[Cite as Columbia Gas of Ohio, Inc. v. Holloway, 2023-Ohio-4257.]
IN THE COURT OF APPEALS OF OHIO
THIRD APPELLATE DISTRICT
UNION COUNTY
COLUMBIA GAS OF OHIO, INC.,
CASE NO. 14-23-18
PETITIONER-APPELLEE,
v.
JOHN L. HOLLOWAY, JR., OPINION
RESPONDENT-APPELLANT.
COLUMBIA GAS OF OHIO, INC.,
CASE NO. 14-23-19
PETITIONER-APPELLEE,
v.
JEREMY W. TILLER, ET AL., OPINION
RESPONDENTS-APPELLANTS.
COLUMBIA GAS OF OHIO, INC.,
CASE NO. 14-23-20
PEITIONER-APPELLEE,
v.
TERESA PERRY, ET AL., OPINION
RESPONDENT-APPELLANTS.
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
COLUMBIA GAS OF OHIO, INC.
CASE NO. 14-23-21
PETITIONER-APPELLEE
v.
SCHRADER 10944, LLC, OPINION
RESONDENT-APPELLANT.
COLUMBIA GAS OF OHIO, INC.,
CASE NO. 14-23-22
PETITIONER-APPELLEE,
v.
OLIVE K. FLEMING, OPINION
RESPONDENT-APPELLANT.
COLUMBIA GAS OF OHIO, INC.,
CASE NO. 14-23-23
PETITIONER-APPELLEE,
v.
JOHN H. PUGH, ET AL., OPINION
RESPONDENTS-APPELLANTS.
-2-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
COLUMBIA GAS OF OHIO, INC.,
CASE NO. 14-23-24
PETITIONER-APPELLEE,
v.
GB FAMILY LIMITED PARTNERSHIP, OPINION
RESPONDENT-APPELLANT.
COLUMBIA GAS OF OHIO, INC.,
CASE NO. 14-23-25
PETITIONER-APPELLEE,
v.
RONALD E. KUHN, ET AL., OPINION
RESPONDENTS-APPELLANTS.
Appeals from Union County Common Pleas Court
Trial Court Nos. 2022-CV-0135, 2022-CV-0138, 2022-CV-0134, 2022-CV-
0140, 2022-CV-0131, 2022-CV-0142, 2022-CV-0129 and 2022-CV-0139
Judgments Affirmed
Date of Decision: November 27, 2023
APPEARANCES:
Thomas H. Fusonie for Appellants
Adam C. Smith for Appellee
-3-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
Ryan P. Sherman Counsel for Amici Curiae Ohio Power Company and
AEP Ohio Transmission Company, INC in support of Appellee
Columbia Gas of Ohio, Inc.
WALDICK, J.
{¶1} Respondents-appellants, GB Limited Partnership, Olive K. Fleming,
Teresa Perry, et al., John L. Holloway, Jr., Jeremy W. Tiller, et al., Ronald E. Kuhn,
et al., Schrader 10944, LLC, John Pugh, et al., (collectively, “respondents”), bring
these appeals from the April 19, 2023, judgments of the Union County Common
Pleas Court determining that petitioner-appellee, Columbia Gas of Ohio, Inc.,
(“Columbia Gas”), established the necessity of easement appropriations for a natural
gas pipeline. On appeal, respondents argue that the trial court erred by determining
that Columbia Gas established the necessity of the appropriations and that the trial
court failed to make required, specific findings concerning the necessity of the
individually challenged easement terms. For the reasons that follow, we affirm the
judgments of the trial court.
Background
{¶2} Columbia Gas is a natural gas distribution company that operates a
public utility subject to regulation by the State of Ohio. This case concerns
Columbia Gas appropriating easement rights on respondents’ properties in order to
-4-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
construct and operate a subsurface natural gas pipeline.1 The specific pipeline
constitutes “Phase VII” of the “Northern Columbus Loop,” and will supply natural
gas to Union, Delaware, and Franklin Counties to meet rising energy demands.2 The
pipeline was approved by the Ohio Power Siting Board (“OPSB”) after various
parties, including the Union County Commissioners, recommended the project’s
approval.3
{¶3} On August 5, 2022, Columbia Gas filed “Verified Petition[s] for
Appropriation of Easement Rights” related to respondents’ properties. 4 The
easements Columbia Gas seeks to acquire on respondents’ properties are essentially
the same: “the right to lay, operate, maintain, repair, replace, alter, relocate, and
remove a single natural gas pipeline, no greater than 24 inches in diameter, with a
maximum allowable operating pressure of 720 psig, together with valves and
appurtenances * * *, subsurface within a 50-foot-wide permanent easement[.]”5 In
addition, Columbia Gas seeks to acquire a “50-foot-wide temporary easement * * *
1
Columbia Gas asserts that the pipeline runs 16 miles through 115 parcels of land and that respondents own
10 of the subject parcels. Columbia Gas asserts that respondents are the only landowners challenging the
easements in Union County.
2
According to Columbia Gas, this is the final phase of the pipeline project.
3
This Court and the trial court have addressed prior cases involving Columbia Gas and pipeline projects. See
Columbia Gas v. Bailey, 3d Dist. Union Nos. 14-22-13, 14-22-14, 2023-Ohio-1245 (specifically dealing with
the Northern Columbus Loop Pipeline); Columbia Gas v. Phelps, 3d Dist. Union No. 14-22-07, 2022-Ohio-
2540 (dealing with the “Marysville Connector”).
4
In the petitions, Columbia Gas asserted that the route of the pipeline project was selected after “evaluating
approximately 37,800 acres of land,” that the “route parallels property lines and existing utility easements as
much as practicable,” that the route minimized tree clearing, and that the route avoided “six wetlands and
four streams.”
5
The pipeline on one property will be smaller.
-5-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
for the purpose of initial construction of the Pipeline and restoration of the Property
resulting from the construction of the Pipeline.”6 The rights would be transferable
to Columbia Gas’s “successors and assigns.”
{¶4} In the appropriation petitions Columbia Gas asserted, inter alia, that it
had provided respondents with Notices of Intent to Acquire and Written Good Faith
Offers based on appraisals. Columbia Gas asserted that the easements were
necessary and reasonably convenient for public use. Because Columbia Gas and
respondents had been unable to agree on the easement rights and/or compensation,
Columbia Gas asserted the appropriation action was necessary.
{¶5} Respondents filed “Verified Answer[s]” asserting, inter alia, that the
appropriations were not necessary in that they sought easement rights in excess of
those necessary for the project.7 Respondents specifically argued that the proposed
easements would improperly provide “unfettered blanket assignability rights,” that
the proposed easements would improperly provide Columbia Gas unnecessary
rights to maintain its pipeline, that the proposed 36-month temporary easements for
construction of the pipeline were too indefinite, and that the easements improperly
allowed Columbia Gas to construct “unspecified ‘appurtenances and valves’” on
respondents’ property. Respondents sought a hearing on the necessity of the
easements and their terms.
6
The temporary easement for one property owner was smaller since the pipeline being installed was smaller.
7
Respondents are represented collectively by the same law firm.
-6-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
{¶6} On February 10, 2023, the trial court held a consolidated “necessity”
hearing and heard testimony from Columbia Gas employees attesting to the
necessity of the easements. The parties filed written closing arguments containing
proposed findings of fact and conclusions of law.
{¶7} On April 19, 2023 the trial court filed a judgment entry determining that
Columbia Gas was entitled to a rebuttable presumption of necessity due to the
evidence presented, that respondents did not rebut the presumption, that the
appropriations were necessary, and that the appropriations were not excessive.8 The
trial court thus set the matter to proceed to compensation hearings. Respondents
now appeal the trial court’s judgments, asserting the following assignments of error
for our review.
First Assignment of Error
The Trial Court erred when it found that Columbia Gas of Ohio,
Inc. showed the necessity of the underlying appropriations, that
the evidence at the necessity hearing did not rebut the
presumption under R.C. 163.09(B)(1)(b), and that the proposed
easements do not constitute an excessive taking.
Second Assignment of Error
The Trial Court erred when it failed to make specific findings
concerning the necessity of the easements at issue pursuant to
Ohio Power Co. v. Burns, Slip Opinion No. 2022-Ohio-4713.
8
The trial court filed a nunc pro tunc entry on May 3, 2023.
-7-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
First Assignment of Error
{¶8} In their first assignment of error, respondents argue that the trial court
erred by determining that Columbia Gas established the necessity of the underlying
appropriations. Respondents contend, inter alia, that numerous provisions in the
easements are undefined or overbroad.
Standard of Review
{¶9} The Supreme Court of Ohio has indicated that a trial court’s review of
easement terms in an appropriation action should be upheld when they are supported
by some competent credible evidence. Ohio Power Company v. Burns, 171 Ohio
St.3d 84, 2022-Ohio-4713, ¶ 35.9 When a trial court’s decision regarding a petition
for appropriation rights is supported by some competent credible evidence it will
not be reversed as against the manifest weight of the evidence. Columbia Gas v.
Bailey, 3d Dist. Union Nos. 14-22-13, 14-22-14, 2023-Ohio-1245, ¶ 60.
Relevant Authority
{¶10} When an owner files an answer to an appropriation petition under R.C.
163.08 asserting specific denials to the appropriation petition, a trial court is
9
The standard of review is actually disputed between the parties. Respondents argue that we should apply a
de novo standard of review, citing our decision in Phelps, where we stated that the interpretation of a statute
is a matter of law that we review de novo. Phelps at ¶ 10. In Phelps, we referred to our decision in ODNR v.
Thomas, 3d Dist. Mercer No. 10-16-05, 2016-Ohio-8406, wherein we stated that a trial court’s decision on
the extent of the take is reviewed de novo. However, the extent of the take is not at issue here in the same
way it was in Thomas as the appropriation is specifically defined with regard to the land acquired.
Respondents are challenging the terms of the appropriation, and the Supreme Court of Ohio indicated in
Burns that a deferential standard of review is appropriate under such circumstances, so we will apply that
standard here.
-8-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
required to hold a hearing on the matter. At the hearing, which is governed by R.C.
163.09, a trial court determines “‘whether the entire appropriation was necessary;
specifically whether the amount taken was excessive.’” Columbia Gas v. Phelps, 3d
Dist. Union No. 14-22-07, 2022-Ohio-2540, ¶ 23, quoting Octa v. Octa Retail, 12th
Dist. Fayette No. CA2007-04-015, 2008-Ohio-4505, ¶ 43. Importantly, the
necessity required for the appropriation does not require a showing of absolute
necessity, but rather that which is reasonably convenient or useful to the public.
Columbia Gas v. Bailey, 3d Dist. Union Nos. 14-22-13, 14-22-14, 2023-Ohio-1245,
¶ 68.
{¶11} Generally, when a landowner challenges the necessity of an
appropriation sought by an agency, the burden of proof to establish the necessity of
the appropriation is “upon the agency by a preponderance of the evidence[.]” R.C.
163.09(B)(1).10 However, “[t]he presentation by a public utility or common carrier
of evidence of the necessity for the appropriation creates a rebuttable presumption
of the necessity for the appropriation.” Id. at (B)(1)(b)
{¶12} Stated differently, where an “agency” presents evidence of the
necessity of an appropriation, the agency is entitled to a rebuttable presumption of
necessity under R.C. 163.09(B)(1)(b), creating a prima facie showing of necessity.
10
Agency is defined in 163.01 and it includes private agencies. Private agencies such as Columbia Gas are
permitted to appropriate property. See Burns, 171 Ohio St.3d 84, 2022-Ohio-4713, ¶ 1.
-9-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
Burns at ¶ 32. The presumption imposes upon the landowners the burden of going
forward with evidence to rebut or meet the presumption of necessity. Id.
Evidence Presented at the Necessity Hearing
{¶13} At the necessity hearing in this case, Columbia Gas presented the
testimony of its Director of Regulatory Policy. She testified that the pipeline
Columbia Gas intended to build served two primary purposes: operational reliability
for current customers and serving growth to new customers.
{¶14} As to operational reliability, the Director explained that the project
provides [an] additional source of feed for our west side of Columbus.
The west side, itself, is a constrained area specifically with the feed
coming from the southeast at our Rome Hilliard Station. This will
permit an additional feed of natural gas to that system traveling from
New Albany which is a different interstate pipeline system.
(Tr. at 32). Regarding growth, the Director explained that there had been a lot of
development in Delaware and Union Counties, and the pipeline would help serve
that area by interconnecting with the Marysville Connector, providing an additional
feed to the Marysville market.
{¶15} The Director testified that the pipeline had been approved by the
OPSB, that only one pipeline could be installed pursuant to the easements, that the
pipeline had to transport natural gas, that the pipeline was limited in size, and that
the pipeline was limited in pressure. The Director also testified that acquiring the
-10-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
right to assign the easement was important because of, inter alia, corporate
restructuring.
{¶16} Columbia Gas also presented the testimony of the pipeline’s Project
Manager. The Project Manager testified as to why the permanent easement needed
to be 50 feet and he testified that the additional temporary easement was necessary
to support construction of the pipeline and restoration of the property to its original
state. The Project Manager testified that the temporary easement would last 36
months or until the pipeline was completed and the property restored. He testified
that the start date for construction could not yet be determined because Columbia
Gas had yet to acquire all the easements.
{¶17} The Project Manager testified that the pipeline, valves, and
appurtenances would all be subsurface. He also testified that it was not possible to
list in the easements all of the potential valves and appurtenances that could be
installed because the installation would depend in part on the character of the land
and in part on potential changes to regulatory standards.
{¶18} Based on the evidence presented, the trial court determined that
Columbia Gas was entitled to a rebuttable presumption of necessity pursuant to R.C.
163.09(B)(1)(b). Thus Columbia Gas had established a prima facie case of necessity
of the easements and their terms, and the respondents had the burden of going
forward with evidence to rebut the presumption. The trial court determined that
-11-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
respondents did not meet their burden and that the easements did not constitute an
excessive taking, ruling in favor of Columbia Gas in a written entry addressing
respondents’ arguments.
Analysis
{¶19} On appeal, respondents largely renew all of the specific challenges
they made to the easements and the easements’ terms at the trial court level. We will
address each argument in turn.
{¶20} Respondents first contend that the trial court erred because Columbia
Gas failed to meet its burden of proving necessity of the appropriations. However,
Columbia Gas presented evidence that the project had been approved by the OPSB
and that the pipeline had multiple purposes that would be beneficial to residents of,
inter alia, Union County. Thus there was some competent credible evidence to
support the trial court’s finding regarding necessity, and respondents arguments on
this issue are not well-taken.
{¶21} Respondents next contend that the appropriations sought were
overbroad because they did not specifically define the “natural gas” that was to be
transmitted through the pipeline. Respondents cite the fact that the Director of
Regulatory Policy for Columbia Gas testified that there were multiple types of
natural gases that technically existed.
-12-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
{¶22} However, the Director also testified that the Public Utilities
Commission of Ohio actually does not define “natural gas,” but Columbia Gas’s
“tariff” does. The Director testified that the “natural gas” that would be transported
would meet the quality contained in their “tariff” standards. Further, the easement
is clear in that the only substance that can be transported in the pipeline is “natural
gas.”
{¶23} The trial court reviewed the evidence and determined that the lack of
definition of “natural gas” did not rebut the presumption of necessity, particularly
given that the pipeline was limited to being a “single natural gas pipeline” with a
specific diameter and a maximum pressure.11 We agree with the trial court. Thus
this argument is not well-taken.
{¶24} Respondents next challenge the trial court’s judgment by arguing that
the easements would place “impermissibly vague restrictions on the use of
[respondents] properties.” This challenge is related to the following provision in the
easements:
Grantors shall not allow the existence of any obstructions, or in any
way impair the ability of the Grantee to exercise the Grantee’s rights
granted herein, within the Permanent Easement Area and Temporary
Easement Area.
11
Given the specifics related to the pipeline’s parameters contained in the easement and given that only
“natural gas” can be transported in the pipeline, we do not agree with respondents that the Director’s
testimony that “it’s just a pipeline easement without any specificity” is somehow “fatal” to the easements
here, particularly given that the Director gave that particular response after being asked whether the pipeline
would be used only for, inter alia, transmission or distribution. Thus the Director’s answer is taken out-of-
context by respondents and the trial court’s finding that respondents did not rebut the presumption afforded
to Columbia Gas is supported by the record.
-13-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
The Pipeline shall be buried below plow depth so as not to interfere
with the present use of the land.
{¶25} Respondents argue that the language of the easements grants
Columbia Gas “unconstrained latitude to arbitrarily restrict [respondents] use and
enjoyment of their properties.” (Appt.’s Br. at 10). Respondents contend that
Columbia Gas effectively should list all the potential obstructions that were
impermissible so the respondents could know how they could use their land.
{¶26} The trial court determined that the lack of definition of “obstruction or
impairment” did not equate to an excessive taking considering the words could be
defined by their normal usage. We agree with the trial court, particularly given that
the very next line in the easement provides some key context, namely that the
pipeline should be buried so as to not interfere with the present use of the land. The
land, primarily agricultural according to the filings, will thus still be usable as it is.
{¶27} Furthermore, the Project Manager for Columbia Gas testified that it
would be impossible to list every conceivable obstruction or impairment in an
easement. Moreover, he testified that Columbia Gas reviews possible obstructions
to a pipeline on a case-by-case basis to allow landowners the greatest latitude with
their land. Finally, as Columbia Gas notes, the law already generally establishes that
“the owner of the servient estate may not interfere with the dominant estate’s use
and enjoyment of the easement.” Ohio Power Co. v. Ogle, 4th Dist. Hocking Nos.
-14-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
10CA13, 10AP13, 2011-Ohio-3903, ¶ 15. As the testimony provides some
competent credible evidence supporting the trial court’s determination, we find no
error here, and respondents’ argument is not well-taken.
{¶28} Respondents next argue that the easements are impermissibly vague
by granting Columbia Gas “blanket assignability rights.” In reviewing the matter,
we emphasize that the Director of Regulatory Policy testified that assignability of
the easement rights was important because companies change, split, or are sold.
Regardless, the Director testified that while the rights in the easements technically
could be assigned to anyone, in reality only a regulated natural gas company could
lawfully operate the pipeline placed on respondents’ properties. Based on the
evidence presented, we find that there is some competent credible evidence to
support the trial court’s determination on this issue.12 Thus respondents’ arguments
regarding assignability of rights are not well-taken.
{¶29} Respondents next argue that the temporary easements are indefinite
and contain no start date, rendering them excessive. Notably, Columbia Gas has
modified the language of their temporary easements providing stricter timelines
after we rejected a “perpetual” temporary easement in Columbia Gas v. Phelps, 3d
Dist. No. 14-22-07, 2022-Ohio-2540, ¶ 35-39. Moreover, as the trial court
12
The trial court’s original judgment entry was corrected in its nunc pro tunc entry to indicate that the
assignability issue does not demonstrate an excessive taking to overcome the rebuttable presumption of
necessity. It is clear from the surrounding context of the trial court’s original entry that the word “not” was
intended to be included in the original entry.
-15-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
determined, the temporary easements end either 36 months after the commencement
of construction or on the completion of construction and restoration of the premises,
whichever occurs first. A precise start date could not be listed by Columbia Gas
because the easements had not all been acquired. We find no error with the trial
court’s determination that the easement terms are not overbroad or that respondents
failed to rebut the presumption here. As the evidence supports the trial court’s
determination, respondents’ argument is not well-taken.
{¶30} Finally, respondents argue that the easements impermissibly provide
Columbia Gas a “blanket” right to construct “undefined” valves and appurtenances
on their properties. However, testimony indicated that all valves and appurtenances
would be subsurface, thus it is not clear how this would cause any impact to the
respondents. At the very least, respondents did not meet their burden to rebut the
presumption.
{¶31} In addition, testimony indicated that it was impossible to predict what
valves or appurtenances would be necessary for each property until the ground had
been removed. Furthermore, testimony indicated it was impossible to predict future
regulations regarding valves and appurtenances. After reviewing the testimony, we
find that the trial court’s rejection of respondents’ arguments is supported by some
competent credible evidence and respondents’ challenge to the “undefined” valves
and appurtenances in the easements is not well-taken.
-16-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
{¶32} In sum, the trial court rejected all of respondents’ challenges to the
easement terms and determined that the appropriations were necessary. The record
supports the trial court’s findings and respondents’ challenges to the trial court’s
judgment are not well-taken.13 Therefore, the first assignment of error is overruled.
Second Assignment of Error
{¶33} In their second assignment of error, respondents argue that the trial
court erred by failing to make “specific findings concerning the necessity of the
easements at issue.” (Appt.’s Br. at 16). Respondents emphasize that in Ohio Power
Company v. Burns, 171 Ohio St.3d 84, 2022-Ohio-4713, ¶ 33, the Supreme Court
of Ohio determined that a blanket finding regarding challenges to easement terms
was improper. Rather, a trial court needed to analyze the challenged easement terms
separately. Respondents contend that the trial court did not conduct a separate,
specific review here.
{¶34} Contrary to respondents’ arguments, a simple review of the trial
court’s judgment entry entirely undermines their claim. The trial court explicitly
listed the five specific denials made by respondents in its judgment entry and
individually addressed each denial. There was no “blanket finding” here of the type
rejected in Burns.
13
Legal authority cited by respondents not directly addressed herein has been considered and found to either
be distinguishable or to have little relevance. For example, respondents rely on Norwood v. Horney, 110 Ohio
St.3d 353, 2006-Ohio-3799, ¶ 1 but Norwood dealt with a municipality “taking [] an individual’s property
by eminent domain and transferring the property to a private entity for redevelopment.”
-17-
Case Nos. 14-23-18, 14-23-19, 14-23-20, 14-23-21
14-23-22, 14-23-23, 14-23-24, 14-23-25
{¶35} While respondents may have preferred a more detailed analysis, a trial
court under Burns is only required to make specific findings concerning the
challenged terms, and that was specifically done here. Burns at ¶ 35. Each denial
was mentioned, summarized, and rejected. The trial court also made the specific
finding of necessity. Therefore, respondents’ second assignment of error is
overruled.
Conclusion
{¶36} Having found no error prejudicial to respondents in the particulars
assigned and argued, the assignments of error are overruled and the judgments of
the Union County Common Pleas Court are affirmed.
Judgments Affirmed
WILLAMOWSKI and ZIMMERMAN J.J., concur.
/eks
-18-