NOT FOR PUBLICATION WITHOUT THE
APPROVAL OF THE APPELLATE DIVISION
This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY
APPELLATE DIVISION
DOCKET NO. A-0305-18T4
JENNIFER S. INGENITO,
Plaintiff-Appellant,
v.
BOROUGH OF ATLANTIC
HIGHLANDS,
Defendant-Respondent,
and
COMPASS CONSTRUCTION,
INC., and BIRDSALL
ENGINEERING, INC.,
Defendants.
__________________________
Argued October 10, 2019 – Decided July 13, 2020
Before Judges Nugent and Suter.
On appeal from the Superior Court of New Jersey, Law
Division, Monmouth County, Docket No. L-2179-11.
Vincent P. Manning argued the cause for appellant
(Manning Caliendo & Thomson, PA, attorneys;
Vincent P. Manning, of counsel and on the briefs).
Jason R. Hawrylak argued the cause for respondent
(Wisniewski & Associates LLC, attorneys; Jason R.
Hawrylak, on the brief).
PER CURIAM
Plaintiff, Jennifer Ingenito, appeals the summary judgment dismissal of
her personal injury complaint, which alleged she fell from her bike and sustained
serious injuries as she rode off a wooden bridge on public property of defendant,
the Borough of Atlantic Highlands ("Borough"). Because we conclude genuine
issues of material fact should have precluded summary judgment—mostly
because the scant record leaves many critical facts disputed and unresolved —
we reverse and remand.
I.
A.
Plaintiff filed a three-count personal injury complaint in May 2011. She
alleged she was injured while bicycling through a scenic trail in the Borough.
Her accident happened when, while "coming off a bridge which connects the
trail to the Atlantic Highlands Harbor Commission property, . . . she was caused
A-0305-18T4
2
to fall off her bicycle due to a steeply sloped section of asphalt pavement on said
trail[.]"
In the complaint's first count, she alleged a cause of action against the
Borough under the Tort Claims Act (TCA), N.J.S.A. 59:1-1 to 12-3, for
designing, constructing, managing, supervising, and maintaining a dangerous
condition of public property. In the second count, she alleged defendant
Compass Construction, Inc. ("Compass") negligently designed, installed, and
constructed the bridge and area around it. In the third count, she alleged
defendant Birdsall Engineering, Inc. ("Birdsall") negligently planned and
designed the portion of the trail and bridge where she fell.
Defendants filed answers but discovery was delayed when Birdsall filed
for bankruptcy and the trial court dismissed plaintiff's complaint without
prejudice pending completion of the bankruptcy proceedings. The court
reinstated plaintiff's complaint in January 2018. Defendants moved for
summary judgment. The trial court granted summary judgment to the Borough
and Compass but denied summary judgment to Birdsall. Plaintiff and Birdsall
later settled, after which plaintiff appealed the order granting the Borough
summary judgment.
A-0305-18T4
3
B.
The summary judgment motion record, construed in the light most
favorable to plaintiff as the non-moving party, Petro-Lubricant Testing Labs.,
Inc. v. Adelman, 233 N.J. 236, 256 (2018), includes the following facts.
Plaintiff was injured in May 2009 while bicycling on the Bayshore Trail
("Trail") in the Borough. The Trail is over 8000 feet long, is constructed mostly
of asphalt, and runs in a general east-west direction. A wooden bridge spans a
section of the Trail.
The westerly end of the bridge abuts an asphalt portion of the Trail. There,
"the side flare has a gradient of over twenty-five (25) percent," which according
to plaintiff's engineering expert, "is quite steep." The expert asserted this steeply
sloped side flare created a hazardous and unsafe condition to walkers and those
on bicycles. The expert opined the construction and maintenance of this section
of the Trail is contrary to specific general safety practices and rules prevailing
in the industry, which he cited in his report. Although "the trail leading up to
[the] bridge, with [the] exception of [the] side flare, is protected on one side
with fencing and on the opposite side, a grassed area[,]" there was "no type of
guard to prevent persons from riding over" the sloped side flare.
A-0305-18T4
4
Plaintiff's expert noted the side flare exceeded the permissible gradient
and was missing a guardrail. He also noted a dedication ceremony was
conducted near the site of the accident, so the "steeply pitched surface, as noted,
was certainly observed and some type of guard could easily have been erected
to protect persons." He opined that relocation of the Trail or a "field change"
without re-engineering to account for a different location "violated engineering
standards and caused this bridge to be located at a place where it created the
hazard which caused plaintiff's injuries."
Plaintiff described the accident during her deposition. Riding in a
westerly direction, as she neared the bridge, she saw "a gentleman and a young
girl" on the bridge, to her right, straddling their bicycles. She believed they
were waiting for a young boy, who was approaching them. The young boy was
approaching from the opposite direction she was riding. The boy appeared to
be nervous as he saw plaintiff riding over the bridge. She had to make a sharp
left turn to avoid hitting the young boy. Unaware of the severely pitched side
flare, she fell from her bike into a ditch and was severely injured.
The engineer who signed off on the plans for the Trail was Katherine
Elliott, who worked for Birdsall. She testified during her deposition she
"inherited" the project from a previous engineering firm when the Borough
A-0305-18T4
5
appointed Birdsall as the Borough engineer. When she inherited the project, the
plans were "construction ready." She made some minor revisions—none in the
vicinity of plaintiff's accident—and signed off on them.
Elliott testified in her deposition: "No, [the Trail] was not constructed as
shown on the plans." She explained the bridge was constructed at a location
different from that shown on the plans. It was constructed further to the north.
She did not observe how its construction differed from the plans until after the
Trail was constructed.
According to Elliott, the bridge was relocated from its original designed
site because its final location provided for a more scenic view of the Sandy Hook
Bay "and also the original design location ran not only the bridge but part of the
trail to the active drainage site and it would have conflicted with dredging
operations." The recommendation was made to Elliott by a Borough official at
a pre-construction meeting that took place in the summer of 2008. She made no
further plans for the move because there were construction details already on
the plan.
Elliott further explained the asphalt placed toward the drainage ditch,
described as the side flare, was not part of the accessible route. The side flare
was capped "to prevent the exposed soil from eroding and to provide drainage,
A-0305-18T4
6
basically positive drainage off the ramp itself as the shoulder and as a soil table
measure." The asphalt section that continued off of what Elliott described as
the "accessible route" and into the drainage ditch was not part of the original
design, nor was it a part of the design added by Elliott. Rather, according to
Elliott, another Birdsall employee, Corey Germano, made the decision to asphalt
the portion that sloped into the drainage ditch. In fact, according to Elliott ,
Germano made the decision to asphalt the sloped portion into the drainage ditch
before even consulting with Elliott about the decision.
Elliot attended a ribbon-cutting ceremony when the Trail was complete.
She testified the ceremony took place in the vicinity where the accident later
occurred. Pressed, she testified the accident took place "right where the ribbon
cutting occurred." According to Elliott, after plaintiff's accident occurred "a
planter had been placed at the corner by the [B]orough."
In support of its summary judgment motion, the Borough submitted a
certification of its Business Administrator. The certification does not appear to
be based on personal knowledge. The Business Administrator certified that
when the Borough council approved the plan and design of the Trail prepared
by Birdsall, "the proposition of moving the [T]rail as shown on the plans a short
distance north was presented to the Council." The Business Administrator
A-0305-18T4
7
added, "[a]fter reviewing the plans and documents, the Council approved the
plan and design of the Trail with the knowledge that the Trail would be moved
further north than was depicted so as to avoid a dredge pit area in the location
where the [T]rail was original[ly] planned to be built."
The Business Administrator averred the approval is codified in Resolution
068-2008. This resolution was adopted on April 9, 2008. Although the Business
Administrator states in his certification that "Birdsall Engineering informed the
Borough that no new plans needed to be constructed to show the move further
north because the plans and construction details already called for what was
necessary to construct the trail[,]" the Business Administrator does not identify
the Birdsall employee who made such representations, state when they were
made, or state where they were made.
The Borough also presented the deposition testimony of Corey Germano,
Birdsall's "construction observer" and the construction supervisor for the Trail
project. Germano, by his own testimony, "was not privy to any plans." He
received plans the day of the pre-construction meeting. He testified construction
was done in accordance with the plan that was prepared by Elliott and signed by
her.
A-0305-18T4
8
The trial court granted summary judgment to the Borough. The court
determined the Borough had established design immunity. The court further
determined plaintiff had failed to establish a genuinely disputed issue of material
fact as to whether the Borough's property was in a dangerous condition that
caused plaintiff's injuries.
II.
On appeal, plaintiff argues the court erred because genuinely disputed
issues of material fact existed as to both issues. Plaintiff contends the court
overlooked the requirement that the specific defective condition of public
property that causes injury must have been encompassed with an approved
design. Plaintiff also argues the court's determination that the Borough had no
notice, actual or constructive, of the dangerous condition, was erroneous
because it was in part created by the Borough.
The Borough argues the court correctly determined the Borough had
design immunity because even though the bridge was moved, details of the
actual bridge's construction were provided in the plans. Acknowledging the
"'defect' in question . . . is the alleged steep slope of the side flare of the
bridge[,]" the Borough insists the trial court correctly found "all evide nce of
record indicates that that side flare was designed and constructed in accordance
A-0305-18T4
9
with the approved plans." The Borough also argues plaintiff cannot establish
the Borough had either actual or constructive notice of the dangerous condition.
III.
We review a trial court's order granting summary judgment under settled
standards. A trial court's order granting summary judgment is entitled to no
"special deference" by an appellate court and is subject to de novo
review. Cypress Point Condo. Ass'n v. Adria Towers, L.L.C., 226 N.J. 403, 415
(2016) (citation omitted). Appellate courts "review the competent evidential
materials submitted by the parties to identify whether there are genuine issues
of material fact and, if not, whether the moving party is entitled to summary
judgment as a matter of law." Bhagat v. Bhagat, 217 N.J. 22, 38 (2014) (citing
Brill v. Guardian Life Ins. Co. of Am., 142 N.J. 520, 540 (1995)). Here, we
conclude genuine issues of material fact preclude the grant of summary
judgment.
A.
We first address design immunity. The TCA provides:
Neither the public entity nor a public employee is liable
under this chapter for an injury caused by the plan or
design of public property, either in its original
construction or any improvement thereto, where such
plan or design has been approved in advance of the
construction or improvement by the Legislature or the
A-0305-18T4
10
governing body of a public entity or some other body
or a public employee exercising discretionary authority
to give such approval or where such plan or design is
prepared in conformity with standards previously so
approved.
[N.J.S.A. 59:4-6(a).]
The Borough was required to establish plan or design immunity. "It is
well established that the burden is on the public entity both to plead and prove
its immunity under our Act." Wymbs v. Twp. of Wayne, 163 N.J. 523, 539
(2000) (quoting Kolitch v. Lindedahl, 100 N.J. 485, 497 (1985)). Moreover,
plan or design immunity turns on whether "the public entity has approved the
feature in question so as to immunize it from challenge." Manna v. State, 129
N.J. 341, 353 (1992). "In other words, 'the public entity must establish that an
approved feature of the plan sufficiently addressed the condition that is causally
related to the accident.'" Ibid. (quoting Thompson v. Newark Hous. Auth., 108
N.J. 525, 536 (1987)). Although a public entity need not show each feature of
a plan was specifically considered and rejected, it must "offer evidence that it
had considered the general condition about which a plaintiff complains in
formulating the original plan or design." Luczak v. Twp. of Evesham, 311 N.J.
Super. 103, 109 (App. Div. 1998).
A-0305-18T4
11
Here, the Borough did not produce the plans Elliott signed. Nor did the
Borough have someone testify that asphalting the steep slope adjacent to the
Trail and bridge—and not providing a protective barrier—was specified or
considered before the plan was approved by the Borough's 2008 resolution. The
Borough produced no evidence that the bridge in its originally designed location
was near a drainage ditch, or that such ditch was required to be constructed as
part of the design plan. And of course, such testimony would have been
contradicted by Elliott's testimony. Even if the Borough Council had considered
moving the bridge when it adopted its resolution in April 2008, Elliott was
unaware the governing body was considering moving the bridge until a pre -
construction job meeting later that summer.
The Business Administrator's certification is incompetent because it does
not establish it was based on personal knowledge as required by Rule 1:6-6. But
even if it is considered, it at most creates a factual dispute to be resolved by the
jury. The Business Administrator avers that when the Borough Council
approved the Birdsall plans, "the proposition of moving the trail as shown on
the plans a short distance north was presented to the Council." The "presenter's"
identity is not disclosed, so no one can determine from the certification who
allegedly made the presentation.
A-0305-18T4
12
Further along in his certification, the Business Administrator identifies
the actor as "Birdsall Engineering," who also allegedly informed the Borough
no new plans would be needed to show the move because the plan details
previously called for what was necessary to construct the Trail. Elliott, who
signed the plans, testified she did not know about the move until a pre-
construction meeting in the summer of 2008. Germano, who oversaw the
construction, had nothing to do with the plans until he was provided a copy at
the pre-construction meeting.
In any event, even if the Business Administrator's certification is given
any credence, it is contradicted by Elliott and thus, at best, creates a factual
dispute about whether the Borough Council considered the relocation of the
bridge when it adopted the 2008 resolution. Furthermore, as previously noted,
the specific dangerous condition—the steeply sloped, unguarded side flare—had
never been considered by Elliott by April 2008 when the Borough Council
adopted the resolution. Paving the slope was a decision allegedly made later by
Germano.
In short, based on the proofs on the summary judgment motion record,
there was at minimum a genuinely disputed issue of material fact concerning
A-0305-18T4
13
design immunity. The Borough was not entitled to design immunity as a matter
of law.
B.
There were also genuinely disputed issues of material fact as to whether
the Borough's property was in a dangerous condition when plaintiff fell. To
establish a public entity's liability for a dangerous condition of property under
the TCA, a plaintiff must establish:
that the property was in dangerous condition at the time
of the injury, that the injury was proximately caused by
the dangerous condition, that the dangerous condition
created a reasonably foreseeable risk of the kind of
injury which was incurred, and that either:
a. a negligent or wrongful act or omission of an
employee of the public entity within the scope of his
employment created the dangerous condition; or
b. a public entity had actual or constructive notice
of the dangerous condition under section 59:4-3 a
sufficient time prior to the injury to have taken
measures to protect against the dangerous condition.
Nothing in this section shall be construed to impose
liability upon a public entity for a dangerous condition
of its public property if the action the entity took to
protect against the condition or the failure to take such
action was not palpably unreasonable.
[N.J.S.A. 59:4-2.]
A-0305-18T4
14
The Borough argues plaintiff's proofs were insufficient to create a
genuinely disputed issue of material fact concerning two elements of this cause
of action. Specifically, the Borough argues there is no evidence from which a
fact finder could conclude the Borough had actual or constructive notice of the
dangerous condition, and there is no evidence from which a fact finder could
conclude the Borough's inaction was palpably unreasonable. We disagree.
First, a fact finder could conclude it was reasonably foreseeable that an
unguarded, steeply-sloped side flare to a ditch, adjacent to a recreational trail
and bridge, created a risk to bicyclists and joggers of precisely the type of
accident that befell plaintiff. Actual and constructive notice are defined in the
TCA:
a. A public entity shall be deemed to have actual
notice of a dangerous condition within the meaning of
subsection b. of section 59:4-2 if it had actual
knowledge of the existence of the condition and knew
or should have known of its dangerous character.
b. A public entity shall be deemed to have
constructive notice of a dangerous condition within the
meaning of subsection b. of section 59:4-2 only if the
plaintiff establishes that the condition had existed for
such a period of time and was of such an obvious nature
that the public entity, in the exercise of due care, should
have discovered the condition and its dangerous
character.
[N.J.S.A. 59:4-3.]
A-0305-18T4
15
The facts plaintiff developed on the motion record create a factual dispute
as to whether the Borough had actual or constructive notice. Plaintiff
established through Elliott's testimony that the ribbon-cutting ceremony took
place at the location where plaintiff fell from her bike. A fact finder could infer
from that testimony that public officials were present at the site and observed
the condition. There is a question of fact as to whether the proximity of the
unguarded slope to the bridge and path created a readily discernible, obvious
risk of danger, and there is also a question of fact as to whether Borough officials
knew or should have known of its dangerous character. These issues should be
decided by the fact finder.
Plaintiff also argues the Borough created the dangerous condition by
directing the relocation of the bridge to the site where it was constructed. We
reject this argument. That decision did not create the paved slope to the ditch
adjacent to the bridge and asphalt path.
The Borough next argues its failure to take action to protect against the
dangerous condition was not palpably unreasonable. "Palpable
unreasonableness is a question of fact." Vincitore v. N.J. Sports & Exposition
Auth., 169 N.J. 119, 130 (2001) (citing Furey v. Cty. of Ocean, 273 N.J. Super.
300, 313 (App. Div. 1994)). Thus, if the fact finder determines the paved slope
A-0305-18T4
16
was a dangerous condition of the Borough's property, it must also determine
whether it was palpably unreasonable not to take any action to guard against the
danger. Ibid.
Reversed and remanded. We do not retain jurisdiction.
A-0305-18T4
17