[Cite as State ex rel. Betton v. Burgess & Niple, Inc., 2023-Ohio-740.]
IN THE COURT OF APPEALS OF OHIO
SIXTH APPELLATE DISTRICT
ERIE COUNTY
State of Ohio, ex rel. Timothy Betton Court of Appeals No. E-22-001
E-22-002
Appellant/Cross-appellee
Trial Court No. 2016-CV-0593
Erie Co. Board of Commissioners
Intervenor/Appellant-
Cross-appellee
v.
Burgess & Niple, Inc., et al.
Defendant
DECISION AND JUDGMENT
Speer Bros., Inc.
Appellee/Cross-appellant Decided: March 10, 2023
*****
Dennis E. Murray, Sr., Charles M. Murray, and Donna J.
Evans, for appellant/cross-appellee.
Kevin J. Baxter, Erie County Prosecuting Attorney, and
Gerhard K. Gross, Assistant Prosecuting Attorney, for
Intervenor/appellant-cross-appellee.
Matthew A. Dooley, Ryan M. Gembala, Stephen M. Bosak, Jr.,
And Michael R. Briach, for appellee/cross-appellant.
*****
OSOWIK, J.
{¶ 1} This is a consolidated appeal and cross-appeal from five judgments by the
Erie County Common Pleas Court. For the reasons set forth below, this court affirms, in
part, and reverses, in part, the judgments of the trial court.
I. Background
{¶ 2} This matter is a refiled1 and supplemented2 R.C. 309.13 taxpayer complaint
by plaintiff-appellant/cross-appellee Timothy Betton (“Betton”) against defendant-
nonappellant Burgess & Niple, Inc. (“Burgess”) and defendant-appellee/cross-appellant
Speer Bros., Inc. (“Speer”) alleging breaches of four contracts3 with the intervening
plaintiff-appellant/cross-appellee Erie County Board of Commissioners (“Erie”). Betton
alleged Speer failed to adhere to the contracts’ specific requirements for improvements to
existing waterlines, referred to as “District A,” and the design and construction of new
waterlines, referred to as “District B,” which was completed in August 2004. Betton
further alleged that due to the contract breaches by Burgess, as the waterlines’ project
1
Betton originally filed his taxpayer complaint against Burgess and Speer on February 1,
2016, and assigned case No. 2016-CV-0082. On August 22, 2016, the trial court granted
the defendants’ Civ.R. 12(B)(6) motions to dismiss Betton’s complaint for lack of R.C.
309.13 standing. Betton then refiled his taxpayer complaint on September 7, 2016, and
assigned case No. 2016-CV-0593.
2
Betton sought, and the trial court granted him, leave to supplement his taxpayer
complaint with 11 additional instances of District B waterline failures, which he filed on
May 15, 2017.
3
The four contracts between Speer and Erie are dated September 20, 2001, March 24,
2002, November 25, 2002, and July 3, 2003.
2.
designer and construction supervisor, and by Speer, as the waterlines’ installer, the
waterlines are defective, and Erie will incur damages for repairs and to its credit rating.
{¶ 3} On July 7, 2017, Speer counterclaimed Betton for specific performance
under the contracts and for declaratory judgment under the dispute resolution provisions
of the contracts.
{¶ 4} Previously, on January 29, 2016, Erie declined Betton’s request to initiate a
civil action pursuant to R.C. 309.12 after, “our office examined and researched the
specific issues [you raised,] reviewed the applicable public records and met multiple
times with the Erie County Sanitary Engineer Jack Meyers. Based on the information
before us, [we] will not institute a civil action for breach of contracts related to the
installation of water pipelines in Erie County in 2001.” Later, Erie explained it did so
“solely due to practical reasons, such as staffing and finances.” Nevertheless, by October
18, 2017, Erie, self-styled as “Intervenor for a Limited Purpose,” received leave from the
trial court to file its complaint in intervention. Erie’s complaint, as subsequently
amended, described the limited purpose intervention as follows: “participating in pre-trial
and trial matters, addressing damages and resolution of the claims, [assisting Betton] in
gathering information necessary to establish damages, and in attempting a resolution of
the Breach of Contract claims pled by Betton in the Taxpayer Complaint” for an award of
damages. Erie’s complaint focused on Betton’s allegations regarding the ongoing repairs
to Speer’s defectively-installed District B waterlines.
3.
{¶ 5} On May 14, 2018, Speer counterclaimed Erie for breach of contract and for
declaratory judgment.
{¶ 6} The litigation continued, and the parties engaged in discovery. Eventually,
Betton and Erie dismissed, with prejudice, Burgess,4 and our review of the record will be
limited to Betton, Erie and Speer.
{¶ 7} Speer repeatedly sought dismissal of Betton and Erie’s complaints, which
they opposed. Speer initially filed a Civ.R. 12(B)(6) motion to dismiss Betton’s
complaint on November 8, 2016. Among the grounds sought for dismissal, Speer argued
that Betton lacked standing to bring a taxpayer suit under R.C. 309.13 because the
complaint differed from the claims Betton presented to Erie in order to receive the
January 29, 2016 letter from the Erie County prosecutor declining to file a civil action.
The trial court denied the motion on June 12, 2017.
{¶ 8} Then Speer filed a Civ.R. 12(B)(1) motion to dismiss Betton’s complaint on
May 21, 2018, again alleging Betton’s lack of standing. However, Speer now argued that
since Erie fully intervened to assert Betton’s claims against Speer, Erie is the real party in
interest, and Betton lost his R.C. 309.13 standing to assert the identical claims against
Speer. Betton and Erie opposed Speer’s motion and acknowledged that Erie is the real
party in interest.
4
The Partially Stipulated Dismissal was filed on January 18, 2022. Burgess is not a party
in this appeal.
4.
{¶ 9} While Speer’s motion to dismiss was pending, Speer then filed a Civ.R. 56
motion for summary judgment on September 16, 2019. Speer argued that Betton’s
allegations of contract breaches for improvements completed in 2004 were barred by the
R.C. 2305.131 statute of repose under the authority of New Riegel Local School Dist. Bd.
of Education v. Buehrer Group Architecture & Eng., Inc., 157 Ohio St.3d 164, 2019-
Ohio-2851, 133 N.E.3d 482. Betton and Erie opposed the motion. The trial court denied
the motion on October 28, 2019, as amended on May 20, 2020.5 The litigation continued.
{¶ 10} On August 31, 2021, Speer filed a “renewed motion to dismiss” Betton’s
complaint pursuant to Civ.R. 12(B)(1). Speer argued that Betton lacked standing, and,
consequently, the trial court lacked subject-matter jurisdiction, because deposition
testimony indicated Betton was not a ratepayer of District B and lacked any personal
stake in District B distinct from the general public. Betton opposed the motion. On
October 14, 2021, the trial court converted the Civ.R. 12(B) motion to a Civ. R. 56
motion for summary judgment and provided the parties opportunities to file additional
evidence, which they did. On November 12, 2021, the trial court granted partial
summary judgment against Betton, explaining:
Plaintiff Betton has failed to provide any evidence that he qualifies
as a taxpayer pursuant to its definition as contemplated in R.C. [309.13] or
5
The trial court’s amended judgment entry was in response to this court’s remand for the
lack of a final, appealable order. State ex rel. Betton v. Burgess & Niple, Inc., 6th Dist.
Erie No. E-19-064 (May 4, 2020). We determined that had the trial court found Betton’s
claims did not met the requirements of R.C. 2305.131, and that R.C. 2305.06 applied, the
order would not be final and appealable.
5.
R.C. 733.59. The operating funds for the relevant water district services are
collected from rates paid by customers, and not by the taxpayers of Erie
County. The court finds no authority to allow Betton to continue his
taxpayer action as a ratepayer under the facts at hand. Because Betton is not
a taxpayer bringing an action on behalf of the public, he lacks standing to
bring such a case, and the court can no longer continue this action. * * *
Plaintiff Board of Erie County Commissioners’ claims remain pending, and
trial will proceed as previously scheduled. Partial judgment.
{¶ 11} On December 14, 2021, Betton moved for reconsideration of the trial
court’s November 12 decision, and the trial court denied the motion on December 23.
{¶ 12} Meanwhile, on November 16, 2021, Speer filed a Civ.R. 12(B)(1) motion
to dismiss Erie’s complaint arguing that Erie’s limited intervention was to support
Betton’s claims, and since Betton lacked standing, Erie also lacks standing. Erie opposed
the motion, and on January 5, 2022, the trial court granted Speer’s motion.
{¶ 13} Betton appealed the November 12 and December 23, 2021, judgment
entries, which was assigned case No. E-22-001. Erie appealed the January 5, 2022
judgment entry, which was assigned case No. E-22-002. After this court consolidated
both appeals on January 26, 2022, Betton and Erie jointly set forth two assignments of
error:
1. The trial court erred when it granted Summary Judgment in favor
of Appellee, Speer Bros., Inc., and denied Appellant Betton’s Motion for
6.
Reconsideration, after deciding that Timothy Betton did not meet the
statutory definition of a “taxpayer” as contemplated in R.C. 309.13 and
therefore did not have standing to bring this action.
2. The trial court erred when it granted Appellee, Speer Bros., Inc’s
Civil Rule 12(B)(1) Motion to Dismiss Intervening Plaintiff-Appellant, Erie
County Board of Commissioners’ complaint for lack of standing.
{¶ 14} Speer timely filed a cross-appeal of the June 12, 2017, and October 28,
2019, as amended, judgment entries and set forth one assignment of error: “The trial
court erred by failing to apply Ohio’s statute of repose, R.C. 2305.131, to Betton’s
contract claims, and denying Speer Bros., Inc.’s Motion for Summary Judgment.”
II. Standard of Review
{¶ 15} We will first address Speer’s cross-appeal as it is dispositive to this appeal.
Speer’s cross-appeal challenges the trial court’s decision denying summary judgment,
which we review de novo. Ratonel v. Roetzel & Andress, L.P.A., 147 Ohio St.3d 485,
2016-Ohio-8013, 67 N.E.3d 775, ¶ 18.
{¶ 16} Pursuant to Civ.R. 56(C), summary judgment may be granted under the
following three-part test: (1) no genuine issue as to any material fact remains to be
litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it
appears from the evidence that reasonable minds can come to but one conclusion, and
viewing such evidence most strongly in favor of the non-moving party, that conclusion is
adverse to that party. Id. Summary judgment isolates and disposes of factually
7.
unsupported claims or defenses. Dresher v. Burt, 75 Ohio St.3d 280, 288, 662 N.E.2d
264 (1996). “The main purpose of the summary judgment statute is to enable a party to
go behind allegations in the pleadings and assess the proof in order to see whether there is
a genuine need for trial.” Cunningham v. J. A. Myers Co., 176 Ohio St. 410, 413, 200
N.E.2d 305 (1964) (evaluating former R.C. 2311.041(D), now Civ.R. 56).
{¶ 17} “A ‘material’ fact is one which would affect the outcome of the suit under
the applicable substantive law.” Mike McGarry & Sons, Inc. v. Construction Resources
One, LLC, 2018-Ohio-528, 107 N.E.3d 91, ¶ 57 (6th Dist.). “Whether a genuine issue
exists is answered by the following inquiry: Does the evidence present ‘a sufficient
disagreement to require submission to a jury’ or is it ‘so one-sided that one party must
prevail as a matter of law[?]’” Turner v. Turner, 67 Ohio St.3d 337, 340, 617 N.E.2d
1123 (1993), quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 251-52, 91 L.Ed.2d
202, 106 S.Ct. 2505 (1986).
{¶ 18} After the moving party demonstrates the absence of a genuine issue of
material fact, the burden shifts to the nonmoving party to “produce evidence as to any
issue for which that party bears the burden of production at trial.” Dejaiffe v. KeyBank
USA Natl. Assn., 6th Dist. Lucas No. L-05-1191, 2006-Ohio-2919, ¶ 15.
{¶ 19} To withstand summary judgment under Civ.R. 56(E), the non-moving party
must do more than speculate or offer unsupported conclusory assertions. Deutsche Bank
Natl. Tr. Co. v. Boreman, 6th Dist. Ottawa No. OT-18-031, 2020-Ohio-3545, ¶ 45. Thus,
we may make reasonable inferences from supported facts, but we may not make
8.
inferences from another inference, leading to speculation as to what the facts are. Hurt v.
Charles J. Rogers Transp. Co., 164 Ohio St. 329, 130 N.E.2d 820 (1955), paragraphs one
and two of the syllabus. Where there are claims and defenses having no factual basis,
summary judgment allows a trial court to resolve them prior to trial. Pettiford v.
Aggarwal, 126 Ohio St.3d 413, 2010-Ohio-3237, 934 N.E.2d 913, ¶ 21, citing Byrd v.
Smith, 110 Ohio St.3d 24, 2006-Ohio-3455, 850 N.E.2d 47, ¶ 11 and Celotex Corp. v.
Catrett, 477 U.S. 317, 327, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).
III. R.C. 2305.131 Statute of Repose
{¶ 20} In support of its cross-assignment of error, Speer argues the trial court erred
when it failed to grant summary judgment by disregarding the 10-year construction
statute of repose, R.C. 2305.131, in favor of the 15-year statute of limitations, R.C.
2305.06, for written contracts. Speer argues the New Riegel decision clearly signaled that
Betton’s construction-oriented breach of contract claims, as supported by Erie, were
barred by the statute of repose. We agree and find that, upon de novo review, even if
Betton and Erie in this litigation had standing in which to confer subject-matter
jurisdiction with the trial court, their breach of contract claims were barred by R.C.
2305.131.
{¶ 21} The trial court’s amended journal entry is brief:
On October 28, 2019 Erie County Common Pleas Court denied the
parties’ respective motions for summary judgment. On November 26, 2019
Burgess and Speer filed separate notices of appeal from the October 28,
9.
2019 trial court decision. On May 4, 2020 the Sixth District Court of
Appeals remanded the matter to the Erie County Common Pleas Court.
Court of Appeals No. E-19-064. Pursuant to the decision from the Sixth
District Court of Appeals this Court hereby finds that Plaintiff’s claims do
not meet the requirements of the statute of repose and therefore the statute
of limitations set forth in R.C. 2305.06 apply. Therefore, the order
[journalized on] October 28, 2019 denying the parties’ respective motions
for summary judgment is not a final appealable order.
{¶ 22} The trial court did not make any specific findings prior to concluding that
Betton’s claims do not meet the statute of repose. We will do so in our de novo review.
{¶ 23} The Ohio Supreme Court determined that R.C. 2305.131 “applies to
contract actions that meet the requirements of the statute.” New Riegel, 157 Ohio St.3d
164, 2019-Ohio-2851, 133 N.E.3d 482, at ¶ 26. R.C. 2305.131(A)(1) states:
Notwithstanding an otherwise applicable period of limitations
specified in this chapter * * *, no cause of action to recover damages for * *
* an injury to real or personal property, * * * that arises out of a defective
and unsafe condition of an improvement to real property * * *, shall accrue
against a person who performed services for the improvement to real
property or a person who furnished the design, planning, supervision of
construction, or construction of the improvement to real property later than
ten years from the date of substantial completion of such improvement.
10.
{¶ 24} The statue defines “substantial completion” as “the date the improvement
to real property is first used by the owner or tenant of the real property or when the real
property is first available for use after having the improvement completed in accordance
with the contract or agreement covering the improvement, including any agreed changes
to the contract or agreement, whichever occurs first.” R.C. 2305.131(G).
{¶ 25} In support of its motion for summary judgment, Speer pointed to Betton’s
complaint, among other parts of the record, to show that construction was substantially
completed by, and the waterline operational by, 2004: “A break that occurred on or about
May 4, 2004 at Strecker Road where the pipe was found to be resting on a sharp rock.”
Speer also pointed to Betton’s complaint where construction was substantially completed
by, and the waterline operational by, 2003: “[O]n or about January 3, 2013, which was
approximately only ten years after being placed into service, a 16-inch pipe cracked along
its full length on Hayes Avenue (State Route 4).” In addition, the Erie County
prosecutor’s letter to Betton declining to initiate civil litigation stated the defective
waterlines were installed in 2001. Betton then points to the undisputed fact that Betton
did not file his complaint until September 7, 2016, which is more than ten years after
substantial completion of the waterline and, therefore, barred by R.C. 2305.131(A)(1).
{¶ 26} Having met its burden on summary judgment to raise R.C. 2305.131(A)(1),
the burden shifted to Betton to point to the evidence in the record of a genuine issue of
material fact that R.C. 2305.131(A)(1) does not bar his complaint. First, Betton argued
the trial court properly concluded, after the New Riegel decision, that R.C. 2305.131 did
11.
not bar Betton’s complaint and that the longer limitations period under R.C. 2305.06
applied. Then Betton pointed to his complaint, among other parts of the record, to show
that he alleged Speer breached the construction contracts by defectively installing the
District B waterline system, and such defects are causing injury to the public in excess of
$25,000. Without clearly identifying the relevant portions of the contracts themselves,
Betton points to five examples of contract breaches by Speer: (1) some of the new
waterline pipes were “improperly laid upon, or adjacent to, rocks of all sizes,” (2) “proper
granular stone bedding was not provided in waterline trenches,” (3) “PVC pipes were
joined by pushing them together using a backhoe or other machinery, which supplied too
much force, (4) the welds on the high density polyethylene pipes “were not fused
properly and have been failing with ever increasing frequency,” and (5) “the service
saddles installed by Speer as ‘equals’ to those specified in the contracts were not equals.”
{¶ 27} While Betton carefully avoids pointing to evidence in the record of when
substantial completion of the District B waterline occurred,6 Betton argues in his
opposition to summary judgment that his complaint alleges breaches of contract from
Speer’s installation of a defective waterline system, which has caused excessive repair
costs, and does not allege unsafe conditions or any “injury” to real or personal property.
Betton insists that none of his allegations of District B waterline defects by Speer are
“injuries” to trigger R.C. 2305.131(A)(1). Thus, Betton argues that the excessive and
6
Betton’s statement of the facts of this appeal acknowledges, “The construction of the
District B waterline was completed in August 2004.”
12.
costly repairs to the District B waterlines allegedly caused by Speer’s breaches of the
construction contracts, and which also caused excessive water rate increases on
customers, are simply not “injuries” to the waterlines for purposes of the statute of
repose.
{¶ 28} We disagree in light of the essence of Betton’s allegations in his complaint,
as supplemented, of numerous injuries to Erie property in the form of subsurface
waterline breaks. Betton points to those injuries to Erie’s property as the evidence of
Speer’s breach of contract, arguing if Speer had installed the waterlines by following the
contract specifications, there would not be waterline breaks. We find that Betton’s self-
serving evidence opposing summary judgment, by refusing to label the defects resulting
from the contract breaches as “injuries,” fails Civ.R. 56(E) requirements.
{¶ 29} We begin with the requirements of a statute of repose, as stated by the Ohio
Supreme Court.
A statute of repose is a statute that bars “any suit that is brought after
a specified time since the defendant acted * * *, even if this period ends
before the plaintiff has suffered a resulting injury.” Black’s Law Dictionary
1637 (10th Ed.2014). The repose period begins to run “‘when a specific
event occurs, regardless of whether a cause of action has accrued or
whether any injury has resulted.’” Id., quoting 54 Corpus Juris Secundum,
Limitations of Actions, Section 4, at 20-21 (1987).
New Riegel, 157 Ohio St.3d 164, 2019-Ohio-2851, 133 N.E.3d 482, at ¶ 11.
13.
{¶ 30} The Ohio Supreme Court acknowledged that R.C. 2305.131(A)(1)
specifically states the repose period applies notwithstanding an otherwise applicable
period of limitations specified in this chapter, such as R.C. 2305.06 for written contract
claims. Id. at ¶ 27. However, the court declined to opine on the issue of whether R.C.
2305.131(A)(1) shortens the time to file an accrued contract claim under R.C. 2305.06
because that issue was not addressed by either the trial court or the Third District Court of
Appeals. Id. at ¶ 31-32. That is the essence of the assignment of error raised by Speer’s
cross-appeal.
{¶ 31} Following the New Riegel decision, the Seventh District Court of Appeals
determined that specific issue and stated, “R.C. 2305.131 prohibits an action after a set
amount of time from a certain event (substantial completion), without regard to the date
of accrual, and thus it is a statute of repose that eliminates the right to a cause of action
after that set amount of time from the named event.” Union Local School Dist., Bd. of
Education v. Grae-Con Construction, Inc., 2019-Ohio-4877, 137 N.E.3d 122, ¶ 35 (7th
Dist.). The court explained that while “a statute of repose and a statute of limitations
both limit the time during which one must be prepared to defend a claim, they have
distinct applications.” Id. at ¶ 14. A statute of limitations is a time limit for suing in a
civil case based on the date when the claim accrued. Id. A statute of repose places an
absolute outer limit on the right to bring a civil action measured from the date specified in
the statute, not the date when the claim accrues. Id. at ¶ 15. Therefore, R.C. 2305.131, as
a true statute of repose, bars accrued contract claims and those claims that have not yet
14.
vested after ten years from substantial completion of the improvement. Id. at ¶ 36. It is
undisputed in the record that the District B waterlines constructed by Speer as a result of
the four construction contracts entered into with Erie are “improvements.”
{¶ 32} The application of R.C. 2305.131(A)(1) is not altered if the basis of the
injury is unknown or speculative, which is reflected in the record before us. New Riegel
at ¶ 11.
{¶ 33} Betton testified at his deposition of the speculative basis for the injury
caused by Speer’s breaches of the construction contracts:
Q: But you don’t get water from District B, you get it from the City
of Sandusky. So did you ever go to the City of Sandusky and say, “Hey,
you know, I’m trying to connect the dots here. Are these issues that I’m
hearing about with pipe depth and rocks impacting me as a Sandusky rate
payer at all”?
A: No.
Q: Did you believe that they were impacting your rates?
A: I figured they would be sooner or later, yes.
Q: Can you tell me why you made that conclusion?
A: Because it was a big project costing a lot of money. If it was
wrong and had to be redone, that was going to be through the ratepayers.
15.
{¶ 34} Former Erie County Administrator Peter Daniel testified at his deposition
of the speculative basis for the injury caused by Speer’s breaches of the construction
contracts:
Q: So our clients are being sued based on work in a contract they
entered into in 2001[,] or earlier than that[,] for services provided from
2000 to 2004. If that county commissioner board knew what those costs
were, that should be the expectation upon our clients in their performance,
correct?
A: If those same board members were in place.
Q: Well, let me just understand your answer. Are you saying with
your clarification that the current county commissioners potentially have a
different expectation as what’s the appropriate repair costs for Erie County
in District B than the county commissioners who signed the contracts with
Burgess & Niple and Speer Brothers?
A: I think that’s fair.
Q: Do you know what the current county commissioners’
expectations are in terms of the repair costs incurred for Erie County for
District B?
A: Do I know?
Q: Yes.
A: No.
16.
***
Q: And did [the breaks] continue to a point that it became an unusual
amount of breaks?
A: I think so.
Q: How did you make that determination?
A: Just my opinion.
Q: Based on what training?
A: None.
{¶ 35} Erie County Utilities Director David Moyer also testified at his deposition
of the speculative basis for the injury caused by Speer’s breaches of the construction
contracts:
Q: You said there’s been a lot of breaks in [District] B. I think you
used “a lot” as your word, right? Is that what you used?
A: Yeah. I used a lot because a newer system like this shouldn’t be
breaking like it is.
Q: Tell me the standard or what’s the accepted amount of breaks for
the [District] B waterline?
A: For the newer [District] B, the standard should be it shouldn’t be
hardly any breaks right now. * * * That’s my opinion. * * * We have a
system that’s * * * 17 to 20 years old that’s breaking that shouldn’t be
breaking for another 20 years in my opinion.
17.
Q: Okay. I understand that’s your opinion. Have you ever consulted
with any standards that have actually gone into studies that * * * said,
here’s the performance or what they call the accepted failure rate of a
waterline system? Have you ever reviewed any of those studies?
A: No.
{¶ 36} We agree with the Seventh District and, upon de novo review, find that
Betton’s breach of construction contract claims against Speer are barred by the statute of
repose, R.C. 2305.131, having been filed more than ten years after substantial completion
of the improvements. The record indicates substantial completion occurred by 2004, and
Betton initiated this litigation more than ten years after substantial completion. The trial
court erred when it denied Speer’s motion for summary judgment where no genuine issue
as to any material fact remained to be litigated, and reasonable minds can come to but
one conclusion that Speer was entitled to judgment as a matter of law.
{¶ 37} Speer’s cross-assignment of error is well-taken.
{¶ 38} In light of our determination on Speer’s cross-assignment of error, we find
that Betton’s and Erie’s first and second assignments of error are moot. App.R.
12(A)(1)(c).
IV. Conclusion
{¶ 39} On consideration whereof, the judgments of the Erie County Court of
Common Pleas are affirmed, in part, and reversed, in part. On reversal, judgment is
18.
hereby entered for Speer. App.R. 12(B). Betton and Erie are ordered to equally pay the
costs of this appeal pursuant to App.R. 24.
Judgments affirmed, in part,
and reversed, in part.
A certified copy of this entry shall constitute the mandate pursuant to App.R. 27.
See also 6th Dist.Loc.App.R. 4.
Thomas J. Osowik, J. ____________________________
JUDGE
Myron C. Duhart, P.J.
____________________________
JUDGE
Christine E. Mayle, J. ____________________________
CONCURS AND WRITES JUDGE
SEPARATELY.
MAYLE, J., concurring.
{¶ 40} I agree with the ultimate disposition of this case. I write separately to more
fully address the parties’ arguments relating to Speer’s cross-appeal.
{¶ 41} The majority states that the “essence” of the parties’ dispute centers upon
whether R.C. 2305.131 is a true statute of repose—i.e., whether it bars accrued claims as
well as claims that have not vested. Ultimately, the majority agrees with the Seventh
19.
District’s determination that “R.C. 2305.131 prohibits an action after a set amount of time
from a certain event (substantial completion), without regard to the date of accrual, and
thus it is a statute of repose that eliminates the right to a cause of action after that set
amount of time from the named event.” Union Local School Dist., Bd. of Edn. v. Grae-
Con Constr., Inc., 2019-Ohio-4877, 137 N.E.3d 122, ¶ 35 (7th Dist.). In other words, the
majority concludes that R.C. 2305.131 is a true statute of repose.
{¶ 42} I agree with this conclusion.7 See New Riegel Local School Dist. Bd. of
Edn. v. Buehrer Group Architecture & Eng., Inc., 157 Ohio St.3d 164, 2019-Ohio-2851,
133 N.E.3d 482, ¶ 43 (Kennedy, J., concurring) (“It is * * * manifest that the General
Assembly understood R.C. 2305.131 to be a true statute of repose * * *.”). I also agree
that we must expressly resolve this issue as a necessary prerequisite to the cross-appeal.
But the majority essentially ends its analysis there—and then summarily concludes that
because R.C. 2305.131 is a true statute of repose, “Betton’s breach of construction
contract claims against Speer are barred [because they were] filed more than ten years
after substantial completion of the improvements.” Again, I agree, but there are a few
missed steps in the analysis.
7
Indeed, the parties do not dispute that R.C. 2305.131 is a true statute of repose. See,
e.g., Betton’s response brief, pg. 7 (“Speer argues that the trial court’s decision of
October 28, 2019, to apply the fifteen-year statute of limitations for breach of contract,
may be based upon the theory that R.C. 2305.131 is not a true statute of repose. This
conclusion is pure speculation. This argument was not presented to the trial court by
Appellants/Cross-Appellees, nor was it ever stated by the court.” (Emphasis sic.)).
20.
{¶ 43} Betton has steadfastly maintained, in the trial court and on appeal, that
“R.C. 2305.131 is a true statute of repose, but it does not apply to every action dealing
with construction and it does not apply to the cause of action asserted by the Plaintiffs
below in this case.” The majority does not fully address this argument—i.e., Betton’s
claim that R.C. 2305.131 does not apply because his cause of action does not “meet[] the
requirements of the statute.” New Riegel at ¶ 1 (stating that R.C. 2305.131 “applies to
any cause of action, whether sounding in tort or contract, so long as the cause of action
meets the requirements of the statute.” (Emphasis added.)).
{¶ 44} R.C. 2305.131 states, in relevant part, “no cause of action to recover
damages for * * * an injury to real or personal property * * * that arises out of a defective
and unsafe condition of an improvement to real property * * * shall accrue against a
person who performed services for the improvement to real property * * * later than ten
years from the date of substantial completion of such improvement.” R.C.
2305.131(A)(1). Betton argues that R.C. 2305.131 is inapplicable because (1) he does
not seek to recover damages for an injury to real or personal property other than the
improvements themselves, and (2) his claim against Speer does not arise out of a
“defective and unsafe” condition in an improvement to real property.
{¶ 45} Regarding Betton’s first argument, the majority states that Betton denies
that he has alleged any “‘injuries’ to the waterlines for purposes of the statute of repose.”
This is inaccurate. Betton expressly recognizes that he alleges injuries to the waterlines
themselves—i.e., Betton concedes that the improvements are, in fact, defective. Betton
21.
actually argues that his claim against Speer does not fit within R.C. 2305.131 because he
does not allege damage to any real or personal property other than the defective
improvements themselves. That is, Betton claims that “[t]he law distinguishes between
situations where a defective improvement to real property causes damage to other real or
personal property and those situations when the improvement to real property is found to
be defective and does not perform as it should.” (Emphasis added.) He maintains that
his cause of action merely seeks economic damages “arising directly from the improper
installation of the waterline and [do not include] allegations of any damage caused by the
waterline to other real or personal property resulting from the defective conditions of the
waterline.” (Emphasis added.)
{¶ 46} Essentially, Betton argues that “an injury to real or personal property * * *”
under R.C. 2305.131 should be interpreted as “an injury to other real or personal
property other than the defective improvement itself * * *.” (Emphasized text added.)
But courts must give effect to the words the General Assembly has chosen when enacting
a statute, and may not add or delete words from the statutory language. See, e.g., Griffith
v. Aultman Hosp., 146 Ohio St.3d 196, 2016-Ohio-1138, 54 N.E.3d 1196, ¶ 18 (“We
apply the statute as written * * * and we refrain from adding or deleting words when the
statute’s meaning is clear and unambiguous * * *.”). Here, the language of R.C.
2305.131 is unambiguous, and is not limited in the manner that Betton suggests. Rather,
it applies broadly to causes of action “to recover damages for * * * an injury to real or
personal property * * * that arises out of a defective and unsafe condition of an
22.
improvement to real property * * *.” R.C. 2305.131(A)(1). Betton’s cause of action—
which seeks to recover breach-of-contract damages for allegedly-defective improvements
to real property—falls squarely within the rubric of R.C. 2305.131 under New Riegel.
{¶ 47} Alternatively, Betton also argues that his claim against Speer does not arise
out of a “defective and unsafe” condition in the improvement to real property, as required
by R.C. 2305.131. He claims that “[t]he entire premise of the Complaint is that Speer
failed to comply with the agreed-upon requirements of the construction contracts and
those failures resulted in defective installations. There is no allegation of an unsafe
condition of the waterline.”
{¶ 48} To the contrary, at paragraph 47 of the complaint, Betton specifically
alleges that “Erie County has incurred, and will continue to incur, expenses to repair
future waterline breaks, expenses for user notifications and costs to minimize
contamination risks, due to improperly installed sections of waterlines.” (Emphasis
added.) In his brief, Betton attempts to minimize this allegation, claiming that “[t]he
expenses listed in ⁋ [sic] 47 are the expenses necessary to disinfect the repaired pipe,
prior to notifying customers that the water is again safe to drink, after a break. The
contamination risk, that must be prevented, is an economic consequence of Speer’s
breaches, not an unsafe condition from which the claims arise.” Betton’s explanation,
however, does not help his cause: damages that Erie incurs to ensure that “the water is
again safe to drink” after a break necessarily means that the water is unsafe to drink
23.
during a break. These damages unquestionably arise out of a “defective and unsafe
condition of an improvement to real property * * *” under R.C. 2305.131.
{¶ 49} For these reasons, I concur with the majority’s ultimate conclusion that
Betton’s cause of action against Speer is barred by R.C. 2305.131.
This decision is subject to further editing by the Supreme Court of
Ohio’s Reporter of Decisions. Parties interested in viewing the final reported
version are advised to visit the Ohio Supreme Court’s web site at:
http://www.supremecourt.ohio.gov/ROD/docs/.
24.