Robert E. Thomas Trust, V. Johns Real Estate Corp

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

THOMAS CENTER OWNERS
ASSOCIATION,                          DIVISION ONE

                   Respondent,        No. 81987-9-I

              v.                      PUBLISHED OPINION

THE ROBERT E. THOMAS TRUST and
MICHAEL HYTOPOULOS, Trustee,

                   Appellant.

HADLEY IMPROVEMENTS OWNER
LLC,

           Intervenor Plaintiff,

              v.

THE JOHN’S REAL ESTATE
CORPORATION, a Washington
corporation,

                   Respondent,

THE ROBERT E. THOMAS TRUST and
MICHAEL HYTOPOULOS, Trustee,
THOMAS CENTER OWNERS
ASSOCIATION, a Washington nonprofit
corporation, ESTATES OF ROBERT L.
POLLOCK, and THOMAS A.
WOLTHAUSEN, Personal
Representative,

             Intervenor Defendants.
No. 81987-9-I/2


 ESTATES OF ROBERT L. POLLOCK,
 and THOMAS A. WOLTHAUSEN,
 Personal Representative,

                  Third Party Plaintiff,

                     v.

 HADLEY LAND OWNER, LLC, a
 Delaware limited liability company,
 WHIRLPOOL CORPORATION, a
 Delaware corporation, SYHADLEY LLC,
 a Delaware limited liability company,
 and KEELER 2013, LLC, a Washington
 limited liability company,

                   Third Party Defendants.

 WHIRLPOOL CORPORATION, a
 Delaware corporation,

                  Fourth Party Plaintiff,

                     v.

 BORG WARNER MORSE TECH LLC,

                  Fourth Party Defendant.

       DWYER, J. — The Robert E. Thomas Trust (the Trust) appeals from the

judgment entered in an action initiated by the Thomas Center Owners

Association (the Association) pursuant to the Model Toxics Control Act (MTCA).1

The Trust contends that the trial court erred by concluding that an indemnity

clause contained within a 99-year ground lease did not cover liability arising

under MTCA. Additionally, the Trust asserts that the trial court erred by (1)

concluding that the Association qualified for the third party exemption to liability




       1   Former chapter 70.105D RCW, recodified as chapter 70A.305 RCW.


                                             2
No. 81987-9-I/3


under MTCA, (2) awarding the Association remedial action costs that were

proved through documentary evidence submitted after the trial court entered an

order regarding each party’s equitable share of liability, (3) denying the Trust’s

request that John’s Real Estate Corporation (John’s Real Estate) pay its

equitable share of liability for certain remedial action costs that were incurred by

the Trust, and (4) not awarding attorney fees and costs to the Trust and against

John’s Real Estate pursuant to MTCA.2

        We hold that the trial court erred by concluding that the indemnity clause

did not cover MTCA liability. Accordingly, we vacate both the trial court’s

allocation of each party’s equitable share of MTCA liability and the trial court’s

award of remedial action costs and attorney fees and costs to the Association.

On remand, the trial court must determine whether and how the parties’ equitable

shares of liability are impacted by the obligations of the Association and John’s

Real Estate pursuant to the indemnity clause.

        We further hold that the trial court erred by denying the Trust’s request

that John’s Real Estate be ordered to pay its equitable share of certain remedial

action costs that were incurred by the Trust. Because the Trust is entitled to an

award of remedial action costs, the Trust, on remand, is also entitled to an award

of reasonable attorney fees and costs to be assessed against John’s Real Estate

under MTCA.

        Giving perhaps some solace to the trial court, we affirm its ruling that the


         2 The Trust also contends that the trial court abused its discretion in calculating each

party’s equitable share of liability under MTCA and entering an unreasonable award of attorney
fees and costs to the Association. Because of the manner in which we resolve the issues herein,
we need not address these other issues raised by the Trust on appeal.


                                                3
No. 81987-9-I/4


Association qualified for the third party exemption to liability under MTCA. We

also affirm the trial court’s order authorizing the parties to prove the amount of

remedial action costs that each party claimed to be entitled to through

documentary evidence after the trial court entered its order on liability.

                                          I

       In the 1950s, Robert Thomas acquired the property on Mercer Island that

is the subject of this dispute (the Thomas Property). In 1961, Thomas

constructed two commercial buildings on the property and, that same year,

leased a commercial unit in one of those buildings to Robert and Inez Pollock.

From 1961 to 1974, the Pollocks operated a dry cleaning business on the

property. The Pollocks subsequently transferred operation of the dry cleaning

business to the Kerk Company, which operated the business until sometime

between 1976 and 1978.

       In 1963, Thomas entered into a ground lease with Charles and Vincenta

Sparling and George and Jean Donnally. The ground lease provided that “[t]he

term of this lease shall be ninety-nine (99) years, commencing on the 1st day of

September, 1963.” The ground lease also contained the following indemnity

clause:

              (8) Indemnity: The Lessees shall keep the premises and all
       the appurtenances thereto and improvements thereon including the
       sidewalks, and street area surrounding the same in a safe and
       secure condition and free from all obstructions and clean and
       sanitary to the satisfaction of the officials of any governmental
       agency and the Lessees will save and hold the Lessor harmless
       from any and all damages, costs, fees and expenses or suits by
       public officials or private parties on account of any defective
       conditions of said premises, sidewalks and street areas or on
       account of any business, use or occupation of the said premises or



                                          4
No. 81987-9-I/5


       any part thereof. However, the obligations of the Lessees under
       this paragraph shall not inure to the benefit of any one other than
       the Lessor and his successors in title and in no way shall create a
       duty upon the part of the Lessees as to strangers which the
       Lessees would not have in absence of this paragraph.

       From August 1963 through July 1975, Thomas was the landlord under the

ground lease. In 1976, Thomas died and the Robert E. Thomas Trust was

created by his will. Through Thomas’s will, the fee title interest in the property

and the landlord interest in the ground lease was transferred to the Trust.

       In July 1975, the Sparlings and Donnallys assigned their tenant interest in

the ground lease to John’s Real Estate. John’s Real Estate remained as the

tenant under the ground lease until June 1985.

       In January 1976, John’s Real Estate recorded a declaration of covenants,

conditions, restrictions, and reservations to create a commercial condominium

complex, the Thomas Center Condominiums. The recording of this declaration

also created the Thomas Center Owners Association. Pursuant to the

declaration, John’s Real Estate reserved control over the common areas of the

buildings located on the property for six months. In July 1976, the Association

assumed the authority to manage the common areas of these buildings.

       John’s Real Estate reserved assigning its interest in the ground lease to

the Association so that it could construct a third building on the property. In June

1985, John’s Real Estate assigned its interest in the ground lease to the

Association.

       In January 2014, the owner of a neighboring property (the Hadley

Property) notified the Trust that the Thomas Property was contaminated with




                                          5
No. 81987-9-I/6


Tetrachloroethylene (PCE) and that the contamination was spreading to the

Hadley Property. In April 2014, the Trust received a letter from the Department

of Ecology in which the Department notified the Trust that the Thomas Property

was added to a list of known or suspected contaminated properties.

        The Trust subsequently hired Pacific Groundwater Group (PGG) to

investigate the potential contamination of the Thomas Property. PGG issued a

report confirming that the Thomas Property was contaminated with PCE and that

its likely release occurred from the dry cleaning business.3

        In the meantime, the Association hired a commercial real estate expert,

Gus Levin, to investigate potential contamination on the Thomas Property. In

April 2014, Levin informed the Association that the Thomas property was

potentially contaminated with a hazardous substance. All parties believe that the

contamination on the Thomas Property was caused by the dry cleaning business,

which operated from 1961 until sometime between 1976 and 1978.

        In January 2015, the Association sued the Trust, seeking, in part, a

declaratory judgment that it had no liability related to the contamination on the

Thomas Property under MTCA. In June 2015, both the Association and the Trust

filed motions for summary judgment. In the Trust’s motion, the Trust sought

summary judgment determinations that the Association was a potentially liable

person under MTCA and that the ground lease’s indemnity clause required the

Association to indemnify the Trust for liability arising under MTCA. In the




        3 An invoice from PGG that was admitted into evidence at trial indicates that the Trust
incurred approximately $100,000 in costs for the investigation conducted by PGG.


                                                6
No. 81987-9-I/7


Association’s motion, the Association sought a summary judgment determination

that it was not a potentially liable person under MTCA.

        The trial court granted the Trust’s motion in part and denied the

Association’s motion. The trial court granted the Trust’s motion insofar as it

sought a determination that the Association was a potentially liable person under

MTCA. However, the trial court denied the Trust’s motion with respect to the

indemnity clause, reasoning that the “issue of the intent and expectations of the

parties . . . precludes a determination that, as a matter of law, [the indemnity

clause] would apply in the present context.”

        The Trust subsequently moved to join John’s Real Estate as a third party

defendant. The trial court granted the motion.4 On November 12, 2019, the case

proceeded to a bench trial.

        Following the trial proceeding on liability, the trial court entered findings of

fact and conclusions of law. The trial court found that the indemnity clause “was

not intended to and did not contemplate indemnification for subsurface

environmental conditions.” Finding of Fact 56. Additionally, the trial court

concluded that the Association was not liable under MTCA because it qualified

for the third party exemption to liability under former RCW 70.105D.040 (2013),



        4  In September 2015, Hadley Improvements Owner LLC intervened in the action by
stipulation. Hadley filed a complaint seeking recovery under MTCA from the Association, the
Trust, John’s Real Estate, and the estates of Robert and Inez Pollock. The Association, the
Trust, John’s Real Estate, and the Pollock estates entered into a joint defense agreement and
retained Environmental Partners, Inc. (EPI) to investigate both the contamination at the Thomas
Property and claims that were raised by Hadley. EPI estimated that the cost of remediating the
Thomas Property could range between $2 million and $4 million. The parties ultimately entered
into a settlement agreement with Hadley and the Pollock estates. Accordingly, only the
Association, the Trust, and John’s Real Estate litigated at trial.



                                               7
No. 81987-9-I/8


recodified as RCW 70A.305.040. In addition, the trial court determined that,

under MTCA, the Trust’s equitable share of liability amounted to 85.35 percent

and John’s Real Estate’s equitable share of liability amounted to 14.65 percent.

Finally, the trial court’s findings of fact and conclusions of law provided that “[t]he

parties are awarded their statutory fees and costs based on the foregoing

allocation, and are directed to submit the same to this court within 14 days of this

Order.”

       Subsequently, the Association submitted a motion, attached with a

declaration and exhibits, in which it sought an award of remedial action costs and

attorney fees and costs. The Trust and John’s Real Estate filed responses to the

Association’s request. On March 20, 2020, the trial court entered an order

denying the Association’s motion without prejudice, requesting that the

Association file a renewed motion clarifying the costs and fees to which it

believed it was entitled.

       The Association then submitted a renewed motion for remedial action

costs and attorney fees and costs. Attached to this renewed motion was a

declaration and various exhibits. The Trust and John’s Real Estate again filed

responses. On August 19, 2020, the trial court entered findings of fact and

conclusions of law wherein the court awarded remedial action costs and attorney

fees and costs to the Association. On October 16, 2020, the trial court entered

judgment.

       The Trust appeals.




                                           8
No. 81987-9-I/9


                                          II

       The Trust first contends that the trial court erred by finding that the

Association was not required to indemnify the Trust for liability arising under

MTCA. Because the language in the indemnity clause unambiguously covered

liability arising under MTCA, we agree.

                                          A

       “Indemnity agreements are subject to the fundamental rules of contract

interpretation.” Newport Yacht Basin Ass’n of Condo. Owners v. Supreme Nw.,

Inc., 168 Wn. App. 86, 100, 285 P.3d 70 (2012). “The interpretation of a contract

can be a mixed question of law and fact.” Rekhter v. Dep’t of Soc. & Health

Servs., 180 Wn.2d 102, 134, 323 P.3d 1036 (2014) (plurality opinion). “But

where the contract presents no ambiguity and no extrinsic evidence is required to

make sense of the contract terms, contract interpretation is a question of law.”

Rekhter, 180 Wn.2d at 134 (plurality opinion).

       “A court’s purpose in interpreting a written contract is to ascertain the

parties’ intent.” Spectrum Glass Co. v. Pub. Util. Dist. No. 1 of Snohomish

County, 129 Wn. App. 303, 310, 119 P.3d 854 (2005). “Washington follows the

objective manifestation theory of contract interpretation, under which courts

attempt to ascertain the intent of the parties ‘by focusing on the objective

manifestations of the agreement, rather than on the unexpressed subjective

intent of the parties.’” Hulbert v. Port of Everett, 159 Wn. App. 389, 399, 245

P.3d 779 (2011) (quoting Hearst Commc’ns, Inc. v. Seattle Times Co., 154

Wn.2d 493, 503, 115 P.3d 262 (2005)). “Courts ‘impute an intention




                                          9
No. 81987-9-I/10


corresponding to the reasonable meaning of the words used,’ and words are

given their ordinary, usual, and popular meaning unless the agreement as a

whole clearly demonstrates otherwise.” Hulbert, 159 Wn. App. at 399 (quoting

Hearst, 154 Wn.2d at 503).

       “Under the context rule, extrinsic evidence relating to the context in which

a contract is made may be examined to determine the meaning of specific words

and terms.” Hulbert, 159 Wn. App. at 399-400. Notably, however, “surrounding

circumstances and other extrinsic evidence are to be used ‘to determine the

meaning of specific words and terms used’ and not to ‘show an intention

independent of the instrument’ or to ‘vary, contradict or modify the written word.’”

Hearst, 154 Wn.2d at 503 (italicization omitted) (quoting Hollis v. Garwall, Inc.,

137 Wn.2d 683, 695-96, 974 P.2d 836 (1999)).

                                         B

       The ground lease contains two provisions of particular significance to our

inquiry. First, the indemnity clause within the ground lease states:

              (8) Indemnity: The Lessees shall keep the premises and all
       the appurtenances thereto and improvements thereon including the
       sidewalks, and street area surrounding the same in a safe and
       secure condition and free from all obstructions and clean and
       sanitary to the satisfaction of the officials of any governmental
       agency and the Lessees will save and hold the Lessor harmless
       from any and all damages, costs, fees and expenses or suits by
       public officials or private parties on account of any defective
       conditions of said premises, sidewalks and street areas or on
       account of any business, use or occupation of the said premises or
       any part thereof. However, the obligations of the Lessees under
       this paragraph shall not inure to the benefit of any one other than
       the Lessor and his successors in title and in no way shall create a
       duty upon the part of the Lessees as to strangers which the
       Lessees would not have in absence of this paragraph.




                                         10
No. 81987-9-I/11


(Emphasis added.)

       Second, the ground lease specifies that “[t]he term of this lease shall be

ninety-nine (99) years, commencing on the 1st day of September, 1963.”

       The trial court found that, read in its entirety, the indemnity clause was not

intended to cover liability arising from subsurface environmental contamination:

       The language of paragraph 8 of the Ground Lease primarily
       references indemnification for general tort liability and non-
       compliance with governmental regulations related to sanitation or
       hazardous conditions that could lead to tort liability. Considering
       the entirety of Paragraph 8, as written, the Court finds that the
       indemnity language contained therein was not intended to and did
       not contemplate indemnification for subsurface environmental
       conditions.

Finding of Fact 56.

       Furthermore, the trial court relied on an expert witness’s testimony to find

that “it was neither routine nor customary for a purchaser or ground lessee to

undertake any investigation into possible subsurface environmental

contamination” in 1963, when the ground lease was executed. Finding of Fact

53.

       The trial court erred. Because the language of the document is clear, no

testimony speculating on its meaning was authorized. Moreover, all necessary

context is provided by the contract term setting forth the length of the lease.

       The trial court incorrectly determined that the language used in the

indemnity clause was not intended to cover liability arising from subsurface

contamination. To the contrary, the indemnity clause explicitly provided that “the

Lessees will save and hold the Lessor harmless from any and all damages,

costs, fees and expenses or suits.” (Emphasis added.) It is well established that



                                         11
No. 81987-9-I/12


“the phrase ‘any and all claims’ is to be given its ordinary meaning and includes

all types of claims.” Newport Yacht Basin, 168 Wn. App. at 101 (quoting

MacLean Townhomes, LLC v. Am. 1st Roofing & Builders, Inc., 133 Wn. App.

828, 831, 138 P.3d 155 (2006)); see also Jacob’s Meadow Owners Ass’n v.

Plateau 44 II, LLC, 139 Wn. App. 743, 769-70, 162 P.3d 1153 (2007) (holding

that the phrase “any and all claims” in an indemnity clause referenced all claims

and was not limited to tort-based claims).

       For instance, in MacLean Townhomes, an indemnity clause provided:

       SUBCONTRACTOR shall defend, indemnify, and hold
       CONTRACTOR harmless from any and all claims, demands, losses
       and liabilities to or by third parties arising from, resulting from, or
       connected with, services performed or to be performed under this
       Subcontract . . . to the fullest extent permitted by law and subject to
       the limitations provided below.

133 Wn. App. at 831 (bold face omitted).

       We therein explained that the paragraphs that followed the portion of the

clause quoted above “contain[ed] various specifications regarding the

subcontractor’s duties, none of which say that the initial characterization ‘any and

all’ [was], in fact, restricted to only tort-based claims.” MacLean Townhomes,

133 Wn. App. at 833.

       The indemnity clause herein stated, in pertinent part, that

       the Lessees will save and hold the Lessor harmless from any and
       all damages, costs, fees and expenses or suits by public officials or
       private parties . . . on account of any business, use or occupation of
       the said premises or any part thereof.

(Emphasis added.)




                                         12
No. 81987-9-I/13


       The portion of the clause that preceded this language described the

lessees’ general duties as lessees; it did not restrict the phrase “any and all

damages, costs, fees and expenses or suits” in any way:

       The Lessees shall keep the premises and all the appurtenances
       thereto and improvements thereon including the sidewalks, and
       street area surrounding the same in a safe and secure condition
       and free from all obstructions and clean and sanitary to the
       satisfaction of the officials of any governmental agency.

       Furthermore, the lease agreement itself specified that “[t]he term of this

lease shall be ninety-nine (99) years.” This language is significant. In the

context of a 99-year lease, the phrase “any and all” encompasses the entire

universe of all causes of action and means of loss, regardless of whether those

causes of action or means of loss were foreseeable or foreseen when the lease

was executed. Indeed, when entering into such an indemnity clause in the

context of a 99-year lease agreement, reasonable parties would foresee that

then-unforeseen or unforeseeable causes of action and means of loss could

arise over the course of a century.

       During oral argument, counsel for the Association asserted that, for the

indemnity clause to cover liability arising under MTCA, the phrase “any and all”

must be followed by the phrase “and that now exist or may in the future come to

exist.”5 But that added language is redundant. The phrase “any and all,” by its

plain terms, encompasses those causes of action and means of loss that now




       5   Wash. Court of Appeals oral argument, Thomas Center Owners Ass’n v. The Robert E.
Thomas Trust, No. 81987-9-I (Sept. 23, 2021), at 20 min., 20 sec. through 21 min., 57 sec. (on
file with court).


                                              13
No. 81987-9-I/14


exist or may in the future come to exist. This is no mystery. In plain English,

“any and all” means any and all.

       The following hypothetical is illustrative of the point we make. Had the

same 99-year lease agreement been entered into in 1864 (99 years before the

lease agreement herein was executed) then various unforeseen causes of action

and means of loss could have arisen on this very property over the next century

that would plainly fall within the scope of the indemnity clause. For example, it is

conceivable that an electrical fire in a building could occur in 1960, leading to the

death of two people: the first of whom dies from the fire inside the building and

the second of whom dies as he attempts to escape the fire and, as he enters his

parked automobile, is killed when flames and heat from the fire cause the car’s

gas tank to explode. Under these circumstances, the survivors of these

decedents could be entitled to file wrongful death actions against the owner of

the property. See RCW 4.20.010.

       However, the hypothetical presents two means of loss that were

unforeseeable when the lease agreement was executed in 1864. First, it was

unforeseeable that a person could die in an electrical fire in a building because

buildings were not equipped with electricity in 1864. Second, it was

unforeseeable that a person could die as a result of an automobile exploding in

1864 because neither automobiles nor internal combustion engines then existed.

Moreover, even the particular cause of action alleged was unforeseeable




                                         14
No. 81987-9-I/15


because, in 1864, there was no cause of action for wrongful death.6

        Extraordinarily, however, the position advanced herein by the Association

and John’s Real Estate would necessarily lead to the conclusion that the 1864

indemnity clause would not cover the losses arising from these two deaths

because neither the means of loss (electrical fires and automobile explosions)

nor the cause of action (wrongful death) were foreseeable at the time of the Civil

War. This is a ridiculous conclusion. After all, it is undeniable that, when the

original parties executed the lease agreement herein in 1963, they were sentient

beings who would reasonably have been aware that the world would evolve over

the course of the next century, as it had over the course of the prior century.

        Furthermore, by 1963, Washington courts had long recognized that parties

could be held liable in tort for losses arising from what may today be classified as

environmental contamination. See, e.g., Cunningham v. Town of Tieton, 60

Wn.2d 434, 435, 438-39, 374 P.2d 375 (1962) (affirming a judgment wherein a

town was held liable for “an unconstitutional damaging by nuisance” because it

deposited sewage into a lagoon that contaminated private water wells located

underneath the lagoon); Lennon v. City of Seattle, 69 Wash. 447, 453, 125 P.

770 (1912) (affirming a judgment wherein a city was found negligent for a

sewage leak that caused damage to private property); Hayes v. City of

Vancouver, 61 Wash. 536, 539, 112 P. 498 (1911) (stating that cities may be




        6The cause of action for wrongful death first arose in the Washington territory in 1875.
LAWS OF 1875, § 4. Later, in 1909, the Washington state legislature enacted a statute that
provided a cause of action for wrongful death. LAWS OF 1909, ch. 129, § 1.


                                                15
No. 81987-9-I/16


held liable for trespass when sewage from a public utility system floods the

premises of private property).7

        It is of no consequence that the particular cause of action—here, the

cause of action arising under MTCA—was unforeseen when the lease

agreement was entered into. The indemnity clause, by its plain terms, covered

such liability and losses arising therefrom.

                                                  C

        Nevertheless, the Association and John’s Real Estate contend that the

indemnity clause was required to explicitly state that it applied to environmental

contamination for it to cover liability arising under MTCA. In support of this

argument, they cite to Hulbert, 159 Wn. App. 389, and Car Wash Enterprises,

Inc. v. Kampanos, 74 Wn. App. 537, 874 P.2d (1994). Neither authority supports

their argument.

        Notwithstanding assertions to the contrary, Hulbert does not require that

an indemnity clause explicitly mention liability arising under MTCA for a party to

be required to indemnify another for losses arising from such liability. In that

case, a purchase and sale agreement provided that the sellers “agreed to

indemnify the [purchaser] against liability involving hazardous substances for

three years after the date of sale.” Hulbert, 159 Wn. App. at 395. Fifteen years

after the agreement was executed, the purchaser was required to perform



         7 Thus it is clear that, in 1963, had sewage leaked from the dry cleaning business to

surrounding properties, tort liability would exist on the basis of trespass, nuisance, or negligence.
Thus, when the lease was entered into, it was indeed foreseeable that environmental
contamination could give rise to actionable losses. While such foreseeability is not necessary for
parties to enter into a contract of this type, even on this basis the trial court’s ruling comes up
short.


                                                 16
No. 81987-9-I/17


remedial investigation and cleanup work on the property. Hulbert, 159 Wn. App.

at 396. The sellers were subsequently “notified that they were potentially liable

for costs incurred in the investigation and remediation of the land under the

MTCA.” Hulbert, 159 Wn. App. at 396.

       We held that the indemnity clause therein did not contain any language

indicating that the purchaser agreed to release the sellers from environmental

liability arising after the three-year indemnity period expired. Hulbert, 159 Wn.

App. at 396. Therefore, “the Agreement did not preclude a statutory MTCA

contribution action after the three years expired.” Hulbert, 159 Wn. App. at 400.

       The indemnity clause in Hulbert is significantly distinguishable from the

indemnity clause herein. Indeed, unlike the indemnity clause in Hulbert, the

indemnity clause at issue herein provided that the lessees will indemnify the

lessor for “any and all damages, costs, fees and expenses or suits by public

officials or private parties . . . on account of any business, use or occupation of

the said premises or any part thereof.” (Emphasis added.) As already explained,

such language unambiguously covers losses arising under MTCA. Moreover,

this indemnity clause was contained within a lease agreement, which, by its own

wording, had a term of “ninety-nine (99) years.” The 99-year term of one contract

starkly contrasts with the 3-year term of the other.

       The sellers in Hulbert also argued that an “as is” clause demonstrated that

the parties intended that the sellers would not be held liable for hazardous

substances on the property after the three-year indemnity period expired. 159

Wn. App. at 400-01. The “as is” clause stated that the purchaser




                                         17
No. 81987-9-I/18


       “inspected the physical condition of the Property and accepts such
       condition subject to the terms and conditions of the Agreement and
       the Certificate and Indemnity attached hereto . . . relating to
       hazardous materials investigation and cleanup, if required.”

Hulbert, 159 Wn. App. at 401.

       We noted that “conspicuously absent from the Agreement and the

Certificate is an explicit expression of an intent to allocate MTCA liability.”

Hulbert, 159 Wn. App. at 401. However, we did not hold that, in order to allocate

liability arising under MTCA, an indemnity clause must explicitly mention MTCA.

Rather, we explained that, “where the evidence does not demonstrate that the

parties so intended, an ‘as is’ clause does not contractually allocate MTCA

liability.” Hulbert, 159 Wn. App. at 401.

       Because the language of the indemnity clause herein unambiguously

covered unforeseen liability, Hulbert is inapplicable and the trial court was not

authorized to examine extrinsic evidence in order to vary, contradict, or modify

the lease’s written words. See Hearst, 154 Wn.2d at 503.

       The Car Wash Enterprises decision is also of no aid to the Association

and John’s Real Estate. In that case, a seller sold property on which a service

station had once operated. Car Wash Enters., 74 Wn. App. at 539. The

purchase agreement contained an “as is” clause:

       “5. CONDITION OF PROPERTY. Purchaser has examined the
       Property and all improvements thereon, and accept [sic] the same
       as is and in present condition.”

Car Wash Enters., 74 Wn. App. at 539. In a later MTCA contribution action

brought by the buyer, the seller argued that the “as is” clause allocated the risk of

MTCA liability to the purchaser. Car Wash Enters., 74 Wn. App. at 543.



                                            18
No. 81987-9-I/19


        We began by noting that private agreements that allocate the risk of

liability between themselves are not prohibited under MTCA. Car Wash Enters.,

74 Wn. App. at 544. Based on the facts of that case, however, we held that “the

trial court did not err in failing to conclude that [the] parties intended the ‘as is’

clause to allocate MTCA liability to [the purchaser].” Car Wash Enters., 74 Wn.

App. at 547. Our holding was based on the trial court’s factual findings:

        The trial court . . . entered no specific finding that the parties did
        intend the “as is” clause to transfer MTCA liability to [the
        purchaser]. The absence of a finding of fact in favor of the party
        with the burden of proof about a disputed issue is the equivalent of
        a finding against that party on that issue. In re Marriage of
        Olivares, 69 Wn. App. 324, 334, 848 P.2d 1281, review denied, 122
        Wn.2d 1009, 863 P.2d 72 (1993).

Car Wash Enters., 74 Wn. App. at 546.

        We did not hold that, in order to allocate liability arising under MTCA, an

indemnity clause must explicitly mention MTCA. Instead, the Car Wash decision

is best read as simply recognizing that “accepting” a property after inspections

“as is” in a real estate sale is not the same as “accepting” the seller’s tort liability

arising from the seller’s prior use of that property. Indeed, “as is” clauses in

purchase and sale agreements are common. They routinely convey the property

in its existing condition. They do not routinely convey tort liability arising from

prior use of that property (either real or personal).8

        One final note. The indemnity agreement not only includes “any and all”

claims—it also covers these claims as they arise from “any . . . use” of the



        8 In fact, the premier law dictionary defines “as is” as follows: “In the existing condition
without modification.” BLACK’S LAW DICTIONARY 141 (11th ed. 2019). This definition supports our
analysis.


                                                 19
No. 81987-9-I/20


subject property. As the dry cleaning business obviously amounted to a use of

the property—and any use falls within the scope of the clause—the fact that the

dry cleaner’s use caused pollution and contamination does not exclude it from

the ambit of the agreement.

        The trial court erred by ruling that the indemnity clause did not cover

losses arising under MTCA.

                                                 III

        The Trust next asserts that the trial court erred by concluding that the

Association qualified for the third party exemption to liability provided by former

RCW 70.105D.040(3)(a)(iii). This is so, the Trust avers, because the trial court

found that the Association “caused or contributed” to the release of a hazardous

substance when it determined that the Association did not qualify as an innocent

purchaser. Because the trial court did not find that the Association caused or

contributed to the release of a hazardous substance, we disagree.

        Former RCW 70.105D.040 provides that each owner and operator of a

“facility”9 is generally strictly liable, jointly and severally, for all remedial action

costs and for all natural resource damages resulting from the release of

hazardous substances. However, certain categories of persons are exempted

from liability. One such exemption provides:

                 (3) The following persons are not liable under this section:

        9  “‘Facility’ means (a) any building, structure, installation, equipment, pipe or pipeline
(including any pipe into a sewer or publicly owned treatment works), well, pit, pond, lagoon,
impoundment, ditch, landfill, storage container, motor vehicle, rolling stock, vessel, or aircraft, or
(b) any site or area where a hazardous substance, other than a consumer product in a consumer
use, has been deposited, stored, disposed of, or placed, or otherwise come to be located.”
Former RCW 70A.105D.020(8) (2013). Here, the trial court concluded that the “facility” was the
building “from which the parties agree that the release at issue was occurring during the operation
of the [dry cleaning business].” Conclusion of Law 12.


                                                 20
No. 81987-9-I/21

                (a) Any person who can establish that the release or
        threatened release of a hazardous substance for which the person
        would be otherwise responsible was caused solely by:
                ...
                (iii) An act or omission of a third party (including but not
        limited to a trespasser) other than (A) an employee or agent of the
        person asserting the defense, or (B) any person whose act or
        omission occurs in connection with a contractual relationship
        existing, directly or indirectly, with the person asserting this defense
        to liability. This defense only applies where the person asserting
        the defense has exercised the utmost care with respect to the
        hazardous substance, the foreseeable acts or omissions of the third
        party, and the foreseeable consequences of those acts or
        omissions.

Former RCW 70.105D.040 (emphasis added).

        The trial court concluded that the Association qualified for the third party

liability exemption. The Trust assigns error to this ruling because, according to

the Trust, the trial court inconsistently determined that the Association “caused or

contributed” to the release of a hazardous substance by concluding that the

Association did not qualify as an innocent purchaser under former RCW

70.105D.040(3)(b)(iii).10 As such, the Trust claims, the trial court erred by

concluding that the Association qualified for the third party exemption, which

requires that the “release or threatened release of a hazardous substance for

which the person would be otherwise responsible was caused solely by . . . [a]n

act or omission of a third party.” Former RCW 70.105D.040(3)(a)(iii).

        However, in fact, the trial court did not find that the Association caused or

contributed to the release of a hazardous substance. To the contrary, the trial

court found that “[t]he Association had no fault related to the contamination as it



        10
         The Trust does not contend that the Association failed to establish the other statutory
requirements of the third party liability exemption.


                                               21
No. 81987-9-I/22


did not cause or contribute to the cause thereof.” Finding of Fact 59(iii).

Moreover, the trial court found that “[i]t is undisputed that the contamination on

the Thomas Property was caused by the dry-cleaning operations.” Finding of

Fact 27.

       In determining that the Association did not qualify as an innocent

purchaser, the trial court concluded that “under Grey v. Leach, 158 Wn. App.

837, 847, 244 P.3d 970, 974 (2010)[,] a party cannot be an innocent purchaser, if

the contamination occurred while they owned or operated the facility, even if they

did not know contamination of the land was occurring.” Conclusion of Law 11.

According to the trial court,

       the Association assumed from [John’s Real Estate] on July 22,
       1976, power and authority to manage the Common Areas, which
       included responsibility for maintaining Building A, the facility from
       which the parties agree that the release at issue was occurring
       during the operation of the [dry cleaning business]. Accordingly,
       the Court concludes that the Association’s control of the “facility” for
       the short period between July 22, 1976 and January 1, 1978, when
       [the] contamination was still occurring under Kerk Company
       operation precludes the Association from being found “not liable” as
       an innocent purchaser under RCW 70.105D.040(3)(b).

Conclusion of Law 12.

       Notably, the trial court found that “[n]o evidence was presented that the

contamination on the Thomas Property was caused or permitted due to a failure

on the part of any party to maintain the Common Areas.” Finding of Fact 62.

       Therefore, the trial court did not conclude that the Association failed to

qualify as an innocent purchaser because it “caused or contributed” to the

release of a hazardous substance. Rather, the trial court concluded that the

Association did not qualify as an innocent purchaser because it exercised control



                                         22
No. 81987-9-I/23


over the common areas of the facility when the release of a hazardous substance

occurred.11

        Accordingly, the Trust’s assignment of error fails.

                                                IV

        The Trust also contends that the trial court erred by awarding remedial

action costs that were proved through documentary evidence submitted after the



        11   This ruling was correct. To qualify as an innocent purchaser, an owner of a facility
must have acquired the facility after the hazardous substance had already been released or
disposed of at the facility. Indeed, federal appellate courts have interpreted the analogous
“innocent landowner” defense under the Comprehensive Environmental Response,
Compensation, and Liability Act of 1980, (CERCLA), 42 U.S.C. ch. 103, to require a property
owner to prove that the “disposal” of the hazardous substance at issue both occurred before the
owner acquired the property and did not continue to occur thereafter. See, e.g., Carson Harbor
Vill., Ltd. v. Unocal Corp., 270 F.3d 863, 882-83 (9th Cir. 2001); ABB Indus. Sys., Inc. v. Prime
Tech., Inc., 120 F.3d 351, 358 (2d Cir. 1997); accord 4 W ILLIAM H. RODGERS, JR., ENVIRONMENTAL
LAW, HAZARDOUS W ASTES & SUBSTANCES § 8.13, at 698 (1992) (stating that, with regard to the
innocent landowner defense under CERCLA, “[t]he requirement that the property be acquired
after the polluting event . . . has defeated a number of owners seeking refuge as innocents”). In
fact, the innocent landowner defense under CERCLA requires a defendant to establish, in part,
that “the real property on which the facility concerned is located was acquired by the defendant
after the disposal or placement of the hazardous substance on, in, or at the facility.” 42 U.S.C. §
9601(35)(A) (emphasis added).
          Although MTCA does not contain this precise statutory language, it does state that, to
qualify as an innocent purchaser, “an owner, past owner, or purchaser of a facility” must
establish, in part, that “at the time the facility was acquired by the person, the person had no
knowledge or reason to know that any hazardous substance . . . was released or disposed of on,
in, or at the facility.” Former RCW 70.105D.040(3)(b) (emphasis added). Accordingly, we
interpret the innocent purchaser exclusion under MTCA to require a property owner to establish
that no release or disposal of a hazardous substance took place while the person owned or
operated the facility. See Grey, 158 Wn. App. at 847 (stating that “‘the innocent purchaser
defense applies only where . . . [liability] status results from mere ownership’” (emphasis added)
(alterations in original) (quoting 24 TIMOTHY BUTLER & MATTHEW KING, W ASHINGTON PRACTICE:
ENVIRONMENTAL LAW AND PRACTICE § 15.2, at 93 (2d ed. 2007))).
          The Association managed the common areas of the building when the dry cleaning
business operated. During this time, the Association exercised control over the facility and,
therefore, was an owner under MTCA. See former RCW 70.105D.020(22)(a) (“‘Owner or
operator’ means . . . [a]ny person with any ownership interest in the facility or who exercises any
control over the facility.” (emphasis added)). Additionally, “[n]o evidence was presented as to the
precise dates or years that the PCE was released, although there was no dispute that the PCE
could have only been released during the years that the [dry cleaning business] operated, which
was from 1961 until sometime between 1976 and 1978.” Finding of Fact 27. Because the
Association failed to establish that the release of a hazardous substance did not continue to occur
while it managed the common areas of the facility, the Association failed to meet the
requirements of the innocent purchaser exemption to liability.



                                               23
No. 81987-9-I/24


trial court entered its order regarding each party’s equitable share of liability. We

disagree.

       Under MTCA, “a person may bring a private right of action, including a

claim for contribution or for declaratory relief, against any other person liable

under RCW 70.105D.040 for the recovery of remedial action costs.” Former

RCW 70.105D.080 (1997), recodified as RCW 70A.305.080. In its findings of

fact and conclusion of law regarding the liability of the parties, the trial court

stated: “The parties are awarded their statutory fees and costs based on the

foregoing allocation, and are directed to submit the same to this court within 14

days of this Order.”

       After the trial court denied without prejudice the Association’s initial motion

for fees and costs, the Association submitted a motion, attached with a

declaration and exhibits, in which it requested remedial action costs. The Trust

and John’s Real Estate filed responses to the Association’s requested fees and

costs. Thereafter, the trial court entered an order in which it awarded the

Association remedial action costs.

       We have previously explained that, “if trial is to a jury, the determination of

the amount of damages to which the plaintiff is entitled is within the jury’s

province.” Jacob’s Meadow, 139 Wn. App. at 760-61. As such, in the context of

a jury trial, damages must be determined by the jury at trial, rather than by the

judge after trial, because the jury is the fact-finder. Jacob’s Meadow, 139 Wn.

App. at 758-59.




                                          24
No. 81987-9-I/25


      However, when the judge serves as fact-finder, the trial court has broader

discretion to both bifurcate the trial proceeding and determine the mode by which

evidence is to be submitted by the parties. Indeed, trial courts are authorized to

bifurcate a trial proceeding such that different issues may be adjudicated in

separate proceedings:

      Separate Trials. The court, in furtherance of convenience or to
      avoid prejudice, or when separate trials will be conducive to
      expedition and economy, may order a separate trial of any claim,
      cross claim, counterclaim, or third party claim, or of any separate
      issue or of any number of claims, cross claims, counterclaims, third
      party claims, or issues, always preserving inviolate the right of trial
      by jury.

CR 42(b).

      Under CR 42(b), “[t]he court may order . . . separate trials on its own

motion, and the consent of the parties is not necessary.” 10 DAVID E. BRESKIN,

WASHINGTON PRACTICE: CIVIL PROCEDURE FORMS AND COMMENTARY § 42.1, at 358

(3d ed. 2000).

      Furthermore, under Federal Rule of Civil Procedure 42(b), which is

analogous to CR 42(b), a trial court is authorized

      “‘in furtherance of convenience or to avoid prejudice, or when
      separate trials will be conducive to expedition and economy,’ to
      order a separate trial of any ‘claim, cross-claim, counter claim, or
      third-party claim, or of any separate issue or of any number of . . .
      issues’ as long as the court preserves inviolate the right of trial by
      jury as declared by the Seventh Amendment or as given by a
      statute of the United States.”

State of Ala. v. Blue Bird Body Co., 573 F.2d 309, 318 (5th Cir. 1978) (emphasis

added) (quoting Fed. R. Civ. P. 42(b)).




                                          25
No. 81987-9-I/26


         Therefore, in order for issues to be bifurcated, “the issue to be tried must

be so distinct and separable from the others that a trial of it alone may be had

without injustice.” Blue Bird Body Co., 573 F.2d at 318. “Such a rule is dictated

for the very practical reason that if separate juries are allowed to pass on issues

involving overlapping legal and factual questions the verdicts rendered by each

jury could be inconsistent.” Blue Bird Body Co., 573 F.2d at 318 (emphasis

added); accord Sitton v. State Farm Mut. Auto. Ins. Co., 116 Wn. App. 245, 259,

63 P.3d 198 (2003) (“Bifurcation does not violate the Seventh Amendment unless

the questions sought to be bifurcated are so interwoven that one cannot be

submitted independently of the other without confusion and uncertainty.”).

         Here, the trial court bifurcated the trial proceeding with regard to the

issues of liability and damages owed in the form of remedial action costs. It is

well established that “[o]ne of the common uses of Rule 42 is bifurcation of the

issues of liability and damages for separate trial.” 10 BRESKIN, supra, at 359; see

e.g., State v. Comcast Cable Commc’ns Mgmt., LLC, 16 Wn. App. 2d 664, 678,

482 P.3d 925 (2021); Sitton, 116 Wn. App. at 257. Additionally, because this

case was tried as a bench trial, there was no concern that the trial court’s

determination of remedial action costs in a proceeding following its determination

of each party’s equitable share of liability would violate the Trust’s right to a jury

trial.

         Indeed, our Supreme Court has explained that “[t]he trial court is generally

in the best position to perceive and structure its own proceedings” and, therefore,

it “has broad discretion to make a variety of trial management decisions,




                                           26
No. 81987-9-I/27


[including] ‘the mode and order of . . . presenting evidence.’” State v. Dye, 178

Wn.2d 541, 547, 309 P.3d 1192 (2013) (quoting ER 611(a)). In fact, ER 611(a)

provides that trial courts have discretion over the mode and order of presenting

evidence “so as to . . . make the . . . presentation effective for the ascertainment

of the truth [and] . . . avoid needless consumption of time.” ER 611(a).

        Consistent with the trial court’s broad discretion over the mode and order

of presenting evidence, “an enactment of our first state legislature, now codified

as a foundational provision of Title 2 RCW, provides the trial judge with the

flexibility to authorize the particular procedure that—in the judge’s estimation—

best fits the needs of the case.” Comcast Cable Commc’ns, 16 Wn. App. 2d at

684. This statute provides:

        When jurisdiction is, by the Constitution of this state, or by statute,
        conferred on a court or judicial officer all the means to carry it into
        effect are also given; and in the exercise of the jurisdiction, if the
        course of proceeding is not specifically pointed out by statute, any
        suitable process or mode of proceeding may be adopted which may
        appear most conformable to the spirit of the laws.

RCW 2.28.150 (emphasis added).

        In the context of bench trials, trial courts properly have, depending on the

particular needs of the case, ordered parties to submit proofs of damages after

the trial court entered an order on liability. See, e.g., Wright v. Sheppard, 919

F.2d 665, 667 (11th Cir. 1990);12 Tlacoapa v. Carregal, 386 F. Supp. 2d 362,


        12    In Wright, the trial court, during a bench trial, entered an order regarding liability
wherein it “reserved ruling on compensatory damages and directed counsel to file ‘proofs of past
and anticipated future medical expenses and other damages.’” 919 F.2d at 667. Thereafter, the
plaintiff “filed an affidavit with attachments.” Wright, 919 F.2d at 667. The trial court
subsequently entered an order wherein it awarded the plaintiff compensatory damages based on
the affidavit and attachments that the plaintiff submitted. Wright, 919 F.2d at 667. On appeal, the
order on damages was vacated because the appellate court determined that the plaintiff was
entitled to additional awards of damages based, in part, on information contained within the


                                                27
No. 81987-9-I/28


365-66, 367-68 (S.D.N.Y. 2005).13

        Accordingly, the trial court did not err by authorizing the parties to prove

remedial action costs through the submission of documentary evidence after the

trial court entered its order on liability.

                                                  V

        The Trust next asserts that the trial court erred by not ordering John’s

Real Estate to compensate the Trust for certain remedial action costs that were

incurred by the Trust. In particular, the Trust contends that John’s Real Estate

was required to pay its equitable share of the costs incurred by the Trust for

PGG’s investigation of the contamination. We agree.

        The term “remedial action” is defined as

        any action or expenditure consistent with the purposes of this
        chapter to identify, eliminate, or minimize any threat or potential
        threat posed by hazardous substances to human health or the
        environment including any investigative and monitoring activities
        with respect to any release or threatened release of a hazardous
        substance and any health assessments or health effects studies
        conducted in order to determine the risk or potential risk to human
        health.

Former RCW 70.105D.020(33) (2013), recodified as RCW 70A.305.020(33).




affidavit submitted by the plaintiff and that the trial court’s order did not address. Wright, 919 F.2d
at 669.
          13 In Tlacoapa, the trial court, during a bench trial, “found Defendant liable for unpaid

wages and overtime, in violation of the [Fair Labor Standards Act].” 386 F. Supp. 2d at 365. The
trial court explained that, “[a]t the conclusion of trial, the court ordered the Plaintiff to submit
specific requests for damages . . . in order to facilitate the court’s determination of appropriate
damages.” Tlacoapa, 386 F. Supp. 2d at 365. The trial court further explained that, “[a]s part of
his post-trial submission, Plaintiff submitted a week-by-week analysis of Plaintiff’s unpaid wages
and overtime.” Tlacoapa, 386 F. Supp. 2d at 367. The court then “adopt[ed] Plaintiff’s calculation
of unpaid wages and overtime” and awarded the plaintiff damages for the unpaid wages and
overtime. Tlacoapa, 386 F. Supp. 2d at 368.


                                                 28
No. 81987-9-I/29


       Our Supreme Court has clarified that, “[b]ased on the plain meaning of the

statute, investigations of hazardous substances are remedial actions because

their purpose is to ‘discern whether such a threat exists.’” Douglass v. Shamrock

Paving, Inc., 189 Wn.2d 733, 741, 406 P.3d 1155 (2017). Moreover, “[r]emedial

action costs shall include reasonable attorneys’ fees and expenses” and

“[r]ecovery shall be based on such equitable factors as the court determines are

appropriate.” Former RCW 70.105D.080.

       Before the trial court entered its findings of fact and conclusions of law on

the issues regarding each party’s equitable share of liability under MTCA, the

Trust submitted proposed findings of fact and conclusions of law in which it

requested the trial court to order John’s Real Estate to pay its equitable share of

the costs incurred by the Trust for the investigation conducted by PGG. The trial

court’s findings of fact and conclusions of law did not require John’s Real Estate

to pay its equitable share of these costs. Subsequently, the Trust filed a motion

for reconsideration wherein it requested the trial court to order John’s Real Estate

to pay its equitable share of these costs. The trial court denied this motion.

       John’s Real Estate asserts that the trial court did not err by denying the

Trust’s requests for these remedial action costs because John’s Real Estate had

already paid the costs associated with the PGG investigation pursuant to a joint

defense agreement. Not so. In fact, the joint defense agreement did not regard

the costs incurred from the investigation conducted by PGG. Rather, as the trial

court found, the joint defense agreement regarded costs incurred from a different




                                         29
No. 81987-9-I/30


investigation, which was conducted by EPI in response to the claim filed by

Hadley:

       The overriding dispute on the Hadley claim was whether the
       contamination on the Thomas Center property had in fact spread to
       the Hadley property, and whether Hadley’s remediation costs were
       legitimate and recoverable. To defend that claim, a “Joint Defense
       Group” made up of Pollock, the Trust, Association, and Johns,
       agreed to jointly retain Thom Morin at EPI. Each of those four
       parties paid roughly $106,000 to EPI for its joint defense of the
       Hadley claims. EPI performed testing and analysis to defend the
       Hadley claim.

Finding of Fact 13.

       The investigation conducted by EPI was not the same as the investigation

conducted by PGG. Indeed, the trial court found that, “[p]rior to this litigation, . . .

the Trust hired Pacific Groundwater Group to determine whether the Thomas

Center property was contaminated, and with what substances” and, “[i]n April of

2015, PGG issued a report confirming the presence of PCE on site, and its likely

release from the dry cleaners.” Finding of Fact 31.

       John’s Real Estate cites to testimony from Michael Hytopoulos, the trustee

of the Trust, in support of its argument that the joint defense agreement regarded

costs incurred from the PGG investigation. However, this testimony indicates

that the joint defense agreement regarded costs incurred from the investigation

conducted by EPI, not the investigation conducted by PGG:

              Q.      Exhibit 68. And can you explain what Exhibit 68 is,
       please?
              A.      It’s a bill from PGG dated November 4th, 2019.
              Q.      And does this show an itemization of all the invoices
       the trust received from Pacific Groundwater Group?
              A.      That’s correct. It should summarize all the charges
       since they’ve been engaged.




                                           30
No. 81987-9-I/31


               Q.    Okay. And was the total that’s been charged here?
      Is it the 90,000 plus the 9,900 or so?
               A.    Yes, sir.
               Q.    Okay. So just right around $100,000?
               A.    That’s correct.
               Q.    And has the trust paid Pacific Groundwater Group
      that full amount?
               A.    Yes.
               Q.    And is this -- this is for their investigations at the
      property?
               A.    That’s correct.
               Q.    And as far as the joint defense group, same question
      there with EPI: They prepared various reports for the group?
               A.    That’s correct.
               Q.    And then the costs of that were split between four
      different parties; is that right?
               A.    That’s correct.
               Q.    And will you turn to Exhibit 69, please. Exhibit 69 . . .
      is this an itemization of all the bills from EPI split four ways between
      the association, The John’s Company, the trust, and the Pollock
      estates?
               A.    Therein lies the rub. It’s hard to tell sometimes
      because they – their charges roll off as paid, so I know that the total
      should be somewhere in the neighborhood of 50-some thousand
      dollars per – per member of the joint defense. . . .
      ....
               Q.    So this shows that the association and the trust have
      been billed $106,210; right?
               A.    That’s correct.
               Q.    And the Pollock Estate and The John’s Company
      have been billed 115,656?
               A.    That’s correct.

      Accordingly, the trial court erred by denying the Trust’s request for an

award of an equitable share of remedial action costs from John’s Real Estate for

the investigation conducted by PGG.

                                         VI

      The Trust next contends that the trial court erred by not awarding it

prevailing party attorney fees and costs under MTCA from John’s Real Estate.

Because the Trust was entitled to an award of remedial action costs from John’s



                                        31
No. 81987-9-I/32


Real Estate for the costs incurred from the investigation conducted by PGG, we

agree.

         “Whether a party is entitled to attorney fees is an issue of law which is

reviewed de novo.” Taliesen Corp. v. Razore Land Co., 135 Wn. App. 106, 141,

144 P.3d 1185 (2006). “Under the MTCA, the prevailing party in a private right of

action ‘shall recover its reasonable attorneys’ fees and costs.’” Douglass, 189

Wn.2d at 744 (quoting former RCW 70.105D.080). “The ‘prevailing party’ is not

defined, but the meaning is clear—the ‘prevailing party’ is the party that either

recovers remedial action costs or successfully defends against a claim for such

costs.” Douglass, 189 Wn.2d at 744-45. “The recovery amount, or percentage

recovered in comparison to the amount sought, is not dispositive to determine

prevailing party status.” Douglass, 189 Wn.2d at 745. As such, “prevailing party

status depends on whether [a party] recovers his [or her] remedial action costs.”

Douglass, 189 Wn.2d at 745. “If [a] trial court awards remedial action cost

recovery for at least some of [a party’s] costs, [the party] will be the prevailing

party, entitled to attorney fees.” Douglass, 189 Wn.2d at 746.

         As already explained, the trial court erred by denying the Trust’s request

that John’s Real Estate pay its equitable share of the remedial action costs for

the investigation conducted by PGG. Accordingly, on remand, the Trust is

entitled to an award of reasonable attorney fees and costs from John’s Real

Estate for prevailing on this claim.14


        14 The Trust asserts that it is entitled to an award of attorney fees and costs under MTCA

from John’s Real Estate merely because the trial court found that John’s Real Estate’s equitable
share of liability amounted to 14.65 percent. We reject this argument. Our Supreme Court has
made clear that, under MTCA, a party is entitled to an award of attorney fees and costs if that


                                               32
No. 81987-9-I/33


                                                VII

        The Trust, the Association, and John’s Real Estate all request an award of

attorney fees and costs on appeal pursuant to RAP 18.1 and RCW 70A.305.080.

See Dash Point Vill. Assocs. v. Exxon Corp., 86 Wn. App. 596, 613 n.39, 937

P.2d 1148, 971 P.2d 57 (1997) (holding that prevailing party attorney fees and

costs under MTCA apply to successful appellate actions).

        Because the Trust was entitled to an award of remedial action costs from

John’s Real Estate, the Trust is entitled to an award of reasonable attorney fees

and costs for prevailing against John’s Real Estate on appeal. See Douglass,

189 Wn.2d at 744-45. The amount of this award is to be determined by the trial

court on remand.

        Additionally, the plain language of the indemnity clause covers attorney

fees and costs incurred by the Trust both in the trial court and on appeal.

Indeed, this clause provides that “the Lessees will save and hold the Lessor

harmless from any and all damages, costs, fees and expenses or suits by public

officials or private parties . . . on account of any business, use or occupation of

the said premises or any part thereof.” (Emphasis added.)

        On remand, the Trust must establish the award of attorney fees that it is

entitled to under the indemnity clause as an element of damages, the measure of



party “either recovers remedial action costs or successfully defends against a claim for such
costs.” Douglass, 189 Wn.2d at 744-45. Here, the trial court erred by denying the Trust’s request
for an award of remedial action costs from John’s Real Estate for costs incurred as a result of the
investigation conducted by PGG. These were the only remedial action costs that the Trust
sought from John’s Real Estate. Additionally, the Trust did not defend against any claim for
remedial action costs from John’s Real Estate. Therefore, it is solely because the Trust is entitled
to an award of remedial action costs from John’s Real Estate that the Trust is also entitled to an
award of prevailing party attorney fees and costs from John’s Real Estate under MTCA.


                                                33
No. 81987-9-I/34


which must be determined by the trier of fact. See Newport Yacht Basin, 168

Wn. App. at 102 (“[A]ttorney fees sought pursuant to a contractual indemnity

provision are an element of damages that must be proved to the trier of fact.”

(citing Jacob’s Meadow, 139 Wn. App. at 760)).15

                                                 VIII

        The trial court’s ruling that the indemnity clause did not cover liability

arising under MTCA is reversed. Because of the trial court’s ruling on this issue,

the parties did not litigate whether the liability of the Association and John’s Real

Estate is joint, several, or joint and several under the indemnity clause. On

remand, the trial court must determine the extent of the obligations of both the

Association and John’s Real Estate pursuant to the indemnity clause.

        Additionally, the trial court’s allocation of each party’s equitable share of

liability under MTCA is vacated and, on remand, the trial court must determine

whether the parties’ equitable shares of liability are impacted by the obligations of

the Association and John’s Real Estate pursuant to the indemnity clause.16


        15    Because neither the Association nor John’s Real Estate prevailed on appeal, we deny
their requests for an award of attorney fees and costs.
           16 In calculating each party’s equitable share of liability, the trial court considered the

equitable factors set forth in Seattle Times Co. v. LeatherCare, Inc., 337 F. Supp. 3d 999, 1072-
73 (W.D. Wash. 2018), which included as an equitable factor the existence of any indemnification
agreement. Indeed, the trial court stated that, in allocating liability among the parties, it
specifically considered the existence of any indemnification agreement. Finding of Fact 57.
Therefore, on remand, the trial court must determine whether the parties’ equitable shares of
liability are impacted by the obligations of the Association and John’s Real Estate under the
indemnity clause.
           Additionally, on remand, the trial court must determine whether the Trust’s equitable
share of liability is either set off or extinguished in light of the obligations of the Association and
John’s Real Estate under the indemnity clause. Such a determination may impact whether the
Trust is entitled to an additional award of prevailing party attorney fees and costs under MTCA.
For example, if the Trust’s equitable share of liability is extinguished by the obligations of the
Association and John’s Real Estate under the indemnity clause, then the Trust may be entitled to
an award of prevailing party attorney fees and costs under MTCA. See Douglass, 189 Wn.2d at
744-45 (stating that, under MTCA, “[t]he ‘prevailing party’ is not defined, but the meaning is
clear—the ‘prevailing party’ is the party that either recovers remedial action costs or successfully


                                                  34
No. 81987-9-I/35


        Furthermore, because of the Association’s obligation to indemnify the

Trust, the trial court’s award of remedial action costs and attorney fees and costs

to the Association is vacated and, on remand, any award of remedial action costs

and prevailing party attorney fees and costs must be consistent with the

obligations of the Association and John’s Real Estate pursuant to the indemnity

clause.

        In addition, the trial court’s order on the Trust’s motion for reconsideration

in which the Trust sought remedial action costs from John’s Real Estate for the

investigation conducted by PGG is reversed and remanded for a determination of

the amount that the Trust is entitled to recover from John’s Real Estate, including

prevailing party attorney fees and costs and in light of the indemnification clause.

        The trial court’s ruling that the Association qualified for the third party

exemption to liability under MTCA is affirmed. The trial court’s order authorizing

the parties to prove remedial action costs through the submission of

documentary evidence after the trial court entered its order on liability is also

affirmed.

        Reversed in part, affirmed in part, and remanded for further proceedings

consistent with this opinion.




defends against a claim for such costs” (emphasis added)). However, because this issue was
neither litigated in the trial court nor adequately briefed on appeal, we do not opine on it.


                                              35
No. 81987-9-I/36


CONCUR:




                   36