United States Court of Appeals
For the First Circuit
No. 10-2418
P. GIOIOSO & SONS, INC.,
Petitioner,
v.
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION;
HILDA L. SOLÍS, SECRETARY OF LABOR,
Respondents.
PETITION FOR REVIEW OF A FINAL ORDER OF
THE OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
Before
Lynch, Chief Judge,
Torruella and Thompson, Circuit Judges.
Matthew Watsky, for petitioner.
Scott Glabman, Senior Appellate Attorney, U.S. Department of
Labor, with whom M. Patricia Smith, Solicitor of Labor, Joseph M.
Woodward, Associate Solicitor for Occupational Safety and Health,
and Heather R. Phillips, Counsel for Appellate Litigation, was on
brief for respondents.
March 28, 2012
TORRUELLA, Circuit Judge. The Occupational Safety and
Health Administration ("OSHA") fined Petitioner P. Gioioso & Sons,
Inc. ("Gioioso") $33,700 for violations of safety regulations
relating to the excavation of a trench. Gioioso contested the fine
at a hearing before an administrative law judge ("ALJ"), who
confirmed the fine. Gioioso requested review by the Respondent,
the Occupational Safety and Health Review Commission ("OSHRC"),
which upheld the ALJ's decision. Gioioso now petitions this Court
for review of OSHRC's order. Finding no error, we deny the
petition for review.
I. Facts and Procedural History
A. Regulatory Scheme Regarding Trenches
We first lay the relevant regulatory foundation. Federal
safety regulations require that any excavation at least five feet
deep in potentially unstable soil be "protected" from cave-ins
using approved protective measures such as shoring or trench boxes.
See 29 C.F.R. § 1926.652(a)(1) (the "cave-in provision"). In
addition, any trench with a depth of four feet or more must have a
ladder or other safe means of egress positioned within twenty-five
feet of where employees in the trench are working. See id.
§ 1926.651(c)(2) (the "ladder provision"). All excavations,
protective systems, and adjacent areas must be inspected by a
"competent person" before the start of work and as needed
throughout a shift. Id. § 1926.651(k)(1) (the "inspection
-2-
provision"). A "competent person" is defined as one "who is
capable of identifying existing and predictable hazards" and who
has the authority to eliminate them. Id. § 1926.650(b).
B. Safety Violations at the Work Site
We now dig into the evidence presented before the ALJ.
Gioioso is a public works contractor that constructs and installs
water supply and sewer pipes. As part of its work, Gioioso
performs excavations to remove and replace old utility pipes. On
July 10, 2009, Gioioso's employees were performing trenching work
to install water service lines at a site in Boston, Massachusetts.
An OSHA compliance officer, Sean Henrikson ("Henrikson"),
was assigned to inspect the Gioioso work site. That morning, while
walking to work, Henrikson observed employees in a trench at the
site. Henrikson reported this to his supervisor, who ordered him
to inspect the site. When Henrikson returned around noon to
perform the inspection, he saw a Gioioso employee climbing out of
an unprotected trench that appeared to be roughly six feet deep.
Later that day, around 1:00 P.M., from roughly fifty yards away,
Henrikson observed a Gioioso employee, later identified as Robert
Bruni ("Bruni"), climb out of the east end of a second trench
located near the first trench. Henrikson walked to the second
trench and observed equipment operator Gregory Perreira
("Perreira") standing next to the trench and foreman José Ourique
("Ourique") digging with a shovel in the east end of the trench.
-3-
Henrikson observed that the trench was unprotected and that it rose
to the top of Ourique's head. Henrikson identified himself and
instructed Ourique to exit the trench. Ourique did so by climbing
over what Henrikson identified as a box containing electrical
wiring.1
The site superintendent, Joseph Zenga ("Zenga"), arrived
at the scene roughly five minutes later. According to Henrikson,
Zenga told him that he had not inspected the trench or measured it
before any employees entered it. Henrikson spoke with Ourique,
who, according to Henrikson, said that he was not the "competent
person" at the site and that he had not measured the trench.
Henrikson also spoke with Perreira, who said that Zenga came by the
trench six to eight times per day, roughly once every twenty to
thirty minutes. Furthermore, Perreira told Henrikson that Zenga
had been by the trench earlier in the day while Ourique was in it,
but that Zenga did not say anything to Ourique or to anyone else
regarding trench protection.
Henrikson then measured the trench to be roughly 20 feet
long and 68 inches deep at the east end, the deepest end. The
trench was 51 inches wide. There was a trench box at the site, but
it would not have fit into the trench due to the presence of
1
Gioioso contends that the box contained non-hazardous wiring for
telecommunications. The dispute over the contents of the box does
not affect our decision.
-4-
utility lines. Henrikson also observed that there were no shoring
materials at the site.
C. Procedural History
Based on his observations of the site on July 10, 2009,
Henrikson recommended that OSHA issue citations to Gioioso. OSHA
cited Gioioso for violation of the "cave-in provision," 29 C.F.R.
§ 1926.652(a)(1), due to the lack of protection in the trench.
Furthermore, because OSHA had previously cited Gioioso for
violations of this provision, this citation was designated a
"Repeat Citation." OSHA also issued "Serious Citations" for
violations of the "ladder provision," id. § 1926.651(c)(2), and the
"inspection provision," id. § 1926.651(k)(1). Gioioso contested
the citations and the proposed penalties. The parties appeared at
a hearing before the ALJ on June 2, 2010.
The citations initially erroneously stated that three
employees were in the trench; the parties later stipulated that
Ourique was in the trench, and OSHA notified Gioioso prior to the
hearing that it would try to prove that a second employee was
exposed to the cited hazards. At the hearing, both Perreira and
Ourique testified that Bruni had not been in the deep end of the
trench, as Henrikson claimed, but rather in the shallow end.
Ourique testified that he was the competent person at the site,
contradicting Henrikson's claim that Ourique had told him he was
not the competent person. Perreira testified that he "may have"
-5-
told Henrikson that Zenga, the superintendent, came by the site
every twenty to thirty minutes, but that if he had, this was not
true. The ALJ determined based on their answers and their demeanor
that neither Ourique nor Perreira were reliable witnesses, and thus
chose to credit Henrikson's testimony over theirs.
Gioioso did not dispute that Ourique was in the deep end
of the trench when Henrikson observed him. However, Gioioso argued
that it should not be held liable because Ourique's conduct was the
result of unpreventable employee misconduct ("UEM"). To prove a
UEM defense, an employer must show that it: "(1) established a work
rule to prevent the reckless behavior and/or unsafe condition from
occurring, (2) adequately communicated the rule to its employees,
(3) took steps to discover incidents of noncompliance, and (4)
effectively enforced the rule whenever employees transgressed it."
P. Gioioso & Sons, Inc. v. Occupational Safety & Health Review
Comm'n, 115 F.3d 100, 109 (1st Cir. 1997) ("Gioioso I"). Gioioso
presented evidence on all four of these factors, but the ALJ found
Gioioso's evidence to be insufficient to sustain the UEM defense.
First, Gioioso presented evidence -- specifically, a
single-page document listing excavation procedures -- to show that
it had established work rules to prevent the cited violations.
However, the ALJ found that the fact that two employees were
digging in an unprotected trench, including a foreman (Ourique),
suggested that Gioioso's rules were not effective.
-6-
Second, Gioioso presented evidence that it had
communicated its rules to its employees. Gioioso's Safety
Director, John Condlin ("Condlin"), testified that Gioioso conducts
"tool box talks" at work sites and conducts safety meetings in the
office for foremen and supervisors. Condlin testified that Ourique
attended a safety meeting on June 4, 2009, and a tool box talk on
July 2, 2009, at which trenching safety was discussed. Gioioso
also introduced into evidence documents showing the agendas for
those two events and that Ourique attended them. However, the ALJ
noted that despite attending these meetings, Ourique did not follow
Gioioso's safety rules on July 10, 2009. The ALJ also faulted
Gioioso for not presenting documentation regarding other safety
meetings and tool box talks where trench safety had been discussed.
Third, Gioioso presented evidence to show that it took
steps to discover noncompliance. Condlin testified that he visited
work sites, sometimes unannounced, to make sure that the work crews
complied with safety regulations; Condlin also testified that
representatives of Gioioso's insurers sometimes conducted
inspections. However, the ALJ pointed out that Zenga, the site
superintendent, had observed Ourique in the trench but had never
said anything to him or to anyone else about trench protection.
The ALJ also noted that Gioioso did not present any documentary
evidence of the site visits about which Condlin testified.
-7-
Finally, Condlin testified that Ourique had been
disciplined for being in the trench without protection. He also
testified about other instances in which Gioioso had disciplined
employees for safety violations or had stopped work until safety
measures could be implemented. However, the ALJ again emphasized
that at least three safety violations occurred at the Gioioso site
on July 10, 2009. The ALJ also pointed to Condlin's concession
that Zenga had not been disciplined for the July 10, 2009 incident
or for another incident involving an unprotected trench that
occurred on April 24, 2009. The ALJ further noted that Gioioso had
failed to present documentation regarding any disciplinary actions
it had taken in the previous two years.
Based on the above-mentioned testimony and evidence, the
ALJ affirmed the citation for violation of the "cave-in provision,"
29 C.F.R. § 1926.652(a)(1). The ALJ also affirmed the "repeat"
violation citation in light of Gioioso's previous citations for
violation of the "cave-in provision." The ALJ further affirmed the
"serious" citations for violation of the "ladder provision," id.
§ 1926.651(c)(2), and the "competent person" provision, id.
§ 1926.651(k)(1). Finally, the ALJ affirmed the fines proposed by
OSHA for these violations.
Gioioso appealed the ALJ's decision to OSHRC. OSHRC
declined to review the decision, at which point the ALJ's decision
-8-
became a final order. See 29 U.S.C. § 661(j); 29 C.F.R.
§ 2200.90(d). Gioioso now petitions this Court for review.
II. Discussion
A. Applicable Law and Standard of Review
In order to establish a violation of a safety or health
standard, OSHA must prove: (1) that the cited standard applies; (2)
that there was a failure to comply with the standard; (3) that
employees had access to the violative condition; and (4) that the
employer had actual or constructive knowledge of the violation.
N&N Contractors, Inc. v. OSHRC, 255 F.3d 122, 125-26 (4th Cir.
2001). Final orders of the Commission are subject to the general
judicial review provisions of the Administrative Procedure Act, 5
U.S.C. §§ 701-706. See Gioioso I, 115 F.3d at 107-08. We will
uphold agency determinations unless they are "arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance
with law." 5 U.S.C. § 706(2)(A).
In conducting our review, we defer to the agency's
reasonable interpretation of the Occupational Safety and Health
("OSH") Act and its governing regulations. See Beaver Plant
Operations, Inc. v. Herman, 223 F.3d 25, 29 (1st Cir. 2000). The
OSH Act also directs that "[t]he findings of the Commission with
respect to questions of fact, if supported by substantial evidence
on the record considered as a whole, shall be conclusive." 29
U.S.C. § 660(a); see also Gioioso I, 115 F.3d at 108. This
-9-
deferential standard governs even where, as here, the Commission
does not hear the case itself but instead adopts an ALJ's findings.
Modern Cont'l/Obayashi v. OSHRC, 196 F.3d 274, 280 (1st Cir. 1999).
Under this deferential standard, we must "accept reasonable factual
inferences drawn by the Commission." Donovan v. Daniel Constr.
Co., 692 F.2d 818, 820 (1st Cir. 1982) (citations omitted). We
also give great deference to credibility determinations by the ALJ.
See Gioioso I, 115 F.3d at 108.
B. Actual or Constructive Knowledge of Violation
Gioioso argues that it was inappropriate to impose
sanctions because OSHA failed to show that Gioioso had actual or
constructive knowledge of Ourique's violations. Gioioso contends
that because Ourique was the "competent person" on the site, and
because he himself violated Gioioso's rules, his knowledge of the
violation cannot be imputed to Gioioso. However, Henrikson
testified that Ourique told him he was not the competent person.
The ALJ chose to credit Henrikson's testimony, and we defer to the
ALJ's credibility determination. See Gioioso I, 115 F.3d at 108.
Moreover, an employer can be charged with constructive
knowledge of a safety violation that supervisory employees know or
should reasonably know about. See Cent. Soya de P.R., Inc. v.
Sec'y of Labor, 653 F.2d 38, 40 (1st Cir. 1981) (where two
supervisors in charge of facility knew of hazard, "the knowledge of
these supervisory employees [was] properly imputed to the
-10-
employer"); Simplex Time Recorder Co. v. Sec'y of Labor, 766 F.2d
575, 589 (D.C. Cir. 1985) (finding employer had constructive
knowledge of a "readily apparent" safety violation that
"indisputably should have been known to management"). Here,
Henrikson testified that Perreira told him that Zenga, the site
superintendent, came by the trench roughly every twenty or thirty
minutes and had been by the trench at one point while Ourique was
in it. Thus, it is reasonable to infer that Zenga knew of
Ourique's presence in the unprotected trench. Since Zenga was the
site superintendent, Gioioso had constructive knowledge of the
violation.
C. Unpreventable Employee Misconduct
Gioioso argues that the ALJ misapplied the law regarding
the UEM defense. We bypass the argument on the first two prongs
and turn to the third prong. We find no error in the ALJ's ruling
on the third prong of the UEM defense, which is supported by
substantial evidence.
As to the third prong of the defense -- that the employer
took steps to discover noncompliance -- Gioioso argues that the
ALJ's decision was contrary to the record evidence. Gioioso
contends that the ALJ did not factor in Condlin's testimony that he
or Gioioso's insurers conducted inspections of work sites. Gioioso
also points out that Zenga was only minutes away from the trench in
which Ourique was working, and contends that this showed that
-11-
Gioioso took steps to discover noncompliance by having supervisors
nearby.
However, Zenga's failure to do anything after seeing
Ourique in the unprotected trench supports a finding of a
deficiency in Gioioso's efforts to discover incidents of
noncompliance. Moreover, as the ALJ noted, Gioioso did not present
any documentary evidence of safety inspections by Condlin or by
representatives of Gioioso's insurers. It is not error for an ALJ
to "count[] the absence of documentation against the proponent of
[a UEM] defense." Gioioso I, 115 F.3d at 110.
We need go no further. Substantial evidence shows that
Gioioso failed to satisfy the third prong of the UEM defense.
Accordingly, we do not need to consider Gioioso's objections to the
ALJ's ruling on the fourth prong.
D. Whether Substantial Evidence Supports the Decision Below
In its final offensive, Gioioso attacks various factual
findings by the ALJ. First, Gioioso attacks the ALJ's reliance on
Henrikson's testimony. Gioioso argues that it was wrong to credit
Henrikson's account of statements made by Ourique and Perreira
because this testimony was inadmissible hearsay. Gioioso also
argues that Henrikson's testimony about what he saw at the site was
unreliable because he initially observed the trench from fifty feet
away. Furthermore, Gioioso contends that, contrary to Henrikson's
-12-
testimony that there was no safe means of exiting the trench, a
photograph he took at the site showed a ladder on site.
The hearsay attack bogs down in the trenches of waiver
rules and the Federal Rules of Evidence. First, Gioioso waived its
challenge to this testimony by not objecting at the hearing before
the ALJ. See Fed. R. Evid. 103(a)(1) (objection not made at trial
is not preserved on appeal); 29 C.F.R. § 2200.71 (Federal Rules of
Evidence applicable to ALJ hearings). See also Capeway Roofing
Sys. v. Chao, 391 F.3d 56, 62 (1st Cir. 2004) (hearsay objection to
statement made to OSHA inspector waived on appeal because it was
not made at the hearing). Moreover, any statements made by Ourique
and Perreira to Henrikson were not hearsay because they were
statements by Gioioso's employees within the scope of their
employment. See Fed. R. Evid. 801(d)(2)(D) (statement not hearsay
if it is "offered against an opposing party" and "was made by
[that] party's agent or employee on a matter within the scope of
that relationship and while it existed"); Astra Pharm. Prods., Inc.
v. Occupational Safety & Health Review Comm'n, 681 F.2d 69, 73 n.8
(1st Cir. 1982) (statements by company's employees to OSHA
inspector not hearsay under Fed. R. Evid. 801(d)(2)(D)).
As for Gioioso's attacks on Henrikson's credibility, we
see no reason not to accord the ALJ's credibility determination our
traditional deference. See Gioioso I, 115 F.3d at 108. There is
no reason to believe that Henrikson could not have made an accurate
-13-
observation of the trench from fifty feet away. Finally, as OSHRC
points out, the photograph to which Gioioso refers shows a ladder
on the site in a truck; a ladder in a truck is of course no use to
workers at the bottom of a trench.
In addition to challenging the finding of liability,
Gioioso attacks the amount of the penalties imposed. Gioioso
claims that the ALJ improperly assessed a higher penalty than was
warranted because she credited Henrikson's speculation that the box
Ourique had to step on to exit the trench contained electrical
wiring. However, the danger the ALJ pointed to in her decision was
the danger of slipping and falling, not of electrocution. There
is no evidence that the fine was based in any way on the type of
wiring in the box.
Gioioso also alleges it was prejudiced by the fact that
the original OSHA citation mentioned three employees in the trench.
However, the ALJ properly found that this citation error was
harmless because OSHA notified Gioioso prior to the hearing that it
would only try to prove that two employees were in the trench.
Finally, Gioioso complains that the repeat citation for violation
of the "cave-in provision" was incorrect because the citation does
not recite the earlier violation upon which it was based. However,
the ALJ properly found that Gioioso was not prejudiced by this
error because the parties stipulated to the earlier violation two
weeks before the hearing.
-14-
III. Conclusion
Since we find that substantial evidence supports the
decision below, we deny the petition for review.
Denied.
-15-