file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
No. 99-158
IN THE SUPREME COURT OF THE STATE OF MONTANA
2000 MT 209
FRIENDS OF THE WILD SWAN, a
nonprofit corporation,
Plaintiff, Respondent, and
Cross-Appellant,
v.
DEPARTMENT OF NATURAL RESOURCES
AND CONSERVATION,
Defendant, Appellant, and
Cross-Respondent.
APPEAL FROM: District Court of the First Judicial District,
In and for the County of Lewis and Clark,
The Honorable Thomas C. Honzel, Judge presiding.
COUNSEL OF RECORD:
For Appellant:
Tom Butler and Michael J. Mortimer, Montana Department of
Natural Resources & Conservation, Helena, Montana
For Respondent:
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (1 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
Stephen C. Pohl, Attorney at Law, Bozeman, Montana
For Amicus:
Rebecca W. Watson, Gough, Shanahan, Johnson & Waterman,
Helena, Montana
Submitted on Briefs: November 4, 1999
Decided: August 8, 2000
Filed:
__________________________________________
Clerk
Justice Terry N. Trieweiler delivered the opinion of the Court.
¶1 The Plaintiff, Friends of the Wild Swan, brought this action in the District Court for the
First Judicial District in Lewis and Clark County to challenge the sufficiency of the
Environmental Impact Statement (EIS) prepared by the Defendant, Montana Department
of Natural Resources and Conservation (DNRC), for the Middle Soup Creek Project
pursuant to the Montana Environmental Policy Act (MEPA) §§ 75-1-201, et seq., MCA.
The District Court held that the EIS prepared by the DNRC inadequately addressed the
cumulative impacts of the project and also held that the DNRC should have prepared a
supplemental EIS due to changed economic circumstances of the project. The District
Court enjoined any harvest of timber on the Middle Soup Creek Project until the DNRC
prepares the supplemental EIS. DNRC appeals from that judgment. Friends of the Wild
Swan cross-appeals from the District Court's denial of Rule 11 sanctions against the
DNRC. We affirm the judgment of the District Court.
¶2 The following issues are presented on appeal by the DNRC:
¶3 1. Did the District Court err when it held that the DNRC violated the MEPA by its
failure to include an adequate cumulative impacts analysis in its EIS?
¶4 2. Did the District Court err when it held that the DNRC was required to prepare a
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (2 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
supplemental EIS?
¶5 3. Did the District Court err when it held that Friends of the Wild Swan was not
required to provide a postappeal injunction bond pursuant to § 77-1-110, MCA?
¶6 The following issue is presented on cross-appeal by Friends of the Wild Swan:
¶7 4. Did the District Court err when it denied Friends of the Wild Swan's motion for
imposition of Rule 11, M.R.Civ.P., sanctions against the DNRC?
FACTUAL BACKGROUND
¶8 This dispute relates to the DNRC's proposed timber sale, known as the Middle Soup
Creek Project, on land near Swan Lake, Montana. The land is owned by the State of
Montana and held in trust by the DNRC for the support of the public schools pursuant to
Article X of the Montana Constitution. The purpose of the project is to generate both short-
and long-term revenue for the Montana School Trust. The project, as originally proposed,
involved the harvest of approximately 6 million board feet of timber on 2591 acres of
Swan Valley forest. Approximately 50 percent of the Swan Valley forest consists of old
growth, including one of the last large stands of old growth remaining in Montana.
¶9 In September 1996, the DNRC issued a draft EIS which discussed the impacts of four
alternative management plans for the Middle Soup Creek Project. Alternative "A" required
no action and would have left the Middle Soup Creek area unmanaged and permitted the
DNRC to enter into a 20-year conservation lease. Alternative "B" required intensive
management and was designed to promote sustainability of the ecosystem by harvesting
approximately 5.2 million board feet of timber. Alternative "C" required preservation of
old growth timber, while permitting the harvest of approximately 150,000 board feet of
saw-timber stand. Alternative "D" maximized timber productivity by harvesting
approximately 5.6 million board feet of old growth, saw-timber, and multistoried stands.
¶10 Following public hearings and comments, the DNRC issued the final Middle Soup
Creek Project EIS in February 1997. Alternative "B" was identified as the preferred
alternative because of its economic viability and its positive short- and long-term benefits
in accordance with the State Forest Land Management Plan philosophy and its Resource
Management Standards. Alternative "B" was projected to generate approximately
$1,045,572 in net revenue in the short-term, and was to be accomplished by using a
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (3 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
harvesting process known as "structural enhancement," in which selected trees would be
cut in order to mimic historical forest conditions.
¶11 In July 1997, the Board of Land Commissioners approved the Middle Soup Creek
timber sale. The minutes of the board's meeting reflect their approval of a harvest of
approximately 3.8 million board feet from 970 acres of the Swan Valley forest. There was
no explanation for reduction of the sale from 5.2 million board feet as proposed in the
final EIS to 3.8 million board feet as approved by the board.
¶12 On September 4, 1997, Friends of the Wild Swan, a Montana nonprofit corporation
dedicated to preserving the natural environment of the Swan Valley, filed a complaint
alleging various violations of the MEPA by the DNRC in its final EIS, including
inadequate environmental analysis. Friends of the Wild Swan sought an order directing the
DNRC to complete an EIS in accordance with the MEPA and an injunction prohibiting the
DNRC from proceeding with any activity in furtherance of the Middle Soup Creek Project
until a proper EIS was prepared.
¶13 On September 10, 1997, the DNRC entered into a contract with Plum Creek
Manufacturing Company for the harvest of 3.8 million board feet of timber on the Middle
Soup Creek Project. Pursuant to the contract, the DNRC staff marked the trees to be
harvested by Plum Creek with orange paint.
¶14 Following the DNRC's selection of trees to be harvested, Friends of the Wild Swan
requested Sara Johnson, Ph.D., a wildlife biologist, to review the site of the sale, the
selection of trees by the DNRC, and the final EIS. Johnson concluded that the selection of
trees by the DNRC was more extensive than described by the final EIS, and that the final
EIS was misleading to the public regarding the amount of old growth timber to be
harvested.
¶15 On January 5, 1998, Friends of the Wild Swan and the DNRC stipulated that no
timber would be harvested on the Middle Soup Creek Project until December 1, 1998. As
a result of the parties' stipulation, Friends of the Wild Swan withdrew its pending motion
for a preliminary injunction.
¶16 On March 16, 1998, the DNRC sent a letter to all interested parties and acknowledged
that it had made a mistake when it identified the trees to be harvested by Plum Creek. The
DNRC explained that proper identification of the trees would result in a harvest of fewer
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (4 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
and smaller trees, which in turn would reduce the volume of timber harvested from 3.8
million board feet to 1.99 million board feet. Because of the reduction in volume and tree
size, the DNRC and Plum Creek negotiated a reduced price per thousand board feet of
timber harvested.
¶17 On October 6, 1998, Friends of the Wild Swan filed its Second Amended Complaint
which added the alleged MEPA violation of failure to prepare a supplemental EIS in light
of the changed economic circumstances of the sale.
¶18 On October 15 and 16, 1998, the District Court held a hearing to consider the merits
of Friends of the Wild Swan's complaint.
¶19 The parties' stipulation that no harvest would occur expired on December 1, 1998.
Friends of the Wild Swan received a letter from the DNRC dated November 27, 1998,
which informed them that "Plum Creek timber Company is preparing to begin harvesting
operations on December 1 or as soon after that date when the desired environmental
conditions are achieved." The letter further informed them that the "sale contract allows
logging activities to begin on December 1, 1998, if there is at least 18 inches of snow
accumulation and freezing temperatures. Logging activities may begin on December 15 if
there is at least 24 inches of snow accumulation, even though temperatures may not be
freezing." Friends of the Wild Swan recognized that these environmental conditions were
also set forth in the EIS as required mitigators for reducing impact upon the soil.
¶20 In an affidavit dated January 14, 1999, Arlene Montgomery, Director of Friends of the
Wild Swan, stated that she personally made visits to the Middle Soup Creek Project area
on November 28 and December 18, 1998, and on both occasions it was raining and
muddy, there was no measurable snow accumulation on the ground, nor was the ground
frozen.
¶21 On December 23, 1998, the District Court issued its findings of fact, conclusions of
law, and order in which the District Court held that the DNRC was required to include a
cumulative impacts analysis in the EIS and a supplemental EIS as a result of the change in
economic circumstances. The order enjoined the DNRC from proceeding with further
activities relating to the Middle Soup Creek Project until the supplemental EIS and the
cumulative impacts analysis have been prepared.
¶22 On December 29, 1998, the DNRC filed a motion and brief requesting the District
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (5 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
Court to modify the injunction issued in its December 23, 1998 order. In its motion, the
DNRC admitted that it had allowed Plum Creek to commence harvesting timber on the
Middle Soup Creek Project on December 15, 1998, and then ordered Plum Creek to cease
activities upon receipt of the District Court's order on December 23, 1998. As a result, the
DNRC requested the District Court to modify its injunction to allow the DNRC and Plum
Creek to remove any timber that was felled prior to December 23, 1998. Additionally, the
DNRC requested that the District Court require Friends of the Wild Swan to post an
injunction bond pursuant to § 77-1-110, MCA, to compensate the school trust
beneficiaries should the injunction be wrongful.
¶23 On January 11, 1999, the DNRC sent a letter to Arlene Montgomery, Director of
Friends of the Wild Swan, which detailed the timber harvesting that occurred prior to
December 23, 1998 on the Middle Soup Creek Project. The DNRC explained that 90,000
board feet of timber was cut by Plum Creek during that time and that the harvesting was
done pursuant to a timber sale inspection report in which the DNRC "gave approval for
the felling of timber in Unit #1 to proceed, but due to unfrozen wet soils . . . did not allow
skidding activities to proceed."
¶24 On January 21, 1999, Friends of the Wild Swan sought Rule 11, M.R.Civ.P. sanctions
against the DNRC for its motion to modify the injunction and request for Friends of the
Wild Swan to post an injunction bond.
¶25 On February 26, 1999, the District Court issued its memorandum and order denying
the DNRC's motion for modification of the injunction and request for an injunction bond
and denying Friends of the Wild Swan's motion for Rule 11 sanctions.
¶26 The DNRC filed its notice of appeal on March 2, 1999, and Friends of the Wild Swan
filed its notice of cross-appeal on March 16, 1999.
STANDARD OF REVIEW
¶27 The proper standard of review of an administrative decision pursuant to the Montana
Environmental Policy Act (MEPA), is whether the record establishes that the agency acted
arbitrarily, capriciously or unlawfully. North Fork Preservation Ass'n v. Department of
State Lands (1989), 238 Mont. 451, 465, 778 P.2d 862, 871. In North Fork Preservation
Ass'n, we stated that:
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (6 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
[I]n making the factual inquiry concerning whether an agency decision was
"arbitrary or capricious," the reviewing court "must consider whether the decision
was based on a consideration of the relevant factors and whether there has been a
clear error of judgment." This inquiry must "be searching and careful," but "the
ultimate standard of review is a narrow one."
North Fork Preservation Ass'n, 238 Mont. at 465, 778 P.2d at 871 (quoting Marsh v. Oregon
Natural Resources Council (1989), 490 U.S. 360, 378).
¶28 In Marsh, the U.S. Supreme Court stated:
[I]n the context of reviewing a decision not to supplement an EIS, courts should not
automatically defer to the agency's express reliance on an interest in finality without
carefully reviewing the record and satisfying themselves that the agency has made a
reasoned decision based on its evaluation of the significance-or lack of significance-
of the new information. A contrary approach would not simply render judicial
review generally meaningless, but would be contrary to the demand that courts
ensure that agency decisions are founded on a reasoned evaluation "of the relevant
factors."
Marsh, 490 U.S. at 378.
¶29 In North Fork Preservation Ass'n, 238 Mont. at 460, 778 P.2d at 868, we stated that
the omission of the cumulative impacts analysis was directly relevant to the "unlawful"
portion of our standard of review.
DISCUSSION
ISSUE 1
¶30 Did the District Court err when it held that the DNRC violated the MEPA as a result
of its failure to include an adequate cumulative impacts analysis in its EIS?
¶31 The DNRC asserts that the District Court erred when it found that the EIS prepared by
the DNRC for the Middle Soup Creek Project was insufficient because it did not
adequately analyze and discuss the cumulative impacts of the project. The DNRC
contends that the District Court failed to comprehend that the new "coarse filter"
ecological analysis takes into account all of the prevailing conditions of the affected lands
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (7 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
and therefore incorporates a cumulative effects analysis. The DNRC argues that the
District Court's primary error was its "disregard for the evidence presented that each of the
court's concerns had in fact been considered in the preparation of the final EIS, and that
the cumulative impacts of all the past and present actions were carefully considered."
¶32 In response, Friends of the Wild Swan contends that even if the DRNC's new "coarse
filter" approach is recognized as valid and includes cumulative impacts analysis as part of
its methodology, the MEPA still requires a cumulative impacts analysis in every EIS and
therefore the DNRC is required to include the requisite discussion in its EIS.
¶33 The Administrative Rules of Montana provide in relevant part as follows:
36.2.529 Preparation and Contents of Draft Environmental Impact Statements
If required by these rules, the agency shall prepare a draft environmental impact statement
using an interdisciplinary approach and containing the following:
....
(4) a description of the impacts on the quality of the human environment of the
proposed action including:
....
(b) primary, secondary, and cumulative impacts;
36.2.522 Definitions
....
(7) "Cumulative impact" means the collective impacts on the human environment of the
proposed action when considered in conjunction with other past and present actions related
to the proposed action by location or generic type. Related future actions must also be
considered when these actions are under concurrent consideration by any state agency
through pre-impact statement studies, separate impact statement evaluation, or permit
processing procedures.
....
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (8 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
(12) "Human environment" includes, but is not limited to biological, physical,
social, economic, cultural, and aesthetic factors that interrelate to form the
environment. As the term applies to the agency's determination of whether an EIS is
necessary, economic and social impacts do not by themselves require an EIS.
However, whenever an EIS is prepared, economic and social impacts and their
relationship to biological, physical, cultural and aesthetic impacts must be discussed.
¶34 The District Court found that:
The purpose of allowing public involvement in environmental decision-making is
frustrated if an EIS does not accurately describe the impact of proposed action in the
context of past, present and future proposed action. The average member of the
public must rely on DNRC's expertise, and therefore, DNRC must give sufficient
information so that the public can make a meaningful evaluation of the proposed
action. To do so, a thorough analysis and discussion of cumulative impacts is
necessary. The legislature recognized as much, making a cumulative impacts
analysis mandatory. A thorough analysis of cumulative impacts is lacking here.
¶35 The DNRC argues that the District Court's findings were erroneous because, although
Rule 36.2.529, ARM, requires a cumulative effects analysis, the Administrative Rules do
not dictate any particular methodology. However, we conclude that Rule 36.2.529(4)(b),
ARM, clearly states that the EIS shall contain a description of the cumulative effects and
does not allow, as the DRNC suggests, mere analysis implicit within the EIS. The public is
not benefited by reviewing an EIS which does not explicitly set forth the actual cumulative
impacts analysis and the facts which form the basis for the analysis.
¶36 The DNRC additionally argues that the District Court erred when it relied on Rule
36.2.524(1)(g), ARM, to conclude that the DNRC's cumulative impacts analysis was also
inadequate for its failure to reconcile the proposed action with the State Forest Land
Management Plan (SFLMP). The DNRC states that Rule 36.2.524, ARM, "applies only to
the analysis performed in attempting to ascertain whether an EIS should be prepared. . . .
This section is not a substantive element to be contained within an EIS."
¶37 Rule 36.2.524, ARM, states, in relevant part:
(1) In order to implement 75-1-201, MCA, the agency shall determine the
significance of impacts associated with a proposed action. This determination is the
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (9 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
basis of the agency's decision concerning the need to prepare an EIS and also refers
to the agency's evaluation of individual and cumulative impacts in either EAs or
EISs. The agency shall consider the following criteria in determining the
significance of each impact on the quality of the human environment:
....
(g) potential conflict with local, state, or federal laws, requirements, or formal plans;
(Emphasis added.) Clearly, Rule 36.2.524, ARM, pertains to the contents of an EIS, in
addition to the decision of whether or not to prepare an EIS.
¶38 The DNRC further contends that the EIS did discuss the SFLMP. We note that the
District Court did recognize discussion of the SFLMP, stating that: "Although the Middle
Soup Creek final EIS does discuss old growth and fragmentation, listing them as
'concerns,' it does not discuss the SFLMP's objective to preserve old growth, reduce
fragmentation, and protect unique habitat." The District Court was correct.
¶39 Accordingly, we conclude that the EIS prepared by the DNRC fails to comport with
the provision in Rule 36.2.529(4)(b), ARM, which requires an explicit discussion of the
cumulative impacts analysis, in accordance with the definitions of "cumulative impact"
and "human environment" set forth at Rule 36.2.522, ARM, or with the provision provided
by Rule 36.2.524(1)(g), ARM. As a result, we conclude that the DNRC acted unlawfully,
in violation of the MEPA, in its preparation of the EIS for the Middle Soup Creek Project.
Therefore, we further conclude that the District Court did not err when it held that the
DNRC violated the MEPA as a result of its failure to include an adequate cumulative
impacts analysis in its EIS.
ISSUE 2
¶40 Did the District Court err when it held that the DNRC was required to prepare a
supplemental EIS?
¶41 The DNRC contends that the District Court erred by concluding that a supplemental
EIS is required, because there was no proof offered by Friends of the Wild Swan that a
reduction in the total timber sale revenue would result in any physical impact to the human
environment. The DNRC argues based on Rule 36.2.522(12), ARM, that a change in
economic impacts alone does not compel the preparation of a supplemental EIS. The
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (10 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
DNRC further asserts that it acted reasonably in preparing its economic estimate and did
not portray the economic returns in the EIS as reliable estimates of absolute, guaranteed
revenues.
¶42 In response, Friends of the Wild Swan asserts that the DNRC's failure to supplement
the EIS was arbitrary and capricious in light of the substantial changes in the proposed
action. Friends of the Wild Swan points out that the final EIS described a sale of nearly 6
million board feet of timber, estimated to net over a million dollars in revenue for the
school trust. Whereas, the sale as now proposed describes a sale of 1.99 million board feet
of timber, which is estimated to result in a loss to the State.
¶43 The final EIS identifies Alternative "B" as the preferred alternative and sets forth an
estimated sale of 5.2 million board feet of timber. The final EIS further states that
Alternative "B" is projected to generate approximately $1,045,572 of net revenue in the
short-term. The final EIS states that:
The objective of the Middle Soup Creek Project is to generate the largest,
reasonable monetary return to the school trust in both the short term and long term
by either selling approximately six million board feet of timber or selling a twenty-
year conservation lease. Alternatives A and C are each projected to generate
negative net revenue if harvested this year or if harvesting is deferred for twenty
years. These alternatives do not meet the project objective and therefore are not
considered further.
¶44 It appears that by the time of the meeting of the Board of Land Commissioners on
July 21, 1997, the DNRC had re-estimated the Middle Soup Creek Timber Sale to include
the sale of 3.8 million board feet of timber and $812,605 in revenue. In April 1998,
following the discovery of the mismarked trees in the Middle Soup Creek Project, the
DNRC notified Friends of the Wild Swan that the project would be further reduced to 1.99
million board feet of timber and $350,000 in revenue. However, the costs to the State of
the Middle Soup Creek Project, including the MEPA costs, sale preparation costs,
administrative costs and treatment costs has reached approximately $500,000.
Accordingly, the DNRC's proposed sale of 1.99 million board feet results in a loss of
approximately $150,000 to the State.
¶45 Rule 36.2.533, ARM, provides in relevant part as follows:
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (11 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
(1) The agency shall prepare supplements to either draft or final environmental impact
statements whenever:
(a) the agency or the applicant makes a substantial change in a proposed action;
....
(2) A supplement must include, but is not limited to, a description of the following:
....
(c) any impacts, alternatives or other items required by ARM 36.2.529 for a draft
EIS or ARM 36.2.531 for a final EIS that were either not covered in the original
statement or that must be revised based on new information or circumstances
concerning the proposed action.
¶46 We conclude that, contrary to the DNRC's assertions, there is no requirement in Rule
36.2.533, ARM, that a substantial change must result in an additional impact to the
environment before a supplemental EIS is required. There is no limitation on what may be
considered a "substantial change". Accordingly, we further conclude that a substantial
economic change in a project can serve as the basis for the supplemental EIS required by
Rule 36.2.533, ARM.
¶47 In this case, the District Court found that:
The substantial change in the harvest quantity and in the net revenue resulting from
the harvest certainly are "substantial changes" to the proposed action. Indeed, the
motivation for the sale, producing net revenue for the trust, has been completely
removed. The sale now will cost the State money. The public and the Board of Land
Commissioners may have been willing to lose valuable old growth timber for the
benefit of substantial revenue to the trust, but the cost benefit had now been
substantially changed. The public may not be willing, and the Board of Land
Commissioners may not wish to require the public to pay to lose its old growth
timber.
¶48 We conclude that the change in economic circumstances in the Middle Soup Creek
Project was a "substantial change" pursuant to Rule 36.2.533, ARM, which required the
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (12 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
preparation of a supplemental EIS. Accordingly, we conclude that the DNRC's decision
not to supplement the EIS was a clear error of judgment. Therefore, we further conclude
that the District Court did not err when it held that the DNRC was required to prepare a
supplemental EIS.
ISSUE 3
¶49 Did the District Court err when it held that Friends of the Wild Swan was not required
to post a postappeal injunction bond pursuant to § 77-1-110, MCA?
¶50 The DNRC contends that § 77-1-110, MCA, required the District Court to order
Friends of the Wild Swan to post an injunction bond during the pendency of this appeal.
¶51 Section 77-1-110, MCA, provides:
In any civil action seeking an injunction or restraining order concerning a decision
of the board approving a use or disposition of state lands that would produce
revenue for any state lands trust beneficiary, the court shall require a written
undertaking for the payment of damages that may be incurred by the trust
beneficiary if the board is wrongfully enjoined or restrained.
¶52 The District Court concluded that because the Middle Soup sale was expected to lose
money, it would be difficult to comprehend how damages might be incurred as a result of
enjoining the project and, therefore, concluded that Friends of the Wild Swan was not
required to post a bond.
¶53 On appeal, Friends of the Wild Swan contends that the DNRC has no standing to
invoke § 77-1-110, MCA, because that statute only pertains to actions enjoining a decision
of the State Land Board. Friends of the Wild Swan argues that, here, no injunction has
been issued against the Land Board, nor is the Land Board even a party to this action.
¶54 Section 77-1-110, MCA, provides for a bond in a civil action "seeking an injunction
or restraining order concerning a decision of the board" for damages "that may be
incurred by the trust beneficiary if the board is wrongfully enjoined or
restrained." (Emphasis added.) This statute does not apply to this case which deals with an
injunction against the DRNC based on the inadequacy of its EIS and has no effect on the
Land Board's decision.
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (13 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
¶55 Therefore, we conclude that the District Court came to the right conclusion, whether
or not it was for the right reason and that Friends of the Wild Swan was not required to
post an injunction bond pursuant to § 77-1-110, MCA.
ISSUE 4
¶56 The following issue is presented on cross-appeal by Friends of the Wild Swan:
¶57 Did the District Court err when it denied Friends of the Wild Swan's motion for
imposition of Rule 11, M.R.Civ.P., sanctions against the DNRC?
¶58 This Court gives a district court broad discretion to determine whether the factual
circumstances of a particular case amount to frivolous or abusive litigation tactics.
Accordingly, we apply the following standard of review:
A district court's findings of fact will be overturned if clearly erroneous. The court's
legal conclusion that the facts constitute a violation of Rule 11 will be reversed if
the determination constitutes an abuse of discretion. We will review the case de
novo only if the violation is based on the legal sufficiency of a plea or motion.
D'Agostino v. Swanson (1990), 240 Mont. 435, 446, 784 P.2d 919, 926.
¶59 Friends of the Wild Swan contends that Rule 11, M.R.Civ.P. clearly applies to the
circumstances underlying the DNRC's request for an injunction bond pursuant to § 77-1-
110, MCA, and request for modification of the District Court's injunction. Friends of the
Wild Swan asserts that the DNRC's request of the District Court to allow it to sell the
"illegally harvested timber" and to require an injunction bond, was made solely to harass
and cause needless increase in the costs of this litigation.
¶60 Rule 11, M.R.Civ.P., provides:
The signature of an attorney or party constitutes a certificate by the signer that the
signer had read the pleading, motion, or other paper; that to the best of the signer's
knowledge, information, and belief formed after reasonable inquiry it is well
grounded in fact and is warranted by existing law or a good faith argument for the
extension, modification, or reversal of existing law, and that it is not interposed for
any improper purpose, such as to harass or to cause unnecessary delay or increase in
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (14 of 15)3/29/2007 10:47:16 AM
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm
the cost of litigation . . . . If a pleading, motion, or other paper is signed in violation
of this rule, the court, upon motion or upon its own initiative, shall impose upon the
person who signed it, a represented party, or both, an appropriate sanction . . . .
¶61 The District Court found the following:
The fact that DNRC may have violated the mitigation controls prescribed in the EIS
does not implicate Rule 11. If DNRC acted in bad faith or violated the EIS, there are
specific statutory remedies, but Rule 11 sanctions is not one of those remedies. Nor
does Rule 11 constitute grounds to impose sanctions merely because DNRC sought
to have a bond posted. Section 77-1-110, MCA, is a fairly new provision, having
been enacted in 1995. The Court cannot say DNRC acted in bad faith by seeking to
have a bond posted. Therefore, the Court declines to impose Rule 11 sanctions
against DNRC.
¶62 We conclude that the District Court's findings that the DNRC did not act in bad faith
are not clearly erroneous, and that the District Court did not abuse its discretion.
Therefore, we affirm the District Court's denial of Rule 11, M.R.Civ.P. sanctions against
the DNRC.
¶63 The judgment of the District Court is affirmed.
/S/ TERRY N. TRIEWEILER
We Concur:
/S/ KARLA M. GRAY
/S/ JIM REGNIER
/S/ JAMES C. NELSON
/S/ W. WILLIAM LEAPHART
file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/99-158%20Opinion.htm (15 of 15)3/29/2007 10:47:16 AM