Crummey v. Popp

This is an original proceeding in mandamus to require the respondent superintendent of streets to enter into a contract with petitioner for the performance of certain street improvements in the city of San *Page 232 Jose, and to require the respondent city manager to approve a bond offered by petitioner to secure the payment of labor and materials under such contract. The respondents defend upon the ground that the respondent Clark, as agent of property owners, is entitled to the contract instead of the petitioner.

It would serve no useful purpose to outline the pleadings or the facts of the case. It is sufficient to say that it is conceded that the municipal authorities initiated proceedings for the improvement of a public street under the "Improvement Act of 1911" (Stats. 1911, p. 730; Deering's Gen. Laws 1923, Act No. 8199), and that all these proceedings were in due form and within time until the respondent Clark, as agent for the property owners, gave notice that they elected to take the contract at the same price at which it had been awarded to the petitioner. The claims of the respective parties arose at this point in the proceedings and the sole question to be determined on this action is whether, under section 12 of the "Improvement Act of 1911," where the improvement is to be made under the district plan, property owners may elect to take over the contract.

[1] The act in question provides an alternative method for all public improvements specified in section 2 and was intended to be all-inclusive, though not repealing any of the other acts providing for similar improvements. Any interpretation of the act must therefore be made in view of the well-known rule that where one act is intended to be complete in itself and some specific provision therein is susceptible to two interpretations — one which effects that purpose, and the other which would require resort to some other act or proceeding — the former interpretation should be favored.

The specific provision which is in issue here is found in section 12, reading, in part, as follows: "The owners of three-fourths of the frontage of lots and lands liable to be assessed . . . may . . . elect to take said work and enter into a written contract to do the whole work at the price at which the same has been awarded." The petitioner argues that this section is applicable only when the work has been agreed to be done on the "front-foot" plan of assessment, while the respondents argue that it is applicable *Page 233 to work to be done under the "district" plan of assessment as well.

[2] Looking at the act as a whole it is apparent that the legislature provided for both methods of assessment and expressly included the "district" plan in section 4 where the council was expressly authorized to adopt that plan whenever the contemplated improvement "is of more than local or ordinary public benefit, or . . . the total estimated costs and expenses thereof would exceed one-half the total assessed value of the lots and lands assessed." In section 79 the meaning of the words "work" and "improvement" as used in the act is defined to "include all work mentioned in this act." Thus every improvement contemplated by the act may be paid for under the "district" plan of assessment when so determined by the council under the provisions of section 4. With but a few exceptions, all the proceedings required to be taken down to the award of the contract are the same under either method of assessment. Throughout the act we find a very definite policy on the part of the framers of the act to provide a complete scheme for the improvement of streets under both methods of assessment, and we also find that the provisions of the entire act are applicable to both of these methods except in the few instances where special distinctions are made.

[3] Turning to section 12 we find that provision was made whereby the owners "liable to be assessed" might take over the contract and do the work in their own behalf. There is here no distinction between owners liable to be assessed under the "front-foot" and "district" plans of assessment. The terms are general and must be held to include contracts awarded under both plans, as to hold otherwise would necessitate our writing into the section an exception which the legislature has given no indication that it intended to be there.

The section provides that "the owners of three-fourths of the frontage of lots and lands liable to be assessed" may elect to take over the contract. From this it is argued that the election can be had only when the work is done on the frontage plan of assessment, because otherwise it would be difficult to determine the true owners of a sufficient amount of frontage. But the "district" plan *Page 234 may be adopted when the improvement is confined to lots fronting on the street improved if the work is of more than ordinary public benefit or if the cost of the work is more than one-half of the assessed value of the lots assessed. No reason has been suggested why the owners should not be permitted to take over the work in such a case. The fact that it would be difficult to ascertain the correct number of owners where the assessment district included the entire municipality is a consideration to be addressed to the legislature.

Petition denied and writ discharged.

Nourse, J., and Sturtevant, J., concurred.