Defense v. Northrop Grumman Corporation

United States Court of Appeals for the Federal Circuit ______________________ SECRETARY OF DEFENSE, Appellant v. NORTHROP GRUMMAN CORPORATION, Appellee -------------------------------------------- NORTHROP GRUMMAN CORPORATION, Appellant v. SECRETARY OF DEFENSE, Appellee ______________________ 2018-1945, 2018-1990 ______________________ Appeals from the Armed Services Board of Contract Appeals in Nos. 57625, 60190, Administrative Judge Rob- ert T. Peacock. ______________________ Decided: November 15, 2019 ______________________ DANIEL B. VOLK, Commercial Litigation Branch, Civil Division, United States Department of Justice, 2 DEFENSE v. NORTHROP GRUMMAN CORPORATION Washington, DC, argued for Secretary of Defense. Also represented by JOSEPH H. HUNT, ROBERT EDWARD KIRSCHMAN, JR., PATRICIA M. MCCARTHY; ROBERT LYN DUECASTER, Contract Disputes Resolution Center, Defense Contract Management Agency, Chantilly, VA. DONALD B. VERRILLI, JR., Munger, Tolles & Olson LLP, Washington, DC, argued for Northrop Grumman Corpora- tion. Also represented by GINGER ANDERS; CHARLES BAEK, STEPHEN JOHN MCBRADY, NICOLE J. OWREN-WIEST, Crow- ell & Moring LLP, Washington, DC. ______________________ Before PROST, Chief Judge, BRYSON and REYNA, Circuit Judges. REYNA, Circuit Judge. The Secretary of Defense appeals a final decision of the Armed Services Board of Contract Appeals finding that the United States Government improperly disallowed certain retirement benefits costs that Northrop Grumman Corpo- ration asserts are eligible for reimbursement. Northrop Grumman Corporation conditionally cross-appeals the Armed Services Board of Contract Appeals’ finding that the retirement benefit costs are unallowable under the appli- cable regulations because they were calculated using an improper accounting method. Because substantial evi- dence supports the Armed Services Board of Contract Ap- peal’s finding that Northrop Grumman Corporation never claimed and will never claim any of the disputed retire- ment benefits, we affirm and do not reach the cross-appeal. BACKGROUND I. Post-Retirement Benefits Costs This dispute concerns Northrop Grumman Corpora- tion’s (“Northrop”) accounting of costs for providing post- retirement benefits (“PRB”). PRBs are non-pension DEFENSE v. NORTHROP GRUMMAN CORPORATION 3 benefits that are made available to employees upon their retirement. Examples of PRBs include post-retirement health care, life insurance, disability benefits, and other welfare benefits. Relevant to these appeals is that PRBs can be modified or eliminated entirely, unlike pension ben- efits which cannot be modified by the employer. The Federal Acquisition Regulation (“FAR”) 1 permits contractors such as Northrop to seek reimbursement from the federal government for its PRB costs. Only those PRB costs that are “allowable,” however, may be reimbursed by the government. Effective July 25, 1991, the FAR was amended to add FAR 31.205-6(o), which governed allowa- bility of reimbursement of PRB costs in government con- tracts. This amendment required PRB costs assigned to a given year to be funded by that year’s tax return deadline in order to be allowable. While the amendment permitted the use of accrual accounting 2 methods for PRB costs, it did not expressly require that any specific accounting standard be used. However, effective February 27, 1995, the FAR was amended again, this time to require the use of the ac- counting standards set out in the Statement of Financial 1 The version of the FAR in effect on July 8, 2005, applies to this case. 2 Accrual accounting (unlike cash accounting) fo- cuses on when transactions occur, rather than when pay- ments are made. Because PRB plans are funded well before retirement occurs and benefits are paid out, accrual accounting relies on actuarial assumptions such as life ex- pectancy to predict future costs while allocating those costs to current years. 4 DEFENSE v. NORTHROP GRUMMAN CORPORATION Accounting Standards 106 (“FAS 106”) 3 to determine al- lowable PRB costs in government contracts. 4 At the time of the 1995 FAR amendment, Northrop ac- counted for its PRB costs using an accounting method that conformed to the requirements established by the Deficit Reduction Act of 1984 (“DEFRA”) rather than FAS 106. Following the 1995 FAR amendment, Northrop continued to account for its PRB costs for government contracting purposes using the DEFRA method, even though that method was no longer in compliance with the FAR. The DEFRA and FAS 106 both require the use of ac- crual accounting methods, but the actuarial assumptions underlying each method are different. The primary differ- ence between the DEFRA method and the FAS 106 method is that the DEFRA method calculates PRB costs based on current medical costs, while the FAS 106 method calcu- lates PRB costs to include future increases in medical costs. J.A. 32. As a result, annual PRB costs computed using the DEFRA method typically start lower and increase over time whereas annual PRB costs computed using the FAS 106 method typically start higher and decrease over time. J.A. 2. 3 FAS 106 as issued in 1990 is available on the Fi- nancial Accounting Standards Board’s website at https://www.fasb.org/jsp/FASB/Document_C/DocumentPa ge?cid=1218220123671. 4 After the February 27, 1995, amendment, FAR 31.205-6(o)(2)(iii) provided in relevant part that “to be allowable, PRB costs . . . must be measured and assigned according to Generally Accepted Accounting Principles.” FAR 31.205-6(o)(2)(iii) (1995); see also 59 Fed. Reg. 67045 (Dec. 28, 1994). It is undisputed that the reference to “Gen- erally Accepted Accounting Principles” in FAR 31.205- 6(o)(2)(iii) refers to FAS 106. J.A. 3. DEFENSE v. NORTHROP GRUMMAN CORPORATION 5 Between 1995 and 2006, Northrop filed disclosure statements with the government on numerous occasions, disclosing its continued use of the DEFRA method. The government was aware that Northrop was not in compli- ance with the FAR, but it did not object to Northrop’s con- tinued use of the DEFRA method because its use resulted in lower reimbursement costs to the government. J.A. 99. Indeed, had Northrop used the FAS 106 method between 1995 and 2005, the government would have paid an addi- tional $253 million during that period. See J.A. 32; Oral Arg. at 15:18–15:34; see also J.A. 1000 (member of DCAA testifying that the government saved $253 million between 1995 and 2006). In addition, both the Defense Contract Management Agency (“DCMA”) and the Defense Contract Audit Agency (“DCAA”) informed Northrop during these years that the agencies found “no instances of noncompli- ance with applicable Cost Accounting Standards or with FAR Part 31 cost principles.” J.A. 4; see also J.A. 3–6. Alt- hough not reflective of official policy, DCMA even used Northrop’s continued use of the DEFRA method in its in- ternal training documents as an example of acceptable ac- counting methods under the FAR. J.A. 10, 33. 5 At the time, DCMA members interpreted the FAR’s requirement that FAS 106 method be used as setting a ceiling on allow- able costs under the regulations, concluding that the differ- ence between the DEFRA and FAS 106 calculations would not become unallowable even if not assigned and funded within a given year as required by FAR 31.205-6(o)(3). 6 Id. 5 Internally, there was disagreement between mem- bers of the DCMA and the DCAA about whether Northrop’s continued use of the DEFRA method was acceptable. 6 FAR 31.205-6(o)(3) provided: “To be allowable, costs must be funded by the time set for filing the Federal 6 DEFENSE v. NORTHROP GRUMMAN CORPORATION Because PRB cost calculations under the DEFRA method increase over time, and calculations using the FAS 106 method decrease over time, Northrop predicted that its PRB cost calculations using the DEFRA method would ex- ceed those allowable under the FAR and FAS 106 in 2015. To avoid this eventuality, Northrop in 2006 switched from using the DEFRA method to using the FAS 106 method. As part of the switch, Northrop was required to calculate its “transition obligation”—the difference between the PRB costs that would have accrued had Northrop adopted the FAS 106 method in 1995 and the PRB costs that actually accrued due to its continued use of the DEFRA method. See 56 Fed. Reg. 41,738, 41,739 (Aug. 22, 1991); FAS 106, ¶ 110. Northrop’s transition obligation in 2006 would have been approximately $305 million. At the same time it adopted the FAS 106 method, Northrop amended its PRB plans. The amendment capped the annual amount Northrop would contribute to the PRB plans independent of future healthcare cost increases, thereby limiting the benefits available to its employees un- der those plans. As a result of this “negative plan amend- ment,” Northrop’s PRB cost obligations were reduced by approximately $307 million. Northrop subtracted these savings from its transition obligation, as required by FAS 106. Northrop notified DCMA of its PRB plan amendment and its switch to the FAS 106 accounting method on Octo- ber 23, 2006, and November 3, 2006, respectively. On July 26, 2007, DCMA issued a notice of its intent to disallow costs. DCMA took the position that Northrop’s transition obligation was unallowable in future accounting periods because Northrop did not measure or fund its PRB income tax return or any extension thereof. PRB costs as- signed to the current year, but not funded or otherwise liq- uidated by the tax return time, shall not be allowable in any subsequent year.” FAR 31.205-6(o)(3) (1995). DEFENSE v. NORTHROP GRUMMAN CORPORATION 7 plans between 1995 and 2006 using the required FAS 106 method, and therefore failed to timely assign the unfunded difference between the higher FAS 106 amount and the lower DEFRA amount to those years. J.A. 27. DCMA is- sued a Final Determination on April 9, 2008, disallowing approximately $253 million of Northrop’s PRB costs from its post-2006 reimbursement submissions. 7 Northrop sub- mitted a certified claim for these funds on May 20, 2010. DCMA denied Northrop’s claim on February 18, 2011. As a result of the government’s disallowance, Northrop has de- ducted the disputed $253 million from its annual PRB cost reimbursement submissions since 2007, amortized over a 20-year period—approximately $12.7 million annually. II. Proceedings Before the Board Northrop appealed DCMA’s denial to the Armed Ser- vices Board of Contract Appeals (“the Board”). The Board bifurcated the proceedings into two phases—entitlement and quantum. The Board held an evidentiary hearing in each phase. A. Entitlement Phase During the entitlement phase, the Board determined that Northrop’s use of the DEFRA method was not in com- pliance with FAR 31.205-6(o). J.A. 12. The Board pointed to Northrop’s concession that “there is no dispute that the DEFRA method did not comply with GAAP requirements,” as required by the FAR. Id. The Board also found that by 7 Of the $304,754,315 that constituted Northrop’s transition obligation prior to factoring in its negative plan amendment, DCMA allowed $51,392,803, finding those PRB costs to be applicable to contracts awarded prior to the February 27, 1995, FAR amendment that required the use of the FAS 106 method. J.A. 1292 n.10. The remaining $253,361,512 in disallowed PRB costs is at issue in this ap- peal. 8 DEFENSE v. NORTHROP GRUMMAN CORPORATION not using the FAS 106 method, Northrop did not timely fund its PRB obligations to the full extent permitted by the FAR. Id. According to the Board, this rendered $253 mil- lion of Northrop’s transition obligation unallowable under FAR 31.205-6(o)(3). J.A. 12–13. The Board rejected sev- eral of Northrop’s arguments, including its contention that the FAS 106 method only set a ceiling for allowable costs under the FAR and any costs up to that amount should be allowable notwithstanding Northrop’s failure to fund those costs. J.A. 13–16. The Board explained that “no such lan- guage is contained” in FAR 31.205-6(o)(3), and thus the plain language of that regulation contradicted Northrop’s arguments. J.A. 13. The Board determined, however, that it could not re- solve Northrop’s argument that the government’s disallow- ance was improper because the negative amendment to Northrop’s PRB plans ensured that the $253 million in dis- puted PRB costs “have never been and will never be claimed or incurred.” J.A. 16. The Board explained that there was inconsistent testimony as to whether Northrop included the unallowable costs in its reimbursement sub- missions in 2007 and subsequent years, and those submis- sions were not in the record. J.A. 11, 16. The Board left the resolution of these quantum issues until the next phase of the proceedings. J.A. 17. Northrop moved for reconsid- eration, which the Board denied. J.A. 19–24. B. Quantum Phase During the quantum phase, the Board found that Northrop’s negative amendment to its PRB plans saved $307 million from its future PRB plan obligations, “en- sur[ing] that [Northrop] would not have to pay PRB costs arising from future increases in healthcare costs in excess of the fixed dollar ‘cap.’” J.A. 35. The Board further found that FAS 106 required Northrop to exclude these savings from its transition obligation calculations. Id. (citing FAS 106, ¶ 28). Citing expert testimony, the Board explained DEFENSE v. NORTHROP GRUMMAN CORPORATION 9 that because the primary difference between the DEFRA method and the FAS 106 method is that FAS 106 requires accounting for future increases in healthcare costs, “the costs that were eliminated before computing the transition obligation were the same costs that comprised the $253 million of unfunded pre-transition costs.” Id. The Board determined that, therefore, “it would not have been possi- ble for [Northrop] to include the $253 million of unfunded costs in its calculated PRB costs in 2007 or thereafter,” meaning that Northrop could not have claimed those costs for reimbursement. Id. According to the Board, Northrop’s use of the DEFRA method therefore “did not lead to any recovery of claimed but unfunded costs, or to duplicate re- covery,” and instead benefitted the government. J.A. 35– 36, 40. The Board rejected the government’s argument that even though Northrop did not use the FAS 106 method be- tween 1995 and 2006, it nonetheless still incurred the ad- ditional $253 million in PRB costs “by operation of law” due to the FAR’s requirement of using the FAS 106 method. The Board stated that the government “disregards funda- mental concepts related to cost ‘incurrence,’ and misfocuses on an ‘allowability’ regulation rather than [Northrop’s PRB plans].” J.A. 39. The Board explained that cost incurrence is defined by Northrop’s plan obligations, and thus the only costs that Northrop incurred prior to 2006 were those cal- culated using the DEFRA method. Id. The Board deter- mined, therefore, that Northrop did not “incur” the disputed $253 million between 1995 and 2006. Id. The Board also rejected the government’s argument that Northrop’s negative plan amendment had no effect on the costs Northrop incurred between 1995 and 2006. J.A. 37, 41. The Board pointed to the unrebutted testimony of actuaries, who testified that Northrop’s transition obliga- tion was eliminated “as a consequence” of its negative PRB plan amendment. J.A. 41. The Board noted that the gov- ernment was justly concerned about allowability of 10 DEFENSE v. NORTHROP GRUMMAN CORPORATION Northrop’s transition obligation because the PRB costs that constituted that obligation were not timely funded be- tween 1995 and 2006 as required by the FAR. J.A. 40–41. The Board explained, however, that Northrop’s negative plan “amendment should have assuaged and eliminated the government’s valid concerns here” because it “removed properly objectionable portions [from] the transition obli- gation.” J.A. 42. The Board further found the government’s disallow- ance to be inconsistent with FAR 31.201-2(c), which pro- vides that only costs “in excess of the amount that would have resulted from using practices consistent with this subpart are unallowable.” J.A. 38 (quoting FAR 31.201- 2(c)) (emphasis removed). The Board explained that alt- hough Northrop did not use the proper accounting method, it was undisputed that the PRB costs that Northrop calcu- lated using the DEFRA method did not exceed the amount that Northrop could have claimed if it had used the FAS 106 method since 1995. Id. Combined with Northrop’s negative amendment to its PRB plans, this resulted in “no excess to disallow.” Id. (emphasis removed). Based on its findings, the Board concluded that Northrop’s negative plan amendment “ensured that [Northrop] would never incur the costs disallowed and ef- fectively mooted allowability issues associated with the transition obligation” because Northrop “has never, and will never, claim, and the government will never pay,” the disputed $253 million in disallowed costs. J.A. 41–42. Ac- cordingly, the Board sustained Northrop’s appeal, explain- ing that “the government suffered no damages” as a result of Northrop’s noncompliance with FAR 31.205-6(o). J.A. 25, 42. Following the Board’s quantum phase decision, the government moved for reconsideration, which the Board denied on January 9, 2018. J.A. 45, 51. The Board rejected the government’s argument that the quantum phase DEFENSE v. NORTHROP GRUMMAN CORPORATION 11 decision was inconsistent with the earlier entitlement phase decision. The Board explained that during the enti- tlement phase, it only decided that Northrop failed to com- ply with the FAR requirement of using the FAS 106 method. J.A. 45. The Board stated that the entitlement phase decision expressly left open the issue of the resulting financial consequences of Northrop’s noncompliance. J.A. 46. The Board reiterated its quantum phase finding that “it is clear beyond cavil on a fully developed quantitative record that [Northrop] never has and never will incur and claim the disallowed costs and the government never has and never will pay any ‘excess’ resulting from the noncom- pliance.” Accordingly, the Board concluded that the gov- ernment failed to prove its quantum damages. J.A. 51. On appeal, the Secretary of Defense (“Secretary”) asks us to reverse the Board’s quantum phase decision that Northrop has never and will never claim reimbursement for the disputed $253 million in PRB costs because it did not incur those costs between 1995 and 2006. Northrop conditionally cross-appeals the Board’s entitlement phase decision that the $253 million in PRB costs that Northrop failed to timely fund between 1995 and 2006 are unallowa- ble. We have jurisdiction under 28 U.S.C. § 1295(a)(10). DISCUSSION We review the Board’s legal conclusions de novo. Par- sons Glob. Servs., Inc. ex rel. Odell Int’l, Inc. v. McHugh, 677 F.3d 1166, 1170 (Fed. Cir. 2012). Interpretation and application of the FAR are issues of law that we review de novo. Id. We set aside the Board’s factual findings only if they are fraudulent, arbitrary or capricious, so grossly er- roneous as to necessarily imply bad faith, or not supported by substantial evidence. Laguna Constr. Co., Inc. v. Carter, 828 F.3d 1364, 1368 (Fed. Cir. 2016); Rockies Exp. Pipeline LLC v. Salazar, 730 F.3d 1330, 1335 (Fed. Cir. 2013) (citing 41 U.S.C. § 7107(b)(2)). 12 DEFENSE v. NORTHROP GRUMMAN CORPORATION Resolution of this appeal turns on whether substantial evidence supports the Board’s finding that Northrop’s neg- ative amendment to its PRB plans effectively eliminated the $253 million in disputed PRB costs from its transition obligation such that those costs were never and will never be charged to the government. We conclude that it does. The Board found that Northrop’s negative amendment to its PRB plans saved $307 million from its future PRB plan obligations, and the Secretary does not dispute this finding. J.A. 35; Appellant’s Br. 27. 8 It is also undisputed that these savings resulted from capping the amount Northrop would pay in PRB costs regardless of future healthcare increases, thus removing the effect of those in- creases on its PRB cost calculations. J.A. 35; see J.A. 1539. The government also conceded that the major difference between the DEFRA method and the FAS 106 method is that the FAS 106 method accounts for future healthcare cost increases and the DEFRA method does not. J.A. 32, 177. These undisputed facts support the Board’s finding that by eliminating the effect of future healthcare cost in- creases from its PRB obligation, Northrop’s negative plan amendment eliminated “the same costs that comprised the $253 million” in dispute. J.A. 35. The Board also cited to FAS 106, explaining that it re- quired Northrop “to exclude obligations associated with the future health care cost increases that were eliminated pur- suant” to its negative amendment prior to calculating its transition obligation. Id.; see also FAS 106, ¶ 28 (“[P]lan amendments shall be included in the computation of the expected and accumulated postretirement benefit 8 The Board explained that the facts were substan- tively not in dispute below, and that the majority of its fac- tual findings were “in essence ‘stipulated.’” J.A. 26 n.2. Accordingly, the Board adopted the undisputed facts as proposed by the parties. Id. DEFENSE v. NORTHROP GRUMMAN CORPORATION 13 obligations.” (emphasis removed)). This evidence also sup- ports the Board’s findings that the disputed $253 million in unfunded pre-transition PRB costs were never part of Northrop’s transition obligation. J.A. 35. The Board’s findings are also supported by unrebutted testimony of Northrop’s independent actuary expert, Mr. McQuade, on which the Board relied. See id. Mr. McQuade testified that Northrop’s negative amendment eliminated the disputed $253 million from Northrop’s transition obli- gation because the amendment eliminated $307 million from Northrop’s accumulated post-retirement benefit obli- gation on which its transition obligation was based. J.A. 821–22. He also testified that the amended PRB costs and the $253 million in unfunded costs “are both based on fu- ture increases in healthcare costs,” and by eliminating the effect of those increases on its PRB obligations, Northrop’s amendment more than eliminated its transition obligation. J.A. 830. Mr. McQuade further testified that the govern- ment “will never pay for the $253 [million] of unfunded costs because those costs have been eliminated.” J.A. 822. This testimony is substantial evidence that supports the Board’s findings that it would have been impossible for Northrop to include the disputed $253 million in its post- 2006 PRB cost calculations or to subsequently claim those costs for reimbursement from the government, and that as a result, the government’s disallowance of those costs was improper. J.A. 35, 42. On appeal, the Secretary frames his challenge to the Board’s decision as disputing the Board’s legal interpreta- tion and application of FAR 31.205-6(o) to undisputed facts. Appellant’s Br. 25; Appellant’s Reply Br. 19. We dis- agree with this characterization. The dispute here is not over whether Northrop violated FAR 31.205-6(o) by using the DEFRA method or whether Northrop’s $253 million in 14 DEFENSE v. NORTHROP GRUMMAN CORPORATION unfunded PRB costs are unallowable. 9 Rather, the Secre- tary disputes the Board’s factual findings that those unal- lowable costs were not charged to the government by virtue of being excluded from Northrop’s transition obligation by Northrop’s negative amendment to its PRB plans. As ex- plained above, these factual findings are supported by sub- stantial evidence and are therefore “final and conclusive.” 41 U.S.C. § 7107 (2012). We also disagree with the substance of the Secretary’s arguments. The Secretary argues that because Northrop underfunded its PRB costs by $253 million between 1995 and 2006 by using a noncompliant accounting method, those costs will always remain “unallowable” pursuant to FAR 31.205-6(o)(3), and the government is therefore re- quired to disallow that amount from Northrop’s future PRB reimbursement claims. Appellant’s Br. 25–26. This argu- ment would have merit had Northrop not amended its PRB plans because that underfunded amount would then have been part of the Northrop’s transition obligation. As the Board correctly explained, however, Northrop’s negative plan amendment mooted the issue of allowability by elimi- nating the disputed $253 million from the transition obli- gation. J.A. 41. Thus, Northrop never actually submitted any unallowable costs for reimbursement, and the govern- ment had no basis to disallow that amount from Northrop’s post-2006 reimbursement submissions. The crux of the Secretary’s argument is his assertion that Northrop’s negative plan amendment was a separate event from its switch to the FAS 106 method. Appellant’s Reply Br. 4, 9; see also Oral Arg. at 4:30–4:49, 9 In its conditional cross-appeal, Northrop does chal- lenge the Board’s determination at the entitlement phase that these costs are unallowable under FAR 31.205-6(o). We do not reach this question, however, because we affirm the Board’s quantum decision. DEFENSE v. NORTHROP GRUMMAN CORPORATION 15 http://oralarguments.cafc.uscourts.gov/default.aspx?fl= 2018-1945.mp3. Based on this assertion, the Secretary ar- gues that Northrop’s negative plan amendment cannot off- set the disputed $253 million in PRB costs because had either of these events happened without the other, the gov- ernment would be entitled to disallow the disputed $253 million. Appellant’s Br. 25–26; Appellant’s Reply Br. 4–10. We disagree. Both events occurred simultaneously in this case, and Northrop’s negative plan amendment had a direct effect on its adoption of the FAS 106 method. We agree that the amendment did not go so far as to transform Northrop’s underfunded $253 million in PRB costs into allowable costs under FAR 31.205-6(o). The amendment, however, low- ered the entire accumulated value of Northrop’s PRB plans, which was used to calculate its transition obligation. Thus, although the amendment did not affect the allowa- bility of the disputed $253 million, it cannot be viewed in isolation from Northrop’s adoption of the FAS 106 method because the amendment completely eliminated Northrop’s transition obligation. The Secretary further contends that because the two events should be treated separately, the government is en- titled to receive the full benefit of Northrop’s negative plan amendment. Appellant’s Br. 27; Appellant’s Reply Br. 21. The Secretary asserts that if Northrop had properly ac- counted for its PRB costs using the FAS 106 method since 1995, then the government “would have realized the full $307 million in cost reductions” upon Northrop’s amend- ment to its PRB plans in 2006. Appellant’s Br. 27. Instead, the Secretary contends, the government has been deprived of the benefit of Northrop’s amendment. We disagree. It is undisputed that the government has already benefitted by saving $253 million between 1995 and 2006 as a result of Northrop’s use of the DEFRA method. See J.A. 32; see also J.A. 1000 (member of DCAA testifying that the gov- ernment saved $253 million between 1995 and 2006); Oral 16 DEFENSE v. NORTHROP GRUMMAN CORPORATION Arg. at 15:18–15:34 (government’s counsel conceding that had Northrop used the FAS 106 method between 1995 and 2005, the government would have paid an additional $253 million during that period). Rather than attempting to re- cover a lost benefit, the Secretary in essence now seeks to benefit twice from Northrop’s noncompliance with FAS 106. 10 The Secretary next argues that the Board erred by de- termining that Northrop never incurred the full PRB costs as calculated under FAS 106, even though Northrop calcu- lated a lower PRB cost amount using the DEFRA method. Appellant’s Br. 28–31; Appellant’s Reply Br. 14–15. The Secretary contends that regardless of which method Northrop used to calculate its PRB costs between 1995 and 2006, Northrop still incurred the same PRB costs because its employees were earning their benefits during that time. Appellant’s Br. 29–30; Appellant’s Reply Br. 16. According to the Secretary, those costs are therefore necessarily part of Northrop’s transition obligation and must be disallowed because Northrop did not timely fund those costs. Appel- lant’s Reply Br. 16. Whether Northrop incurred these costs, however, is immaterial to our analysis because Northrop never charged the government the disputed $253 million. As a member of DCAA admitted to the Board, the government therefore “has not been damaged.” J.A. 933– 34. Nor can Northrop charge those costs to the government in the future because its negative amendment eliminated 10 We note that the government did not object to Northrop’s use of the DEFRA method while Northrop was saving the government money between 1995 and 2006. J.A. 3–5, 32–33. The government even internally approved of Northrop’s accounting practices. J.A. 33. It was only after Northrop adopted the FAS 106 method and amended its PRB plans to eliminate its transition obligation that the government changed its position. DEFENSE v. NORTHROP GRUMMAN CORPORATION 17 those costs from its transition obligation, as required by FAS 106. See J.A. 35, 38, 820–21; FAS 106, ¶ 28. CONCLUSION We have considered the Secretary’s remaining argu- ments and find them unpersuasive. We conclude that sub- stantial evidence supports the Board’s finding that Northrop’s negative PRB plan amendment effectively elim- inated Northrop’s transition obligation. We therefore af- firm the Board’s decision that the government’s disallowance of the disputed $253,361,512 of Northrop’s PRB costs was improper and dismiss Northrop’s condi- tional cross-appeal. AFFIRMED