 13.
Therein, EPA noted that “an adequate permit program provides for public participation by ensuring
that: (1) Documents for permit determinations are made available for public review and comment;
and (2) Final determinations on permit applications are made known to the public[; and] (3) Public
comments on permit determinations are considered.” Interim Final Guidance at 2-3.
Waterkeeper argues that this non-binding guidance does not suffice to satisfy § 6974(b)’s
requirements. According to Waterkeeper, the “mandate that EPA develop and publish guidelines
is a directive to promulgate enforceable regulations setting out minimum public participation
requirements.” Pls.’ Reply at 8 (internal quotation marks omitted). But the plain language of
§ 6974(b) does not require the promulgation of binding regulations—only the development and
publication of “minimum guidelines.” It is not as if Congress does not know how to require the
promulgation of regulations when it wants to; indeed, it explicitly did so elsewhere in RCRA, see,
e.g., 42 U.S.C. § 6942(a) (requiring EPA “by regulation [to] publish guidelines for the
identification of those areas which have common solid waste management problems”); id.
§ 6926(a) (requiring EPA to “promulgate guidelines to assist States in the Development of State
hazardous waste programs”). And § 6974(b)(1) itself distinguishes between “guidelines” and
“regulations” when it lists them separately in describing the various matters for which EPA should
promote public participation. See 42 U.S.C. § 6974(b)(1) (“any regulation, guideline, information,
or program under this chapter”); see also Defs.’ Opp’n at 11. That Congress listed both terms in
the first sentence of § 6974(b)(1) and then chose to include only “guidelines” in the second
sentence strongly suggests that it did not intend to require EPA to create more than non-binding
guidance in support of public participation. See Persinger v. Islamic Republic of Iran, 729 F.2d
9
835, 843 (D.C. Cir. 1984) (“When Congress uses explicit language in one part of a statute to cover
a particular situation and then uses different language in another part of the same statute, a strong
inference arises that the two provisions do not mean the same thing.”).
The case law bolsters this reading of § 6974(b)(1). Courts have recognized that Congress
uses particular words when referring to binding legal rules. Use of the word “promulgate” would
have suggested that EPA’s guidelines needed to be published in the Federal Register, Horsehead
Res. Dev. Co. v. EPA, 130 F.3d 1090, 1093 (D.C. Cir. 1997), and the addition of the phrase “legal
effect” would have suggested that the guidelines needed to be binding, see Brock v. Cathedral
Bluffs Shale Oil Co., 796 F.2d 533, 539 (D.C. Cir. 1986). No such words were used in the relevant
provision here, and given the exacting meaning of “regulations” in administrative law, the absence
of the term from the second sentence of § 6974(b)(1) leads the Court to conclude that the Interim
Final Guidance sufficed to satisfy any nondiscretionary obligation.1
Count 1 of the complaint, Waterkeeper’s citizen suit, thus fails, for even if § 6974(b)(1)
sets forth a nondiscretionary duty to publish public-participation guidelines, EPA has satisfied this
requirement through the publication of the Interim Final Guidance on state permitting programs.
II. APA Claims
Waterkeeper also argues that EPA’s approval of Oklahoma’s coal residuals program was
arbitrary and capricious under the APA. To that end, Waterkeeper brings six separate claims
1
EPA also argues that it independently satisfied § 6974(b) by issuing general public-participation guidelines
that establish “minimum requirements and suggested program elements for public participation in activities under
[RCRA],” 40 C.F.R. § 25.1. Defs.’ Opp’n at 14–15. This argument faces an uphill battle, however, for these
regulations do not apply to state permitting programs. See U.S. Envtl. Prot. Agency, EPA-HQ-OLEM-2017-0613-
0073, Comment Summary and Response Document: Oklahoma CCR Permit Program Approval (“Response to
Comments”) at 9 (June 2018). Moreover, the language of § 6974(b)(1) appears to require that separate guidelines be
developed and published for “any regulation, guideline, information, or program” under RCRA. 42 U.S.C.
§ 6974(b)(1); see also id. (requiring EPA to “develop and publish minimum guidelines for public participation in such
processes” (i.e. any regulation or guidelines)). Because 40 C.F.R. § 25.1 does not apply to the state programs, it
cannot suffice to fulfill this statutory requirement.
10
challenging the approval of the Oklahoma program. See Compl. ¶¶ 73–113. The Court will
address each in turn.
1. Decision in USWAG Renders Final Program Approval Invalid
Waterkeeper first argues that the Final Program Approval is invalid under RCRA because
Oklahoma’s coal residuals regulations “contain provisions nearly identical to the provisions
vacated by the D.C. Circuit” in USWAG. Pls.’ Mem. at 26; see also Compl. ¶¶ 74–78. In
USWAG, various environmental groups petitioned for review of the 2015 Final Rule setting
national minimum criteria for coal residuals disposal units. The D.C. Circuit partially vacated the
2015 Final Rule, concluding, in relevant part, that “the EPA acted arbitrarily and capriciously and
contrary to RCRA in failing to require the closure of unlined surface impoundments.” USWAG,
901 F.3d at 449. Under the 2015 Final Rule, EPA required that all new impoundments for coal
residuals be equipped with a composite lining that prevented leakage of contaminants. But the
Final Rule did not require that existing, unlined surface impoundments be retrofitted with such a
lining; rather, the Final Rule allowed such impoundments to “continue to operate until they cause
groundwater contamination.” Id. at 427. The D.C. Circuit concluded that this approach failed to
address the “health and environmental harms” of unlined impoundments that were identified in the
record, and the court therefore vacated the portion of the Final Rule allowing for the continued
operation of unlined impoundments. Id. at 429–30.
In light of this decision, Waterkeeper argues that EPA’s approval of Oklahoma’s coal
residuals program is invalid because “Oklahoma is home to several [unlined] impoundments . . . ,
and Oklahoma’s regulations will allow them to continue operating unless and until they leak.”
Pls.’ Mem. at 26. Waterkeeper argues that this setup violates the WIIN Act, under which state
coal residuals programs “must be ‘at least as protective as’” their federal analogues. Id. at 27
11
(quoting 42 U.S.C. § 6945(d)(1)(B)). Given that the D.C. Circuit ruled the 2015 Final Rule’s wait-
and-see approach to be inadequate under RCRA’s protectiveness standard, see USWAG, 901 F.3d
at 427–30 (concluding that the 2015 Final Rule failed to address RCRA’s requirement that there
be “no reasonable probability of adverse effects on health or the environment” (quoting 42 U.S.C.
§ 6944(a)), Waterkeeper contends that EPA’s approval of the Oklahoma program, which allegedly
takes the same approach, must be set aside. Pls.’ Mem. at 27–28.
EPA appears to concede that Oklahoma’s program does not comply with the requirements
for unlined impoundments established by RCRA and clarified by the D.C. Circuit in USWAG, but
nonetheless argues that “courts should allow the administrative process to play out to allow
agencies the first opportunity to address new developments,” rather than vacating the Final
Program Approval straight out. Defs.’ Opp’n at 30–31. EPA bases this argument on the statutory
structure of the WIIN Act, which requires that EPA review approved state programs within three
years of a revision to federal criteria. 42 U.S.C. § 6945(d)(1)(D)(i)(II). This three-year lag,
according to EPA, allows for a previously approved state program to update its standards and make
the necessary adjustments. Defs.’ Opp’n at 32. Given that the WIIN Act imposed a 180-day
deadline for EPA to evaluate and act on state program submissions, 42 U.S.C. § 6945(d)(1)(B),
EPA argues that it could not have waited on the outcome of any judicial review of the 2015 Final
Rule before evaluating Oklahoma’s application. Defs.’ Reply in Supp. of Cross-Mot. for Summ.
J. (“Defs.’ Reply”) [ECF No. 51] at 20. Together with the statutory framework for revising state
programs, this timeline suggests, EPA contends, that the proper method for resolving the tension
between USWAG and the Oklahoma state program is not to invalidate the latter, but rather to allow
for improvements to arise. Id.
12
The various intervenors in this action—the State of Oklahoma, Oklahoma Department of
Environmental Quality, and several industry and trade groups—echo EPA’s argument that “the
WIIN Act provides a state with the necessary time to update its CCR program to reflect subsequent
changes in federal regulations.” Intervenors’ Opp’n at 6–10. They also argue that, in the event
the Court does determine that EPA’s approval of the Oklahoma program must be invalidated under
USWAG, the agency need not invalidate the entire program, but can invalidate just the parts related
to the sections paralleling the holding of USWAG—in particular, the continued use of unlined
impoundments absent groundwater impact. Defs.-Intervenors’ Reply in Supp. of Cross-Mot. for
Summ. J. (“Intervenors’ Reply”) [ECF No. 52] at 11–12.
The Court agrees with Waterkeeper that Oklahoma’s permitting plan, as approved,
contravenes the D.C. Circuit’s holding in USWAG, but also concludes that vacating the final
approval of the Oklahoma coal residuals program outright is not necessary. Circuit precedent is
clear as to the retroactivity of court decisions:
Because the decision of an Article III court announces the law as though it were
finding it—discerning what the law is, rather than decreeing what it is changed to,
or what it will tomorrow be[—]all parties charged with applying that decision,
whether agency or court, state or federal, must treat it as if it had always been the
law.
Nat’l Fuel Gas Supply Corp. v. FERC, 59 F.3d 1281, 1289 (D.C. Cir. 1995) (internal brackets,
ellipses, citations, and quotation marks omitted). In USWAG, the D.C. Circuit confirmed that the
wait-and-see approach to unlined impoundment was contrary to RCRA, and thus vacated that
portion of the 2015 Final Rule. USWAG, 901 F.3d at 430. Presented with Oklahoma’s coal
residuals plan that permits a similar practice, see Response to Comments at 4–5, the Court must
apply “the controlling interpretation of federal law . . . in all cases still open on direct review and
as to all events, regardless of whether such events predate or postdate [the D.C. Circuit’s]
13
announcement of the rule.” Nat’l R.R. Passenger Corp. v. Fraternal Order of Police, Lodge 189,
142 F. Supp. 3d 82, 90 (D.D.C. 2015), aff’d sub nom. Nat’l R.R. Passenger Corp. v. Fraternal
Order of Police, Lodge 189 Labor Comm., 855 F.3d 335 (D.C. Cir. 2017) (quoting Harper v. Va.
Dep’t of Taxation, 509 US. 86, 97 (1993)).
EPA and intervenors argue that this approach undermines the statutory structure of RCRA
and the WIIN Act, which allow states three years to update their programs in light of changes to
federal policies. But this approach in no way reads those provisions out of the statutes or makes
them mere surplusage. Future adjustments to federal regulations will almost certainly require state
programs to adjust in turn, but that statutory structure alone does not change the reality that
Oklahoma now seeks approval of a state permitting program that includes, at least in principle, see
Response to Comments at 4–5, unlined impoundments whose continued existence without
intervention was deemed unlawful in USWAG, see 901 F.3d at 430.2
But this conclusion does not necessitate vacating the entire authorization for the Oklahoma
coal residuals program. As intervenors suggest, the WIIN Act permits partial program approval,
42 U.S.C. § 6945(d)(1)(B), and the determination that Oklahoma’s approach to monitoring unlined
impoundments is contrary to RCRA does not require invalidation of the rest of the program.
Intervenors’ Reply at 12. To that end, the Court concludes that, in line with the D.C. Circuit’s
decision in USWAG, EPA’s authorization will be partially vacated and remanded. Cf., e.g., Sierra
Club v. Van Antwerp, 719 F. Supp. 2d 77, 79–80 (D.D.C. 2010) (remanding and partially vacating
an agency action).
2
Likewise, the argument that the 180-day turnaround on approving state program applications somehow
militates against retroactive application of USWAG, see Defs.’ Reply at 20, is unpersuasive. Under this Court’s ruling
today, that timeline has continuing relevance for future applications, even if it is assumed that states that chose to
apply early may need to adjust their programs in light of judicial review of the 2015 Final Rule.
14
2. Failure to Afford Required Public Participation Opportunities
Waterkeeper next contends that EPA’s approval of Oklahoma’s coal residuals program is
unlawful because the state program fails to afford adequate public participation opportunities. Pls.’
Mem. at 28. Focusing again on 42 U.S.C. § 6974(b)(1), Waterkeeper argues that all programs
under RCRA—including state permitting programs under the WIIN Act—must include “broad
public participation opportunities in permitting, modification of permits, rulemaking, and beyond.”
Pls.’ Mem. at 28–29. Such opportunities for public engagement must be allowed, the argument
goes, both for new permits and for “significant modifications” to already issued permits. Id. at 31.
Waterkeeper claims that Oklahoma’s coal residuals program fails to provide adequate
opportunities for public participation. Id. at 32. It highlights the lack of opportunities for public
comment on so-called Tier 1 permits, or permits on “existing coal ash landfills . . . that had already
been granted permits by the state prior to EPA’s approval of” the coal residuals program. Id. In
particular, Waterkeeper takes issue with the Oklahoma Department of Environmental Quality’s
exemption of certain permit modifications from any substantive public participation. Id. at 33.
Under the Oklahoma Uniform Environmental Permitting Act, all permit applications and
modifications are classified into one of three categories based on, among other factors, the
activity’s potential impact on the environment, the amount and type of waste involved, and the
“public concern traditionally connected with the type of activity.” Final Authorization, 83 Fed.
Reg. at 30,358. Waterkeeper complains that, while Tier II and Tier III do incorporate some forms
of public participation, Tier I activities (the lowest level) do not. Pls.’ Mem. at 32–34.
Moreover, Waterkeeper argues that, even when there is some form of public review and
comment on state permits, Oklahoma “fails to ensure that that participation is meaningful.” Id. at
34. For example, Oklahoma requires that new permit applications include closure plans, which
15
are subject to public review and comment when those permits are classified as Tier II or Tier III.
See Final Authorization, 83 Fed. Reg. at 30,357, 30,363–64. But Waterkeeper complains that
permittees may modify their closure plans at any time, and such modifications are classified under
Tier I, meaning that front-end public participation can all be for naught if a permittee just modifies
its plan after initial approval. See Pls.’ Mem. at 34.
As with the citizen-suit claim, however, Waterkeeper’s argument is undermined by the
general terms of § 6974(b)(1), which affords significant discretion to EPA as to the methods by
which it can “provide[] for, encourage[], and assist[]” public participation in the state coal residuals
programs. Under such circumstances, EPA’s efforts to ensure that the Oklahoma permitting
program promotes public participation are sufficient.
To start, EPA has fulfilled whatever duty it may have to “develop and publish minimum
guidelines for public participation in” the state coal residuals programs by publishing the Interim
Final Guidance. See supra at 8–10 (citing Interim Final Guidance at 2-3). In the case of the
Oklahoma permitting program, EPA considered these guidelines as they applied to Oklahoma’s
application and assessed the various public-participation measures in Oklahoma’s permitting
programs. See Final Authorization, 83 Fed. Reg. at 30,358–59. These actions are all that is
necessary to satisfy RCRA’s public-participation requirements in approving Oklahoma’s state
program.
This Court came to the same determination in City of Dover v. EPA, 956 F. Supp. 2d 272
(D.D.C. 2013), concluding that almost identical language in the Clean Water Act afforded EPA
considerable latitude in how to promote public participation. Id. at 283.3 This Court observed
3
City of Dover concerned EPA’s duty under 33 U.S.C. § 1251(e), which reads:
Public participation in the development, revision, and enforcement of any regulation, standard,
effluent limitation, plan, or program established by the Administrator or any State under this chapter
16
that, “[a]lthough the EPA must act to promote public participation, it has vast discretion as to the
methods it uses to promote participation, and ‘a court would have no meaningful standard against
which to judge the agency’s exercise of discretion.’” Id. (quoting Heckler v. Chaney, 470 U.S.
821, 830 (1985)).
None of the cases that Waterkeeper cites to the contrary is persuasive. In Waterkeeper
Alliance, Inc. v. EPA, 399 F.3d 486 (2d Cir. 2005), the court’s conclusion that EPA violated the
Clean Water Act’s specific public-participation requirements turned not on the general language
of 33 U.S.C. § 1251(e), which is paralleled in RCRA, but on the specific requirements of 33 U.S.C.
§§ 1342(a), (b)(3), (j), which is not paralleled here. See 399 F.3d at 503. Although Waterkeeper
is correct that the Second Circuit concluded that EPA’s failure to afford public participation
opportunities violated § 1251(e), Pls.’ Reply at 11, the court’s reasoning turned “[m]ore
specifically” on the other statutory provisions, for which there is no analogue with respect to state
coal residuals programs, see Waterkeeper All., 399 F.3d at 503. Given the extent to which these
specific provisions, rather than the general admonition in § 1291(e), guided that court’s
conclusion, the decision provides little guidance.
Nor is Waterkeeper correct in describing Oklahoma’s permitting program as paying mere
“lip-service,” Citizens for a Better Env’t v. EPA, 596 F.2d 720, 726 (7th Cir. 1979), to
§ 6974(b)(1)’s directive to promote public participation. See Pls.’ Reply at 12. Under Oklahoma’s
plan, all Tier II applications require “published notice of the application filing, published notice of
the draft permit or denial, opportunity for a public meeting, and submittal of public comment.”
Final Authorization, 83 Fed. Reg. at 30,359. Tier III applications include all the requirements of
shall be provided for, encouraged, and assisted by the Administrator and the States. The
Administrator, in cooperation with the States, shall develop and publish regulations specifying
minimum guidelines for public participation in such processes.
17
Tier II, plus additional “notice of an opportunity for a process meeting (i.e. how the permit process
works).” Id. Given the wide discretion afforded by the language of § 6974(b)(1), EPA’s approval
of such measures—at least for Tiers II and III—seems well within its statutory mandate.
Despite these measures, Waterkeeper focuses on Oklahoma’s comparatively limited
opportunities for public participation in Tier I decisions and argues that later Tier-I modifications
to permits will create a loophole that effectively undermines the entire regime. See Pls.’ Mem. at
32–34. But this description mischaracterizes Oklahoma’s approach in at least two respects. First,
Tier I concerns “those things that are basically administrative decisions which can be made by a
technical supervisor,” but even so, notice must still be given to the affected landowner. See Final
Authorization, 83 Fed. Reg. at 30,358. Thus, the process is not entirely a black box. Second,
despite Waterkeeper’s assertions otherwise, see Pls.’ Mem. at 34, modifications do not necessarily
all fall under Tier I. Rather, the Final Authorization requires that such modifications be classified
based on the environmental impact of the adjustment. Final Authorization, 83 Fed. Reg. at 30,358.
As a result, if a facility applied to adjust its closure to be less protective, then such a modification
would be classified as Tier II and require public input. Id. at 30,358–59. In light of the wide
discretion afforded to EPA under § 6974(b)(1), approval of these elaborate public participation
measures as part of Oklahoma’s plan cannot be considered arbitrary or capricious.
Finally, Waterkeeper argues that EPA’s approval of Oklahoma’s coal residuals program
prior to publication of guidelines for public participation violates RCRA and renders the state
approval arbitrary and capricious. Pls.’ Mem. at 35. Drawing on the analogous regulations for
EPA approval of state hazardous waste programs, see 40 C.F.R. Part 256, Waterkeeper contends
that Oklahoma’s program is deficient for failing to require public hearings on permits of
“significant” public interest. Pls.’ Mem. at 36. But this argument fails because, as explained
18
above, RCRA does not require EPA to promulgate regulations prior to the approval of state
programs under the WIIN Act. See supra at 5–8. And insofar as any requirement does exist, EPA
has satisfied its duty by publishing minimum guidelines before approving the Oklahoma coal
residuals program. See Interim Final Guidance at 2-3. Waterkeeper’s argument from the
regulations setting out public-participation requirements for state solid waste management
programs is also unavailing because, as Waterkeeper itself acknowledges, those regulations do not
concern coal residuals programs. See Pls.’ Mem. at 36–37.
3. Illegality of “Permits for Life”
Waterkeeper’s third APA challenge concerns Oklahoma’s approval of so-called “permits
for life.” Under the WIIN Act, state coal residuals programs must be “at least as protective as”
their federal analogues to be approved by EPA. See 42 U.S.C. § 6945(d)(1)(B), (C). The federal
standards in this comparison are benchmarked, by statute, to “the applicable criteria for coal
combustion residuals units under” 40 C.F.R. Part 257. See 42 U.S.C. § 6945(d)(1)(B)(i). State
programs have an ongoing duty to satisfy this requirement, and if the federal requirements change,
EPA must review each state program within three years to confirm that it “continues to ensure that
each coal . . . residuals unit located in the State” complies. Id. at § 6945(d)(1)(D)(i)(II), (ii)(I). If
the state program fails to align its standards with the revised federal requirements, EPA must
withdraw approval of the state program until it “correct[s] the deficiencies.” Id. § 6945(d)(1)(E).
Waterkeeper argues that EPA’s approval of Oklahoma’s coal residuals program violates
these requirements by granting “permits for life,” “with no obligation to increase protections
consistent with strengthened federal or state requirements.” Pls.’ Mem. at 37–38. According to
Waterkeeper, “Oklahoma’s program freezes permits in time, holding ash dump operators only to
those standards in effect at the time of permit issuance” and not requiring further updates for
19
developments in technology or science. Id. at 38; see also Response to Comments at 12 (“With
the exception of an . . . enforcement action to revoke a facility’s permit, a facility’s permit will not
terminate until the facility successfully completes closure, post-closure and any corrective action
requirements.”). The State of Oklahoma concedes as much. Intervenors’ Opp’n at 11 (“Oklahoma
law does provide that ‘[p]ermits shall be issued for the life of the [coal residuals] unit.’” (quoting
Okla. Admin. Code § 252:517-3-1(A)). But the State emphasizes that these permits “for the life
of the [coal residuals] unit” do not give permittees carte blanche to operate their units however
they like; rather, they are the start of “a regulatory relationship.” Intervenors’ Opp’n at 10–11.
Waterkeeper’s argument fails for two reasons. First, Waterkeeper reads too much into the
WIIN Act’s requirement that the state program “be at least as protective” as its federal analogue.
42 U.S.C. § 6945(d)(1)(B). Neither the text of the WIIN Act nor EPA’s guidance on approving
state permitting programs, see Interim Final Guidance at 2-3 to -4, requires that a state pass a law
or promulgate a regulation explicitly tying its coal residuals program standards to the federal
requirements. Rather, the WIIN Act leaves the task of determining whether a state program is
adequately protective to EPA. See 42 U.S.C. § 6945(d)(1)(B). And neither the WIIN Act nor the
Interim Final Guidance explicitly forbids “permits for life.”
It also seems that the name “permits for life” suggests a more laissez-faire approach than
is actually practiced in Oklahoma. Despite describing its permits as “issued for the life of the
given [impoundment] site,” U.S. Envtl. Prot. Agency, EPA-HQ-OLME-2017-0613-0055
Oklahoma Department of Environmental Quality (ODEQ) Process Response Clarifications, at 20
(June 2018), these permits are not exempt from all future revision. Under Oklahoma law,
“permittees are subject to the laws and rules of the [Department of Environmental Quality] as they
exist on the date of filing an application and afterwards as changed.” Okla. Admin. Code § 252:4-
20
7-3. Indeed, Oklahoma has previously required exactly what Waterkeeper claims “permits for
life” prevent: the updating of existing permits based on changes to Oklahoma’s laws around coal
residuals after the federal 2015 Final Rule. See id. § 252:517-1-7(b)(2) (requiring the submission
within 180 days of a “permit modification application . . . to ensure compliance with” Oklahoma’s
coal residuals regulations). In short, although “permits for life” may ease administrative
requirements around renewing permits or the like, Oklahoma’s program nevertheless mandates
continual compliance with state regulations, which in turn must track federal standards lest the
state permitting program’s approval be withdrawn, see 42 U.S.C. § 6945(d)(1)(D).
Waterkeeper retorts that the “one-time update” after the promulgation of the state coal
residuals regulations only highlights the absence of “periodic and ongoing updates to the permits
in the future.” Pls.’ Reply at 22. But as much as Waterkeeper may wish for this fluid setup, such
an arrangement is not mandated by the WIIN Act or any binding regulations. Waterkeeper also
argues that, unless Oklahoma has the continuous “authority to impose requirements for [coal
residual] units adequate to ensure compliance with regulations at least as protective as” their
federal analogue, then EPA cannot assure itself that the approved state program is in line with
federal standards. Id. at 23–24 (internal quotation marks omitted). But, again, this reading imposes
an immediacy on state compliance with adjustments to federal standards that is not present in the
WIIN Act. Section 6945(d)(1)(B) does not index the at-least-as-protective standard to mere EPA
guidance or some mercurial body of law. Rather, it requires that state programs be at least as
protective as 40 C.F.R. Part 257. 42 U.S.C. § 6945(d)(1)(B)(i). Given the formalities required to
promulgate or adjust a regulation, the federal benchmarks here will not be fast-moving standards.
See also id. § 6912(b) (requiring EPA to “review[] and, where necessary, revise[]” its regulations
“not less frequently than every three years”). Oklahoma has also demonstrated the capacity and
21
willingness to require permit modifications when such changes do arise. See Okla. Admin. Code
§ 252:517-1-7(b)(2).
Considering the discretion that reviewing courts give to agencies’ “reasoned and rational”
choices, the Court must defer to EPA’s determination that the potential for lag does not make
Oklahoma’s program less protective than its federal analogue. See Cooper v. Nat’l Transp. Safety
Bd., 660 F.3d 476, 481 (D.C. Cir. 2011) (internal quotation omitted). The Court concludes, then,
that Oklahoma’s so-called “permits for life” are acceptable under the WIIN Act and its own
regulatory scheme for coal combustion residuals.
4. Failure to Respond to Comments
Finally, Waterkeeper brings two claims based on EPA’s alleged failure to respond to
significant comments it submitted during the notice-and-comment period. Pls.’ Mem. at 40–41;
see also Compl. ¶¶ 100–07, 109–13. Agencies have a duty to “consider and respond to significant
comments received during the period for public comment” on a proposed rule. Perez v. Mortg.
Bankers Ass’n, 135 S. Ct. 1199, 1203 (2015). “Although EPA is not required to discuss every
item of fact or opinion included in the submissions it receives in response to a Notice of Proposed
Rulemaking, it must respond to those comments which, if true, would require a change in the
proposed rule.” Genuine Parts Co. v. EPA, 890 F.3d 304, 313 (D.C. Cir. 2018) (internal quotation
marks omitted).
Waterkeeper submitted two comments. First, it argued that “EPA may not proceed with
final approval of Oklahoma’s [coal residuals] program—and should not have tentatively approved
the state’s [coal residuals] program—unless and until it promulgates formal guidelines specifying
the public participation opportunities that states must afford.” Environmental Comments at 41.
Second, Waterkeeper commented that Oklahoma’s “grant of a permit for life is not permissible
22
under the WIIN Act.” Id. at 21. Waterkeeper contends that EPA failed to address the substance
of both comments, either of “which, if true, would require a change in the proposed rule,” Genuine
Parts Co., 890 F.3d at 313 (quotation omitted).
Neither of these arguments is persuasive. Waterkeeper’s first argument is just another
repackaging of its claim in the citizen suit that EPA must first promulgate formal guidelines for
public participation in state coal residuals programs before approving state applications. As
discussed above, it is unclear whether such a requirement exists, and if it did, EPA satisfied the
need for “guidelines” through its publication of various criteria for public participation in the
Interim Final Guidance, see Interim Final Guidance at 2-3. See supra at 8–10. EPA’s response to
Waterkeeper’s comment hits on this very point, noting that the WIIN Act “does not require EPA
to promulgate regulations for determining the adequacy of state programs.” Response to
Comments at 14.
Waterkeeper argues that this response is unsatisfactorily “conclusory” and fails to provide
“a reasoned explanation for [EPA’s] decision.” Pls.’ Mem. at 42 (quoting Int’l Union, United
Mine Workers of Am. v. Mine Safety & Health Admin., 626 F.3d 84, 94 (D.C. Cir. 2010)). But,
as EPA notes, “[a]n agency’s obligation to respond . . . is not particularly demanding” Ass’n of
Private Sector Colls. & Univs. v. Duncan, 681 F.3d 427, 441 (D.C. Cir. 2012) (internal quotation
marks omitted). Rather, “the agency’s response to public comments must at least ‘enable [the
court] to see what major issues of policy were ventilated . . . and why the agency reacted to them
as it did.’” Am. Coll. of Emergency Physicians v. Price, 264 F. Supp. 3d 89, 94 (D.D.C. 2017)
(quoting Auto. Parts & Accessories Ass’n v. Boyd, 407 F.2d 330, 338 (D.C. Cir. 1968)). EPA did
just that in its response by explaining the legal basis for not promulgating regulations for public
participation in state programs. While International Union, United Mine Workers of America
23
involved an agency’s response to “a central factual dispute where there is considerable evidence
in conflict,” 626 F.3d at 94, the comment here concerned a legal question, and EPA’s response
adequately explained the agency’s reasoning.
Likewise, EPA adequately addressed Waterkeeper’s comment concerning Oklahoma’s use
of permits for life. As discussed above, Oklahoma’s “permits for life” do not contravene the WIIN
Act’s requirement that state programs be as protective of human life and the environment as their
federal analogues, and Oklahoma’s coal residuals program allows for updating such permits in line
with changes to federal standards. See supra at 19–22. EPA laid out the heart of this point in its
response, explaining that “Oklahoma’s program ensures there will be continued regulatory
oversight throughout” the life of a permit. Response to Comments at 12. Waterkeeper focuses on
the line in the response that “nothing in the Federal rule prohibits such permits,” id. (emphasis
added), and argues that EPA failed to respond to its comment, given that the agency’s actual
reasoning is based on the text of the WIIN Act. See Pls.’ Mem. at 42. Once again, however,
Waterkeeper’s critique is unpersuasive because EPA did present the core aspects of its reasoning.
That the focus of its analysis has shifted from the 2015 Final Rule to the WIIN Act does not provide
a basis for setting aside the approval of Oklahoma’s program. And even if it were an error for the
agency to have cited the “Federal rule,” rather than the WIIN Act itself, such an error was harmless;
the absence of a specific citation of the WIIN Act in EPA’s response hardly prejudiced
Waterkeeper in its challenge. See FBME Bank Ltd. v. Lew, 209 F. Supp. 3d 299, 311 (D.D.C.
2016). In sum, neither of EPA’s responses to Waterkeeper’s comments was so deficient as to
provide a basis for invalidating the state program approval.
CONCLUSION
For all the foregoing reasons, [45] EPA’s cross-motion for summary judgment and
24
[48] intervenors’ cross-motion for summary judgment will both be granted with respect to all but
Count 2 of the complaint, plaintiffs’ challenge to the lawfulness of the final authorization in light
of the D.C. Circuit’s decision in USWAG. Accordingly, [42] plaintiffs’ motion for summary
judgment will be granted with respect to Count 2 and denied with respect to all other counts. In
line with the D.C. Circuit’s decision in USWAG, EPA’s authorization will be partially vacated
and will be remanded to EPA for further consideration. A separate order will issue on this date.
/s/
JOHN D. BATES
United States District Judge
Dated: April 15, 2020
25