MEMORANDUM DECISION
FILED
Pursuant to Ind. Appellate Rule 65(D), Mar 07 2017, 9:03 am
this Memorandum Decision shall not be CLERK
Indiana Supreme Court
regarded as precedent or cited before any Court of Appeals
and Tax Court
court except for the purpose of establishing
the defense of res judicata, collateral
estoppel, or the law of the case.
ATTORNEYS FOR APPELLANT ATTORNEYS FOR APPELLEE
Robert E. Heidorn INDIANA UTILITY
P. Jason Stephenson REGULATORY COMMISSION
Vectren Corporation Curtis T. Hill, Jr.
Evansville, Indiana Attorney General of Indiana
Wayne C. Turner David Lee Steiner
Patrick A. Ziepolt Deputy Attorney General
Hoover Hull Turner LLP Indianapolis, Indiana
Indianapolis, Indiana
ATTORNEYS FOR AMICUS CURIAE Beth Krogel Roads
INDIANA ENERGY ASSOCIATION General Counsel
Derek R. Molter Jeremy R. Comeau
Jenny R. Buchheit Assistant General Counsel
Mark R. Alson Indiana Utility Regulatory
Kay E. Pashos Commission
Ice Miller LLP Indianapolis, Indiana
Indianapolis, Indiana
ATTORNEYS FOR AMICUS CURIAE
INDIANA INDUSTRIAL GROUP
Todd A. Richardson
Joseph P. Rompala
Lewis Kappes, P.C.
Indianapolis, Indiana
IN THE
COURT OF APPEALS OF INDIANA
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 1 of 18
Southern Indiana Gas & Electric March 7, 2017
Company d/b/a Vectren Energy Court of Appeals Case No.
Delivery of Indiana, Inc., 93A02-1604-EX-914
Appellant-Petitioner, Appeal from the Indiana Utility
Regulatory Commission
v. The Honorable Carol A. Stephan,
Commission Chair
Indiana Utility Regulatory
Commission, The Honorable James Huston and
The Honorable David Ziegner,
Appellee-Administrative Agency, Commissioners
and The Honorable Loraine L.
Seyfried,
Chief Administrative Law Judge
Indiana Office of Utility
Counselor, IURC Cause No. 44645
Appellee-Statutory Representative,
and
Citizens Action Coalition of
Indiana, Inc.,
Appellee-Intervenor
Crone, Judge.
Case Summary
[1] As required by statute, Southern Indiana Gas & Electric Company d/b/a
Vectren Energy Delivery of Indiana, Inc. (“Vectren South” or “Petitioner”),
filed a petition with the Indiana Utility Regulatory Commission
(“Commission”) seeking approval of its Electric Demand Side Management
(“DSM”) Plan for 2016-2017 (“Plan”). The Plan outlined Vectren South’s
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 2 of 18
energy-efficiency (“EE”) programs and their budgets and costs, including lost
revenues resulting from reduced demand for electricity. Indiana law requires
the Commission to allow an electricity supplier to recover reasonable lost
revenues associated with an energy-efficiency plan. The Commission held an
evidentiary hearing and issued an order purporting to find the Plan to be
reasonable in its entirety but limiting lost revenue recovery to four years or the
life of the energy-efficiency measure, whichever is less, or until rates are
implemented pursuant to a final order in Vectren South’s next base rate case,
whichever occurs earlier.
[2] Vectren South now appeals, arguing that the Commission erred in finding the
Plan to be reasonable in its entirety but capping lost revenue recovery at four
years. Vectren South also argues that the cap is arbitrary and capricious
because the Commission made no specific factual findings that the cap would
allow for the recovery of reasonable lost revenues. We agree on both counts
and therefore reverse and remand for further proceedings.
Facts and Procedural History
[3] Vectren South is a public utility based in Evansville that “provides electric
utility service to approximately 140,000 customers in six counties in
southwestern Indiana.” Appealed Order at 2. In June 2015, Vectren South
filed a petition with the Commission seeking approval of the Plan pursuant to
Indiana Code Section 8-1-8.5-10 (“Section 10”), which reads in pertinent part as
follows:
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 3 of 18
(h) Beginning not later than calendar year 2017, and not less than
one (1) time every three (3) years, an electricity supplier[1] shall
petition the commission for approval of a plan that includes:
(1) energy efficiency goals;
(2) energy efficiency programs to achieve the energy
efficiency goals;[2]
(3) program budgets and program costs [including lost
revenues and financial incentives approved by the
commission under subsection (o)3]; and
(4) evaluation, measurement, and verification [“EM&V”]
procedures that must include independent evaluation,
measurement, and verification.
An electricity supplier may submit a plan required under this
subsection to the commission for a determination of the overall
reasonableness of the plan either as part of a general basic rate
proceeding or as an independent proceeding.…
1
“Electricity supplier” means a public utility “that furnishes retail electric service to customers in Indiana.”
Ind. Code § 8-1-8.5-10(a). The term does not include a municipally owned utility and certain other
corporations. Id.
2
“Energy efficiency” means “a reduction in electricity use for a comparable level of electricity service.” Ind.
Code § 8-1-8.5-10(b). “Energy efficiency goals” means “all energy efficiency produced by cost effective plans
that are: (1) reasonably achievable; (2) consistent with an electricity supplier’s integrated resource plan; and
(3) designed to achieve an optimal balance of energy resources in an electricity supplier’s service territory.”
Ind. Code § 8-1-8.5-10(c). “Energy efficiency program” or “program” means “a program that is: (1)
sponsored by an electricity supplier; and (2) designed to implement energy efficiency improvements. The
term does not include a program designed primarily to reduce demand for limited intervals of time, such as
during peak electricity usage or emergency conditions.” Ind. Code § 8-1-8.5-10(d).
3
Ind. Code § 8-1-8.5-10(g)(3). “Lost revenues” means “the difference, if any, between: (1) revenues lost; and
(2) the variable operating and maintenance costs saved; by an electricity supplier as a result of implementing
energy efficiency programs.” Ind. Code § 8-1-8.5-10(e).
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 4 of 18
….
(j) In making a determination of the overall reasonableness of a
plan submitted under subsection (h), the commission shall
consider the following [ten factors, including]:
….
(4) The inclusion and reasonableness of procedures to
evaluate, measure, and verify the results of the energy
efficiency programs included in the plan, including the
alignment of the procedures with applicable environmental
regulations, including federal regulations concerning
credits for emission reductions.
….
(8) The lost revenues and financial incentives associated
with the plan and sought to be recovered or received by the
electricity supplier.
….
(10) Any other information the commission considers
necessary.
(k) If, after notice and hearing, the commission determines that
an electricity supplier’s plan is reasonable in its entirety, the
commission shall:
(1) approve the plan in its entirety;
(2) allow the electricity supplier to recover all associated
program costs on a timely basis through a periodic rate
adjustment mechanism; and
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 5 of 18
(3) allocate and assign costs associated with a program to
the class or classes of customers that are eligible to
participate in the program.
….
(m) If, after notice and hearing, the commission determines that
an electricity supplier’s plan is not reasonable in its entirety, the
commission shall issue an order setting forth the reasons
supporting its determination. The electricity supplier shall submit
a modified plan within a reasonable time. After notice and
hearing, the commission shall issue an order approving or
denying the modified plan. If the commission approves the
modified plan, the commission shall allow the electricity supplier
to recover program costs associated with the modified plan on a
timely basis through a periodic rate adjustment mechanism.
….
(o) If the commission finds a plan submitted by an electricity
supplier under subsection (h) to be reasonable, the commission
shall allow the electricity supplier to recover or receive the
following:
(1) Reasonable financial incentives that:
(A) encourage implementation of cost effective
energy efficiency programs; or
(B) eliminate or offset regulatory or financial bias:
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 6 of 18
(i) against energy efficiency programs;[4] or
(ii) in favor of supply side resources.
(2) Reasonable lost revenues.[5]
A retail rate adjustment mechanism proposed by an electricity
supplier under this section to implement the timely recovery of
program costs (including reasonable lost revenues) may be based
on a reasonable forecast, with consideration given to the
electricity supplier’s historical lost revenue forecasting accuracy.
If forecasted data is used, the retail rate adjustment mechanism
must include a reconciliation mechanism to correct for any
variance between the forecasted program costs (including
reasonable lost revenues and financial incentives) and the actual
program costs (including reasonable lost revenues and financial
incentives based on the evaluation, measurement, and
verification of the energy efficiency programs under the plan).
….
(q) The commission shall adopt:
4
A reduction in demand for electricity may lead to a reduction in a utility’s revenues, which in turn may lead
to a financial bias against promoting demand-reducing programs.
5
Vectren South points out that this provision is inconsistent with 170 Indiana Administrative Code (“IAC”)
4-8-6(a), which states that the Commission “may allow the utility to recover the utility’s lost revenue from the
implementation of a demand-side management program sponsored or instituted by the utility.” (Emphasis
added.) We note that an administrative agency may not make rules or regulations inconsistent with the
statute it is administering. Ind. Dep’t of State Revenue v. Best Ever Cos., 495 N.E.2d 785, 787 (Ind. Ct. App.
1986).
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 7 of 18
(1) rules under IC 4-22-2; or
(2) guidelines;
to assist electricity suppliers and industrial customers in
complying with this section.
[4] Citizens Action Coalition of Indiana, Inc. (“CAC”), was allowed to intervene
in Vectren South’s proceeding. In November 2015, the Commission held an
evidentiary hearing at which Vectren South, CAC, and the Indiana Office of
Utility Consumer Counselor (“OUCC”) appeared and presented evidence. In
March 2016, the Commission issued a twenty-eight-page order, which reads in
relevant part as follows:
6. Vectren South 2016-2017 Plan. The 2016-2017 Plan includes
the following DSM programs, the majority of which are current
programs …: [residential lighting, home energy assessment and
weatherization, appliance recycling, and smart thermostats, as
well as commercial and industrial new construction and retrofit
programs, among others].
7. Evidence.
[The Commission summarized the often conflicting evidence and
recommendations presented by Vectren South, the OUCC, and
CAC, including those regarding lost revenues and cost recovery.
The accuracy and adequacy of these findings are not at issue
here.]
8. Discussion and Commission Findings. Vectren South
requests approval of its Energy Efficiency Plan and authority to
recover program costs, lost revenues, and performance incentives
associated with the 2016-2017 Plan through its DSMA [demand
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 8 of 18
side management adjustment] in accordance with [Indiana Code
Section 8-1-8.5-9] and [Section] 10 and the DSM Rules [adopted
by the Commission, i.e., 170 Indiana Administrative Code
(“IAC”) 4-8].
….
B. Reasonableness of the 2016-2017 Plan. Having determined
that Vectren South has submitted an EE plan as required by
Section 10(h), Section 10(j) identifies ten factors the Commission
must consider in determining its overall reasonableness.… For
the reasons set forth below, we find that Vectren South's 2016-
2017 Plan is reasonable and should be approved.
….
iv. EM&V. Evaluation for all programs in the Plan will be
conducted by an independent evaluator every year for the prior
year's programs.…
….
Based on the evidence presented, we find that Vectren South’s
proposed EM&V procedures to independently verify the results
of its proposed programs and the estimated EM&V costs are
reasonable. Petitioner shall file its annual evaluation in its
DSMA proceeding.
….
viii. Lost Revenues and Financial Incentives. Petitioner’s
requested lost revenues and financial incentives are discussed in
detail below.
….
D. Lost Revenues and Performance Incentives. ….
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 9 of 18
Because we have found Vectren South’s 2016-2017 Plan is
reasonable, we must consider whether Petitioner’s request for
financial incentives and lost revenues associated with its EE
programs is reasonable. We also note that 170 IAC 4-8
authorizes the provision of financial incentives and lost revenues
that the Commission finds reasonable for DR programs.
Accordingly, we consider them together.
i. Lost Revenues. Vectren South seeks to recover lost revenues
associated with its 2016-2017 Plan in the same manner in which
it has been authorized to recover lost revenues associated with its
DSM programs previously. Both the OUCC and CAC generally
oppose Petitioner’s recovery of lost revenues.
Both the OUCC and CAC argue that lost revenues should be
authorized only if Petitioner has experienced a reduction in kWh
[kilowatt hour] sales compared to the kWh sales used to set rates
in its last base rate case. The OUCC presented evidence that
Vectren South’s sales had exceeded test year sales for calendar
years 2010 through 2014. However, on rebuttal, Vectren South
pointed out that the increase in sales was attributable to industrial
customers who had opted out of EE and that this trend is
expected to reverse due to a large industrial customer's plans to
begin self-generating in 2017. [Vectren Utility Holdings, Inc.’s
Vice President of Customer Energy Solutions Robert C. Sears]
testified that should sales continue to remain flat to declining,
implementation of the EE programs will cause lost revenues that
are not covered by load growth.
As we have previously explained, because the purpose of lost
revenue recovery is to return the utility to the position it would
have been in absent implementation of DSM, simply eliminating
lost revenue recovery when sales are higher than the levels used
to develop a utility’s current base rates would be contrary to this
purpose. Recovery of lost revenues is intended as a tool to
remove the disincentive a utility would otherwise face as a result
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 10 of 18
of promoting DSM in its service territory.…
The OUCC and CAC appear to be primarily concerned with
what [CAC consultant Natalie Mims] termed the pancake effect,
which is caused when lost revenues caused by EE investments in
different years aggregate. For example, if the average weighted
measure life is ten years for an EE measure then the utility
company, assuming there is no rate case in the interim, would
still be collecting lost revenues in 2025 for measures installed in
2016, along with lost revenues for measures installed during
2017-2025.[6]
The proposed annual budgets for the 2016-2017 Plan show lost
revenue as a percentage of the total budget is 11.8% in 2016 and
12.5% in 2017. Ms. Mims noted that Petitioner is requesting $2.5
million in lost revenues, but that this amount does not appear to
include the legacy lost revenues, incremental or cumulative lost
revenues for 2015 through 2017 that Petitioner has requested or is
receiving, or the total amount of lost revenues that Vectren South
has recovered.
6
According to the Commission, Mims testified that
Vectren did not provide a breakdown of lost revenue by program or year, or any evidence that it
will under-recover authorized costs due to the impacts of its EE programs. She testified it is
unreasonable to recover lost revenues if there is no evidence that the revenues are actually lost.
She also testified that lost revenue recovery is meant to be a short-term solution to address
revenue loss in between rate cases. She stated that in the absence of a rate case, Vectren South
will continue to add lost revenues from prior years to existing years for EE measures that are
still in service, which is known as the Pancake Effect. Accordingly, she recommended that if
recovery of lost revenue is allowed, it should be limited to three years or the life of the measure,
whichever is shorter, to avoid the Pancake Effect. She indicated that the rationale for a cap of
three years of lost revenue can be found in [Senate Enrolled Act 412, enacted as Section 10],
which requires the utilities to submit EE plans at least once every three years.
Appealed Order at 11. In Vectren South’s rebuttal, Sears
disagreed with Ms. Mims that the Pancake Effect warranted limiting lost revenues because the
lost revenues reflect a history of successful EE and DSM programs that produce significant
savings each year. Mr. Sears testified that the average life of the weighted program savings in
the Plan is 6.6 years with 31% of the program savings having an average life of three years or
less for the residential sector; an average life of the weighted program savings of 10.9 years for
the commercial sector and 8.5 years for the overall portfolio.
Id. at 12.
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 11 of 18
Although we have previously approved lost revenues over a
measure’s life or until a utility’s next base rate case, whichever is
shorter, Ms. Mims’ and the other parties’ concerns with
pancaking and the increased length of time between base rate
cases for utilities in Indiana raise a valid concern. Clearly,
pancaking of lost revenue is much less of an issue in an
environment where a utility comes in regularly, i.e., every three
to five years, for a base rate case. When the Commission’s DSM
Rules were adopted in the early 1990’s, the previous 20 years was
characterized by routine and sometimes almost back-to-back rate
case filings where utilities’ rates were reset on a regular basis.
Consequently, recovery of lost revenues at that time was viewed
as a tool of limited duration until the utility filed its next base rate
case in the not too distant future. However, in the years after
adoption of the DSM Rules, utilities have been staying out for
ten or more years before filing for a rate case. E.g., Indianapolis
Power & Light, 19 years between Cause No. 38664 (IURC
8/23/95) and pending Cause No. 44576; Southern Indiana Gas &
Electric Co., 12 years between Cause No. 39871 (IURC 6/21/95)
and Cause No. 43111 (IURC 8/15/07); Duke Energy Indiana, Inc.,
last rate case was filed 13 years ago in Cause No. 42359 (IURC
5/18/04, rh’g denied 7/28/04).
Because we believe the parties raise a valid concern, we find that
Vectren South’s lost revenue recovery should be limited to: (1)
four years or the life of the measure, whichever is less, or (2) until
rates are implemented pursuant to a final order in Vectren
South’s next base rate case, whichever occurs earlier. We note
that the CAC also requested that the Commission initiate some
type of formal process to develop a standard methodology for
Indiana utilities to calculate lost revenues for an EE measure.
Because Section 10 authorizes the recovery of reasonable lost
revenues to utilities with an approved EE plan and Section 10(q)
requires the Commission to adopt rules implementing the
requirements of Section 10, we fully expect that this issue will be
addressed in that future rulemaking.
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 12 of 18
….
IT IS THEREFORE ORDERED BY THE INDIANA
UTILITY REGULATORY COMMISSION that:
1. Vectren South’s 2016-2017 Plan is approved as set forth in this
Order.
2. Vectren South’s request for timely recovery of all costs,
including program costs, lost revenues, and financial incentives
associated with the 2016-2017 Plan, through its DSMA is
approved consistent with the terms of this Order.
Appealed Order at 5-28 (underlining and citations to administrative orders
omitted). Vectren South now appeals.7
Discussion and Decision
[5] The General Assembly created the Commission primarily as a factfinding body
with the technical expertise to administer the regulatory scheme devised by the
legislature. N. Ind. Pub. Serv. Co. v. U.S. Steel Corp., 907 N.E.2d 1012, 1015 (Ind.
2009). “The Commission can exercise only power conferred upon it by
7
Unlike the Indiana Department of Workforce Development’s Review Board, the Commission is not made a
party appellee in every appeal of its decisions pursuant to statute. Cf. Ind. Code § 22-4-17-12(b). In a recent
unrelated appeal involving Vectren South, we granted the appellant intervenors’ motion to dismiss the
Commission as a party to the appeal, agreeing with their argument that because the Commission “acted as a
fact-finding administrative tribunal and no statute or administrative provision expressly makes the
[Commission] a party on appeal, it is not a proper party on appeal from its own decision.” Citizens Action
Coalition of Indiana, Inc. v. S. Ind. Gas & Elec. Co., No. 93A02-1607-EX-1637, 2017 WL 587261, at *1 n.1 (Ind.
Ct. App. Feb. 14, 2017). One of the intervenors in that case was CAC, which has not filed a brief in this
appeal. We decline to dismiss the Commission in this case sua sponte.
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 13 of 18
statute.” Id. Indiana Code Section 8-1-3-1 authorizes judicial review of
Commission orders by this Court. The review involves multiple tiers. Id. “On
the first level, it requires a review of whether there is substantial evidence in
light of the whole record to support the Commission’s findings of basic fact.
Such determinations of basic fact are reviewed under a substantial evidence
standard, meaning the order will stand unless no substantial evidence supports
it.” Id. at 1016 (citation and footnote omitted). We neither reweigh evidence
nor assess witness credibility, and we consider only the evidence favorable to
the Commission’s findings. Id. The Commission’s order is not binding if it is
unreasonable or arbitrary. Id.
[6] “At the second level, the order must contain specific findings on all the factual
determinations material to its ultimate conclusions.” Id. We review the
Commission’s conclusions of ultimate facts for reasonableness, the deference of
which is based on the amount of expertise exercised by the agency. Id. If the
order involves a subject within the Commission’s special competence, we
should give it greater deference; if the subject is outside the Commission’s
expertise, we give it less deference. Id. Findings of fact are important because
they help us understand the Commission’s reasoning and policy judgments and
allow for a reasoned and informed basis of review, which decreases the
likelihood that we will substitute our judgment on complex evidentiary issues
and policy determinations best left to an agency with technical expertise. N.
Ind. Pub. Serv. Co. v. LaPorte, 791 N.E.2d 271, 278 (Ind. Ct. App. 2003).
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 14 of 18
Further, requiring findings of fact helps the Commission avoid arbitrary and
capricious action. Id.
[7] “Additionally, an agency action is always subject to review as contrary to law,
but this constitutionally preserved review is limited to whether the Commission
stayed within its jurisdiction and conformed to the statutory standards and legal
principles involved in producing its decision, ruling, or order.” U.S. Steel, 907
N.E.2d at 1016. “Courts should consider a statute in its entirety, keeping in
mind the subject it addresses and the legislature’s apparent objective in enacting
it.” In re Dunn, 848 N.E.2d 310, 316 (Ind. Ct. App. 2006).
The best indication of legislative intent is the statutory language,
given its plain and ordinary meaning. Where the language of a
statute is clear and unambiguous, courts should apply the statute
without resort to further aids of statutory construction. It should
be presumed that the legislature did not intend an absurd,
inconvenient, or unjust result.
Id. (citations and quotation marks omitted). We give considerable deference to
an interpretation of a statute by an administrative agency charged with
administering the statute, but that interpretation is not binding on us when it is
incorrect or if the legislative intent is obvious. Sadler v. State ex rel. Sanders, 811
N.E.2d 936, 953-54 (Ind. Ct. App. 2004).
[8] In challenging the Commission’s order in this case, Vectren South makes
several interrelated arguments, one of which is that the Commission erred as a
matter of law by approving its “energy-efficiency plan ‘in its entirety’ but then
rejecting the portion of that plan addressing lost revenue recovery.” Appellant’s
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 15 of 18
Br. at 31. Vectren South asserts that Section 10 “calls for a single
reasonableness inquiry that considers the ten factors in subjection (j). Recovery
of lost revenues is included in this reasonableness inquiry.” Id. Based on the
plain language of the statute, we agree. See Ind. Code § 8-1-8.5-10(j)(8)
(requiring Commission to consider lost revenues sought to be recovered by
electricity supplier in determining overall reasonableness of plan).8 By capping
lost revenue recovery at four years, the Commission implicitly found Vectren
South’s lost revenue recovery proposal to be unreasonable.9
[9] Vectren South also argues that the Commission’s four-year cap is arbitrary and
capricious, noting that “[t]he basis for capping lost revenue recovery is never
tied to a finding that recovery equal to DSM measure life would be
unreasonable[,]” that the cap “effectively throws out twenty years of [the
8
Because the relevant portions of Section 10 are unambiguous, we decline the invitation of Vectren South
and amicus Indiana Energy Association to use legislative history to interpret them. See Orr v. Turco Mfg. Co.,
484 N.E.2d 1300, 1302 (Ind. Ct. App. 1985) (“When a statute is unambiguous, legislative history should not
be used to determine its meaning.”), trans. denied (1986).
9
170 IAC 4-8-5(b), which was readopted by the Commission two years before Section 10 was enacted by the
legislature, provides that the Commission “shall determine the cost recovery mechanism for a demand-side
management program when the demand-side management program is submitted for commission approval.”
We note, however, that Section 10(o) contemplates that an electricity supplier will propose its own cost
recovery mechanism as part of its plan and that Section 10(k) contemplates that the electricity supplier will be
allowed to “recover all associated program costs” (including reasonable lost revenues) through that
mechanism if the Commission determines that the plan is reasonable in its entirety. We reiterate that an
administrative agency may not make rules or regulations inconsistent with the statute it is administering. Best
Ever Cos., 495 N.E.2d at 787.
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 16 of 18
Commission’s own precedent] regarding lost-revenue recovery[,]”10 and that
“[t]he Commission appears to have picked a number that arbitrarily splits the
difference between a frequently observed measure-life and a 3-year cap proposal
[by CAC].” Appellant’s Br. at 35, 36, 37; n.6 supra. Indeed, as Vectren South
points out, the financial effect of the four-year cap is “unknown to the
Commission” because no party proposed a four-year cap or “presented data
about its economic effect.” Id. at 38, 39.11 A four-year cap may have the
superficial virtues of simplicity and uniformity,12 but the Commission made no
specific factual findings that the cap would allow Vectren South to recover
reasonable lost revenues as provided in Section 10(o).13
10
The Commission observes that “this is the first plan submitted by Vectren [South] under the new statutory
framework in Section 10” and that “[a]n agency may change its course and is not forever bound by prior
policy or precedent” as long as it explains its reasons for the change. Appellee’s Br. at 24 (citing Cmty. Care
Ctrs., Inc. v. Ind. Dep’t of Pub. Welfare, 523 N.E.2d 448, 450-51 (Ind. Ct. App. 1988)). The problem here is that
the Commission’s change of course regarding lost revenue recovery is unsupported by adequate factual
findings.
11
Vectren South observes that although the Commission expressed “concern” about the pancaking of lost-
revenue recovery, it failed to explain “why it believes pancaking is bad” or “why the amount of pancaking
that will occur with a 4-year cap is reasonable, but the amount that will occur with a smaller or larger cap is
not.” Appellant’s Br. at 39. On page 17 of its appellate brief, the Commission quotes from a document that
Mims cited regarding the alleged difficulty of tracking the pancake effect over time, but the Commission did
not specifically rely on this document in its order or specifically find that the independent EM&V required by
statute (and approved by the Commission) is unable to adequately account for this effect. The Commission
addresses EM&V on pages 18 through 20 of its brief, but this is too little, too late.
12
The Commission notes that it “similarly capped lost revenue recovery at four years” in two recent orders
involving other utilities and that neither utility appealed. Appellee’s Br. at 24. The legal actions or inactions
of other utilities are irrelevant here.
13
Contrary to the suggestion of amicus Indiana Industrial Group, Vectren South is not seeking recovery of
“unlimited” lost revenues. Amicus Br. of Indiana Industrial Group at 15.
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 17 of 18
[10] Consequently, we reverse the Commission’s order and remand for further
proceedings consistent with this opinion. On remand, the Commission may
either (1) issue specific factual findings to justify its implicit determination that
Vectren South’s lost revenue recovery proposals are unreasonable, determine
that the Plan is not reasonable in its entirety pursuant to Section 10(m), and
allow Vectren South to submit a modified plan within a reasonable time; or (2)
issue specific factual findings to justify a determination that the Plan is in fact
reasonable in its entirety pursuant to Section 10(k) and allow Vectren South to
recover reasonable lost revenues in accordance with the Plan.14
[11] Reversed and remanded.15
Riley, J., and Altice, J., concur.
14
170 IAC 4-8-6(c) provides that “the approval of a lost revenue recovery mechanism shall not constitute
approval of a specific dollar amount, the prudence or reasonableness of which may be debated in a future
proceeding before the commission.” According to the Commission, Sears testified that Vectren South
takes a conservative approach to its projected lost revenues to ensure Petitioner is not over-
collecting lost revenues from customers. Any over/under collection variance will be recovered
in Petitioner’s next DSMA filing. He further testified that forecasted program costs will be
reconciled against actual results based on EM&V of the EE programs under the Plan.
Appealed Order at 6. The Commission made no findings regarding Vectren South’s historical lost revenue
forecasting accuracy or reconciliation mechanism as mentioned in Section 10(o).
15
We need not pass upon the wisdom of the Commission’s justification of a four-year cap based on the trend
toward less frequent base rate cases. We note, however, that another panel of this Court recently stated that
rate cases are “expensive, time consuming, and sometimes result in large, sudden rate hikes for customers.”
NIPSCO Indus. Grp. v. N. Ind. Pub. Serv. Co., 31 N.E.3d 1, 4 (Ind. Ct. App. 2015).
Court of Appeals of Indiana | Memorandum Decision 93A02-1604-EX-914 | March 7, 2017 Page 18 of 18