Dechio v. Raymark Industries, Inc.

Opinion

WEST, J.

This case presents an issue of first impression for this court regarding the time limitation for appeal from a decision of a workers’ compensation commissioner (commissioner) to the compensation review board (board) by the second injury fund (fund) under General Statutes § 31-301.1 Essentially we must answer this question: Is an appeal taken from a supplemental order directing the fund to compensate a plaintiff a timely appeal challenging the findings and awards preceding that order if that appeal was taken outside the mandated twenty days from the issuing of the operative finding and award? For the reasons we will state, we conclude that in the circumstances present here, such an appeal is not timely.

*60The following background provides the necessary context for our resolution of this issue. Although the fund became a part of our workers’ compensation statutory scheme during World War II, essentially for the purpose of enticing employers to hire returning disabled war veterans, the legislature has, in the intervening years, altered the fund’s statutory parameters.2 At present, the fund’s essential purpose is “to provide compensation for an injured [plaintiff] when the employer fails to pay.” Matey v. Estate of Dember, 256 Conn. 456, 486, 774 A.2d 113 (2001). For the fund to fulfill this purpose, a supplemental order must issue from a commissioner directing the fund to make payment to a plaintiff.3 Under our workers’ compensation statutory framework, the “prerequisites to an order [issuing from a commissioner] to the fund to make payment [to a plaintiff] are that: (1) the substantive and procedural requirements of the [workers’ compensation] act have been met; (2) an award against the employer has been entered; and (3) the employer and its insurer have failed to pay.” Id., 487-88. Only when these prerequisites—a finding and award properly entered against an employer and an employer’s or insurer’s failure to pay—have been satisfied, may a commissioner issue a supplemental order directing the fund to compensate a plaintiff in accordance with General Statutes § 31-355.4

*61The fund’s appeal concerns the timeliness of its petition for review by the board from a supplemental order issued on October 25, 2006, by the commissioner for the fifth district, Amado J. Vargas, directing the fund to make such payment to the plaintiff, Lovie Dechio, in accordance with § 31-355. Specifically, the fund appeals from the board’s granting of the plaintiffs motion to dismiss the fund’s petition for review of the commissioner’s supplemental order as untimely. In Stec v. Raymark Industries, Inc., 114 Conn. App. 81, 968 A.2d 960 (2009),5 we concluded that § 31-301 (a) does not limit the board’s subject matter jurisdiction to hear a late appeal but, rather, provides the board with discretion to hear a late appeal when no timely motion to dismiss has been filed. Essentially, the issue we are presented with, therefore, is whether, under the circumstances, the plaintiffs motion to dismiss the fund’s appeal to the board was a timely filed motion objecting properly to a late appeal by the fund. The questions we must address, therefore, concern the timeliness of both the fund’s petition for review and the plaintiffs motion to dismiss. For the reasons indicated, we conclude that the fund’s petition for review was untimely and that the plaintiffs motion to dismiss was timely. Therefore, the board properly dismissed the fund’s appeal.

A review of the prolonged procedural history of the underlying claim is essential to the resolution of the *62fund’s appeal. On December 12, 1981, Peter Dechio, a retired, longtime blue collar worker for Raymark Industries Inc. (Raymark),6 died from complications resulting from lung cancer. Peter Dechio was the plaintiffs husband of nearly forty years at the time of his death. On June 24, 1988, the commission rendered a finding and award that found, inter alia, that Peter Dechio died as a result of his exposure to asbestos arising out of and during the course of his employment with Raymark and that his wife was entitled to benefits from his date of death until her death or remarriage pursuant to General Statutes § 31-306.7 The commissioner ordered Raymark to pay those benefits and stated that a hearing would be held to determine Peter Dechio’s average weekly wage. In 1988, Raymark entered involuntary bankruptcy, from which it briefly emerged in 1996. As a result, hearings on the compensation rate were not held until August and September, 1997. A decision was not reached, however, because Raymark entered voluntary bankruptcy in March, 1998, again putting a halt to the proceedings.

The plaintiff then sought relief from the automatic stay provisions of federal bankruptcy law8 so as to allow her to pursue payment from the fund under § 31-355. On June 29,2000, the plaintiff received an order from the *63Bankruptcy Court granting her relief from the automatic stay, which, in turn, allowed her to pursue her workers’ compensation claim. In 2002, the fund was cited into the proceedings because of its potential liability under § 31-355. Also cited into the proceedings as defendants were Zurich North America Insurance Company (Zurich), The Hartford Insurance Group (The Hartford), General Reinsurance Group (General Reinsurance) and the Connecticut Insurance Guarantee Association (association).9 Multiple formal hearings over the subsequent months10 formed the basis of the September 30, 2005 finding and award issued by Commissioner Vargas. In this finding and award, the commissioner found, among other things, that the “June 24, 1988 finding and award was proper in all respects and [that] the commissioner had the jurisdiction and authority to hear and rule on the claim.” He also found that there was no credible evidence that Zurich or The Hartford had insured Raymark’s blue collar, manufacturing employees and dismissed the fund’s claims against each of them. He also found, in regard to the association, that pursuant to General Statutes § 38a-838 (6), the claim was not a covered claim, nor did the commission have jurisdiction to determine the association’s liability. The commissioner also dismissed the fund’s claims against General Reinsurance, finding that the commission lacked the authority and jurisdiction to interpret the contract between General Reinsurance and Raymark.

*64The commissioner also found that, at that time, he was precluded from issuing a supplemental order against the fund because, he reasoned, an order must first be issued against Raymark, as the employer of record. Such an order, however, could not be issued, the commissioner found, because of Raymark’s bankruptcy status. The commissioner, however, left open the option of issuing a subsequent order against Raymark if it emerged from bankruptcy or if another relief from automatic stay was issued directly against Raymark by the Bankruptcy Court. Following either of those events, the commissioner could issue a supplemental order against the fund. The commissioner also found Peter Dechio’s average weekly wage adjusted for cost of living increases to be $337.22 and the resultant statutory compensation rate due the plaintiff to be $224.93.11

On December 23,2005, the Bankruptcy Court granted the plaintiffs motion for relief from the automatic stay and ordered Raymark’s automatic stay lifted so as to allow the plaintiff to seek an order directly against Raymark pursuant to the commissioner’s September 30, 2005 finding and award.12 In his September 29, 2006 finding and award, the commissioner directed Raymark *65to pay all the benefits due the plaintiff under the September 30, 2005 finding and award. He also ratified and made applicable to the fund the June 24, 1988 and September 30, 2005 findings and awards. The order issued against Raymark went unpaid. On October 25, 2006, the commissioner issued a supplemental order directing the fund to pay the plaintiff pursuant to § 31-355. On November 14, 2006, the fund filed a petition for review with the board. On November 20, 2006, the plaintiff filed a motion to dismiss the fund’s petition for review.13 In its November 28, 2007 opinion, the board granted the plaintiffs motion to dismiss, and this appeal timely followed. Further facts will be put forth as necessary.

“As a threshold matter, we set forth the standard of review applicable to workers’ compensation appeals. ... It is well established that [although not dispositive, we accord great weight to the construction given to the workers’ compensation statutes by the commissioner and [the] board. ... A state agency is not entitled, however, to special deference when its determination of a question of law has not previously been subject to judicial scrutiny. . . . Whe[n] ... [a workers’ compensation] appeal involves an issue of statutory construction that has not yet been subjected to judicial scrutiny, this court has plenary power to review the administrative decision.” (Internal quotation marks omitted.) Kuehl v. Z-Loda Systems Engineering, Inc., 265 Conn. 525, 532, 829 A.2d 818 (2003).

Whether § 31-301 precludes the fund from timely appealing from the supplemental order directing it to compensate the plaintiff in the present case “raises a question of statutory construction, which is a [question] of law, over which we exercise plenary review. . . . *66The process of statutory interpretation involves the determination of the meaning of the statutory language as applied to the facts of the case, including the question of whether the language does so apply. . . .

“When construing a statute, [o]ur fundamental objective is to ascertain and give effect to the apparent intent of the legislature. ... In other words, we seek to determine, in a reasoned manner, the meaning of the statutory language as applied to the facts of [the] case, including the question of whether the language actually does apply. ... In seeking to determine that meaning, General Statutes § l-2z directs us first to consider the text of the statute itself and its relationship to other statutes. If, after examining such text and considering such relationship, the meaning of such text is plain and unambiguous and does not yield absurd or unworkable results, extratextua! evidence of the meaning of the statute shall not be considered. . . . The test to determine ambiguity is whether the statute, when read in context, is susceptible to more than one reasonable interpretation.” (Internal quotation marks omitted.) Hees v. Burke Construction, Inc., 290 Conn. 1, 10, 961 A.2d 373 (2009).

Our analysis begins, therefore, with the language of the relevant provisions. General Statutes § 31-301 (a)14 provides in relevant part that “[a]t any time within twenty days after entry of an award by the commissioner, after a decision of the commissioner upon a motion or after an order by the commissioner according *67to the provisions of section 31-299b, either party may appeal therefrom to the Compensation Review Board . . . .” Section 31-301 (e) provides further that “[t]he procedure in appealing from an award of the commissioner shall be the same as the procedure employed in an appeal from the Superior Court to the Supreme Court, where applicable. . . .” Last, we note the mandate of General Statutes § 31-300 that “[i]f no appeal from the decision is taken by either party within twenty days thereafter, such award shall be final and may be enforced in the same manner as a judgment of the Superior Court. ...”

In resolving this issue, “we are mindful that the [workers’ compensation] act indisputably is a remedial statute that should be construed generously to accomplish its purpose. . . . The humanitarian and remedial purposes of the act counsel against an overly narrow construction that unduly limits eligibility for workers’ compensation. . . . Accordingly, [i]n construing workers’ compensation law, we must resolve statutory ambiguities or lacunae in a manner that will further the remedial purpose of the act. . . . [T]he purposes of the act itself are best served by allowing the remedial legislation a reasonable sphere of operation considering those purposes.” (Internal quotation marks omitted.) Deschenes v. Transco, Inc., 288 Conn. 303, 314-15, 953 A.2d 13 (2008). With these precepts in mind, we turn to the matter under review.

At issue here is the timeliness of the fund’s appeal to the board from the commissioner’s supplemental order directing it to compensate the plaintiff. Prior to and leading to that order, there were three separate findings and awards issued by commissioners in this case: the first was issued by the commissioner for the fourth district, Frank J. Verrilli, on June 24, 1988, who found, inter alia, that the plaintiff was entitled to workers’ compensation benefits under General Statutes *68(Rev. to 1989) § 31-301;15 the second was issued on September 30,2005;16 and the last was issued on September 29, 2006. Although it is reasonable that the fund would not have immediately appealed from the finding and award issued in 1988 in which it was not involved, the fund, though cited into the matter in 2002, failed to appeal timely from either of the subsequent findings and awards even though it admitted before this court during oral argument that it had a “bone to pick” with each finding and award upon issuance. The fund also did not attempt to preserve its right to appeal from either finding and award rendered after it was cited into the proceedings by filing with the commissioner notice of intent to appeal as prescribed under Practice Book § 61-5.17 The fund now contends that because no order was specifically issued against it until October 25, 2006, it can challenge the order itself and, in so doing, assail each of the preceding findings and awards through its appeal from that order. We disagree.

Our Supreme Court has stated that “[i]t has long been accepted that a system of laws upon which individuals, *69governments and organizations rely to resolve disputes is dependent upon according finality to judicial decisions. ... [A] party should not be able to relitigate a matter which it already has had an opportunity to litigate. . . . Stability in judgments grants to parties and others the certainty in the management of their affairs which results when a controversy is finally laid to rest.” (Citation omitted; internal quotation marks omitted.) Marone v. Waterbury, 244 Conn. 1, 11, 707 A.2d 725 (1998). The court concluded that “[principles of finality are equally applicable to administrative decisions, such as workers’ compensation awards, that are appealable .... Both employers and their injured employees must be able to depend on the finality of administrative decisions and the appeals taken therefrom in order to regulate their future behavior.” Id., 12-13. Furthermore, “ [w]hether a judgment is final depends upon the governing statute[s].” Id., 12. Also, “while workers’ compensation awards may bear some resemblance to interlocutory decrees, [however] that similarity does not mean that such an award is, in fact, interlocutory. For example, a workers’ compensation award conclusively establishes the employer’s liability and precludes relitigation of that issue in a subsequent action brought in a court of general jurisdiction.” Id., 13-14.

In this appeal, we are presented with a procedural posture that is the converse, in a sense, of the usual scenario in which the finality of a commissioner’s decision is examined for a determination of whether that decision is a final judgment for the purposes of an appeal. Generally, these questions of finality arise in a context involving issues revolving around a subsequent necessary remand of an award from the board to the commissioner. See Hunt v. Naugatuck, 273 Conn. 97, 104, 868 A.2d 54 (2005) (when remand of matter to commissioner for further proceedings necessary, finality of board’s decision called into question). In this *70appeal, we are faced with the same questions of finality involving not a remand but a then prospective decision of the commissioner that has since occurred—the issuance of the supplemental order directing the fund to compensate the plaintiff. Levarge v. General Dynamics Corp., 282 Conn. 386, 390, 920 A.2d 996 (2007), a workers’ compensation case, though interpreting General Statutes §§ 31-301a and 31-301b, concisely sets out the usual context when such issues arise and the method utilized in resolving those issues and is instructive for our purposes.

In Levarge, the issue was “whether the decision of the . . . board . . . which affirmed the decision of the . . . commissioner that the defendants were collaterally estopped from relitigating the issue of causation, constitutes a final judgment or an otherwise appealable interlocutory order, thereby impheating [the court’s] subject matter jurisdiction.” Levarge v. Dynamics Corp., supra, 282 Conn. 387. After relating the facts and circumstances present, the court set forth the governing legal principles. Id., 390. The court stated that “the Appellate Court’s review of disputed claims of law and fact ordinarily must await the rendering of a final judgment by the [board]. . . . When the remand of a matter to the commissioner for further proceedings is necessary, the finality of the board’s decision is called into question .... In such circumstances, [t]he test that determines whether such a decision is a final judgment turns on the scope of the proceedings on remand: if such further proceedings are merely ministerial, the decision is an appealable final judgment, but if further proceedings will require the exercise of independent judgment or discretion and the taking of additional evidence, the appeal is premature and must be dismissed. . . . This rule is an application of the more general final judgment principle that an otherwise interlocutory order is appealable [when] (1) it terminates a *71separate and distinct proceeding, or (2) so concludes the rights of the parties that further proceedings cannot affect them.” (Citations omitted; emphasis added; internal quotation marks omitted.) Id. We conclude that these principles are applicable to this appeal, in part, because the mandates of the more general final judgment principles require it.18

Levarge is also helpful to our analysis for its application of these principles to the facts and circumstances the court faced there. First, the court established that on remand, under the applicable statute, the commissioner had to apportion liability for the plaintiffs injuries between two insurers and the employer. Then, as a result, the court concluded that it was compelled to “determine whether apportionment constitutes a ministerial act or will require the exercise of independent judgment and the taking of additional evidence.” Id., 391. After interpreting the applicable statutes, the court concluded that, generally, “if the commissioner awards benefits, and there is a question as to the extent of liability of prior employers or successive insurers for the compensable injury, the commissioner must apportion liability among these employers or insurers within a reasonable period of time after the initial award.” Id. The court found that the record revealed that no such apportionment had taken place and that on remand the apportionment must be done. Id. The court then concluded that “[t]his determination will require a proceeding before the commissioner involving the production of evidence by all parties and a review of various medical and employment records. This court long has *72held that such a determination on remand will require the commissioner’s exercise of independent judgment and certainly will not be ministerial in nature.” Id., 392.

We now must determine, under the circumstances, whether the October 25, 2006 supplemental order directing the fund to compensate the plaintiff resulted from further proceedings that were merely ministerial in nature, thus making the September 29, 2006 finding and award an appealable final judgment. See id., 390. Here, there was not the exercise of independent judgment or discretion and the taking of additional evidence on the part of the commissioner in regard to the issuing of the supplemental order against the fund. The commissioner, prior to issuing its supplemental order against the fund had to determine only one matter: whether Raymark compensated the plaintiff in the intervening days since the September 29, 2006 finding and award. This is so because in the September 30, 2005 finding and award, the commissioner had dismissed the claims against The Hartford, General Reinsurance and Zurich and found that the commission had no jurisdiction to determine the association’s liability. Unlike in the usual circumstance when this court is called on to determine if a decision of the board is an appealable final order, here the “further proceeding” has already occurred. That is, we are not called on to ascertain what the commissioner will do on remand but to determine what the commissioner did do and was required to do when he issued his supplemental order. There is nothing in the record to indicate that the commissioner in the proceeding that led to the issuance of the supplemental order exercised independent judgment or discretion and took evidence. More importantly, there is nothing to indicate that the commissioner was required to exercise independent judgment or discretion and to take evidence.

*73The record reveals that Raymark had been in bankruptcy status for many years prior to the issuance of the order. It was precluded from compensating the plaintiff as a result, and the plaintiff was barred from seeking any recovery from Raymark whatsoever, regardless of the huge profits it was making. We find compelling to the determination that the proceeding was merely ministerial the language of the bankruptcy order granting the plaintiff a relief from stay that was part of the record before the commissioner in the proceeding leading to the issuance of the supplemental order. The amended order, issued on January 5, 2006, provided in relevant part: “The Connecticut Workers’ Compensation Commission is authorized to enter an order/award directly against debtors, Raymark ... in order to properly trigger the effect of ... § 31-355 for the purpose of allowing the movants to collect their duly awarded workers’ compensation benefits from the [fund]. The movants shall not seek to collect any damages, settlements, judgments and/or benefits from the debtors, Raymark ... or Raymark Corporation . . . individually or from the bankruptcy estate, and/or the Raytech Asbestos Personal Injury Trust . . . that are or may be awarded in the Workers’ Compensation Commission, but may seek, as allowed by law and consistent with this order, to collect said damages, settlements, judgments and/or benefits from the [fund].” See footnote 12. Simply stated, the record on which the commissioner relied reveals that at the time of the issuance of the order directing the fund to compensate the plaintiff, the plaintiff was precluded from seeking recovery from Raymark, and Raymark was precluded from compensating the plaintiff.

In light of Raymark’s prolonged bankruptcy, the express provisions of the Bankruptcy Court’s order granting the relief from automatic stay, the dismissal, more than one year prior, of all the defendant insurance *74companies and the remedial nature of the workers’ compensation scheme, we conclude that the commissioner’s issuance of the supplemental order against the fund was a ministerial act. The facts and circumstances of this matter removed from the commissioner any requirement of the exercise of independent judgment or discretion. The commissioner’s role in issuing the order was merely the fulfillment of a function akin to the application of a simple mathematical formula. See Smith v. Yurkovsky, 265 Conn. 816, 820, 830 A.2d 743 (2003) (holding that remand requiring commissioner to perform basic mathematical calculation is ministerial and does not require exercise of independent judgment or discretion); Szudora v. Fairfield, 214 Conn. 552, 557, 573 A.2d 1 (1990) (holding that because compliance with compensation review division’s remand order required only “a ministerial, noncontroversial compilation of salary information retrievable from an existing computer data bank” already in evidence, decision of compensation review division was appealable final judgment).

As a result of concluding that the September 29, 2006 finding and award was final for the purposes of an appeal by the fund, it is clear that the petition for review was not filed within the statutory mandate of § 31-301. In cases in which a party is represented by counsel, such as this case, the twenty day appeal period prescribed by § 31-301 (a) begins to run on the date that notice of a commissioner’s decision is sent to the party’s counsel. See Schreck v. Stamford, 250 Conn. 592, 600-601, 737 A.2d 916 (1999). The fund does not contend, nor does the record reflect, that notice of the September 29, 2006 finding and award was sent to it at a point in time that would bring its petition for review within the scope of § 31-301, and we will not here assume such a circumstance.

*75The record also reveals, and the parties do not dispute, the timeliness of the plaintiffs motion to dismiss, which was filed three days after the fund’s petition for review was filed with the board.19 Thus, because we conclude that the fund’s petition for review was untimely and that the plaintiffs motion to dismiss was timely, we conclude that the board dismissed properly the fund’s appeal.

The decision of the workers’ compensation review board is affirmed.

In this opinion GRUENDEL, J., concurred.

General Statutes § 31-301 (a) provides in relevant part: “At any time within twenty days after entry of an award by the commissioner, after a decision of the commissioner upon a motion or after an order by the commissioner according to the provisions of section 31-299b, either party may appeal therefrom to the Compensation Review Board . . . .”

See Fimiani v. Star Gallo Distributors, Inc., 248 Conn. 635, 644-50, 729 A.2d 212 (1999); 1 A. Sevarino, Connecticut Workers’ Compensation After Reforms (3d Ed. 2002) § 8.00, pp. 1285-1408.

Section 31-354-12 of the Regulations of Connecticut State Agencies provides: “Payment [to a claimant under § 31-355 of the General Statutes] of compensation shall be paid from the Fund provided: (a) A formal hearing is held and the Second Injury Fund, the Attorney General’s Office, and Workers’ Compensation Department, were noticed to attend, (b) A finding and award is granted against the employer after notice to the employer, (c) Ten days have passed from the date of notice of the award to the employer and the claimant has not received payment and the employer has not instituted an appeal, (d) The claimant requests and is granted a supplemental order of payment against the Fund.” (Emphasis added.)

General Statutes § 31-355 (b) provides in relevant part: “When an award of compensation has been made under the provisions of this chapter against *61an employer who failed, neglected, refused or is unable to pay any type of benefit coming due as a consequence of such award or any adjustment in compensation required by this chapter, and whose insurer failed, neglected, refused or is unable to pay the compensation, such compensation shall be paid from the Second Irqury Fund. The commissioner, on a finding of failure or inability to pay compensation, shall give notice to the Treasurer of the award, directing the Treasurer to make payment from the fund. ...”

Stec involves the fund, as well as Raymark Industries, Inc., and the same underlying issue of the appellant filing an appeal outside of the twenty day time period set out in General Statutes § 31-301 (a). This case differs from Stec in that here, the appellee did file a timely motion to dismiss the fund’s late appeal.

Raymark was formerly known as Raybestos-Manhattan, Inc.

General Statutes § 31-306 (a) provides in relevant part: “Compensation shall be paid to dependents on account of death resulting from an accident arising out of and in the course of employment or from an occupational disease . . .

Section 362 (a) of title 11 of the United States Code provides that the filing of a bankruptcy petition with the Bankruptcy Court “operates as a stay, applicable to all entities, of . . . the commencement or continuation ... of a judicial, administrative, or other action or proceeding against the debtor that was or could have been commenced before the commencement of the [bankruptcy case], or to recover a claim against the debtor that arose before the commencement of [the bankruptcy case].” The Bankruptcy Court has the power, however, to grant relief from the automatic stay. See 11 U.S.C. § 362 (d) through (g).

The association is a nonprofit legal entity established by General Statutes § 38a-839 and governed by the Connecticut Insurance Guaranty Association Act, which is codified at General Statutes § 38a-836 et seq. The association was established to reimburse, to a limited extent, covered claims against insolvent insurers. Here, the association, pursuant to its statutory mandate, was the successor of the Ideal Mutual Insurance Company, which insured Raymark’s blue collar employees in the early 1980s and was later acljudicated insolvent.

These formal hearings took place on December 3, 2002, and March 26, August 13 and November 19, 2003, and April 26 and June 24, 2004.

See General Statutes § 31-310.

The Bankruptcy Court issued an amended order for relief from the automatic stay on January 5, 2006. Both this amended order and the December 23,2005 order, were entered as evidence in the September 27,2006 formal hearing before the commissioner, which directly preceded the September 29, 2006 finding and award. The January 5, 2006 order from the Bankruptcy Court provides in relevant part: “The Connecticut Workers’ Compensation Commission is authorized to enter an order/award directly against debtors, Raymark ... in order to properly trigger the effect of ... § 31-355 for the purpose of allowing the movants to collect their duly awarded workers’ compensation benefits from the [fund]. The movants shall not seek to collect any damages, settlements, judgments and/or benefits from the debtors, Raymark ... or Raymark Corporation . . . individually or from the bankruptcy estate, and/or the Raytech Asbestos Personal Ipjuiy Trust . . . that are or may be awarded in the Workers’ Compensation Commission, but may seek, as allowed by law and consistent with this order, to collect said damages, settlements, judgments and/or benefits from the [fund].”

Zurich and The Hartford each filed a motion to dismiss, as well, and subsequently filed supporting memoranda of law. General Reinsurance also filed a motion to dismiss, but it was untimely and without a supporting memorandum of law.

We note that General Statutes § 31-301 (a) was amended in 2007 by Public Acts 2007, No. 07-31, “An Act Concerning The Workers’ Compensation Medical Practitioners’ Fee Schedule and Time For Piling A Workers’ Compensation Appeal.” This legislation added the following language to § 31-301 (a) effective October 1, 2007: “If a party files a motion subsequent to the finding and award, order or decision, the twenty-day period for filing an appeal of an award or an order by the commissioner shall commence on the date of the decision on such motion.”

The fund was not a party to this proceeding, as the record reveals that Raybestos-Manhattan (Raymark’s predecessor) was solvent at that time.

This finding and award determined, inter alia, the compensation rate to be paid to the plaintiff, as well as disposed of various claims the fund made against The Hartford, Zurich, General Reinsurance and the association.

Practice Book § 61-5 (a) provides in relevant part: “An appeal of a judgment. . . may be deferred until the judgment that disposes of the case for all purposes and as to all parties is rendered. ... [A] notice of intent to appeal must be filed in order to defer the taking of an appeal until the final judgment that disposes of the case for all purposes and as to all parties is rendered . . .

“(2) when the deferred appeal is to be taken from a judgment that disposes of only part of a complaint, counterclaim, or cross complaint but nevertheless disposes of all causes of action in that pleading brought by or against a particular party or parties.” Moreover, this section of the rules of appellate procedure is made applicable to appeals to the board from decisions of a commissioner by General Statutes § 31-301 (e), which provides in relevant part: “The procedure in appealing from an award of the commissioner shall be the same as the procedure employed in an appeal from the Superior Court to the Supreme Court, where applicable. ...”

We also note that “[t]he procedure In appealing from an award of the commissioner [to the board] shall be the same procedure employed in an appeal from the Superior Court to the Supreme Court, where applicable. . . General Statutes § 31-301 (e). The conclusion is further bolstered by the language of General Statutes § 31-300, which provides in relevant part: “If no appeal from the decision [of the commissioner] is taken by either party within twenty days thereafter, such award shall be final [and enforceable].”

Practice Book § 66-8 provides in relevant part: “Any claim that an appeal or writ of error should be dismissed, whether based on lack of jurisdiction, failure to file papers within the time allowed or other defect, shall be made by a motion to dismiss the appeal or writ. Any such motion must be filed . . . within ten days after the filing of the appeal . . . .”