Opinion issued December 23, 2021
In The
Court of Appeals
For The
First District of Texas
———————————
NO. 01-19-01000-CV
———————————
TRIMCOS, LLC, Appellant
V.
COMPASS BANK, Appellee
On Appeal from the 157th District Court
Harris County, Texas
Trial Court Case No. 2018-42334
OPINION
Appellant, Trimcos, LLC (“Trimcos”), challenges the trial court’s rendition
of summary judgment in favor of appellee, Compass Bank (“Compass”), in
Trimcos’s suit against Compass for money had and received, constructive trust, and
breach of contract. In three issues, Trimcos contends that the trial court erred in
granting Compass summary judgment.
We affirm.
Background
In its first amended petition, Trimcos alleged that on or about April 26, 2013,
it entered a general construction contract (the “contract”) to build an office building
on vacant land (the “project”) “for Raffy O. Bell and/or Bell Tech Enterprises, Inc.”
(collectively, “Bell”).1 On or about April 30, 2013, Trimcos and Bell executed a
“Contractor’s Agreement and Consent” (the “contractor’s agreement”) for Compass,
Bell’s lender, at a loan closing. (Internal quotations omitted.) As consideration for
the contractor’s agreement, Compass represented to Bell that it would be financially
liable for the work Trimcos completed under the contract. On May 8, 2013,
Compass recorded a deed of trust relating to the project.
1
The Harris County Clerk’s real property records show that Bell Tech Enterprises,
Inc. acquired the property at issue by warranty deed on December 9, 2008. See TEX.
R. EVID. 201(b)(2); Office of Public Util. Counsel v. Public Util. Comm’n of Tex.,
878 S.W.2d 598, 600 (Tex. 1994) (appellate courts may take judicial notice of facts
which are “capable of accurate and ready determination by resort to a published
record whose accuracy cannot reasonably be questioned”); Alsobrook v. MTGLQ
Investors, LP, No. 05-20-00400-CV, 2021 WL 4958860, at *2 (Tex. App.—Dallas
Oct. 26, 2021, no pet.) (mem. op.) (taking judicial notice of property records).
2
During construction of the project, Trimcos received progress payments
directly from Compass. But “[b]ecause Trimcos was not paid in full for [the] work
completed,” it “recorded a mechanic’s lien affidavit on June 15, 2015.”
Then Bell defaulted on its loan from Compass, and, as a result, Compass
foreclosed on the property where the project was to be built. On July 10, 2017,
Compass “recorded a substitute trustee’s deed relating to the [p]roject.” According
to the substitute trustee’s deed, Compass “bid $1,953,000.00 for the [p]roject.”
Trimcos “repeatedly demanded” that Compass “pay for work it [had] completed per
the [c]ontract and . . . account for proceeds resulting from the foreclosure sale,” but
Compass “refused to pay.”
Trimcos brought claims against Compass for money had and received,
constructive trust, and breach of contract.2 As to its claim for money had and
received, Trimcos maintained that “[i]f [Compass] was subrogated to the 2008 deed
of trust” and Trimcos’s “[mechanic’s] lien claim was extinguished, Trimcos still
ha[d] a [mechanic’s] lien claim against the foreclosure proceeds in excess of the
amount needed to satisfy the 2008 deed of trust.” And Trimcos requested the
imposition of a “constructive trust in the foreclosure proceeds in an amount
sufficient to satisfy its lien claim.” As to its breach-of-contract claim, Trimcos
2
Trimcos also brought a fraudulent-inducement claim against Compass.
3
alleged that Compass “failed to comply with its obligation under the [c]ontractor’s
[a]greement (which Compass Bank made part of the loan transaction between it and
Bell) to pay for work completed” under the contract. Trimcos sought damages,
attorney’s fees, and costs.
Compass answered, generally denying the allegations in Trimcos’s petition
and pleading certain affirmative defenses. Compass also brought several
counterclaims against Trimcos. In its second amended counterclaim, Compass
alleged that in 2013, Bell “approached [Compass]” to obtain a Small Business Act3
“construction loan to purchase land and build an office building for [its] business.”
And Compass acknowledged that Trimcos entered the contract with Bell for Trimcos
to serve as the general contractor for the project on April 26, 2013.
According to Compass, “[a]s part of [its] pre-loan procedures, Compass
communicated with and interacted with Trimcos.” To ensure that its deed of trust
would constitute a first lien on the property where the project was to be built,
Compass acquired, among other things, documentation signed by Trimcos that
Trimcos had not commenced construction or delivered materials to the project
property and Trimcos’s written assurance that construction “would not begin” and
materials would not “be delivered until” Compass had filed its deed of trust.
3
See 15 U.S.C. §§ 631–657u.
4
As part of the loan transaction, Compass also required Bell and Trimcos to
execute a “Contractor and Owner Joint Affidavit of Commencement” (the “first
affidavit”) and an “Affidavit of Commencement” (the “second affidavit”).4 Bell and
Trimcos signed the first affidavit on April 25, 2013, the day before they executed
the contract for the project. In the second affidavit, signed on April 30, 2013, Bell
and Trimcos represented that no construction had begun on the project and no
materials had been delivered to the property where the project was to be built and
that construction would not begin and materials would not be delivered until
Compass “notified [Bell] and [Trimcos] in writing that the [d]eed of [t]rust has been
filed in the county records.” Bell and Trimcos also attested that they executed the
second affidavit “in order to assure [Compass] that the time of the inception of any
mechanic’s lien ha[d] not occurred, and w[ould] not occur until after [Compass]’s
[d]eed of [t]rust [wa]s duly perfected by filing.”
Compass further alleged that although Trimcos had executed the first and
second affidavits, “Trimcos sent a demand letter to Compass” on August 16, 2017,
“claiming for the first time that Trimcos began construction of the [project] before
Compass [had] recorded its [d]eed of [t]rust.”
4
See TEX. PROP. CODE ANN. § 53.124(c).
5
Compass brought a counterclaim against Trimcos for “fraud involving a false
promise of future performance.” According to Compass, it was “not responsible for
[making] payments to Trimcos,” because, among other things, the contractor’s
agreement specifically precluded Compass from being liable to Trimcos, the
“conditions [precedent] for payment under the [contractor’s] agreement” were “not
met,” and “the amounts claimed by Trimcos [we]re not due and owing.” And,
according to Compass, Trimcos committed fraud “[w]ith respect to the [s]econd
[a]ffidavit,” in which “Trimcos promised that construction [of the project] would not
commence” and materials would not “be delivered to the [project property] until”
Compass “notified Trimcos that the [d]eed of [t]rust was filed.”
Compass also brought a breach-of-contract claim against Trimcos, asserting
that, “as a direct creditor third party beneficiary of the [second affidavit],” Trimcos
breached the second affidavit by “beginning construction or delivering materials to
the [project property]” before Compass’s deed of trust was filed. And Compass
sought a declaration that it was not liable to Trimcos for any amount under the
contractor’s agreement.
Trimcos answered, generally denying the allegations in Compass’s
counterclaim and asserting certain affirmative defenses.
Compass then filed a combined no-evidence and matter-of-law
summary-judgment motion on Trimcos’s claims for money had and received,
6
constructive trust, and breach of contract. As to the no-evidence portion of its
motion, Compass argued that Trimcos’s money-had-and-received claim failed
because there was no evidence that Trimcos’s mechanic’s lien had priority over
Compass’s deed of trust or that Compass held funds belonging to Trimcos. And as
to Trimcos’s constructive-trust claim, Compass argued that there was “no evidence
that [Compass] [wa]s holding money” that belonged to Trimcos because, as with
Trimcos’s money-had-and-received claim, its constructive-trust claim was
dependent on establishing that the priority of Trimcos’s mechanic’s lien was
superior to that of Compass’s deed of trust, which Trimcos could not do.
As to the matter-of-law portion of its motion, Compass argued that it was
entitled to judgment as a matter of law on Trimcos’s breach-of-contract claim
because Compass was not a party to the contractor’s agreement between Bell and
Trimcos, which was the basis for Trimcos’s breach-of-contract claim. Alternatively,
Compass argued that the particular “conditions precedent for [Trimcos’s] right to
receive payment under the [c]ontractor’s [a]greement” had not been satisfied. To
support its argument, Compass relied on paragraph 7 of the contractor’s agreement,
which provides that “the final advance, including all retainage, will not be made until
[Compass] has received . . . evidence that no mechanic’s or materialmen’s liens or
other encumbrances have been filed and remain in effect against the [project]
[p]roperty” and “final lien releases or waivers [have been made] by
7
[Trimcos], . . . subcontractors, materialmen and all other parties who have supplied
labor, materials or services for the construction” of the project.5 And Compass
attached to its summary-judgment motion the affidavit of Robert Zazula, a Senior
Vice President of Compass, who attested that on April 30, 2013, Bell executed a
promissory note payable to Compass in the amount of $4,622,500.00 as well as a
deed of trust in favor of Compass to secure that indebtedness. Also, on April 30,
2013, “as part of th[at] transaction,” Trimcos and Bell executed the contractor’s
agreement. According to Zazula, another company working on the project got into
a dispute with Trimcos and that company filed a mechanic’s lien on the project
property which was covered by the deed of trust. “[A] lawsuit was in progress”
between that other company and Trimcos. In February 2015, Trimcos’s attorney
informed Compass that Trimcos had worked on the project with that other company
as a subcontractor, “even though [the other company] claimed that it was actually a
general contractor.” And in June 2015, Zazula learned from Trimcos’s attorney that
Trimcos “had also filed a mechanic[’]s lien on the [project] property [which was]
being covered by the [d]eed of [t]rust.” Zazula stated that “Compass declined to pay
[to Trimcos the] retainage withheld during the . . . project,” as permitted under the
5
Compass attached a copy of the contractor’s agreement to its summary-judgment
motion.
8
contractor’s agreement, because of the existing mechanic’s liens and because
Trimcos had failed to provide Compass with a lien release from the other company.
Compass also argued, in the matter-of-law portion of its summary-judgment
motion, that it had not breached its obligations under the contractor’s agreement
because it was not required to pay for certain additional items sought by Trimcos.
Under paragraph 7 of the contractor’s agreement, Compass was required to pay only
for “costs and expenses specified in the budget approved by [Compass].” And the
additional items for which Trimcos sought payment “were not presented to Compass
in a budget or a change order and were therefore not contractually or properly
presented for payment.” Those items included permit fees, an additional
$135,000.00 for a retaining wall, and certain other additional expenses. As to those
items, Zazula testified, in his affidavit attached to the summary-judgment motion,
that “the budget approved for [the project] did not include permit fees, and no change
order was submitted to include those fees.” As to Trimcos’s $135,000.00 claim for
the retaining wall, Zazula attached to his affidavit documentation showing that
Trimcos had agreed to absorb that additional expense. And as to the other additional
expenses, Zazula stated that “[n]o change order request[s] were received for th[o]se
items,” so they had not been “approved by [Compass]” as required for payment
under the contractor’s agreement.
9
In response to Compass’s summary-judgment motion, Trimcos asserted that
as to Compass’s no-evidence grounds related to its money-had-and-received and
constructive-trust claims, it was not required to “prove that it rendered services or
delivered materials before Compass . . . recorded its deed of trust on May 8. 2013,”
only that it entered the contract with Bell before May 8, 2013. And Trimcos argued
that because the contract was executed April 26, 2013, its mechanic’s lien had
priority over Compass’s deed of trust under the “relation-back doctrine,” under
which a general construction contract between an owner and a contractor sets the
time of inception of all mechanic’s liens created by the construction as the date that
the contract was executed.6 Further, Trimcos asserted that the following allegation,
in Compass’s first amended counterclaim—a pleading that was superseded—
constituted an admission of a party opponent that raised a fact issue precluding
summary judgment on Trimcos’s money-had-and-received and constructive-trust
claims: “Based on statements by Trimcos before and after the filing on this lawsuit,
Trimcos breached the terms of the [s]econd [a]ffidavit by beginning construction or
delivering materials to the [project property] prior to the date the [d]eed of [t]rust
was filed.”
6
See Suntex Fuller Corp. v. Flint Mortg. Grp., No. 01-04-00994-CV, 2007 WL
1018637, at *3 (Tex. App.—Houston [1st Dist.] April 5, 2007, no pet.) (mem. op.)
(citing McConnell v. Mortg. Inv. Co. of El Paso, 305 S.W.2d 280, 283 (Tex. 1957)).
10
As to Compass’s matter-of-law grounds related to Trimcos’s
breach-of-contract claim, Trimcos responded that it had “standing to assert a claim
based on the [c]ontractor’s [a]greement” and that there were “no unsatisfied
conditions precedent under the [c]ontractor’s [a]greement.” Alternatively, Trimcos
argued that summary judgment on its breach-of-contract claim was not proper
“because the removal of liens [was] not [a] condition[] precedent” under the
contractor’s agreement. And Trimcos referred to the contract to support its position
that it “was entitled to final payment for its work [on the project] within three (3)
days of obtaining the certificate of occupancy,” which was issued on June 3, 2015.
The trial court granted Compass summary judgment on Trimcos’s claims for
money had and received, constructive trust, and breach of contract and awarded
Compass attorney’s fees. Compass then nonsuited its counterclaims against
Trimcos, making the trial court’s summary judgment final.
Standard of Review
We review a trial court’s decision to grant summary judgment de novo.
Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex. 2005); Provident Life
& Accident Ins. Co. v. Knott, 128 S.W.3d 211, 215 (Tex. 2003). In conducting our
review, we take as true all evidence favorable to the non-movant, and we indulge
every reasonable inference and resolve any doubts in the non-movant’s favor.
Valence Operating, 164 S.W.3d at 661; Knott, 128 S.W.3d at 215. If a trial court
11
grants summary judgment without specifying the grounds for granting the motion,
we must uphold the trial court’s judgment if any of the asserted grounds are
meritorious. Beverick v. Koch Power, Inc., 186 S.W.3d 145, 148 (Tex. App.—
Houston [1st Dist.] 2005, pet. denied).
A party seeking summary judgment may combine in a single motion a request
for summary judgment under the no-evidence standard with a request for summary
judgment as a matter of law. Binur v. Jacobo, 135 S.W.3d 646, 650–51 (Tex. 2004).
To prevail on a no-evidence summary-judgment motion, the movant must establish
that there is no evidence to support an essential element of the non-movant’s claim
on which the non-movant would have the burden of proof at trial. See TEX. R. CIV.
P. 166a(i); Fort Worth Osteopathic Hosp., Inc. v. Reese, 148 S.W.3d 94, 99 (Tex.
2004); Hahn v. Love, 321 S.W.3d 517, 523–24 (Tex. App.—Houston [1st Dist.]
2009, pet. denied). The burden then shifts to the non-movant to present evidence
raising a genuine issue of material fact as to each of the elements challenged in the
motion. Mack Trucks, Inc. v. Tamez, 206 S.W.3d 572, 582 (Tex. 2006); Hahn, 321
S.W.3d at 524. A no-evidence summary-judgment may not be granted if the
non-movant brings forth more than a scintilla of evidence to raise a genuine issue of
material fact on the challenged elements in the motion. See Ford Motor Co. v.
Ridgway, 135 S.W.3d 598, 600 (Tex. 2004). More than a scintilla of evidence exists
when the evidence “rises to a level that would enable reasonable and fair-minded
12
people to differ in their conclusions.” Merrell Dow Pharm., Inc. v. Havner, 953
S.W.2d 706, 711 (Tex. 1997) (internal quotations omitted). The trial court must
grant a no-evidence summary-judgment motion if the movant asserts that there is no
evidence of one or more specified elements of the non-movant’s claim on which the
non-movant would have the burden of proof at trial and the non-movant fails to file
a timely response or fails to produce summary-judgment evidence raising a genuine
issue of material fact on each challenged element. See TEX. R. CIV. P. 166a(i);
Lockett v. HB Zachry Co., 285 S.W.3d 63, 67 (Tex. App.—Houston [1st Dist.] 2009,
no pet.).
To prevail on a matter-of-law summary-judgment motion, a movant has the
burden of establishing that it is entitled to judgment as a matter of law and there is
no genuine issue of material fact. TEX. R. CIV. P. 166a(c); Cathey v. Booth, 900
S.W.2d 339, 341 (Tex. 1995). When a defendant moves for a matter-of-law
summary judgment, it must either: (1) disprove at least one essential element of the
plaintiff’s cause of action, or (2) plead and conclusively establish each essential
element of an affirmative defense, thereby defeating the plaintiff’s cause of action.
See Cathey v. Booth, 900 S.W.2d 339, 341 (Tex. 1995); Centeq Realty, Inc. v.
Siegler, 899 S.W.2d 195, 197 (Tex. 1995). Once the movant meets its burden, the
burden shifts to the non-movant to raise a genuine issue of material fact precluding
summary judgment. See Siegler, 899 S.W.2d at 197; Transcon. Ins. Co. v. Briggs
13
Equip. Trust, 321 S.W.3d 685, 691 (Tex. App.—Houston [14th Dist.] 2010, no pet.).
The evidence raises a genuine issue of fact if reasonable and fair-minded jurors could
differ in their conclusions in light of all of the summary-judgment evidence.
Goodyear Tire & Rubber Co. v. Mayes, 236 S.W.3d 754, 755 (Tex. 2007).
No-Evidence Summary Judgment
In its first and second issues, Trimcos argues that the trial court erred in
granting Compass summary judgment on Trimcos’s claims for money had and
received and for constructive trust because Trimcos’s mechanic’s lien had priority
over Compass’s deed of trust.
The equitable doctrines of money had and received and constructive trust are
applied to prevent unjust enrichment. Ferrara v. Nutt, 555 S.W.3d 227, 244 (Tex.
App.—Houston [1st Dist.] 2018, no pet.); Pickelner v. Adler, 229 S.W.3d 516, 527
(Tex. App.—Houston [1st Dist.] 2007, pet. denied); Nivens v. City of League City,
245 S.W.3d 470, 474 n.2 (Tex. App.—Houston [1st Dist.] 2007, pet. denied);
Swinehart v. Stubbeman, McRae, Sealy, Laughlin, & Browder, Inc., 48 S.W.3d 865,
878 (Tex. App.—Houston [14th Dist.] 2001, pet. denied). Trimcos’s
money-had-and-received and constructive-trust claims were both premised on
Trimcos’s position that its mechanic’s lien on the project property was superior to
Compass’s deed of trust. Specifically, Trimcos maintains that the filing of its
14
mechanic’s lien relates back to April 26, 2013, the date that Trimcos and Bell
executed the contract, and thus predates the recording of Compass’s deed of trust.
“Mechanic’s liens did not exist at common law or in equity, but rather are
creatures of statute.” CVN Grp. v. Delgado, 95 S.W.3d 234, 246 (Tex. 2002)
(Hankinson, J., dissenting) (citing Lippencott v. York, 24 S.W. 275, 276 (Tex. 1893);
Pratt v. Tudor, 14 Tex. 37, 39 (1855)); see also Crawford Servs., Inc. v. Skillman
Int’l Firm, L.L.C., 444 S.W.3d 265, 267 (Tex. App.—Dallas 2014, pet. dism’d). The
Texas Constitution and Texas Property Code Chapter 53 address the creation of
mechanic’s liens. See TEX. CONST. art. XVI, § 37;7 TEX. PROP. CODE ANN.
§§ 53.001–.260; CVN Grp., 95 S.W.3d at 246–47 (Hankinson, J., dissenting); Hayek
v. W. Steel Co., 478 S.W.2d 786, 790–91 (Tex. 1972). In her dissenting opinion in
CVN Group, Justice Hankinson discussed the interplay between the constitutional
and statutory provisions:
The constitution grants to each contractor who enters into a direct
contractual relationship with the real property owner a lien upon the
property for materials and labor provided in improving it. . . . [T]he
constitutional lien is self-executing; that is, no notice or filing
7
Article 16, section 37 of the Texas Constitution, titled, “Liens of mechanics,
artisans, and material men,” states:
Mechanics, artisans and material men, of every class, shall have a lien
upon the buildings and articles made or repaired by them for the value
of their labor done thereon, or material furnished therefor; and the
[Texas] Legislature shall provide by law for the speedy and efficient
enforcement of said liens.
TEX. CONST. art. XVI, § 37 (emphasis added).
15
requirements must be met for the lien to attach, and the lien exists
independently and apart from any legislative act. The constitutional
lien is not, however, self-enforcing, and the constitution further requires
the [Texas] Legislature to provide for the enforcement of mechanic’s
liens.
CVN Grp., 95 S.W.3d at 246–47 (Hankinson, J., dissenting) (internal citations
omitted).
The question here involves the time of inception of Trimcos’s mechanic’s
lien. In connection with the closing on the construction loan for the project,
Trimcos—the general contractor—signed affidavits attesting that no work had
commenced on the project and no materials had been delivered to the property where
the project was to be built. These representations track the statutory language
establishing when a lien attaches. See TEX. PROP. CODE ANN. § 53.124.8 Compass
8
Texas Property Code section 53.124, titled “Inception of Mechanic’s Lien,”
provides:
(a) Except as provided by [s]ubsection (e), for purposes of [Texas
Property Code] [s]ection 53.123, the time of inception of a mechanic’s
lien is the commencement of construction of improvements or
delivery of materials to the land on which the improvements are to be
located and on which the materials are to be used.
(b) The construction or materials under [s]ubsection (a) must be
visible from inspection of the land on which the improvements are
being made.
(c) An owner and original contractor may jointly file an affidavit
of commencement with the county clerk of the county in which the
land is located not later than the 30th day after the date of actual
commencement of construction of the improvements or delivery of
materials to the land. The affidavit must contain:
(1) the name and address of the owner;
16
relied on those representations in lending funds to Bell for the project’s construction
to ensure that its deed of trust would constitute a first lien on the project property.
Trimcos urges us to follow the “relation[-]back” doctrine first declared by the
Texas Supreme Court in Oriental Hotel v. Griffiths. 33 S.W. 652, 653 (Tex. 1895).
According to that common-law doctrine, if there is a general construction contract
between an owner and a contractor, the time of inception of all mechanic’s liens
(2) the name and address of each original contractor, known
at the time to the owner, that is furnishing labor, service, or
materials for the construction of the improvements;
(3) a description, legally sufficient for identification, of the
property being improved;
(4) the date the work actually commenced; and
(5) a general description of the improvement.
(d) An affidavit filed in compliance with this section is prima facie
evidence of the date of the commencement of the improvement
described in the affidavit. The time of inception of a mechanic’s lien
arising from work described in an affidavit of commencement is the
date of commencement of the work stated in the affidavit.
(e) The time of inception of a lien that is created under [Texas
Property Code [s]ection 53.021(c), (d), or (e)[, addressing liens for
architects, surveyors, landscapers, demolition workers, and others,] is
the date of recording of an affidavit of lien under [s]ection 53.052.
The priority of a lien claimed by a person entitled to a lien under
[s]ection 53.021(c), (d), or (e) with respect to other mechanic’s liens
is determined by the date of recording. A lien created under [s]ection
53.021(c), (d), or (e) is not valid or enforceable against a grantee or
purchaser who acquires an interest in the real property before the time
of inception of the lien.
TEX. PROP. CODE ANN. § 53.124(a)–(e).
17
created by the construction is the date that the general construction contract was
executed. McConnell v. Mortg. Inv. Co. of El Paso, 305 S.W.2d 280, 283 (Tex.
1957); Suntex Fuller Corp. v. Flint Mortg. Grp., No. 01-04-00994-CV, 2007 WL
1018637, at *3 (Tex. App.—Houston [1st Dist.] Apr. 5, 2007, no pet.) (mem. op.).
Applying that doctrine here, Trimcos argues that because its execution of the
contract—a general construction contract—with Bell predates Compass’s deed of
trust, its mechanic’s lien has priority over Compass’s deed of trust. Compass, on the
other hand, looks to Texas Property Code section 53.124 as the sole authority for
establishing the priority of Trimcos’s mechanic’s lien and argues that, because that
section does not declare that a mechanic’s lien relates back to the date of the contract,
Trimcos’s mechanic’s lien does not predate Compass’s deed of trust.
When the Texas Supreme Court decided Oriental Hotel, the mechanic’s lien
statute did not address a lien’s time of inception. See 33 S.W. at 661–62. In 1971,
though, the Texas Legislature amended the statute to define “inception of the lien.”
See Act of May 17, 1971, 62d Leg., R.S., ch. 231, § 1, 1971 Tex. Gen. Laws 1082.
This amendment was passed “in reaction to the first opinion rendered [by the Texas
Supreme Court] in Irving Lumber Co[.] v. Alltex Mortgage Co[.],[9] which allowed
9
14 Tex. Sup. Ct. J. 212 (July 2, 1971), on reh’g, 468 S.W.2d 341 (Tex. 1971); see
also Diversified Mortg. Invs. v. Lloyd D. Blaylock Gen. Contractor, Inc., 576
S.W.2d 794, 804–05 (Tex. 1978) (explaining first opinion in Irving Lumber “was
rendered on July 2, 1971,” but Texas Supreme Court “consider[ed] [a] motion for
rehearing,” “withdrew the first opinion[,] and substituted the second opinion on May
18
oral construction contracts to indicate the inception of a mechanic’s lien, thereby in
effect allowing the creation of silent or secret mechanic’s liens.” Diversified Mortg.
Invs. v. Lloyd D. Blaylock Gen. Contractor, Inc., 576 S.W.2d 794, 804–05 (Tex.
1978) (internal citation omitted). By defining the “inception of a lien,” the amended
statute “created the system whereby mortgagors could rely upon notice in the county
records or by visual inspection of the property as to any existing liens on the
property.” Id. at 805 (internal quotations omitted).
Since 1971, then, Texas has statutorily defined the time of inception of a
mechanic’s lien. Currently, Texas Property Code section 53.124 specifies that the
time of inception of a mechanic’s lien is “the commencement of construction of
improvements or delivery of materials to the land on which the improvements are to
be located and on which the materials are to be used,” as long as they are “visible
from inspection of the land on which the improvements are being made.” TEX. PROP.
CODE ANN. § 53.124(a), (b). And section 53.124 specifically addresses “original
contractors,” i.e., persons who “contract with an owner either directly or through the
owner’s agent,”10 providing that the owner and original contractor “may jointly file
an affidavit of commencement with the county clerk of the county in which the land
19, 1971”; “[t]he second opinion d[id] not construe or refer in any way to the
amendment”).
10
See TEX. PROP. CODE ANN. § 53.001(7) (defining “[o]riginal contractor” (internal
quotations omitted)).
19
is located not later than the 30th day after the date of actual commencement of
construction of the improvements or delivery of materials to the land.” Id.
§ 53.124(c). An affidavit with contents that comply with the statute will constitute
“prima facie evidence of the date of the commencement of the improvement
described in the affidavit,” which is “[t]he time of inception of a mechanic’s lien
arising from work described” in the affidavit. Id. § 53.124(d), (e). These provisions
would have no purpose if the general contractor could simply rely on the date of the
general construction contract as the time of the inception of the mechanic’s lien.
The Texas Constitution directs the Texas Legislature to “provide by law for
the speedy and efficient enforcement of [mechanic’s] liens.” TEX. CONST. art. XVI,
§ 37. Because mechanic’s liens are “creatures of statute,” it would violate that
constitutional directive if we decided to override the Texas Property Code’s specific
definition of the time of a lien’s inception with a common-law rule gleaned from a
case decided before the applicable statute defined the time of inception.11 “A
11
In Hubert Lumber Co. v. King, an appeal decided on rehearing shortly after the
Texas Supreme Court issued its second opinion in Irving Lumber, this Court was
asked to apply the lien inception rule stated in Oriental Hotel v. Griffiths, 33 S.W.
652 (Tex. 1895), but determined that the rule did not apply because the party
contracting with the lienholder was only a prospective owner. See 468 S.W.2d 503,
504–05 (Tex. App.—Houston [1st Dist.] 1971, writ ref’d n.r.e.). And in a 2011
opinion, this Court cited to Oriental Hotel in explaining that:
The time of inception of a properly perfected [mechanic]’s lien is
the earlier of either (1) the commencement of a lienholder’s
construction of improvements on the property or (2) the
lienholder’s delivery of materials to the land on which the
20
fundamental constraint on the courts’ role in statutory interpretation is that the
[l]egislature enacts the laws of the state and the courts must find their intent in that
language and not elsewhere.” Liberty Mut. Ins. Co. v. Adcock, 412 S.W.3d 492, 493
(Tex. 2013). We must presume that “the [l]egislature deliberately and purposefully
selects words and phrases it enacts, as well as deliberately and purposefully omits
words and phrases it does not enact.” Tex. Mut. Ins. Co. v. Ruttiger, 381 S.W.3d
430, 452 (Tex. 2012). These interpretive constraints have particular force here,
where the Texas Constitution gives the legislature the exclusive authority to enact
laws for the enforcement of mechanic’s liens. And we acknowledge that the
improvements are to be located and on which the materials are to
be used. TEX. PROP. CODE ANN. § 53.124(a) . . . . If there is a
general contract regarding the construction of improvements to the
property, the courts apply the relation[-]back doctrine to determine
the time of a lien’s inception. Under the relation[-]back doctrine,
the time of inception of all [mechanic’s] liens created will be the
date the contract was executed if there is a general construction
contract between the owner and a contractor.
Texan Drywall, Inc. v. Le, No. 01-09 01063-CV, 2011 WL 2089668, at *3 (Tex.
App.—Houston [1st Dist.] May 19, 2011) (mem. op.). In that case, though, “there
was no evidence of a general construction contract,” so the Court’s discussion of
the date of inception of a mechanic’s lien is dicta. See id. And this Court used
similar language in Suntex Fuller. See 2007 WL 1018637, at *3. But, as in Texan
Drywall, in Suntex Fuller, “there was no general construction contract or general
contractor,” so that portion of the opinion is likewise dicta. See id.; see also Inman
v. Orndorff, 596 S.W.2d 236, 238 (Tex. App.—Houston [1st Dist.] 1980, no writ)
(using similar language but observing “[t]here is nothing in the evidence to show
that the improvements were placed on the subject land under a contract with the
owner of the land”). Thus, none of these cases are binding precedent as to the time
of inception of the mechanic’s lien in this case.
21
legislature has nowhere defined the time of inception of a mechanic’s lien as the date
that an owner and an original contractor execute a general construction contract.
We conclude that, for purposes of enforcing a mechanic’s lien, Texas Property
Code section 53.124, which defines the time of inception of a properly perfected
mechanic’s lien as the earlier of either (1) the commencement of a lienholder’s
construction of improvements on the property or (2) the lienholder’s delivery of
materials to the land on which the improvements are to be located and on which the
materials are to be used, provides the only measures for calculating the time of
inception of a mechanic’s lien, including those liens between an original contractor
and owner. Thus, the priority of Trimcos’s mechanic’s lien is determined by one of
those statutory measures, not by when Trimcos and Bell executed the contract.
We note Trimcos also maintains that Compass made an admission against
interest in a superseded pleading—its first amended counterclaim—that raises a fact
issue as to whether Trimcos began construction of improvements or delivered
materials to the property where the project was to be built before Compass’s deed of
trust was filed.12 An admission against interest in an abandoned pleading may be
used in evidence. Long v. Knox, 291 S.W.2d 292, 294 (Tex. 1956); Loy v. Harter,
12
The argument on this issue in Trimcos’s appellant’s brief cites to a different
pleading than the one cited in its summary-judgment response. Trimcos is limited
to the arguments raised in its response in the trial court. See Lee v. Braeburn Valley
W. Civic Ass’n, 786 S.W.2d 262, 263 (Tex. 1990); City of Houston v. Clear Creek
Basin Auth., 589 S.W.2d 671, 675 (Tex. 1979).
22
128 S.W.3d 397, 407 (Tex. App.—Texarkana 2004, pet. denied). Compass’s first
amended counterclaim states: “Based on statements by Trimcos before and after the
filing of this lawsuit, Trimcos breached the terms of the [s]econd [a]ffidavit by
beginning construction or delivering materials to the [project property] prior to the
date the [d]eed of [t]rust was filed.” Read in context, this is not a statement against
Compass’s interest. It is not an unconditional statement that Trimcos actually began
construction or delivered materials to the property where the project was to be built.
It is conditioned on representations made by Trimcos that, if proven, it would have
satisfied one of the elements necessary to hold Trimcos liable for breach of contract
and fraud against Compass because they contradict representations made by Trimcos
in the first and second affidavits. See, e.g., Zorrilla v. Aypco Constr. II, LLC, 469
S.W.3d 143, 153 (Tex. 2015) (reciting elements of fraud claim); B & W Supply, Inc.
v. Beckman, 305 S.W.3d 10, 16 (Tex. App.—Houston [1st Dist.] 2009, pet. denied)
(reciting elements of breach-of-contract claim). Because the cited portion of
Compass’s first amended counterclaim is not an admission against interest, it does
not create a fact issue as to whether the time of inception of Trimcos’s mechanic’s
lien predates Compass’s deed of trust.
Based on the foregoing, we conclude that Trimcos failed to raise a fact issue
that it commenced the construction of improvements or delivered materials to the
project property before Compass filed its deed of trust. See TEX. PROP. CODE ANN.
23
§ 53.124(a). And, because Trimcos failed to raise a fact issue as to whether its
mechanic’s lien had priority over Compass’s deed of trust, there is no fact issue as
to whether Compass was unjustly enriched. Unjust enrichment is the foundation of
Trimcos’s money-had-and-received and constructive-trust claims. See Ferrara, 555
S.W.3d at 244; Pickelner, 229 S.W.3d at 527; Nivens, 245 S.W.3d at 474 n.2;
Swinehart, 48 S.W.3d at 878. As a result, we hold that the trial court did not err in
granting Compass summary judgment on Trimcos’s money-had-and-received and
constructive-trust claims.
We overrule Trimcos’s first and second issues.
Matter-of-Law Summary Judgment
In its third issue, Trimcos argues that the trial court erred in granting Compass
summary judgment on Trimcos’s claims for breach of contract and attorney’s fees
because Compass’s summary-judgment motion relied in part on its assertion that
Trimcos failed to satisfy the conditions precedent to recovery under paragraph 7 of
the contractor’s agreement.
Paragraph 7 of the contractor’s agreement provided that Compass would not
pay the “final advance, including all retainage,” until it received evidence “that no
mechanic’s or materialmen’s liens or other encumbrances ha[d] been filed and
remain[ed] in effect against the [project] [p]roperty” as well as “final lien releases
or waivers” by Trimcos and others with any lien or claim on the project property.
24
Compass’s summary-judgment evidence established that Trimcos and one of its
subcontractors had filed a mechanic’s lien on the project property and had not
provided releases or waivers of those liens. Trimcos asserts that if Compass is
correct about the priority of its deed of trust, the mechanic’s liens have been
extinguished. But that assertion does not satisfy the contractor’s agreement, which
requires, before payment of the final advance, Compass must receive “evidence that
no mechanic’s . . . liens or other encumbrances . . . remain in effect” as well as “final
lien releases or waivers” by Trimcos and others “who otherwise might be entitled to
claim any type or kind of lien against the [project] [p]roperty.”
Compass’s summary-judgment motion further asserted that in seeking
payment of certain costs and expenses not specified in the budget approved by
Compass, paragraph 7 of the contractor’s agreement only required Compass to pay
“for costs and expenses” approved by Compass. And Compass provided evidence
showing that the additional expenses for which Trimcos sought repayment had not
been approved for payment by Compass, either in the budget or in a change order.
Trimcos complains that its failure to “obtain pre-approval on items not included in
the . . . contract should not result in forfeiture of amounts that were agreed upon.”
But Trimcos did not identify any “amounts that were agreed upon” in its
summary-judgment response. And although Trimcos cites general propositions of
law in its appellant’s brief, it provides no analysis of the cited authorities or
25
explanation of how they are relevant to the specific conditions precedent challenged
in Compass’s summary-judgment motion. See TEX. R. APP. P. 38.1(i); Bolling v.
Farmers Branch Indep. Sch. Dist., 315 S.W.3d 893, 896 (Tex. App.—Dallas 2010,
no pet.) (noting “references to sweeping statements of general law are rarely
appropriate” and briefing is inadequate if it does not provide existing legal authority
that can be applied to facts of case).
Texas Rule of Appellate Procedure 38.1(i) requires that an appellant’s brief
“contain a clear and concise argument for the contentions made, with appropriate
citations to authorities and to the record.” See TEX. R. APP. P. 38.1(i). A failure to
provide substantive analysis of an issue or cite appropriate authority waives a
complaint on appeal. Marin Real Estate Partners, L.P. v. Vogt, 373 S.W.3d 57, 75
(Tex. App.—San Antonio 2011, no pet.); Huey v. Huey, 200 S.W.3d 851, 854 (Tex.
App.—Dallas 2006, no pet.); Cervantes-Peterson v. Tex. Dep’t of Family &
Protective Servs., 221 S.W.3d 244, 255 (Tex. App.—Houston [1st Dist.] 2006, no
pet.); see also In re Estate of Taylor, 305 S.W.3d 829, 836 (Tex. App.—Texarkana
2010, no pet.) (failure to cite legal authority or to provide substantive analysis of
issue presented results in waiver of complaint on appeal). To the extent that Trimcos
attempts to raise additional arguments to support its complaint that the trial court
erred in granting Compass summary judgment on Trimcos’s breach-of-contract and
26
attorney’s-fees claims, we hold that those arguments are waived due to inadequate
briefing.
Based on the foregoing, we conclude that the undisputed evidence establishes
as a matter of law that the conditions precedent found in paragraph 7 of the
contractor’s agreement and addressed in Compass’s summary-judgment motion
were not satisfied, and that, as a result, Compass was not required to make the
payments demanded by Trimcos.13 Thus, we hold that the trial court did not err in
granting Compass summary judgment on Trimcos’s breach-of-contract and
attorney’s-fees claim.
We overrule Trimcos’s third issue.
Conclusion
We affirm the judgment of the trial court.
Julie Countiss
Justice
Panel consists of Justices Goodman, Landau, and Countiss.
13
Because we affirm Compass’s summary judgment on this ground, we need not
consider whether Trimcos has standing under the contractor’s agreement. See TEX.
R. APP. P. 47.1.
27