Kincaid Henry Building Group Inc v. Heart of Howell LLC

         If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
              revision until final publication in the Michigan Appeals Reports.




                        STATE OF MICHIGAN

                        COURT OF APPEALS


KINCAID HENRY BUILDING GROUP, INC.,                            UNPUBLISHED
                                                               December 3, 2020
           Plaintiff/Counterdefendant/Third-
           Party Defendant-Appellee,

v                                                              No. 346034
                                                               Livingston Circuit Court
HEART OF HOWELL, LLC,                                          LC No. 14-028116-CK

           Defendant/Counterplaintiff/Cross-
           Defendant/Third-Party Plaintiff-
           Appellee,

and

STEPHEN DAVID, INC.,

           Defendant/Counterplaintiff/Cross-
           Plaintiff-Appellant,

and

COMERICA BANK, PLATTE RIVER
INSURANCE COMPANY, and REKON
CORPORATION,

           Defendants-Appellees,

and

THYSSENKRUPP ELEVATOR COMPANY,

           Defendant,

and

EBELS CONSTRUCTION, LLC,


                                           -1-
               Third-Party Defendant,

and

DE LAU FIRE & SAFETY, INC.,

               Third-Party Defendant/Third-Party
               Plaintiff-Appellee,

and

MODERN DRYWALL, INC.,

               Third-Party Defendant/Cross-
               Plaintiff/Third-Party Plaintiff-
               Appellee,

and

AB LOCK AND SAFE, INC., doing business as
FISHER DOOR & HARDWARE,

               Third-Party Defendant.


Before: REDFORD, P.J., and RIORDAN and TUKEL, JJ.

PER CURIAM.

        Cross-plaintiff Stephen David, Inc. (SDI) appeals as of right the trial court’s judgment in
favor of SDI on its construction lien claim against Heart of Howell, LLC (HOH) and postjudgment
order awarding SDI attorney fees of $4,224 under the Construction Lien Act (CLA), MCL
570.1101 et seq. For the reasons set forth in this opinion, we affirm in part, but vacate the trial
court’s judgment and award of attorney fees and remand for further proceedings.

                                        I. BACKGROUND

       This case arises from a dispute between HOH and SDI regarding an unpaid balance for
SDI’s work on the Heart of Howell project (“HOH building project”) which involved renovation
of three historical buildings purchased by HOH in downtown Howell known as the “Swan’s,
Thistledown, and Spags buildings.” SDI contracted with Kincaid Henry Building Group, Inc.
(Kincaid), the general contractor on the HOH building project, to perform paint removal and
masonry work. In September 2013, Kincaid terminated SDI from the project because of alleged
poor workmanship, SDI’s failure to timely complete work, and insubordination. Replacement
contractors finished the work that SDI did not complete. On October 7, 2013, SDI recorded a
claim of lien against the HOH building project, stating that it last provided labor and materials on


                                                  -2-
September 17, 2013, and that its lien claim amounted to $80,969 by taking the contract amount of
$177,411 and deducting $96,442 for payments it received from Kincaid. Kincaid filed suit against
HOH, SDI, and numerous other parties, and SDI cross-claimed against HOH for foreclosure of its
construction lien. Following the dismissal of all claims involving other parties, the trial court held
a nine-day bench trial on SDI’s cross-claim against HOH.

        The trial court found that SDI had been terminated for no fault of its own and was entitled
to a claim of lien valued at $57,707.14. The trial court ruled that SDI may recover its reasonable
attorney fees under the CLA, but limited the amount to 24% of the attorney fees that were incurred
solely during trial and later awarded SDI $4,224 in attorney fees.

                                   II. STANDARD OF REVIEW

        We review de novo a trial court’s decision regarding a question of law, but the trial court’s
factual findings at a bench trial are reviewed for clear error. In re Receivership of 11910 South
Francis Rd, 492 Mich 208, 218; 821 NW2d 503 (2012). A finding is clearly erroneous, if, after a
review of the entire record, this Court is left with a definite and firm conviction that the trial court
made a mistake. Alan Custom Homes, Inc v Krol, 256 Mich App 505, 512; 667 NW2d 379 (2003)
(citations omitted). To the extent that this issue requires interpretation and application of the CLA,
we review issues of statutory interpretation de novo. Id. at 507.

                                           III. ANALYSIS

                                            A. WAIVER

       HOH claims that SDI waived any claim of error respecting the trial court’s calculation of
the amount of its lien or that SDI should be judicially estopped from challenging the trial court’s
decision on this issue. We disagree that waiver is applicable to the case at bar.

        A waiver occurs when a party intentionally relinquishes a known right. Sweebe v Sweebe,
474 Mich 151, 156-157; 712 NW2d 708 (2006). “It is also well-settled that a waiver may be
shown by express declarations or by declarations that manifest the parties’ intent and purpose.”
Id. at 157 (citation omitted). To constitute a waiver, there must be a showing of “an affirmative
expression of assent” and an intention to plainly relinquish a right. VHS Huron Valley Sinai Hosp
v Sentinel Ins Co, 322 Mich App 707, 716; 916 NW2d 218 (2018). Judicial estoppel is an equitable
doctrine which prevents a party from prevailing on one phase of a case on an argument and then
relying on a contradictory argument to prevail in another phase. Spohn v Van Dyke Public Sch,
296 Mich App 470, 479; 822 NW2d 239 (2012). The doctrine is used to preserve the court’s
integrity by preventing a party by abusing the judicial process through cynical gamesmanship. Id.
at 479-480. For the judicial estoppel doctrine to apply, there must be some showing that the court
in the earlier proceedings accepted an inconsistent position advanced by the litigant as true. Id. at
480.

       In support of its waiver or estoppel argument, HOH relies on the fact that SDI moved for
an order permitting it to order less than the full transcript of the lower court proceedings for
purposes of appeal. At the hearing on SDI’s motion, counsel for SDI stated that “the only issue
that we intended to pursue on appeal was the issue of attorney fees under the [CLA].” The trial
court granted the motion permitting SDI to order less than the full transcript of the lower court


                                                  -3-
proceedings. However, SDI apparently decided otherwise and it ordered a complete transcript of
the proceedings in this case.

        Although SDI stated an intention to only pursue the issue of attorney fees on appeal, its
statements in its motion and at the motion hearing do not otherwise reflect that SDI plainly
intended to relinquish all right to pursue additional appellate relief respecting other claimed errors
by the trial court. VHS Huron Valley Sinai Hosp, 322 Mich App at 716. Accordingly, we are not
persuaded that SDI waived the instant claim of error. Further, although SDI did not inform the
trial court of an intention to challenge the court’s determination of the amount of SDI’s
construction lien, SDI’s decision to raise the issue on appeal is not necessarily an inconsistent
position, but rather simply reflects that SDI later decided to ultimately pursue this additional claim
of error. The earlier statements were associated with SDI’s request to order less than a full
transcript of the proceedings, but SDI later ordered a complete transcript and the complete
transcript has been filed with this Court. SDI is not judicially estopped from challenging the trial
court’s determination of the amount of its construction lien on appeal.1

                             B. THE CONSTRUCTION LIEN ACT

                   1. GENERAL PRINCIPLES FOR CALCULATING LIENS

       In Ronnisch Constr Group, Inc v Lofts on the Nine, LLC, 499 Mich 544, 552-553; 886
NW2d 113 (2016) (quotation marks, alterations, and citations omitted), our Supreme Court
explained:

               The CLA is intended to protect the interests of contractors, workers, and
       suppliers through construction liens, while protecting owners from excessive costs.
       The fundamental purpose of the CLA with respect to contractors, workers, and
       suppliers is to provide a method to secure payment for their labor and materials.
       The Legislature has declared that the CLA is a remedial statute that shall be
       liberally construed to secure the beneficial results, intents, and purposes of the act.
       Accordingly, when interpreting the CLA, we should always be mindful of the
       CLA’s intended purpose.

                                               * * *

               The first inquiry in determining whether a party may seek attorney fees
       under the CLA is whether the party is a lien claimant. Under [MCL 570.1]118(2),
       the trial court has discretion to award attorney fees to a lien claimant who is the
       prevailing party. The CLA defines a lien claimant as a person having a right to a
       construction lien under the act.




1
  We similarly reject HOH’s suggestion that SDI’s earlier-filed motion to file less than a full
transcript thereby waived this Court’s jurisdiction.


                                                 -4-
        The CLA specifies the extent to which a lien claimant may claim a right to a construction
lien in MCL 570.1107 which provides in relevant part:

               (1) Each contractor, subcontractor, supplier, or laborer who provides an
       improvement to real property has a construction lien upon the interest of the owner
       or lessee who contracted for the improvement to the real property, as described in
       the notice of commencement given under section 108 or 108a, the interest of an
       owner who has subordinated his or her interest to the mortgage for the improvement
       of the real property, and the interest of an owner who has required the improvement.
       A construction lien acquired pursuant to this act shall not exceed the amount of the
       lien claimant’s contract less payments made on the contract.[2]

                                              * * *

              (6) If the real property of an owner or lessee is subject to multiple
       construction liens, the sum of the construction liens shall not exceed the amount the
       owner or lessee agreed to pay the person with whom he or she contracted for the
       improvement as modified by all additions, deletions, and other amendments, less
       payments made by or on behalf of the owner or lessee, pursuant to either a
       contractor’s sworn statement or a waiver of lien, in accordance with this act.

       MCL 570.1120 provides:

              If a lien claimant, by reason of the failure of an owner or lessee to perform
       the contract, and without fault on the part of the lien claimant, has been prevented
       from completely performing the contract, the lien claimant shall be entitled to
       compensation for as much as was performed by the claimant under the contract, in
       proportion to the price stipulated for complete performance of the whole contract,
       less any payments made to the lien claimant and also to any additional damages
       which the lien claimant may be entitled to as a matter of law.

       The plain language of these statutory provisions provides that the amount of a lien
claimant’s construction lien must be calculated by determining the total value of the claimant’s
contract, the amount of work performed by the claimant under the contract, i.e., the proportion or
percentage completed, and the amount paid by the owner in relation to the work performed. The
value of the total contract multiplied by the proportion of the contract completed equals the amount
owed by the owner, minus the amount paid by the owner, equals the value of the lien. MCL
570.1107(1) and MCL 570.1120. Under MCL 570.1107(6), however, where an owner is subject
to multiple construction liens, the sum of the construction liens shall not exceed the amount the
owner agreed to pay under its contract as modified by change orders that added, deleted, or




2
  See also Erb Lumber, Inc v Gidley, 234 Mich App 387, 396; 594 NW2d 81 (1999) (“The proper
amount of a lien is the lien claimant’s contract price less payments made on that contract to the
lien claimant.”) (Emphasis added.)


                                                -5-
amended the contract, less payments made by the owner pursuant to contractor sworn statements
or lien waivers.

                      2. OWNER’S DEFENSE UNDER MCL 570.1107(6)

        SDI first argues that the trial court erred in determining the amount of SDI’s construction
lien claim against HOH. We agree that the trial court erred in its application of the law and that
remand for further consideration of SDI’s construction lien claim is necessary. Although the
parties frame the issue as whether the trial court correctly determined the amount of SDI’s
construction lien, that issue hinges on whether HOH may invoke the defense set forth in MCL
570.1107(6).

        In Vugterveen Sys, Inc v Olde Millpond Corp, 454 Mich 119; 560 NW2d 43 (1997), the
lodestar case of Michigan jurisprudence addressing the application of MCL 570.1107(6), our
Supreme Court addressed whether a property owner could use payments made to a second general
contractor as a defense to a construction lien foreclosure asserted by a subcontractor. The Court
acknowledged that the system under the CLA could be used by “unscrupulous contractors to force
property owners to pay excessive construction charges.” Id. at 124. Therefore, the Legislature
included in the CLA “a defense to liens that would force owners to pay more than the price stated
in the general contract.” Id. In Vugterveen, the general contractor, Vander Wall Construction,
contracted with the plaintiff subcontractor to perform work on two units in a condominium
building for a total amount of $9,750. The defendant owner of the property later fired both the
general contractor and Vugterveen which prompted Vugterveen to record a construction lien and
notice of furnishing against the property. Id. at 126. The owner of the property, Olde Millpond,
paid $276,969 to complete construction, $10,374 more than it had agreed to pay Vander Wall to
complete the construction work under their contract. Id.

        Our Supreme Court evaluated Olde Millpond’s claim that MCL 570.1107(6) provided a
defense to Vugterveen’s construction lien because it paid more than the original contract price to
complete the project. Id. at 127. The Court noted that in enacting MCL 570.1107(6), the
Legislature intended to protect owners of real property “from excessive liens by allowing an owner
to rely on the price set forth in its contract with the general contractor.” Id. at 128. The Court
rejected Olde Millpond’s assertion that MCL 570.1107(6) directly applied to the case and that it
could not be required to satisfy an outstanding construction lien because it had already paid an
amount in excess of the original contract price. First, our Supreme Court concluded that the terms
in MCL 570.1107(6), “person with whom [the owner] contracted,” did not contemplate situations
in which more than one general contractor served on the job, or factual scenarios in which a general
contractor and its subcontractors were fired and subsequently replaced. Id. at 128. The Court
explained:

       Further, Olde Millpond’s analysis allows an owner to cut off liens held by
       subcontractors by merely firing them and hiring successor contractors. Under this
       reading, an owner would be able to assert [MCL 570.1107(6)] as a defense to all
       liens held by subcontractors on the first general contract whenever the owner pays
       the successor contractors amounts which, when added to the payments already
       made on the first general contract, exceed the price of the first general contract.



                                                -6-
       This is clearly contrary to the act’s stated purpose of protecting the rights of such
       parties. Thus, this reading must be rejected. [Id.]

        Because MCL 570.1107(6) must be interpreted in a manner “so as to give full effect to the
act’s purpose of protecting the interests of builders as well as owners[,]” our Supreme Court
clarified that the phrase “payments made” in MCL 570.1107(6) referred only to “payments made
on the specific contract between the owner and the person with whom the owner contracted.” Id.
at 129. The Court clarified:

       Thus, Olde Millpond may use all payments made on the contract with Vander Wall
       as a defense to Vugterveen’s lien because Vugterveen was a subcontractor on the
       contract between Olde Millpond and Vander Wall. Olde Millpond may not use
       payments made on the second general contract as a defense to Vugterveen’s lien
       because these payments were not made on the relevant contract. [Id.]

        Our Supreme Court held that Olde Millpond could only raise MCL 570.1107(6) as a
defense if it could establish that what it paid under the contract with Vander Wall, together with
the claim of lien asserted by Vugterveen, exceeded the cost of the Vander Wall contract. Id.
Because the trial court had not factually determined how much Olde Millpond paid under the
Vander Wall contract “as attested by sworn statements or waivers of lien,” the Court remanded the
case to the trial court to allow it to undertake that inquiry. Id. Our Supreme Court directed that
“Vugterveen has a valid lien to the extent that the lien and the payments made by Olde Millpond
on the Vander Wall contract do not exceed the price of the contract between Olde Millpond and
Vander Wall.” Id. at 130, 134.

        SDI essentially argues that the trial court erred as a matter of law by deducting from the
amount of its construction lien the costs that HOH paid to other subcontractors to complete the
work on the project that was not finished by SDI. SDI relies upon MCL 570.1107(1), which
provides that “[a] construction lien acquired pursuant to this act shall not exceed the amount of the
lien claimant’s contract less payments made on the contract.” (Emphasis added.) MCL
570.1103(4) defines “contract” as “a contract, of whatever nature, for the providing of
improvements to real property, including any and all additions to, deletions from, and amendments
to the contract.”

         Neither MCL 570.1107(1) nor MCL 570.1120 authorize HOH to deduct from SDI’s lien
the payments HOH made to additional subcontractors who completed work on the project after
SDI’s termination by Kincaid. MCL 570.1107(6) also does not authorize such a deduction.
Notably, HOH points to no provision in the CLA that allows HOH to deduct what the parties and
the trial court characterized as the “cost of cover.” Indeed, in Vugterveen, 454 Mich at 128, our
Supreme Court expressly disavowed an interpretation of MCL 570.1107(6) that would allow “an
owner to cut off liens held by subcontractors by merely firing them and hiring successor
contractors.” Specifically, the Court rejected an interpretation of the CLA that would allow an
owner to rely on MCL 570.1107(6) as a defense to a lien claim that it had paid amounts to
additional subcontractors that, when added to the payments made on the first general contract,
exceed the price set forth in the first general contract.




                                                -7-
         HOH urged the trial court to consider the total contract price minus the amount paid minus
its cost to cover as the method for calculating SDI’s lien amount. Under that formula, HOH urged
the trial court to deduct from SDI’s contract the amounts that it paid to replacement contractors to
finish the work that SDI started. HOH has advanced the argument that its costs to cover paid to
replacement subcontractors to complete the work left undone by SDI, a subcontractor, should be
deducted from SDI’s construction lien under MCL 570.1107(1). The record reflects that the trial
court agreed with and applied HOH’s formula to reduce SDI’s lien claim by amounts paid to the
subcontractors which were hired after SDI’s termination from the project. The CLA, however,
does not permit doing so.

       On appeal, HOH attempts to distinguish this case from Vugterveen on the ground that the
replacement subcontractors, Helms and Zimmerman Masonry, Inc., were both hired and paid by
Kincaid. This assertion, however, is not supported by a close reading of the case. Specifically, in
Vugterveen, 454 Mich at 128, our Supreme Court disagreed with the interpretation of
MCL 570.1107(6) advanced by the owner, Olde Millpond, which argued that it should not have to
pay any outstanding liens because it had already paid more than the original contract price to
complete the building project. Our Supreme Court rejected this interpretation because
MCL 570.1107(6) did not expressly address factual scenarios in which a general contractor and its
subcontractors were fired and replaced.

        The principles articulated in Vugterveen apply to this case. Although HOH does not seek
to completely cut off SDI’s construction lien, it asserts the defense set forth in MCL 570.1107(6)
to reduce the amount of SDI’s lien. In Vugterveen, 454 Mich at 129, our Supreme Court explained
that MCL 570.1107(6) must be interpreted in a manner that protects owners like HOH from paying
lien claims in excess of the contract terms, and that the defense of MCL 570.1107(6) may be
invoked, but that the phrase “payments made” “refers to payments made on the specific contract
between the owner and the person with whom the owner contracted.” In that case, the Court held
that payments made by Olde Millpond on the general contract with Vander Wall could be used as
a defense to Vugterveen’s lien, because Vugterveen constituted a subcontractor under the contract
that existed between Vander Wall and Olde Millpond. Id. at 129. Accordingly, under the statute,
HOH could assert as a defense to SDI’s lien claim the payments that it made on the contract with
Kincaid, “the person with whom [HOH] contracted,” but such amounts would only be a defense
to the extent that “the sum of the construction liens . . . exceed[ed] the amount” that HOH agreed
to pay Kincaid under their contract. MCL 570.1107(6). In Vugterveen, 454 Mich at 129, our
Supreme Court expressly recognized the limitation of the MCL 570.1107(6) defense:

              Olde Millpond will have a defense to Vugterveen’s lien if it can show that
       the sum of payments made pursuant to sworn statements and waivers of lien under
       the Vander Wall contract plus Vugterveen’s claim of lien exceed the price of the
       Vander Wall contract.

        Therefore, under the CLA, contrary to HOH’s argument in the present case, an owner of
real property may not simply rely on MCL 570.1107(6) to assert that it was required to pay
additional “costs of cover” to complete a building project, and then attempt to reduce the
construction lien of a subcontractor which, for whatever reason, did not finish its work. Instead,
to establish entitlement to reduce SDI’s claimed lien, HOH was required to demonstrate that the



                                                -8-
payments it made under the sworn statements and lien waivers under the Kincaid contract, plus
SDI’s claim of lien, exceeded the price of its contract with Kincaid. Vugterveen, 454 Mich at 129.

        SDI argues that the trial court erred by relying on Steelcon, Inc v Bennett & Wright Group,
Inc, 257 F Supp 2d 895 (ED Mich, 2003), to calculate the amount of SDI’s lien. In Steelcon, which
involved consolidated cases, the plaintiff subcontractor, subcontracted to perform modifications
to the owner’s slag grinding and handling plant in Detroit. Id. at 896-897. After not being fully
paid, the plaintiff sued to foreclose on its construction lien against the owner’s property. Id. at
897. The cases were removed to federal court, and in the context of the plaintiff’s motion for
summary judgment against the owner and general contractor, the federal district court, reading
MCL 570.1107(6) and MCL 570.1110(7) together, held that, if a subcontractor properly files a
notice of furnishing under the CLA, an owner may not invoke the defense of MCL 570.1107(6)
by relying on the sworn statements or lien waivers of a general contractor. Steelcon, 257 F Supp
2d at 899. The court further concluded that MCL 570.1107(6) did not limit the plaintiff’s lien
because it had filed a notice of furnishing, and therefore, the owner could not rely on the general
contractor’s sworn statements or lien waivers, and thus the owner had not made payments pursuant
to the sworn statements or lien waivers of a general contractor as required to invoke the defense
set forth in MCL 570.1107(6). Steelcon, 257 F Supp 2d at 900. In our view, the Steelcon decision
does not support SDI’s contention that it contained a specific calculation formula for determining
the amount of SDI’s construction lien in this case.

        In Vugterveen, 454 Mich at 129, our Supreme Court instructed that an owner raising the
defense set forth in MCL 570.1107(6) must demonstrate “that the sum of payments made pursuant
to sworn statements and waivers of lien under the [general contractor’s] contract plus [the
subcontractor’s] claim of lien exceed the price of the . . . contract [between the owner and the
general contractor].” Throughout the proceedings in the trial court, HOH presented evidence
establishing what HOH paid on its contract with Kincaid through the testimony of Courtney
Tarara. For example, on cross-examination by SDI’s counsel, Tarara estimated the initial contract
amount between HOH and Kincaid at approximately $1.7 million. In their posttrial briefs, SDI
and HOH both agreed that the specific amount of the contract between Kincaid and HOH
amounted to $1,716,787.25. Regarding payments, Tarara stated that before Kincaid left the project
and submitted its last sworn statement, HOH had paid Kincaid $1,263,500.67. Tarara also
recounted that in order to discharge the lien Kincaid had recorded against HOH’s property, HOH
made later additional payments of $95,000 and $310,714.24 on the contract, with the payment of
$310,714.24 paid to Kincaid’s subcontractors. On direct examination, Tarara also testified
regarding discrete payments made to Kincaid’s subcontractors.

        The trial court, however, did not make any factual findings concerning (1) the total amount
of the contract between Kincaid and HOH, (2) whether the sum of payments HOH made in
conformance with sworn statements and lien waivers under the contract between Kincaid and
HOH, plus SDI’s claim of lien, exceeded the price set forth in the contract between Kincaid and
HOH. Instead, perhaps because of the trial court’s erroneous legal conclusion that HOH could
simply defend SDI’s claim of lien by arguing that HOH had to pay additional subcontractors to
finish the building project, and its misunderstanding concerning what proofs HOH was required
to establish to support a defense under MCL 570.1107(6), the trial court simply did not address
and determine these pivotal factual issues. Moreover, although the trial court cited MCL
570.1107(6) in its written opinion, it did not apply the statute to the facts of this case.


                                                -9-
        HOH claims that SDI “invited error”3 because it conceded in the trial court that what was
paid to additional subcontractors to complete the work that SDI did not perform could be deducted
from SDI’s lien. We disagree. The record reflects that the parties and the trial court
misapprehended the defense set forth in MCL 570.1107(6), and this misunderstanding resulted in
the deduction of the costs paid to cover SDI’s work to new subcontractors from the amount of
SDI’s construction lien, rather than determining whether HOH’s payments on the contract with
Kincaid, combined with the payments made to SDI, exceeded the price of the contract between
HOH and Kincaid. Vugterveen, 454 Mich at 129, 134.

        We conclude that this case must be remanded to the trial court for it to render the necessary
findings of fact and to then make a legal determination regarding whether HOH established a
defense under MCL 570.1107(6) to SDI’s claim of lien. The trial court must apply MCL
570.1107(6) as directed by Vugterveen to determine whether the sum of the construction liens
exceed the amount HOH agreed to pay Kincaid for the improvements as modified by all additions,
deletions, and other amendments to the Kincaid contract, less payments made by or on behalf of
HOH pursuant to either a contractor’s sworn statement or a waiver of lien, in accordance with the
CLA.

        SDI disputed below whether the payments that HOH made to subcontractors in the amount
of $310,714.24 were in fact made to subcontractors who had contracted with Kincaid, and SDI
maintains on appeal that payments to the replacement subcontractors were unrelated to the contract
between Kincaid and HOH. This Court is an error-correcting Court, and its “review is generally
limited to matters actually decided by the lower court.” Jawad A Shah, MD, PC v State Farm Mut
Auto Ins Co, 324 Mich App 182, 210; 920 NW2d 148 (2018). On remand, the trial court must
render factual findings concerning (1) the total amount of the contract between HOH and Kincaid,
(2) the amount of payments HOH made under that contract, (3) whether the sum of the payments
HOH made were in conformance with the sworn statements and lien waivers under that contract
between HOH and Kincaid, and (4) whether the sum of the liens claimed in relation to HOH and
Kincaid’s contract, including SDI’s claim of lien, exceeded the contract between Kincaid and
HOH.

        SDI further argues that under MCL 570.1107(6) and Vugterveen, the trial court should not
have admitted and considered evidence of payments made to replacement subcontractors to
complete the work left undone by SDI because the replacement subcontractors were paid under a
second contract between HOH and Rekon, the replacement general contractor, and no evidence
was presented that these subcontractors were paid by Kincaid under its contract with HOH. The
record, however, does not support this assertion. Specifically, both Tarara and Dan Zimmerman
of Zimmerman Masonry, Inc., testified that the replacement contractors that completed SDI’s work
were paid under the contract with Kincaid. Tarara further stated that Trust Thermal was hired to
complete the exterior paint removal that SDI did not complete, and HOH paid Kincaid
approximately $33,000 for the work that Trust Thermal performed. Helms was hired to complete



3
   As this Court stated in Cassidy v Cassidy, 318 Mich App 463, 476; 899 NW2d 65 (2017),
“ ‘[i]nvited error’ ” is typically said to occur when a party’s own affirmative conduct directly
causes the error.”


                                                -10-
the sealing of the brick work and HOH paid $7,203 for that work. HOH similarly paid Kincaid
payments of $34,111.58 and $24,970.05 for Zimmerman’s masonry work on the HOH building
project. Zimmerman also testified that after signing a subcontract with Kincaid in September
2013, Kincaid fully paid for its services and had submitted a full unconditional lien waiver for the
project.

        SDI also argues that evidence of payments made to replacement contractors should not
have been admitted and considered by the trial court as “cost to cover” because the work completed
by the subcontractors went far beyond the scope of work that SDI contracted to complete. The
trial court indicated in its opinion that it made one adjustment for the expansion of the work beyond
the scope of the SDI contract respecting work Zimmerman Masonry, Inc. performed. SDI,
however, describes, based upon the record, several instances in which the later subcontractors
performed work additional to and different from the work SDI contracted to perform. SDI submits
that it contracted to complete chemical paint removal on the HOH building project, but HOH
contracted with Trust Thermal to perform soda-blasting of the brick to remove paint which caused
additional damage that HOH paid to repair. SDI contends that the cost of the amount for the repairs
occasioned by Trust Thermal’s work at HOH’s request should not have been deducted from SDI’s
lien. SDI also submits that HOH’s principal, Joseph Parker, chose a new type of brick for the
HOH building project after SDI had already installed the brick HOH chose for the project which
substantially changed the project from what SDI had contracted to perform. Thus, SDI argues that
any attempt by HOH to deduct the cost that Zimmerman Masonry charged for installing the new
brick from SDI’s lien is inappropriate. During trial, Rich Stouffer, SDI’s principal, further testified
that the work that Zimmerman Masonry completed went beyond SDI’s scope of work, and Dan
Zimmerman acknowledged in his testimony that the scope of work for Zimmerman Masonry, Inc.
“mushroomed” over the life of the project.

         In its opinion, the trial court treated the “Total Repair/Cost to Cover” as a category of costs
that it deducted from the total subcontract price for SDI’s services minus the amounts reflected by
lien waivers for painting and masonry work performed by SDI. The trial court reduced SDI’s lien
claim by the amount of the “Total Repair/Cost to Cover” but the record is not entirely clear
regarding what work may have been performed to repair defective work by SDI and what work
constituted completion of the work SDI contracted to perform but because Kincaid terminated SDI
it did not. These are not distinctions without a difference. Repair of defective work by SDI could
properly be considered by the trial court to determine what proportion of SDI’s contract SDI
completed. Deduction of HOH’s cost of cover to complete SDI unfinished work, however, is not
authorized by the CLA for calculation of the amount of SDI’s lien claim.

        MCL 570.1107(1) and MCL 570.1120, when read in conjunction, do not prescribe the
deduction of the cost to cover the completion of the work that SDI could not perform because of
its termination. Under these statutory provisions, an owner is required only to pay for the amount
of work performed by the subcontractor and if it hires another contractor to complete the project
it must pay that contractor for the work it performs and cannot reduce the unpaid lien claimant’s
construction lien by the amount it paid the newly hired contractor. This is because the
subcontractor lien claimant is only entitled to be paid for the proportion of the work it actually
performed. The proper amount of a lien is the lien claimant’s contract price in relation to the
proportion of the work performed, less payments made on that contract to the lien claimant. MCL
570.1107(1); Erb Lumber Co v Homeowner Constr Lien Recovery Fund, 206 Mich App 716, 720;


                                                 -11-
522 NW2d 917 (1994). Therefore, the scope of the construction lien at issue depends on what the
lien claimant performed and does not encompass the entire project as later completed by others.
MCL 570.1120. Under MCL 570.1107(1), the amount of the lien is limited to the amount owed
for the work performed under the applicable contract. C D Barnes Assoc, Inc v Star Heaven, LLC,
300 Mich App 389, 427-428; 834 NW2d 878 (2013). Noticeably absent from the trial court’s
opinion, however, is any indication of a determination of the proportion of SDI’s contract that SDI
completed.

        MCL 570.1107(6) specifies that the sum of the construction liens on real property “shall
not exceed the amount the owner [] agreed to pay the person with whom he [] contracted for the
improvement as modified by all additions, deletions, and other amendments, less payments made
by or on behalf of the owner,” as evidenced by sworn statements or lien waivers. Admission of
cost of cover evidence respecting the completion of the work for which SDI contracted for the
project should not have been used by the trial court to determine the amount of SDI’s lien for the
work it performed and for which it had not been paid. Further, the additional costs made necessary
merely because the owner changed the project’s scope beyond the scope of the subcontractor’s
contract cannot be factored into the calculation of the subcontractor’s lien unless the lien claimant
actually agreed to perform the added work and it became part of the subcontractor’s total contract
price. Reduction of the construction lien amount by the cost of cover or because of an owner’s
later expansion or change of the scope of the work does not comport with MCL 570.1107(1) and
MCL 570.1120, nor is it authorized under MCL 570.1107(6).

         Later in its opinion the trial court stated that the value of SDI’s completed work should not
be reduced by the value of the work performed by replacement contractors because SDI had been
fired through no fault of its own and the evidence did not convince the trial court that SDI provided
defective performance respecting the work it performed, nor that Zimmerman Masonry, Inc.
merely continued and finished work within the same scope of SDI’s contract. Despite these
significant factual findings, the trial court indicated that it concluded that SDI’s lien claim could
be reduced by the cost of cover incurred by HOH. In so doing, the trial court erred to the extent
that it calculated the amount of SDI’s construction lien by subtracting the cost of cover and the
cost of any work beyond the scope of SDI’s contract with Kincaid in relation to Kincaid’s contract
with HOH after termination of SDI.

                 C. ADVERSE INFERENCE REGARDING JOSEPH PARKER

        SDI next argues that the trial court erred by not inferring that because HOH failed to call
its principal, Joseph Parker, as a witness, his testimony would have been adverse to HOH. We
disagree.

       We review de novo the legal question whether the trial court should have drawn an adverse
inference against HOH for its failure to call Parker as a witness. Kuhlgert v Mich State Univ, 328
Mich App 357, 371; 937 NW2d 716 (2019). As a preliminary matter, HOH contends that SDI
waived this issue because during a motion hearing that preceded trial, counsel for SDI confirmed
that SDI was satisfied with its witness list, which did not list Parker as a witness. We find no merit
to HOH’s contention. At most, SDI waived its own right to call Parker as a witness, but that is not
determinative of whether SDI waived any right to request that an adverse inference be drawn from
HOH’s decision to not call Parker as a witness. Regardless, the trial court correctly decided that


                                                -12-
HOH’s decision not to call Parker as a witness did not entitle SDI to a presumption that Parker’s
testimony would have been adverse to HOH.

        In Ward v Consol Rail Corp, 472 Mich 77, 84; 693 NW2d 366 (2005), our Supreme Court
explained the underpinnings of an evidentiary presumption. The Court described a presumption
as a “procedural device” that will entitle the party relying on it at trial to a directed verdict if the
opposing party does not proffer evidence to rebut the presumption. Id. If the opposing party does
present rebuttal evidence, the presumption will disappear, but an underlying inference will remain,
to be weighed by the fact-finder against the rebuttal evidence. Id. The Court stated, “It is well
settled that missing evidence gives rise to an adverse presumption only when the complaining
party can establish intentional conduct indicating fraud and a desire to destroy [evidence] and
thereby suppress the truth.” Id. at 85 (quotation marks and citations omitted). The fact-finder may
only draw an adverse inference from a party’s failure to produce evidence “when: (1) the evidence
was under the party’s control and could have been produced; (2) the party lacks a reasonable
excuse for its failure to produce the evidence; and (3) the evidence is material, not merely
cumulative, and not equally available to the other party.” Id. at 86 (citations omitted); see also
Pugno v Blue Harvest Farms, LLC, 326 Mich App 1, 24; 930 NW2d 393 (2018) (setting forth the
same requirements that must be met before the fact-finder can draw an adverse inference against
a party who does not present evidence).

         In this case, the trial court did not err by declining to draw an adverse presumption or
inference as a result of HOH’s decision to not call Parker as a trial witness. First, the procedural
device of an adverse presumption would not have been appropriate because SDI did not
demonstrate that HOH acted intentionally or fraudulently to suppress the truth at trial. Although
HOH did not offer a reason for not calling Parker, HOH could decide which witnesses to call in
its defense. Even assuming that Parker’s testimony would have been material, as the trial court
correctly stated in its ruling, SDI could have named Parker as a witness and subpoenaed him to
testify at trial, but it did not do so. The record does not reflect that SDI sought to call Parker as a
witness and HOH refused to make him available. SDI has failed to establish its entitlement to an
adverse presumption or inference and the trial court did not err in this regard.

        SDI also asserts in a reply brief that the trial court abused its discretion by not admitting
into evidence a transcript of Parker’s deposition testimony and by not allowing SDI’s counsel to
question Tarara regarding admissions made by Parker. These issues are not properly before this
Court. “Reply briefs must be confined to rebuttal of the arguments in the appellee’s . . . brief[.]”
MCR 7.212(G). It is well settled that a party is not permitted to raise a new issue in a reply brief.
Blazer Foods, Inc v Restaurant Props, Inc, 259 Mich App 241, 252; 673 NW2d 805 (2003). See
also Vanalstine v Land O’Lakes Purina Feeds, LLC, 326 Mich App 641, 650; 929 NW2d 789
(2018) (this Court may decline to address an issue not raised in an appellant’s statement of
questions presented on appeal). Although SDI requests in its reply brief that leave to amend be
granted to the extent that its brief on appeal does not sufficiently challenge the admissibility of
Parker’s deposition testimony, we deny this request, particularly because HOH has not had an
opportunity to respond to these evidentiary claims.




                                                 -13-
                                      D. ATTORNEY FEES

        SDI also argues that the trial court erred in determining the attorney fees to which it was
entitled under the CLA by awarding SDI only $4,224, a small percentage of the trial cost only,
without holding an evidentiary hearing. We find that the trial court erred by failing to set forth its
analysis under the rubric defined in Smith v Khouri, 481 Mich 519; 751 NW2d 472 (2008), Pirgu
v United Servs Auto Ass’n, 499 Mich 269; 884 NW2d 257 (2016), and Wood v Detroit Auto-Inter
Ins Exch, 413 Mich 573; 321 NW2d 653 (1982).

        Where attorney fees are authorized, a trial court’s determination regarding the amount of a
fee award is reviewed for an abuse of discretion. Pirgu, 499 Mich at 274. A court abuses its
discretion when it erroneously applies the law or its determination of a fee award falls outside the
range of reasonable and principled outcomes. Id.

        As a preliminary matter, we reject HOH’s claim that counsel for SDI “forfeited” this issue
by waiving, on the record, “any further hearing on attorney fees.” The statement on which HOH
relies was made in the limited context of a discussion regarding the hourly rate the trial court
intended to use to calculate the limited attorney fees that the court had already decided would be
awarded to SDI. The trial court agreed to use the hourly rate requested by SDI, and HOH has not
challenged that decision. Viewed in context, SDI’s counsel did not agree that an evidentiary
hearing was not necessary to decide the broader issue of a reasonable attorney fee award. On the
contrary, in its motion and at the motion hearing, SDI’s counsel repeatedly requested that the trial
court hold an evidentiary hearing respecting attorney fees. Accordingly, HOH’s claim that SDI
waived this issue lacks merit.

        The CLA provides that attorney fees may be awarded to a construction lien claimant that
prevails on its claim. MCL 570.1118(2) provides:

               In an action to enforce a construction lien through foreclosure, the court
       shall examine each claim and defense that is presented and determine the amount,
       if any, due to each lien claimant or to any mortgagee or holder of an encumbrance
       and their respective priorities. The court may allow reasonable attorneys’ fees to a
       lien claimant who is the prevailing party. The court also may allow reasonable
       attorneys’ fees to a prevailing defendant if the court determines the lien claimant’s
       action to enforce a construction lien under this section was vexatious.

       In Pirgu, 499 Mich at 271, our Supreme Court reaffirmed the legal framework for
determining reasonable attorney fees set forth in Smith, 481 Mich 519. The Court explained:

       [A] trial court must begin its reasonableness analysis “by determining the fee
       customarily charged in the locality for similar legal services” and then multiplying
       that number “by the reasonable number of hours expended in the case.” After a
       trial court has calculated this baseline figure, it must consider and briefly discuss
       on the record the remaining Wood factors and the factors in MRPC 1.5(a) to
       determine whether any up or down adjustments from the base number are
       appropriate. [Pirgu, 499 Mich at 276, quoting Smith, 481 Mich at 530-531 (opinion
       by TAYLOR, C.J.).]



                                                -14-
Because Wood and Smith contained two different lists of factors to be considered, some of which
were duplicative, to assist trial courts in their analysis, the Court in Pirgu refined the factors for
consideration as follows:

              (1) the experience, reputation, and ability of the lawyer or lawyers
       performing the services,

              (2) the difficulty of the case, i.e., the novelty and difficulty of the questions
       involved, and the skill requisite to perform the legal service properly,

               (3) the amount in question and the results obtained,

               (4) the expenses incurred,

               (5) the nature and length of the professional relationship with the client,

             (6) the likelihood, if apparent to the client, that acceptance of the particular
       employment will preclude other employment by the lawyer,

               (7) the time limitations imposed by the client or by the circumstances, and

               (8) whether the fee is fixed or contingent. [Pirgu, 499 Mich at 282.]

       This list of factors is not exclusive. Id. To allow for meaningful appellate review, the trial
court “should briefly discuss its view of each of the factors above on the record and justify the
relevance and use of any additional factors.” Id. (citation omitted). If the opposing party
challenges the request for attorney fees, “[t]he trial court should normally hold an evidentiary
hearing.” Head v Phillips Camper Sales & Rental, Inc, 234 Mich App 94, 113; 593 NW2d 595
(1999). However, if the parties establish a sufficient record and the trial court fully explains its
reasoning, an evidentiary hearing may not be required. Id.

         In this case, in setting the attorney fee award, the trial court, consistent with Pirgu, 499
Mich at 276, first considered a reasonable hourly rate for SDI’s counsel by consulting the 2017
Economics of Law and Practice Attorney Income and Billing Rate Summary Report, and HOH
does not challenge the trial court’s conclusion that an hourly rate of $400 was reasonable. The
trial court, however, ruled that SDI could recover attorney fees for only 10.56 hours expended by
its attorneys. SDI substantially prevailed on the amount it sought under the claim of lien which
made it a prevailing party under the CLA. Ronnisch Constr Group, Inc v Lofts on the Nine, LLC,
306 Mich App 203, 211-214; 854 NW2d 744 (2014).

        Moreover, noticeably absent from the trial court’s ruling was the determination of a
baseline figure of the attorney fees expended in the case by SDI and consideration of the factors
from Wood and MRPC 1.5(a) to determine whether an up or down adjustment to such baseline
figure was warranted. Pirgu, 499 Mich at 276. In Powers v Brown, 328 Mich App 617, 623-624;
939 NW2d 733 (2019), this Court clearly indicated that when the trial court fails to follow the
Smith/Pirgu method and does not apply the relevant factors, it errs. Like the trial courts in Pirgu
and Powers, the trial court here focused on one of the factors in the Smith/Pirgu framework—the
amount sought by SDI and the result obtained in comparison to that amount—without addressing


                                                -15-
the remaining factors or articulating its rationale for the amount awarded. The trial court’s failure
to address the other factors constituted an abuse of discretion. Therefore, it is necessary to vacate
the trial court’s attorney fee award and remand for further proceedings. Powers, 328 Mich App at
624.

       The trial court’s conclusion that SDI had entitlement only to attorney fees incurred for
10.56 hours expended during trial rests solely on its consideration of the third factor set forth in
the Smith/Pirgu framework, the amount sought by SDI and the results obtained. However, in
Smith, 481 Mich at 532 (opinion by TAYLOR, C.J.), our Supreme Court explained:

                In considering the time and labor involved (factor 1 under MRPC 1.5 [a]
        and factor 2 under Wood) the court must determine the reasonable number of hours
        expended by each attorney. The fee applicant must submit detailed billing records,
        which the court must examine and opposing parties may contest for reasonableness.
        The fee applicant bears the burden of supporting its claimed hours with evidentiary
        support. If a factual dispute exists over the reasonableness of the hours billed or
        hourly rate claimed by the fee applicant, the party opposing the fee request is
        entitled to an evidentiary hearing to challenge the applicant’s evidence and to
        present any countervailing evidence.

        After the trial court awarded 24% of the attorney fees incurred solely during trial, SDI
submitted detailed billings demonstrating the work performed by its attorneys and the hours spent
supported by an affidavit from its lead attorney regarding details of the attorneys who assisted in
the case. The trial court multiplied 10.56 hours, the time that the trial court determined that SDI
spent at trial on the issues on which it prevailed, by the rate it deemed reasonable. The trial court,
however, should have considered all of the applicable factors and made findings regarding them
on the record.

         On remand, the trial court must first consider and determine the extent to which HOH may
rely, if at all, on the defense claimed under MCL 570.1107(6) to SDI’s construction lien claim.
The trial court must analyze the record and determine the total value of SDI’s contract, the value
of work actually performed by SDI in proportion with the total it contracted to perform, and then
subtract the amount paid to SDI for the work to derive the value of its construction lien. If, after
such analysis SDI is determined to have prevailed on its construction lien claim, the trial court
must analyze and decide SDI’s attorney fee award under the factors set forth in Smith/Pirgu/Woods
and Powers while being mindful of the remedial nature of the CLA. To the extent that the trial
court’s consideration of these matters depends on resolution of disputed factual issues, the trial
court may hold an evidentiary hearing to resolve the disputed issues and then, in the exercise of its
discretion, determine the amount to which SDI may be entitled.

                      CONCLUSION AND INSTRUCTIONS ON REMAND

         Although we affirm the trial court’s decision not to draw an adverse inference from HOH’s
decision not to call Joseph Parker as a witness, we vacate the trial court’s judgment and remand to
the trial court for further proceedings consistent with this opinion including that the trial court shall
render the necessary findings to enable it to make a legal determination whether HOH established
the defense set forth in MCL 570.1107(6) to SDI’s lien claim. We also vacate the trial court’s


                                                  -16-
award of attorney fees, and upon its determination of the validity and extent of SDI’s lien claim,
the trial court should consider the applicable factors set forth in Smith/Pirgu/Woods and Powers
and make appropriate findings on the record in its exercise of discretion in determining whether
and to what extent SDI may be entitled to recover attorney fees that it incurred to enforce its
construction lien claim.

       Therefore, we direct the trial court to undertake the following upon remand:

A.     Related to SDI’s lien claim, the trial court shall determine the following:

       1.      The amount of SDI’s subcontracts for paint and masonry work (as modified
               by all additions, deletions, and other amendments);

       2.      The percentage SDI completed in its performance of its subcontracts;

       3.      The amount paid to SDI under its subcontracts (pursuant to either a
               contractor’s sworn statement or a waiver of lien, in accordance with the
               CLA);

       4.      After determination of 1, 2, and 3, the trial court shall calculate the amount
               of SDI’s construction lien by multiplying the percentage of SDI’s
               performance by the total amount of SDI’s subcontracts, from which it shall
               then subtract the amount paid to SDI.4 If this calculation results in a positive
               value, the amount equals SDI’s enforceable lien claim, i.e., the amount
               owed to SDI;5 and

       5.      Whether and to what extent HOH may assert the defense set forth in
               MCL 570.1107(6), according to its plain language as explained in this
               opinion and as directed in Vugterveen, by determining (a) whether HOH is
               subject to multiple construction liens related to HOH’s contract with
               Kincaid, (b) the sum of those construction liens, (c) whether those
               construction liens exceed the amount HOH agreed to pay Kincaid for the
               improvements as modified by all additions, deletions, and other
               amendments, (d) the amount of payments made by HOH under the Kincaid
               contract pursuant to either a contractor’s sworn statement or lien waiver in
               accordance with the CLA, and (5) the contract amount minus what HOH
               paid to Kincaid or its subcontractors.

B.     Related to SDI’s attorney fees claim, if upon the completion of the CLA analysis set forth
above, the trial court concludes that SDI is the prevailing party, the trial court shall undertake the
analysis of SDI’s attorney fees under the rubric of Smith, Purgu, and Wood. In undertaking this


4
  The trial court shall not deduct the “cost of cover,” the cost of completion of the work SDI
contracted to perform.
5
 If the calculation results in a negative value, the result would indicate an overpayment owed to
HOH.


                                                -17-
analysis, the trial court shall consider, evaluate, and articulate its reasoning respecting factors (1)-
(8) of Pirgu and any other factors the trial court deems appropriate.

C.     On remand, if the trial court is satisfied that the factual record is adequate for its analysis
and sufficient for it to rule, the trial court is not required to conduct an evidentiary hearing or allow
any party to supplement the record with either evidence or offers of proof. If, however, the trial
court deems it helpful or necessary, it may allow additional proofs on any specific issue or sub-
issue. Head, 234 Mich App at 113.

D.     The trial court may provide the parties the opportunity to submit briefs and may impose
page limits on any written submissions as it deems appropriate. The trial court may entertain oral
argument but is not required to do so.

       Affirmed in part, vacated in part, and remanded for further proceedings consistent with this
opinion. We do not retain jurisdiction.

                                                                /s/ James Robert Redford
                                                                /s/ Michael J. Riordan
                                                                /s/ Jonathan Tukel




                                                  -18-