COURT OF APPEALS
SECOND DISTRICT OF TEXAS
FORT WORTH
NO. 02-14-00268-CV
TOWN CENTER MALL, L.P. APPELLANT
V.
NEVADA C. DYER, D/B/A ANKAS APPELLEE
ENTERPRISES
----------
FROM THE 236TH DISTRICT COURT OF TARRANT COUNTY
TRIAL COURT NO. 236-241807-09
----------
MEMORANDUM OPINION1
----------
I. INTRODUCTION
In eight issues, Appellant Town Center Mall, L.P. (TCM) appeals from a
final judgment awarding damages and attorney’s fees to Appellee Nevada C.
Dyer, d/b/a Ankas Enterprises. We will affirm.
1
See Tex. R. App. P. 47.4.
II. BACKGROUND
In 2004, TCM purchased “La Gran Plaza,” a retail mall located in Fort
Worth. The following year, after entering into an “Economic Development
Program Agreement” with the City of Fort Worth, TCM began a large-scale
renovation of the property. It hired project managers and entered into written
agreements with contractors to perform the renovation.2
One of the project managers that TCM hired was Tony Ozuna. Ozuna was
responsible for overseeing the completion of part of the renovation, and he
approached a number of people about submitting bids, including wife, Latecha,
and his sister, Dyer. Dyer and Latecha had worked together in the past and were
interested in participating in the renovation. They therefore filed an assumed
name certificate and placed a bid under the name of Ankas Enterprises to
perform certain work.3 TCM accepted the bid and contracted with Ankas in
August 2005 to perform the agreed-upon services. Over the next seven months,
TCM and Ankas entered into six additional written construction contracts for the
performance of various services as part of the renovation of the mall. Ankas also
signed fourteen “Release and Waiver of Lien and Indemnity Agreement[s]” when
TCM paid Ankas for work performed.
2
Boxer Property Management Corporation managed the property.
3
Dyer and Latecha both filed an assumed name certificate—Dyer identified
the business as “Ankass Ent” and Latecha identified the business as “Ankas
Ent.” At the time, neither realized that the other was going to file the document.
Dyer applied for a tax-identification number and used her Social Security
number.
2
According to Ozuna, the renovation was a “very fast-tracked project” and
proceeded “very quickly.” Although Ankas and TCM executed seven written
contracts that detailed the scope of the work to be performed and the
compensation to be paid, Ankas and other contractors were “often” asked to
perform additional services that were not covered by any written contract.4 The
written contracts contained a provision requiring that change orders be used to
document “[a]ny alterations, changes[,] or revisions to the [w]ork, or any
increases to the [c]ontract [p]rice,” but TCM never issued a single change order
for any extra-contractual work that Ankas performed. Dyer nonetheless
documented those “miscellaneous tasks” and requested that Ankas be paid for
them. TCM ultimately paid Ankas a total of $501,491.07 for the work that it
performed on the renovation project. Of that amount, approximately $194,000
accounted for work that was not covered by any of the seven written contracts
that Ankas and TCM had executed.
Dyer, d/b/a/ Ankas Enterprises, later sued TCM for breach of contract,
sworn account, and quantum meruit, alleging that TCM owed Ankas an additional
$116,000 for work performed on the project. TCM denied Dyer’s allegations,
4
For example, one written contract between Ankas and TCM required
Ankas to construct wired “cages”—spaces measuring about 10 feet x 10 feet that
vendors occupied to sell their wares. At times, Ashwin Thakker, TCM’s
employee responsible for “contract administration,” or Shelly Campbell, the
leasing manager, directed Ankas employees to modify a cage when the tenant
so requested. Ozuna also asked Ankas to perform extra-contractual work.
3
asserted verified pleas, and alleged counterclaims for fraudulent lien and fraud.5
Following a bench trial, the trial court signed a final judgment awarding Dyer
$139,787.61; pre- and post-judgment interest; and attorney’s fees.6 The trial
court denied TCM’s fraud claims and also entered findings of fact and
conclusions of law, finding in part the following:
5. There were seven (7) written contracts entered into
between Plaintiff and Defendant. In addition to the work as outlined
in those seven contracts, Defendant had Plaintiff perform numerous
other items of work outside the scope of the original contracts which
should have been reflected as work change orders, but was not.
Plaintiff was not fully paid on contracts 2, 4 & 5.
....
10. Plaintiff’s evidence, which established that Plaintiff was
entitled to a recovery, was not contested by any credible evidence
offered by Defendant. Defendant relied upon Lien Releases in an
attempt to vary the terms of written contracts, prohibited under
provisions 1.2 and 14.8 of those very same contracts, unless signed
by both the Owner and Contractor. The evidence established that
the first Lien Release was for a material draw and the last Lien
Release was for a partial payment (of an undisclosed contract or
change order item), indicative of both parties[’] understanding that
further monies are due. Plaintiff acknowledged signing those in
order to obtain payment, but she did not intend to release Defendant
5
Regarding the fraudulent lien claim, in June 2006, Dyer filed a mechanic’s
and materialmen’s lien affidavit against the mall, claiming that TCM owed Ankas
approximately $105,000 for work performed, materials, or both. Dyer released
the lien during the pendency of this litigation. TCM’s fraud-by-nondisclosure
claim centered around Ozuna’s relationship with Dyer and Latecha.
6
The trial court awarded Dyer “attorney fees of $70,000[] through the date
of [the] judgment”; “attorney fees of $20,000.00 if appealed to the court of
appeals”; and “attorney fees of $10,000.00 if appealed to the Texas Supreme
Court.”
4
for work performed by Plaintiff but not yet paid for by Defendant as
evidenced by repeated invoicing. . . .
11. The evidence at trial established that the Defendant
owed Plaintiff the sum of $116,561.47, as set forth in Plaintiff’s
Second Amended Petition.
12. Defendant’s Vice-President, Michael Pariza, testified
that Plaintiff should not have been back charged $23,226.14, rather
that amount should have been charged off to the project by the
Defendant.
The trial court concluded in part as follows:
1. From August 2005 through March 2006, Plaintiff and
Defendant entered into seven (7) contracts. Plaintiff performed its
obligations under these contracts. Defendant failed to pay the full
amounts due for contacts 2, 4, [a]nd 5. . . . Defendant requested
change order work to existing contracts which Plaintiff performed but
was not fully compensated by Defendant.
2. Plaintiff furnished services to Defendant and charged
the usual, customary, and reasonable price for those services.
Plaintiff has provided Defendant a systematic record of these
transactions. All lawful offsets, payments, and credits have been
applied to Defendant’s account. The account was not paid in full
and the damages in the amount of $116,561.47 are liquidated and
proved by the Affidavit of Nevada Dyer attached to Plaintiff’s 2nd
Amended Petition.
3. The trial testimony of Defendant’s Vice President,
Michael Pariza, established that Defendant erred in taking credits
totaling $23,226.14 from monies owed Plaintiff for services rendered
....
4. In addition to breach of contract and sworn account,
Plaintiff also pled for quantum meruit, an equitable remedy to
compensate the Plaintiff when goods or services are provided at
Defendant’s request absent an express agreement. . . . Plaintiff
established the following elements of quantum meruit:
A. Plaintiff provided services or materials;
B. The services or materials were provided for Defendant;
5
C. Defendant accepted the services or materials; and,
D. Defendant had reasonable notice that Plaintiff expected
compensation for the services or materials
TCM appeals.
III. STANDING
In its first issue, TCM argues that the trial court lacked subject-matter
jurisdiction over Dyer’s claims because she did not have standing to assert
claims involving alleged breaches of contractual or quasi-contractual obligations
owed only to Ankas. Dyer responds that TCM confuses standing with capacity
and waived any challenge to Dyer’s capacity to sue by not raising the issue in a
verified pleading.
“A plaintiff has standing when it is personally aggrieved, regardless of
whether it is acting with legal authority; a party has capacity when it has the legal
authority to act, regardless of whether it has a justiciable interest in the
controversy.” Nootsie, Ltd. v. Williamson Cnty. Appraisal Dist., 925 S.W.2d 659,
661 (Tex. 1996). A challenge to who owns a claim raises the issue of capacity,
not standing. Prostok v. Browning, 112 S.W.3d 876, 921 (Tex. App.—Dallas
2003), rev’d in part on other grounds, 165 S.W.3d 336 (Tex. 2005); see
Heartland Holdings, Inc. v. U.S. Trust Co. of Tex. N.A., 316 S.W.3d 1, 7 (Tex.
App.—Houston [14th Dist.] 2010, no pet.) (“When it is established that a breach
of contract plaintiff lacks entitlement to sue on a contract, the proper disposition
may be summary judgment on the merits, but it is not dismissal for want of
jurisdiction.”).
6
According to TCM, “Dyer was not the proper party to bring any claims
concerning the business dealings between Ankas and [TCM].” This complaint
relates to capacity rather than to standing. See Dakil v. Lege, 408 S.W.3d 9, 11
(Tex. App.—El Paso 2012, no pet.) (“Dakil claims that Lege was not a proper
party to file a breach of contract action because he brought the original suit
based on invoices from 2-L Contractors Inc. but he had not filed an assumed-
name certificate. These complaints relate to capacity rather than standing.”).
Capacity must be challenged by a verified pleading or it is waived. Nootsie, 925
S.W.2d at 662; see Tex. R. Civ. P. 93. TCM filed a verified pleading asserting
that Latecha was a necessary party to the lawsuit, but it did not raise Dyer’s
capacity to sue under an assumed name certificate that someone else (Latecha)
had filed. See Tex. R. Civ. P. 93(14). TCM therefore waived this complaint. We
overrule its first issue.
IV. BREACH OF CONTRACT AND QUANTUM MERUIT
In its second and fourth issues, TCM argues that the evidence is legally
insufficient to support the trial court’s judgment insofar as it is premised upon
Dyer’s claims for breach of contract and quantum meruit.
We may sustain a legal sufficiency challenge only when (1) the record
discloses a complete absence of evidence of a vital fact; (2) the court is barred
by rules of law or of evidence from giving weight to the only evidence offered to
prove a vital fact; (3) the evidence offered to prove a vital fact is no more than a
mere scintilla; or (4) the evidence establishes conclusively the opposite of a vital
7
fact. Uniroyal Goodrich Tire Co. v. Martinez, 977 S.W.2d 328, 334 (Tex. 1998),
cert. denied, 526 U.S. 1040 (1999); Robert W. Calvert, “No Evidence” and
“Insufficient Evidence” Points of Error, 38 Tex. L. Rev. 361, 362–63 (1960). In
determining whether there is legally sufficient evidence to support the finding
under review, we must consider evidence favorable to the finding if a reasonable
factfinder could and disregard evidence contrary to the finding unless a
reasonable factfinder could not. Cent. Ready Mix Concrete Co. v. Islas, 228
S.W.3d 649, 651 (Tex. 2007); City of Keller v. Wilson, 168 S.W.3d 802, 807, 827
(Tex. 2005). Any ultimate fact may be proved by circumstantial evidence.
Russell v. Russell, 865 S.W.2d 929, 933 (Tex. 1993). A fact is established by
circumstantial evidence when the fact may be fairly and reasonably inferred from
other facts proved in the case. Id.
The elements of a breach-of-contract claim are (1) the existence of a valid
contract, (2) performance or tendered performance by the plaintiff, (3) breach of
the contract by the defendant, and (4) resulting damages to the plaintiff. Rice v.
Metro. Life Ins. Co., 324 S.W.3d 660, 666 (Tex. App.—Fort Worth 2010, no pet.).
By contrast, quantum meruit is an equitable theory of recovery based on an
implied agreement to pay for benefits received. Heldenfels Bros., Inc. v. City of
Corpus Christi, 832 S.W.2d 39, 41 (Tex. 1992). The elements of a quantum-
meruit claim are (1) valuable services or materials provided by plaintiff to the
defendant, (2) who accepted the services or materials, (3) under such
circumstances as would reasonably notify defendant that the plaintiff expected to
8
be paid. BP Auto., L.P. v. RML Waxahachie Dodge, L.L.C., 448 S.W.3d 562,
572 (Tex. App.—Houston [1st Dist.] 2014, no pet.).
TCM initially contends in its second issue that Dyer could not have
prevailed on her contract claim “because she was not a party to any contract
sued upon.” Similarly, TCM argues in its fourth issue that Dyer could not have
prevailed under a quantum meruit theory because “any services or materials
allegedly provided outside the scope of the contracts [were] performed by Ankas
Enterprises.” Both arguments are variations of the same issue that we already
considered regarding capacity. We therefore overrule this part of TCM’s second
and fourth issues.
TCM challenges elements (2) and (3) of Dyer’s contract claim, arguing that
there is no evidence that Ankas performed and no evidence that TCM failed to
comply with its pertinent contractual obligations. In advancing this argument,
TCM contends that the trial court never admitted Dyer’s exhibits into evidence
and that we are therefore limited to considering only the testimonial evidence
admitted during trial.7 We need not decide whether Dyer’s exhibits were
7
At the conclusion of the bench trial, Dyer offered two trial notebooks into
evidence—an “unedited” version and an “edited” version. TCM re-urged the
written objections that it had previously lodged against Dyer’s evidence, and the
trial court stated that it would “take the admission of [Dyer’s] two notebooks
under advisement.” Thereafter, in this order, the trial court signed a final
judgment in favor of Dyer, TCM filed a “Motion for Entry of Order on Defendant’s
Objections to the Admission of Plaintiff’s Trial Exhibits,” and the trial court signed
an order denying each and every one of TCM’s objections. TCM and Dyer
disagree about whether the trial court’s post-judgment order denying TCM’s
objections impliedly admitted Dyer’s exhibits.
9
admitted because even without considering them, legally sufficient evidence
supports the trial court’s judgment.
Dyer testified that TCM failed to pay Ankas in full for (1) the contractual
work and (2) the extra-contractual, “miscellaneous tasks” that Ankas had
performed on the renovation, and Ozuna testified that Ankas had performed work
on the renovation and was owed money. Dyer explained that TCM had paid
Ankas a total of $501,491.07 but that Ankas had performed work totaling
$641,278.68, leaving a balance due and owing of $139,787.61, the same amount
that the trial court awarded Dyer. Regarding the unpaid amounts for work
covered by a written contract—which support an award for breach of contract—
Dyer testified that TCM owed Ankas $7,013.75 for Contract “2”; $40,500 for
Contract “4”; and $10,800 for Contract “5.” Regarding the extra-contractual,
“miscellaneous tasks” that Ankas performed—which support an award under a
quantum-meruit theory—Dyer identified a number of the tasks and testified that
TCM owed Ankas $32,771. Dyer failed to disclose an amount owed for several
of the tasks (rain-damage repair and modifications to cages), but TCM’s own
documentary evidence reflected that TCM owed Ankas $6,450 for those tasks.
TCM’s evidence also showed that it owed Ankas at least $2,100 for two
additional “miscellaneous tasks” that Ankas had performed (converting cages
and repairing walls). Finally, the trial court’s award included an amount that TCM
10
had improperly back charged to Ankas—$40,172.8 To the extent that any of the
evidence conflicted, the trial court, as factfinder, could have resolved the conflict
in favor of Dyer. See City of Keller, 168 S.W.3d at 820.
TCM argues that Dyer’s evidence of extra-contractual, “miscellaneous
tasks” is barred by the parol evidence rule. The parol evidence rule did not bar
testimony about the extra-contractual tasks because that evidence was not
admitted to construe the terms of the written contracts upon which Ankas was
underpaid. See Gail v. Berry, 343 S.W.3d 520, 523 (Tex. App.—Eastland 2011,
pet. denied) (“The parol evidence rule is a rule of substantive law which provides
that, in the absence of fraud, accident, or mistake, extrinsic evidence is not
admissible to vary, add to, or contradict the terms of a written contract that is
facially complete and unambiguous.”).
TCM contends that there is no evidence that Dyer gave it notice that Ankas
expected to be paid for the “miscellaneous tasks” that Ankas performed, but Dyer
testified that she documented those tasks and requested that Ankas be paid for
them. Moreover, it simply cannot be ignored that TCM paid Ankas approximately
$194,000 for work that was not covered by any of the seven written contracts that
Ankas and TCM had executed. The trial court therefore could have reasonably
inferred that TCM had notice that Ankas expected to be paid for all of the
miscellaneous tasks. See City of Keller, 168 S.W.3d at 821.
8
This figure represents two different amounts that were improperly back
charged—one for $16,946 and one for $23,226.
11
TCM further complains that the trial court’s findings of fact “are insufficient
to support a quantum meruit cause of action” because there is no specific finding
that TCM had reasonable notice that Dyer expected compensation for the
“miscellaneous tasks” that Ankas performed.9 “When a court makes findings of
fact, but inadvertently omits an essential element of a ground of recovery or
defense, the presumption of validity will supply the omitted element by
implication.” Vickery v. Comm’n for Lawyer Discipline, 5 S.W.3d 241, 252 (Tex.
App.—Houston [14th Dist.] 1999, pet. denied); see Tex. R. Civ. P. 299. The trial
court’s findings implicate elements (1) and (2) of Dyer’s quantum-meruit claim;
consequently, the omission of the notice-of-compensation element is deemed to
be inadvertent, and we presume that the trial court made the finding in support of
its judgment.10 See Vickery, 5 S.W.3d at 252.
Lastly, TCM argues that Dyer cannot recover under a theory of quantum
meruit because she entered into written construction contracts with TCM for the
performance of work towards the renovation. “[A]n express contract between the
parties precludes a plaintiff from recovering for services rendered in quantum
9
We note that that the trial court’s conclusions of law address each
quantum-meruit element.
10
TCM directs us to Vortt Exploration Co., Inc. v. Chevron U.S.A., Inc., 787
S.W.2d 942 (Tex. 1990), but it is inapposite. There, the supreme court
considered whether an express finding was sufficient to state the notice-of-
compensation element. Id. at 944‒45. We consider the opposite situation in this
case—what effect the omission of that element from the trial court’s findings has
on the judgment, if any.
12
meruit if the contract covers those services or materials.” Christus Health v.
Quality Infusion Care, Inc., 359 S.W.3d 719, 723 (Tex. App.—Houston [1st Dist.]
2011, no pet.) (emphasis added) (citing Fortune Prod. Co. v. Conoco, Inc., 52
S.W.3d 671, 683‒84 (Tex. 2000)). But “[w]hen the evidence shows that no
contract covers the service at issue, [then] the question of whether a party may
recover in quantum meruit is for the trier of fact.” Id. at 724. As explained in
detail above, no contract covered the amounts that Dyer sought to recover for the
“miscellaneous tasks” that Ankas performed.11
The evidence is legally sufficient to support the trial court’s judgment
insofar as it is premised upon Dyer’s breach-of-contract and quantum-meruit
claims. See City of Keller, 168 S.W.3d at 807, 827. We overrule the remainder
of TCM’s second and fourth issues. Having overruled TCM’s second and fourth
issues, we need not address its third issue challenging Dyer’s recovery under a
sworn-account theory. See Tex. R. App. P. 47.1.
V. OBJECTIONS
TCM argues in its fifth issue that the trial court erred by overruling its
objections to Dyer’s tendered exhibits. We concluded above that the evidence is
legally sufficient to support the trial court’s judgment even without considering the
challenged exhibits. Therefore, any error in denying TCM’s evidentiary
11
Hence, our reference to those tasks as “extra-contractual.”
13
objections was harmless. See Tex. R. App. P. 44.1(a). We overrule TCM’s fifth
issue.
VI. RELEASES
In its sixth issue, TCM argues that all of Dyer’s claims—or at a minimum,
her claim for breach of the written contracts—are barred by “valid and
enforceable” releases that she signed when TCM paid Ankas for work performed
on the renovation. We construe TCM’s argument as a challenge to the legal
sufficiency of the evidence to support the trial court’s implied finding that Dyer did
not agree to release her claims against TCM for amounts remaining unpaid
under the written contracts or for “miscellaneous tasks” performed.
A release is a contract. Williams v. Glash, 789 S.W.2d 261, 264 (Tex.
1990). Therefore, it is subject to the same requirements as any other contract.
In re J.P., 296 S.W.3d 830, 835 (Tex. App.—Fort Worth 2009, no pet.). As we
set out above, the existence of a valid, binding contract is one of the essential
elements of a breach-of-contract claim. See Rice, 324 S.W.3d at 666. In that
regard,
[p]arties form a binding contract when the following elements are
present: (1) an offer, (2) an acceptance in strict compliance with the
terms of the offer, (3) a meeting of the minds, (4) each party’s
consent to the terms, and (5) execution and delivery of the contract
with the intent that it be mutual and binding. The determination of a
meeting of the minds, and thus offer and acceptance, is based on
the objective standard of what the parties said and did and not on
their subjective state of mind. Therefore, whether the parties
intended to enter into a binding agreement is often a question of
fact. It is only when the intent of the parties is clear and
14
unambiguous on the face of the agreement may the court determine
intent as a matter of law.
McCoy v. Alden Indus., Inc., No. 02-12-00200-CV, 2015 WL 4268363, at *9 (Tex.
App.—Fort Worth July 9, 2015, no pet.) (citations omitted).
The evidence shows that when TCM issued a check, it also required that a
release be signed. Each form release stated that the corresponding payment
was for “all amounts owed” to the contractor under a particular contract.
However, according to Dyer, when she signed a release upon being given a
check by TCM and the payment was for less than the total amount owed on the
job for which the check was issued, she did not understand it to mean that Ankas
had been paid in full. For example, the first check that Ankas received from TCM
was for $45,000. Dyer explained that when TCM issued the check, Ankas had
not yet performed any work in exchange for the partial payment; it was merely an
advance for materials. Ozuna testified similarly—the lien releases were only for
partial payment. Although each release contained language that was intended to
match the release to a particular contract, six of the fourteen releases that Dyer
signed referenced a date that did not correspond to any particular signed
contract, and four of the releases failed to reference any corresponding contract
at all.
The parties thus disputed whether a given release applied to all amounts
owed under a corresponding contract or to only the amount then paid when the
release was signed. Consequently, a fact issue existed as to whether the parties
15
achieved a meeting of the minds, and therefore formed a valid, binding contract,
to release all amounts due and owing under a contract when Dyer signed a
release for less than the total amount owed under the purported corresponding
contract. The trial court chose to resolve the disputed issue in favor of Dyer—
i.e., that Ankas had not agreed to release its claims for amounts remaining
unpaid either under the written contracts or for the “miscellaneous tasks”
performed—and given the conflicting evidence, we are not at liberty to disturb
that finding. See City of Keller, 168 S.W.3d at 827; see also Green Int’l, Inc. v.
Solis, 951 S.W.2d 384, 388‒89 (Tex. 1997) (holding that waiver of lien releases
did not bar recovery for extra-contractual work performed). We overrule TCM’s
sixth issue.
VII. CASTEEL ERROR
Directing us to Crown Life Insurance Co. v. Casteel, TCM argues in its
seventh issue that “[i]n the event this Court determines that one or more of the
contracts found to have been breached below . . . , or the quasi-contractual
theories under which the trial court awarded liability, cannot justify the judgment,
then this Court must presume harm in the entirety of the judgment.” See 22
S.W.3d 378, 388 (Tex. 2000) (holding that “when a trial court submits a single
broad-form liability question incorporating multiple theories of liability, the error is
harmful and a new trial is required when the appellate court cannot determine
whether the jury based its verdict on an improperly submitted invalid theory.”).
We have not determined that any particular theory of recovery asserted by Dyer
16
cannot justify the judgment. Rather, we have concluded that legally sufficient
evidence supports the trial court’s judgment insofar as it is premised upon Dyer’s
claims for breach of contract and quantum meruit. For this and other reasons,
this case involves no presumed-harm Casteel issue. We overrule TCM’s
seventh issue.
VIII. ATTORNEY’S FEES
TCM argues in the first part of its eighth issue that Dyer is not entitled to
recover attorney’s fees because she did not specifically plead for their recovery
pursuant to civil practice and remedies code chapter 38. See Tex. Civ. Prac. &
Rem. Code Ann. §§ 38.001‒.006 (West 2015). If a party pleads facts which, if
true, entitle her to the relief sought, then she need not specifically plead the
applicable statute in order to recover under it. Whallon v. City of Houston, 462
S.W.3d 146, 165 (Tex. App.—Houston [1st Dist.] 2015, no pet.); Mitchell v.
LaFlamme, 60 S.W.3d 123, 130 (Tex. App.—Houston [14th Dist.] 2000, no pet.).
Dyer generally pleaded for “[a]ttorney fees to be proved at [the] time of trial” and
recited facts in her petition in support of that pleading. TCM did not specially
except to the pleading. We hold that Dyer’s pleadings were sufficient to support
a claim for attorney’s fees under chapter 38. See, e.g., Bancservices Grp., Inc.
v. Strunk & Assocs., L.P., No. 14-03-00797-CV, 2005 WL 2674985, at *6 (Tex.
App.—Houston [14th Dist.] Oct. 20, 2005, pets. denied) (holding that general
pleading for attorney’s fees, coupled with facts detailing claim for breach of
17
contract, was sufficient to support claim for attorney’s fees under chapter 38);
Mitchell, 60 S.W.3d at 130 (same).
In the other part of its eighth issue, TCM argues that Dyer failed to offer
evidence of presentment under section 38.002(2) and made no showing of
compliance with section 38.002(3). See Tex. Civ. Prac. & Rem. Code Ann.
§ 38.002(2), (3). To recover attorney’s fees under chapter 38, “the claimant must
present the claim to the opposing party or to a duly authorized agent of the
opposing party,” and “payment for the just amount owed must not have been
tendered before the expiration of the 30th day after the claim is presented.” Id.
No particular form of presentment is required. France v. Am. Indem. Co., 648
S.W.2d 283, 286 (Tex. 1983). “[A]ll that is necessary is that a party show that its
assertion of a debt or claim and a request for compliance was made to the
opposing party, and the opposing party refused to pay the claim.” Standard
Constructors, Inc. v. Chevron Chem. Co., 101 S.W.3d 619, 627 (Tex. App.—
Houston [1st Dist.] 2003, pet. denied). Here, Dyer submitted invoices to TCM for
the work that Ankas had performed on the mall renovation, and Dyer testified that
TCM failed to pay Ankas for certain contractual and extra-contractual work that
Ankas performed on the renovation. The evidence was sufficient to show
compliance with civil practice and remedies code sections 38.002(2) and (3). We
overrule TCM’s eighth issue.
18
IX. CONCLUSION
Having overruled all of TCM’s issues, we affirm the trial court’s judgment.
/s/ Bill Meier
BILL MEIER
JUSTICE
PANEL: DAUPHINOT, WALKER, and MEIER, JJ.
DELIVERED: October 1, 2015
19