UNITED STATES COURT OF APPEALS U .S. C O U R T OF APPE ALS
FOR THE NINTH CIRCUIT
INUPIAT COMMUNITY OF THE No. 12-70440
ARCTIC SLOPE,
Petitioner, MEMORANDUM *
v.
KENNETH LEE SALAZAR, Secretary of
the Interior; BUREAU OF OCEAN
ENERGY MANAGEMENT,
Respondents,
STATE OF ALASKA; SHELL GULF OF
MEXICO INC.,
Respondents-Intervenors.
NATIVE VILLAGE OF POINT HOPE; No. 12-70459
ALASKA WILDERNESS LEAGUE;
CENTER FOR BIOLOGICAL
DIVERSITY; DEFENDERS OF
WILDLIFE; NATIONAL AUDUBON
SOCIETY, INC.; NATURAL
RESOURCES DEFENSE COUNCIL;
NORTHERN ALASKA
ENVIRONMENTAL CENTER;
*
This disposition is not appropriate for publication and is not precedent
except as provided by Ninth Circuit Rule 36-3.
OCEANA; RESISTING
ENVIRONMENTAL DESTRUCTION
ON INDIGENOUS LANDS, REDOIL;
SIERRA CLUB; THE WILDERNESS
SOCIETY, INC.; OCEAN
CONSERVANCY,
Petitioners,
v.
KENNETH LEE SALAZAR, Secretary of
the Interior; BUREAU OF OCEAN
ENERGY MANAGEMENT,
Respondents,
STATE OF ALASKA; SHELL GULF OF
MEXICO INC.,
Respondents-Intervenors.
On Petition for Review of a Final Agency Action
Bureau of Ocean Energy Management
Argued and Submitted May 15, 2012
Pasadena, California
Before: KOZINSKI, Chief Judge, BEA and IKUTA, Circuit Judges.
In these expedited petitions, Inupiat Community of the Arctic Slope and
Native Village of Point Hope et al. (collectively, “petitioners”) challenge the
Bureau of Ocean Management’s (BOEM) approval of Shell Gulf of Mexico Inc.’s
2
plan for exploratory drilling in the Chukchi Sea under the Outer Continental Shelf
Lands Act (OCSLA).
Petitioners incorporate by reference much of the briefing and argument from
the companion case challenging drilling in the Beaufort Sea. See Native Vill. of
Point Hope v. Salazar, No. 11-72891, --- F.3d ---- (9th Cir. 2012).1 To the extent
such incorporation by reference is sufficient to preserve these arguments, we have
reviewed the applicable excerpts of record and reject petitioners’ claims for the
same reasons expressed in our decision in that case.
Specifically, to the extent it was preserved, petitioners’ argument that the
Chukchi Sea exploration plan’s description of the well-capping stack and
containment system does not comply with the informational requirements of 30
C.F.R. § 550.213(d) fails. BOEM could reasonably conclude that the seven-
paragraph description of the technology satisfied § 550.213(d)’s requirement of a
“description and discussion of any new or unusual technology.” See Native Vill.,
No. 11-72891, at *16–19. We also reject petitioners’ argument, to the extent
preserved, that the exploration plan does not comply with 30 C.F.R. § 250.107(c),
1
There is one major difference: These petitions do not include the argument
raised in the Beaufort Sea petitions that BOEM erred by approving Shell’s
exploration plan in the absence of an approved oil spill response plan as required
by 30 C.F.R. § 550.219(a).
3
which requires use of the best available and safest technology (BAST), because the
authority to decide whether the BAST standard has been satisfied is vested in the
Bureau of Safety and Environmental Enforcement (BSEE), the agency tasked with
review of Shell’s oil spill response plan, not BOEM. See Native Vill., No. 11-
72891, at *19 n.10; see also 76 Fed. Reg. 64,432, 64,435 (Oct. 18, 2011).
BOEM also did not err in approving the exploration plan without expressly
reconciling Shell’s proposal to use a well-capping stack and containment system in
the event of an oil spill with Shell’s statements in its 2010 plan that a well-capping
system was not feasible, because such reconciliation is not required. See Native
Vill., No. 11-72891, at *20–21. Moreover, because well-capping was just one of
many relief efforts proposed by Shell in the exploration plan, and because the
record suggests that “[s]ubsea capping capability has recently been developed” and
“is directly transferable to Shell’s operations in the Chukchi sea,” it was reasonable
for BOEM to conclude that the exploration plan would not “probably cause serious
harm or damage” to environment, as required to approve the plan. See 43 U.S.C.
§§ 1334(a)(2)(A)(i), 1340(c)(1); see also Native Vill., No. 11-72891, at *21–22.
Nor did BOEM err in approving Shell’s exploration plan without expressly
reconciling the difference between the plan’s estimate for the time it will take to
drill exploration wells and the time it will take to drill an emergency relief well.
4
The exploration plan’s estimate that it would take a shorter time to drill relief wells
than to drill exploratory wells was “supported by substantial evidence on the
record considered as a whole” and is therefore “conclusive.” 43 U.S.C.
§ 1349(c)(6). Specifically, the exploration plan explained that “[r]elief well
drilling is rapid” because the relief well does not necessarily require the drilling of
a mudline cellar; relief wells may intercept a deep blowout above the total vertical
depth; and, in the event of a blowout, additional resources will be funneled into
drilling the relief well. Cf. Native Vill., No. 11-72891, at *22–24. BOEM could
reasonably accept the exploration plan’s site- and reservoir-specific estimates of
the time it would take to drill a relief well, as opposed to the slightly longer times
estimated by the Lease Sale 193 blowout analysis, which was based on an
unspecified location in the Chukchi Sea. Further, BOEM’s conclusion that Shell
provided a realistic estimate of the time it would take to drill a relief well is a
technical issue that lies squarely within the agency’s scientific expertise and
therefore is entitled to “great deference.” See Envtl. Def. Ctr., Inc. v. EPA, 344
F.3d 832, 869 (9th Cir. 2003).
Finally, because the OCSLA regulations permit BOEM to approve an
exploration plan with conditions so long as the exploration plan “complies with all
applicable requirements” under OCSLA, 30 C.F.R. § 550.233(b)(1), BOEM did
5
not err in imposing conditions on Shell as part of BOEM’s approval of the Chukchi
Sea exploration plan. See Native Vill., No. 11-72891, at *24–25.
DENIED.