IN THE SUPREME COURT OF TEXAS
══════════
No. 19-0045
══════════
AEP TEXAS CENTRAL COMPANY AND
T&D SOLUTIONS, LLC, PETITIONERS,
v.
MARTA ARREDONDO, RESPONDENT
══════════════════════════════════════════
ON PETITION FOR REVIEW FROM THE
COURT OF APPEALS FOR THE FOURTH DISTRICT OF TEXAS
══════════════════════════════════════════
Argued September 16, 2020
JUSTICE LEHRMANN delivered the opinion of the Court.
The issues presented in this personal-injury case include whether an electric utility owed
a duty to ensure the safe performance of its independent contractor’s work and whether genuine
issues of material fact exist with respect to the contractor’s own negligence. The court of
appeals answered yes to both questions, resulting in a partial reversal of the trial court’s
summary judgments in favor of the utility and the contractor. We hold that the utility did not
retain control over the pertinent details of the contractor’s work and thus owed no duty that
would otherwise flow from such control. However, we agree with the court of appeals that fact
issues preclude summary judgment for the contractor. Accordingly, we affirm the court of
appeals’ judgment in part and reverse it in part.
I. Background
AEP Texas Central Company is an electric utility. On July 1, 2012, AEP entered into a
two-year contract with T&D Solutions, LLC, pursuant to which T&D was to supply to AEP on
an as-needed basis “all supervision, labor, equipment and specified materials necessary to
perform underground distribution line construction and/or maintenance services,” “underground
distribution line construction and/or maintenance bid projects,” and “storm restoration
services.” 1 The contract designated T&D an “independent contractor[] . . . solely responsible for
the supervision, direction, and control of its employees and Subcontractors.” AEP contracted
with another company, TechServ Consulting and Training Ltd., to inspect the work of AEP’s
contractors, including T&D.
Pursuant to the T&D contract, AEP issued a work order that included a directive to T&D
to remove a stub pole—a utility pole from which electric wires have been removed and the top
portion cut off—located in a municipal right-of-way on the edge of Marta Arredondo’s property
in Falfurrias, Texas. Removal of a stub pole involves “[p]ulling it out of the ground and
returning it back to the yard, [and] filling the hole up with dirt.” T&D removed the pole and
certified the job as complete on December 2, 2013. TechServ in turn certified the job as
complete on December 9, 2013.
On July 30, 2014, Arredondo was injured while mowing her lawn when she stepped into
a hole approximately two-and-a-half feet deep in the area where the pole had been removed.
According to Arredondo, the grass in that area had grown tall because the pole had been left on
1
The “Contract Letter” the parties signed incorporated several additional documents that governed
performance. References to the “contract” include all such documents.
2
the ground for some period of time before being hauled away. Arredondo “called the City” to
report the issue, and an AEP employee was dispatched to the property to fill the hole.
Arredondo sued AEP, T&D, and TechServ for negligence, negligence per se, and gross
negligence. Arredondo alleged that the defendants “had a utility easement” on her property and
“created a defect in the easement property when they removed the pole and failed to fill the hole
or otherwise warn of its existence.” The defendants each moved for no-evidence and traditional
summary judgment, and the trial court granted all three motions. Arredondo appealed.
The court of appeals affirmed the summary judgment as to all claims against TechServ
and as to the negligence per se and gross negligence claims against T&D. 567 S.W.3d 383, 388
(Tex. App.—San Antonio 2018). Arredondo did not file a petition for review, and those portions
of the court of appeals’ judgment are thus final. TEX. R. APP. P. 53.1 (“A party who seeks to
alter the court of appeals’ judgment must file a petition for review.”). The court of appeals
reversed the trial court’s summary judgment as to the negligence claim against T&D and as to all
claims against AEP, remanding the case to the trial court for further proceedings on those claims.
567 S.W.3d at 388. AEP and T&D filed petitions for review, which we granted. We address
each petition in turn.
II. Contractor T&D’s Petition
In holding that summary judgment was improper on Arredondo’s negligence claim
against T&D, the court of appeals first held that the claim sounds in ordinary negligence rather
than premises liability. Id. at 393; see Occidental Chem. Corp. v. Jenkins, 478 S.W.3d 640, 644
(Tex. 2016) (“Although premises liability is itself a branch of negligence law, it is a ‘special
form’ with different elements that define a property owner or occupant’s duty with respect to
3
those who enter the property.”). The court further held that T&D owed Arredondo a duty to
either warn of or make safe the hole it created by removing the utility pole. 567 S.W.3d at 394.
Finally, the court did not address T&D’s argument that Arredondo failed to raise a fact issue as
to whether T&D breached that duty, holding T&D waived the issue by raising it for the first time
in reply to Arredondo’s summary-judgment response. Id. at 394 n.5.
In its petition for review in this Court, T&D takes no issue with the court of appeals’
holdings regarding the nature and scope of the duty T&D owed Arredondo. We thus express no
opinion on that portion of the court of appeals’ analysis. Fort Worth Transp. Auth. v. Rodriguez,
547 S.W.3d 830, 849 (Tex. 2018) (“A petition for review must state all issues or points presented
for review, and issues not presented in the petition for review are waived.” (citing TEX. R. APP.
P. 53.2(f))). Instead, T&D focuses on the breach element of Arredondo’s negligence claim. See
IHS Cedars Treatment Ctr. of DeSoto, Tex., Inc. v. Mason, 143 S.W.3d 794, 798 (Tex. 2004)
(“The elements of a negligence cause of action are the existence of a legal duty, a breach of that
duty, and damages proximately caused by the breach.”). Specifically, T&D contends that (1) the
summary-judgment evidence conclusively establishes that T&D “properly filled the hole with
dirt after it extracted the stub pole on Arredondo’s property” and thus that T&D did not breach
any duty owed to Arredondo, and (2) T&D timely and properly raised that argument in its
motion for summary judgment. As discussed below, we disagree with T&D’s characterization of
the evidence and hold that a fact issue exists as to whether T&D failed to properly fill the hole.
Accordingly, even assuming that T&D properly raised the breach issue in the trial court, the
court of appeals correctly reversed summary judgment as to the negligence claim against T&D.
4
To be entitled to summary judgment, T&D had the burden to prove that no genuine issue
of material fact exists and that T&D is entitled to judgment as a matter of law. Hillis v. McCall,
602 S.W.3d 436, 439–40 (Tex. 2020); TEX. R. CIV. P. 166a(c). 2 We review an order granting
summary judgment de novo, taking as true all evidence favorable to the nonmovant and
indulging every reasonable inference in the nonmovant’s favor. Valence Operating Co. v.
Dorsett, 164 S.W.3d 656, 661 (Tex. 2005).
T&D relies on the deposition of Robert Ramos, the foreman of the T&D crew responsible
for removing the stub pole on Arredondo’s property. Ramos testified that when the crew
removed the pole, the resulting hole was “filled in immediately” with dirt: “[W]hen I removed
this pole, I filled [the hole] up with dirt and I tamped it, and I left it with like six inches of
dirt . . . on [top of] that.” He testified that this occurred before December 2, 2013, when he
certified the job as completed. Arredondo was injured over seven months later. T&D argues
that this evidence amounts to an “undisputed fact” that T&D filled the hole immediately after
removing the stub pole and shows that “T&D safely completed its job in a workmanlike
manner.”
However, as the court of appeals correctly recognized, Arredondo presented evidence
that the two-and-a-half-foot hole in which she fell on July 30, 2014 was in the same location
where T&D had removed the stub pole and was the same size and diameter as a hole produced
by the removal of a utility pole. 567 S.W.3d at 394. The existence, size, shape, and location of
2
As noted, T&D also filed a no-evidence motion for summary judgment under Rule 166a(i), which allows
a party to move for summary judgment, without presenting evidence, “on the ground that there is no evidence of one
or more essential elements of a claim or defense on which an adverse party would have the burden of proof at trial.”
TEX. R. CIV. P. 166a(i). In this Court, T&D focuses only on its traditional motion for summary judgment, arguing
that the summary-judgment evidence conclusively establishes that it did not breach its duty. Thus, we do not
address whether the trial court properly granted T&D’s no-evidence motion.
5
the hole on the date of Arredondo’s injury call into question whether T&D filled the hole created
by removal of the stub pole, or at least whether T&D did so properly. Thus, the evidence of
breach is conflicting, not conclusive. Because a genuine issue of material fact exists as to
whether T&D failed to exercise reasonable care in removing the stub pole, T&D is not entitled to
summary judgment on Arredondo’s negligence claim.
III. Utility AEP’s Petition
Arredondo’s claims against AEP are premised on its alleged liability in tort for harm
caused by the acts or omissions of its independent contractor, T&D. AEP argued in its motion
for summary judgment that, as a matter of law, it owed no duty to ensure that T&D performed its
work in a safe manner. Arredondo responded that AEP owed her a duty in light of AEP’s
contractual right to control T&D and the inherently dangerous nature of the work T&D was
contracted to perform. 3 The court of appeals held that AEP owed a duty arising from its
“contractual right to control the aspect of T&D’s work [removal of the utility pole] that allegedly
caused Arredondo’s injury.” Id. at 399.
In this Court, AEP again argues that it owed no duty to Arredondo with respect to T&D’s
work because AEP did not retain control over the operative details of T&D’s removal of the stub
pole, including filling in the resulting hole. AEP also disputes Arredondo’s alternative theory
that AEP may be liable for its contractor’s actions based on the “inherently dangerous” nature of
the work performed. Arredondo maintains that AEP’s right to control T&D’s work and the
3
Arredondo also argued that AEP owed her a duty as “the dominant easement holder of the property where
th[e] incident occurred.” However, in this Court Arredondo no longer contends that AEP’s alleged status as an
easement holder, which AEP disputes, provides an independent basis for a duty of care in the absence of either
control over T&D’s work or a nondelegable duty arising from the nature of the work T&D performed.
6
nature of that work gave rise to a duty of care. For the reasons discussed below, we agree with
AEP that it owed no duty as a matter of law. See Tri v. J.T.T., 162 S.W.3d 552, 563 (Tex. 2005)
(“The existence of a legal duty is a question of law for the court to decide . . . from the facts
surrounding the occurrence in question.” (citations and internal quotation marks omitted)).
A. No Duty Based on Right to Control
As a general rule, one who employs an independent contractor has no duty to ensure that
the contractor performs its work in a safe manner. Fifth Club, Inc. v. Ramirez, 196 S.W.3d 788,
791 (Tex. 2006). We have recognized an exception to this rule, however, when “the employer
retains some control over the manner in which the contractor performs the work that causes the
damage.” Id. To that end, in Redinger v. Living, Inc., we adopted section 414 of the
Restatement (Second) of Torts, which states:
One who entrusts work to an independent contractor, but who retains the control
of any part of the work, is subject to liability for physical harm to others for
whose safety the employer owes a duty to exercise reasonable care, which is
caused by his failure to exercise his control with reasonable care.
689 S.W.2d 415, 418 (Tex. 1985) (quoting RESTATEMENT (SECOND) OF TORTS § 414 (1977)). If
the right to control a contractor’s work exists, a duty arises regardless of whether actual control
is exercised. Dow Chem. Co. v. Bright, 89 S.W.3d 602, 606 (Tex. 2002) (“It is the [contractual]
right of control, and not the actual exercise of control, which gives rise to a duty to see that an
independent contractor performs work in a safe manner.” (citation and internal quotation marks
omitted) (alteration in original)).
In evaluating whether a duty is owed under section 414, we have explained that an
employer “must have some latitude to tell its independent contractors what to do, in general
terms, . . . without becoming subject to liability.” Koch Ref. Co. v. Chapa, 11 S.W.3d 153, 156
7
(Tex. 1999). Thus, the duty arises where the right to control extends to “the means, methods, or
details of the independent contractor’s work,” Bright, 89 S.W.3d at 606, such that the contractor
“is not entirely free to do the work in his own way,” Chapa, 11 S.W.3d at 155 (quoting
RESTATEMENT (SECOND) OF TORTS § 414 cmt. c). 4 Further, the control “must relate to the
condition or activity that caused the injury.” Clayton W. Williams, Jr., Inc. v. Olivo, 952 S.W.2d
523, 528 (Tex. 1997). Applying those principles, we have held that no duty of care arose with
respect to an independent contractor’s work by virtue of the employer’s general right to order
work started and stopped, Chapa, 11 S.W.3d at 155, to direct when and where the work was
done, Fifth Club, 196 S.W.3d at 791–92, to require that work be done by a certain time, Shell Oil
Co. v. Khan, 138 S.W.3d 288, 295 (Tex. 2004), or to control activities that had nothing to do
with the resulting injury, id. at 294.
Here, Arredondo does not assert that AEP exercised actual control over T&D’s removal
of the stub pole. Rather, she argues that AEP’s contract with T&D gave AEP the right to control
that work, triggering a duty to use reasonable care in exercising such control. The court of
appeals agreed, holding that two provisions in the contract conferred the requisite right to
control:
• [T&D] shall have an authorized representative at the Site to whom [AEP]
may give instructions at all times when Work is being performed.
4
This duty requires the employer “to exercise any retained supervisory control ‘with reasonable care so as
to prevent the work which he has ordered to be done from causing injury to others.’” Clayton W. Williams, Jr., Inc.
v. Olivo, 952 S.W.2d 523, 528 (Tex. 1997) (quoting RESTATEMENT (SECOND) OF TORTS § 414 cmt. a). AEP argues
that the court of appeals erroneously implied that such a duty gives rise to strict vicarious liability for the negligent
acts of an independent contractor regardless of the employer’s own fault. See 567 S.W.3d at 400. AEP contends
that, properly construed, section 414 subjects an employer to liability only for its own negligence in exercising
retained control. Because we hold that no duty arose, we need not address AEP’s arguments regarding the duty’s
scope.
8
• When Work is performed on private property, . . . [T&D] shall use its best
efforts to arrange for the completion of Work to be with the least
inconvenience practicable to [the owner]. Work performance on private
property shall be done as expeditiously as possible and the premises
restored immediately.
567 S.W.3d at 398–99 (ellipsis in original). The court concluded that, by virtue of these two
provisions, 5 AEP “retained control over the method and means of T&D’s work as it related to
removing the utility pole on Arredondo’s property.” Id. at 399. We disagree.
As to the first provision, requiring the presence of a T&D authorized representative to
whom AEP may give unspecified instructions says nothing about AEP’s control over the specific
means and methods of T&D’s work. The Fourth Court of Appeals interpreted a similar
provision in Victoria Electric Co-op, Inc. v. Williams, holding that it had “nothing to do with
right of control” but rather clarified that giving instructions to the contractor’s designated
“superintendent” was equivalent to giving them directly to the contractor. 100 S.W.3d 323, 327
& n.3 (Tex. App.—San Antonio 2002, pet. denied). 6 We agree with that interpretation, which
gives meaning to the provision without wholly supplanting the contract’s designation of T&D as
5
Arredondo cited numerous additional contractual provisions that the court of appeals held “do not relate
to the specific condition or activity from which her injuries arose.” 567 S.W.3d at 399 & n.6. Arredondo disputes
the court’s conclusion as to three of those provisions. Two provisions, which relate to change orders, allow AEP to
add to, delete from, or modify the scope of work by issuing such orders, and require T&D to comply with change
orders even when T&D disputes the scope of work. Arredondo provides no explanation, and we discern none, as to
how those provisions speak to the means and methods of T&D’s work with respect to the removal of the stub pole.
The third provision allows AEP to prohibit or restrict the use of certain specialty tooling. Arredondo contends that
“removing stub poles actually requires T&D to use specialized equipment that AEP can contractually prohibit or
restrict,” but that assertion inaccurately characterizes the record. The “Specialty Tooling” that AEP may
contractually prohibit is defined as “tooling fabricated, developed by or modified by [T&D].” A T&D employee
testified that T&D uses a “digger derrick” to remove a utility pole and uses shovels to fill the resulting hole. There
is no indication in the record that such equipment qualifies as “Specialty Tooling” over which AEP retained control
or that the particular equipment used had anything to do with Arredondo’s injury.
6
The provision stated in pertinent part: “The Contractor shall cause the construction work on the Project to
receive constant supervision by a competent superintendent . . . who shall be present at all times during working
hours where construction is being carried on. . . . Directions and instructions given to the Superintendent by the
Owner shall be binding upon the Contractor.” Victoria Elec., 100 S.W.3d at 327.
9
an independent contractor “solely responsible for the supervision, direction, and control of its
employees and Subcontractors.” See MCI Telecomms. Corp. v. Tex. Utils. Elec. Co., 995 S.W.2d
647, 652 (Tex. 1999) (“When interpreting a contract, we examine the entire agreement in an
effort to harmonize and give effect to all provisions of the contract so that none will be
meaningless.”). At most, the provision is consistent with the recognition that AEP is T&D’s
“boss,” which is insufficient to confer liability under section 414. See Gonzalez v. Ramirez, 463
S.W.3d 499, 507 (Tex. 2015) (“If the fact that the general contractor is the ‘boss’ of a
subcontractor were enough to create liability, the requirement of control would be obsolete.”).
Because the provision sets forth no requirements as to “the means, methods, or details of
[T&D’s] work,” it does not support the court of appeals’ conclusion that AEP owed Arredondo a
duty of care.
The second provision on which the court of appeals relied, which requires that work
performed on private property “be done as expeditiously as possible and the premises restored
immediately,” fares no better. The court of appeals correctly noted that this provision “relates to
the source of Arredondo’s injuries: T&D’s alleged failure to fill in the hole caused by its removal
of a utility pole.” 567 S.W.3d at 399. But the court said nothing about how the provision
confers a right of control as to the means, methods, and details of that work, id., and we see no
such connection. The provision informs the scope of T&D’s work when private property is
involved and requires a particular result—restoration of the premises. But it provides no
indication of how T&D should accomplish that result, such as by using a particular type of fill,
equipment, or technique. See Bright, 89 S.W.3d at 607 (contract stating that its provisions “shall
be deemed to mean that [contractor] shall follow the desires of [owner] in the results of the work
10
only” did not impose a duty of care on the owner). And as noted, a “general requirement that
work be done by a certain time is insufficient to show right of control.” Khan, 138 S.W.3d at
295; see also Fifth Club, 196 S.W.3d at 792.
In sum, we hold that AEP did not have the right to control the means, methods, or details
of T&D’s work with respect to removal of the stub pole or restoration of the property
necessitated by the pole’s removal. Accordingly, AEP did not owe a duty to Arredondo under
section 414. 7
B. No Duty Based on Inherently Dangerous Activity
Arredondo alternatively argues that AEP owed her a “nondelegable duty” with respect to
T&D’s work by virtue of the “inherently dangerous” nature of that work. See Fifth Club, 196
S.W.3d at 795 (explaining that an employer can be held liable for an independent contractor’s
tortious acts “only if the employer maintains detailed control over the independent contractor’s
acts or if the work itself involves a nondelegable duty, whether inherently dangerous or
statutorily prescribed”) (emphasis added). Although the court of appeals did not reach this issue,
the parties have raised and briefed it here, and we address it in the interest of judicial economy.
State v. Morello, 547 S.W.3d 881, 888 (Tex. 2018).
An “inherently dangerous” activity in this context is one in which the danger “stems from
the activity itself rather than the manner of performance.” Fifth Club, 196 S.W.3d at 795. That
is, such activities are “dangerous in their normal, nondefective state.” Cent. Ready Mix Concrete
7
AEP argues that, to the extent it could be held liable under a “retained control” theory, Arredondo’s claim
against it sounds in premises liability, not ordinary negligence. AEP further argues that Arredondo produced no
evidence to support several elements of her premises-liability claim. Arredondo responds that her claim sounds in
ordinary negligence and that, in any event, the evidence raises a genuine issue of material fact as to the elements of a
premises-liability claim. Because we hold that AEP may not be held liable under a retained-control theory, we need
not reach these issues.
11
Co. v. Islas, 228 S.W.3d 649, 653 (Tex. 2007); see also Goolsby v. Kenney, 545 S.W.2d 591, 594
(Tex. App.—Tyler 1976, writ ref’d n.r.e.) (inherently dangerous work “must result in probable
injury to third persons or the public,” meaning that no liability is imposed for an injury that
“arises entirely from the wrongful act of the independent contractor”). The doctrine is thus
exceedingly narrow. See Cent. Ready Mix, 228 S.W.3d at 652 (noting that “Texas courts have
found very few activities so inherently dangerous as to impose a nondelegable duty”).
AEP argues that there is nothing inherently dangerous about the removal of a stub pole
and that Arredondo’s injuries arose from T&D’s allegedly negligent performance of the work,
not the innate danger of the work itself. Arredondo responds that the contract between AEP and
T&D contemplated the performance of “inherently dangerous” electrical work. We agree with
AEP.
Assuming that some electrical work can qualify as inherently dangerous, the work that
allegedly caused Arredondo’s injury does not fall into that category. Rather, T&D’s scope of
work was to remove a stub pole—meaning all live electrical wires had already been removed—
and restore the property. The danger to third persons or the public stems not from the nature of
the work itself but from its improper performance. Accordingly, we hold that the work T&D
performed did not constitute an inherently dangerous activity giving rise to a nondelegable duty
of care by AEP.
C. No Duty Based on Statute
Finally, by pleading a negligence per se claim, Arredondo impliedly asserted that AEP
owed her a duty of care imposed by statute. See Carter v. William Sommerville & Son, Inc., 584
S.W.2d 274, 278 (Tex. 1979) (“Negligence per se is a tort concept whereby a legislatively
12
imposed standard of conduct is adopted by the civil courts as defining the conduct of a
reasonably prudent person.”). The court of appeals held that AEP did not challenge Arredondo’s
negligence per se claim in its summary-judgment motions and that the trial court therefore erred
in granting AEP summary judgment on that claim. 567 S.W.3d at 400. We disagree.
As noted, AEP argued in its no-evidence motion that Arredondo produced no evidence
that AEP “had any duty to [Arredondo]” or “breached any legal duty to [Arredondo].” See TEX.
R. CIV. P. 166a(i) (a no-evidence motion for summary judgment “must state the elements as to
which there is no evidence”). Thus, to the extent Arredondo wished to pursue a negligence claim
premised on a duty imposed by statute, she bore the burden to respond to the motion with
summary-judgment evidence raising a genuine issue of material fact on the existence and breach
of such a duty. See id. In her response to AEP’s motion, however, Arredondo cited no statute
that allegedly imposed a duty on AEP. Nor did she do so in her brief in the court of appeals or in
this Court. Accordingly, we see no basis on which to question the trial court’s summary
judgment on Arredondo’s negligence per se claim. 8
D. Disposition of Claims
The existence of a duty of care is an element of Arredondo’s negligence, negligence per
se, and gross negligence claims. See La.-Pac. Corp. v. Andrade, 19 S.W.3d 245, 246 (Tex.
1999) (“[W]hat separates ordinary negligence from gross negligence is the defendant’s state of
8
In response to T&D’s summary-judgment motion, Arredondo argued that a federal statute requiring
employers to furnish a safe workplace imposed a duty of care on T&D. See 29 U.S.C. § 654(a)(1). The court of
appeals rejected that statute as a basis for a negligence per se claim against T&D, holding that the statute is designed
to protect employees and that Arredondo thus “failed to present any evidence T&D violated a statute that was
designed to prevent an injury to the class of persons to which Arredondo belongs.” 567 S.W.3d at 395; see El Chico
Corp. v. Poole, 732 S.W.2d 306, 312 (Tex. 1987) (explaining that a threshold question in determining whether to
adopt a statute as a standard for negligence is whether “the statute is designed to prevent an injury to that class of
persons to which the injured party belongs”).
13
mind[.]”); Ford Motor Co. v. Miles, 967 S.W.2d 377, 390 (Tex. 1998) (Gonzalez, J., concurring)
(“[N]egligence and gross negligence are not separable causes of action but are inextricably
intertwined.”). AEP did not owe Arredondo a duty with respect to T&D’s work, and the trial
court thus correctly granted summary judgment on all of Arredondo’s claims against AEP.
IV. Conclusion
Because a genuine issue of material fact exists as to whether T&D breached a duty of
care, the court of appeals correctly reversed summary judgment on Arredondo’s negligence
claim against T&D. We thus affirm the court of appeals’ judgment as to that claim. However,
because AEP owed no duty with respect to T&D’s work, the court of appeals erred in reversing
summary judgment as to Arredondo’s claims against AEP. Accordingly, we reverse the court of
appeals’ judgment as to those claims and render judgment for AEP. We remand the case to the
trial court for further proceedings on the negligence claim against T&D.
________________________________
Debra H. Lehrmann
Justice
OPINION DELIVERED: November 20, 2020
14