United States Court of Appeals
For the First Circuit
No. 03-1830
UNITED STATES PUBLIC INTEREST RESEARCH GROUP,
STEPHEN E. CRAWFORD, CHARLES FITZGERALD,
Plaintiffs, Appellees,
____________________
NANCY ODEN,
Plaintiff,
v.
ATLANTIC SALMON OF MAINE, LLC,
Defendant, Appellant.
___________________
No. 03-1831
UNITED STATES PUBLIC INTEREST RESEARCH GROUP,
STEPHEN E. CRAWFORD, CHARLES FITZGERALD,
Plaintiffs, Appellees,
_____________________
NANCY ODEN,
Plaintiff,
v.
STOLT SEA FARM, INC.,
Defendant, Appellant.
APPEALS FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MAINE
[Hon. Gene Carter, U.S. District Judge]
Before
Boudin, Chief Judge,
Torruella, Circuit Judge, and
Baldock,* Senior Circuit Judge.
Richard E. Schwartz with whom Adam D. Wilson and Crowell &
Moring LLP were on brief for appellants.
David A. Nicholas, with whom Joshua R. Kratka, Joseph J. Mann,
National Environmental Law Center and Bruce M. Merrill were on
brief for appellees.
G. Steven Rowe, Attorney General, State of Maine, and
Christopher C. Taub, Assistant Attorney General, State of Maine, on
brief for State of Maine, amicus curiae.
August 6, 2003
*
Of the Tenth Circuit, sitting by designation.
BOUDIN, Chief Judge. This is an appeal by two companies
("the companies") engaged in operating salmon farms in Maine:
Atlantic Salmon of Maine, LLC, and Stolt Sea Farm, Inc. In a
citizen-suit civil action under the Clean Water Act, 33 U.S.C. §
1365 (2000), the district court found the companies liable for
polluting Maine waters, USPIRG v. Atl. Salmon, LLC, 215 F. Supp. 2d
239 (D. Me. 2002) ("Atlantic Salmon I"), and granted injunctive
relief, USPIRG v. Atl. Salmon, LLC, 257 F. Supp. 2d 407 (D. Me.
2003) ("Atlantic Salmon II"). The companies claim that the
district court's authority to grant injunctive relief has been
superceded by a subsequent state permit.
We recount only what is needed to frame the legal issues
before us. The two companies are engaged in sea-farming or
"aquaculture." Its key feature is that young salmon, called
"smolts," are transferred from freshwater hatcheries to sea cages
called "net pens," the net pens being submerged in ocean water.
The smolts are held in these net pens for 18 months or so while
they mature and the salmon are then harvested. The origin of this
case is the pollution that occurs in various forms incident to the
net pen operations.
Atlantic Salmon began operating salmon farms along the
Maine coast in 1988 and currently operates four farms (previously
five) in Machias Bay and two in Pleasant Bay. It also owns two
other companies that together operate seven more farms. Stolt,
-3-
which began operating in Maine in 1987, runs three farms in
Cobscook Bay and has a subsidiary operating two more salmon farms.
Both parent companies hold aquaculture leases from the Maine
Department of Marine Resources and site permits from the Army Corps
of Engineers.
The Clean Water Act provides that, except as otherwise
authorized, "the discharge of any pollutant [into navigable waters]
by any person shall be unlawful." 33 U.S.C. §§ 1311(a), 1362(12)
(2000). One of the exceptions allows discharge where the person
holds a discharge permit from the Environmental Protection Agency
("EPA") or, if the state has been authorized by EPA to conduct its
own program, a state discharge permit. 33 U.S.C. §§ 1342(a)(1) &
(b) (2000). Where the state issues a permit, EPA retains power to
veto it, 33 U.S.C. § 1342(c)(3) (2000), subject to review in the
federal courts of appeals. 33 U.S.C. § 1369(b)(1) (2000).
The permits may be either "general," authorizing a class
of operations by anyone, or "individual," i.e., specific to one
permit holder. Tex. Oil & Gas Ass'n v. EPA, 161 F.3d 923, 929
(5th Cir. 1998); Atlantic Salmon I, 215 F. Supp. 2d at 245 n.2.
The grant or denial of a federal permit is reviewable in the
appropriate federal court of appeals, 33 U.S.C. § 1369(b)(1)
(2000), and state permits are reviewable under state law and
subject to EPA veto. However, while a permit is in effect, it
protects the holder (with exceptions not here relevant) against
-4-
claims that the holder is violating the Clean Water Act, thus
providing a kind of safe harbor or shield. 33 U.S.C. § 1342(k)
(2000).1
The companies in this case say that in the late 1980s EPA
told them that they did not need a permit under the Clean Water
Act; but indisputably in 1990 EPA told the companies that they did
need permits. In the same year the companies began to seek permits
for one or more sites, and further applications (and entreaties for
action) followed but EPA never issued permits for any of the
companies' sites. Instead, EPA began what appears to have been a
leisurely process of consultation, ending in January 2001 with EPA
delegating to Maine the authority to issue permits.
On September 25, 2000, the United States Public Interest
Research Group and two of its members (collectively, "USPIRG"),
filed suit against the companies in district court to enjoin the
discharge of pollutants without a permit. The Clean Water Act
permits such citizen suits and invests the district courts with
authority to enjoin violations. 33 U.S.C. § 1365(a) (2000). There
ensued discovery and cross motions for summary judgment before a
magistrate judge. In February 2002, the magistrate judge
1
Atl. States Legal Found. v. Eastman Kodak, Co., 12 F.3d 353,
357 (2d Cir. 1993); see also E.I. du Pont de Nemours & Co. v.
Train, 430 U.S. 112, 138 n.28 (1977) ("The purpose of § 402(k)
seems to be to insulate permit holders from changes in various
regulations during the period of a permit and to relieve them of
having to litigate in an enforcement action the question whether
their permits are sufficiently strict.").
-5-
recommended that summary judgment be granted against the companies.
Atlantic Salmon I, 215 F. Supp. 2d at 241-42; USPIRG v. Stolt Sea
Farm, Inc., Civ. No. 00-149-B-C, 2002 WL 240386 (D. Me. Feb. 19,
2002).
On June 17, 2002, the district judge issued a decision
adopting the recommendation, determined that the companies had
violated the Clean Water Act, and ordered a hearing on injunctive
relief and civil penalties. Atlantic Salmon I, 215 F. Supp. 2d at
241. After a lengthy evidentiary hearing in October 2002 followed
by more briefing, the district court on May 28, 2003, issued a
decision making further fact findings, rejecting various legal
defenses by the companies, imposing a statutory civil penalty of
$50,000 on each of the two companies, and ordering injunctive
relief. Atlantic Salmon II, 257 F. Supp. 2d at 416-27, 434-36.2
The two injunctive provisions of principal concern here
required specified periods of fallowing (that is, temporary idling)
of net pens after the next harvest and prohibited the future
stocking of any of the companies' net pens with non-native strains
of salmon. Atlantic Salmon II, 257 F. Supp. 2d at 435-36. The
court also ordered that each pen be stocked with only a one-year
2
In early May 2003, the district court also held Atlantic
Salmon in civil contempt for violating an interim directive issued
in January 2003 against stocking any new class of fish pending the
decision on full-scale injunctive relief. USPIRG v. Atl. Salmon,
LLC, Civ. No. 00-151-B-C, 2003 WL 21068373, at *13-*14 (D. Me. May
9, 2003).
-6-
class of fish at any time. Id. at 435. However, the court did
allow fish currently in the pens to be harvested, both to avoid
irreparable loss and because the environmental harm would be
reparable. Id. at 435-36.
While the district court was considering this case, the
Maine Board of Environmental Protection was conducting proceedings
looking to the issuance of a general permit covering all Maine
salmon farming operations. Draft permit provisions were made known
to the district court during its deliberations. Atlantic Salmon
II, 257 F. Supp. 2d at 430 n.19. On June 19, 2003, the Maine Board
issued its general permit, which is currently being challenged in
the Maine Superior Court by USPIRG. USPIRG v. Bd. of Envtl. Prot.,
Docket No. AP-03-43. The permit is currently effective but
provides protection for individual companies only after a notice
period.
The companies have now appealed to this court to challenge
the injunction. Because of the impact on their ongoing operations,
they sought expedited briefing and oral argument, which we granted,
and a stay of the injunction pending our decision, a request that
we denied immediately after the oral argument on July 29, 2003. The
companies have primarily focused on a single claim, namely, that the
district court's injunction is beyond its "jurisdiction" insofar as
the terms of the injunction differ from those of the Maine general
-7-
permit. Maine regulators have filed an amicus brief supporting this
position.
The companies do not challenge the district court's
ruling that they have been violating the Clean Water Act for over
a decade or its rejection of their various defenses (e.g., laches,
estoppel, de minimus effects). Yet the liability ruling is a
necessary backdrop for demarcating the district court's authority
vis-à-vis that of EPA and Maine. Congress set out in the Clean
Water Act to solve a set of practical problems, and any useful
construction of the statute must be responsive to this objective.
See, e.g., Chapman v. United States, 500 U.S. 453, 473 (1991).
In this case, the district court found that both
companies had discharged into navigable waters, in violation of the
statute, five types of pollutants: non-North American salmon that
escape from the pens; large quantities of salmon feces and urine
that exit the pens; uneaten salmon feed containing a range of
chemicals for combating infection and providing coloring; other
chemicals to fight sea lice; and copper that flakes from the net
pens themselves. Atlantic Salmon I, 215 F. Supp. 2d at 247-49;
USPIRG v. Stolt Sea Farm, Inc., Civ. No. 00-149-B-C, 2002 WL
240386, at *5-*7 (D. Me. Feb. 19, 2002), aff'd USPIRG v. Stolt Sea
Farm, Inc., Civ. No. 00-1490B0C, 2002 WL 1552165, at *1 (D. Me.
June 17, 2002).
-8-
That the wastes and chemicals should be classified as
pollutants of the sea floor and waters is hardly surprising; but
the district court also found that non-native strains of salmon are
pollutants under the statute and regulations. Atlantic Salmon II,
257 F. Supp. 2d at 420-22. The reason is that through a variety of
causes, some of the penned salmon tend to escape and to interbreed
with native North Atlantic salmon;3 and through competition from
the non-native salmon and the genetic effects of interbreeding, the
native strain's survival is threatened. Id. North Atlantic salmon
is currently listed as an endangered species. Id. at 420.
Just how serious and immediate this threat may be is a
matter of dispute. But the companies do not challenge the ultimate
finding that non-native species are a pollutant and can be banned.
The Maine Board's general permit also has a ban on non-native
species, although one more flexible than that adopted by the
district court. The companies do not dispute that the other
pollutants are regularly released by their operations nor do they
now claim that their past operations complied with the statute.
Instead, the companies argue that in three respects the
injunction, as applied to their future operations, is at odds with
more lenient regulation limned by the Maine Board general permit.
3
The escapes, well documented in the case of Atlantic Salmon
and less so as to Stolt, result from natural wear or injury to the
pens, accidents in delivering the fish, submergence of the open
pens tops in bad conditions, and other documented causes. Atlantic
Salmon II, 257 F. Supp. 2d at 412, 414.
-9-
The areas of alleged conflict are the treatment of non-native
salmon, the fallowing schedule, and (potentially) the limits on
one-class year stocking--all matters described more fully below.
However, the threshold question is whether it is premature for us
to consider this so-called jurisdictional attack at all.
At the time the injunction was issued, the general permit
itself had not been issued. Indeed, after it was issued, it did
not apply to the two companies until a notice period expired.
However, the general permit became effective for at least one farm
of each company in late July 2003. Although the permit has itself
been challenged in state court by USPIRG, it would--but for the
injunction--be the main regime governing the companies' future
operations.
Yet, the general permit is an event occurring after the
issuance of the injunction, and ordinarily the proper course would
be for the appellants to seek a modification by the district court
before raising the conflict issue with us. Cf. Fed. R. App. P.
8(a)(1)(c); Daubert v. Schmidt, 498 F. Supp. 1344, 1346 (E.D. Wis.
1980). Until then, ordinarily there would be no error to be
reviewed. However, in this instance the district court anticipated
the permit, drafts of which were known to it, and expressly
addressed the then-prospective question of conflict between the
injunction and the general permit.
-10-
On the two main issues--fallowing and non-native species-
-the district court's decision adopting the injunction makes clear
that the obligations imposed by the injunction are intended to
apply notwithstanding any less stringent regulation of the same
topics that might be imposed by the state permit. Atlantic Salmon
II, 257 F. Supp. 2d at 435-36. In short, the district court in
issuing the injunction considered and rejected the companies'
present claim that the injunction should be qualified by the
permit. The district court reaffirmed this position when, on June
25, 2003, it denied the companies' motion for a stay of the
injunction pending this appeal. USPIRG v. Atl. Salmon, LLC, Civ.
No. 00-151-B-C (D. Me. July 25, 2003).
This brings us to the merits of the so-called
jurisdictional objection that the companies assert. The term
"jurisdiction" has several reasonably distinct usages in relation
to court authority (e.g., subject matter jurisdiction, personal
jurisdiction), although it is sometimes used simply as an epithet
meaning little more than that an issue is fundamental or important.
The more specific usages entail specific consequences: here, the
companies urge that their objection is based on subject matter
jurisdiction and therefore (among other consequences) requires de
novo review of everything but raw factual findings. Francis v.
Goodman, 81 F.3d 5, 7 (1st Cir. 1996).
-11-
The companies' characterization of their objection is
doubtful. The Clean Water Act expressly grants the district court
authority--that is, subject matter jurisdiction--to enforce the
statute against violators and to provide equitable relief, and the
companies do not contest that they violated the statute. Their
main argument is essentially a substantive claim, based on language
in the statute, that in granting relief the district court must
refrain from ordering conduct that an effective permit would allow.
Still, this is an issue of law even if non-jurisdictional so in any
event we review the issue de novo.
The companies' statutory argument is straightforward.
Although the statute authorizes the court to enforce the Clean
Water Act against violators, it also provides--in the so-called
shield provision--that compliance with an effective permit is
compliance with the statute. 33 U.S.C. § 1342(k) (2000); Atl.
States Legal Found. v. Eastman Kodak, Co., 12 F.3d 353, 357 (2d
Cir. 1993). Thus, say the companies, the injunction must give way
to the permit wherever they "conflict"--a concept they construe
generously. Otherwise, the district court would be overriding the
substantive protection granted by the shield provision.
The supposed conflicts between court and agency authority
in this case are several. The sharpest contrast between what is
required by the injunction and by the permit concerns the stocking
of non-native species. Up to now, the companies have included in
-12-
their pens non-native species of salmon which are apparently bred
for economically desirable characteristics. Atlantic Salmon II,
257 F. Supp. 2d at 420-22. Such non-native salmon were in the pens
when the injunction issued. The district court did not require
removal of those salmon already in the pens but did ban outright
any future introduction of non-native species. Id. at 435-36.
The Maine general permit, by contrast, says that non-
native salmon can be re-stocked until July 31, 2004; thereafter the
stocking must be of native salmon unless the permit holder proves
that native stock is not available in sufficient quantities to
match the farm's prior stocking level based on historical data.
Maine Permit 24. The injunction thus provides a flat ban for
future stocking effective immediately, preventing the companies
from transferring smolts due to be placed into the pens this summer
(July-August 2003); the permit by contrast would permit this
stocking.
The second supposed conflict is slightly less direct.
The district court ordered that the companies' pens once emptied
remain fallow for fixed periods: 24 months for most, 36 months for
one badly degraded site, and 6 months for the least afflicted site.
Atlantic Salmon II, 257 F. Supp. 2d at 435. The Maine permit
requires fallowing only "for a sufficient time to avoid harboring
or spread of diseases from one class year to the next," allowing
retention of carryover stock for reproduction purposes of up to 10
-13-
percent of the prior fish in the last year class, unless otherwise
directed. Maine Permit 30.
Lastly both the injunction and the Maine permit seek to
reduce the risk of pathogens inside the pens, which can also infect
fish outside the pens, by requiring that operators stock individual
pens with only a single-year class of salmon at any one time. Thus
a net pen stocking salmon of the 2003 year class would have to be
emptied before 2004 salmon were introduced. Atlantic Salmon II,
257 F. Supp. 2d at 435; Maine Permit 30. The companies see a
potential conflict because the district court ban would apply--
unless modified--even if the Maine Board were in the future to
relax this restriction.4
It is evident that the conflict in all three instances is
of a specific kind, namely, that the district court's restriction
is more demanding than the state permit. Hypothetically, the
vaguely phrased state fallowing restriction might turn out to be
more stringent in a specific case; but this would probably be rare.
In all events, the injunction in this case would be unlikely to
impair a stricter permit because the injunction explicitly requires
compliance with federal and state requirements as well as the more
4
As to this provision, there is arguably a ripeness objection
to litigating the matter now, Abbott Labs. v. Gardner, 387 U.S. 136
(1967), but it turns out not to matter in this case. The other two
conflicts are live enough to justify consideration of the legal
issues addressed in this decision and no issue peculiar to the
single-year class stocking is presented in the briefs.
-14-
specific requirements of the injunction. Atlantic Salmon II, 257
F. Supp. 2d at 435.
Accordingly, our concern here is with an injunction that
requires more of the companies than an agency permit sanctioned by
the federal statute. And, if the companies had never violated the
statute and now held a valid state permit, the shield provision in
the statute would protect the companies as to future operations, 33
U.S.C. § 1342(k) (2000). In such a case we would agree that the
district court could not substitute its view as to what the Clean
Water Act required for that of the agency.
Here, however, the companies have violated the statute;
and, despite the companies' argument to the contrary, nothing in
the shield provision's language directly addresses the question
whether and when in such a situation the district court's authority
gives way to the agency's. This is hardly unique: overlapping
grants of authority are the common stuff of statutes and the fare
of judicial decisions. 2 Pierce, Administrative Law Treatise § 14-
1 (4th ed. 2002). Here Congress may never have thought about the
precise issue of how the shield provision should affect a district
court order issued before a permit and designed to remedy pre-
permit violations. Certainly nothing definitive is cited to us.
Sensibly reconciling court and agency power is not very
difficult. In our view, the fact that violations have occurred in
the past does not generally strip the violator of the shield's
-15-
protection as to future operations; but so long as a district court
does not reduce the environmental protection provided by the
permit, the court may grant additional injunctive relief governing
the post-permit operations of the companies insofar as the court is
remedying harm caused by their past violations. This is a loose
formulation, but it is sufficient for the present case.
This premise gives meaning to the statute's grant of
enforcement authority to the court without undercutting the ability
of the agency to regulate generally through the permitting process.
Conventionally, a court's equitable power to enforce a statute
includes the power to provide remedies for past violations--an area
in which the courts have settled authority and competence,
Weinberger v. Romero-Barcelo, 456 U.S. 305 (1982), and "the
comprehensiveness of this equitable jurisdiction is not to be
denied or limited in the absence of a clear and valid legislative
command." Id. at 313 (quoting Porter v. Warner Holding Co., 328
U.S. 395, 398 (1946)); accord United States v. Mass. Water Res.
Auth., 256 F.3d 36, 48 (1st Cir. 2001).
The language of the enforcement provision is generous: it
says that the district court has authority "to enforce [] an
effluent standard or limitation," 33 U.S.C. § 1365(a), a phrase
that encompasses the pollution ban in this case. Atlantic Salmon
I, 215 F. Supp. 2d at 245-46, 256-57. Nothing in this language
precludes, as part of this enforcement authority, measures
-16-
remediating the harm caused by an existing violation, nor have we
been cited to any legislative history or circuit precedent imposing
such a limitation. Cf. United States v. Alcoa, 98 F. Supp. 2d 1031
(N.D. Ind. 2000).
This view does not disregard the shield provision which
still fully protects non-violators and also protects violators
except so far as more may be required of them than of others until
they have repaired the damage they have done. True, for this
limited purpose, the agency's judgment that less is necessary will
not control; but it is hardly inevitable that the agency's general
permit calculus will focus on the special remediation that may be
required by a violator's individual past transgressions. In any
case the statute gives the district court authority to make this
judgment so far as it is remedial.
Of course, if the district court thought that the
agency's general permit requirements were themselves adequate to
remedy past violations, it might defer to the agency's solution.
But, so far as authority goes, the remedying of past violations, so
long as it does not reduce protection ordered by the agency, is a
matter of district court judgment reviewed for abuse of discretion.
United States v. Deaton, 332 F.3d 698, 714 (4th Cir. 2003). That
does not mean that a district court's judgment is untrammeled but
only that it is not ousted by the later grant of a permit.
-17-
There is not much direct precedent but the closest case
in point comports with our own reading.5 In National Resources
Defense Council v. Southwest Marine, Inc., 236 F.3d 985 (9th Cir.
2000), the district court was concerned with a company that had a
permit but had been violating its terms--not a situation identical
to our case but somewhat analogous. On appeal, the question was
whether the district court was confined to merely ordering that the
permit be observed or whether it could impose additional
obligations to remedy the violation. The court rejected the more
restrictive view, saying (id. at 1000 (quoting Alaska Ctr. for
Env't v. Browner, 20 F.3d 981, 986 (9th Cir. 1994))):
According to Defendant, a court may do little
more than tell the violator to comply with the
applicable [state plan] requirements. . . .
We do not agree that a district court's
equitable authority is so cramped. The
authority to "enforce" an existing requirement
is more than the authority to declare that the
requirement exists and repeat that it must be
followed. So long as the district court's
equitable measures are reasonably calculated
to "remedy an established wrong," they are not
an abuse of discretion.
The companies say that in Southwest Marine there was less
or no "conflict" between the plan and the injunctive relief. But
the Ninth Circuit's broad proposition--that the court may go where
5
There are also some consonant cases involving different
sections of the Clean Water Act that are in accord with our
approach. See, e.g., Deaton, 332 F.3d at 713-14 (affirming remedial
injunction for violation of the statute, even though the remedial
order required defendants to do more than what would be required to
comply with the statute had they never violated the Act).
-18-
the agency's plan did not in order to remedy a past violation--is
what is relevant. As we have seen, the "conflict" in this case is
not a dangerous one. It is confined to injunctive measures that do
or may go beyond state protections for the purpose of remedying
past violations and vindicating the statutory prohibition on non-
permitted pollution.
Whether this last proposition governs the present case is
debated by the companies, and this is not surprising. The district
court's injunction, after all, was framed before the general permit
became effective. Thus, the district court was not at the time
necessarily confined to remedying past violations (as opposed to
preventing new ones based on its own view of the Clean Water Act).
Nevertheless, as we will see, the district court's remedial aim is
sufficiently clear as to the three contested provisions that a
remand merely to make the court spell out this remedial purpose
even more clearly would be a waste of time.
The district court's decision as to all three of the
contested requirements had a remedial purpose. This is borne out
by statements of the district court, Atlantic Salmon II, 257 F.
Supp. 2d at 414, 419-21, 419 n.3, 420 n.5, 428-30, and by ample, if
originally disputed, evidence as to the ongoing harm to the ocean
and the native fish population caused by past violations. The
varying periods set for fallowing further evidence a purpose to
remedy past violations and not just to set general standards for
-19-
the future based on a different view of how all companies should
operate.
In what is really a legal argument rather than one
concerned with actual intent, the companies say that the purpose
cannot be remedial because the injunction--like a permit--regulates
future conduct. This is a classic non sequitur. Injunctive
remedies for past harm commonly dictate future conduct so as to
mitigate past harm. Lovell v. Brennan, 728 F.2d 560, 562-63 (1st
Cir. 1984). To say that the injunction looks to the future does
not alter the fact that it is rooted in past violations, nor
prevent its aims or its effects from being remedial.
Conceivably, the companies could have challenged the
substantive findings linking the admitted past violations to the
remedial provisions of the injunction. They do so only in one
respect, namely, by arguing at the very end of their main brief
that escaping non-native salmon do not degrade the native species
and so the remedial provision is without support even if it is
otherwise within the district court's authority. They point to
gaps in the testimony of USPIRG's expert, along with testimony by
their own expert at the remedy hearing that non-native salmon do
not cause genetic damage to native salmon.
This is a permissible attack but hopeless on the facts.
The companies' expert may or may not take a minority view among
experts, but in any event USPIRG presented an expert who took the
-20-
opposite view and specifically refuted the companies' expert. The
district court credited USPIRG's expert and was satisfied "beyond
any reasonable doubt that use of [non-native salmon] stocks
imperils the survival of wild salmon." Atlantic Salmon II, 257 F.
Supp. 2d at 428 n.16. This conclusion was neither clearly
erroneous nor irrational. That the Maine Board's own general
permit severely limits non-native stocking further undermines the
position urged by the companies.
In their reply brief, the companies now offer a further
quite different legal argument against treating the injunction as
a remedial measure. They say that, whether so intended or
supported, any remedial injunction is barred by statutory language
that precludes citizen suits where there is no current violation
but only a past violation that has ceased. Specifically, the
citizen suit provision says: "[A]ny citizen may commence a civil
action on his own behalf . . . against any person . . . who is
alleged to be in violation of . . . an effluent standard or
limitation. . . . The district courts shall have jurisdiction .
. . to enforce such an effluent standard or limitation. . . ." 33
U.S.C. § 1365(a) (2000) (emphasis added).
This argument may be forfeit because not presented in the
opening brief, Rivera-Muriente v. Agosto-Alicea, 959 F.2d 349, 354
(1st Cir. 1992), but it is useful to lay it to rest. The statute's
use of the present tense does limit the district court's
-21-
authority; only citizen suits alleging that defendants are in
violation of the Clean Water Act at the time suit is brought are
cognizeable. Gwaltney v. Chesapeake Bay Found., 484 U.S. 49, 64-67
(1987). Accordingly, if the suit alleges a past violation but no
present violation, it is subject to dismissal, at least assuming a
timely objection (whether the requirement is jurisdictional or can
be waived need not be decided here). Id. at 57-64.
But once a citizen suit is brought and establishes a
present violation, there is nothing in the statute or in Gwaltney
that prevents a court from ordering equitable relief to remedy the
harm done in the past. See Romero-Barcelo, 456 U.S. at 313, 318,
& related discussion above. Nor would it make policy sense to
allow such a suit or remedy, if legitimate when brought, to be
defeated by having the offender cease the violation as soon as the
suit is filed while leaving the past harm unremedied. Gwaltney,
484 U.S. at 69 (Scalia, J., concurring).
We turn, finally, to two arguments that the companies
have not made on this appeal. Notably, in the district court, the
companies invoked the doctrine of primary jurisdiction. They were
unsuccessful, Atlantic Salmon II, 257 F. Supp. 2d at 426, and have
not pursued the issue in this court. Nevertheless, the interests
served by the doctrine are such that a court may choose to invoke
it on its own even if neither side raises the concern. So
-22-
something ought to be said about an issue implicit in the
controversy and one that could easily arise in future cases.
In a nutshell, the primary jurisdiction doctrine permits
and occasionally requires a court to stay its hand while allowing
an agency to address issues within its ken. Ass'n of Int'l Auto.
Mfrs. v. Comm'r, Mass. Dep't of Envt'l Prot., 196 F.3d 302, 304
(1st Cir. 1999); 2 Pierce, supra, § 14-1. Although sometimes
treated as a mechanical and rigid requirement, the modern view is
more flexible, United States v. W. Pac. R.R. Co., 352 U.S. 59, 64
(1956) ("No fixed formula exists . . . ."), and the decision
usually depends on whether a reference will advance the sound
disposition of the court case and whether failure to refer will
impair the statutory scheme or undermine the agency to which the
reference might be made. Pejepscot Indus. Park, Inc. v. Maine
Cent. R.R. Co., 215 F.3d 195, 205 (1st Cir. 2000) (listing relevant
factors).
In this instance, the underlying scientific issues are
clearly technical ones--a factor that encourages a reference to an
agency--but expert testimony was employed in the court proceeding.
Weighing against a reference were inter alia the need for
reasonable dispatch--matched against a decade of delay by the
pertinent agencies--and the necessary focus upon the actions of two
particular companies. Indeed, we were advised at oral argument
that USPIRG's efforts to broaden the Maine general permit
-23-
proceeding to include special concerns raised by the companies'
past violations were rejected.
Conversely, because the district court's injunction does
no more than impose additional constraints, it cannot undermine the
central thrust of the Maine general permit regime; and, the court
proceedings having now been completed, invoking the assistance of
the agency would be a waste of time. Accordingly, a refusal in this
case to make a primary jurisdiction reference prior to the state's
issuance of the permit was neither a mistake of law nor an abuse of
discretion. See also Student Pub. Interest Research Group v.
Fritzsche, Dodge & Olcott, Inc., 579 F. Supp. 1528, 1537 (D.N.J.
1984) (suggesting that primary jurisdiction should be invoked
sparingly where it would preempt a citizen suit under the Clean
Water Act).
A second issue not squarely raised by appellants also
deserves mention. The injunction is inherently time limited as to
one aspect of relief; the fallowing periods prescribed are only for
one cycle beginning after the injunction. But the prohibitions on
non-native stocking and inclusion of more than a single-year class
of salmon in a pen appear to be permanent. Yet there may be doubt
whether such specific provisions are permanently needed to remedy
past harms which, in the nature of things, are likely to be
assuaged with the passage of time. Cf. Swann v. Charlotte-
-24-
Mecklenburg Bd. of Ed., 402 U.S. 1, 32 (1971); Quinn v. City of
Boston, 325 F.3d 18, 27 (1st Cir. 2003).
Once the past violations are remedied, the companies are
normally entitled to be regulated as to the details of their
operations on the same basis as other companies that do or might
operate in Maine. If the Maine Board's permit is defective in its
detailed prescriptions, the remedy lies with an EPA veto or review
in the state courts. Given that the companies have not raised this
objection directly, we think the sound course is leave it to them
to seek modification of the injunction if and when they can show
that their past harms have been remedied.
The judgment of the district court is affirmed without
prejudice to future requests in the district court for
modifications of the injunction. The mandate shall issue forthwith
without prejudice to petitions for rehearing or rehearing en banc.
It is so ordered.
-25-