IN THE COMMONWEALTH COURT OF PENNSYLVANIA
PPL Electric Utilities Corporation, :
Petitioner :
: No. 624 C.D. 2019
v. :
: Argued: May 13, 2020
Public Utility Commission, :
Respondent :
BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge
HONORABLE RENÉE COHN JUBELIRER, Judge
HONORABLE P. KEVIN BROBSON, Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE ELLEN CEISLER, Judge
HONORABLE J. ANDREW CROMPTON, Judge
OPINION NOT REPORTED
MEMORANDUM OPINION
BY JUDGE McCULLOUGH FILED: October 27, 2020
PPL Electric Utilities Corporation (Utility) petitions for review from the
April 25, 2019 order of the Pennsylvania Public Utility Commission (Commission)
denying its application for approval of internal corporate restructuring pursuant to
section 1102(a)(3) of the Public Utility Code (Code), 66 Pa.C.S. §1102(a)(3),1 and the
1
This section states, in notable part, as follows:
Upon the application of any public utility and the approval of such
application by the [C]ommission, evidenced by its certificate of
public convenience first had and obtained, and upon compliance with
existing laws, it shall be lawful . . . [f]or any public utility . . . to
acquire from, or to transfer to, any person or corporation, including a
(Footnote continued on next page…)
Commission’s Statement of Policy located at 52 Pa. Code §69.901. The issues
presented are whether the proposed restructuring is one that would require a
certificate of public convenience (CPC) and, if so, what legal standard the
Commission should have utilized to determine whether to grant such a certificate.
See section 1103(a) of the Code, 66 Pa.C.S. §1103(a) (stating that the Commission
shall grant a CPC “only if the [C]ommission shall find or determine that the granting
of such certificate is necessary or proper for the service, accommodation,
convenience, or safety of the public”).2
(continued…)
municipal corporation, by any method or device whatsoever,
including the sale or transfer of stock and including a consolidation,
merger, sale or lease, the title to, or the possession or use of, any
tangible or intangible property used or useful in the public service.
66 Pa.C.S. §1102(a)(3).
2
In its relevant respects, section 1103(a) provides that
[a] certificate of public convenience shall be granted by order of the
commission, only if the [C]ommission shall find or determine that the
granting of such certificate is necessary or proper for the service,
accommodation, convenience, or safety of the public. The
commission, in granting such certificate, may impose such conditions
as it may deem to be just and reasonable. In every case, the
commission shall make a finding or determination in writing, stating
whether or not its approval is granted. Any holder of a certificate of
public convenience, exercising the authority conferred by such
certificate, shall be deemed to have waived any and all objections to
the terms and conditions of such certificate.
66 Pa.C.S. §1103(a)(3).
2
Background
The germane facts and procedural history of this case are as follows. On
October 16, 2017, Utility filed its application and on November 21, 2017, the Office
of Small Business Advocate (OSBA) filed a notice of intervention and protest,
opposing the application. Thereafter, Utility and the OSBA filed a joint stipulation
for the admission of evidence and submitted uncontested testimony and documents to
the Administrative Law Judges (ALJs), from which we glean the following pertinent
facts.
In terms of corporate structure, PPL Corporation stands at the top of the
pyramid and is the bona fide parent corporation and a pure holding company that
owns, among other things, a controlling share of stock of certain subsidiaries engaged
in the electric utility business. Utility is a direct subsidiary of PPL Corporation and is
a “public utility” as defined in section 102 of the Code, 66 Pa.C.S. §102, providing
electric service to approximately 1.4 million customers in eastern and central
Pennsylvania. PPL Corporation owns all of the shares of stock of Utility, and Utility
owns all of its operational assets. The proposed restructuring would vertically
interject two new Delaware holding companies, PPL Subsidiary Holdings, LLC
(Newco 1) and PPL Energy Holdings, LLC (Newco 2), between PPL Corporation and
Utility, thereby rendering Utility an indirect and down-the-stream subsidiary of PPL
Corporation. Meanwhile, Newco 1 would become a wholly-owned direct subsidiary
of PPL Corporation, while Newco 2 would become a wholly-owned direct subsidiary
of Newco 1. PPL Corporation would then contribute all of the interests that it owns
in Utility to Newco 1, and Newco 1, in turn, would contribute all of the shares of
Utility’s stock that it received from PPL Corporation to Newco 2. The net result
would be that, through these transactions, PPL Corporation would ultimately transfer
3
all of the shares of stock in Utility to Newco 2. As such, Newco 2 would become the
new or immediate “parent” of Utility and Utility would become a direct subsidiary of
Newco 2. (Commission’s decision at 3-6; ALJs’ decision at 1-5.)
With respect to the effect that the proposed restructuring would have on
PPL Corporation, Utility, and the public in general, PPL Corporation averred that the
general and overall purpose of the restructuring would allow PPL Corporation to
control its tax liabilities in a more prudent manner. For instance, by consolidating the
tax basis of the relevant subsidiaries within Newco 1 and Newco 2, PPL Corporation
alleged that it would be able to manage the movement of cash within its corporate
framework with increased efficiency, while, at the same time, mitigate the negative
tax impact on capital gains. PPL Corporation also stated that the restructuring would
permit it to operate its regulated businesses more effectively because intracompany
financing, including the management of Utility’s capital structure and associated
regulatory requirements, would be conducted and facilitated by and through Newco 1
and Newco 2, rather than PPL Corporation itself. In addition, PPL Corporation
asserted that the proposed restructuring would promote the public interest because it
would create an enhanced and viable method for it to distribute cash received from
Utility for purposes of funding capital expenditures and projects, and the
establishment of Newco 1 and Newco 2 would provide a flexible corporate structure
through which PPL Corporation could engage in business acquisitions, including the
combination or consolidation of existing non-regulated corporate entities. PPL
Corporation further averred that, under the proposed reorganization, it would be able
to raise equity capital at more favorable rates, which would improve Utility’s
financial condition and reduce the need for Utility to raise additional external debt.
According to PPL Corporation, the restructuring would have no adverse effect on the
4
finances, management, or operations of Utility, and Utility would maintain a separate
investment rating from credit rating agencies. (Commission’s decision at 6-7; ALJs’
decision at 18-19.)
In a decision dated August 23, 2018, the ALJs recommended that
Utility’s application be denied in its entirety. The ALJs noted that PPL Corporation
owns all of Utility’s shares of stock and that, pursuant to the proposed restructuring,
PPL Corporation would transfer these shares to Newco 1 and then, via a subsequent
transfer, to Newco 2. The ALJs reasoned that Utility’s application, in essence, sought
approval to vest a new corporate entity with a controlling interest in a public utility
and, therefore, PPL Corporation was required to meet the standards to obtain a CPC.
The ALJs further concluded that Utility and PPL Corporation failed to establish that
the proposed restructuring would result in an affirmative and substantial benefit to the
public or that it would be a necessary or proper way to further the service,
accommodation, convenience, or safety of the public. (ALJs’ decision at 14-17, 20-
21.)
On October 11, 2018, Utility filed exceptions, contending that the ALJs
erred in concluding that it was required to obtain a CPC because the proposed internal
restructuring would amount to a technical change in control, as opposed to a change
in ultimate ownership, and would have no negative effect on its management or
operations. In the alternative, Utility asserted that, even if a CPC was necessary, the
ALJs erred in applying a “substantial affirmative public benefit” standard given the
internal nature of the proposed restructuring.
5
On April 25, 2019, the Commission entered an opinion and order
dismissing the exceptions filed by Utility and denying its application for corporate
restructuring. Subsequently, Utility filed a petition for review in this Court.3, 4
Discussion
First, Utility argues that it did not need to obtain Commission approval
and a CPC under section 1102(a)(3) of the Code because the proposed restructuring
would not change the entity that would have ultimate control over the Utility, i.e.,
PPL Corporation, would not affect the management or operations of Utility, and
would not result in the transfer of title or possession of Utility’s property or
operational assets.5
Relevantly, section 1102(a)(3) of Code mandates that a corporate entity
obtain a CPC when the entity seeks “to acquire from, or to transfer to, any person or
corporation, including a municipal corporation, by any method or device
whatsoever, including the sale or transfer of stock . . . the title to, or the possession
or use of, any tangible or intangible property used or useful in the public service.”
66 Pa.C.S. §1102(a)(3) (emphasis added). A “corporation” is defined in the Code as
“[a]ll bodies corporate, joint-stock companies, or associations, domestic or foreign,
their lessees, assignees, trustees, receivers, or other successors in interest, having any
3
Our scope of review of the Commission’s order is limited to determining whether
constitutional rights were violated, whether an error of law was committed, or whether the findings,
determinations, or order are supported by substantial evidence. Regency Transportation Group,
Ltd. v. Pennsylvania Public Utility Commission, 44 A.3d 107, 110 n.3 (Pa. Cmwlth. 2012).
4
The OSBA has filed an appellate brief as an intervenor in support of the Commission.
5
On the latter point, the Energy Association of Pennsylvania filed an amicus curiae brief in
support of Utility and PPL Corporation.
6
of the powers or privileges of corporations not possessed by individuals or
partnerships.” 66 Pa.C.S. §102.
In the Statement of Policy, the Commission noted the “ambiguous
language” of section 1102(a)(3) and how it had created “considerable uncertainty . . .
regarding what type of transaction requires Commission approval,” particularly with
respect to “stock transfers which may equate to the transfer of utility property.” 52
Pa. Code §69.901(a)(1). The Commission thus deemed it “necessary,” with regard to
stock transfers, “to further define and establish clear standards regarding what
transfer of voting interest constitutes a change in de facto control and thereby
constitutes the transfer or acquisition of utility property within the intendment of
[section] 1102(a)(3).” 52 Pa. Code §69.901(a)(2).
In clarifying the vernacular in section 1102(a)(3), the Commission
reiterated its holding in Joint Application of Paging Network of Pittsburgh, Inc. (Pa.
P.U.C., No. A-330013, F.5000, filed October 22, 1993), that approval and a CPC
were necessary when there was “a transaction resulting in a change of the de facto
controlling interest in a utility or its parent, regardless of the tier in the corporate
organization” because this type of transaction “constitutes a change of control of the
utility.” 52 Pa. Code §69.901(a)(2). Drawing on this administrative adjudication,
and others, the Commission determined in the Statement of Policy that approval and a
CPC are needed when there is “[a] transaction or series of transactions resulting in a
new controlling interest,” namely “when the transaction or transactions result in a
different entity becoming the beneficial holder of the largest voting interest in the
utility or parent, regardless of the tier.” 52 Pa. Code §69.901(b)(1). By definition, “a
controlling interest is an interest, held by a person or a group acting in concert, which
enables the beneficial holders to control at least 20% of the voting interest in the
7
utility or its parent, regardless of the remoteness of the transaction.” 52 Pa. Code
§69.901(b)(2).
Here, the proposed restructuring sought to effectuate internal corporate
transactions that would ultimately transfer all of the shares of Utility’s stock from
PPL Corporation to Newco 2. As a matter of black letter corporate law, a subsidiary
(Utility) is a “corporation” in its own right, and it is an entity that is separate and
distinct from its proffered immediate parent (Newco 2), thereby constituting an
entirely “different entity” altogether. 52 Pa. Code §69.901(b)(1). See, e.g.,
Commonwealth v. Gulf Oil Corporation, 60 A.2d 46, 48 (Pa. 1948) (“Appellant
[parent corporation] and its subsidiary are distinct corporations notwithstanding that
the former owns all of the latter’s stock.”); Appeal of Callery, 116 A. 222, 224 (Pa.
1922) (“A corporation does not lose its corporate identity when its stock is all owned
by another corporation.”); Simon v. Commonwealth, 422 A.2d 1229, 1230-31 (Pa.
Cmwlth. 1980) (noting that a parent corporation and a subsidiary are “separate legal
entities,” “separate and distinct corporations,” each with their own “separate
corporate identity”) (internal citation omitted). Pursuant to the plain language of
section 1102(a)(3) and the Statement of Policy, Newco 2 would obtain a controlling
interest in Utility, and “the transaction [would] result in a different entity becoming
the beneficial holder of the largest voting interest in [Utility].” 52 Pa. Code
§69.901(b)(1). Indeed, in this case, Newco 2 would receive all of the voting interest
and stock in Utility, and, therefore, a CPC was mandatory in order to receive
Commission approval for the proffered reorganization. This is so regardless of the
fact that PPL Corporation, by way of its internal hierarchy, is associated with Newco
2—as Newco 2 is a wholly-owned subsidiary of Newco 1, and Newco 1 is a wholly-
owned subsidiary of PPL Corporation—because it is Newco 2, and not PPL
8
Corporation, that would own all the stock of Utility. As the Statement of Policy
elucidates, the fact that a new entity has obtained a controlling interest in stock is the
paramount and dipositive factor in the inquiry, and considerations such as the
“remoteness” or “tier” of the transactions are immaterial. 52 Pa. Code §69.901(b)(1),
(2).
While this may be simple enough, PPL Corporation nonetheless argues
that Utility would maintain its own internal managerial and operational facets. But
this contention overlooks one basic fact and reality. That is, by owning all of the
shares of Utility, and possessing a “controlling interest in [Utility],” Newco 2—the
would be immediate parent company—would acquire the direct and/or indirect
authority “to manage, direct, or oversee” and ultimately “govern the management and
policies of [Utility].” Black’s Law Dictionary 378, 885 (9th ed. 2009). See Appeal of
Callery, 116 A. at 224 (“Holding company, as its sole stockholder, controls
subsidiary [and] through its officers . . . it imposes its will on subsidiary.”); Craig v.
Lake Asbestos of Quebec, Ltd., 843 F.2d 145, 150 (3d Cir. 1988) (“It is assumed to be
the norm that a parent will have not only . . . the potential to exercise control [over
the subsidiary], but to exercise it to a substantial degree.”) (internal citation and
quotation marks omitted, brackets in original); Action Manufacturing Co. v. Simon
Wrecking Co., 375 F.Supp. 2d 411, 423 (E.D. Pa. 2005) (stating that the “officers of
any corporation that owns the stock . . . necessarily exercise a considerable degree of
control over the subsidiary corporation”). Consequently, Newco 2 would be vested
with the authority to alter Utility’s managerial and operational directions, irrespective
of the fact that Newco 2 would be a wholly-owned subsidiary of Newco 1 and an
indirect subsidiary, up through the corporate chain, of PPL Corporation.
9
PPL Corporation also takes issue with the language of section 1102(a)(3)
of the Code and posits that a new corporate entity must receive the assets and
property of a public utility in order for the requirements of approval and a CPC to
apply. In PPL Corporation’s view, the proposed transaction would not result in the
transfer of any of Utility’s assets and property and Newco 2 would not obtain
ownership over or possession of such assets or property.
However, the language of section 1102(a)(3) was not written so
narrowly and restrictively. Instead, the phraseology of the statute is very broad and
encompasses instances where there is the simple “transfer of stock.” 66 Pa.C.S.
§1102(a)(3). Generally, a stock transfer, in its common parlance and understanding,
is not tantamount to a transfer of assets. See In re Goetz’s Estate, 85 A. 65, 66 (Pa.
1912) (“The estate, as a holder of all the stock, would not be the owner of the
corporation, but only of the shares of its capital stock, which constitute a species of
property entirely distinct from the corporate property.”); id. (“We have been referred
to no authority, and we know of none, that asserts the doctrine that the purchaser of
all the shares of the capital stock of a corporation thereby becomes the owner of its
property.”). Stated otherwise, a stock transfer stands in stark contrast to a contractual
exchange where the operational assets of one entity are transferred or otherwise
conveyed to another entity for monetary consideration. See Schmidt v. Boardman
Co., 958 A.2d 498, 504 (Pa. Super. 2008), aff’d, 11 A.3d 924 (Pa. 2011) (discussing
situations where “one company sells or transfers all of its assets to another
company”). A simple stock transfer is also remarkably different from classical
fundamental changes in corporate structure that yield an acquisition of assets, such as
that which occurs in the case of a merger or consolidation. See Seven Springs Farm,
Inc. v. Croker, 748 A.2d 740, 744 n.4 (Pa. Super. 2000) (en banc), aff’d, 801 A.2d
10
1212 (Pa. 2002) (“A merger occurs when a seller corporation, including all of its
assets and liabilities, is absorbed into a purchasing corporation and the seller loses its
identity as a separate entity.”) (internal citation omitted); id. at 774 (“The merger of
two or more corporations is neither a sale nor a liquidation of corporate property, but
a consolidation of properties, powers, and facilities of the constituent companies,
forming a new corporate entity.”) (internal citation omitted); Cortland Specialty Co.
v. Commissioner of Internal Revenue, 60 F.2d 937, 939 (2d Cir. 1932) (“A
consolidation involves a dissolution of the companies consolidating and a transfer of
corporate assets and franchises to a new company.”).
Notably, section 1102(a)(3) covers transfers “by any method or device
whatsoever, including the sale or transfer of stock and including a consolidation,
merger, [or] sale . . . .” 66 Pa.C.S. §1102(a)(3). Because the term “including” is a
word of enlargement, and not one of limitation, see Readinger v. Workers’
Compensation Appeal Board (Epler Masonry), 855 A.2d 952, 955 (Pa. Cmwlth.
2004), we must presume that our General Assembly intended a sale of stock to be
distinct from, and in addition to, a merger, consolidation, or a sale of assets. In this
vein, the Statement of Policy is entirely consonant with the statute by deeming the
transfer of a controlling interest of stock as essentially constituting a transfer of utility
property requiring Commission approval under section 1102(a)(3) of the Code.
Further, the Commission’s current adjudication and its Statement of Policy, which
was adopted and became effective in 1994 and was predicated upon previous
adjudications, expound upon the ambiguity surrounding what “stock transfers,” in
particular, should fall within the ambit of section 1102(a)(3). Consequently, and
contrary to the arguments of Utility, the Commission’s interpretation and application
of the phrase “transfer of stock” is entitled to administrative deference. See Snyder
11
Brothers, Inc. v. Pennsylvania Public Utility Commission, 198 A.3d 1056, 1069,
1077-78 (Pa. 2018) (concluding that the Commission’s interpretation of an
ambiguity, in accordance with rulemaking orders, was entitled to administrative
deference even though “the administrative orders were not enacted according to
formal rulemaking procedures” and were “mere ‘non-legislative rules,’ or agency
‘pronouncements,’” because the Commission had “faithfully adhered to its
construction” in the rulemaking orders for years prior to the litigation that ensued in
that case); see also Pennsylvania Human Relations Commission v. Norristown Area
School District, 374 A.2d 671, 679 (Pa. 1977) (stating that an administrative agency
can formulate “policy that will have the force of law,” among other ways, “through
adjudications which constitute binding precedents”).
Moreover, as crafted by our General Assembly, section 1102(a)(3)
embodies those instances where there is a “transfer of stock” that effectively assigns
the “use of[] any . . . intangible property used . . . in the public service.” 66 Pa.C.S.
§1102(a)(3). In its corporate form, and considered in isolation and in and of itself,
Utility is undoubtedly “intangible property” and is the means by which the “public
service” of providing electricity is accomplished or “used.” See Trustees of
Dartmouth College v. Woodward, 17 U.S. 518, 636 (1819) (“A corporation is an
artificial being, invisible, intangible, and existing only in contemplation of law.”). As
explained above, Newco 2, as a result of acquiring a controlling interest in Utility,
would attain the authority to exercise control over the management and operations of
Utility. Hence, at the very least, the proffered restructuring would have the effect of
bestowing upon Newco 2 the authority to “use” Utility in the sense that Utility would
become a direct subsidiary of Newco 2, subject to Newco 2’s control in terms of
policy, management, and operations as they pertain to providing electric service to
12
the public. See State Farm Mutual Automobile Insurance Co. v. Cavoto, 34 A.3d
123, 133 (Pa. Super. 2011) (quoting an authoritative dictionary and defining the term
“use,” in part, as “the privilege or benefit of using something,” “a method or manner
of employing or applying something,” or “the ability or power to use something”).
Quite simply, Newco 2 could exercise significant influence over Utility in its conduct
of providing services as a utility and, thus, shape and “use” Utility to a substantial
degree with respect to the functional aspects that are associated with the assimilation
and distribution of electrical energy.
On this note, based on the terms of the proposal, PPL Corporation, via a
transfer through Newco 1, would relinquish not only all of its ownership interest in
Utility, but also its right to exercise direct control over Utility, to Newco 2.6 Because
PPL Corporation seeks to divest itself of any and every direct legal interest that it has
in Utility, it is difficult to understand how the Concurring and Dissenting Opinion
(CDO) repeatedly pronounces that PPL Corporation “would [] retain sole ultimate
ownership of Utility” and “ultimate title to Utility and its assets.” PPL Electric
Utilities Corp. v. Public Utility Commission (Pa. Cmwlth., 624 C.D. 2019, filed
October 27, 2020) (Ceisler, J., concurring and dissenting) (CDO), slip op. at 2, 8. To
be sure, the CDO attempts to support this proposition with a blanket statement that
6
The only connection PPL Corporation would have to Utility is that PPL Corporation would
wholly own Newco 1, Newco 1 would wholly own Newco 2, and Newco 2 would wholly own
Utility. By owning all of the shares of Utility’s voting stock, Newco 2 has direct control of Utility
and the authority to “use” and dictate Utility in any manner that it deems fit, including its
operational strategies and objectives. Although PPL Corporation could potentially exert indirect
influence on (or rather render advice to) Newco 2, because PPL Corporation wholly owns Newco 1,
and Newco 1 wholly owns Newco 2, PPL Corporation cannot legally compel Newco 2 or Utility to
abide by those directives. In other words, the board of directors of PPL Corporation cannot get
together and vote to change Utility’s operational policy because PPL Corporation does not possess
any of Utility’s stock and, hence, lacks the voting power necessary to effectuate such a change.
13
relegates “the stock transfers to Newco 1 and 2” to “merely paper transactions.” Id.
Unfortunately, as explained above, the law governing stock transfers of a controlling
interest in a corporation does not share this view, see Appeal of Callery, 116 A. at
224; Craig, 843 F.2d at 150; Action Manufacturing Co., 375 F.Supp. 2d at 423, and
neither do the courts, which have interpreted statutory provisions substantially similar
to section 1102(a)(3) and the Statement of Policy. For example, in Title Insurance
and Trust Co. v. County of Riverside, 767 P.2d 1148 (Cal. 1989), the Supreme of
California interpreted a statute, which, akin to section 1102(a)(3) and the Statement of
Policy, stated, in pertinent part, that “[w]hen a corporation . . . obtains control through
direct or indirect ownership or control of more than 50[%] of the voting stock of any
corporation . . . the purchase or transfer of that stock . . . shall be a change of
ownership of the real property owned by the corporation . . . in which the controlling
interest is obtained.” Cal. Rev. & Tax Code §64(c) (1995) (section 64(c)). In
discussing this provision, the California court persuasively explained,
[t]he section provides, in essence, that if one corporation
either directly or indirectly obtains control over another by
the transfer or purchase of stock, a change of ownership
occurs as to the real property owned by the corporation over
which it has obtained direct or indirect control . . . . The
fundamental requirement for a change in ownership under
the section is the obtaining of control of the corporation that
owns the property subject to reassessment, whether that
control is obtained directly or indirectly. The purchase of
stock is the means by which the control [is] secured.
Title Insurance and Trust Co., 767 P.2d at 1152 (bold emphasis added); see id. at
1156 (“As we emphasize repeatedly above, the touchstone of a change of ownership
under section 64(c) is control of the corporation that owns the property subject to
reassessment; it is not the right to occupy the property or to take possession of it.”).
14
Likewise, in section 1102(a)(3), our General Assembly determined that a “transfer of
stock” could result in “the possession or use of [a utility’s] tangible or intangible
property,” 66 Pa.C.S. §1102(a)(3), and the Statement of Policy declares that when “a
different entity becom[es] the beneficial holder of the largest voting interest in the
utility,” 52 Pa. Code §69.901(b)(1), the transaction “constitutes the transfer or
acquisition of utility property within the intendment of [section 1102(a)(3)].” 52 Pa.
Code §69.901(a)(2).
Otherwise, the CDO, in an apparent form of fact-finding, appears to
credit, at face value, PPL Corporation’s assertion that it would retain ultimate control
over and ownership of Utility because PPL Corporation “is not seeking to deny
responsibility for Utility’s obligations” and would be estopped “from asserting in the
future that [it] lacks such ownership, control, and responsibility.” (CDO, slip op. at
12.) However, the Commission, as the actual fact-finder in these proceedings, see
Kviatkovsky v. Pennsylvania Public Utility Commission, 618 A.2d 1209, 1211 (Pa.
Cmwlth. 1992), did not find PPL Corporation’s representation credible, seemingly
because it lacks any basis in law or fact. To the extent that the CDO and Utility rely
on the theory of piercing the corporate veil to establish that PPL Corporation would
have ultimate ownership and control of Utility, such reliance is severely misplaced.
Traditionally, the doctrine of piercing the corporate veil has been used to allow a
court to “ignore the corporate boundaries between parent and subsidiary if fraud or
inequity is shown,” Applied Biosystems, Inc. v. Cruachem, Ltd., 772 F.Supp. 1458,
1463 (D. Del. 1991), and, if so, “the parent corporation will be held liable for the
obligations of its subsidiary.” Japan Petroleum Co. (Nigeria) Ltd. v. Ashland Oil,
Inc., 456 F.Supp. 831, 839 (D. Del. 1978). To pierce the corporate veil, a plaintiff
must show that the defendant corporation is “involved in an elaborate shell game or
15
[is] otherwise abusing the corporate form to effect a fraud,” for example, when the
parent corporation exercises such “exclusive domination and control . . . to the point
that [the subsidiary] no longer ha[s] legal or independent significance of [its] own.”
Outokumpu Engineering Enterprises, Inc. v. Kvaerner EnviroPower, Inc., 685 A.2d
724, 729 & n.2 (Del. Super. Ct. 1996). In short, while the equitable doctrine of
piercing the corporate veil is a way to impose liability on a parent for a subsidiary’s
conduct, it has never been a means through which a corporation can create distinct
corporate entities like subsidiaries to control wholly-owned subsidiaries, and then
disregard that corporate form and structure in order to exercise the very right of
ownership and control that it has transferred to those subsidiaries and wholly-owned
subsidiaries. Therefore, we believe that the CDO offers an unpersuasive expression
of rationale to support its position.
For these reasons, we conclude that the Commission did not err in
determining that Utility’s proposed restructuring would require approval and a CPC
for purposes of section 1102(a)(3) of the Code.
Next, Utility asserts that, assuming arguendo, it was required to receive
a CPC, it was not required to establish that its internal reorganization would confer a
substantial, affirmative benefit to the public. In this regard, Utility posits that
application of such a standard “would produce an absurd and unreasonable result as it
would create a standard of review of internal reorganizations that, for all practical
purposes, would be impossible to meet.” (Br. for Utility at 26.) Emphasizing the
plain language of section 1103(a) of the Code, the Utility contends that the phrase,
“necessary or proper,” is disjunctive in nature and that a showing that the proffered
reorganization would be proper for serving the public with electricity would suffice.
16
To recapitulate, section 1103(a) provides that a CPC “shall be granted
by order of the [C]ommission, only if the [C]ommission shall find or determine
that the granting of such certificate is necessary or proper for the service,
accommodation, convenience, or safety of the public.” 66 Pa.C.S. §1103(a)
(emphasis added).
In its adjudication, the Commission applied an “affirmative public
benefit” standard and, for support, relied predominately upon two decisions from our
Supreme Court. (Commission’s decision at 41.) See City of York v. Pennsylvania
Public Utility Commission, 295 A.2d 825, 828 (Pa. 1972) (stating that section 1103(a)
“makes it clear that a [CPC] approving a merger is not to be granted unless the
Commission is able to find affirmatively that [a] public benefit will result from the
merger”; the statute “requires that the proponents of a merger demonstrate that the
merger will affirmatively promote the service, accommodation, convenience, or
safety of the public in some substantial way”) (internal quotation marks omitted);
accord Popowsky v. Pennsylvania Public Utility Commission, 937 A.2d 1040, 1057
(Pa. 2007) (“[A]s indicated in City of York, the appropriate legal framework requires
a reviewing court to determine whether substantial evidence supports the
Commission’s finding that a merger will affirmatively promote the service,
accommodation, convenience, or safety of the public in some substantial way.”). In
point of fact, the Commission determined that, “as an administrative agency, [it was]
bound by judicial interpretation of the Code,” (Commission’s decision at 40 n.10),
indicated that it had no choice or discretion in the matter, and stated that, pursuant to
City of York and Popowsky, it was obligated to decide whether Utility’s proposed
restructuring would confer an “affirmative public benefit.” (Commission’s decision
at 40-41.)
17
However, as this Court has noted, both City of York and Popowsky
“provided [] guidance for reviewing merger applications.” Lloyd v. Pennsylvania
Public Utility Commission, 17 A.3d 425, 430 (Pa. Cmwlth. 2011) (emphasis added).
This observation is extremely critical because, in the unique and specific context
when there is a proffered merger between two utility companies at the parent level or
otherwise, there are overarching and serious concerns about the potential for attaining
monopolistic power, which could have an adverse effect on consumer rates.
By way of background, “[i]n Pennsylvania, the regulation of electric
service distribution has traditionally afforded utility companies natural monopolies”
City of Pittsburgh v. West Penn Power Co., 147 F.3d 256, 259 (3d Cir. 1998), or, in
other words, “a regulated quasi-monopoly.” City of Pittsburgh v. Pennsylvania
Public Utility Commission, 128 A.2d 372, 386 (Pa. Super. 1956). In 1996, our
General Assembly passed the Electricity Generation Customer Choice and
Competition Act (Competition Act),7 which became effective in 1997. In terms of
electric distribution, this legislation “effectuated . . . the de-regulation of the electric
market,” PECO Energy Company v. Commonwealth, 919 A.2d 188, 189 (Pa. 2007),
and “was passed to encourage a more competitive marketplace for electricity sales.”
Spectrum Arena Limited Partnership v. Commonwealth, 983 A.2d 641, 645 (Pa.
2009). Stated otherwise, the Competition Act was based on the underlying view that
“[c]ompetitive market forces are more effective than economic regulation in
controlling the cost of generating electricity,” George v. Pennsylvania Public Utility
Commission, 735 A.2d 1282, 1284, 1288 (Pa. Cmwlth. 1999), and “was enacted to
encourage a competitive wholesale electric market and to provide cost savings to
7
66 Pa.C.S. §§2801-2812.
18
consumers.” American Electric Power Service Corporation v. Commonwealth, 160
A.3d 950, 955 (Pa. Cmwlth. 2017).
In West Penn Power Co., the City of Pittsburgh commenced suit against
two electrical utility companies that were planning to merge, asserting claims under
section 1 of the Sherman Antitrust Act (Sherman Act)8 and section 7 of the Clayton
Act.9 Addressing the nature of these claims in light of the Commission’s regulatory
oversight of public utilities, the United States Court of Appeals for the Third Circuit
stated:
The present case arises in a factual context which is
substantially different from that of most antitrust cases. The
[City of Pittsburgh] has alleged anticompetitive behavior in
an industry which is highly regulated: those [that] wish to
compete to provide their services must obtain a [CPC] from
the [the Commission] to do so. As the First Circuit has
explained, “[f]ull price regulation dramatically alters the
calculus of antitrust harms and benefits.” Town of Concord,
Massachusetts v. Boston Edison Co., 915 F.2d 17, 25 (1st
Cir. 1990) (holding that alleged price squeeze did not
violate [the] Sherman Act because utility’s rates were
regulated). Similarly, here, the regulation which frames the
issue is the statutory requirement that a utility obtain
permission from the [Commission], in the form of a [CPC],
in order to provide electric service to a particular
geographic region.
The [United States] Supreme Court has made clear that
regulated industries—even those that historically have been
treated as natural monopolies—are not exempt from the
antitrust laws. See Otter Tail Power Co. v. United States,
410 U.S. 366 (1973). However, in this case, the
comprehensive regulatory framework significantly restricts
8
15 U.S.C. §1.
9
15 U.S.C. §18.
19
the nature of the competition which is permitted. While it is
true that the regulatory landscape of the electric power
industry is in the process of changing, even the Competition
Act does not anticipate a completely “free market” for
electric services. Rather, the changes will result in a form
of regulated competition.
West Penn Power Co., 147 F.3d at 263-64.
That said, in City of York, which was decided prior to the Competition
Act, our Supreme Court instructed “that the Commission should consider, at least in a
general fashion, the effect that a proposed merger is likely to have on future rates to
consumers” because “the probable general effect of the merger upon rates is certainly
a relevant criter[ion] of whether the merger will benefit the public.” 295 A.2d at 829.
Approximately 35 years after City of York was decided, our Supreme Court
reaffirmed and clarified that decision in Popowsky. In doing so, the Court noted “that
City of York does not hold that a merger benefits the public only if the [proponent]
can demonstrate that the merger savings will lower prices to consumers” and added
that “competitive impact is a substantial component of a rational net public benefits
evaluation in the merger context.” 937 A.2d at 1056 (emphasis in original).
Then, in Lloyd, this Court discussed and synthesized City of York and
Popowsky. We explained that when conducting an “affirmative public benefit”
inquiry,
the Supreme Court instructed the [Commission] in all cases
of merger, (1) to evaluate the competitive effects of the
merger; and, (2) if the effects of the merger are anti-
competitive, then the [Commission] must consider whether
those anti-competitive effects outweigh or “negate” the
affirmative public benefits it has identified. If the
[Commission] concludes that the anti-competitive effects
outweigh the affirmative public benefits, then the
[Commission] should not issue a [CPC].
Lloyd, 17 A.3d at 432 (internal citation omitted) (emphasis in original).
20
In enacting section 1103(a) of the Code, our General Assembly
“provided no definition of specifically what the criteria were to be in determining the
propriety of granting a [CPC].” Elite Industries, Inc. v. Pennsylvania Public Utility
Commission, 832 A.2d 428, 432 (Pa. 2003). In light of the inherent nature of
mergers, “transactions [which] are so highly regulated,” Popowsky, 937 A.2d at 1057,
considered in the background of federal antitrust laws and later the Competition Act,
we can readily discern that mergers and consolidations are deserving of special
attention in terms of their impact on the public. And, given the Commission’s
regulatory role and oversight with respect to a merger’s effect on competition in the
marketplace, it makes complete sense that our Supreme Court would engraft an
“affirmative public benefit” standard into the statute and develop an analytical
framework that focuses on competitive effects, while taking into account the rate
prices that will inure to consumers. This is especially true considering that when
dealing with utilities in the merger scenario, if the thrust of a proffered merger, on
balance, would result in anticompetitive behavior, then public utilities could resort to
the monopolistic and/or monopsonistic practices of the antiquated past, potentially
resulting in unreasonable increases in consumer prices and harm to the public in
general.
However, in the circumstances before us, the concerns and dangers
associated with anticompetitive behavior are not present, or at least not present to a
degree that is reasonably comparable to those that could occur in the situation of a
merger. In its proposed internal restructuring, Utility is not seeking to gain a larger
share of market power by combining two separate public utilities. Rather, the
proffered reorganization would merely divest PPL Corporation of any and all
interests, including a controlling share of stock, that it has in Utility and would
21
transfer these interests to Newco 1 and Newco 2 as holding companies. Perhaps
significantly, holding companies have traditionally been created for internal structural
advantages, namely in order to receive shelter from legal liability, obtain tax benefits,
and facilitate strategic corporate finance objectives. See Douglas G. Smith, Piercing
the Corporate Veil in Regulated Industries, 2008 B.Y.U. L. REV. 1165, 1170-71
(2008) (noting that “limited liability is the rule not the exception” for holding
companies, parents, and subsidiaries and explaining that “[c]ourts will pierce the
corporate veil only in exceptional circumstances” because “disregarding the corporate
form and imposing liability on affiliated corporate entities is an extreme remedy,
sparingly used”); 1189 (“[H]olding companies can provide subsidiaries with a level
of financial flexibility, including capital infusions, access to capital markets, and in
some cases, additional cash flow sources from other operations.”); 1190 (“[H]olding
companies can be advantageous from a tax perspective; by combining losses and
gains from different subsidiaries, all companies may benefit through reduction in tax
liabilities.”). In its application, Utility averred benefits that arguably duplicate or
mimic those above and have asserted that the proposed internal reorganization would
not have a detrimental effect on the public, but instead, could be advantageous to the
public due to the possibility that Utility would be more fiscally sound and secure.
In view of the schematics of Utility’s proposed internal restructuring, it
would be very difficult, if not impossible, for Utility to establish an affirmative and
substantial benefit to the public as that concept has been employed by our Supreme
Court when there has been a proposed merger between two or more public utilities.
Distilled to its essence, the test to decide whether there is an affirmative public
benefit necessitates the Commission to “evaluate[] the impact of [a] merger on
competition” and to ultimately determine if “the merger would have a positive impact
22
on competition,” Lloyd, 17 A.3d at 434, or lower prices to consumers. See City of
York, 295 A.2d at 829. Quite simply, this mode of analysis does not fit the facts of
this case and has no place in the calculus for determining whether Utility has met the
statutory requirements for a CPC.
Our Supreme Court has cautioned that its decisions must be read against
their specific facts because “decisional law generally develops incrementally, within
the confines of the circumstances of cases as they come before the Court.” Scampone
v. Highland Park Care Center, LLC, 57 A.3d 582, 604 (Pa. 2012). We follow that
lead here and conclude that the “substantial” and “affirmative public benefit” test
developed in City of York and Popowsky is circumscribed to utilities’ applications for
a merger, consolidation, or the like, specifically where two separate public utilities
propose to combine. This analysis, however, is ill suited and unworkable for internal
reorganizations such as the one in this case, where a parent creates subsidiaries that
are set up as holding companies and only one public utility is moved downward in the
parental vertical chain. In this situation, a less demanding evidentiary burden is
warranted—one that does not mandate an appraisal of the effects on competition in
the marketplace, yet is consistent with the plain language of the statute, and pays due
consideration to the public. Therefore, the Court concludes that, contrary to the
Commission’s understanding, the Commission was not bound to apply the test
enunciated in City of York and Popowsky, and we reverse the Commission on this
point.
In Elite Industries, Inc., our Supreme Court reviewed section 1103(a) of
the Code and concluded that this Court erred in determining that an applicant for a
CPC to operate a limousine service had to prove “public necessity” or “public need.”
832 A.2d at 430-31. The Supreme Court found that we erroneously “focused only on
23
the word ‘necessary’ rather than on the phrase ‘necessary or proper.’” Id. at 431.
“However,” said the Supreme Court, “the conjunction ‘or’ must be given its
ordinarily disjunctive meaning unless such a construction would lead to an absurd
result.” Id. Heeding this advice, we believe the Commission can conduct a
disjunctive analysis in this case and that, for purposes of section 1103(a), Utility need
only establish—and the Commission need only find—that granting a CPC would be
“proper for the service . . . of the public.” 66 Pa.C.S. §1103(a). As a general guide,
the customary dictionary definition of “proper” is being “adapted or appropriate to
the purpose or circumstances; fit; suitable.” Vodvarka v Grasmeyer, 675 N.W.2d
847, 853 (Mich. Ct. App. 2003) (quoting Random House College Dictionary 1061
(rev. ed. 1979)). Nonetheless, we leave it to the sound discretion of the Commission
to formulate the specific criteria or factors to be used in assessing whether Utility’s
proposed internal restructuring is “proper” for servicing the public with electricity
and deserving of a CPC. See Elite Industries, Inc., 832 A.2d at 432. Accordingly, we
remand to the Commission to undertake this inquiry and determine whether Utility is
entitled to a CPC pursuant to the above-mentioned standard.10
10
Ostensibly, the CDO wants to import a revised version of the “affirmative public benefit
standard” that our Supreme Court has developed in the context of merger acquisitions to this case.
According to the CDO, “Utility met its burden of showing a substantial affirmative public benefit
by establishing the financial advantages” that would inure to PPL. Corporation, specifically, “a
stronger company, ease of access to money markets, improved administrative efficiencies, and tax
benefits.” (CDO, slip op. at 13, 15.) Respectfully, we believe that there is no “public” in the
CDO’s “affirmative public benefit” analysis—only the strengthening of a corporate entity and the
potential pavement of its way toward monopolistic power in its most archaic and oppressive form.
24
For all of the foregoing reasons and grounds, we affirm in part and
reverse and remand in part.
________________________________
PATRICIA A. McCULLOUGH, Judge
Judge Fizzano Cannon did not participate in this decision.
25
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
PPL Electric Utilities Corporation, :
Petitioner :
: No. 624 C.D. 2019
v. :
:
Public Utility Commission, :
Respondent :
ORDER
AND NOW, this 27th day of October, 2020, the April 25, 2019 order
of the Pennsylvania Public Utility Commission (Commission) is affirmed in part
and reversed in part. The matter is remanded to the Commission for further
proceedings consistent with this opinion.
Jurisdiction relinquished.
________________________________
PATRICIA A. McCULLOUGH, Judge
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
PPL Electric Utilities Corporation, :
Petitioner :
:
v. : No. 624 C.D. 2019
: ARGUED: May 13, 2020
Public Utility Commission, :
Respondent :
BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge
HONORABLE RENÉE COHN JUBELIRER, Judge
HONORABLE P. KEVIN BROBSON, Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE ELLEN CEISLER, Judge
HONORABLE J. ANDREW CROMPTON, Judge
OPINION NOT REPORTED
DISSENTING/CONCURRING OPINION
BY JUDGE CEISLER FILED: October 27, 2020
Respectfully, I concur in part and dissent in part.
I disagree with the majority’s conclusion that a certificate of public
convenience from the Pennsylvania Public Utility Commission (PUC) was required
for an internal corporate restructuring in which the parent corporation, PPL
Corporation (Parent), would retain ultimate ownership of a wholly owned
subsidiary, PPL Electric Utilities Corporation (Utility).
Even if a certificate of public convenience was required, I believe the PUC
erred as a matter of law by determining that the evidence demonstrated no substantial
affirmative public benefit from Parent’s proposed internal restructuring. Therefore,
I agree with the majority’s reasoning insofar as it reverses the PUC’s finding of no
affirmative public benefit. However, I do not believe a remand is needed to allow
the PUC to reconsider its decision under a different legal standard.
I. Background
Parent currently owns all shares of Utility directly. Utility applied to the PUC
for approval of Parent’s proposal to insert two new wholly owned subsidiary holding
companies, PPL Subsidiary Holdings, LLC (Newco 1) and PPL Energy Holdings,
LLC (Newco 2), between Parent and Utility in the corporate structure, as part of a
larger internal restructuring. The ownership of Utility is illustrated as follows:
Current: Parent —> Utility
Proposed: Parent —> Newco 1 —> Newco 2 —> Utility
See Reproduced Record (R.R.) at 106a-07a (illustrating complete present and
proposed corporate structures). Under the restructuring proposal, each entity in the
chain of ownership would wholly own the entity below. Thus, Parent would still
retain sole ultimate ownership of Utility through its ownership of Newco 1 and
Newco 2.
Parent proposed the restructuring in order to manage intercompany cash flows
more effectively, operate more efficiently, and manage its tax liabilities more
prudently, thereby improving its financial profile. The proposed restructuring would
not alter the management or operations of Utility. Parent also would retain ultimate
control over all of its subsidiaries, including Utility.
Two administrative law judges (ALJs) issued a decision recommending that
the PUC deny Utility’s application for approval of Parent’s proposed restructuring.
The ALJs concluded that although the restructuring might benefit the shareholders
EC - 2
and would not harm the public, it would not provide a substantial affirmative public
benefit to Utility’s customers. See R.R. at 98a.
Utility filed exceptions to the ALJs’ decision. In a 3-2 decision with two
dissenting statements, the PUC denied Utility’s exceptions. R.R. at 149a-50a. The
PUC majority concluded that Parent’s proposed internal restructuring required a
certificate of public convenience pursuant to Section 1102(a)(3) of the Public Utility
Code, 66 Pa.C.S. § 1102(a)(3) (Section 1102(a)(3)), because the proposed new
structure would constitute a de facto change of control of Utility, as set forth in the
PUC’s Policy Statement at 52 Pa. Code § 69.901 (Policy Statement). R.R. at 139a-
42a; see also Policy Statement Regarding Interpretation of 66 Pa.C.S. § 1102 (a)(3)
(Pa. P.U.C., No. M-930490, filed September 13, 1994), 1994 Pa. PUC LEXIS 56.
The PUC majority denied Utility’s application, agreeing with the ALJs that Utility
failed to demonstrate the proposed restructuring would produce a substantial
affirmative public benefit to its customers. R.R. at 148a.
Two Commissioners voted against denying the restructuring proposal.
Commissioner John F. Coleman, Jr. opined that Utility met its burden of
demonstrating that the restructuring would provide a substantial affirmative public
benefit. Noting that Parent “is the ultimate source of equity capital” for Utility,
Commissioner Coleman found that improved cash flow and more efficient financial
management would result in “reduced capital needs and an improved ability to raise
capital at more favorable rates, thereby benefitting [Utility’s] customers.” R.R. at
157a. Citing the PUC’s own decision in Application of Duquesne Light Co. for a
Certificate of Public Convenience Under Section 1102(a)(3) (Pa. P.U.C., Nos. A-
110150 & A-311233, filed April 24, 2007), Commissioner Coleman concluded that
EC - 3
“[m]ore efficient access to capital has been previously recognized by the [PUC] as
an example of an affirmative public benefit.” R.R. at 158a.
Commissioner Norman J. Kennard also dissented. Commissioner Kennard
observed that the restructuring would involve “no change in the ultimate control of
[Utility] or any of the other entities involved,” that Parent would remain the 100%
owner of all subsidiaries, and that there would be no change in Utility’s management.
R.R. at 152a. Noting the PUC’s own conclusion that Section 1102(a)(3) was
intended to address transfers of control, Commissioner Kennard opined, “I don’t
think that we should have it both ways. Having declared Section 1102(a)(3) to be a
change of control statute via the Policy Statement, the [PUC] should not now rule
that a change of control is not required for the [PUC] to have jurisdiction over a
transaction under Section 1102(a)(3).” R.R. at 153a. Therefore, he concluded no
certificate of public convenience was needed for the restructuring.
Alternatively, Commissioner Kennard suggested that even if a certificate of
public convenience was required, Utility sustained its burden of demonstrating a
substantial affirmative public benefit through increased cash flow flexibility and
better management of tax liabilities. Like Commissioner Coleman, Commissioner
Kennard pointed to the PUC’s prior determination that “the ability of a parent
company of a utility to raise capital on reasonable terms and attract investors is an
example of a substantial public benefit under Section 1102(a)(3) and the City of
York[1] standard.” R.R. at 154a.
Even one of the three Commissioners who voted to deny Utility’s application
did so reluctantly. Vice Chairman David W. Sweet found the outcome of the PUC’s
majority decision “troubling” and voted “regretfully” to deny Utility’s application,
1
City of York v. Pa. Pub. Util. Comm’n, 295 A.2d 825 (Pa. 1972). Our Supreme Court’s
decision in City of York is discussed in Section III, C, below.
EC - 4
commenting that he had “difficulty believing the General Assembly intended this
interpretation of Section 1102[(a)(3)] . . . .” R.R. at 156a.
II. Issues
Utility raises several related arguments in its petition for review:
1. The PUC erred as a matter of law by concluding that a certificate of
public convenience was required for the proposed restructuring.
2. The PUC erred as a matter of law by concluding that its Policy
Statement required the restructuring proposal to meet the requirements of Section
1102(a)(3).
3. Even assuming a certificate of public convenience was required, the
PUC erred as a matter of law and abused its discretion in applying the “substantial
affirmative public benefit” standard to the restructuring proposal.
III. Discussion
A. Certificate of Public Convenience Requirement
1. Section 1102(a)(3)’s Provisions
Section 1102(a)(3) specifies when a certificate of public convenience must be
obtained from the PUC. Section 1102(a)(3) provides, in pertinent part:
(a) General rule.--Upon the application of any public utility and
the approval of such application by the [PUC], evidenced by its
certificate of public convenience first had and obtained, and upon
compliance with existing laws, it shall be lawful:
* * *
(3) For any public utility or an affiliated interest of
a public utility. . . to acquire from, or to transfer to, any
person or corporation, including a municipal corporation,
EC - 5
by any method or device whatsoever, including the sale or
transfer of stock and including a consolidation, merger,
sale or lease, the title to, or the possession or use of, any
tangible or intangible property used or useful in the
public service.
66 Pa.C.S. § 1102(a)(3) (emphasis added).
2. The Policy Statement’s Provisions
In the Policy Statement, the PUC concluded that Section 1102(a)(3) is
ambiguous, resulting in confusion “regarding what type of transaction requires
[PUC] approval.” 52 Pa. Code § 69.901(a)(1). The PUC then “determined that the
transfer of stock or other voting interest of a utility’s parent is jurisdictional [i.e., it
requires a certificate of public convenience approved by the PUC] regardless of the
remoteness of the transaction if the effect of the transaction is to change the control
of a utility.” 52 Pa. Code § 69.901(a)(2) (emphasis added). Further, “a transaction
resulting in a change of the de facto controlling interest in a utility or its parent,
regardless of the tier in the corporate organization, constitutes a change of control
of the utility and is jurisdictional under [Section 1102(a)(3)].” Id. (emphasis added).
3. Utility’s Position
Utility observes that the PUC’s interpretation of a statute is not entitled to
deference from courts unless the statute is ambiguous. See Scanlon v. Dep’t of Pub.
Welfare, 739 A.2d 635, 636 (Pa. Cmwlth. 1999). Utility asserts that, contrary to the
PUC’s conclusory averment in the Policy Statement, Section 1102(a)(3) is not
ambiguous. Utility argues Section 1102(a)(3) facially does not require a certificate
of public convenience here, because the proposed restructuring would not transfer
any title, possession or use of property useful in the public service (i.e., any interest
EC - 6
in Utility); rather, Parent would continue to hold the ultimate ownership and control
of Utility.
Utility also contends that even if Section 1102(a)(3) is ambiguous, the
legislature did not intend to require a certificate of public convenience for an internal
restructuring that does not alter the ultimate ownership or control of a utility. Utility
argues Parent is entitled to autonomy in its internal structuring. The legislature did
not intend to, nor could it, assert control over purely internal organizational
transactions.
4. PUC’s Position
The PUC contends Section 1102(a)(3) is reasonably susceptible to more than
one interpretation, and accordingly, it is ambiguous. Therefore, the PUC insists the
Policy Statement, as the PUC’s interpretation of Section 1102(a)(3), is entitled to
deference.
The PUC also disputes Utility’s contention that no change of control would
occur through the proposed restructuring. The PUC argues that as a matter of law,
the proposed new subsidiaries, Newco 1 and Newco 2, are separate legal entities.
Therefore, the proposed restructuring would result in a change of ownership and
control, despite Parent’s retention of ultimate ownership of all its subsidiaries. The
majority essentially adopts this argument.
5. Analysis
a. Ambiguity
As Utility points out, whether Section 1102(a)(3) is ambiguous is a question
of first impression for Pennsylvania courts; only the PUC has so far made such a
EC - 7
determination. Contrary to the PUC’s position, in my view, Section 1102(a)(3) is
unambiguous as it applies to this case. Section 1102(a)(3) provides that a certificate
of public convenience is required for a transfer of “the title to, or the possession or
use of, any tangible or intangible property used or useful in the public service.”
Id. (emphasis added). That language is clear. Because the statute is not ambiguous,
the PUC’s interpretation of it is not entitled to deference from this Court. See
Scanlon, 739 A.2d at 636.
Moreover, even according deference to the PUC, its reading of Section
1102(a)(3) is incorrect. Parent proposes to retain ultimate title to Utility and its
assets, while Utility would retain possession and use of the property over which it
exercises control in its normal operations. By contrast, neither Newco 1 nor Newco
2 would gain either ultimate title to Utility or possession and use of its assets.
The PUC’s distinction between ultimate control and de facto control also
seems inapt here. It is evident from the record that the stock transfers to Newco 1
and 2 as part of the planned restructuring are merely paper transactions and that
Newco 1 and 2 will be merely holding companies formed to facilitate financial and
tax transactions. Parent will retain de facto control as well as ultimate ownership.
In my view, Parent’s proposed internal restructuring would not transfer title,
possession, or use of any property of Utility that is “used or useful in the public
service.” Section 1102(a)(3), 66 Pa. C.S. § 1102(a)(3). Accordingly, I respectfully
disagree with the majority’s conclusion that a certificate of public convenience is
required for Parent’s proposed internal restructuring.
b. PUC’s Judicial Estoppel Argument
The PUC also argues that Parent and Utility are foreclosed by the principle of
judicial estoppel from denying the requirement of a certificate of public
EC - 8
convenience. According to the PUC, Utility’s very application for a certificate of
public convenience constituted a representation that one was required. Although the
majority’s analysis made it unnecessary to address this argument, I do so here for
completeness. In my opinion, the PUC’s judicial estoppel argument is without merit.
Judicial estoppel applies to prevent a party that has successfully asserted a
position in one legal proceeding from later asserting the opposite position in a
subsequent proceeding. Trowbridge v. Scranton Artificial Limb Co., 747 A.2d 862
(Pa. 2000). The purpose of the doctrine of judicial estoppel is to prevent litigants
from “‘play[ing] fast and loose’ with the courts by switching legal positions to suit
their own ends.” Id. at 865 (quoting Ligon v. Middletown Area Sch. Dist., 584 A.2d
376, 380 (Pa. Cmwlth. 1990)); see also id. (quoting Gross v. City of Pittsburgh, 686
A.2d 864, 867 (Pa. Cmwlth. 1997) (“the purpose of this doctrine is to uphold the
integrity of the courts by ‘preventing parties from abusing the judicial process by
changing positions as the moment requires’”)).
For judicial estoppel to apply, the estopped party’s asserted positions on the
pertinent issue must be completely inconsistent,2 and the party must have prevailed
on that issue in the prior proceeding. See Trowbridge. Here, Utility did not assert
in its application that a certificate of public convenience was required; in fact, it
2
For example, in Trowbridge, the plaintiff, who suffered from muscular dystrophy, was
fired from her job. She sought and obtained social security disability benefits on the basis that she
was totally disabled. She then sued her former employer under the Pennsylvania Human Relations
Act, Act of October 27, 1955, P.L. 744, as amended, 43 P.S. §§ 951-963, alleging she was
improperly fired on the basis of a non-job-related disability, because she was capable of
performing her job with a reasonable accommodation. Our Supreme Court rejected the former
employer’s assertion of judicial estoppel. The Court reasoned that the criteria for assessing
eligibility for social security disability did not include consideration of possible job
accommodations. Therefore, it was not necessarily inconsistent for the plaintiff to sue her former
employer, alleging she could have performed her job with a reasonable accommodation, while also
receiving social security benefits based on total disability.
EC - 9
asserted that it was not required. Utility merely requested any approval that might
be necessary for Parent’s restructuring. See Petitioner’s Reply Br. at 15-16 and
record cites therein. Moreover, Utility was unsuccessful in asserting before the PUC
that no certificate of public convenience was required for the restructuring. Id.
Therefore, neither element of judicial estoppel was met.
Indeed, it would have been reckless for Parent to proceed with its restructuring
without informing the PUC and seeking review. Such a course of action would have
exposed both Parent and Utility to potentially damaging consequences if the PUC
decided – as in fact it did – that its approval was required for the restructuring to
move forward. By seeking the necessary approval, if any, before implementing the
restructuring, Parent and Utility were simply acting prudently; they were not
conceding that such approval was definitely required.
For all of the reasons discussed above, I conclude that no change of ownership
or control of Utility would result from Parent’s proposed internal restructuring.
Accordingly, the PUC erred in concluding that a certificate of public convenience
was required for Parent’s proposed restructuring. I respectfully dissent from the
majority’s conclusion on this issue.
B. PUC Policy Statement and Internal Restructuring
Notably, the PUC has not previously applied Section1102(a)(3) to require a
certificate of public convenience for a purely internal restructuring; this is an issue
of first impression. As Utility aptly points out, the PUC’s Policy Statement
emphasizes the element of “de facto” control as key in determining whether a
certificate of public convenience is required. Utility’s argument that de facto control
of Utility would not change under the proposed restructuring is well taken. Newco
1 and 2, as their corporate names suggest, would be holding companies, passing
EC - 10
through ultimate ownership and control of Utility to Parent. Indeed, the majority
correctly acknowledges that a mere transfer of stock does not convey any corporate
assets. Moreover, the day-to-day management of Utility itself would remain
unchanged.
The PUC points out that Newco 1 and 2, which are limited liability
corporations (LLCs), are separate corporations. The PUC reasons that corporate
separation must be maintained, notwithstanding Parent’s sole ultimate ownership of
all its subsidiaries. Therefore, according to the PUC, insertion of holding companies
in the chain of ownership between Parent and Utility constitutes a change in Utility’s
ownership for purposes of requiring a certificate of public convenience. The
majority again agrees with the PUC. Respectfully, I believe the majority errs by
failing to consider in its analysis the applicable law governing business corporations
generally.
Utility essentially seeks to pierce the corporate veil to acknowledge Parent’s
ultimate ownership and control of Utility. Newco 1 and 2 are LLCs registered in
Delaware. Therefore, Delaware law governs piercing of the corporate veil.
Commonwealth v. Golden Gate Nat’l Senior Care LLC, 194 A.3d 1010 (Pa. 2018).
Delaware law generally recognizes the legal separation of corporate entities,
but a court will disregard the corporate form where equitable considerations require
it in the interests of justice. Mabon, Nugent & Co. v. Texas Am. Energy Corp. (Del.
Ch., No. 8578, filed January 27, 1988), 1988 Del. Ch. LEXIS 11. Under Delaware
law, a party seeking to pierce the corporate veil must plead and prove detailed facts
in support. Albert v. Alex. Brown Mgmt. Servs. (Del. Ch., Nos. 762-N, 763-N, filed
August 26, 2005), 2005 Del. Ch. LEXIS 133.
EC - 11
For example, in Mabon, the plaintiffs alleged that the defendant had led them
to believe it was assuming the liabilities of its subsidiary as part of a corporate
consolidation and reorganization. The complaint also alleged that both parent and
subsidiary operated through joint management, obtained their financing through a
joint credit agreement, and jointly engaged in borrowings and intercorporate
transfers of assets. Further, the parent listed the subsidiary’s debts as part of the
parent’s obligations in federal securities filings and submissions to credit rating
services. The Delaware court found the plaintiffs pleaded sufficient facts to support
their request to pierce the corporate veil. Moreover, the complaint averred sufficient
facts to support the plaintiffs’ assertion that the defendant was estopped from
denying responsibility for its subsidiary’s obligations.
Significantly, here, Parent is not seeking to deny responsibility for Utility’s
obligations. On the contrary, Parent insists that its proposed insertion of two wholly
owned subsidiary LLC holding companies between itself and Utility in the corporate
hierarchy is purely an internal restructuring tool that will improve efficiency and
financial performance without altering Parent’s ultimate ownership and control of
Utility. That assertion does not appear to be disputed.
In this circumstance, the analysis of Mabon offers support for Parent’s
position on two bases. First, Utility pleaded and proved before the PUC sufficient
facts to support Parent’s retention of ultimate ownership and control of, and
responsibility for, the obligations of Utility. Second, if Utility prevails in this appeal,
the positions taken before the PUC and this Court on that issue will estop both Parent
and Utility from asserting in the future that Parent lacks such ownership, control,
and responsibility.3
3
See the discussion of judicial estoppel above.
EC - 12
In my opinion, based on this analysis, the PUC erred in refusing to pierce the
corporate veil as Parent and Utility themselves requested. The PUC offers no reason
why Parent may not avail itself of corporate separation for financial purposes while
still retaining ultimate ownership and control of Utility for purposes of compliance
with the PUC’s governing statute and regulations. Therefore, I respectfully dissent
from the majority’s refusal to pierce the corporate veil here.
C. “Substantial Affirmative Public Benefit” Standard
In City of York v. Pennsylvania Public Utility Commission, 295 A.2d 825 (Pa.
1972), our Supreme Court affirmed the decisions of the PUC and this Court
approving a merger of three telephone companies.4 Our Supreme Court disapproved
its prior decisions applying a standard that merely required no harm to the public;
instead, the Court explained that the terms of Section 1102(a)(3) required
demonstration of a substantial affirmative public benefit. Id. at 828.
However, our Supreme Court in City of York pointed with approval to the
PUC’s determination that the anticipated public benefits included formation of a
stronger company, ease of obtaining capital in money markets, and lower
administrative costs. Id. at 828-29. Although the PUC did not expressly find the
merger would provide an affirmative public benefit, our Supreme Court concluded
the PUC’s determination that financial benefits would result from the merger
constituted such a finding. Id. at 829. As the Court observed, “the [PUC’s] explicit
finding that the merger would result in ‘considerable’ economies can only be taken
as an indication of the [PUC’s] belief that the merger would in fact have a beneficial
effect upon rates.” Id. Further, the Court pointed to the PUC’s determination that
4
All three companies were owned by the same holding company, and the same person
served as president of all three companies. Notably, however, the City of York opinion does not
suggest the proposed merger was a mere internal restructuring as asserted by Utility here.
EC - 13
because of the economies that would result from the merger, the utility’s subscribers
would be beneficiaries of the merger. Id. at 830. See also McCloskey v. Pa. Pub.
Util. Comm’n, 195 A.3d 1055 (Pa. Cmwlth. 2018) (evidence forecasting better
management practices, economies of scale, increased operational efficiencies, and
lack of adverse effects on customer service constituted substantial evidence of
affirmative public benefit, in support of merger transaction).
Here, the record demonstrates the same kinds of financial benefits recognized
in City of York, including a stronger company, ease of access to money markets,
improved administrative efficiencies, and tax benefits. Moreover, the majority
expressly acknowledges the financial benefits of internal restructuring through the
expedient of holding companies, citing internal structural advantages, shelter against
legal liability, tax benefits, furthering strategic corporate financial objectives,
financial flexibility, capital infusions and capital market access for subsidiaries, and
additional cash flow. See Majority op. at 18.
The PUC does not contend otherwise. The PUC simply argues that such
benefits do not demonstrate that Parent’s proposed restructuring would provide a
substantial affirmative benefit to the public or to Utility’s customers. That argument
is contrary to our Supreme Court’s opinion, and the PUC’s own reasoning, in City
of York.
I agree with the majority’s conclusion that previous applications of the
substantial affirmative benefit test in the context of proposed mergers, which have
anticompetitive overtones not present here, are inapt in analyzing purely internal
restructuring. The majority reasons that a certificate of public convenience should
be granted on a determination that the proposal at issue would be necessary or proper
to serve the public need. Majority op. at 20. Thus, the majority holds that the PUC
EC - 14
could issue a certificate of public convenience based on a determination that it would
be proper for the service of the public. Id. (citing Section 1103(a) of the Public
Utility Code, 66 Pa. C.S. § 1103(a)). I do not disagree with this as a statement of
law. However, I do not believe the Court needs to reach that issue here, because, as
discussed above, financial advantages to the parent and subsidiary constitute
substantial affirmative public benefits justifying issuance of a certificate of public
convenience. The PUC erred in concluding otherwise.
Importantly, Utility did not have to prove with precision what specific
financial benefits would arise from the proposed restructuring. As this Court
explained in McCloskey, it is not necessary to offer specific evidence on how a
transaction will offer substantial affirmative public benefits. Evidence that is general
in nature may support a finding of a public benefit sufficient to justify a
determination that the requested transaction is in the public interest. McCloskey, 195
A.3d at 1065 (citing Popowsky v. Pa. Pub. Util. Comm’n, 937 A.2d 1040 (Pa. 2007)).
Therefore, even if a certificate of public convenience was required, Utility met
its burden of showing a substantial affirmative public benefit by establishing the
financial advantages of Parent’s proposed restructuring. The PUC committed legal
error by concluding otherwise.
IV. Conclusion
For the reasons discussed above, I would reverse the PUC’s decision and find
that no certificate of public convenience was required for Parent’s proposed internal
restructuring. I would further find that even if a certificate of public convenience
was required, the PUC erred as a matter of law by determining that the anticipated
financial advantages demonstrated no substantial affirmative public benefit from
EC - 15
Parent’s proposed internal restructuring. Therefore, respectfully, I also disagree
with the majority’s conclusion that a remand is necessary for the PUC to issue a new
decision applying a different legal standard to determine whether to grant a
certificate of public convenience.
__________________________________
ELLEN CEISLER, Judge
President Judge Leavitt and Judge Crompton join in this dissenting/concurring
opinion.
EC - 16