IN THE SUPREME COURT OF MISSISSIPPI
NO. 96-CA-00464-SCT
COY C. CARPENTER
v.
DAVID W. DAWSON AND THE CITY OF
SOUTHHAVEN
DATE OF JUDGMENT: 04/05/96
TRIAL JUDGE: HON. GEORGE B. READY
COURT FROM WHICH APPEALED: DESOTO COUNTY CIRCUIT COURT
ATTORNEY FOR APPELLANT: WILLIAM P. MYERS
ATTORNEY FOR APPELLEES: WILTON V. BYARS, III
NATURE OF THE CASE: CIVIL - OTHER
DISPOSITION: AFFIRMED - 11/13/97
MOTION FOR REHEARING FILED:
MANDATE ISSUED: 12/4/97
EN BANC.
PRATHER, PRESIDING JUSTICE, FOR THE COURT:
I. STATEMENT OF THE FACTS AND CASE
¶1. On July 17, 1994, Coy Carpenter was injured in a collision with an auto driven by David Dawson,
an officer on duty with the City of Southaven police. Counsel for Carpenter contacted the liability
carrier for Southaven in an unsuccessful attempt to reach a settlement, but Carpenter did not submit a
notice of claim to the City. Carpenter filed suit against Southaven and Dawson on October 5, 1995,
one year and eighty days after the accident in question. Southaven was granted summary judgment by
the Circuit Court of Desoto County based upon the running of the one-year statute of limitations in
Miss. Code Ann. § 11-46-11. Feeling aggrieved, Carpenter timely appealed said ruling to this Court.
II. ISSUES
A. IS NOTICE OF CLAIM TO INSURANCE CARRIER IS SUFFICIENT TO TOLL
RUNNING OF STATUTE OF LIMITATIONS AGAINST THE CITY?
¶2. The instant appeal involves substantially the same issue confronted by this Court in Robinson v.
Lumpkin, 95-CA-00627-SCT, (Miss. July 31, 1997), that is, whether this Court will strictly enforce
the statutory requirement for notice in the Tort Claims Act, specifically Miss. Code Ann. § 11-46-11.
This Court held in Lumpkin that notification which, as here, was not provided to the "chief executive
officer" of the governmental entity in question did not comply with the statutory requirements for
notice. Carpenter argues that the one year statute of limitations provided in the Tort Claims Act
statutes was tolled for an additional ninety-five (95) days based upon the fact that he provided notice
of his claim to the insurance carrier for the City of Southaven.
¶3. Miss. Code Ann. § 11-46-11 provides that:
(1) After all procedures within a governmental entity have been exhausted, any person having a
claim for injury arising under the provisions of this chapter against a governmental entity or its
employee shall proceed as he might in any action at law or in equity; provided, however, that
ninety (90) days prior to maintaining an action thereon, such person shall file a notice of claim
with the chief executive officer of the governmental entity;
(2) The notice of claim required by subsection (1) of this section shall be in writing, delivered in
person or by registered or certified United States mail. Every notice of claim shall contain a
short and plain statement of the facts upon which the claim is based, including the
circumstances which brought about the injury, the extent of the injury, the time and place the
injury occurred, the names of all persons known to be involved, the amount of money damages
sought and the residence of the person making the claim at the time of the injury and at the time
of filing the notice.
(3) All actions brought under the provisions of this chapter shall be commenced within one (1)
year next after the date of the tortious, wrongful or otherwise actionable conduct on which the
liability phase of the action is based, and not after; provided, however, that the filing of a notice
of claim as required by subsection (1) of this section shall serve to toll the statute of limitations
for a period of ninety-five (95) days. The limitations period provided herein shall control and
shall be exclusive in all actions subject to and brought under the provisions of this chapter,
notwithstanding the nature of the claim, the label or other characterization the claimant may use
to describe it, or the provisions of any other statute of limitations which would otherwise
govern the type of claim or legal theory if it were not subject to or brought under the provisions
of this chapter.
¶4. The accident from which the present case arose occurred on July 17, 1994, and Carpenter did not
file suit until October 5, 1995. Absent the tolling of the one-year statute of limitations by the
providing of statutorily valid notice, Carpenter's suit is thus barred by the one-year statute of
limitations. It is clear that the notice provided by Carpenter in the present case did not comply with
the requirements of Miss. Code Ann. § 11-46-11, and the trial court thus correctly ruled that
Carpenter's claim was not timely filed.
¶5. The notice provided by Carpenter, in the form of a two sentence letter to the city's liability carrier,
merely sets forth the names of the plaintiff and the defendant and the date of the accident. In addition
to failing to provide the "chief executive officer" (i.e. the mayor) with the required notice, it is
apparent that the notice lacked much of the statutorily required information regarding the claim.
Specifically, the notice failed to contain a "short and plain statement of facts," the "extent of the
injury," the "time and place the injury occurred," the "names of all persons known to be involved,"
"the amount of damages sought," and the "residence of the person making the claims." Under these
facts, the notice granted by Carpenter could not even be said to "substantially" comply with the
requirements of Miss. Code Ann. § 11-46-11, and the notice is certainly not sufficient under a strict
construction of the statute.
¶6. It is clear that the notice provisions contained in the Torts Claims Act statutes constitute a
litigation "pitfall" for plaintiffs' attorneys in cases filed against the state and its political subdivisions.
The notice provisions in Miss. Code Ann. § 11-46-11 are detailed and set forth requirements for
notice which differ from those in the Mississippi Rules of Civil Procedure, to which attorneys in this
State are accustomed. In this context, mistakes in complying with the required notification
procedures are not surprising, and the enforcement of the statutory notice provisions will, at times,
bring about harsh results. The alternative, however, is that this Court and the trial courts ignore
specific statutory requirements for notice phrased in mandatory language by the Legislature.
¶7. The Legislature mandated that the required notice "shall" be provided, and the trial judge
correctly concluded that the statute should be strictly enforced. It would set a dangerous precedent if
this Court were to ignore specific statutory requirements for notice. This Court must enforce the
statute as written, and the members of the bar will comply with the requirements therein, which are
not overly burdensome or complicated. The main obstacle to compliance with the notice provisions is
a lack of knowledge of the requirements therein, and this obstacle will presumably become less of a
factor with the passage of time and with the assistance of continuing legal education. As always, the
Legislature retains the authority to modify the statutory language in question.
B. DID THE CITY WAIVE ITS RIGHT TO RAISE STATUTE OF LIMITATIONS?
¶8. As an alternative argument, Carpenter contends that the City waived the right to raise the lack of
notification issue through "acceptance of notice to the insurance carrier." This argument is without
merit. The City raised the defenses of the statute of limitations and lack of notice in their answer to
Carpenter's complaint, and these defenses were not waived by the fact that the City did not reject the
notification or otherwise notify Carpenter of the deficiencies therein. It is not the responsibility of the
City or any other defendant to ensure that a plaintiff seeking damages against them complies with the
applicable notice requirements, and this Court concludes that this point of error is without merit. The
Circuit Judge's summary judgment ruling is affirmed.
¶9. JUDGMENT IS AFFIRMED.
LEE, C.J., BANKS, SMITH AND ROBERTS, JJ., CONCUR. McRAE, J., DISSENTS WITH
SEPARATE WRITTEN OPINION JOINED BY SULLIVAN, P.J., AND PITTMAN, J.
MILLS, J., NOT PARTICIPATING.
McRAE, JUSTICE, DISSENTING:
¶10. I disagree with the majority's decision to affirm the lower court's order granting summary
judgment to the City of Southhaven. The City's immunity was waived to the extent of liability
insurance carried. Carpenter's attorney contacted the City's liability insurance carrier, the real party in
interest since it would be liable for payment of any successful claim against the City, and attempted to
reach a settlement within the one year statute of limitations specified by the Tort Claims Act. As the
carrier for the City's liability insurance, the insurer was the City's agent in fact. Thus, the City was
provided with notice of Carpenter's claim.
¶11. As explained in my dissent in City of Jackson v. Lumpkin, 697 So. 2d 1179 (Miss. 1997), we
generally have applied a "substantial compliance" standard when determining whether the
requirements of a statute have been met. Evans v. Boyle Flying Service, Inc., 680 So. 2d 821, 830
(Miss. 1996); Brown v. Riley, 580 So. 2d 1234, 1237 (Miss. 1991); Bell v. Mitchell, 592 So. 2d
528, 531 (Miss. 1991); Jones v. Welford, 208 So. 2d 196, 199 (Miss. 1968). The majority, instead,
as it did in Lumpkin, erroneously imposes a "strict compliance" construction upon the notice
requirement set forth in Miss. Code Ann. § 11-46-11. In the case sub judice, although Carpenter
made no "notice of claim" directly to the statutorily designated officer, his attorney notified the City's
insurance carrier of his claim. He therefore substantially complied with the requirements of the
statute. Because the majority again has departed from our familiar construction of compliance
standards, I dissent.
SULLIVAN, P.J., AND PITTMAN, J., JOIN THIS OPINION.