NO. 94-441
IN THE SUPREME COURT OF THE STATE OF MONTANA
1995
MONTANA POWER COMPANY, a Montana
Corporation,
Plaintiff and Respondent,
BURLINGTON NORTHERN RAILROAD COMPANY,
a subsidiary of BURLINGTON
NORTHERN, INC.,
Defendant and Appellant.
APPEAL FROM: District Court of the Eighth Judicial District,
In and for the County of Cascade,
The Honorable Joel G. Roth, Judge presiding.
COUNSEL OF RECORD:
For Appellant:
J. Daniel Hoven, Ken C. Crippen, Browning, Kaleczyc,
Berry & Haven, Helena, Montana
For Respondent:
Joseph W. Sabol, Bozeman, Montana
Heard and Submitted: May 18, 1995
Decided: July 25, 199.5
Filed:
Justice Fred J. Weber delivered the Opinion of the Court
This is an appeal from a decision of the Eighth Judicial
District Court granting Montana Power Company's (MPC) Preliminary
Condemnation Order and Order of Possession of the easement through
Burlington Northern's (BN) property. We affirm and remand to the
District Court as herein specified.
We restate the issues on appeal:
I. Did the District Court err when it found an easement through
BN's property was necessary for the intended use and subject to
condemnation?
II. Did the District Court err when it found that MPC's
transmission line was a more necessary use?
III. Did the District Court err when it failed to include any of
the requested provisions in its Order of Possession?
MPC has contracted with various railroads using wire-line
permits to construct, operate, and maintain electric transmission
lines through railroad rights-of-way for over fifty years.
Currently, MPC operates transmission lines through such rights-of-
way under 1,400 wire-line permits provided by BN.
In 1990, MPC determined additional facilities needed to be
constructed in southwest Great Falls to adequately service its
customers as required by law. The line's construction cost
approximately $2.2 million. BN does not dispute the need nor the
location of the 100 kV transmission facility. MPC acquired
easements by purchase on all private parcels of property along the
proposed route for the transmission lines except for BN's property.
2
MPC offered to purchase an easement interest for the Great Falls
transmission facility through BN's property. EN offered to grant
a wire-line permit instead. MPC claimed the permit's revocability
and indemnification clauses were onerous and rejected BN's offer.
Subsequently BN offered an easement to MPC which incorporated
a Memorandum of Understanding which BN claimed met MPC's concerns
regarding permanency while addressing the issue of indemnification
which was of concern to BN. MPC rejected BN's offer of an easement
because MPC claimed the Memorandum of Understanding granted to BN
the sole and exclusive option of revocation. Finally, in order to
facilitate MPC's request to begin construction of the transmission
line, BN offered a revised wire-line permit extending the
termination provision from 30 days to 180 days. MPC rejected this
offer as well.
MPC filed a Complaint together with a request for an Order to
Show Cause in the Eighth Judicial District Court to condemn an
easement over BN's property for the purpose of constructing,
operating, and maintaining an electric transmission line. BN filed
a motion for Summary Judgment in its favor with a supporting brief
contending that MPC's purpose could be accomplished through a wire-
line permit historically used by the two parties. MPC filed a
brief in opposition to BN's motion and requested from the court a
Preliminary Condemnation Order under § 70-30-203, MCA. The
District Court found an easement was the minimum estate in BN's
land necessary for MPC's proposed use as required for the public's
interest. The court denied BN's motion for Summary Judgment and
3
granted MPC's Preliminary Condemnation Order.
Pursuant to statute, BN filed its Statement of Claim for
$8,700--the value of the easement sought to be condemned. However,
BN claimed the value represented that of the easement along with
BN's Memorandum of Understanding or subject to additional
compensation for BN's increased liability. After posting $8,700,
MPC requested and was granted an Order of Possession. MPC then
commenced construction of the electrical transmission facility. BN
moved the court to reconsider this Order. The court denied BN's
motion
From the District Court‘s issuance of the Preliminary
Condemnation Order and the Order of Possession, BN appeals.
Standard of Review
Our standard of review is set forth in Y A Bar Livestock
Company v. Harkness (Mont. 1994), 887 P.2d 1211, 1213, 51 St.Rep.
1517, 1519, as follows:
This Court reviews the findings of a trial court
sitting without a jury to determine if the court's
findings are clearly erroneous. Rule 52(a), M.R.Civ.P..
A district court's findings are clearly erroneous if they
are not supported by substantial credible evidence, if
the trial court has misapprehended the effect of the
evidence, or if a review of the record leaves this Court
with the definite and firm conviction that a mistake has
been committed. Interstate Prod. Credit Ass'n v. DeSaye
(1991), 250 Mont. 320, 323, 820 P.2d 1285, 1287.
Issue I
Did the District Court err when it found an easement through
BN's property was necessary for the intended use and subject to
condemnation?
Section 70-30-111, MCA, describes the required proof for a
4
taking by condemnation:
Before property can be taken, the plaintiff must show by
a preponderance of the evidence that the public interest
requires the taking based on the following findings:
(1) that the use to which it is to be applied is a use
authorized by law;
(2) that the taking is necessary to such use;
(3) if already appropriated to some public use, that
the public use to which it is to be applied is a more
necessary public use;
(4) that an effort to obtain the interest sought to be
condemned was made by submission of a written offer and
that such offer was rejected.
Electric power lines are a public use authorized by law for the
exercise of the right of eminent domain. Section 70-30-102(11),
In determining if the taking is necessary for the authorized
use, BN cites to Montana Power Company v. Bokma (1969), 153 Mont.
390, 390, 457 P.2d 769, 774. In that case, we held necessity means
"reasonable, requisite, and proper for the accomplishment of the
end in view, under the particular circumstances of the case." BN
argues MPC's condemned easement over BN's railroad right-of-way is
a greater interest than is necessary for the intended use. BN
refers to Silver Bow County v. Hafer (1975), 166 Mont. 330, 333,
532 P.2d 691, 693, where we stated a condemning authority cannot
acquire a greater interest or estate in the condemned property than
the public use requires. To do so would obligate the public to pay
for more than it needs
BN contends an easement without any restrictions is too great
an interest when a wire-line permit will permit the desired use.
BN claims a wire-line permit includes the right of entry upon and
occupation of land and is a right in land which may be taken for
5
public use. See § 70-30-104(4), MCA. BN offered to MPC a wire-
line permit which allowed for the location, construction,
operation, maintenance, replacement and removal of MPC's Great
Falls transmission line. MPC rejected this offer.
In response to MPC's concern about the wire-line permit's lack
of permanence and allowance for rent escalation, BN offered to MPC
an Electric Transmission Line Non-exclusive Easement which
incorporated a Memorandum of Understanding. BN claims the
proffered easement was non-revocable and contained a one-time fee
payment. Yet, BN argues MPC rejected this offer and insisted upon
the condemnation of an unreasonably unrestricted easement.
BN alleges MPC sought an unrestricted easement because
obtaining greater ownership rights was in the best interest of
MPC's shareholders. BN contends that allowing MPC to take an
easement when a permit interest would suffice all in the name of
shareholders' best interests violates fundamental principles this
Court has upheld in eminent domain proceedings.
MPC claims that for eighty years it has obtained wire-line
permits from BN for constructing electrical lines throughout
Montana. During that time, MPC showed that BN and its assignees
subjected MPC to escalating fee provisions, restrictive
indemnification provisions, and unilateral termination and
relocation provisions. MPC contends it could no longer justify the
permit process required to be followed by BN. A decision was made
by MPC's corporate management to seek and obtain when necessary an
easement from BN for the construction, operation and maintenance of
6
electrical transmission lines in BN's railroad rights-of-way.
MPC concedes that it can construct, operate and maintain the
electrical transmission facility through a wire-line permit.
However, MPC claims the permit offered by BN was revocable without
cause 100 days after receipt of notice by MPC and contained onerous
indemnification and relocation provisions. Under that permit's
indemnification provisions, MPC argues it opens itself up to untold
and unimagined exposure for BN's negligence. MPC submits that
parties should be responsible for their own negligent conduct.
Furthermore, MPC would not accept the unilateral termination
provisions of the permit. MPC argues the permit is nothing more
than a mere license as evidenced by its very terms. A license is
revokable at will and is not an interest in land. An easement,
however, is a non-possessory interest in the land of another. MPC
argues this distinction is significant when resolving questions
about the applicability of the statutes of fraud and the
availability of compensation in condemnation actions.
MPC claims the Non-exclusive Easement proffered by BN is
nothing more than a permit/license no matter what the name implies.
MPC submits that history has taught the company it is no longer
appropriate for MPC to accept BN's wire-line permit, revised or
not, or its supposed Non-exclusive Easement which, when coupled
with the Memorandum of Understanding, grants to BN the sole and
exclusive option of revocation.
Section 70-30-111, MCA, as previously set forth, requires that
the plaintiff show by a preponderance of the evidence that the
7
public interest requires the taking based on four specified
findings. Subparagraph (1) requires a finding that the use which
is to, be applied is a use authorized by law. Section 70-30-
102 (11) , MCA, lists electric power lines as a public use subject to
eminent domain proceedings. MPC produced uncontradicted testimony
about the area's need for the electric transmission facility as
well as the practicality of locating the line on BN's right-of-way.
BN, in fact, does not contest the need nor the location of the
transmission line. We affirm the conclusions of the District Court
that subparagraph (1) of § 70-30-111, MCA, has been met.
Subparagraph (3) of § 70-30-111, MCA, pertains to the more
necessary public use question which is addressed in the next issue.
Subparagraph (4) of that section requires a finding that an effort
was made to obtain the interest by submission of a written offer
and that such offer was rejected. Again, there is no dispute that
MPC made such an offer to BN and that its offer was rejected.
We next discuss subparagraph ('21, which requires a finding
that the taking is necessary to such use. This Court has stated
that "necessary" is not intended to mean absolute, but rather
reasonable, requisite, and proper. Montana Power Company, 457 P.Zd
at 774. As previously mentioned, MPC has submitted uncontradicted
testimony as to the need for the electric transmission facility and
practicality of locating it on the BN's right-of-way and BN does
not contest that need nor the location. We conclude that the
record contains substantial credible evidence to support the
District Court's finding and conclusion that there was a public
8
need for a transmission line in southwest Great Falls which would
run along BN's right-of-way. We note that BN produced no evidence
to contradict the choice of location or the public's need for the
proposed line.
MPC contends that § 70-30-206, MCA, gives the District Court
the power to determine if the interest sought to be condemned is
necessary. In pertinent part § 70-30-206, MCA, provides:
70-30-206. Powers of court--preliminary
condemnation order. (1) The court has power to:
(a) regulate and determine the place and manner of
making the connections and crossings and enjoying the
common uses mentioned in 70-30-103(l) (a) . .
(b) limit the interest in real property sought to be
appropriated if in the opinion of the court the interest
sought is not necessary.
In pertinent part § 70-30-103, MCA, provides:
70-30-103. What private property zay be taken. (1)
The private property which may be taken under this
chapter includes:
iej all rights-of-way for any and all the purposes
mentioned in 70-30-102 and any and all structures and
improvements thereon, and the lands held and used in
connection therewith must be subject to be connected
with, crossed, or intersected by any other rights-of-way
of improvements or structures thereon. They must also be
subject to a limited use in common with the owner thereof
when necessary; but such uses, crossings, intersections,
and connections must be made in manner most compatible
with the greatest public benefit and least private
injury.
MPC contends that under the foregoing sections, the District Court
had the discretion to determine if the interest sought to be
condemned was necessary. It further contends that sufficient
evidence was produced to establish the necessity of taking, and
that, as a result, BN now has the burden of proving the taking was
excessive or arbitrary and therefore unnecessary. Lincoln/Lewis &
9
Clark County Sewer District v. Bossing (1985), 215 Mont. 235, 239,
696 P.2d 989, 991. MPC further stresses that the District Court
found no basis on which to limit the interest sought after
consideration of all of the evidence presented.
The District Court concluded "an easement for so long as the
line is necessary is the minimum estate in [BN'S] land required by
MPC." As a result, the District Court concluded "MPC is entitled
to a preliminary condemnation order for the easement sought to be
condemned over, through and across the lands of [BN] as
specifically described in Exhibit 'A' attached to [MPC'sl Complaint
for the construction of an electrical transmission line."
Applying the above-described standard of review, we hold that
the District Court's conclusion, that an easement for the electric
power transmission line is necessary, is supported by substantial
credible evidence. We further hold that the District Court did not
misapprehend the effect of the evidence and that our review of the
record does not suggest to this Court that a mistake has been
committed.
The dissent points out that it is possible for MPC to locate,
construct, operate, maintain and remove the transmission facility
with a wire-line permit. BN's proposed wire-line permit contained
a 180 day termination provision. There is substantial evidence in
the record to support a conclusion that the termination provision
is unreasonable and improper considering the expenses of over $2
million to initially construct the facility and the length of time
which it takes to reconstruct or move such a facility as well as
10
the public's need for this particular facility. In response to
this suggestion, we therefore conclude that there is substantial
evidence to support the finding of the District Court that an
easement was necessary as compared to such a wire-line permit. 1n
addition, we conclude that the District Court did not misapprehend
the evidence nor make a mistake in its findings.
We hold that the District Court did not err when it found an
easement through BN's property was necessary for the intended use
and subject to condemnation.
Issue II
Did the District Court err when it found that MPC's
transmission line was a more necessary use?
Section 70-30-111(3), MCA, states that if the property is
already appropriated to some public use, the public use to which it
is condemned must be a more necessary use.
BN claims the District Court misapplied the legal analysis in
its determination of "more necessary use". The District Court
found the two public uses compatible, but then went on to find
MPC's public use a more necessary use than that of BN. BN argues
finding the uses compatible in the first instance made it
unnecessary and inappropriate to make the determination of a more
necessary use in favor of MPC. BN alleges the court was confused
on this issue, and, therefore, erred in not including in its grant
to MPC the historical provisions necessary to protect BN's pre-
existing railroad.
MPC asserts the Legislature of the State of Montana intended
11
the classification of a "more necessary public use" to be required
when a proposed use would destroy a prior one. Cocanougher v.
Zeigler (1941), 112 Mont. 76, 112 P.2d 1058. MPC argues a mere
inconvenience to the prior use or the occurrence of compensable
damages is not sufficient to deny a grant of eminent domain for the
proposed use. MPC alleges any potential damage to BN's operation
would be marginal; therefore, the District Court correctly found
the two uses compatible.
Paragraph 7(c) of the District Court's finding of fact states:
That MPC has shown by a preponderance of the evidence
that the public interest requires the taking of a portion
of [BN]'s right-of-way and:
. . .
c . That notwithstanding the fact that the right-of-
way is already appropriated for a public use that the
easement sought to be condemned by MPC for the electrical
transmission line is a more __ ecessary public use and one
n
which is compatible with the use of [BN'S] land;
. .
Section 70-30-111(3), MCA, provides that if the property is
already appropriated to a public use, the use to which it is to be
applied must be determined by a preponderance of the evidence to be
a more necessary public use. In Montana Talc Co. v. Cyprus Mines
Corp. (1987), 229 Mont. 491, 502-04, 748 P.2d 444, 451-52 (citing
Butte, Anaconda & Pacific Railway Company v. The Montana Union
Railway Company (1895), 16 Mont. 504, 538, 41 P. 232, 244), we
recognized that "'our legislature has imposed upon the court the
additional responsibility of judicially determining whether the use
to which the appellants did or would put the particular lands is a
more necessary one to the public than that to which they have
already been appropriated. .I' In interpreting the “more
12
neCeSSary” requirement of § 70-30-111(3), MCA, we have held that
this determination affects condemnation proceedings only when we
have two public uses that are not compatible uses. Montana Talc,
748 P.2d at 452; Cocanouqher, 112 P.2d at 1061; Butte, Anaconda &
Pacific, 41 P. at 244.
In Cocanousher, the issue presented was whether the plaintiff
and defendant could have a joint use of a water supply ditch where
one use was not more necessary than the other. In that case, the
Court stated:
The next question that arises concerns the legal
question of whether or not, as a matter of law, one may
condemn a right-of-way through a ditch on another's land
where the ditch is being used to irrigate the latter's
land. Defendant invokes subdivision 3 of section 9936,
Revised Codes [same as subparagraph (3) of § 70-30-111,
MCAI Under this subdivision the real question is: Will
the taking of this private property, already dedicated to
one public use, destroy the prior public use? Or, in
other words, will the enlargement and joint use of the
ditch in question result in destroying or materially
injuring the defendant's right to the use of the ditch?
That subdivision can only apply where there is a taking
of the property dedicated to a public use and
appropriating it to another public use. The implication
is clear that the legislature had in mind in enacting
that subdivision, when it speaks of a more necessary
public use than that to which the property is already
dedicated, that the latter use is such as will destroy
the prior use. That not being the case, subdivision 3
does not inhibit the condemnation here sought.
Cocanousher, 112 P.2d at 1060
MPC seeks to condemn private property already dedicated to one
public use in order for it to provide a different public use. In
following Cocanouqher, we must ask whether MPC's proposed use will
destroy or materially injure BN's prior use. The District Court
found the two public uses to be compatible uses. BN and MPC both
13
agree that the two uses could be made compatible. The latter use
does not inhibit the prior use; therefore, we conclude subsection
(3) of 5 70-30-111, MCA, does not apply to these condemnation
procedures.
In Montana Talc Co., we refer to Cocanouqher's extensive
.discussion of the requirement in § 70-30-111(3), MCA, for a "more
necessary" public use. We concluded:
The proposed use must be "more necessary" where the
effect of granting the succeeding public use condemnation
will deprive the first owner of his use altogether. If
the first owner will be completely deprived of his public
use of appropriated property, such that his use will be
defeated or seriously interfered with by the proposed
condemnor's right if granted, the statute requiring a
"more necessary" public use comes into play. The
requirement of a more necessary public use "does not
preclude condemnation for a ioint use which will not
interfere with the use thereof bv the owner."
Cocanousher, 112 P.2d at 1051. (Emphasis added.)
Montana Talc Co., 748 P.2d at 454.
BN's argument that "compatibility" and "more necessary" are
inconsistent terms fails. A more necessary use can also be a
compatible use. The District Court made a "more necessary"
determination under the erroneous assumption that such
determination was required under the statute. The court was not
required to make that determination because MPC's use would not
destroy nor materially injure BN's prior use. In any event, we
conclude the court's "more necessary" determination is not
reversible error because the court also found the two uses
compatible.
We hold the District Court did not commit reversible error
when it found that MPC's transmission line was a more necessary
14
use.
Issue III
Did the District Court err when it failed to include any of
the requested provisions in its Order of Possession?
The District Court granted to MPC the easement attached to
MPC's complaint--the Overhead Electric Right-of-way Easement. That
easement gave to MPC the right "to construct, operate, maintain,
replace and remove an electric transmission line with electric
distribution underbuild facilities, associated guy facilities,
communication system and necessary appurtenances over, under, along
and across that certain real property. . .'I The easement
included the "reasonable right of ingress to and egress from said
transmission line right of way over lands of the Grantor using
existing roads and trails where practicable, and the right to clear
and remove all timber and brush from the right of way . . . and to
cut and remove such trees outside of such right of way which may
endanger said line or lines."
BN claims any grant to MPC should also address the location of
poles, the design standards, clearances of lines, crossings,
coordination during construction of the transmission line,
indemnification for damages caused by or resulting from the
operation of the transmission line and its relocation. Without
these provisions, BN argues it may be unable to meet its statutory
obligations to keep timely fixed schedules, furnish shipping
facilities, construct drains and ditches, maintain fences and fire
guards, and construct and maintain commercial spur tracks.
15
In addition, EN contends the District Court's grant to MPC
unreasonably subjects BN to increased liability. BN's witness
testified to the potential safety and operational hazards of
locating high voltage transmission lines near steel railroad
operations. BN claims the two parties have co-existed in the past
solely because of the provisions included in the historical
agreements. BN asks that the Court insert the provisions of the
Memorandum of Understanding. The key provisions of such memorandum
are the following:
. .
13. Montana Power Company does hereby release,
indemnify, and save harmless [BN] . . from and against
all loss, damages, claims, demands, actions, causes of
action, costs and expenses of every character which may
result from any injury to or death of any person
whomsoever, including but not limited to employees and
agents of the parties hereto, or from loss of or damage
to property of any kind or nature to whomsoever
belonging, including but not limited to property owned
by, leased to, or in the care, custody, and control of
the parties hereto, when such injury, death, loss or
damage is caused by or contributed to by, or arises from,
the construction, installation, operation, maintenance,
condition, use, removal or existence of the electric
transmission line upon or adjacent to the Premises.
14. It is understood by the parties that said electric
transmission line will be in danger of damage or
destruction by fire or explosion incident to the
operation, maintenance, or improvement of the railway,
and [MPCI accepts the [easement] subject to such dangers.
It is, therefore, agreed, as one of the material
considerations for such . . easement . . . that [MPCI
hereby assumes all risk of loss, damage, or destruction
to said electric transmission line without regard to
whether such loss be occasioned by fire or sparks from
locomotives, or other causes incident to or arising from
the movement of locomotives, trains, or cars of any kind,
misaligned switches, or in any respect from the
operation, maintenance, or improvement of the railway, or
to whether such loss or damage be the result of
negligence or misconduct or any person in the employ or
services of [BNI, or of defective appliances, engines or
16
machinery, and [MPCI does hereby save and hold harmless
[BNI from all such damage, claims, and losses to said
electric transmission line.
15. Prior to construction, operation, maintenance,
and/or removal of the transmission line or any part of
the premises described on the electric transmission line
. . easement . ., [MPCI shall furnish to [BN] a
Railroad Protective Liability Policy. Such Railroad
Protective Liability Policy shall list [BN] as the named
insured and shall provide a minimum of Two Million
Dollars ($2,000,000) for each bodily injury claim and
property damage claim with an aggregate of Six Million
Dollars ($6,000,000). In addition, [MPC] shall furnish
to [BNI a Commercial General Liability Insurance Policy
. . . listing Burlington Northern Railroad Company as the
named insured. Such Commercial General Liability Policy
shall provide a minimum of One Million Dollars
($l,OOO,OOO) per occurrence for claims arising out of
bodily injury and property damage. [MPCI further agrees
that prior to construction, operation, maintenance and/or
removal of the transmission line, [BN] must expressly
approve of the types and amounts of insurance coverage
provided pursuant to this paragraph.
.
19. [MPCI agrees that if [BN] determines that the
location of the electric transmission line must be
changed for the relocation or placement of railroad
tracks or operational improvements, or for reasons beyond
the control of [BNI, [BN] shall notify [MPCI of such
plans and [BNI shall further use its best reasonable
efforts to secure an alternative location for the
electric transmission line. [MPCI shall then move the
affected electric transmission line to such alternative
location at [MPCl's own expense, cost and risk as soon as
practicable.
. .
22. If the Premises described, or any part thereof,
_ _
shall at any time cease to be used by [MPC] for the
purposes of conducting electric currents through the
electric transmission line, or should the Premises be
converted to any other use whatsoever, or should [MPCI
fail to perform any of the conditions contained in [this
easement], then and in any such event, [BN], its
successors and assigns, may, at its or their option, re-
enter, retake and hold the Premises as of the present
estate of [BNI without compensation to [MPCl or any other
person whomsoever, for improvements or property removed,
taken or destroyed, or liability for loss of, or damage
to any part of the Premises or the improvements thereon,
and all the right, title, interest, benefits and
enjoyment of [MPC] in the premises, for any purposes
17
whatsoever, shall immediately cease.
Although MPC states in its brief that BN's wire-line permit
and Non-exclusive Easement are untenable due to their revocability
provisions (MPC specifically refers to 722 of BN's Memorandum of
Understanding), the transcript of the proceedings reveals MPC
agreed that both parties could be easily accommodated as to this
issue. It is the indemnification provisions which the court found
to be the real stumbling block.
MPC argued at the hearing that conditions included in BN's
Memorandum of Understanding relating to design standards,
coordination between the parties, safety, train delay and
relocation should not be attached to the documents for condemnation
because "it was always common place and common sense that the
district manager notified BN before they came on the property .
[and, in addition,] they never intentionally did anything
unsafe or that would cause harm or damage to BN or anybody else."
MPC alleges BN insists upon the attachment of the provisions in the
Memorandum of Understanding in order to unjustly limit the interest
condemned.
In the District Court's Memorandum Decision attached to its
Order Denying Defendant's Motion for Reconsideration of Order of
Possession, the court concluded there was no statutory basis or
requirement that protective conditions be set forth in the said
Order of Possession. We agree that the eminent domain statues do
not require protective conditions in an easement. However, the
Montana Legislature has given to the courts the power to set forth
18
protective provisions in an order for condemnation.
70-30-206. (1) The court has power to:
(a) regulate and determine the place and manner of
making the connections and crossings and enjoyinq the
m e n tu si s o n e d
common e i n 70-30-103(e) and of the
occupying of canyons, passes, and defiles for railroad
purposes, as permitted and regulated by the laws of this
state or of the United States . . (Emphasis added.)
.
The common uses extend to:
70-30-103. (1) The private property which may be taken
under this chapter includes:
.
(e) all rights-of-way for any and all the purposes
mentioned in 70-30-102 and any and all structures and
improvements thereon, and the lands held and used in
connection therewith must be subject to be connected
with, crossed, or intersected by any other right-of-way
of improvements or structures thereon. They must also be
subject to a limited use in common with the owner thereof
when necessary; but such uses, crossings, intersections,
and connections must be made in manner most compatible
with the greatest public benefit and least private
injury. .
Both railways and electric power lines are public uses enumerated
in this chapter. Section 70-30-102(10),(11), MCA.
Under the facts of this case, we hold that the District Court
did not commit reversible error when it failed to include any of
the requested provisions in its Order of Possession. However, the
District Court properly should have considered the foregoing
statutes and determined if any of the proposed conditions should
have been inserted in its Preliminary Condemnation Order or its
Order of Possession. 1n the absence of such a determination, we
hold the District Court shall determine if any of the conditions
proposed by either party should be inserted in the subsequent Final
Order of Condemnation.
19
Lavoie, 466 P.2d at 599. The case at hand is comparable to Lavoie
in that we have two uses that must be coordinated to achieve the
greatest public benefit and the least private injury. In a similar
manner to Lavoie which considered reasonable access for the
condemnee, we conclude it is reasonable under these circumstances
for the District Court to consider what terms, if any, should be
included in its Final Order of Condemnation.
We affirm the District Court's Preliminary Condemnation Order
and its Order of Possession. On remand the District Court shall
take such action, including the holding of a hearing, which it
finds to be necessary in order to comply with this opinion.
--L+gjiJ&'
John R. Christensen
:,&i/tting for Justice Karla M. Gray
21
Justice James C. Nelson respectfully dissents.
I conclude that under the facts of this case and by reason of
the findings made by the District Court, plaintiff has failed as a
matter of law in its burden of proof under 5 70-30-111, MCA.
Moreover, as a consequence of our straining to interpret the
eminent domain statutes to justify the result, we have also, of
necessity, but improperly, now embroiled the District Court in the
task of writing what is, essentially, a contract for Montana Power
Company and Burlington Northern Railroad.
Among other requirements, 5 70-30-111, MCA, mandates that
before property can be taken by condemnation, the plaintiff must
prove and the trial court must find:
(2) that the taking is necessary to such use; [and]
(3) if already appropriated to some public use, that the
public use to which it is to be applied is a more
necessary public use. . .
As to subsection (2), the record in this case demonstrates
that MPC's taking of BN's property by eminent domain was not
necessary to MPC's location, construction and maintenance of its
powerline. In point of fact, the evidence showed unequivocally
that MPC currently operates and for decades has operated, miles
upon miles of transmission line under well over a thousand wire-
line permits of the very sort at issue here without any of the
drastic consequences that it argues now justifies condemnation. In
that time only one easement was issued by BN to MPC. MPC officials
testified in depositions that MPC could locate, construct, operate,
maintain, replace and remove the Great Falls electric transmission
22
line under a wire-line permit containing the permit fee,
revocation, relocation and indemnification provisions objected to.
In fact, the transmission line was located and constructed on and
over BN's property during the pendency of this litigation.
While MPC maintains that the same wire-line permit provisions
that it has operated under for years are now unacceptable and
onerous, the record clearly demonstrates that it has and does and
would, in this case, locate, construct, operate, maintain, inspect,
replace and remove its transmission line under a wire-line permit
without the necessity of taking BN's property by eminent domain.
In Silver Bow County v. Hafer (1975), 166 Mont. 330, 532 P.2d
691, we held to the long established principle in condemnation
cases that it is an unconstitutional taking to allow the condemnor
to acquire a greater interest or estate in the condemned property
than the public use requires. We stated:
It necessarily follows from the principle that property
cannot constitutionally be taken by eminent domain except
for the public use, that no more property can be taken by
eminent domain than the public use requires, since all
that might be appropriated in excess of the public needs
would not be taken for the public use. While
considerable latitude is allowed in providing for the
anticipated expansion of the requirements of the public,
the rule itself is well established, and applies both to
the amount of property to be acquired for public use and
to the estate or interest acquired in such property. r
an easement will satisfy the public needs, to take the
fee would be unjust to the owner, who is entitled to
retain whatever the public needs do not require. and to
the public, which should not be oblised to pay for more
than it needs. (Empahsis added.)
Silver Bow Countv, 532 P.2d at 693. Necessity contemplates that
which is "reasonably requisite and proper for the accomplishment of
the purpose for which it is sought under the peculiar circumstances
23
of each case." State Highway Com'n v. Crossen-Nissen Co. (1965),
145 Mont. 251, 254, 400 P.2d 283, 284.
As stated above, § 70-30-111, MCA, requires that "[blefore
property can be taken, the plaintiff must show by a preponderance
of the evidence that the public interest requires the taking based
on [a finding] . . that the takins is necessary to such use."
(Emphasis added). In its discussion of this statutory requirement,
the majority misses the point completely. This statutory
requirement does not focus on whether the use (here, the
transmission line) is necessary, but, rather, on whether the taking
(in this case an unrestricted easement versus a wire-line permit)
is necessary to such use. No one, including BN, maintains that it
is not necessary that MPC construct its transmission line. That we
gratuitously conclude that the record supports what everyone has
already conceded does not validate our erroneous application of
this statutory requirement. We have effectively merged the
requirements of subsections (1) and (2) of the statute. Now, if
the condemnor shows that the public use is lawful and that it needs
the property, that ends the inquiry; that the manner of taking
sought may not be required to obtain the use is no longer of
consequence. MPC's burden under subsection (2) of the statute was
to prove that taking by unrestricted easement was necessary to
locate, construct, operate and maintain its transmission line. The
proof was to the contrary: taking by unrestricted easement was not
necessary to such use.
On the record here, it was not "necessary" that MPC take by
24
condemnation an easement on BN's property to accomplish the
location, construction, maintenance and operation of its
transmission line. That could and would have been accomplished, as
it had many, many times in the past under the offered wire-line
permit. In condemning BN's property under such circumstances, MPC
has unconstitutionally acquired a greater interest and estate in
that property than the public use requires.
While it may be more advantageous in a number of ways for MPC
to construct, maintain and operate its transmission line without
any of the restrictions imposed by BN, I find no authority for the
proposition that the condemnation statutes should be used merely to
insure that the condemnor be placed in a more favorable position
than it otherwise could through negotiation or resort to other
legal remedies. While MPC and the majority raise the specter of BN
cancelling one of its wire-line permits after the expenditure of
millions of dollars in construction costs, the record does not
reflect that has actually happened in the lengthy history that MPC
has been locating and maintaining powerlines on BN property, and I
suspect if that had been BN's pattern, MPC would have been in court
decades before this. The courts have no business in this dispute,
and the condemnation statutes have been misused. Accordingly, I
dissent from our decision on Issue I.
With respect to Issue II, the District Court found that MPC's
transmission line is a more necessary use than BN's railroad
operation and that the two uses are compatible. These two findings
are inconsistent with each other under our previous interpretations
25
of subsection (3) of 5 70-30-111, MCA. In Cocanougher v. Zeiegler
(1941), 112 Mont. 76, 112 P.2d 1058, we held that the issue of
whether one public use is "more necessary" than another public use
is not reached unless the proposed use and the pre-existing use
cannot compatibly co-exist on the same property and that the
proposed use would destroy the pre-existing use. Cocanouqher, 112
P.2d at 1060. In Montana Talc Co. v. Cyprus Mines Corp. (1987),
229 Mont. 491, 748 P.2d 444, we defined the inquiry as being
whether the proposed use would defeat or seriously interfere with
the pre-existing use. Montana Talc, 748 P.2d at 452.
On the record here it is clear that not only could MPC's and
BN's public uses co-exist without serious interference on the same
property, but that, historically, such uses have and currently do
so co-exist under the very provisions of the wire-line agreements
to which MPC now objects. Accordingly, under our case law, it was
improper for the District Court to even reach the issue of "more
necessary" use given its finding that the two uses were compatible.
Aside from the District Court's inconsistent findings, the
real problem here, however, is alluded to in the majority's
opinion. While MPC's use and BN's use of BN's property "could be
made compatible," the two uses are not now compatible under the
unrestricted easement granted by the court. Hence, we conclude
that it is necessary to send this matter back to the District Court
to put into the easement at least some of the provisions that have
been historically included in the wire-line permits so that the two
uses will be compatible. That, of course, begs the question: If
26
the two uses were compatible under the provisions included in the
wire-line permits historically utilized by the parties and are not
compatible under the unrestricted easement granted by the court,
thus necessitating at least some of the permit provisions being put
back into the easement, what exactly has the instant condemnation
accomplished? The answer to that question is simple: This
condemnation has allowed MPC to take a greater estate in EN's
property than was necessary to accomplish the use.
Again, our discussion here and under Issue I, demonstrates
that the eminent domain statutes have been misused, and prior case
law has been ignored. Accordingly, I dissent from our decision on
Issue II.
Finally, in Issue III, we come face to face with the
consequences of our decisions on Issues I and II. It is important
to reiterate that for decades MPC has successfully located,
operated and maintained its transmission lines on and over BN
property via the use of wire-line permits. There is really no
dispute that, if it had not successfully condemned BN's property,
MPC could have and would have located, operated and maintained the
transmission line involved in this case under a wire-line permit.
Reduced to its essentials, the problem is that MPC became
dissatisfied with having to live with the various restrictions and
requirements which BN imposed on the granting of its wire-line
permits, but which, nevertheless, were part and parcel of the
parties' compatible and co-existent use of BN's property for
decades. Depending on perspective, the restrictions were either
27
onerous, threatening and unfair or necessary to insure the safe and
effective operation of a high tension powerline on and over a
metal-intensive railroad.
The point to be made is that, without the intervention of the
courts, MPC and BN have successfully dealt with this situation for
years and would just as likely have continued to successfully deal
with this situation in the future if left to their own devices.
Importantly, there was no specific instance of BN wrongfully
revoking one of MPC's wire-line permits or seeking to indemnify its
own negligence at MPC's expense alleged or before the court. Had
that been the case, then MPC no doubt would have had grounds to
pursue other appropriate legal remedies through the courts.
Rather, what brought this case to court was a dispute over the
terms of a proposed contract--a wire-line permit--and speculation
about what BN might do under the contract proposed. Under such
circumstances, the condemnation statutes are not the appropriate
vehicle to resolve that dispute, and if MPC had been held to its
burden of proof under 5 70-30-111(2), MCA, no condemnation order
would have been issued. The parties would have been simply left to
work out the details of their respective operations or to seek
court intervention in the event of some actual problem with some
specific permit or incident.
Now, however, since we have upheld the District Court's
condemnation of BN's property, MPC has the right to occupy that
property without any of the restrictions that are likely necessary
to protect BN's operations and the public safety. Even we
28
recognize that situation is unwise and unworkable. So to remedy
that, we have instructed the trial court to determine and order,
the terms governing the parties relationship--terms that they
should have (and would have) negotiated and written themselves via
contract if left to their own devices. Leaving aside the issue of
the value, technical and business judgments that the District Court
is going to have to make to accomplish that and the question of why
a district court has any particular expertise to determine the
rules and minutiae regulating the location, operation, maintenance,
and replacement of a high tension powerline on and over a busy
railroad, there is a more fundamental legal problem involved.
Quite simply, there is no authority in the condemnation
statutes which would allow the District Court to do what we have
now ordered it to do. At least the District Court recognized that
problem when it concluded that there was "no statutory basis or
requirement that protective conditions be set forth in the said
Order of Possession." Moreover, our reliance on § 70-30-206, MCA,
is misplaced and runs directly counter to our previous
interpretation of the limited authority of the district court under
that statute. In State Highway Commission v. Lavoie (1970), 155
Mont. 33, 466 P.2d 594, we held that while the District Court was
empowered to order the end result--i.e. the crossing itself--it was
not authorized to supervise the minutiae of the design and
construction of the facility. We stated:
However, the district court, in an excess of caution
and concern that proper access be provided, added the
additional requirement that "The plans are subject to
approval by this Court." This the district court was not
29
empowered to do. Details of engineering design and
construction are within the purview of the activities of
the Highway Commission; and, while the district court is
empowered to order a certain end result (as by here
ordering two lane access over the Houle Creek Road), the
court for rather obvious reasons is not qualified nor
staffed to supervise the design or construction of the
facility. Adequate remedies are available both to the
court and to the property owner to ensure compliance with
the court's order.
Lavoie, 466 P.2d at 599. While the majority seeks to distinguish
Lavoie, its distinction is without a meaningful difference.
Moreover, we stated in Lincoln/Lewis & Clark Cty. Sewer v.
Bossing (1985), 215 Mont. 235, 696 P.2d 989, that "[clourts
generally do not have the power to determine what public
improvements shall be constructed, where they shall be located, and
when the power of eminent domain shall be exercised."
Lincoln/Lewis, 696 P.2d at 991. if we have interpreted our eminent
domain statutes as to preclude the courts from those powers, it
follows that courts, similarly, do not have the power to condition
the condemnation order on detailed conditions as to how the parties
are to mutually utilize the condemned property.
Having lost sight of our obligation to drain the swamp, we
have, worse, thrown the trial court into the water with
instructions to subdue the alligators. Accordingly, I also
respectfully dissent from our decision on Issue III.
30