Express Scripts, Inc. v. Del. State Empl. Benefits Comm.

                                    COURT OF CHANCERY
                                          OF THE
                                    STATE OF DELAWARE
KATHALEEN ST. JUDE MCCORMICK                                          LEONARD L. WILLIAMS JUSTICE CENTER
        CHANCELLOR                                                        500 N. KING STREET, SUITE 11400
                                                                         WILMINGTON, DELAWARE 19801-3734


                                          December 13, 2021

     Michael P. Kelly, Esquire                         Daniel B. Rath, Esquire
     Andrew S. Dupre, Esquire                          Rebecca L. Butcher, Esquire
     Travis Ferguson, Esquire                          Jennifer L. Cree, Esquire
     McCarter & English, LLP                           Landis Rath & Cobb LLP
     405 North King Street, 8th Floor                  919 Market Street, Suite 1800
     Wilmington, DE 19801                              Wilmington, DE 19801

     Patricia A. Davis, Esquire
     Lawrence W. Lewis, Esquire
     Zi-Xiang Shen, Esquire
     Delaware Department of Justice
     820 North French Street, 6th Floor
     Wilmington, DE 19801

                   Re:    Express Scripts, Inc. v. Del. State Empl. Benefits Comm.,
                          C.A. No. 2021-0434-KSJM

      Dear Counsel:

            This letter resolves the plaintiff’s motion for summary judgment. Plaintiff Express

      Scripts, Inc. (“ESI”) filed this action alleging that the Defendant State Employee Benefits

      Committee (the “SEBC”) violated the Procurement Statute when awarding the contract for

      the State of Delaware’s Pharmacy Benefit Manager (“PBM”).

            On June 23, 2021, I denied ESI’s motion to preliminarily enjoin the transition to the

      successful bidder, Defendant CaremarkPCS Health, L.L.C. (“CVS”). In a bench ruling, I

      found that ESI was likely to succeed on aspects of its claim, and assumed for the sake of

      analysis that ESI would face irreparable harm, but concluded that the balance of equities

      required denying the preliminary injunction. When balancing the equities, I observed that
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 2 of 32

a preliminary injunction threatened harm to over 129,000 members served by the contract

and could result in a potential disruption of pharmacy benefits. This letter decision assumes

that the reader is familiar with the June 23, 2021 bench ruling (the “PI Ruling”).1

        At the conclusion of the PI Ruling, I invited ESI to seek an interlocutory appeal.

ESI instead moved for summary judgment on its claim for a permanent injunction. The

standard applied at the preliminary injunction phase is more favorable to the movant than

the standard applied on a motion for summary judgment. The former requires a reasonable

probability of success on the merits. The latter requires actual success on the merits based

on undisputed facts.

        This begs the question: What has changed since the preliminary injunction phase to

justify granting ESI, under a more onerous standard, that which it was denied before? The

short answer is: not much. The factual record is largely the same because the parties opted

to forego discovery after the preliminary injunction phase. Nor have the legal arguments

changed significantly.

        The only meaningful difference lies in ESI’s requested relief. Before, ESI sought

to preliminarily enjoin the transition to CVS for the Commercial population, which was to

occur by July 1, 2021. Now, ESI seeks a court-ordered reevaluation of proposals, ideally

before July 1, 2022, when the second year of the CVS contract takes effect. ESI argues




1
    See C.A. No. 2021-0434-KSJM Docket (“Dkt.”) 61.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 3 of 32

that it has met the standard for achieving what, in its view, is a more modest request for

relief.

          In my view, ESI’s motion falls short again. The pared back relief still brings with

it potential for disruption and confusion in a service that thousands of Delawareans depend

on daily. Further, while ESI may be able to show that there were deficiencies in the PBM

procurement process, ESI has failed to show that those deficiencies were material to the

selection process. This decision therefore denies ESI’s motion for summary judgment.

          The SEBC and CVS have cross-moved for summary judgment. Those motions are

held in abeyance pending supplemental briefing on the effects of this decision on the

defendants’ motions.

I.        FACTUAL BACKGROUND

          The facts are drawn from the materials submitted in support of the cross motions for

summary judgment.2 As discussed above, the parties opted to forego additional factual

discovery after the preliminary injunction phase, so the facts before the court now are

nearly the same as they were in June 2021. The only additions to the record are two

declarations explaining efforts undertaken to implement the PBM contract since the

preliminary injunction phase. The first was a supplemental declaration from Faith Rentz,

the Director of the Delaware Statewide Benefits Office (“SBO”), which coordinates the




2
    Dkt. 52, Pl.’s Hr’g Ex. List (by “PX”).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 4 of 32

procurement of employee benefits on behalf of SEBC.3 The second is the declaration of

Michelle Manolovic, CVS’s Vice President for Business Development, Government and

Labor.4

         Although it is true that “factual conclusions reached in a preliminary injunction

proceeding” are “tentative” and “it is open to the court to further consider factual matters

thereafter,”5 because the main part of the factual record is no further developed than it was

at the preliminary injunction hearing, the main part of my factual findings has not changed.

What follows largely tracks the factual background set forth in the PI Ruling.6

                Structure of the State Employee Benefits Committee.

         The SEBC is a statutorily authorized body comprising elected or appointed officials

or their designees formed to carry out the mission of the State’s Group Health Insurance

Plan (“GHIP”).7

         Among its responsibilities, the SEBC selects “all carriers or third-party

administrators necessary to provide coverages to State employees.”8 Relevant to this




3
    Dkt. 70, Decl. of Faith L. Rentz, dated Aug. 27, 2021 (“Supp. Rentz Decl.”).
4
    Dkt. 72, Decl. of Michelle A. Manolovic, dated Aug. 30, 2021.
5
    Braunchsweiger v. Am. Home Shield Corp., 1991 WL 3920, at *1 (Del. Ch. Jan. 7, 1991).
6
    See PI Ruling at 3:21–15:10.
7
  29 Del. C. § 9602(a). In addition to eight specified elected or appointed officials, the
statute requires the Governor to appoint a labor union representative to the SEBC.
8
    29 Del. C. § 9602(b)(2).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 5 of 32

dispute, the SEBC is responsible for procuring service contracts with PBM providers for

the State’s health insurance program.

           PBMs occupy a unique niche in the healthcare ecosystem. Although PBMs’

primary role is to administrate prescription drug programs for health insurance plans,9

PBMs also operate as brokers between payers, drug manufacturers, and pharmacies.10

PBMs earn revenues from client fees for processing claims, rebate savings resulting from

negotiations with drug manufacturers, and “fees and shared savings from the maintenance

of pharmacy networks.”11

           When this litigation was filed, ESI was the incumbent PBM for the State’s GHIP.12

The GHIP includes two different population segments: “Commercial,” comprising

approximately 102,000 non-Medicare members, and “Employee Group Waiver Plan” (or

“EGWP”), comprising approximately 27,000 Medicare Part D beneficiaries.13

           ESI’s contract for the Commercial segment expired on June 30, 2021.14 Its contract

for the EGWP segment will expire on December 31, 2021.15




9
 Cole Werble, Pharmacy Benefit Managers, Health Affairs, Sept. 14, 2017, at 1, https://
www.healthaffairs.org/do/10.1377/hpb20171409.000178/full/healthpolicybrief_178.pdf.
10
     Id.
11
     Id.
12
     Dkt. 44, Decl. of Faith L. Rentz, dated June 14, 2021 (“Rentz Decl.”) ¶¶ 7–8.
13
     Supp. Rentz Decl. ¶ 12.
14
     Rentz Decl. ¶ 8.
15
     Id.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 6 of 32

                 SEBC Requests Proposals for a New PBM Contract.

          With the terms of the PBM contracts expiring in 2021, the SBO began planning the

PBM procurement process in early 2020.16 The SBO engaged the consulting firm Willis

Towers Watson (“WTW”) to help manage and evaluate bids.17

          On June 1, 2020, the SBO publicly announced and posted the Request for Proposal

for PBM services (the “RFP”).18 The Procurement Statute governs the process by which

the state selects professional services contracts.19 Under Section 6981(f), the SEBC is

required to “establish written administrative procedures for the evaluation of applicants.”20

          The RFP established those procedures, setting out a two-phase process and stating

that “[a]ll proposals shall be evaluated using the same criteria and scoring process.”21

Based on bidders’ weighted scores in Phase I, finalists would move on to Phase II for

consideration.22

          In Phase I, bidders were required to state their ability to meet twenty-six “minimum

requirements” that spoke to the bidders’ experience and skill in performing the PBM

contract, as well as their willingness to comply with key contractual and legal



16
     Id. ¶ 10.
17
     Id. ¶ 11.
18
     See generally PX-1.
19
     29 Del. C. §§ 6980–6988.
20
     29 Del. C. § 6981(f).
21
     PX-1 at 8–11.
22
     Id. at 4, 7–10.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 7 of 32

requirements.23 For each requirement, the bidder was required to check either the box

indicating that it “confirmed” its compliance with the minimum requirement or the box

stating, “not confirmed, explain.”24

           The RFP disclosed that a bidder’s inability to confirm all the questions as written

would not necessarily prevent a bidder from proceeding.25 Because the State’s intent in a

procurement “is to have as many qualified bidders in [the] process as possible,” the goal

of Phase I “was not to exclude or narrow the list of bidders who would continue on with

this process.”26

           Phase I responses were due by Wednesday, June 17, 2020.27

           In Phase II, the SEBC focused on a financial and qualitative evaluation of the

finalists’ bids, assigning weight to the following criteria: Responsiveness, 5%, Cost, 50%,

Organization’s Ability and Experience, 20%, Network and Formulary, 15%, and

Administrative Services, 10%.28         The Phase II questionnaire was extensive—ESI’s



23
     Id. at 25–30.
24
     Id.
25
  Id. at 24 (“Failure to meet any minimum requirements may result in disqualification of
the proposal submitted by your organization.”) (emphasis added).
26
   PX-27 (“Rentz Dep. Tr.”) at 47:20–48:1; Dkt. 69, Ex. A at DDHR_00012383 (discussing
at a meeting between the SBO and OMB’s Government Support Services whether the RFP
should include “some true drop-dead mins for a ‘weed-out.’”); Rentz Dep. Tr. at 61:4–9
(testifying that the SBO did not consider whether failure to meet any minimum
requirements was disqualifying because, “[the RFP] say[s] may not shall be disqualified”).
27
     PX-1 at 3.
28
     Id. at 10.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 8 of 32

response was 293 pages and CVS’s response was 317 pages.29 The bid scores took into

account “the bid information WTW provides, the information in the interviews [with

bidders], and the apples-to-apples pricing.”30 The standards ranged from the PBM’s

qualifications and technical abilities, to what performance guarantees it agreed to give to

the State, and the clinical programs offered, among several other categories.31 Bidders

were also required to complete spreadsheets that detailed the offerors’ proposed pricing,

the drug formulary they proposed, and the disruption posed by the offerors’ proposed retail

pharmacy network.32

           Phase II opened on July 6, 2020, and responses were due by August 7, 2020.33

           The SEBC established a Proposal Review Committee (“PRC”) to review the

proposals submitted in Phase I and Phase II.34 Each member of the SEBC selected a

representative to serve on the PRC.35 The PRC was tasked with recommending a winning

bidder to the SEBC, which would have the final and sole authority to award the PBM

contracts.36



29
     PX-5; PX-26.
30
     Dkt. 70, Ex. B at DDHR-00011965.
31
     See, e.g., PX-5.
32
     Id.
33
     PX-29 at 5–6.
34
     PX-1 at 8.
35
     Id.
36
     Id. at 9; 29 Del. C. § 5256(3).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 9 of 32

           Six initial offerors responded to the RFP.37 Five made it past Phase I.38 Those five

included ESI and CVS.39

                 SEBC Awards the PBM Contract to CVS.

           ESI received a letter on December 15, 2020, stating that the SEBC voted to award

the PBM contracts to CVS.40 The transition to CVS would occur on July 1, 2021, for the

Commercial segment41 and on January 1, 2022, for the EGWP segment.42

           The letter specified that CVS’s proposal offered savings of 21.8% over a three-year

period when compared with ESI’s current contract.43 It further highlighted six additional

factors that informed the SEBC’s decision to award the contract to CVS. Those factors

included: minimal disruption in transitioning from the status quo, ability to administer plan

requirements in compliance with Delaware law, superior account management, and

superior customer and implementation services.44




37
     Rentz Dep. Tr. at 49:1.
38
     Rentz Decl. ¶ 17.
39
     Id. ¶ 18.
40
     PX-19.
41
     Rentz Decl. ¶ 8.
42
     Id.
43
     PX-19.
44
     Id.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 10 of 32

           The scoring by the PRC revealed that ten of the twelve PRC members ranked ESI

second after CVS in their Commercial scoring.45 The other two ranked ESI first overall.46

In the EGWP scoring, eleven of the twelve PRC members ranked ESI second after CVS

and one ranked ESI first.47 In the scoring summary, which combined the scores of all PRC

members, ESI again ranked second after CVS.48 Where CVS received an overall score of

approximately 146, ESI scored approximately 132.49

           On December 17, 2020, two days after being notified of the SEBC’s decision, ESI

submitted a Freedom of Information Act (“FOIA”) request to obtain the documents

necessary to evaluate the selection process.50 On December 23, 2020, ESI formally

protested the SEBC’s decision to award the contract to CVS.51

           On January 5, 2021, the SEBC denied ESI’s FOIA request on the grounds that ESI

lacked Delaware citizenship.52 ESI corrected and re-filed its request the following day.53

On February 12, 2021, the SEBC provided ESI with documents responsive to its FOIA




45
     PX-9 at 3.
46
     Id.
47
     Id. at 4.
48
     Id. at 2.
49
     Id.
50
     PX-22 at 1.
51
     See generally PX-22.
52
     Dkt. 1, Ex. G at 1.
53
     Id.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 11 of 32

request.54 The records were redacted.55 ESI requested unredacted records, which the

SEBC denied.56 ESI then filed a supplemental protest of the SEBC’s decision on February

19, 2021.57

           On April 12, 2021, the SEBC issued a final decision in which it rejected ESI’s

protest.58

                   ESI Files This Lawsuit.

           ESI filed this lawsuit on May 17, 2021, asserting two causes of action.59

           In Count I, ESI claims that the SEBC’s evaluation process violated the requirements

contained in the Procurement Statute.60 ESI also claimed that the SEBC improperly

redacted documents turned over in response to the FOIA request, but SEBC did not press

this claim in briefing or oral argument and has thus abandoned the claim.

           In Count II, ESI seeks an injunction either “disqualifying CVS and permanently

enjoining the SEBC from awarding or entering into a formal contract with CVS” or




54
     Id. at 2.
55
     PX-23 at 1.
56
     Id.
57
     See generally PX-23.
58
     PX-24 at 16.
59
     Dkt. 1, Verified Compl. for Injunctive and Declaratory Relief (“Compl.”).
60
     Compl. ¶¶ 39–84.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 12 of 32

“ordering the SEBC to re-evaluate the proposals in accordance with the RFP and its

mandatory minimum requirements.”61

          CVS was not named as a defendant initially. The SEBC took the position that CVS

was a necessary party.62 I then permitted ESI to join CVS as a party and later allowed a

third-party bidder to intervene for the limited purpose of protecting the confidentiality of

its information.63

                  The Court Denies ESI’s Motion for a Preliminary Injunction.

          With the amended complaint, ESI moved for a preliminary injunction to stave off

the July 1, 2021 transition to CVS as the PBM for the Commercial segment.64 The parties

engaged in expedited discovery and briefing on ESI’s motion for a preliminary

injunction.65 The SEBC produced thousands of pages of documents and ESI took the

depositions of SBO Director Faith Rentz and PRC Member Steven Costantino.66




61
     Id. at 37.
62
  Dkt. 60, Tr. of the May 20, 2021 Telephonic Rulings of the Court on Pl.’s Mot. to
Expedite at 10:6–9.
63
  Dkt. 12, First Am. Verified Compl. for Injunctive and Declaratory Relief (“Am.
Compl.”); Dkt. 38.
64
     Am. Compl. ¶¶ 100–07.
65
     Dkt 41.
66
     Rentz Dep. Tr.; PX-28.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 13 of 32

         The standard applicable to a motion for a preliminary injunction required the court

to assess whether ESI demonstrated a reasonable probability of success on the merits. 67 In

running this analysis, I focused on whether the SEBC exercised its discretion in an arbitrary

or capricious manner when awarding the PBM contract.68 I found that it was reasonably

probable that ESI would succeed on aspects of its arguments.69 I questioned, however,

whether any of the arbitrary and capricious actions were material in the sense that they

would have altered the outcome of the process.70

         I ultimately made a plaintiff-friendly presumption, concluding that ESI had “[eked]

past the requirement that it be reasonably likely to succeed” on the merits.71 I next assumed

“[f]or the sake of analysis only” that ESI had established irreparable harm.72 I then denied

the motion on the ground that that the harm to the public and GHIP members from a

disruptive injunction during the PBM transition, resulting in customer confusion and




67
  See PI Ruling at 15:12–20; Protech Sols., Inc. v. Del. Dep’t of Health and Hum. Servs.,
2017 WL 5903357, at *1 (Del. Ch. Nov. 30, 2017).
68
     PI Ruling at 17:15–20:20.
69
     Id. at 48:5–9.
70
   Id. at 47:20–48:5 (“In candor, it’s unclear to me to what degree the odd variability in
[scoring] would support injunctive relief, standing alone. It seems that the primary utility
of the scorecard was to create a ranking system. That system, and the rankings, might not
have been altered, despite the subjective translation of objective metrics like cost and
despite the failure to fully credit the incumbent. It’s unclear.”).
71
     Id. at 50:4–6.
72
     Id. at 49:19–24.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 14 of 32

risking members not receiving medications, outweighed any harm to ESI from its

unsuccessful bid.73

              Delaware Continues Transitioning to CVS.

       At the conclusion of the PI Ruling, I observed that the ruling would be appropriate

to certify for interlocutory appeal.74 ESI did not move to certify an interlocutory appeal of



73
   Id. at 50–53. When balancing the equities on a motion for preliminary injunction, this
court must consider the potential harm of an injunction to persons with a legitimate interest
in the matter, including the public. See Donald J. Wolfe, Jr. & Michael A. Pittenger,
Corporate and Commercial Practice in the Delaware Court of Chancery § 16.02[f] (2d ed.
2020) (“Generally speaking, the balancing of the equities analysis entails a determination
whether the harm that would result to the applicant if an injunction does not issue would
outweigh the harm that will befall the opposing party (or others with a legitimate interest
in the matter, including, in some instances, the public) if such relief is issued.”); Cantor
Fitzgerald, L.P. v. Cantor, 724 A.2d 571, 584 (Del. Ch. 1998) (“‘[A] court of equity has
discretion to grant or deny an application for injunctive relief in light of the relative
hardships of the parties.’ Thus, in order to obtain preliminary injunctive relief, Plaintiff
must prove that this Court's failure to grant the injunction will cause Plaintiff greater harm
than granting the injunction will cause Defendants. It is also appropriate to consider the
impact an injunction will have on the public and on innocent third parties.” (emphasis
added)); Freedman v. Rest. Assocs. Indus., Inc., 1987 WL 14323, at *6 (Del. Ch. Oct. 16,
1987) (“[Equitable relief] requires, first, that plaintiff persuade the court that he has a
reasonable likelihood of prevailing on the merits of his complaint at trial. If that
demonstration is made, the court is to inquire whether plaintiff is threatened with
irreparable injury before a final hearing may be had and, finally, to balance against that
threat, the harm that may befall the defendant (or others with a legitimate interest in the
matter) should the remedy be granted improvidently.” (emphasis added)).
74
   PI Ruling at 57:22–58:11 (“Given the issues at stake, I imagine that Express Scripts is
considering an interlocutory appeal. Anticipating that, I have reviewed the factors of
Delaware Supreme Court Rule 42, and I believe that my ruling decides a substantial issue
of material importance, addresses issues of first impression, and relates to an issue of public
importance such that the considerations of justice would be served by an interlocutory
appeal. For these reasons, I would certify an interlocutory appeal, should Express Scripts
seek leave to pursue one. I have also asked our court reporter to prepare an expedited copy
of the transcript of this ruling.”).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 15 of 32

the PI Ruling. Consequently, the SBO transitioned the Commercial population to CVS,

implementing various member supports in the process.            For example, the SBO

implemented “Safety Protocols” to ensure members can continue to obtain critical

medications during the transition period.75 These protocols enable the CVS Customer Care

Team to authorize one-time exception refills of “life sustaining” medications that members

require within 72 hours of the requested refill.76 In addition to implementing member

supports, the SBO established design and review changes for the PBM Plan, including

correcting prescription maximum fill discrepancies, updating prior authorizations and

coverage, and implementing a prescription savings plus program for non-covered drugs.77

On July 1, 2021, CVS became the PBM for the Commercial segment.78

           The SBO also began planning for the January 1, 2022 transition to CVS for the

EGWP population.79 Although the EGWP population is smaller than the Commercial

population, it is a higher-need group.80 The average age of an EGWP member is 74.6 years

old, compared to 35.1 years old for Commercial members.81 Nearly all EGWP members




75
     Supp. Rentz. Decl. ¶ 6.
76
     Id.
77
     Id. ¶ 7.
78
     Id. ¶ 4.
79
     Id. ¶ 10.
80
     Id. ¶ 12.
81
     Id.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 16 of 32

(92.4%) use the prescription drug benefit, compared to 72.2% of Commercial members.82

And on average, EGWP have 2.28 prescriptions per month, compared to an average of less

than one for Commercial members.83

           In the months leading up to the January 1, 2022 transition, the SEBC has been

coordinating a Fall Medicare Open Enrollment, creating eligibility files and an enrollment

process, reviewing the CVS reporting process, creating a communications strategy tailored

to the EGWP population, and coordinating with the Delaware Office of Pensions to ensure

compliance with internal enrollment and finance reporting processes, among other things.84

                  The Parties Cross-Move for Summary Judgment.

           ESI moved for summary judgment pursuant to Court of Chancery Rule 56 on July

16, 2021.85 In response, both the SEBC and CVS cross-moved for summary judgment on

August 30, 2021.86 The parties fully briefed their respective motions and the court held

oral argument on November 16, 2021.87

           ESI’s request for relief has shifted over the course of this litigation. On its motion

for a preliminary injunction, ESI sought to prevent the State from transitioning the



82
     Id.
83
     Id.
84
     Id. ¶ 10.
 Dkt. 63, Opening Br. in Support of Pl. Express Scripts, Inc.’s Mot. for Summ. J. (“Pl.’s
85

Opening Br.”).
86
     Dkt. 67; Dkt. 71.
87
     Dkt. 85 (“Oral Arg. Tr.”).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 17 of 32

Commercial population to CVS on July 1, 2021.88 In Count II of the Complaint, ESI sought

an injunction either “disqualifying CVS and permanently enjoining the SEBC from

awarding or entering into a formal contract with CVS” or “ordering the SEBC to re-

evaluate the proposals in accordance with the RFP and its mandatory minimum

requirements.”89 In its opening brief in support of its motion for summary judgment, ESI

requested that the court rule on the motion in time to enjoin the December 31 transition. 90

The parties then stipulated to hold argument on November 16, 2021. By the time of oral

argument, ESI sought only an order requiring the SEBC to reevaluate the proposals on a

timeline established by the court.91

II.      LEGAL ANALYSIS

         The cross motions seek summary judgment on both Counts of ESI’s Complaint.

Under Court of Chancery Rule 56, summary judgment “shall be rendered forthwith” if

“there is no genuine issue as to any material fact and . . . the moving party is entitled to a

judgment as a matter of law.”92 Generally, “the court must view the evidence in the light

most favorable to the non-moving party.”93 But where, as here,


88
     PI Ruling at 14:14–19.
89
     Am. Compl. at 37.
90
   Pl.’s Opening Br. at 50 (arguing that “[w]ith respect to the EGWP contract, ESI is the
current PBM provider until December 31, and a potential ruling on this motion can be
issued prior to that time.”).
91
     See Oral Arg. Tr. at 6:9–7:1.
92
     Ct. Ch. R. 56(c).
93
     Merrill v. Crothall-Am., Inc., 606 A.2d 96, 99 (Del. 1992) (citation omitted).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 18 of 32

                the parties have filed cross motions for summary judgment and
                have not presented argument to the Court that there is an issue
                of fact material to the disposition of either motion, the Court
                shall deem the motions to be the equivalent of a stipulation for
                decision on the merits based on the record submitted with the
                motions.94

         “There is no ‘right’ to a summary judgment.”95 The court may, in its discretion,

deny cross motions for summary judgment if it decides upon a preliminary examination of

the facts presented that it is desirable to inquire into and develop the facts more thoroughly

at trial in order to clarify the law or its application.96




94
     Ct. Ch. R. 56(h).
95
  Telxon Corp. v. Meyerson, 802 A.2d 257, 262 (Del. 2002) (quoting Anglin v. Bergold,
565 A.2d 279 (Del. 1989)).
96
   See Cerberus Int’l, Ltd. v. Apollo Mgmt., L.P., 794 A.2d 1141, 1150 (Del. 2002)
(reversing summary judgment holding where there was a triable issue of material fact and
commenting that “the trial court may . . . deny summary judgment in a case where there is
reason to believe that the better course would be to proceed to a full trial.”) (citation
omitted); Alexander Indus., Inc. v. Hill, 211 A.2d 917, 918–19 (Del. 1965) (holding that in
denying the defendant’s motion for summary judgment, the trial court “needed no more
reason than to conclude, upon preliminary examinations of the facts, that it found it
desirable to inquire thoroughly into all of the facts in order to clarify the application of the
law”); Ebersole v. Lowengrub, 180 A.2d 467, 470 (Del. 1962) (reversing summary
judgment holding where a genuine issue of disputed fact remained unresolved and
observing that summary judgment will not be granted “if, upon an examination of all the
facts, it seems desirable to inquire thoroughly into them in order to clarify the application
of the law to the circumstances”) (citation omitted); In re Comverge, Inc. S’holders Litig.,
C.A. No. 7368-VCMR, at 10 ¶ 11 (Del. Ch. Oct. 31, 2016) (ORDER) (denying summary
judgment where “fuller development of the facts should serve to clarify the law or help the
Court determine its application to the case”).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 19 of 32

               Count I

         In Count I, ESI claims that the SEBC violated the Procurement Statute by awarding

the PBM contracts to CVS.97

         When evaluating a claim that an agency violated the Procurement Statute, the court

first assesses whether the agency complied with the statutory requirements. If the agency

complied with the statutory requirements, the court then determines whether the agency

exercised its discretion in an appropriate manner.98

         In this case, ESI does not argue that the SEBC failed to comply with the minimal

statutory requirements when awarding the PBM contract.99 Instead, ESI argues that the

SEBC abused its discretion when awarding the PBM contract to CVS.


97
     Am. Compl. ¶ 41.
98
  See Doctors Pathology Servs. P.A. v. State Div. of Pub. Health, Dep't of Health & Soc.
Servs., 2009 WL 4043299, at *4 (Del. Ch. Nov. 20, 2009).
99
   The Procurement Statute differentiates between public works and professional services.
Compare 29 Del. C. § 6902(23) (defining “Public works contract”) with 29 Del. C. §
6902(20) (defining “Professional services”). The General Assembly granted the executive
branch limited discretion in soliciting bids for and awarding public works contracts and
broad discretion in soliciting bids for and awarding public service contracts. Compare 29
Del. C. §§ 6960–6970A (establishing mandatory procurement requirements for public
works contracts) with 29 Del. C. §§ 6980–6988 (enumerating discretionary criteria that
“may be utilized” in ranking applicants for professional services contracts). As to public
service contracts, the only statutory requirements are that the agency “shall establish
written administrative procedures for the evaluation of applicants” and the “administrative
procedures shall be adopted and made available to the public by each agency before
publicly announcing an occasion when professional services are required.” 29 Del. C. §
6981(f); see also Protech, 2017 WL 5903357, at *3. The PBM contract was a contract for
professional services. See generally PX-1. Thus, the only statutory requirements are the
minimal obligations established by Section 6981(f). ESI does not claim that the SEBC
failed to satisfy those requirements.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 20 of 32

         The purpose of the Procurement Statute is twofold, to:

                 (1) Create a more efficient procurement process to better
                enable the State to obtain the highest quality goods, materials
                and services at the best possible price, thereby maximizing the
                purchasing value of public moneys; and

                (2) Create a single forum in which the procurement needs of
                state agencies and the technical and legal requirements of the
                Government Support Services are addressed simultaneously so
                as to increase mutual understanding, respect, trust and fair and
                equitable treatment for all persons who deal with the state
                procurement process.100

         Of these two purposes, the first is paramount. While the second purpose reflects a

legislative intent to treat all persons, including bidders, in a “fair and equitable manner,”

this court has interpreted this language as subordinate to the first purpose when the

challenge is brought by a disappointed bidder. This interpretive approach is intended to

avoid enticing disappointed bidders into using litigation to obtain leverage in or otherwise

taint the procurement process.101


100
      29 Del. C. § 6901.
101
    See Autotote Lottery Corp. v. Del. State Lottery Off., 1994 WL 163633, at *7 (Del. Ch.
Apr. 22, 1994) (“To issue an injunction here would permit a disappointed bidder to deploy
a statute that seeks to promote the public good so as to occasion delay and achieve private
advantage. This would be a subversion of the statute.”); Gannett Co., Inc. v. State, 1993
WL 19714, at *3 (Del. Ch. Jan. 11, 1993) (“The laws requiring that public contracts be
awarded through competitive bidding are primarily intended for the protection of the
public[.]”); id. at *6 (describing the “primary purpose of competitive bidding on public
contracts” as “to avoid the waste of taxpayers’ money”); Doctors Pathology, 2009 WL
4043299, at *7 & n.65 (observing that “the primary purpose of the competitiveness
requirement is to prevent waste through favoritism”) (cleaned up); id. at *7 (“Any
discretionary procurement structure will tend to advantage certain bidders over others, and
those disfavored bidders will invariably come up with arguments against its use. But that
disagreement cannot give rise to something akin to a due process proceeding absent
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 21 of 32

       Consistent with this hierarchy of purposes, Delaware courts have viewed challenges

under the Procurement Statute advanced by disappointed bidders with a healthy degree of

skepticism.102


evidence that the agency’s decision was so patently unreasonable that it was likely the
product of undue influence. Where a public agency is operating not as a regulator, but in
its proprietary capacity, courts are obligated to tread particularly lightly.”); Asphalt Paving
Sys., Inc. v. Dep't Transp., 2008 WL 852817, at *2 n.15 (Del. Ch. Mar. 20, 2008) (noting
that “public bidding laws were adopted to avoid the waste of public funds, thereby serving
to protect taxpayers.”); Edmonston v. Watson, 1988 WL 32372, at *3 (Del. Ch. Mar. 31,
1988) (“Generally, the purpose of statutes regulating the bidding on public contracts is to
protect the public interest.”); George & Lynch, Inc. v. Div. of Parks & Recreation, Dep't of
Nat. Res. & Env’t Control, 465 A.2d 345, 350 (Del. 1983) (stating that the protection of
public funds was a primary, but not exclusive, purpose of bidding statutes).
102
    See, e.g., George & Lynch, Inc., 465 A.2d at 352 (affirming this court’s denial of
disappointed bidder’s challenge to an agency contract award because disappointed bidder
failed to comply with statutory requirements for bid); Doctors Pathology, 2009 WL
4043299, at *4, *10 (dismissing a disappointed bidder’s challenge to an agency’s contract
award and noting that when the “general guidelines [of the Procurement Statute] are met
and in the absence of agency conduct that facially appears irrational, illegal, or tainted by
undue influence or favoritism, a court’s review of the solicitation process is extremely
limited”); Holley Enters., Inc. v. City of Wilm., 2009 WL 1743726, at *5 (Del. Ch. June 5,
2009) (denying a disappointed bidder’s request for a TRO and holding that agency was
reasonable in concluding that a criminal indictment disqualified the bidder as a
“responsible bidder” because under Delaware law “agencies need only a rational factual
basis for their decisions.”); Danvir Corp. v. City of Wilm., 2008 WL 4560903, at *7 (Del.
Ch. Oct. 6, 2008) (entering summary judgment against a disappointed bidder and noting
that the State is “vested with broad discretion in determining which applicant is the lowest
responsible bidder in a particular case and such a decision will not be disturbed unless it
can be shown to have been illegally or arbitrarily exercised”); Asphalt Paving, 2008 WL
852817, at *5 (granting summary judgment against a disappointed bidder because even if
bid documents supplied by the State were misleading, the disappointed bidder failed to
show they were actually misled); Autotote Lottery, 1994 WL 163633, at *7, *10 (granting
summary judgment against a disappointed bidder and noting that “the state’s business must
be done”); Delmarva Drilling Co., Inc. v. Kent Cty. Dep’t of Cmty. Dev., 1988 WL 39968,
at *2–3 (Del. Ch. Apr. 26, 1988) (dismissing a disappointed bidder’s request for a
preliminary injunction due to lack of standing, mootness, laches, and failure to join a
necessary party); Statewide Hi-Way Safety, Inc. v. Dep’t of Transp., 1983 WL 18024, at *3
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 22 of 32

       This judicial skepticism has manifested in two complimentary aspects of the legal

standard applicable to claims challenging a state agency’s exercise of discretion. When

determining whether a state agency abused its discretion under the Procurement Statute,

the court will only intervene if the agency exceeded the limits of its discretion where (i)

the actions were “arbitrary and capricious”103 and (ii) the violations were “material.”104

       This court has interpreted the arbitrary-and-capricious standard as highly

deferential.105   In Willdel, Chancellor Duffy described the arbitrary-and-capricious

standard in the context of a challenge to a zoning ordinance as follows:



(Del. Ch. June 28, 1983) (denying a disappointed bidder’s request for a TRO based on the
merits and based on standing because “bid statutes are for the benefit of the taxpayers and
others who would be adversely affected by the waste of public funds”).
Although the parties did not raise this issue, Delaware courts are split on whether
disappointed bidders have standing to sue in their capacity as bidders under the
Procurement Statute. See Asphalt Paving Sys., 2008 WL 852817, at *2 n.15 (holding that,
“[a]s a general matter, under Delaware law, disappointed bidders lack standing to challenge
an agency’s award of a contract.”); Statewide Hi-Way Safety, 1983 WL 18024, at *3
(same); Delmarva Drilling Co., 1988 WL 39968, at *2 (holding that “one who is not a
resident or not a taxpayer, but who sues only in the capacity of a disappointed low bidder,
has no standing”); but see Wahl v. City of Wilm., 1994 WL 13638, at *2 (Del. Ch. Jan. 10,
1994) (noting that granting standing to disappointed bidders is the better rule of law);
Danvir Corp., 2008 WL 4560903, at *4 (same).
103
    See Doctors Pathology, 2009 WL 4043299, at *5 (“Courts will only overturn the
determinations of State agencies where those decisions are arbitrary, capricious, or in bad
faith.”).
104
   Autotote Lottery, 1994 WL 163633, at *7 (“[T]hus only where material breaches in the
process are shown will a court intervene.”).
105
   See Protech, 2017 WL 5903357, at *7 (holding that award of maintenance and
operations contract was not an arbitrary and capricious exercise of power); Doctors
Pathology, 2009 WL 4043299, at *6 (holding that award of laboratory services contract
was not an arbitrary and capricious exercise of power); Danvir Corp., 2008 WL 4560903,
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 23 of 32

                    “Arbitrary and capricious” is usually ascribed to action which
                    is unreasonable or irrational, or to that which is unconsidered
                    or which is willful and not the result of a winnowing or sifting
                    process. It means action taken without consideration of and in
                    disregard of the facts and circumstances of the case. Action is
                    also said to be arbitrary and capricious if it is whimsical or
                    fickle, or not done according to reason; that is, it depends upon
                    the will alone.106

          In Harmony Construction, then-Vice Chancellor Jacobs had occasion to apply the

above principles in the context of a challenge under the Procurement Statute. There,

Harmony Construction, Inc. (“Harmony”) submitted the lowest bid for a public works

contract, but the Delaware Department of Transportation (“DelDOT”) awarded the contract

to the second lowest bidder.107 DelDOT reasoned that as start-up entity, Harmony lacked

the resources to complete the project on the contemplated timeline.108 Harmony filed suit

claiming that DelDOT violated the Procurement Statute by acting arbitrarily and

capriciously in arriving at its determination.109




at *7 (holding that award of city towing contract was not an arbitrary and capricious
exercise of power); Willdel Realty, Inc. v. New Castle Cty., 270 A.2d 174, 179 (Del. Ch.
1970), aff'd, 281 A.2d 612 (Del. 1971) (holding that zoning ordinance was not an arbitrary
and capricious exercise of power); but see Harmony Const., Inc. v. State Dep't of Transp.,
668 A.2d 746, 752 (Del. Ch. 1995) (holding that when an agency process deliberately fails
to communicate rules to a bidder, despite requiring compliance with those rules, then it
presents an extraordinary case where highly deferential arbitrary and capricious standard
is satisfied).
106
      Willdel Realty, Inc., 270 A.2d at 178.
107
      Harmony Const., 668 A.2d at 746.
108
      Id. at 749.
109
      Id. at 749–50.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 24 of 32

          The Vice Chancellor held that DelDOT’s decision not to award the contract to

Harmony was arbitrary and capricious and enjoined the contract award to the second lowest

bidder.110 The court held that an agency’s process is relevant to the judicial inquiry, and

found that DelDOT had not established rules in its process, but rather, “made the rules up

as it went along, never told Harmony what they were, and only after the game was over

was Harmony told that it flunked.”111 Consequently, DelDOT’s decision to shun the lowest

bidder based on such a defective process was not “the product of rational fact gathering

and decision-making process.”112

          Although the Vice Chancellor found in favor of the disappointed bidder, he

simultaneously emphasized that

                    [t]his Court will not normally or lightly decline to defer to a . .
                    . decision made by [an agency]. Given the broad discretion
                    conferred upon the agency . . . and the highly deferential nature
                    of the applicable judicial review standard, only in
                    extraordinary cases would this Court be justified in setting
                    aside such a decision.113

Put differently, the arbitrary-and-capricious standard is “clearly . . . deferential, and its

function is similar to that performed by the business judgment standard for reviewing



110
      Id. at 752.
111
      Id. at 751.
112
      Id. at 752.
113
    Id.; see also Doctors Pathology, 2009 WL 4043299, at *5 (describing Harmony as
establishing a highly deferential standard of review that will justify a court “set[ting] aside
[an agency’s] contract based upon the inadequacy of the agency’s decision-making
process” in “exceptional” circumstances only).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 25 of 32

decisions of corporate boards of directors.”114 The standard serves to “prevent second

guessing by courts of decisions that properly fall within the competence of a governmental

. . . decision-making body, so long as those decisions rest upon sufficient evidence and are

made in good faith, disinterestedly, and with appropriate due care.”115

            Second, a disappointed bidder must demonstrate that the alleged wrong was

material.116       In Autotote, Chancellor Allen considered cross-motions for summary

judgment on the State’s decision to award a five-year contract to run the State Lottery

Office.117 Although Autotote’s bid was superior in many ways to the successful bidder,

the Director of the State Lottery Office awarded the contract to the lowest bidder.118 The

plaintiff argued that the State breached the Procurement Statute by failing to get

concurrence that sealed bidding was impractical, disclose the relative weights of factors

being considered, and allow bidders to negotiate after proposals were submitted.119

            The Chancellor cautioned that “the purpose of the bidding laws is not to create a

field over which disappointed vendors can [pore] for hope of upsetting a rational, informed




114
      Harmony Const., 668 A.2d at 751.
115
  Id. (cleaned up); see also Save Our Cty., Inc. v. New Castle Cty., 2013 WL 2664187, at
*10 (Del. Ch. June 11, 2013); Holley Enters., 2009 WL 1743726, at *3.
116
      Autotote Lottery, 1994 WL 163633, at *7.
117
      Id. at *1.
118
      Id.
119
      Id. at *7.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 26 of 32

choice.”120 To further this principle, the Chancellor announced a materiality threshold,

holding that “[t]he state’s business must be done and thus only where material breaches in

the process are shown will a court intervene.”121 Chancellor Allen denied the plaintiff’s

motion for summary judgment. In reaching this conclusion, the Chancellor applied the

materiality threshold, observing in part that the plaintiff had failed to demonstrate any

injury for the imperfections it identified in the agency’s process.122

            To meet the doubly deferential standard in this case, ESI advances the same four

points for why the SEBC abused its discretion that it advanced on its motion for a

preliminary injunction. First, the SEBC treated ESI unequally by imposing “incumbent

vendor only” requirements.123 Second, the SEBC’s scoring of a lack of disruption to the

network and formulary factors did not fully credit the incumbent for this factor.124 Third,

the SEBC’s subjective evaluation of the objective cost factor lacked a rational basis.125

Fourth, the SEBC treated bidders unequally by waiving, as to some, the Phase I minimum

requirements.126




120
      Id.
121
      Id. (emphasis in original).
122
      Id.
123
      Pl.’s Opening Br. at 32–35.
124
      Id. at 38–41.
125
      Id. at 35–38.
126
      Id. at 41–46.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 27 of 32

         On the motion for a preliminary injunction, I found three of these arguments

compelling and concluded that ESI was likely to succeed in proving that aspects of the

SEBC’s process were arbitrary and capricious.127

         To summarize my prior findings, ESI presented evidence demonstrating that the

incumbent-only requirements restricted ESI’s ability to narrow its network and formulary,

that other bidders were not so limited, and that a narrower network and formulary generally

results in more competitive pricing. ESI also made a compelling argument that, because it

did not alter its network and formulary, it should have achieved high marks for minimizing

disruption to plan participants, but its scores on that factor seemed discounted. Similarly,

ESI demonstrated that the SEBC acted arbitrarily by using a subjective system to rank an

objectively quantifiable factor like cost.128 Although I held that these aspects of the process

were imperfect—and, indeed, arbitrary—in the end I questioned whether any of the process

deficiencies were material.129

         The record and arguments before me are the same as they were on the plaintiff’s

motion for a preliminary injunction. Unsurprisingly, my conclusions are the same. This

decision does not repeat the entirety of my prior analysis. It suffices to say that, although

ESI’s arguments concerning various deficiencies in the SEBC’s process continue to carry

logical force, ESI has again failed to demonstrate that the conduct was material. For


127
      PI Ruling at 48:5–9.
128
      PI Ruling at 43:12–21.
129
      PI Ruling at 52:11–53:8.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 28 of 32

example, would removing the incumbent-only requirements, accounting consistently for

the lack of disruption in ESI’s proposal, or standardizing the score cards on quantitative

factors have altered the ranking system in a way that was dispositive to the determination?

ESI has made no effort to meet this showing. The lack of any evidence concerning the

materiality of the alleged violations forecloses summary judgment in favor of ESI on this

issue.

         Accordingly, ESI’s motion for summary judgment as to Count I is DENIED.

                Count II

         In Count II, ESI claims that success on the merits of Counts I entitles ESI to a

permanent injunction, “ordering the SEBC to re-evaluate the proposals in accordance with

the RFP and its mandatory minimum requirements.”130

         A permanent injunction “is an extraordinary form of relief.”131 The elements for

permanent injunctive relief are: (1) actual success on the merits; (2) irreparable harm will

be suffered if injunctive relief is not granted; and (3) the harm to the plaintiff that will result

from a failure to enter an injunction outweighs the harm that befalls the defendants or other

interested parties, such as the public, if an injunction is granted.132 The elements are




130
      Am. Compl. at 37.
131
      N. River Ins. Co. v. Mine Safety Appliances Co., 105 A.3d 369, 384 (Del. 2014).
  Sierra Club v. Del. Dep’t of Nat. Res. & Envtl. Control, 2006 WL 1716913, at *3 (Del.
132

Ch. June 19, 2006).
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 29 of 32

conjunctive, ESI’s failure to satisfy any individual element defeats a request for a

permanent injunction.

         As discussed above, ESI has failed to demonstrate success on the merits of Count I,

thus defeating the first element of its claim for a permanent injunction in Count II. ESI

fails to prevail on its motion as to Count II for the additional reason that it has not

demonstrated based on undisputed facts that the equities tilt in its favor.

         As an initial matter, disrupting the transition to CVS would threaten the medical

benefits of large segments of the State’s population. I made this observation in the PI

Ruling. The same is true now. Although most of the GHIP members have now switched

to CVS, the EGWP segment has yet to transition. The EGWP segment is more vulnerable

than the Commercial segment and has a substantially higher rate of utilization of the

prescription drug benefit.133 Disrupting the transition at this stage would bring harm to the

EGWP population.

         Recognizing this previously identified weakness in its argument, ESI modified its

requested relief on summary judgment to seek a reevaluation of the bids. Specifically, ESI

seeks reevaluation before July 1, 2022, when the second year of CVS’s contract for the

Commercial population takes effect.134 Because the State must provide all plan documents,

rates, and other information to benefit-eligible members no later than 60 days prior to the




133
      Supp. Rentz Decl. ¶ 12.
134
      Oral Arg. Tr. at 23:12–15.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 30 of 32

start of the plan year,135 ESI’s requested relief would require the SEBC to complete its

reevaluation before May 2022.

          Even as modified, ESI’s requested relief would impose some level of harm on the

SEBC and the public. In the ordinary course, the overall time for a PBM procurement

process from start to finish takes approximately six months followed by approximately

three months of implementation work.136        The process, which would begin in mid-

December at the earliest, would have to be completed before the May 2022 open

enrollment. Thus, the reevaluation process contemplated by ESI would be rushed. Any

rebid of the PBM procurement would have to jockey with at least four other RFPs that the

SBO must complete over the specified timeframe, including a procurement for a GHIP

administrator which is described as a “larger scale than the PBM procurement.”137 Thus,

the six-month procurement process would need to be shortened by 25% while being

squeezed in between other planned projects. This timeline would be risky even under ideal

conditions, and any failures in this process would be borne by plan members and the public.

Even assuming that a new procurement was practicable on this timeline, an abrupt change

from CVS to ESI so close to the open enrollment could disrupt members’ benefits.138




135
      Supp. Rentz Decl. ¶ 19.
136
      Id. ¶ 20.
137
      Id. ¶¶ 14–17.
138
      Id. ¶ 21.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 31 of 32

         In the alternative, ESI argues for a reevaluation before January 2023, when the

second year of the EGWP contract takes effect.139 Although this timeline mitigates some

of the harms identified above, it does not eliminate such harm entirely. The SEBC would

still have to conduct the reevaluation atop of its normally scheduled duties. Plan members

would still be exposed to some harm in having to navigate a premature transition from CVS

to ESI in the event the reevaluation favors ESI. Certainly, the harm to CVS becomes more

severe under this scenario since CVS would have labored under the Commercial contract

for nearly a year and a half at the time of the reevaluation.

         While the harm to the public and stakeholders is lower in ESI’s alternative scenario,

the harm to ESI is also lower. In the ordinary course, the next procurement will begin in

June 2023.140 It is hard to conceive of how ESI would experience irreparable harm if I

decline to require the SEBC to act six months earlier—in January 2023.

         For these reasons, ESI has not met its burden of demonstrating that the equities tilt

it its favor, even on a more leisurely 2023 timeline.

         Accordingly, ESI’s motion for summary judgment as to Count II is DENIED.

III.     CONCLUSION

         ESI’s motion for summary judgment is denied. Does it automatically follow that

the Defendants’ cross-motions for summary judgment must be granted? The parties did




139
      Oral Arg. Tr. 28:12–20.
140
      See Rentz Decl. ¶ 14, 24.
C.A. No. 2021-0434-KSJM
December 13, 2021
Page 32 of 32

not develop this issue in briefing.     They are granted leave to make supplemental

submissions concerning the effect of the findings in this decision on Defendants’ cross-

motion for summary judgment.

                                         Sincerely,

                                         /s/ Kathaleen St. J. McCormick

                                         Kathaleen St. J. McCormick
                                         Chancellor

cc:   Counsel of record (by e-filing)