Mullen Lumber Co. v. Lore

Nolan, J.

This appeal presents issues regarding the interpretation of G. L. c. 254, §§ 4, 8, & 11 (1986 ed.), statutes governing mechanic’s liens.

1. Facts. The plaintiff, Mullen Lumber Co., Inc. (Mullen), entered into a contract dated July 2, 1986, to supply building materials to one of the original defendants, Nordberg-Kelley Corporation1 (Nordberg), to be used in constructing a house in *751Norwood for the other defendant, Andrew Lore (Lore). On August 29, 1986, Mullen filed notice of this contract in the registry of deeds to record a mechanic’s lien on the house as provided by G. L. c. 254, § 4. Lore received a copy of this notice. The contract completion date for the construction of Lore’s house, specified in the notice was February 25, 1987, the same completion date specified in the materials contract between Mullen and Nordberg. On December 5, 1986, Mullen recorded a statement of account, specifying both the amount due on the contract, $19,466.12, and the supplies provided as required by G. L. c. 254, § 8, in order to preserve the mechanic’s lien on the property. Mullen took no further action regarding this statement of account.

On or about February 18, 1987, one week before the specified contract completion date, Mullen recorded a second statement in the same amount and for the same supplies detailed in the earlier recorded statement. Mullen also filed its complaint on February 18, 1987, asserting the existence of the lien and seeking its enforcement by sale of Lore’s house.

The parties filed cross motions for summary judgment. The trial judge granted Mullen’s motion, determining that Mullen had an enforceable mechanic’s lien against Lore’s property. Lore then appealed to the Appeals Court, challenging both the denial of his motion for summary judgment and the allowance of Mullen’s motion. The Appeals Court reversed and ordered that judgment be entered dismissing the action as to Lore. 26 Mass. App. Ct. 364 (1988).

We granted Mullen’s application for further appellate review to consider (1) whether a statement of account filed prior to the stated contract completion date will preserve a lien created under G. L. c. 254, § 4 (an issue the Appeals Court did not reach) and (2) if it does, whether, if a person files a statement of account prior to the contract completion date but fails to commence an enforcement action within sixty days, that person may file a second statement of account so as to trigger a new sixty-*752day period within which to commence an action (an issue that the Appeals Court decided against Mullen).2

2. Statutory framework. The mechanic’s lien statute comprises a comprehensive scheme which compels strict compliance in order to obtain relief. Savoie Quarry & Constr. Co. v. Ziman, 234 Mass. 210, 214 (1919). Individual sections of the statute establish the time limitations and other requirements necessary to preserve and to enforce the lien. G. L. c. 254, §§ 4, 8, 11. General Laws c. 254, § 4, requires the filing of a notice of contract, § 8 requires the filing of a statement of account, and § 11 requires commencement of an action to enforce.3 Although not every procedural mistake is fatal, Val*753entine Lumber & Supply Co. v. Thibeault, 336 Mass. 411, 413 (1957), failure to comply normally results in dissolution of the lien, see Blount Bros. v. Lafayette Place Assocs., 399 Mass. 632 (1987), or in failure of the lien to attach, Street Lumber Co. v. Sullivan, 201 Mass. 484 (1909).

3. Filing before contract completion date. We turn now to the issue left undecided by the Appeals Court, namely, whether a statement of account, filed before the contract completion date, constitutes a legal nullity. We consider this issue, although doing so is no more necessary to our decision than it was to the Appeals Court’s decision, because the issue is an important one to people interested in the operation of the statutes governing mechanics’ liens and should not be left unresolved. The parties rely on cases from other jurisdictions to support their positions, yet we need not look beyond our own case law and the statute’s legislative history to resolve this controversy.

*754Lore first asserts that the provisions of § 11 cause a lien created under § 4 to dissolve “unless a civil action to enforce it is commenced within sixty days after the filing of the statement required by section eight.” G. L. c. 254, § 11 (1986 ed.). Lore next contends that the only statement of account acceptable under § 8 is a filing made within the thirty days after the contract completion date specified in the notice of contract filed under § 4. From this, Lore argues that the completion date in the notice of contract is the exclusive date from which the statute of limitations may commence to run and that the earlier filings have no legal effect. We disagree.

The question is whether the filing of a statement of account before the date on which the contract of the subcontractor is to be performed meets the statutory requirement that the statement be filed “within thirty days after the date on which the contract ... is to be performed.”4 The following discussion demonstrates that the Legislature’s intention is satisfied by a filing made before the date that the contract is to be performed.

In 1914, the Legislature appointed a special commission to consider and recommend changes in the laws concerning mechanic’s liens. Res. 1914, c. 121. See Blount Bros. v. Lafayette Place Assocs., supra at 636. It is obvious from the special commission’s report that no effective system existed at the time for notifying purchasers or mortgagors of the existence of a lien and for determining when such a lien would end. Extract from the Report of the Special Commission Appointed to Consider and Recommend Changes in the Laws Relative to Liens, Mortgages, and Tax Titles, 1 Mass. L.Q. 344, 348-349 (No. 4, 1916). The special commission thus urged the Legislature to require the filing of a notice of contract, including the completion date, to aid in providing third parties with notice of encumbrances existing on the property and when such encumbrances would dissolve. Id. Pratt & Forest Co. v. Strand Realty Co. of Lowell, 233 Mass. 314, 317-318 (1919). *755The special commission also suggested that subcontractors should be required to abide by and be afforded the protection of these laws. Extract from the Report of the Special Commission, supra at 349.

In 1915, the mechanic’s lien statute underwent substantial revision and the Legislature adopted many of the special commission’s recommendations. See Blount Bros., supra. In 1918, the predecessor to § 8 was further amended to include the language at issue here, that the lien “shall be dissolved unless the sub-contractor . . . [files a statement of account] within thirty days after the date on which the contract of said sub-contractor is to be performed.” St. 1918, c. 265, § 3. The question presented here is what effect, if any, should be given to a statement filed before the specified contract termination date. It is clear that, before the amendments, a contractor could file the statement once all labor and materials had been furnished and did not have to wait until the contract completion date had passed. General Fire Extinguisher Co. v. Chaplin, 183 Mass. 375, 376 (1903).

The interpretation advanced by Lore and discussed by the dissent protects no legitimate interests of the owner and would effectively penalize subcontractors who complete performance early by preventing them from taking immediate action to enforce their liens. Cf. Hammill-McCormick Assocs. v. New England Tel. & Tel. Co., 399 Mass. 541, 545-546 (1987) (interpreting G. L. c. 254, § 4, to permit subcontractor to file notice of contract after performance completed, but prior to completion date specified in contract). The contract completion date is not the “linchpin of the statutory framework.” Post at 762. Rather, it appears that the statute establishes the latest time at which a lien could be enforced and does not preclude earlier enforcement.5 Indeed, an interpretation permitting early filing of the statement of account promotes the purposes of the *756statutory scheme by putting third parties on notice at an earlier time as to the amount of the lien.6 It also apprises them that the encumbrance will dissolve unless an action to enforce is brought within sixty days after the filing of the statement. See G. L. c. 254, § 11. Accordingly, we see no reason to prohibit the filing of a statement of account before the specified contract completion date when the subcontractor has finished providing the supplies or labor before the specified contract completion date. See Massachusetts Gas & Elec. Light Supply Co. v. Rugo Constr. Co., 321 Mass. 20, 23 (1947) (interpreting § 8 to require subcontractors to file sworn statement after completion of work or after last materials supplied).

4. Filing of a second statement of account. We must next consider the effect of filing á second statement of account for the same supplies before the contract completion date. We conclude that the filing of the second statement of account had no legal effect. Mullen’s first statement was filed on December 5, 1986. The statutory period for enforcing the lien expired on February 3, 1987. G. L. c. 254, § 11. If we were to reach a contrary result, as suggested by the dissent, we would afford the subcontractor a period greater than sixty days in which to commence an enforcement action, a result we believe unintended by the Legislature. Although, as we concluded above, the filing of a statement of account before the contract completion date does not, standing alone, defeat Mullen’s claim for relief, Mullen’s failure to commence an action within the statutory time period reckoned from the first filing proved fatal and, by the terms of the statute, caused the lien to dissolve. Id. There can be but one lien for the materials supplied and the filing of a second statement of account concerning the same materials neither extends the statutory period nor revives the *757lien if the statutory period has passed. See Hilliard v. Allen, 4 Cush. 532, 535-536 (1849).

5. Conclusion. The judgment entered against the defendant Lore is reversed and a new judgment is to be entered dismissing the action as to him.

So ordered.

Nordberg-Kelley Corporation originally was a party to this action in the trial court. The trial judge, however, pursuant to Mass. R. Civ. P. 54 (b), *751365 Mass. 820 (1974), entered a separate judgment against Lore, as Nordberg had filed for liquidation in bankruptcy under c. 7 of the Bankruptcy Code. Nordberg-Kelley is not a party to this appeal.

Lore also argues that no written contract existed between the parties for the purposes of establishing a lien under G. L. c. 254, § 4. This argument was not presented in the trial court and, indeed, as implicitly conceded by Lore in his motion for summary judgment, there was no dispute as to the existence of a written contract. Accordingly, the argument has not been properly preserved for our consideration and no circumstances exist which prompt us to review a question not passed upon by the court below. See Albert v. Municipal Court of the City of Boston, 388 Mass. 491, 494 (1983).

General Laws c. 254, § 4 (1986 ed.), states in pertinent part:

“Whoever, subsequent to the date of the original contract, furnishes labor or material, or both labor and material, or performs labor, under a written contract with a contractor, or with a sub-contractor of such contractor, may file in the registry of deeds for the county or district where such land lies a notice of his contract substantially in the following form:

“Notice is hereby given that by virtue of a written contract dated _, between _, contractor (or sub-contractor), and _ said_is to furnish or has furnished labor or material, or both labor and material, or perform labor in the erection, alteration, repair or removal of a building or structure by-, contractor, for_, owner, on lot of land described as follows:

“Said contract is to be completed on or before--

“A notice of any extension of such contract, stating the date to which it is extended, shall also be filed or recorded in said registry prior to the date stated in the notice of the contract for the completion thereof.

“Upon filing a notice, as hereinbefore provided, and giving actual notice to the owner of such filing, the sub-contractor shall have a lien to secure the payment of all labor and material, which he is to furnish or has furnished upon the building or structure, and upon the interest of the owner, as appears of record at the time of such filing, in the lot of land on which said building or structure is situated. But such lien shall in no event exceed the amount due or to become due under the original contract when notice of the filing *753of the sub-contract is given by the sub-contractor to the owner; and the time for the performance of the contract of the sub-contractor shall not be extended beyond the time for the performance of the original contract and any extension thereof, if the objection thereto of the owner is filed in the registry of deeds and actual notice of such objection is given by the owner to the sub-contractor within five days after the owner received notice of the filing of the contract as provided in this section.”

General Laws c. 254, § 8 (1986 ed.), provides in pertinent part that: “A lien under section four shall be dissolved unless the sub-contractor, or some person claiming by, through or under him, shall, within thirty days after the date on which the contract of said sub-contractor is to be performed, file in the registry of deeds in the county or district where the land lies a statement, signed and sworn to by him, or by some person in his behalf, giving a just and true account of the amount due him, with all just credits, a brief description of the property, and the names of the owners as set forth in the contract.”

General Laws c. 254, § 11, reads in its entirety: “The lien shall be dissolved unless a civil action to enforce it is commenced within sixty days after the filing of the statement required by section eight. The validity of the lien shall not be affected by an inaccuracy in the description of the property to which it attaches, if the description is sufficient to identify the property, or by an inaccuracy in stating the amount due for labor or material unless it is shown that the person filing the statement has wilfully and knowingly claimed more than is due him.”

The dissent fails to address the difference in the language between § 4 and that of § 8. The language of § 4 refers to the date the contract “is to be completed” whereas the language of § 8 refers to “the date on which the contract ... is to be performed.” G. L. c. 254, §§ 4, 8.

Cases from other jurisdictions cited in the dissent are governed by statutes dissimilar to our statutes. These cases speak of filing a “notice of lien,” or a “notice of intention to claim a lien.” See post at 760. The Massachusetts statutes recognize only the filing of a notice of contract and a statement of account. Our law provides for the creation of a single lien.

The dissent maintains that, as a result of our decision today, interested third parties and property owners will suffer because “subcontractors will be careful not to file early statements of account.” Post at 761. Quite to the contrary, a subcontractor whose performance is complete will be encouraged to file early and enforce its claim instead of waiting until the contract performance date has passed.