The North Carolina Department of Health and Human Services, Division of Facility Services (“Agency”) correctly treated appellant Good Hope Health System’s 2003 CON application for a Certificate of Need (“CON”) as one for a new institutional health service. The Agency did not err in determining that appellant had failed to meet its burden of showing compliance with the relevant statutory review criteria.
I. Factual Background
A. Good Hope Hospital’s 2001 CON
Good Hope Hospital (“GHH” and “Good Hope”) is licensed as an acute care hospital and had been in operation since 1921 in Erwin, North Carolina. Respondent Betsy Johnson Regional Hospital, Inc. (“Betsy Johnson”), is located in Dunn, North Carolina. Both hospitals are located in Harnett County.
In 2001, pursuant to N.C. Gen. Stat. Chapter 131E, Good Hope applied for a CON from the Agency’s Certificate of Need Section, *539seeking to partially replace its existing facility. The 2001 CON application proposed to replace the existing acute care facility by constructing a replacement facility on a nearby site in Erwin while utilizing the existing campus for outpatient services and administrative support. Good Hope’s proposal reduced the number of acute care beds from forty-three to thirty-four, reduced the number of psychiatric beds from twenty-nine to twelve, for a total of forty-six beds, and included three operating rooms, at a cost of $16,159,950. Following conditional Agency approval and Good Hope’s subsequent petition for a contested case hearing, Good Hope and the Agency settled disputed matters in a written agreement (“2001 Settlement Agreement”).
Among the terms of the 2001 Settlement Agreement was a “Successors and Assigns” clause; a “Modification or Waiver” clause, requiring that any modifications be in writing, signed by the parties, and adopted and approved by the Director of the Agency; and a timetable by which Good Hope committed itself to secure financing by 1 March 2002 and open the replacement facility by 1 December 2003. On 14 December 2001, the Agency issued a CON to Good Hope (“2001 CON”) for a forty-six bed hospital with three operating rooms.
Good Hope sought funding from the United States Department of Housing and Urban Development (“HUD”) and funding approval from the North Carolina Medical Care Commission (“MCC”), which must approve all HUD financing for non-profit hospitals in North Carolina. Upon MCC’s recommendation, Good Hope entered merger discussions with Betsy Johnson. In June 2002, Good Hope advised MCC that a merger was not possible, and MCC unanimously denied Good Hope’s request for HUD funding approval.
B. The Formation of Good Hope Health System. L.L.C.
In August 2002, seeking financing for the proposed replacement facility, Good Hope entered into a Letter of Intent with Triad Hospitals, Inc. (“Triad”) to develop a 46-bed acute care hospital in or around Lillington, North Carolina, to replace Good Hope Hospital. Seeking a more centrally-located site, Good Hope and Triad settled on Lillington, over ten miles from the current facility in Erwin. Triad would own 90% of the new hospital and Good Hope would own 10%, with an option to sell out its interest to Triad at an agreed upon price or to acquire an additional 5%. On 10 October 2002, the two entities formed Good Hope Health System, L.L.C. (“appellant” and “GHHS”) upon these terms.
*540GHHS sought Agency approval for its plans for a proposed Lillington hospital in three separate ways: (1) in November 2002, Good Hope and GHHS filed a motion for declaratory ruling seeking a “good cause” transfer of the 2001 CON from Good Hope to appellant; (2) in April 2003, GHHS filed a “full acute care” application with the Agency, hereinafter referred to as the “2003 CON application”; and (3) in August 2003, Good Hope and GHHS filed for exemption under N.C. Gen. Stat. § 131E-184 for “a proposal to replace all seventy-two” beds in a new hospital. The second of these is the subject of this appeal. We briefly discuss the first and third of these approaches prior to discussing the second.
O.GHHS’ Lillington Proposal
1.Request for “Good Cause” Transfer
On 12 November 2002, appellant and Good Hope filed a motion for declaratory ruling, seeking (1) a “good cause” transfer of the 2001 CON from Good Hope to appellant, (2) permission to change the proposed location from Erwin to Lillington or Buies Creek, and (3) permission to increase the size of the replacement facility from 61,788 square feet to 67,874 square feet. The revised cost was $18,523,942. The Agency denied this request on 12 February 2003. The Final Agency Decision in the case sub judice noted that the Agency rejected the request for the following reasons:
GHH and GHHS had failed to demonstrate good cause for the transfer of the CON under G.S. 131E-189(c); the transfer would be impermissible because Triad would own 90% of GHHS; the relocation of the project from Erwin to either Lillington or Buies Creek would constitute a material change in the location; and the increase in the size of the proposal of 6,086 square feet would constitute a material change in the defined scope of the project.
Appellant appealed the denial to Wake County Superior Court. The appeal was subsequently stayed by consent.
2.The Exemption Request
On 21 August 2003, appellant and Good Hope gave notice to the Agency, seeking exemption from CON review of “a proposal to replace all seventy-two” beds, pursuant to N.C.G.S. § 131E-184. Upon the Agency’s denial of the exemption request, and prior to exhausting its administrative remedies, appellant sought judicial review in the Superior Court of Harnett County. The trial court’s dismissal of the *541action was appealed to this Court and affirmed in Good Hope Hosp., Inc. v. N.C. Dep’t of Health & Human Servs., 174 N.C. App. 266, 620 S.E.2d 873 (2005). The denial of the exemption request by the Agency was appealed to this Court and affirmed in Good Hope Hosp., Inc. v. N.C. Dep’t of Health & Human Servs., 175 N.C. App. 309, 623 S.E.2d 315, rev. denied, cert. denied, 360 N.C. 480, 632 S.E.2d 172, aff’d per curiam, 360 N.C. 641, 636 S.E.2d 564 (2006).
3. The 2003 CON application
After the “good cause” transfer was denied, but before seeking the exemption, appellant and Good Hope sought to file an amendment -to Good Hope’s 2001 CON in accordance with the Agency’s review schedule for changes in previously approved CON projects and relocations of existing facilities.
On 1 April 2003, two weeks before the scheduled review date under the State Medical Facilities Plan, appellant participated in a pre-application conference with the Chief of the Certificate of Need Section, during which appellant proposed relocating all of the functions from the existing Good Hope facility to the Lillington site and increasing the size of the proposed facility from 67,874 to 112,945 square feet. The CON Section Chief advised appellant that: (1) “a project with a different person, a different location, and a different scope would by definition be a [new] project;” (2) appellant “must complete the full acute care application form;” (3) appellant “could not rely on the representations” made by Good Hope in its 2001 application; (4) appellant “would have to justify all aspects of the services proposed in the new CON application, including the demonstration of need for a third operating room[;]” and (5) appellant “must demonstrate under Criteria 4 why the new proposal was a more effective alternative” than the replacement facility already approved.
On 14 April 2003, appellant filed a “full acute care” application to build a new replacement hospital in Lillington. The application proposed forty-six acute care beds, the relocation of all acute care and inpatient psychiatric services from the existing Erwin facility, plus the development of ten observation beds and three operating rooms in a 112,945 square foot facility, at a cost of $33,488,750. The 2003 CON application sought to relocate all hospital departments to the new facility and abandon Good Hope’s existing campus, in what appellant termed “a more effective alternative” than that approved in the 2001 CON.
*542Page One of the 2003 CON application included the following statement:
Please see Exhibit 1 for a copy of the executive summary of the draft master agreement between Triad Hospitals Inc. and Good Hope Hospital Inc. that relates to formation of Good Hope Health System, LLC. This document constitutes a prior notice to the CON Section that [GHHS] intends to lease the existing hospital, which is an acquisition by lease that is exempt from CON review.
Exhibit 1 was a non-binding “Term Sheet,” dated 14 April 2003, which set forth the “material terms” of mutual intentions for a short-term lease of Good Hope Hospital and development and ownership of a replacement facility. The agreement was signed by representatives of the two parties to the agreement, appellant and Good Hope, and required that any “definitive agreements” be “satisfactory to both Triad and GHH.” The agreement was silent as to the 2001 Settlement Agreement and was not executed by the Agency.
Pursuant to N.C.G.S. § 131E-185(al)(2), the Agency held a public hearing on 12 June 2003, and respondents Betsy Johnson and Central Carolina Hospital submitted written comments to the Agency, setting forth reasons why the Agency should not approve appellant’s 2003 CON application. At the public hearing, speakers spoke for and against the proposal.
II. Procedural History
On 26 September 2003, the Agency’s CON Section found that the 2003 CON application was non-conforming with numerous regulatory and statutory review criteria and denied appellant’s application. On 23 October 2003, appellant filed a petition for a contested case hearing with the Office of Administrative Hearings. Betsy Johnson and Central Carolina Hospital moved to intervene as respondents in support of the Agency’s decision. The Administrative Law Judge (“ALJ”) granted motions to intervene by respondent-intervenors (together with the Agency, “appellees”) and also by petitioner-intervenor Town of Lillington. On 9 July 2004, the ALJ recommended that the Agency’s decision be reversed. On 10 September 2004, finding that the ALJ’s recommended decision was largely based on factors that were immaterial under the CON statutes, the Agency rejected the ALJ’s recommended decision and denied appellant’s 2003 CON application. GHHS and the Town of Lillington appeal from the Final Agency Decision, *543making 616 separate assignments of error. Good Hope is not a party to this appeal.
III. Standard of Review
A.Dictated bv Issues Raised
The standard of review of an administrative agency’s final decision is dictated by the substantive nature of each assignment of error. N.C. Dep’t of Env’t & Natural Res. v. Carroll, 358 N.C. 649, 658-59, 599 S.E.2d 888, 894 (2004) (detailing the standard of review for reversing or modifying an agency’s decision under the six grounds specified by N.C.G.S. § 150B-51(b) and classifying those grounds into “law-based” or “fact-based” inquiries); Total Renal Care of N.C., L.L.C. v. N.C. HHS, 171 N.C. App. 734, 737-39, 615 S.E.2d 81, 83-84 (2005) (detailing the interplay of the CON statutes with the 1999 Administrative Procedures Act).
B. Law-based Inquiries
Where the appellant asserts an error of law in the final agency decision, this Court conducts de novo review. Christenbury Surgery Ctr. v. N.C. HHS, 138 N.C. App. 309, 311-12, 531 S.E.2d 219, 221 (2000); see also Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85. “When the issue on appeal is whether a state agency erred in interpreting a statutory term, an appellate court may freely substitute its judgment for that of the agency . . . .” Britthaven, Inc. v. N.C. Dept. of Human Resources, 118 N.C. App. 379, 384, 455 S.E.2d 455, 460 (1995) (quoting Brooks, Comr. of Labor v. Grading Co., 303 N.C. 573, 580-81, 281 S.E.2d 24, 29 (1981)).
C. Fact-based Inquiries
Fact-intensive issues, such as sufficiency of the evidence or allegations that a decision is arbitrary or capricious, are reviewed under the whole record test. See Carroll, 358 N.C. at 659, 599 S.E.2d at 894-95.
A court applying the whole record test may not substitute its judgment for the agency’s as between two conflicting views, even though it could reasonably have reached a different result had it reviewed the matter de novo. Rather, a court must examine all the record evidence — that which detracts from the agency’s findings and conclusions as well as that which tends to support them — to determine whether there is substantial evidence to justify the agency’s decision.
*544Watkins v. N.C. State Bd. of Dental Exam’rs, 358 N.C. 190, 199, 593 S.E.2d 764, 769 (2004) (internal citations omitted). “ ‘Substantial evidence’ means relevant evidence a reasonable mind might accept as adequate to support a conclusion.” N.C.G.S. § 150B-2(8b) (2005); see also Watkins, 358 N.C. at 199, 593 S.E.2d at 769, Total Renal Care, 171 N.C. App. at 739, 615 S.E.2d at 84. However, “the ‘whole record’ test is not a tool of judicial intrusion; instead, it merely gives a reviewing court the capability to determine whether an administrative decision has a rational basis in the evidence.” Hospital Group of Western N. C., Inc. v. N.C. Dept of Human Resources, 76 N.C. App. 265, 268, 332 S.E.2d 748, 751 (1985) (quoting In re Rogers, 297 N.C. 49, 65, 253 S.E.2d 912, 922 (1979)).
D. Deference under Britthaven and Total Renal Care
In Britthaven and Total Renal Care, this Court applied a standard of deference first described by the United States Supreme Court in Skidmore v. Swift & Company, 323 U.S. 134, 89 L.Ed. 124 (1944), regarding agency interpretations of enabling statutes.
Although the interpretation of a statute by an agency created to administer that statute is traditionally accorded some deference by appellate courts, those interpretations are not binding. ‘The weight of such [an interpretation] in a particular case will depend upon the thoroughness evident in its consideration, the validity of its reasoning, its consistency with earlier and later pronouncements, and all those factors which give it power to persuade, if lacking power to control.’ Skidmore v. Swift & Company, 323 U.S. 134, 140, 89 L.Ed. 124, 129 (1944).
Britthaven, 118 N.C. App. at 384, 455 S.E.2d at 460 (citation omitted); see also Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85 (citation omitted). In Total Renal Care, this Court added: “If appropriate, some deference to the Agency’s interpretation is warranted when we are operating under the ‘traditional’ standards of review ...” Id.
IV. The Final Agency Decision
After setting forth the AU’s findings of fact, including those it rejected, and stating its reasons for rejecting those findings, the Final Agency Decision concluded that (1) the Agency’s denial of a “good cause” transfer was binding on GHHS, (2) the 2001 Settlement Agreement could not alter statutory restrictions on transfers of an undeveloped CON, and (3) the 2001 CON held by Good Hope did not relieve GHHS of the requirements that it comply with the 2003 State *545Medical Facilities Plan and statutory criteria for a new institutional health service. Inter alia, the Agency made the following conclusions of law:
6. The Department’s Declaratory Ruling that good cause did not exist for the transfer to GHHS of GHH’s undeveloped CON rights is binding on GHHS. G.S. 150B-4. (“A declaratory ruling is binding on the agency and the person requesting it unless it is altered or set aside by the court.”)
7. The [2001] CON, by law, is valid only for the defined scope, physical location, and person named in the application. A certificate of need shall not be transferred or assigned except as provided in G.S. 131E-189(c). G.S. 131E-181(a). The Settlement Agreement between the Agency and GHH which led to the issuance of the 2001 CON did not, and properly could not, alter the restriction the CON law imposes upon transfer of undeveloped CONs.
8. The CON law does not permit either the transfer of the [2001] CON to develop the 2001 project with its third operating room from GHH to GHHS nor does it permit the development of an operating room in violation of the 2003 SMFP no-need determination. Even if the CON were transferable, the relocation of an approved, but not yet developed, operating room is subject to the CON requirement set in G.S. 131E-176(16)u for relocation and thus subject to the current SMFP need determination. . . .
9. The prior CON to GHH did not relieve GHHS of the requirement that it comply in this application with Criterion 1 and specifically with the 2003 SMFP need determination regarding addition of a third operating room. G.S. 131E-181(a).
10. While a completed health service facility may be transferred without meeting the review criteria or being subjected to further CON review under the exemption provision of the CON law, G.S. 131E-184, the CON law generally prohibits a CON for an uncompleted project to be transferred. G.S. 131E-181(a).
Among its findings of fact, the Agency included, as ultimate findings of fact, see Woodard v. Mordecai, 234 N.C. 463, 470, 67 S.E.2d 639, 644 (1951), the following:
37. Development of new or additional operating rooms are a new institutional health service, the need for which is subject to any *546determinative limitations set in the State Medical Facilities Plan (“SMFP”). G.S. 131E-176(16)u, 131E-183(a)(l). (GHHS Ex. 29, 2003 SMFP, pp. 29-52.) In addition, the relocation of any operating room to a new different [sic] campus is also subject to CON review and must satisfy the criteria in place at the time of the application. The CON law was amended to this effect after the 2001 application of GHH and before the 2003 CON application of GHHS. G.S. 131E-176(u) [sic]. The application is subject to the statutes, rules, criteria, standards and SMFP in place at the time the review begins. See 10A NCAC 14C.0207(a).
42. The Agency was aware during its review of GHHS’ application that GHH had been granted the 2001 CON with the third operating room. However, the Agency concluded correctly that GHHS would have to nevertheless show a need for the third operating room, since that room had not been developed by GHH, and since the project proposed by GHHS in [the 2003 application] proposed a different applicant, location and scope of services than the project proposed by GHH in [the 2001 CON]. G.S. 131E-181(a). (Hoffman, Tr. Vol. 8, pp. 2450-2451).
(emphasis added).
Applying N.C. Gen. Stat. §§ 131E-176(16) and 131E-181(a), the Agency determined that, because the 2003 CON application proposed doubling the size of the facility and the 2001 CON’s approved capital expenditure, a change in ownership from Good Hope to Good Hope Health System, L.L.C., and a change in location from Erwin to Lillington, the 2003 CON application could not be treated as an amendment to the 2001 CON. See N.C.G.S. § 131E-181(a) (2003). Moreover, because the 2003 CON application proposed the relocation of two operating rooms and added a third, the 2003 CON application was deemed to provide a “new institutional health service” under N.C.G.S. § 131E-176(16)u, which required GHHS to comply with the 2003 State Medical Facilities Plan (“SMFP”). See N.C. Gen. Stat. §§ 131E-176(16)u, 131E-183(a) (2003). As noted in the Final Agency Decision, “The 2001 CON was not approved for GHHS, nor for this location in Lillington, nor for this project.”
Applying the review criteria for a new institutional health service, the Final Agency Decision affirmed the conclusions and findings of the CON Section and rejected the ALJ’s contrary findings as erro*547neous and unsupported by the evidence. The Agency concluded that appellant did'not meet its burden of showing that its application met the relevant criteria or that the Agency had acted outside its authority, acted erroneously, arbitrarily or capriciously, used improper procedure, or failed to act as required by law or rule in finding the application non-conforming with relevant statutory review criteria or in disapproving the 2003 CON application.
The Agency rejected the ALJ’s conclusion that “the agency substantially prejudiced [appellant’s] rights when it denied the 2003 CON application for a CON to build a much needed, centrally located, replacement hospital in Lillington, North Carolina.” The ALJ had based his conclusion upon a finding that appellant “is not seeking to replace any operating room which does not already exist or has not already been approved by the CON section for Harnett County.” The Agency rejected this finding as contrary to the law and the facts, and rejected the conclusion as “not supported by the evidence and [as] contrary to the CON law. An applicant has no vested right to the approval of a CON application, but must meet the requirements set forth in the statute.”
V. Analysis
A. Agency Authority to apply N.C.G.S. § 131E-183(a)
In their first argument, appellants contend that the 2003 CON application sought modification of Good Hope’s existing 2001 CON, and that the Agency exceeded its authority by (1) failing to treat the 2003 CON application as a change in an existing project under N.C.G.S. § 131E-176(16)e and (2) reviewing the 2003 CON application for conformity with criteria in N.C.G.S. § 131E-183(a) that applies only to a “new institutional health service.” We disagree.
1. New Institutional Health Services under N.C.G.S. § 131E-176
Appellants argue that the Agency “exceeded its authority” in classifying its 2003 CON Application as a new institutional health service by ignoring its own statutes, the Agency’s 2001 Settlement Agreement with Good Hope, the State Medical Facilities Plan, and prior Agency decisions. Appellants further contend that the Agency erred in applying the statutory review criteria for a new institutional health service because: (1) under the provisions of the 2001 Settlement Agreement, there was not a change in applicant; (2) under N.C.G.S. § 131E-176(16)e, a change of more than fifteen percent of *548the approved capital expenditure amount constituted a change to the 2001 CON; and (3) the same capital asset is at issue in both the 2001 CON and the 2003 CON application.
N.C. Gen. Stat. Chapter 131E, Article 9 governs certificates of need for health care facilities. N.C.G.S. §§ 131E-175 el seq. (2003). A CON is “valid only for the defined scope, physical location, and person named in the application.” N.C.G.S. § 131E-181(a) (2003) (emphasis added). A “person” is defined as “an individual, a trust or estate, a partnership, a corporation, including associations, joint stock companies, . . .” N.C.G.S.'§ 131E-176(19) (2003). As this argument involves an alleged error of law, we review the matter de novo. Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85.
The Agency'relied upon N.C.G.S. § 131E-176(16)u in its determination that the 2003 CON application mandated review as a new institutional health service. This provision includes in its definition of “[n]ew institutional services:”
(u) The construction, development, establishment, increase in the number, or relocation of an operating room or gastrointestinal endoscopy room in a licensed health service facility, other than the relocation of an operating room or gastrointestinal endoscopy room within the same building or on the same grounds or to grounds not separated by more than a public right-of-way adjacent to the grounds where the operating room or gastrointestinal endoscopy room is currently located.
N.C.G.S. § 131E-176(16)u (2003).
Good Hope was awarded the 2001 CON'for the construction of a sixteen million dollar facility totaling 61,788 square feet in Erwin, North Carolina. At the time of the 2003 CON application, Good Hope had entered into a joint venture with Triad, forming appellant. Appellants argue that there was no change in the applicant for the 2003 CON application because the Agency’s 2001 Settlement Agreement with Good Hope provided that “[t]his agreement shall be binding upon the Parties and their successors and assigns.” Appellants contend that GHHS is the successor and assign of Good Hope by virtue of the Term Sheet appended to the 2003 CON application. We need not reach this argument because the express language of the statute limits the validity of a CON to “the defined scope, physical location, and the person named in the application.” N.C.G.S. *549§ 131E-181(a) (emphasis added). Even assuming arguendo that there was no material change in either the scope or location of the proposed hospital, appellant’s argument that it has rights under the 2001 Settlement Agreement is unpersuasive, as discussed in Section V.A.2.a.ii below.
The evidence before the Agency, presented in appellant’s 2003 CON application, proposed: (1) a thirty-three million dollar facility totaling 112,945 square feet, (2) with three operating rooms, ten observation beds, private rooms, and other expanded services, (3) located in Lillington rather than Erwin, (4) owned by appellant GHHS, rather than Good Hope, the holder of the 2001 CON. Good Hope would instead be a minority shareholder, owning only ten percent of the facility. Moreover, appellant made no showing of “development of the [2001 CON],” which is requisite to treatment as a change in project under N.C.G.S. § 131E-176(16)e.
Appellant changed the location and scope of the project and made no showing of development of the 2001 CON to bring its proposal within the provision of N.C.G.S. § 131E-176(16)e. Appellant proposed a relocation of operating rooms to a site over ten miles away, which is subject to CON review under N.C.G.S. § 131E-176(16)u. Under these circumstances, we hold that the Agency acted within its authority to treat the 2003 CON application as one for a new institutional health service rather than as a modification to the 2001 CON. See N.C.G.S. §§ 131E-181(a), 131E-176(16) (2003).
2. Burden of Proof on Applicant for CON
N.C. Gen. Stat. § 131E-183(a) charges the Agency with reviewing all CON applications utilizing a series of criteria set forth in the statute. The application must either be “consistent with or not in conflict with these criteria before a certificate of need for the proposed project shall be issued.” N.C.G.S. § 131E-183(a) (2003). A certificate of need may not be granted which would allow more medical facilities or equipment than are needed to serve the public. See N.C.G.S. §§ 131E-175(4), 131E-183(a)(l) (2003). Each CON application must conform to all applicable review criteria or the CON will not be granted. N.C.G.S. § 131E-183(a) (2003); see also PresbyterianOrthopaedic Hosp. v. N.C. Dep’t of Human Resources, 122 N.C. App. 529, 534, 470 S.E.2d 831, 834 (1996). The burden rests with the applicant to demonstrate that the CON review criteria are met. See Presbyterian-Orthopaedic Hosp., 122 N.C. App. at 534, 470 S.E.2d at 834.
*550a. Criterion One
N.C.G.S. § 131E-183(a)(l) (“Criterion 1”) provides:
(1) The proposed project shall be consistent with applicable policies and need determinations in the State Medical Facilities Plan, the need determination of which constitutes a determinative limitation on the provision of any health service, health service facility, health service facility beds, dialysis stations, operating rooms, or home health offices that may be approved.
N.C.G.S. § 131E-183(a)(l) (2003).
For purposes of appellant’s 2003 CON application, the 2003 SMFP controlled. The 2003 SMFP applied the need methodology of the 2002 SMFP while the Agency developed a new methodology to reflect amendments made to the CON statute to include regulation of operating rooms. The determinative limitation for operating rooms in Harnett County’s service area, based upon the 2002 SMFP need methodology, was that the service area had no need for additional operating rooms. In fact, including the adjustment for the approved but as yet undeveloped operating room under Good Hope’s 2001 CON, the 2003 SMFP showed a surplus of four operating rooms for that service area. Based upon Good Hope’s 2002 License Renewal Application, the 2003 SMFP inventory of operating rooms reflected that there were two operating rooms at Good Hope Hospital.
The 2003 SMFP also provided a mechanism for seeking adjustments to the need and no-need determinations given in the draft SMFP. Neither appellant nor Good Hope sought an adjustment under the procedures outlined by the 2003 SMFP.
i. Contentions of Appellant
Appellants contend that the Agency erred as a matter of law in subjecting it to the no-need determination for operating rooms under the provisions of the 2003 SMFP. Appellants further argue that the Agency’s conclusion that the 2003 CON application was nonconforming with Criterion 1 must be set aside as contrary to the 2001 Settlement Agreement because (1) under the 2001 Settlement Agreement, Good Hope was entitled to three operating rooms; (2) because appellant is “a successor or assignee” under the terms of the 2003 Term Sheet, the Final Agency Decision “fails to abide” by the terms of its 2001 Settlement Agreement with Good Hope; and (3) interpretation of the language of the 2001 Settlement Agreement is a *551question of law. Appellants then argue in the alternative that the Agency exceeded its authority in concluding that Good Hope had only two operating rooms.
ii. GHHS Has No Rights under the 2001 Settlement Agreement
We review de novo appellants’ argument that the Agency exceeded its authority and erred as a matter of law by ignoring the provisions of the 2001 Settlement Agreement. We note initially that Good Hope was not a named applicant on the 2003 CON application and is not a party to this appeal. Appellant asserts that the 2001 Settlement Agreement is a binding contract and that Good Hope’s rights were transferred to GHHS under the express language of the Term Sheet attached to the 2003 CON application, then requests this Court to interpret, as a question of law, the “plain language of the Settlement Agreement.”
In 2002, appellant sought a declaratory ruling from the Agency that “good cause” existed for a transfer of the 2001 CON from Good Hope to GHHS. See N.C.G.S. § 131E-189(c). This request was denied by the Agency. This ruling has not been overturned, and the appeal of this decision has been stayed.
Appellant now seeks to do through a theory of assignment of the 2001 Settlement Agreement what it could not do through the attempted transfer of the 2001 CON. In its brief, appellant relies solely upon the Term Sheet as the basis for its argument that it is a successor or assignee of Good Hope. This document expressly states that “this non-binding Term Sheet merely constitutes a statement of mutual intentions and any and all obligations of the parties shall be memorialized in definitive agreements reflecting the terms set forth herein.” The Term Sheet contains provisions that GHHS would lease the existing facility from Good Hope; that Good Hope would acquire land in Harnett County that would be leased to GHHS; and that GHHS would construct “an acute care replacement hospital” on the site.
We reject appellant’s argument that a “non-binding” agreement, making no reference to the 2001 Settlement Agreement, was effective to assign any rights under that agreement to appellant, including rights to three operating rooms.
iii. Good Hope had Two, not Three. Operating Rooms
We review de novo appellants’ argument that the Agency erred as a matter of law in concluding that Good Hope presently has two oper*552ating rooms rather than three. See Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85. However, we review the Agency’s findings of fact supporting its conclusions of law under a whole record test review. See Carroll, 358 N.C. at 659, 599 S.E.2d at 894-95. Where substantial evidence exists to justify the Agency’s decision, we may not substitute our judgment for the Agency’s as between two conflicting views, Watkins, 358 N.C. at 199, 593 S.E.2d at 769, but are limited to determining whether the Agency’s decision had a rational basis in the evidence. Hospital Group of Western N.C., 76 N.C. App. at 268, 332 S.E.2d at 751.
In its 2003 CON Application, appellant sought to justify the three proposed operating rooms as follows:
The 2003 State Medical Facilities Plan (SMFP) inventory of operating rooms reflects the hospital[’]s two share[d] operating rooms plus the third operating room that is CON approved for development by Good Hope Hospital. Therefore, Good Hope Hospital already has a total of three shared operating rooms that are allocated in the [2003] SMFP.
(emphasis added).
At the time of the 2003 CON Application, Good Hope had two operating rooms. A third operating room was approved under the 2001 CON. This was reflected in the 2003 SMFP, which was based upon Good Hope’s 2002 License Renewal Application and agency files reflecting the 2001 CON. The Agency made the following specific findings of fact concerning a room that appellant now contends was a third, active operating room:
49. GHHS also contends that the proposed third operating room is not an additional operating room subject to the SMFP no-need determination on the ground that Good Hope Hospital had identified in some of its licensing renewal applications filed in the 1980’s and early 1990’s, a third room in its operating suite used for cystoscopy and endoscopy procedures, which room subsequently had been used as a storage room for a number of years, and which GHHS now contends should have been considered by the Agency as a third operating room. (GHHS Ex. 16, 52-57, 1988-1994 Hospital License Renewal Applications).
50. There was no evidence that this room was in use as an operating room at the time of the [2003] CON application nor at any *553relevant time in the past. The evidence that emerged was that this room is used as a storage room and has been so used for a number of years. Certainly, representatives of neither the CON Section, GHH, nor GHHS had any awareness at the time of the review of the possible past use for an endoscopy or cystoscopy procedure room of what is now a storage room. (Annis, Tr. Vol. 3, p. 934; French, Tr. Vol. 12, p. 3530).
51. The 2003 SMFP reflected that Good Hope Hospital had two existing operating rooms. In addition, the 2003 SMFP listed one approved operating room for Harnett County, reflecting the operating room approved (but not yet developed) in GHH’s [2001] CON. (GHHS Ex. 29, 2003 SMFP atp. 63, 73; Keene, Tr. Vol. 15, pp. 4402-4403, 4451.) Based on the record, this is correct.
52. GHH did not contest the inventory as reported in the 2003 SMFP, as that inventory was based on GHH’s own license renewal forms.
53. GHH’s 2000, 2001, and 2002 Hospital License Renewal Applications report that Good Hope Hospital had two shared operating rooms (shared means used for both inpatient and outpatient or ambulatory procedures), no endoscopy procedure rooms, and no operating rooms or endoscopy procedure rooms which were not in use. (GHHS Ex. 8-10.)
54. GHH’s 2001 and 2003 replacement hospital CON applications represented that Good Hope Hospital had two shared operating rooms and no endoscopy procedure rooms. (GHHS Ex. 5, 2001 CON application, p. 28; GHHS Ex. 1, CON application, p. 28.)
We hold that each of these findings is supported by substantial evidence in the record, as carefully documented by the Agency in its decision. These findings of fact in turn support the Agency’s conclusion that there were only two operating rooms at Good Hope at the time of the 2003 CON Application.
iv. Appellant Required to Comply with 2003 SMFP
We review de novo appellant’s contention that the Agency misapplied the law by requiring GHHS to comply with the no-need determination for operating rooms under the 2003 SMFP
Appellant had no rights to a third operating room under the 2001 Settlement Agreement. Good Hope had only two operating rooms. *554Thus, appellant has failed to demonstrate that the provisions of the 2003 SMFP and Criterion 1 did not apply to its 2003 CON application. We hold that the Agency did not err in subjecting appellant to the no-need determination of the 2003 SMFP.
v. Conformity with Criterion 1
It was appellant’s burden to demonstrate that its 2003 CON application was consistent with or not in conflict with Criterion 1. The Agency’s findings support its conclusion that the application was nonconforming with Criterion 1. Accordingly, we hold that the Agency did not err in concluding that appellant failed to meet its burden of demonstrating conformity with Criterion 1.
Appellants make no further argument regarding conformity with Criterion 1 other than those addressed above concerning its purported right to three operating rooms. Any additional assignments of error pertaining to Criterion 1 are deemed abandoned. N.C. R. App. P. 28(b)(6) (2007).
b. Criterion Three
i. Contentions of Appellant
Appellant contends that the Agency erred in applying N.C.G.S. § 131E-183(a)(3) (“Criterion 3”) because the “common numbering indicates that Criteria 3 and 3(a) are alternative and not independent criteria” and the 2003 CON application did not propose new services. In the alternative, appellant contends that the Agency erred in finding its 2003 CON application non-conforming with Criterion 3, in part because conformity with Policy AC-5 requires the Agency to recognize that the 2003 CON application established the need for the number and appropriate occupancy or utilization of acute care beds under Criterion 3.
ii. Mixed Question of Law and Fact
We review the Agency’s statutory interpretation and legal conclusions under a de novo standard of review. See Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85. However, we review the Agency’s findings of fact supporting its conclusions of law under a whole record test review. See Carroll, 358 N.C. at 659, 599 S.E.2d at 894-95. Where substantial evidence exists to justify the Agency’s decision, we may not substitute our judgment for the Agency’s as between two conflicting views. See Watkins, 358 N.C. at 199, 593 S.E.2d at 769.
*555iii. Criteria 3 and 3(a)
Criterion 3(a) requires the applicant to show that the needs of the population presently served will continue to be adequately met even though the applicant proposes to reduce or eliminate a service. See N.C.G.S. § 131E-183(a)(3a) (2003). Criterion 3 requires the applicant to show that the population that it proposes to serve has a need for the services offered, and the extent to which minority populations will have access to those services:
3. The applicant shall identify the population to be served by the proposed project, and shall demonstrate the need that this population has for the services proposed, and the extent to which all residents of the area, and, in particular, low income persons, racial and ethnic minorities, women, handicapped persons, the elderly, and other underserved groups are likely to have access to the services proposed.
N.C.G.S. § 131E-183(a)(3) (2003). As previously discussed, the burden rests with appellant to demonstrate that all of the CON review criteria have been met. See Presbyterian-Orthopaedic Hosp., 122 N.C. App. at 534, 470 S.E.2d at 834.
Appellant cites no authority for its argument that Criteria 3 and 3(a) are alternative criteria, and we have found none.
The Agency properly applied both Criteria 3 and 3(a) under the facts of this case because appellant proposed both to relocate and reduce the number of acute care beds and psychiatric beds, to which Criterion 3(a) applied, and to expand the various departments of the hospital, including ten observation beds and an operating room, to which Criterion 3 applied. The Agency found that appellant’s 2003 CON application was consistent with Criterion 3(a), but not with Criterion 3. For the reasons set forth in our discussion of Criterion 1, we reject appellant’s argument that it need not conform to Criterion 3 because it had rights to three operating rooms under the 2001 Settlement Agreement.
iv. Conformity with Criterion 3
Appellant argues that the Agency ignored public support and evidence in its 2003 CON Application and in Agency files that demonstrated conformity with Criterion 3. Under the appropriate standard of review, we first determine whether there was substantial evidence supporting the Agency’s findings related to Criterion 3, and, where *556substantial evidence exists, we cannot substitute our judgment for that of the Agency. See Total Renal Care, 171 N.C. App. at 739, 615 S.E.2d at 84.
The Agency found that GHHS had demonstrated the need to replace the existing facility, but had not adequately demonstrated that the population projected to be served needed the scope of services proposed by the application, then documented in detail its findings related to Criterion 3.
Despite historical declines in inpatient utilization, appellant projected double-digit inpatient utilization rate increases in 2005-2008 (19.5%, 20.68%, and 13.4%). These projections followed years of no change, decreases (-12.7% in 2000-2001, -6.7% in 2002-2003), and a single increase (10.5% in 2001-2002). The Final Agency Decision included these numbers in chart form, then made the following findings:
67. The evidence shows that, in' finding that GHHS had not justified these projected increase in utilization of its licensed acute care beds in the first three operating years of the new facility, the Agency found as follows:
The above projected increases in utilization were dependent on the applicant increasing its market share in the proposed service area through recruitment of additional physicians who GHHS predicted would increase the number of admissions above and beyond population growth.
GHHS did not provide current or projected market share data for existing facilities in the area to demonstrate the basis for its projected increase in admissions due to physician recruitment.
The- only market share data provided in the application is based on Good Hope’s discharges in FY 99 as reported to HCIA (see Exhibit 10).
GHHS assumed that the patient origin for the new replacement hospital would remain the same as historical patient origin even though the hospital is moving farther away from the population it currently serves in Sampson and Cumberland Counties. Since geographic access affects patient origin (or more simply put, the distance of the patient from the hospital helps determine to which hospital a patient will be sent), it was not reasonable to project the same patient origin *557or market share from these counties. There was no evidence to demonstrate that such an assumption would be reasonable in the circumstances of this project.
GHHS’s application projected that it would recruit 11 additional physicians and assumes an average of 86 to 97 admissions per year per physician. However, the application did not state any basis for assuming this number of patient admissions per new physician. (GHHS Ex. 2, Agency File, p. 1176-1176; Phillips, Tr. Vol. 6, p. 1780-1786; Hoffman, Tr. Vol. 16, pp. 4866-67.)
68. The application does not show any percentages of Harnett County patients who are now going to other hospitals, but who would come to Good Hope Hospital if it built a new hospital in Lillington. (Annis, Tr. Vol. 3, p. 997.)
69. The Agency found that GHHS did not adequately document in the application the reasonableness of its assumptions regarding increase in inpatient admissions. (GHHS Ex. 2, Agency File, p. 1176).
70. GHHS’ application cited and relied upon a physician recruitment plan to justify its projection of an increase in utilization, but did not include the recruitment plan. (GHHS Ex. 1, p. 63-64.) GHHS’ application projected a net increase of 11 admitting physicians to the staff by 2008. (Id.)
71. GHHS justified the projected increase in staff in part on the fact that GHHS [sic] had added 15 physicians to its staff in the past five years. (I'd) GHHS’ application, however, failed to show how many physicians it had lost during that same five year period. The projection implicitly assumed that GHHS would not lose any physician staff in the future. (Id.; Annis, Tr. Vol. 5, p. 1411; French, Tr. Vol. 12, p. 3559).
72. This assumption is unreasonable. The chart used in the application to describe the stable medical staff demonstrated that Good Hope had experienced a net loss of two medical professionals from the time of the 2001 CON application to the time of the 2003 CON application. (GHHS Ex. 1, p. 225; French, Tr. Vol. 12, p. 3561.)
73. ... GHHS’ application includes a projection that each physician will admit 85 to 100 patients per year. (GHHS Ex. 1, CON *558application, p. 64.) However, the application does not include the assumptions upon which this projection is based and provides no reasonable basis upon which the Agency may accept this assumption.
74. GHHS’s application does not identify which physicians are or will be admitting physicians. (French, Tr. Vol. 12, p. 3571.) There was no showing in the GHHS application that GHHS intended to retain any physicians as employees of the hospital. (Id.; French, Tr. Vol. 12, p. 3569).
We hold that each of these findings is supported by substantial evidence in the record, as carefully documented by the Agency in its Decision.
Although appellant did not include its physician recruitment plan in the 2003 CON application, the plan was offered as evidence by another party, and in its Decision, the Agency included the following findings related to the plan:
77. The physician recruitment plan referred to in the application was not included in the application. (Annis, Tr. Vol. 5, p. 1403.). The recruitment plan contains information that undercuts the assumptions used in the projections. GHHS’ physician recruitment plan, which GHHS cited as the basis for projections in the application, included the following statements:
With this relocation, mostly [sic] likely the residents of Dunn that would utilize Good Hope Hospital as opposed to Betsy Johnson Hospital will for a short time . . . continue to use Good Hope, but ultimately with medical staff change Dunn residents will depend more on Betsy Johnson Hospital. With this anticipated change, Good Hope will need to depend more on a new medical staff than it will upon those physicians holding privileges at both Good Hope and Betsy Johnson.
By 2006[,] of the currently active admitting physicians at Good Hope Hospital, almost 30 will be — have ages in the sixties and most likely either retired or limiting their practice in anticipation of retirement. Half this group will be past retirement age. This age group of physicians currently makes up more than 65 percent of the admissions at the hospital, including all admissions to the psychiatric service. . . . Annualizing FY03 activity indicated admissions this year continue a three-year decline. Inpatient activity is down over 20 *559percent from 2000 levels in part due to physician deaths and resignations. The heavy dependence on the more elderly physicians, recent physician deaths and resignations all combine to suggest the hospital is quickly approaching a crisis situation.
(CCH Ex. 10, p. 3; Annis, Tr. Vol. 5, pp. 1404-1411.)
78. GHHS did not contest the accuracy of the[] conclusions [in Finding of Fact no. 77],
The Agency indicated that GHHS’ omission of the recruitment plan, containing this information, “shows that the application omitted material facts of which GHHS was or should have been aware which would reduce the patient utilization that could reasonably be projected to arise from recruiting] new physicians.”
We hold that there was substantial evidence to support the Agency’s findings regarding non-conformity with Criterion 3. These findings support the Agency’s conclusion that appellant failed to meet its burden of demonstrating conformity with Criterion 3.
We find no error in the Agency’s interpretation of Criterion 3 to require the applicant to demonstrate that the proposal and all its components, not just the number of replacement beds,1 are needed by the particular population that the applicant seeks to serve. As noted above, because the Agency’s findings are supported by substantial evidence and those findings support its conclusions of law regarding Criterion 3, the Agency did not err in concluding that it was non-conforming with Criterion 3.
3. The Agency Acted Within Its Authority
We hold that the Agency’s interpretation of its enabling statutes is reasonable and due “some deference.” Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85. The Agency demonstrated great thoroughness in its consideration, and we find no flaws in its reasoning. Britthaven, 118 N.C. App. at 384, 455 S.E.2d at 460; Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85. Its rulings in this matter are consistent with its earlier rulings involving these parties. Id. Accordingly, we hold that the Agency did not exceed its authority in *560finding appellant’s application non-conforming with Criteria 1 and 3, see Watkins, 358 N.C. at 199, 593 S.E.2d at 769, and that the Agency’s decision has a rational basis in the evidence. Hospital Group of Western N.C., 76 N.C. App. at 268, 332 S.E.2d at 751.
The burden rests with appellant to demonstrate that all of the CON review criteria have been met. See Presbyterian-Orthopaedic Hosp., 122 N.C. App. at 534, 470 S.E.2d at 834. Given our holdings regarding Criteria 1 and 3, we need not reach appellants’ arguments as to criteria 4, 5, 6, 12, or 18a.
This argument is without merit.
B. Agency Review of the GHHS Proposal
In their second argument, appellants contend that the Agency exceeded its authority by requesting evidence demonstrating the reasonableness of the design, size, and cost of the replacement facility outside the scope of the CON statute, disregarding certain CON licensure rules, relying upon unpromulgated rules to secure information not required by statute, and disregarding evidence contained in the 2003 CON application and Agency files that demonstrated the reasonableness of its proposal. We disagree.
1. Agency Authority under the CON Statute
Appellants first contend that the language in N.C.G.S. § 131E-182(b) precludes the Agency from asking for justification for the great increase in square footage and cost in the 2003 CON application when appellant was required to file a new CON application and precluded from exemption of a CON review. See Good Hope Hosp., Inc. v. N.C. Dep’t of Health & Human Servs., 175 N.C. App. 309, 623 S.E.2d 315, rev. denied, cert. denied, 360 N.C. 480, 632 S.E.2d 172, aff’d per curiam, 360 N.C. 641, 636 S.E.2d 564 (2006). Appellants contend that the Agency relied upon “unpromulgated rules” to circumvent the statutory provisions by requiring market share data, projections of admissions in physician’s letters, and particularized square footage requirements by department to demonstrate conformity with the statutory criteria.
Appellants maintain that the scope of the Agency’s authority is limited to that under N.C.G.S. § 131E-182(b), which states:
An applicant shall be required to furnish only that information necessary to determine whether the.proposed new institu*561tional health service is consistent with the review criteria implemented under G.S. 131E-183 and with duly adopted standards, plans and criteria.
N.C.G.S. § 131E-182(b) (2003). However, N.C.G.S. § 131E-183(a)(4) states “[w]here alternative methods of meeting the needs for the proposed project exist, the applicant shall demonstrate that the least costly or most effective alternative has been proposed.” N.C.G.S. § 131E-183(a)(4) (2003).
Good Hope notified the Agency in May 2003 that it was “pursuing legitimate, alternative avenues to obtain any needed government approvals of its replacement hospital project.” Good Hope has not relinquished its 2001 CON for a 61,788 square foot replacement facility, maintaining that if the 2003 CON application were not approved, it would “consider at that time whether to reopen the declaratory ruling appeal, to continue to develop [the 2001 CON] or to pursue appeal” of the 2003 CON application. Appellant and Good Hope together represented to the Agency in the November 2002 request for a “good cause” transfer that their proposal for a single-story, slightly enlarged facility was the “least costly and most effective” alternative. Upon the unique facts of this case, we hold that the request for evidence explaining the vast difference in size and cost between the 2001 CON, the 2002 proposal, and the 2003 CON application was within the Agency’s statutory authority. See N.C.G.S. § 131E-183(a)(4).
2. Appellant’s Burden to Show Compliance
. Appellants next contend that, because appellant provided all the information requested by the application form, as well as a chart comparing categories of space between the 2001 and 2003 CON applications and reasons for the differences, the Agency’s determination that it was non-conforming should be set aside as improperly based upon unpromulgated rules.
Specifically, appellants contend that the 2003 CON application demonstrated the reasonableness of the size and cost of the proposed replacement hospital and supported the ALJ’s findings of conformity with Criteria 3, 4, 5, 6, 12, and 18a. As appellants’ argument does not address Criterion 1, and we have already addressed the Agency’s conclusion that the 2003 CON application was non-conforming with Criterion 1, we need not address these arguments.
*5623.Snace Required bv Licensure Regulations
Appellants next argue that the Agency erred by disregarding its own licensure rules and that the Agency “penalized” appellant for not explaining the need for space that is required by the Agency’s own licensure requirements.
Appellants cite no authority for these propositions. Failure to cite authority is a violation of N.C. R. App. P. 28(b)(6) and subjects this argument to dismissal. Atchley Grading Co. v. W. Cabarrus Church, 148 N.C. App. 211, 212-13, 557 S.E.2d 188, 189 (2001); Wilson v. Wilson, 134 N.C. App. 642, 643, 518 S.E.2d 255, 256 (1999).
4.Evidence from the Agency’s Files
Finally, appellants argue that the Agency disregarded evidence in its own files showing that appellant’s proposal was reasonable compared to other hospital construction projects. The Chief of the Certificate of Need section testified in great detail as to why cost comparisons between the proposed project and other replacement hospitals were not particularly relevant to the reasonableness of the size and cost outlined in the 2003 CON application. Such testimony provides a rational basis for the Agency’s disregard of such evidence.
5.Non-Conformitv with Statutory Criteria
Accordingly, we conclude that the Agency did not exceed its authority in determining that appellant failed to demonstrate that its application met the CON review criteria. See Presbyterian-Orthopaedic Hosp., 122 N.C. App. at 534, 470 S.E.2d at 834.
This argument is without merit.
C. N.C.G.S. § 131E-18B: The Public Hearing
In their third argument, appellants contend that the Agency violated N.C.G.S. § 131E-185 by failing to consider written comments and oral arguments made at a public hearing pertaining to the 2003 CON application. We disagree.
We review this argument de novo as a matter of statutory interpretation. See Britthaven, 118 N.C. App. at 384, 455 S.E.2d at 460; Total Renal Care, 171 N.C. App. at 740, 615 S.E.2d at 85. Specific findings are not required on each piece of evidence presented. See Flanders v. Gabriel, 110 N.C. App. 438, 440, 429 S.E.2d 611, 612 (1993) (stating that the tribunal “need only find those facts which are material to the resolution of the dispute”).
*563N.C.G.S. § 131E-185 sets forth procedures and requirements for the CON review process, allowing any interested party to submit written comments or make oral comments at the scheduled public hearing. The provisions of N.C.G.S. § 131E-185 provide no support for appellants’ conclusion that because the Agency denied appellant’s CON application, and there were arguments made at the public hearing in favor of its application, ergo the Agency failed to consider those comments. There was evidence before the Agency that many of those who spoke in favor of the proposed hospital were unfamiliar with the relevant criteria, the 2003 CON application, or the CON review process.
Under N.C.G.S. §§ 131E-175 et seq., the Agency’s obligation is to hear the public’s arguments, whether in favor of or opposed to an application, then decide, in light of all the evidence before it, whether appellant has met its burden of proving that the relevant statutory review criteria have been met. Public support is not one of those criteria. See N.C.G.S. §§ 131E-183(a). The Agency may hear comments supporting an application yet find that the burden of satisfying the CON criteria has not been met. We hold that the Agency’s application of the statute is without error. See Britthaven, 118 N.C. App. at 384, 455 S.E.2d at 460..
This argument is without merit.
D. Constitutionality of the Agency’s Action
In their fourth argument, appellants contend that the Agency unconstitutionally applied the CON review criteria, thus violating appellant’s substantive due process rights. We disagree.
Appellants argue that the Agency’s “improper” denial of the 2003 CON application deprives them of a “vested right” to continue operating as a hospital. We find appellants’ reliance upon a September 2003 Agency survey to be untimely as it occurred after the Agency’s initial review. The record that was before the Agency is silent on the issue of non-compliance. Moreover, the issue of appellant’s exemption request was resolved in the Agency’s favor, and the 2003 declaratory ruling that resolved the issue of appellant’s rights to a transfer of the existing CON has not been overturned on appeal. Good Hope is not a party to this appeal, and the record provides no support for appellant’s claim that its rights have been constitutionally infringed.
This argument is without merit.
*564VI. Conclusion
On remand, this Court was directed by the Supreme Court to review this case “on the merits.” Good Hope Health Sys., L.L.C. v. N.C. Dep’t of Health & Human Servs., 360 N.C. 635, 637, 637 S.E.2d 517, 518 (2006). Had the Supreme Court intended for this Court to reverse the decision of the Agency based upon treating GHHS’ application as a modification under N.C. Gen. Stat. § 131E-176(16)(e), it would have simply adopted Judge Tyson’s dissent. The Supreme Court did not do this. Id.
This case has been reviewed upon the arguments presented and the -voluminous record in this case, and not by construing statements of counsel in oral arguments as “stipulations.”
The Agency did not err in its conclusion that appellant failed to carry its burden of demonstrating compliance with the relevant statutory review criteria. See Presbyterian-Orthopaedic Hosp., 122 N.C. App. at 534-35, 470 S.E.2d at 834. Accordingly, we conclude that the Agency did not err in the Final Agency Decision by concluding as a matter of law that appellant should be denied a certificate of need. Id. The Final Agency Decision is affirmed.
Having thoroughly reviewed the record before the Agency, we' find appellants’ remaining arguments to be without merit. Further, assignments of error listed in the record but not argued in appellants’ brief or for which no authority is cited are deemed abandoned. N.C. R. App. P. 28(b)(6) (2007).
Because we affirm the Final Agency Decision, we need not address the Agency’s or respondent-intervenor Betsy Johnson’s cross-assignments of error. N.C. R. App. P. 10(d) (2007); see also Carawan v. Tate, 304 N.C. 696, 701, 286 S.E.2d 99, 102 (1982).
AFFIRMED.
Judge GEER concurs. Judge TYSON dissents.. Without citing any authority, appellant argues that the Agency’s finding of conformity with Policy AC-5 of the 2003 SMFP renders its finding of non-conformity with Criterion 3 (as well as Criteria 5, 6, and 18(a)) erroneous as a matter of law. Appellant contends that conformity with Policy AC-5 establishes the need for the number of acute care beds proposed in the 2003 CON Application.