Entergy Nuclear Vermont Yankee, LLC v. Shumlin

DRONEY, Circuit Judge:

Entergy Nuclear Vermont Yankee, LLC, and Entergy Nuclear Operations, Inc., (collectively, “Entergy”)1 own and op*398erate the Vermont Yankee Nuclear Power Station (“Vermont Yankee”), a nuclear power plant in Vernon, Vermont. Entergybrought suit in the United States District Court for the District of Vermont against the Governor and Attorney General of the State of Vermont and the members of the Vermont Public Service Board in their official capacities (collectively, “Vermont”), and asserted three claims. Count One alleged that three recently enacted Vermont statutes governing Vermont Yankee — Acts 74, 160, and 189 — concerned issues of radiological safety and thus were preempted by the federal Atomic Energy Act. Count Two alleged that Vermont had attempted to condition its grant of permission to operate Vermont Yankee on the execution of a power purchase agreement that favored Vermont retail consumers, and that this attempt was preempted by the Federal Power Act. Count Three asserted that these same actions with respect to the power purchase agreement also violated the dormant Commerce Clause of the United States Constitution. Following a bench trial, the district court (Murtha, J.) found in favor of Entergy as to Count One with respect to Acts 74 and 160 and found the challenge to Act 189 to be moot.2 The district court also found in favor of Entergy as to Count Three. Lastly, the district court found Count Two to be premature. We affirm the district court as to Counts One and Two, and reverse the district court as to Count Three.

BACKGROUND

We summarize here those findings of fact relevant to this appeal that were made by the district court following the bench trial.

I. The History of Vermont Yankee

In 1972, Vermont Yankee opened and began operating under the ownership and management of the Vermont Yankee Nuclear Power Corporation (VYNPC), a joint venture of eight New England retail electric utilities. Among the eight members of the joint venture were two Vermont electric companies (Central Vermont Public Service and Green Mountain Power), which owned a collective fifty-five percent share of Vermont Yankee. Vermont Yankee had been granted a forty-year Facility Operating License by the Atomic Energy Commission, the federal agency that preceded the Nuclear Regulatory Commission (NRC). The forty-year license was to expire on March 21, 2012.

In 1999, VYNPC sought to sell Vermont Yankee. After an initial bid by one firm was rejected by the Vermont Public Service Board (the “Board”),3 Entergy submitted a bid for Vermont Yankee in the summer of 2001 and sought a “certificate of public good” (CPG), a license from the Board to continue to operate Vermont Yankee under Vermont state law.4 As it was negotiating with the Board, Entergy entered into a memorandum of under*399standing (MOU) (the “2002 MOU”) with the Vermont Department of Public Service (the “Department”).5 The 2002 MOU incorporated a power purchase agreement (PPA) Entergy executed in 2001 (the “2001 PPA”) that promised Vermont retail electric utilities favorable pricing terms for the purchase of power from Vermont Yankee until 2012.6 Entergy maintains it agreed to the 2001 PPA because it feared that the Department would not otherwise recommend a CPG for Vermont Yankee. Entergy also agreed in the 2002 MOU to “waive any claim ... that federal law preempts the jurisdiction of the Board.”

On June 13, 2002, the Board approved the sale of Vermont Yankee to Entergy and issued a new CPG. In its Decision and Final Order, the Board stated that the sale of Vermont Yankee to Entergy would “promote the general good” in part because, “under most reasonably foreseeable scenarios, the transactions are highly likely to produce an economic benefit for Vermont ratepayers.” In re Vt. Yankee Nuclear Power Corp., Docket No. 6545, 2002 WL 1997942, at *1 (Vt.Pub.Serv.Bd. June 13, 2002). The Order specifically endorsed the 2001 PPA because it allowed Vermont retail utilities to purchase power from Vermont Yankee at prices that “are substantially below the ‘currently committed’ operating costs of Vermont Yankee over the remaining term of its license.” Id. The Order noted that the 2001 PPA also imposed a “cap on the charges for Vermont Yankee power.” Id.

In 2002, Entergy obtained from the Federal Energy Regulatory Commission (FERC) authorization to sell power into the interstate market under a market-based tariff, which remains in effect. The authorization permits Entergy to sell power wholesale through ISO-New England (“ISO-NE”), a nonprofit independent system operator under FERC regulation that administers New England’s energy markets. ISO-NE’s stated responsibilities are to maintain “reliable power system operations,” ensure “efficient and competitive markets,” and to “administer [the] regional transmission tariff, including comprehensive regional system planning.”

II. The Recent Vermont Legislation Concerning Vermont Yankee

A. Act 74: The Vermont Legislation Concerning Increased Nuclear Waste Storage by Vermont Yankee

In 2003, Entergy petitioned the Board to obtain a twenty-percent “uprate,” which would allow an increase in Vermont Yankee’s power output and also result in a concomitant increase in nuclear waste. See Entergy Nuclear Vt. Yankee, LLC v. United States, 95 Fed.Cl. 160, 173 (2010), aff'd in part, rev’d in part sub nom., Vt. Yankee Nuclear Power Corp. v. Entergy Nuclear Vt. Yankee, LLC, 683 F.3d 1330 (Fed.Cir.2012). Under a statute enacted in 1977 — five years after Vermont Yankee first began operating — the construction of new nuclear waste storage facilities in Vermont was prohibited unless the Vermont Legislature passed a bill or joint resolution finding that the facilities promoted the “general good of the state.” Vt. Stat. Ann. tit. 10, § 6501(a). However, two years later, in 1979, the Vermont Legislature *400enacted an “exemption” provision stating that the requirements imposed by § 6501 do “not apply to any temporary storage by Vermont Yankee Nuclear Power Corporation of spent nuclear fuel elements or other radioactive waste at its present site.” Id. § 6505.

At the same time that Entergy sought the uprate, it also entered into a new MOU (the “2003 MOU”) with the Department under which Entergy would pay $6 million into new “State Benefits Funds,” namely the “Environmental Benefit Fund,” the “Low Income Benefit Fund,” and the “Entergy Fund for Economic Benefit.” See Entergy Nuclear, 95 Fed.Cl. at 173-74; In re Entergy Nuclear Vt. Yankee, LLC, 232 P.U.R.4th 219, 223 (Vt.Pub.Serv.Bd. Mar. 15, 2004). The Board then issued a CPG approving the uprate on March 24, 2004. Entergy Nuclear, 95 Fed.Cl. at 188. However, Entergy also needed to obtain approval to construct the new dry cask spent nuclear fuel storage facility, even though it had recently received approval for it from the NRC.7 Entergy then petitioned the Board, requesting permission to expand its spent fuel storage facility. Entergy maintained that the exemption provision of section 6505 applied to the Vermont Yankee site in general, as opposed to a particular owner of the plant. The Board sought guidance from the Vermont Senate, which, in turn, obtained a letter from the Office of the Vermont Attorney General opining that section 6505 was owner-specific. See Letter from Michael McShane, Asst. Att’y Gen., to Sen. Peter Welch, Pres. Pro Tempore of the Vt. Senate, 2004 WL 1737093, at *1-2 (Apr. 30, 2004). Since Vermont Yankee had changed ownership from VYNPC to Entergy, the letter provided that Entergy would need the approval of the Vermont Legislature to add spent fuel storage capacity. Id. at *4.

In response, Entergy presented proposed legislation clarifying that section 6505 was site-specific, rather than owner-specific. This proposal failed to obtain support from the Vermont Legislature, however. The Vermont Legislature then began hearings on the bill that would eventually become Act 74.

Act 74, which was enacted on June 21, 2005, had two principal effects. First, Entergy would only need to seek a CPG from the Board before constructing storage facilities for new spent nuclear fuel, rather than the Vermont Legislature as had been required by section 6501(a). However, this CPG would remain in effect only until March 21, 2012. The second effect of Act 74 was that after March 21, 2012, the storage of any new spent nuclear fuel in Vermont would require an affirmative vote by the Vermont Legislature. If no such affirmative vote occurred, storage of nuclear waste generated from operations after March 21, 2012, would not be permitted. Thus, Vermont Yankee would have to shut down.

The post-March 21, 2012, shift of responsibility for approving the storage of spent nuclear fuel generated by Vermont Yankee from the Board to the Vermont Legislature had important ramifications. Decisions of the Board may be appealed to *401the Vermont Supreme Court. Vt. Stat. Ann. tit. 30, § 12. No such review mechanism would exist for the Vermont Legislature’s decision not to approve additional spent nuclear fuel storage space.

Act 74 added three new sections to title 10 of the Vermont Statutes: sections 6521, 6522, and 6523. Section 6521 outlines the Vermont Legislature’s findings, including recognition of the need to develop renewable and environmentally sustainable energy sources in Vermont. Vt. Stat. Ann. tit. 10, § 6521. To support this objective, section 6521 references the state’s creation of an “energy efficiency fund ... to support cost-effective investments in end-use energy efficiency resources,” and a statewide energy purchasing pool with a “related program to accelerate investments in new renewable and combined-heat and power projects.” Id.

Section 6522 restates the requirement that the owners of Vermont Yankee cannot construct new spent fuel storage facilities for the period up to March 21, 2012, unless they obtain a CPG from the Board. Id. § 6522(a). Section 6522 also mandates that the Board find that the owners of Vermont Yankee have adequate resources to manage spent fuel and decommission the plant, if necessary, and a plan “to remove all spent fuel from Vermont to a federally certified long-term storage facility in a timely manner,” and that the owners comply with any existing MOUs with the state. Id. § 6522(b). Lastly, section 6522 states that any CPG issued by the Board pursuant to Act 74 will apply to spent nuclear fuel generated by Vermont Yankee only until March 21, 2012, which is the “end of the current operating license.” Id. § 6522(c)(2). This provision states that the owners have no “expectation or entitlement to continued operation of Vermont Yankee following the expiration of its current operating license on March 21, 2012.” Id. § 6522(c)(5). Section 6522(c)(4) provides that Vermont Yankee cannot store spent nuclear fuel generated after March 21, 2012, on site, unless the Vermont Legislature enacts legislation granting such permission. In the absence of any other storage options, this would effectively shut down Vermont Yankee.

Section 65238 established a “Clean Energy Development Fund” (the “Fund”), which Entergy agreed to when it received permission for its uprate. See Vt. Stat. Ann. tit. 10, § 6523(a).9 Under section 6523(a), the money Entergy had promised to pay into the State Benefits Funds under the 2003 MOU would instead be paid into the Fund. The Fund’s purpose is to “promote the development and deployment of cost-effective and environmentally sustainable electric power and thermal energy or geothermal resources for the long-term benefit of Vermont consumers.” Id. § 6523(c). Section 6523(d) outlines various types of renewable energy investments that the Fund can undertake, such as energy projects on farms, biofuel production, and thermal energy facility development. Id. § 6523(d). Entergy estimated that its total obligation under section 6523 to the Fund would be $2.5 million per year, or about $15 million over the period from 2005 to 2012.10

*402Act 74 also explicitly incorporates the MOUs, including the 2002 and 2003 MOUs, as well as a new MOU executed on June 21, 2005 (the “2005 MOU”). Vt. Stat. Ann. tit. 10, § 6522(b)(4).11 The 2005 MOU mandated, inter alia, that Entergy locate the spent nuclear fuel storage pad at least one hundred feet from a floodplain, space the storage casks to permit access to individual casks “to the greatest extent possible,” configure the spent-fuel pool so that high-decay heat assemblies are surrounded by low-decay heat assemblies, perform temperature monitoring and monthly manual radiation surveillance of the storage casks and report the results to the Department, not store waste generated outside Vermont on site, remove “high level” spent nuclear fuel from Vermont “as quickly as possible,” and conduct a study addressing the stability of the proposed new spent nuclear fuel storage facility based upon a stated concern that an adjacent river bank might erode and collapse. See 2005 MOU at 1-2; see also Entergy Nuclear Vt. Yankee, 95 Fed.Cl. at 179; In re Entergy Nuclear Vt. Yankee, LLC, 249 P.U.R.4th 1, 2006 WL 1418626, at *48 (Vt.Pub.Serv.Bd. Apr. 26, 2006).12 This “flood analysis” was more extensive than that required by the NRC’s licensing process for the same spent nuclear fuel storage facility and, although Entergy believed that the Board’s concerns regarding the probability of a collapse were “not credible,” Entergy agreed to undertake the study. In re Entergy Nuclear Vt. Yankee, LLC, 2006 WL 1418626, at *28, *51. As with the earlier MOUs, Entergy agreed to waive any federal preemption claim concerning the 2005 MOU. 2005 MOU at 3.

On June 22, 2005, the day after Act 74 went into effect, Entergy filed a petition with the Board seeking to construct a dry fuel storage facility at Vermont Yankee, which, as mentioned, the NRC had already pre-licensed. In re Entergy Nuclear Vt. Yankee, LLC, 2006 WL 1418626, at *6. In the subsequent eight months, the Board held a series of public meetings and conducted technical hearings to evaluate the petition. Id. at *6-7. The Board also received public comments, of which the “vast majority ... highlighted public concerns about the public uprate that [the Board has] previously approved, and the desire for an independent safety assessment, general nuclear safety concerns, and Vermont Yankee as a terrorist target.” Id. at *9. In addition, most of those who attended the Board’s public meetings “opposed the proposed dry fuel storage facility” for reasons relating to the facility’s “vulnerability to natural or manmade disasters,” the adequacy of dry fuel storage technology, and the potential for environmental harm. Id. at *9-10. On April 26, 2006, the Board issued an Order granting the petition until 2012, and issuing a new CPG for the construction of the storage facility. Id. at *1. The Board stated that the “most significant factor” in its decision was the “economic benefit of the facility.” Id. at *5. Noting that Vermont Yankee “now provides approximately one-third of the power consumed by the state of Vermont,” 13 an early shutdown of the plant *403due to the absence of spent nuclear fuel storage facilities would “impose substantial costs on Vermont ratepayers.” Id. “Without the favorably-priced power from Vermont Yankee, Vermont utilities would need to purchase replacement power from sources that are presently expected to be more expensive over this period. Approval of the dry fuel storage facility provides a direct economic benefit to the state by preserving the power.” Id. The Board estimated the likely savings to Vermont ratepayers arising from the 2001 PPA, under which Vermont Yankee power “has been sold to Vermont utilities at prices consistently below the spot-market price of energy in New England,” at “approximately $61 million over the period from 2008 to 2012.” Id. at *21.

B. Act 160: The Vermont Legislation Requiring State Legislative Approval To Operate Vermont Yankee After 2012

On January 25, 2006, Entergy applied to the NRC for a renewal license to operate Vermont Yankee through March 21, 2032. One week later, on February 1, 2006, the Vermont Legislature began considering the bill that would eventually become Act 160. Act 160 was passed on May 18, 2006, and provides that “a nuclear energy generating plant may be operated in Vermont only with the explicit approval of the General Assembly.” Act 160, § 1(a).14

Act 160 provides that, in deciding whether to approve operation of a nuclear power plant, the Vermont Legislature should consider “the state’s need for power, the economics and environmental impacts of long-term storage of nuclear waste, and choice of power sources among various alternafives.” Id. The preamble states that Act 160’s general purpose is to provide the Vermont Legislature with the authority to determine whether to issue a new CPG for Vermont Yankee after March 21, 2012. Id. § 1(c). Act 160 would also help foster a “larger societal discussion of broader economic and environmental issues relating to the operation of a nuclear facility in the state, including an assessment of the potential need for the operation of the facility and its economic benefits, risks, and costs,” and of alternative methods of power generation as well. Id. § 1(d). Act 160 also includes a stated purpose of ensuring that the evaluation of new CPGs be conducted under new cost-benefit assumptions and analyses, rather than those that supported the previous CPG. Id. § 1(e).

Act 160 adds three new sections to title 30 of the Vermont Statutes: sections 248(e)(2), 248(m), and 254. Section 248(e)(2) requires that the Vermont Legislature approve an extension of the Vermont Yankee operating lease before the Board issues a new CPG. See Vt. Stat. Ann. tit. 30, § 248(e)(2). Legislative approval for continued operation of Vermont Yankee is no longer limited to issues concerning spent fuel storage, as under section 6522(c)(4) of Act 74; rather, Act 160 requires that the Vermont Legislature approve all aspects of the continued operation of Vermont Yankee. Section 248(m) requires that the Board “evaluate the application [for a new CPG] under current assumptions and analyses” and not apply “an extension of the cost benefit assumptions and analyses forming the basis of the previous certificate of public good for the operation of the facility.” Id. § 248(m). Lastly, section 254 requires that the own*404ers of Vermont Yankee apply for a new CPG at least four years prior to the expiration of the current CPG, and that the Board inform the Vermont Legislature of the receipt of any new CPG application. Id. § 254(a)(l)-(2). When any new CPG application is submitted, the Department is directed to engage in fact-finding with three stated objectives in mind:

(A) to facilitate public discussion of long-term economic and environmental issues relating to the operation of any nuclear facility in the state;
(B) to identify and assess the potential need for the operation of the facility and its long-term economic and environmental benefits, risks, and costs; and
(C) to assess all practical alternatives to those set forth in the applicant’s petition that may be more cost-effective or that otherwise may better promote the general welfare.

Id. § 254(b)(1).

Section 254 also requires that the Department collect information relating to Entergy’s “funding plans for guardianship of nuclear waste after licensure but before removal of nuclear waste from the site,” plant closure procedures, and funding for emergency management systems. One subsection of section 254 requires the Department to “identify, collect information on, and provide analysis of long-term environmental, economic, and public health issues, including issues relating to dry cask storage of nuclear waste and decommissioning options.” Id. § 254(b)(2)(B). The Department is further directed to report its findings to the Board and to the Vermont Legislature. Id. § 254(a)(2)-(3). The Board, in turn, is directed to consider the findings of the Department in assessing an application for a new CPG. Id. § 254(c).

C. Act 189: The Vermont Legislation Requiring State Inspections of Vermont Yankee

On June 5, 2008, then-Vermont Governor Jim Douglas signed into law Act 189, entitled “An Act Relating to a Comprehensive Vertical Audit and Reliability Assessment of the Vermont Yankee Nuclear Facility.” The purpose of Act 189 was to assist the Vermont Legislature in making its determination as to whether Vermont Yankee should be permitted to operate past 2012, and to reconfirm the “obligation and authority of the general assembly to examine the reliability of the nuclear power station of Entergy Nuclear Vermont Yankee.” Act 189, § 1(a).15 Act 189 further provides that, because Entergy was applying to extend the life of Vermont Yankee beyond its original forty-year design, the Vermont Legislature needed to assess any “reliability issues associated with operating [Entergy] for an additional 20 years after its scheduled closure in 2012.” Id. § 1(b). Act 189’s text also addresses concerns relating to the operating reliability of Vermont Yankee and issues relating to its performance that might arise from expanding the plant. Id. § 2.

Act 189 calls for Department inspections of Vermont Yankee’s operations, such as its electrical, emergency, and mechanical systems. Id. §§ 3(a), 5(a). The Act also sets out documentation requirements and inquiries that must be undertaken by the Department relating to the installation, maintenance, and inspection of safety systems in Vermont Yankee. Id. § 4. To *405maximize the public visibility of these inspections of Vermont Yankee, Act 189 creates an oversight panel consisting of experts in nuclear power appointed by the governor and the Vermont Legislature. Id. § 6. The panel’s findings and evaluation of Vermont Yankee were to be reported to the Vermont Legislature, which would use this information to determine whether to extend the operating license for the plant beyond March 21, 2012. Id. § 6(d).

D. S.289: The Vermont Senate Bill That Would Have Permitted the Continued Operation of Vermont Yankee Beyond 2012, as Required by Act 160

On January 7, 2010, Entergy disclosed a leak of tritium, a decay product of nuclear energy, emanating from Vermont Yankee. Entergy stopped the leak and remediated its impact on the surrounding soil, and after a subsequent investigation, the NRC concluded that the “public’s health and safety and the off-site environment were not adversely affected.” A report by an independent consulting group retained by the State of Vermont concluded, on April 30, 2010, that the leak did not affect the reliability of Vermont Yankee.

At the time of the leak, the Vermont Senate was considering S.289, which was originally titled, “An Act Relating to Approval for Continued Operation of the Vermont Yankee Nuclear Power Station.” S.289, if passed, would have authorized the operation of Vermont Yankee for an additional twenty years past March 21, 2012, as required by Act 160. Although the NRC granted a twenty-year renewal for the operation of Vermont Yankee on March 21, 2011, S.289 failed to pass in the Vermont Senate. As a result, Vermont Yankee has not been granted permission by the Vermont Legislature to operate past March 21, 2012.

Collectively, under Acts 74 and 160, and due to the failure to pass S.289, the operation of Vermont Yankee after March 21, 2012, depends upon the Vermont Legislature approving the power plant’s continued operation. As the Vermont Legislature has failed to act, Vermont Yankee’s CPG expired on March 21, 2012, and the plant would have been forced to shut down absent the district court’s decision below.

In making its determination whether to permit further operation, the Vermont Legislature is required by Acts 74 and 160 to consider the impact of the local storage of spent nuclear fuel on the local economy and environment, and on the diversity of power sources available to Vermont retail utilities. Under the two Acts, the Vermont Legislature must also consider the following in determining whether to allow Vermont Yankee to continue operating: (1) the “public health” implications related to dry cask storage of nuclear waste and decommissioning of the plant; (2) Entergy’s resources for emergency management systems, management of spent nuclear fuel storage, and decommissioning of the plant; (3) Entergy’s planning for the removal of nuclear waste; and (4) Entergy’s long-term plan for the closure of Vermont Yankee.

In addition, Acts 74 and 160 require that Entergy comply with the 2002, 2003, and 2005 MOUs. Those MOUs impose, inter alia, the following additional requirements on Entergy, apart from making payments into a fund used to promote alternative energy sources: (1) analysis of the operational safety of Vermont Yankee in the event of flooding in excess of federal licensing requirements; (2) compliance with specific requirements for the construction and monitoring of spent nuclear fuel casks; *406(3) monitoring of the temperature and radiation of the storage casks and regular reporting to the Department; (4) no storage of any nuclear waste generated outside of Vermont; (5) removal of the nuclear waste generated by Vermont Yankee from the state as quickly as possible; and (6) waiver of any federal preemption challenge to the Board’s authority to regulate the plant. Lastly, the MOUs require that Entergy comply with the 2001 PPA under which Vermont retail utilities must receive favorable pricing terms for the power produced by Vermont Yankee relative to retail utilities in other states.

III. Proceedings Before the District Court

On April 18, 2011, Entergy brought suit in the United States District Court for the District of Vermont against the Governor and Attorney General of the State of Vermont and the members of the Vermont Public Service Board. The complaint sets forth three claims:

• Count One: Entergy sought a permanent injunction and declaration that Act 74, Act 160, and Act 189 are invalid under the Supremacy Clause of the United States Constitution because they are preempted by the Atomic Energy Act. Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 838 F.Supp.2d 183, 188-89 (D.Vt.2012).

• Count Two: Entergy sought a permanent injunction and declaration that the Federal Power Act preempts the State of Vermont from conditioning Vermont Yankee’s continued operation on the existence of a power purchase agreement between Vermont Yankee and Vermont’s retail utilities, because FERC has exclusive jurisdiction over the regulation of power transmission and sale. Id. at 189.

• Count Three: Entergy sought a permanent injunction and declaration that Vermont may not condition continued operation of Vermont Yankee on the existence of a power purchase agreement, because doing so places substantial burdens on interstate commerce, in violation of the dormant Commerce Clause. Id.

On January 19, 2012, the district court issued its opinion following a bench trial. The court first concluded that the Atomic Energy Act facially preempts Act 160, which, through the operation of section 248(e)(2), effectively allows the Vermont Legislature to “deny a pending renewal petition by taking no action on the petition, for any reason, procedural or substantive, stated or unstated, permissible or impermissible under federal law.” Entergy Nuclear, 838 F.Supp.2d at 227. The court also pointed to section 254(b)(2)(B), which calls upon the Department to support the Vermont Legislature’s fact-finding by conducting studies on, inter alia, “long-term environmental, economic, and public health issues, including issues relating to dry cask storage of nuclear waste and decommissioning options.” Id. at 227-28. In light of the statute’s required consideration of “public health issues,” which are not defined elsewhere in the statute, the court then examined the actual legislative purpose leading to the passage of Act 160. Id. Finding the stated legislative policy and purposes offered by Vermont for Act 160 to be unpersuasive, the court conducted an extensive review of the act’s legislative history, including statements made by legislators and state regulators during both committee hearings and on the floor. See id. at 229-31. On the basis of this review, the court held that there was “overwhelming evidence in the legislative record that Act 160 was grounded in radiological safety concerns and the concomitant desire to empower the legislature to act on those concerns in deciding the question of Vermont Yankee’s continued opera*407tion.” Id. at 230. The court concluded that Act 160 was thus preempted on its face by the Atomic Energy Act under the standards articulated by the Supreme Court in Pacific Gas & Electric Co. v. State Energy Resources Conservation & Development Commission, 461 U.S. 190, 103 S.Ct. 1713, 75 L.Ed.2d 752 (1983) (“Pacific Gas ”).

The district court performed the same analysis of Act 74. The court reasoned that by not permitting Entergy to store spent nuclear fuel generated after March 21, 2012, in Vermont, “absent affirmative action by the General Assembly,” section 6522(c)(4) effectively “permits the General Assembly to fail to act on a pending petition to store spent fuel for radiological safety reasons, in a manner that evades review.” Entergy Nuclear, 838 F.Supp.2d at 231. The court conducted another extensive analysis of the legislative history behind Act 74, and determined that Act 74 was “enacted with radiological safety purposes in mind,” and that by “giving the General Assembly the unreviewable power to prohibit storage of fuel, and therefore to prohibit continued operation for preempted radiological safety reasons,” Act 74 was facially preempted under the Atomic Energy Act. Id. at 232-33.

As to Entergy’s preemption challenge to the PPA under the Federal Power Act, the district court considered the scope of FERC authority under the Act and the “filed-rate doctrine,” which holds that “state courts and regulatory agencies are preempted by federal law from requiring the payment of rates other than the federal filed rate.” Id. at 233-34. The district court noted that Vermont Yankee has been operating under a market-based tariff filed with FERC, which only requires that the seller of power “enter into freely negotiated contracts with purchasers,” as opposed to setting a prescribed rate. Id. at 234 (quoting Morgan Stanley Capital Grp., Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty., 554 U.S. 527, 537, 128 S.Ct. 2733, 171 L.Ed.2d 607 (2008) (emphasis in Entergy Nuclear) (internal quotation marks omitted)). The court then held that even if Entergy were to be forced to enter into a new PPA in violation of the market-based tariff, its recourse would be to have the agreement reviewed by FERC. Id. at 235. However, the court concluded that “it is not clear what preemptive effect the [Federal Power Act] has to prevent [Vermont] from refusing to consider continued operation without such an agreement,” as there would be no such agreement to review. Id. The court thus declined to enjoin the defendants on the basis of Entergy’s Federal Power Act claim.

Lastly, the district court found merit in Entergy’s claim that Vermont had conditioned “approval of a CPG for continued operation on the existence of a power purchase agreement at below-wholesale market rates” in violation of the dormant Commerce Clause. Id. at 235. The court concluded that an injunction was an appropriate remedy in this case, even though no new PPA past March 21, 2012, had yet been issued, because there was “evidence of intent to condition continued operation on the demonstration of some marked ‘economic benefit,’ ... in the form of below-wholesale-market long-term power purchase agreements for Vermont utilities.” Id. at 236. The court made this finding by examining the materials submitted and testimony of the representatives of the Department in proceedings before the Board, as well as the statements of state legislators, to find impermissible intent on the part of the defendants. Id. at 236-39. On this basis, the court issued an injunction “enjoin[ing] Defendants from conditioning Vermont Yankee’s continued operation on the existence of a below-market PPA with Vermont utilities.” Id. at 239.

*408In sum, the district court permanently enjoined Vermont from taking any action to shut down Vermont Yankee after March 21, 2012, pursuant to Act 160 or pursuant to section 6522(c)(4) of title 10, as enacted in Act 74. Id. at 243. It also permanently enjoined Vermont from conditioning the issuance of a CPG on the execution of a favorable power purchase agreement. Id. After the district court rendered its decision, Vermont suggested in a statement dated February 22, 2012, that it still had authority over Vermont Yankee’s storage of spent nuclear fuel pursuant to section 6522(c)(2) of title 10 of the Vermont Statutes. ECF No. 192. On March 19, 2012, the district court entered an injunction enjoining Vermont from seeking to shut down Vermont Yankee on the basis of this statute as well. ECF No. 209.

Vermont appeals the district court’s determinations with respect to Entergy’s challenges to Acts 74 and 160 under the Atomic Energy Act and Entergy’s claim under the dormant Commerce Clause. Entergy cross-appeals the district court’s determination that its preemption challenge under the Federal Power Act is premature. Neither party appeals the district court’s determination that the challenge to Act 189 is moot because the safety assessments mandated by Act 189 had been completed by the time of trial.

DISCUSSION

I. Standard of Review

“We review de novo a district court’s application of preemption principles.” N.Y. SMSA Ltd. P’ship v. Town of Clarkstown, 612 F.3d 97, 103 (2d Cir.2010) (per curiam). “Findings of fact in a bench trial are reviewed for clear error; application of law to those facts is reviewed de novo.” Goodspeed Airport LLC v. E. Haddam Inland Wetlands & Watercourses Comm’n, 634 F.3d 206, 209 n. 3 (2d Cir.2011).

A district court’s grant of a permanent injunction is reviewed for abuse of discretion. ACORN v. United States, 618 F.3d 125, 133 (2d Cir.2010). “A district court abuses its discretion ‘when (1) its decision rests on an error of law (such as application of the wrong legal principle) or a clearly erroneous factual finding, or (2) its decision — though not necessarily the product of a legal error or a clearly erroneous factual finding — cannot be located within the range of permissible decisions.’ ” Id. (quoting Kickham Hanley P.C. v. Kodak Ret. Income Plan, 558 F.3d 204, 209 (2d Cir.2009)).

II. Analysis

A. Atomic Energy Act Preemption Claim

A(l). Preemption Principles

The Supremacy Clause of the United States Constitution provides that federal law “shall be the supreme Law of the Land.” U.S. Const, art. VI, cl. 2. In determining whether preemption exists, we must “start with the assumption that the historic police powers of the States were not to be superseded by the Federal Act unless that was the clear and manifest purpose of Congress.” Wyeth v. Levine, 555 U.S. 555, 565, 129 S.Ct. 1187, 173 L.Ed.2d 51 (2009) (internal quotation marks omitted). “This assumption provides assurance that the federal-state balance will not be disturbed unintentionally by Congress or unnecessarily by the courts.” Jones v. Rath Packing Co., 430 U.S. 519, 525, 97 S.Ct. 1305, 51 L.Ed.2d 604 (1977) (internal citation and quotation marks omitted). “[0]ur task is to ascertain Congress’ intent in enacting the federal statute at issue.” Shaw v. Delta Air Lines, Inc., 463 U.S. 85, 95, 103 S.Ct. 2890, *40977 L.Ed.2d 490 (1983). “The purpose of Congress is the ultimate touchstone.” Allis-Chalmers Corp. v. Lueck, 471 U.S. 202, 208, 105 S.Ct. 1904, 85 L.Ed.2d 206 (1985) (internal quotation marks omitted).

There are several forms of preemption. “The most obvious is where Congress expressly states that it is preempting state authority.” Cnty. of Suffolk v. Long Island Lighting Co., 728 F.2d 52, 57 (2d Cir.1984) (citing Jones, 430 U.S. at 525, 97 S.Ct. 1305). Preemption may also occur “where compliance with both federal and state regulations is a physical impossibility,” Fla. Lime & Avocado Growers, Inc. v. Paul, 373 U.S. 132, 142-43, 83 S.Ct. 1210, 10 L.Ed.2d 248 (1963), or where state law impedes the “execution of the full purposes and objectives of Congress.” Hines v. Davidowitz, 312 U.S. 52, 67, 61 S.Ct. 399, 85 L.Ed. 581 (1941). In the absence of such explicit or functionally overt preemption, “Congress’ intent to supersede state law may be found from ‘a scheme of federal regulation ... so pervasive as to make reasonable the inference that Congress left no room for the States to supplement it.’ ” Cnty. of Suffolk, 728 F.2d at 57 (quoting Rice v. Santa Fe Elevator Corp., 331 U.S. 218, 230, 67 S.Ct. 1146, 91 L.Ed. 1447 (1947)). In this latter context, “federal law occupies an entire field of regulation.” Wachovia Bank, N.A. v. Burke, 414 F.3d 305, 313 (2d Cir.2005).

A(2). The Atomic Energy Act and Pacifíc Gas

The domestic nuclear power industry had its genesis in the Atomic Energy Act of 1946, in which Congress “contemplated that the development of nuclear power would be a Government monopoly.” Duke Power Co. v. Carolina Envtl. Study Grp., Inc., 438 U.S. 59, 63, 98 S.Ct. 2620, 57 L.Ed.2d 595 (1978). This view changed with the passage of the Atomic Energy Act of 1954, 42 U.S.C. §§ 2011-2281, which “stemmed from Congress’ belief that the national interest would be served if the Government encouraged the private sector to develop atomic energy for peaceful purposes under a program of federal regulation and licensing.” English v. Gen. Electric Co., 496 U.S. 72, 80-81, 110 S.Ct. 2270, 110 L.Ed.2d 65 (1990). “The Act implemented this policy decision by providing for licensing of private construction, ownership, and operation of commercial nuclear power reactors.” Pacific Gas, 461 U.S. at 207, 103 S.Ct. 1713. The Atomic Energy Commission, the predecessor to the present-day NRC, “was given exclusive jurisdiction to license the transfer, delivery, receipt, acquisition, possession and use of nuclear materials. Upon these subjects, no role was. left for the states.” Id. (internal citations omitted). “Congress’ decision to prohibit the states from regulating the safety aspects of nuclear development was premised on its belief that the [Atomic Energy] Commission was more qualified to determine what type of safety standards should be enacted in this complex area.” Silkwood v. Kerr-McGee Corp., 464 U.S. 238, 250, 104 S.Ct. 615, 78 L.Ed.2d 443 (1984). Indeed, the congressional findings supporting the Atomic Energy Act affirm that the “processing and utilization of source, byproduct, and special nuclear material must be regulated in the national interest,” and that the regulation of such materials “by the United States ... is necessary in the national interest to assure the common defense and security and to protect the health and safety of the public.” 42 U.S.C. § 2012(c)-(e). Radiological safety therefore represents an arena of field preemption that “Congress, acting within its proper authority, has determined must be regulated by its exclusive governance,” thus precluding any regulation by the states. Arizona v. United States, — U.S. -, 132 S.Ct. 2492, 2501, 183 *410L.Ed.2d 351 (2012); see also Skull Valley Band of Goshute Indians v. Nielson, 376 F.3d 1223, 1242 (10th Cir.2004) (“[S]tate laws within ‘the entire field of nuclear safety concerns’ are preempted, even if they do not directly conflict with federal law.” (quoting Pacific Gas, 461 U.S. at 212, 103 S.Ct. 1713)).

Nonetheless, “[t]here is little doubt that under the' Atomic Energy Act of 1954, state public utility commissions or similar bodies are empowered to make the initial decision regarding the need for power.” Vt. Yankee Nuclear Power Corp. v. Natural Res. Def. Council, Inc., 435 U.S. 519, 550, 98 S.Ct. 1197, 55 L.Ed.2d 460 (1978). The Atomic Energy Act also contains two savings clauses reserving certain regulatory powers not related to nuclear safety to the states. The first clause states that the Atomic Energy Act does not limit state authority regarding regulation of the “generation, sale, or transmission of electric power produced through the use of nuclear facilities licensed by the Commission.” 42 U.S.C. § 2018. The second clause provides that the Atomic Energy Act shall not “be construed to affect the authority of any State or local agency to regulate activities for purposes other than protection against radiation hazards.” Id. § 2021(k).

It was against this background that the Supreme Court issued its 1983 decision in Pacific Gas, which concerned whether the Atomic Energy Act preempted a California state statute, the Warren-Alquist State Energy Resources Conservation and Development Act (the “Warren-Alquist Act”). 461 U.S. at 197, 103 S.Ct. 1713. Under thef Warren-Alquist Act, a utility seeking to build' a new nuclear power plant in California was first required to obtain permission from the California State Energy Resources and Conservation Commission (the “State Energy Commission”). Id. Section 25524.2 of the Warren-Alquist Act imposed a moratorium on the construction of new power plants until the State Energy Commission determined that a viable long-term spent nuclear fuel disposal method had been developed. Id. at 197-98, 103 S.Ct. 1713. The State Energy Commission was also required to report this determination to the California Legislature, which could override it. Id. at 198, 103 S.Ct. 1713. The Supreme Court noted that laws similar to the Warren-Alquist Act had been enacted in response to two emerging societal concerns about nuclear waste management:

[FJirst, if not properly stored, nuclear wastes might leak and endanger both the environment and human health; second, the lack of a long-term disposal option increases the risk that the insufficiency of interim storage space for spent fuel will lead to reactor-shutdowns, rendering nuclear energy an unpredictable and uneconomical adventure.

Id. at 196-97,103 S.Ct. 1713.16

The Court then considered whether the Warren-Alquist Act was preempted because “it regulates construction of nuclear plants and because it is allegedly predicated on safety concerns.” Id. at 204, 103 S.Ct. 1713. The Court reviewed the legislative history of the Atomic Energy Act *411and concluded that while the “federal government maintains complete control of the safety and ‘nuclear’ aspects of energy generation,” “the states exercise their traditional authority over the need for additional generating capacity, the type of generating facilities to be licensed, land use, ratemaking, and the like.” Id. at 211-12, 103 S.Ct. 1713. Examples of sole federal authority include the “construction and operation of any production or utiliza-, tion facility,” and the disposal of “byproduct, source or special nuclear material ... because of the hazards or potential hazards thereof.” Id. at 209, 103 S.Ct. 1713 (quoting 42 U.S.C. § 2021(c)). However, states retain authority over “the economic question [of] whether a particular plant should be built”; indeed, “utility financial qualifications are only of concern to the NRC if related to public health and safety.” Id. at 207, 103 S.Ct. 1713. Examples of exclusive state authority therefore include “ratemaking and plant-need questions.” Id. at 208, 103 S.Ct. 1713.

The Court then examined the purposes underlying section 25524.2, emphasizing that a state statute that seeks to “regulate the construction or operation of a nuclear powerplant ... even if enacted out of non-safety concerns, would nevertheless directly conflict with the NRC’s exclusive authority over plant construction and operation.” Id. at 212, 103 S.Ct. 1713. The Court focused on the state legislative committee report that accompanied section 25524.2, which articulated a purely economic rationale for the bill. The’ committee report noted that in the absence of “a federally approved method of waste disposal,” a “ ‘clog’ in the nuclear fuel cycle” would emerge because “[s]torage space was limited while more nuclear wastes were continuously produced.” Id. at 213, 103 S.Ct. 1713. This scenario could lead to “unpredietably high costs to contain the problem or, worse, shutdowns in reactors.” Id. at 213-14, 103 S.Ct. 1713. Because section 25524.2 was “concerned not with the adequacy of the method [of spent nuclear fuel storage], but rather its existence,” the Court concluded that it was not preempted by the Atomic Energy Act. Id. at 214, 103 S.Ct. 1713 (quoting Pac. Legal Found. v. State Energy Res. Conservation & Dev. Comm’n, 659 F.2d 903, 925 (9th Cir.1981)).

A(3). The Evolution of the Wholesale Energy Market After Pacific Gas

Critical to appreciating the Supreme Court’s concern in Pacific Gas about the prospect of state responsibility for rising nuclear energy costs is an understanding of the structure of the retail energy market in the 1970s and-1980s. In that era, electric utilities were typically vertically integrated entities that sold the power they generated directly to in-state retail consumers. State regulatory agencies would focus on the “retail rates charged directly to the public.” Pub. Util. Dist. No. 1 of Snohomish Cnty. Wash. v. FERC, 471 F.3d 1053, 1062 (9th Cir.2006) (“PUD No. 1 ”), vacated on other grounds, 547 F.3d 1081 (9th Cir.2008). These state agencies would determine the rates at which power could be sold by the electric utility to ensure that such rates were reasonable. See, e.g., Consol. Edison Co. of N.Y., Inc. v. Pataki, 292 F.3d 338, 343 (2d Cir.2002). Federal agencies, on the other hand, would regulate the “wholesale rates charged among businesses involved in providing” power. PUD No. 1, 471 F.3d at 1Ó62 (internal quotation marks omitted). Nonetheless, prior to the 1980s, the dominance of retail utilities ensured that “arms-length transactions on wholesale markets were relatively few.” David B: Spence & Robert Prentice, The Transformation of American Energy Markets and the Prob*412lew, of Market Power, 53 B.C. L.Rev. 131, 146 (2012).

As a result of this market structure, “electricity generation, transmission, and distribution for a particular geographic area were generally provided by and under the control of a single regulated utility.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1363 (D.C.Cir.2004) (Roberts, J.). “Although there were some interconnections among utilities, most operated as separate, local monopolies subject to state or local regulation.” New York v. FERC, 535 U.S. 1, 5, 122 S.Ct. 1012, 152 L.Ed.2d 47 (2002). This concentration of market power meant that if a local utility’s operating costs rose — due to the expense associated with long-term storage of spent nuclear fuel, for example — then consumers would likely experience direct increases in prices as well. As a result, the Pacific Gas Court accepted California’s argument that the spent nuclear “waste disposal problem was largely economic or the result of poor planning, not safety related.” Pacific Gas, 461 U.S. at 213, 103 S.Ct. 1713 (internal quotation marks omitted).17

The national marketplace for power began to evolve in the late 1970s. First, Congress passed the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. §§ 2601 et seq., which sought “to promote the development of new generating facilities and to conserve the use of fossil fuels.” New York, 535 U.S. at 9, 122 S.Ct. 1012. To do so, PURPA “directed FERC to promulgate rules requiring utilities to purchase electricity from ‘qualifying cogeneration and small power production facilities.’ ” Id. (quoting FERC v. Mississippi, 456 U.S. 742, 751, 102 S.Ct. 2126, 72 L.Ed.2d 532 (1982)). Even more significant, Congress enacted the Energy Policy Act of 1992, which “authorized FERC to order individual utilities to provide transmission services to unaffiliated wholesale generators (ie., to ‘wheel’ power) on a case-by-case basis.” Id. (citing 16 U.S.C. §§ 824j-824k). FERC exercised this authority in 1996 by promulgating Orders 888 and 889, which require “all public utilities owning and/or controlling transmission facilities to offer non-discriminatory open access transmission service.” Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667, 682 (D.C.Cir.2000) (per curiam), aff'd sub nom., New York, 535 U.S. 1, 122 S.Ct. 1012.18

By the late 1990s, the structure of the power industry had changed dramatically. Many integrated utilities had divested their generating assets, and new participants entered the market “in the form of both independent and affiliated power marketers and generators as well as independent power exchanges.” Regional Transmission Organizations, Order No. 2000, 89 F.E.R.C. ¶ 61,285, at *7 (Dec. 20, 1999). Many formerly retail utilities became independent “merchant generators,” selling the power they generated wholesale across state lines. The emergence of merchant generators placed a significant strain on existing power grids. In response, FERC sought to organize owners of trans*413mission lines into “independent system operators” (ISOs) and “regional transmission organizations” (RTOs) “to help manage the grid, ensure system reliability, and guard against discrimination and the exercise of market power in the provision of transmission services.” Spence & Prentice, supra, at 148. These ISOs and RTOs gave rise to several large regional electricity trading hubs, including the California ISO, the Pennsylvania-New Jersey-Maryland (PJM) ISO, the New York ISO, the Electric Reliability Council of Texas (ERCOT) ISO, and ISO New England.19

The development of merchant generators had two effects on the marketplace for power that are relevant here. First, consumers gained access to new sources of power, which meant that they were no longer captive to a single in-state provider. See Transmission Access, 225 F.3d at 683. Correspondingly, “[l]ocal energy utilities, could, rather than producing their own power to sell to the public, choose between various competing producers and then transfer the expected savings from this competition to the public.” PUD No. 1, 471 F.3d at 1065. The development of large regional power grids gave consumers access to power generated by out-of-state merchant generators. As the Supreme Court has noted, it is now “possible for a customer in Vermont [to] purchase electricity from an environmentally friendly power producer in California or a cogeneration facility in Oklahoma.” New York, 535 U.S. at 8, 122 S.Ct. 1012 (internal quotation marks omitted). Indeed, Vermont Yankee presently supplies only one-third of the power consumed by Vermont residents; the rest is purchased by Vermont electrical companies from other sources. See In re Entergy Nuclear Vt. Yankee, LLC, 2006 WL 1418626, at *12. Second, because states may obtain power from energy plants located in other states, there is less public support for continued operation of in-state nuclear power plants and greater opposition to such local plants on safety as well as non-safety grounds.20

With the advent of merchant generators, the challenge of identifying a long-term spent nuclear fuel storage solution has grown even more pressing. After a useful life of four-to-six years, spent nuclear fuel rods are thermally hot when removed from reactors and emit substantial amounts of radiation. New York v. NRC, 681 F.3d 471, 474 (D.C.Cir.2012) (citing Blue Ribbon Commission on America’s Nuclear Future, Report to the Secretary of Energy 10-11 (2012)). The rods are transferred to deep, water-filled pools for cooling; they may then be transferred to large concrete and steel “casks” for storage, even though they will continue to emit dangerous radiation “for time spans seemingly beyond human comprehension.” Id. (quoting Nuclear Energy Inst., Inc. v. EPA, 373 F.3d 1251, 1258 (D.C.Cir.2004) (per curiam)). Nonetheless, despite the continued production of nuclear waste, and despite “years of ‘blue ribbon’ commissions, congressional *414hearings, agency reports, and site investigations, the United States has not yet developed a permanent solution.” Id. Most recently, plans to develop a federally-sponsored storage site at Yucca Mountain in Nevada were abandoned when the Department of Energy withdrew its license application for the facility. See Nat'l Ass’n of Regulatory Util. Comm’rs v. U.S. Dep’t of Energy, 680 F.3d 819, 822-23 (D.C.Cir.2012). “At this time, there is not even a prospective site for a repository, let alone progress toward the actual construction of one.” New York v. NRC, 681 F.3d at 474.

A(4). Act 160

With this general background in mind, we begin our preemption analysis of Act 160, the most recent of Vermont’s legislative enactments at issue.21 The proper place to begin the analysis of a statute is its text. See, e.g., United States v. Am. Trucking Ass’ns, 310 U.S. 534, 543, 60 S.Ct. 1059, 84 L.Ed. 1345 (1940) (“There is, of course, no more persuasive evidence of the purpose of a statute than the words by which the legislature undertook to give expression to its wishes.”). As described previously, Act 160 adds three new sections to the Vermont Statutes: sections 248(e)(2), 248(m), and 254 of title 30. Section 248(e)(2) requires the Vermont Legislature to determine whether an extension of the Vermont Yankee operating lease should be granted (that is, to determine whether the lease advances the “general welfare”) before the Board can issue a new CPG. Vt. Stat. Ann. tit. 30, § 248(e)(2). Section 248(m) requires that the evaluation of a new CPG be conducted using current cost-benefit assumptions, rather than those that informed the issuance of the previous CPG. Id. § 248(m). Section 254 requires that an application to operate Vermont Yankee past March 21, 2012, be submitted at least four years in advance, and that the Department engage in extensive fact-finding to support the legislative determination that the lease advances the general welfare. Id. § 254(a). The statute requires that the Department “identify, collect information on, and provide analysis of long-term environmental, economic, and public health issues, including issues relating to dry cask storage of nuclear waste and decommissioning options.” Id. § 254(b)(2)(B) (emphasis added). These are factors that the Board “shall consider” in “acting on a petition” subject to the statute, id. § 254(b)-(c), and the Board’s conclusions are reported to the Vermont Legislature to inform its own determination regarding the status of Vermont Yankee, id. § 254(a)(2)-(3).

As an initial matter, we must consider whether it is appropriate to consider a facial challenge to Act 160. In this regard, we find it important that Act 160, through the operation of section 248(e)(2), transfers the process for determining whether to approve a new operating license for Vermont Yankee from the Board to the Vermont Legislature. Before the passage of Act 160, the Board’s decision *415regarding whether to approve the continued operation of Vermont Yankee would have been subject to review by the Vermont Supreme Court. Vt. Stat. Ann. tit. 30, § 12. Such a review likely would have encompassed legal questions regarding whether Act 160 was preempted by federal law. See, e.g., Petition of E. Ga. Cogeneration Ltd. P’ship, 614 A.2d 799, 804-05 (Vt.1992). After the passage of Act 160, if the Vermont Legislature chose not to act, the operating license for Vermont Yankee would lapse on March 21, 2012, and that decision would not be subject to judicial review. See Bd. of Educ. of Kiryas Joel Vill. Sch. Dist. v. Grumet, 512 U.S. 687, 703, 114 S.Ct. 2481, 129 L.Ed.2d 546 (1994) (“[Ujnlike an administrative agency’s denial of an exemption from a generally applicable law, which would be entitled to a judicial audience, a legislature’s failure to enact a special law is itself unreviewable.” (internal citations and quotation marks omitted)).

Because a “state moratorium” on the operation of Vermont Yankee “grounded in safety concerns falls squarely within the prohibited field,” Pacific Gas, 461 U.S. at 213, 103 S.Ct. 1713, a law enacted for that purpose would facially lack any “plainly legitimate sweep.” Wash. State Grange v. Wash. State Republican Party, 552 U.S. 442, 449, 128 S.Ct. 1184, 170 L.Ed.2d 151 (2008) (internal quotation marks omitted). We also note several other reasons why it is appropriate to consider Entergy’s facial challenge to the validity of Act 160. First, because of the extensive legislative record accompanying Act 160 and the detailed inquiry conducted by the district court below, it “is not the case ... that the Court today is premature in interpreting [Act 160] on the basis of a factually barebones record.’ ” Citizens United v. FEC, 558 U.S. 310, 130 S.Ct. 876, 894, 175 L.Ed.2d 753 (2010) (internal quotation marks and alterations omitted). Second, because Act 160 shifts the decision regarding whether to approve the operation of Vermont Yankee into the unreviewable province of the Vermont Legislature’s “failure to enact a special law,” Grumet, 512 U.S. at 703, 114 S.Ct. 2481, we will not otherwise have any “occasion to construe the law in the context of actual disputes.” Wash. State Grange, 552 U.S. at 450, 128 S.Ct. 1184. Lastly, we believe that “the issues before the court are concrete and sharply presented” so as to permit meaningful review. Dickerson v. Napolitano, 604 F.3d 732, 741 (2d Cir.2010) (quoting Thibodeau v. Portuondo, 486 F.3d 61, 71 (2d Cir.2007)). It is therefore “necessary to determine whether there is a non-safety rationale” for Act 160 by considering whether the decision to effectively shut down Vermont Yankee serves the policy interests articulated in the statute. Pacific Gas, 461 U.S. at 213,103 S.Ct. 1713.

The legislative policy and purpose section of Act 160 sets forth several rationales for the statute. Section 1(a) states that “a nuclear energy generating plant may be operated in Vermont only with the explicit approval of the General Assembly expressed in law,” and that legislative approval requires a “public deliberation” of such factors as “the state’s need for power, the economics and environmental impacts of long-term storage of nuclear waste, and choice of power sources among various alternatives.” Act 160 § 1(a). The statute later states that the issue of long-term spent fuel storage should be framed as

a part of the larger societal discussion of broader economic and environmental issues relating to the operation of a nuclear facility in the state, including an assessment of the potential need for the operation of the facility and its economic benefits, risks, and costs; and in order to allow opportunity to assess alternatives that may be more cost-effective or *416that otherwise may better promote the general welfare.

Id. § 1(d). Drawing on the language in sections 1(a) and 1(d), Vermont argues that Act 160 advances two policy interests: (1) increased use of a diverse array of renewable power sources; and (2) promotion of energy sources that are more cost-effective.

Although Vermont’s asserted policy interests would not necessarily interfere with the preempted concern of radiological safety, our inquiry does not end at the text of the statute.

We do not blindly accept the articulated purpose of [a state statute] for preemption purposes. If that were the rule, legislatures could “nullify nearly all unwanted federal legislation by simply publishing a legislative committee report articulating some state interest or policy — other than frustration of the federal objective — that would be tangentially furthered by the proposed state law.”

Greater N.Y. Metro. Food Council, Inc. v. Giuliani, 195 F.3d 100, 108 (2d Cir.1999) (quoting Gade v. Nat’l Solid Wastes Mgmt. Ass’n, 505 U.S. 88, 106, 112 S.Ct. 2374, 120 L.Ed.2d 73 (1992)) (internal citation omitted), abrogated on other grounds by Lorillard Tobacco Co. v. Reilly, 533 U.S. 525, 121 S.Ct. 2404, 150 L.Ed.2d 532 (2001). As a result, “we have refused to rely solely on the legislature’s professed purpose and have looked as well to the effects of the law.” Gade, 505 U.S. at 105, 112 S.Ct. 2374; see also Vango Media, Inc. v. City of N.Y., 34 F.3d 68, 73 (2d Cir.1994) (“[T]he question of preemption is defined, in part, by the purpose of the state law, and, in part, by the state law’s actual effect. Both must be considered in answering the question whether state regulation in a given field so interferes with federal regulation as to be deemed preempted by the federal statute.” (citing Gade, 505 U.S. at 103-06, 112 S.Ct. 2374) (internal citations omitted)).22 Although the Pacific Gas Court did not explicitly delineate the level of scrutiny a court must perform to determine whether a statute is preempted by the Atomic Energy Act, we believe the Court’s admonition against a “state judgment that nuclear power is not safe enough to be further developed,” 461 U.S. at 213, 103 S.Ct. 1713, requires us to conduct a more searching review to determine whether a statute was enacted based upon radiological safety concerns. See also Cnty. of Suffolk, 728 F.2d at 58 (“[A] state, in evaluating the need for a nuclear generating facility, [can] not even consider the safety aspects.” (citing Pacific Gas, 461 U.S. at 213, 103 S.Ct. 1713)). We therefore decline Vermont’s invitation to apply an analytic framework akin to “rational basis review,” which would preclude us from identifying the true purpose of a statute as required by Pacific Gas and would allow states to implement a “moratorium on nuclear construction grounded in safety concerns [that] falls squarely within the prohibited field.” Pacific Gas, 461 U.S. at 213,103 S.Ct. 1713.23

*417As to the goal of diversifying the State’s means of producing power, Vermont argues that the presence of Vermont Yankee “hamper[s] efforts at diversification and has a dampening effect on the development of alternatives.” Citing the testimony of the State’s former Director of Regulated Utility Planning, Vermont argues that closing Vermont Yankee “would free up space in the electrical generation market and make it easier to promote diversity and sustainable resources.” Vermont also quotes a former Maine state power regulator and NRC commissioner, who testified before the district court that the State has a “legitimate interest in energy planning and promoting renewables” and argued that “any sensible energy planner would be anticipating a time when Vermont would be without Vermont Yankee.”

However, this argument presupposes that Vermont retail utilities lack choices with respect to the sources of the energy they purchase. “[S]tates have broad powers under state law to direct the planning and resource decisions of utilities under their jurisdiction. States may, for example, order utilities to build renewable generators themselves, or ... order utilities to purchase renewable generation.” S. Cal. Edison Co. San Diego Gas & Elec. Co., 71 FERC ¶ 61,269, at *8 (June 2, 1995). Vermont Yankee provides only one third of the power consumed in the State, so it is clear that the Vermont Legislature can direct retail utilities to “purchase electricity from an environmentally friendly power producer in • California or a cogeneration facility in Oklahoma,” if it so chooses. New York, 535 U.S. at 8, 122 S.Ct. 1012 (internal quotation marks omitted). Vermont can also direct or encourage its utilities to purchase power from nuclear power plants located out-of-state. Indeed, Vermont recently pursued this exact approach by approving a petition to allow its retail utilities to purchase power from the Sea-brook Station Nuclear Power Plant in New Hampshire, a merchant generator like Vermont Yankee. In re Green Mountain Power Corp., Docket No. 7742, 2011 WL 5507224, at *1 (Vt.Pub.Serv.Bd. Nov. 4, 2011). Closing Vermont Yankee would thus have little effect on the actual array of energy sources from which Vermont utilities can purchase power.24

As to the second goal of containing costs, Vermont argues that the economic rationale relied on by the Pacific Gas Court applies with equal force here. Vermont suggests that shutting down Vermont Yankee might assist the State in identifying “alternatives that may be more cost-effective.” However, this argument is also not persuasive in light of Vermont Yankee’s status as a merchant generator. Increases in the prices Vermont Yankee charges for its power would not be borne directly by a captive audience of retail consumers, as was the case for California residents in Pacific Gas. Instead, Vermont *418Yankee is “a merchant generator, which means that it sells power on the open wholesale market.” Envtl. Law & Policy Ctr. v. NRC, 470 F.3d 676, 679 (7th Cir.2006). For that reason, local energy utilities could simply “choose between various competing producers” and purchase power from the more cost-effective provider. See PUD No. 1, 471 F.3d at 1065. Closing Vermont Yankee would not affect the availability of other sources of power from which local retail utilities could purchase power that might be more “cost-effective;” indeed, they are free to do so now.25

Vermont’s second economic argument regarding the State’s potential future liability for decommissioning costs is also of little weight. Vermont contends that the recent collapse of the plan to construct a long-term spent nuclear fuel storage facility in Yucca Mountain means that “[i]f plant operators such as Entergy become insolvent or abandon their obligations, the financial burdens will fall on host states.” However, “[i]n 1988, the Nuclear Regulatory Commission adopted a final rule requiring operators of nuclear facilities to file decommissioning plans, and to pre-fund decommissioning by placing money aside in an external sinking fund.” Neb. Pub. Power Dist. v. MidAmerican Energy Co., 234 F.3d 1032, 1037 (8th Cir.2000) (citing Nuclear Regulatory Commission Final Rule, General Requirements for Decommissioning Nuclear Facilities, 53 Fed.Reg. 24018-01 (June 27, 1988) (codified at 10 C.F.R. § 50.82)). “By regulation, decommissioning funds may not be used for non-decommissioning related expenses, such as [spent nuclear fuel] storage.” Bos. Edison Co. v. United States, 93 Fed.Cl. 105, 136 (2010), rev’d on other grounds, 658 F.3d 1361 (Fed.Cir.2011). Nuclear power plants must provide periodic reports to the NRC concerning the status of such funds for the purpose of providing “reasonable assurance that funds will be available for the decommissioning process.” 10 C.F.R. § 50.75(a).26

We must also look to the statute’s legislative history to determine if it was passed with an impermissible motive. Vermont argues that Pacific Gas forecloses the use of legislative history to analyze a state statute for Atomic Energy Act preemption, noting the Court’s dictum describing “inquiry into legislative motive [as] often an unsatisfactory venture.” 461 U.S. at 216, 103 S.Ct. 1713. In analyzing the purpose of the Warren-Alquist Act, *419however, the Court looked to a report issued by the state legislative committee that presented the bill. Id. at 214, 103 S.Ct. 1713. Moreover, in a subsequent decision, the Court interpreted Pacific Gas to hold that a “state moratorium on nuclear construction grounded in safety concerns falls squarely within the prohibited field.” English, 496 U.S. at 84, 110 S.Ct. 2270 (quoting Pacific Gas, 461 U.S. at 213, 103 S.Ct. 1713). “In other words, the Court defined the preempted field, in part, by reference to the motivation behind the state law.” Id. (emphasis added); see also Gade, 505 U.S. at 105-06, 112 S.Ct. 2374 (“We can no longer adhere to the aberrational doctrine ... that state law may frustrate the operation of federal law as long as the state legislature in passing its law had some purpose in mind other than one of frustration [of the federal regulatory scheme].” (quoting Perez v. Campbell, 402 U.S. 637, 651-52, 91 S.Ct. 1704, 29 L.Ed.2d 233 (1971)) (emphasis added)). Indeed, several other courts applying Pacific Gas have endorsed the use of legislative history to determine whether the Atomic Energy Act preempts a particular state statute or local ordinance. See, e.g., Skull Valley, 376 F.3d at 1251-53; Long Island Lighting Co. v. Cnty. of Suffolk, N.Y., 628 F.Supp. 654, 665-66 (E.D.N.Y.1986); see also Loyal Tire & Auto Ctr., Inc. v. Town of Woodbury, 445 F.3d 136, 145 (2d Cir.2006) (Sotomayor, J.) (holding, in the context of Interstate Commerce Act preemption, that a court “must consider any specific expressions of legislative intent in the statute itself as well as the legislative history”); Greater N.Y. Metro., 195 F.3d at 108 & n. 1 (examining legislative history to determine whether a New York City local law was preempted by the Federal Cigarette Labeling and Advertising Act). We therefore believe that legislative history is an important source for determining whether a particular statute was motivated by an impermissible motive in the preemption context.27

Vermont argues that the task of determining the legislative intent behind Act 160 is particularly difficult in this case because the Vermont Legislature, as a “part-time citizen body, does not produce formal committee reports like those Congress prepares, and it has no requirement to preserve complete records of its proceedings.” In addition, “[e]ommittee hearings are generally recorded, but are not contemporaneously transcribed, and often do not identify the speaker. Floor debates are usually recorded in the Senate, but not in the House of Representatives.” For this reason, Vermont argues that much of the legislative history behind Act 160 is “missing or incomplete.”

*420Acknowledging these conditions does not change the fact that a “court’s primary purpose in statutory interpretation is to discern legislative intent.” Morgan v. Gay, 466 F.3d 276, 277 (3d Cir.2006).28 Although the lack of systemized record-keeping may make our task more challenging, the informality of the proceedings of the Vermont Legislature and the State’s decision to not document its legislative history do not immunize Act 160 from judicial inquiry into legislative motivation. Cf. Blanton v. City of Murfreesboro, 856 F.2d 731, 734 (6th Cir.1988) (“While we recognize today that the use of legislative history, much of which is not recorded until after the final congressional action, in trying to understand the intent of Congress, is not as meaningful as it once was, we find ourselves with no other means of determining the intent of Congress in enacting this legislation.”).

We agree with the district court’s careful analysis of the legislative intent motivating Vermont’s enactment of Act 160 insofar as the district court identified radiological safety as the Vermont legislature’s primary purpose in enacting the statute.29 The district court concluded that the legislative record contained “references, almost too numerous to count, [that] reveal legislators’ radiological safety motivations and reflect their wish to empower the legislature to address their constituents’ fear of radiological risk, and [the legislators’] beliefs that the plant was too unsafe to operate, in deciding a petition for continued operation.” Entergy Nuclear, 838 F.Supp.2d at 229. We need not repeat the entirety of the district court’s examination, which included considering many hours of audiotapes of floor debates and committee meetings for which written transcriptions are not typically maintained, except to note the remarkable consistency with which both state legislators and regulators expressed concern about radiological safety and expressed a desire to evade federal preemption. See Disabled in Action of Metro. N.Y. v. Hammons, 202 F.3d 110, 124 (2d Cir.2000) (noting that the “sponsor/floor manager statement and floor and hearing colloquy” are among “the most authoritative and reliable materials of legislative history”).

The Vermont Senate Finance Committee conducted its first hearings on the bill that would ultimately become Act 160 only days after Entergy filed its application with the NRC for an extension of its operating license for Vermont Yankee past 2012. During those first hearings, the committee chair and the chairman of the Board engaged in an extended colloquy regarding the permissible legislative purposes for the bill, with particular emphasis on Pacific Gas and its roadmap for appropriate state legislative regulation of nuclear facilities. After being informed that regulation based on radiological safety was preempted and impermissible, the committee chair responded, “Okay, let’s find another word for safety,” an approach also *421adopted by the Board chairman. A state legislator participating in the hearing responded to testimony from a law professor regarding the permissible scope of the bill by stating, “I understand that only the feds are allowed to think of safety issues, and we carefully don’t use that word here.” Another member of the Finance Committee expressed concern that “all of our work [will] get overturned ... by the feds because it’s based on safety? That’s all it’s going to be based on.” A third member of the committee asserted that the federal government likely would not be able to transport Vermont Yankee’s spent nuclear fuel out of the state, and then asked rhetorically, “[D]o we want another 40 years’ worth of radioactive materials sitting somewhere in this State? I think the people ... are getting a little concerned and obviously the closer you live to that radioactivity, the more concerned you are.” That same senator also referenced the incidents at Three Mile Island and Chernobyl, and stated that the potential for a similar disaster was sufficiently serious that “the legislature felt [that the bill presented] a public policy decision that they needed to make.” The Committee also considered testimony from the Vermont Legislature’s Chief Legislative Counsel and a Department representative concerning ways of writing the bill so as to avoid overt references to radiological safety.

The record also indicates that during hearings on the bill that would become Act 160, members of the Department, regulators, and Vermont legislators repeatedly demonstrated awareness of the potential for a preemption problem and disguised their comments accordingly. For example, during a hearing of the Senate Finance Committee on the bill that would become Act 160, a member of the Vermont State Nuclear Advisory Panel told the committee chair that the Board “is not allowed to think about safety, as you know,” but then proceeded to opine on various safety risks. The committee chair then admonished the panel member to speak purely about “economic risks,” which led that individual to suggest that “a safety problem has economic implications, too.” The committee also heard testimony from a professor at a local law school and former chairman of the Board, who warned the committee that because “the State is preempted in its concerns about radiological safety,” the “State has to make its decision on other grounds, which would include anything from aesthetics to the obvious ones about financial implication to such things as reliability of the electric grid.” During a subsequent exchange, the current chairman of the Board instructed the committee on whether and in what circumstances it could “talk about public health.” A member of the Department then recommended that “some alternative language be placed into the bill” so as to avoid the issues referenced by the chairman of the Board. These are not merely isolated comments by a few legislators, but rather a part of a consistent effort by those responsible for drafting and passing Act 160 to obfuscate the record through the use of misleading statements that they thought would pass muster under Pacific Gas. We conclude that the district court carefully, fairly, and properly analyzed the legislative intent undergirding Act 160 and found that it demonstrated an impermissible primary purpose on the part of the Vermont Legislature.30

*422In concluding that the Vermont Legislature was improperly motivated by concerns relating to radiological safety in enacting Act 160, we recognize that many legislators, were likely acting with some non-preempted concerns in mind as well. “What motivates one legislator to vote for a statute is not necessarily what motivates scores of others to enact it.” Pacific Gas, 461 U.S. at 216, 103 S.Ct. 1713. We also acknowledge that the mere transfer of authority from a state administrative board to the legislature does not require a finding of preemption. We further recognize that the extent to which a state legislature’s permissible concerns outweigh its impermissible motive in passing a statute is not an issue that the Pacific Gas Court elucidated with great clarity. Compare id. at 213, 103 S.Ct. 1713 (“A state prohibition on nuclear construction for safety reasons would also be in the teeth of the Atomic Energy Act’s objective to insure that nuclear technology be safe enough for widespread development and use — and would be preempted for that reason.” (emphasis added)), with id. (“[I]t is necessary to determine whether there is a non-safety rationale for [the Warren-Alquist Act].” (emphasis added)). Nonetheless, our task is not “[t]o look for the sole purpose ” of the Vermont Legislature; that exercise would require us “probably to look for something that does not exist.” Edwards v. Aguillard, 482 U.S. 578, 637, 107 S.Ct. 2573, 96 L.Ed.2d 510 (1987) (Scalia, J., dissenting). Our task is to determine whether the Vermont Legislature’s decision to pass Act 160 was “grounded in [radiological] safety concerns.” Pacific Gas, 461 U.S. at 213, 103 S.Ct. 1713. A record as consistent and replete with references to radiological safety as that here meets any conceivable standard for the allowable threshold level of impermissible concerns under Pacific Gas. As such, we affirm the district court’s determination that Act 160 is preempted on its face by the Atomic Energy Act.

We likewise affirm the district court’s grant of a permanent injunction enjoining the defendants from enforcing Act 160. A plaintiff seeking a permanent injunction must demonstrate:

(1) that it has suffered an irreparable injury; (2) that remedies available at law, such as monetary damages, are inadequate to compensate for that injury; (3) that, considering the balance of hardships between the plaintiff and defendant, a remedy in equity is warranted; and (4) that the public interest would not be disserved by a permanent injunction.

*423Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 130 S.Ct. 2743, 2756, 177 L.Ed.2d 461 (2010) (quoting eBay, Inc. v. MercExchange, L.L.C., 547 U.S. 388, 391, 126 S.Ct. 1837, 164 L.Ed.2d 641 (2006)). Each of these four factors is clearly satisfied here. First, Entergy would suffer an irreparable injury if the defendants were able to enforce Act 160 and shut down Vermont Yankee. See Tom Doherty Assocs., Inc. v. Saban Entm’t, Inc., 60 F.3d 27, 37 (2d Cir.1995) (finding irreparable harm in part because “the right to continue a business ‘is not measurable entirely in monetary terms’ ” (quoting Semmes Motors, Inc. v. Ford Motor Co., 429 F.2d 1197, 1205 (2d Cir.1970))). Second, Entergy would be unable to recover monetary damages from Vermont because of the Eleventh Amendment. See United States v. State of N.Y., 708 F.2d 92, 93 (2d Cir.1983) (per curiam). Third, the balance of hardships favors Entergy because it would suffer irreparable losses from Vermont Yankee being shut down while Act 160 would not meaningfully advance the rationales offered by Vermont. Lastly, the public interest would not be disserved by a permanent injunction, because Vermont would be able to continue purchasing the power generated by Vermont Yankee while still diversifying its energy base and purchasing power from more cost-effective sources if it so chooses. The district court thus did not abuse its discretion in granting the permanent injunction enjoining the defendants from enforcing Act 160.

A(5). Act 74

As with Act 160, our analysis of Act 74 begins with the text of the statute. Act 74 adds three sections to title 10 of the Vermont statutes: sections 6521, 6522, and 6523. As discussed above, section 6521 summarizes the stated legislative findings. Vt. Stat. Ann. tit. 10, § 6521. Section 6522 requires that the Board make certain findings before issuing a CPG allowing an expansion of the spent nuclear fuel storage facility beyond the capacity previously authorized, and for any such expansion after the expiration of the CPG on March 21, 2012, the affirmative approval of the Vermont Legislature is required. Id. § 6522(c)(2), (c)(4). Section 6523 establishes a “Clean Energy Development Fund” into which, pursuant to the 2003 MOU entered into between Entergy and the Department, Entergy would make payments for the purpose of promoting “cost-effective and environmentally sustainable” power for the “long-term benefit of Vermont electric consumers.” Id. § 6523 (current version at Vt. Stat. Ann. tit. 30, § 8015).

Act 74 also incorporates the 2005 MOU, which imposes on Entergy a variety of requirements related to radiological safety. These requirements include rules regarding the placement and configuration of dry-fuel-storage facilities that exceed the licensing standards required by the NRC; the spacing of casks; temperature and radiation monitoring with concomitant reporting requirements to the Department; and the density of spent-fuel pools. 2005 MOU at 1-2. The 2005 MOU also prohibits the storage of waste generated outside Vermont on site, and requires Entergy to use its best efforts to move the spent nuclear fuel generated by Vermont Yankee to a permanent location outside the state as soon as possible. Id. at 2.

Lastly, much like Act 160, section 6522 allows the Vermont Legislature to terminate the operation of Vermont Yankee after March 21, 2012, by refusing to act affirmatively. This effectively codifies the Vermont Attorney General’s opinion that section 6505, which had previously exempted Vermont Yankee from the provision requiring legislative approval of new dry cask storage facilities codified at sec*424tion 6501(a), did not apply to Entergy. As a result, the decision regarding whether to permit Entergy to build additional spent nuclear fuel storage facilities was vested in the Vermont Legislature. Unlike a decision of the Board, which would be subject to review by the Vermont Supreme Court, the Vermont Legislature’s decision not to authorize the construction of new storage facilities — even those already approved by the NRC, as in this case — would be unreviewable.

The reasons for the statute articulated in Act 74’s legislative findings section mirror many of those offered in the preamble to Act 160. For instance, section 6521 expresses the State’s goal of making its “future power supply ... diverse, reliable, economically sound, and environmentally sustainable.” Vt. Stat. Ann. tit. 10, § 6521(3). The statute also emphasizes the State’s need “to make a smooth transition to the future,” which requires accelerating ‘Vermont’s investment in electricity resources that are economically and environmentally sound and that can be acquired in modest increments.” Id. § 6521(4). To make this “transition,” the statute states, “there is a great value in investing in renewable energy sources, efficient, combined heat and power facilities, and energy efficiency.” Id. § 6521(5).

These statements of legislative purpose reflect the two policy interests Vermont argues are advanced by Act 160: (1) increased use of a diverse array of renewable power sources; and (2) promotion of energy sources that are more cost-effective. For the reasons discussed above, we believe that neither of these interests is plausibly served by Act 74’s conferring unreviewable power over the continued operation of Vermont Yankee past March 21, 2012, on the Vermont Legislature. In addition, the regulations relating to radiological safety incorporated into Act 74 from the 2005 MOU demonstrate that the Vermont Legislature’s primary motivation in enacting Act 74 relates to neither diversifying the State’s power supply nor reducing costs. We therefore turn to the legislative history behind Act 74 to determine the actual intent motivating its passage.

As with Act 160, we find that the district court’s comprehensive review of the legislative history demonstrates convincingly that Act 74 was motivated by impermissible concerns about the radiological safety of spent nuclear fuel storage. We note again the frequency with which concerns about radiological safety appear in the legislative record in Senate committee meetings and floor debates from legislators and regulators, notwithstanding obvious and frequent attempts to avoid specific mention of safety concerns and of deference to Pacific Gas. In hearings of the House Natural Resources Committee considering the bill that would become Act 74, for example, representatives asked numerous questions about the relative safety of spent nuclear fuel storage methods Entergy was considering and heard testimony questioning the competence of the NRC to evaluate safety. One witness described the legislative “problem that we’re dealing with here [is] that a lot of the concerns that citizens have are concerns that you can’t address directly the way they want them to be addressed.” Several representatives asked questions about the dangers posed by an accidental release of radioactive waste. One member of the committee admonished another for referring to radiological safety, stating, “but we can’t say that, anything about safety. It can only be about economics and aesthetics.” A member of the Department expressed the same sentiment and advised a representative to frame his questions about the value of maintaining Vermont Yankee as an “aesthetic issue,” rather than one concerned with safety. In a concluding committee meet*425ing on the bill, one representative praised the committee’s work to ensure that “the findings have been emasculated and sanitized,” noting that the bill no longer makes any “mention of high-level nuclear waste” or “the fact that [nuclear waste] lasts, it’s dangerous for 100,000 years.” During the subsequent floor debate on Act 74, one senator stated candidly, “none of us wants to have nuclear waste stored on the soil of Vermont.... The reality is that [Vermont Yankee] will require some temporary storage ... in order to [e]nsure safety for our environment.” Other speeches adverted to the problem of storing radioactive nuclear waste in Vermont while the federal government worked on developing a long-term storage facility, and to the need to ensure that the method of waste storage employed by Vermont Yankee was safe. As with our analysis of Act 160, the deficiencies in the record-keeping of Vermont legislative history, as well as the obvious coaching of Vermont legislators to avoid explicit statements about nuclear safety, make our task in determining the principal purpose of Act 74 more difficult. Nonetheless, this does not make our task less important, and the volume, frequency, and content of the legislators’ comments show clearly that their actions were motivated by preempted safety concerns.

The record also contains several statements by state legislators about the value of assigning their concerns regarding radiological safety to the 2005 MOU, which required Entergy to take several actions specifically addressing radiological safety. In re Entergy Nuclear Vt. Yankee, LLC, 2006 WL 1418626, at *48.31 During a meeting of the Senate Natural Resources Committee, for example, the State’s legislative council remarked that an earlier draft of Act 74 contained a “laundry list of [nuclear-waste] cask-related issues ... [that] are now covered by the [2005] MOU.” A member .of the Department testified that “the federal government takes jurisdiction over any radiological safety and health. And so anything that touched on that, it’s better to have in an agreed upon MOU than to have in the bill itself.” Other legislators echoed this sentiment at several other junctures. On the Senate floor, one senator stated explicitly that a favorable aspect of Act 74 was that it left regulations relating to radiological safety to the 2005 MOU entered into by Entergy and the Department, which, the senator believed, could save Act 74 from a preemption challenge.32 Indeed, the 2005 MOU endorsed by Act 74 includes a provision under which Entergy “waived” any right to bring a preemption challenge to the Board’s authority to regulate Vermont Yankee, which clearly demonstrates the concern of the Vermont Legislature and the Board as to whether their actions would withstand scrutiny under the Atomic Energy Act and Pacific Gas.33

*426These statements demonstrate the Vermont Legislature’s impermissible motive in passing Act 74 — namely, to shut down Vermont Yankee based on concerns of radiological safety while attempting to avoid a preemption challenge under Pacific Gas. Vermont legislators and regulators attempted to achieve this objective by shifting provisions regarding radiological safety into the 2005 MOU and by creating an unreviewable mechanism by which the construction of new spent nuclear fuel storage facilities based on safety concerns would not be authorized. This is a legislative approach that Pacific Gas does not permit. We therefore also affirm the district court’s judgment that sections 6522(c)(2) and 6522(c)(4) of title 10 of the Vermont Statutes, as enacted by Act 74, are preempted on their face by the Atomic Energy Act. For the reasons discussed above regarding Act 160, we also affirm the district court’s grant of a permanent injunction enjoining the defendants from enforcing sections 6522(c)(2) or 6522(c)(4) of the Vermont Statutes.

In conducting this analysis of Acts 74 and 160 and their adoption, we are mindful of the traditional “presumption against preemption with respect to areas where states have historically exercised their police powers.” N.Y. SMSA Ltd. P’ship, 612 F.3d at 104. Vermont would have us conclude that Acts 74 and 160 are merely “process statutes” that simply reallocate the responsibility for approving the continued operation of Vermont Yankee from an administrative agency to the state legislature. Indeed, Justice Brandéis once observed that the “franchise to operate a public utility ... is a special privilege which ... may be granted or withheld at the pleasure of the state.” Frost v. Corp. Comm’n, 278 U.S. 515, 534, 49 S.Ct. 235, 73 L.Ed. 483 (1929) (Brandéis, J., dissenting). Vermont further contends that it enacted Acts 74 and 160 on several bases, such as diversifying the state’s power supply and controlling economic costs, that, if true, would surely be permissible reasons to deny the construction of a nuclear power plant. See Pacific Gas, 461 U.S. at 211, 103 S.Ct. 1713. However, the Supreme Court has instructed us that the regulation of nuclear power is different from the “areas where states have historically exercised their police powers.” N.Y. SMSA Ltd. P’ship, 612 F.3d at 104. “The federal government has occupied the entire field of nuclear safety concerns, except the limited powers expressly ceded to the states.” Silkwood, 464 U.S. at 249, 104 S.Ct. 615 (internal quotation marks and alteration omitted). We have conducted a review that reflects the Supreme Court’s specific directive that a “state judgment that nuclear power is not safe enough to be further developed would conflict directly with the countervailing judgment of the NRC ... and would be preempted for that reason.” Pacific Gas, 461 U.S. at 212, 103 S.Ct. 1713. We conclude that Vermont legislators and regulators have undertaken a sustained effort to shut down Vermont Yankee based on this impermissible reason.

We have considered the legislative history behind Acts 74 and 160 — undertaken in large part through the district court’s exhaustive examination of audiotape recordings — and found that it contains innumerable expressions of concern for radiological safety from Vermont legislators and regu*427lators.34 We have taken note of the fact that the Vermont Legislature began considering the bill that would become Act 160 — requiring Entergy to seek legislative approval to operate Vermont Yankee past 2012 — only one week after Entergy applied to the NRC for an extension of its operating license. We have observed that witnesses at committee meetings, legislators, executive officials, and regulators were obviously coached to avoid making references to radiological safety to navigate the shoals of Pacific Gas. We have sought to reconcile the rationales proffered by the Vermont Legislature for Acts 74 and 160 with those Acts’ operative effects and found them to be untethered from Vermont Yankee’s status as a merchant generator and from the oversight already provided by the NRC. We have noted Vermont’s efforts to evade court review by shunting requirements that concern radiological safety to MOUs, which in turn contain provisions requiring Entergy to “waive” its right to bring a preemption challenge in court. We have concluded that Vermont shifted decision-making responsibility for approving the . continued operation of Vermont Yankee from the Board, whose decisions were subject to review by the Vermont Supreme Court, to the Vermont Legislature, where no judicial review of its action — or inaction — would be available. Providing an inadequate and misleading legislative record, failing to provide plausible legislative rationales, and imposing impermissible safety-related obligations through non-statutory memoranda of understanding, do not and cannot shield Acts 74 and 160 from this Court’s review.

We do not question the legitimacy or sincerity of those Vermont residents and officials who have safety-related concerns about Vermont Yankee, but Vermont has other avenues available to air its concerns. For example, the'Atomic Energy Act mandates that the NRC hold hearings — if requested by “any person whose interest may be affected” — when taking certain actions relating to the licensing of a nuclear *428power plant. See Brodsky v. U.S. Nuclear Regulatory Comm’n, 578 F.3d 175, 177-78 (2d Cir.2009) (quoting 42 U.S.C. § 2239(a)(1)(A)). The NRC has also promulgated regulations requiring a public notice-and-comment period before amending any aspect of a nuclear power plant’s operating license. See 10 C.F.R. § 50.91. Lastly, “the federal courts of appeals have exclusive jurisdiction to adjudicate appeals from ‘all final orders of the [NRC] made reviewable by section 2239 of title 42.’” Riverkeeper, Inc. v. Collins, 359 F.3d 156, 164 (2d Cir.2004) (quoting 28 U.S.C. § 2342(4)). Such reviewable final orders include “all final orders in licensing proceedings whether or not a hearing before the [NRC] occurred or could have occurred.” Id. (quoting Fla. Power & Light Co. v. Lorion, 470 U.S. 729, 737, 105 S.Ct. 1598, 84 L.Ed.2d 643 (1985)). Vermont and its residents are free to pursue any of these routes to express their concerns regarding the potential public safety hazards posed by Vermont Yankee. The legislation passed here, however, was not the way to resolve those concerns.

As the Supreme Court has held, the one avenue Vermont may not pursue is to pass a “state moratorium” on nuclear energy “grounded in safety concerns.” Pacific Gas, 461 U.S. at 213, 103 S.Ct. 1713. For this reason, we hold that sections 6522(c)(2) and 6522(c)(4) of title 10 of the Vermont Statutes and Act 160 in its entirety are preempted on their face by the Atomic Energy Act.35 We affirm the district court’s grant of a permanent injunction enjoining the defendants from enforcing Act 160 or section 6522(c)(4) of title 10 of the Vermont Statutes, as enacted by Act 74. Entergy Nuclear, 838 F.Supp.2d at 243. We also affirm the district court’s subsequent order of March 19, 2012, enjoining the defendants from enforcing section 6522(c)(2) of title 10 of the Vermont Statutes.

B. Dormant Commerce Clause Claim

Entergy argues that Vermont’s efforts to condition the approval of a new CPG for Vermont Yankee on the execution of a new PPA (to replace the 2001 PPA) represents a demand “that Entergy provide more favorable rates to in-state than out-of-state retail utilities” in contravention of the dormant Commerce Clause. The district court agreed, after examining materials submitted by the Department to the Board; statements by state legislators and regulators during committee meetings, and floor debates in the Vermont Legislature advocating for a new favorable PPA. Entergy Nuclear, 838 F.Supp.2d at 236-39. The district court found “evidence of intent to condition continued operation [of Vermont Yankee] on the demonstration of some marked ‘economic benefit,’ or ‘incremental value,’ beyond that reflected in market rates for long-term contracts, in the form of below-wholesale-market long-term power purchase agreements for Vermont utilities.” Id. at 236. The district court held that this conduct violated the dormant Commerce Clause. Vermont argues, however, that the district court erred in issuing an injunction on the basis of its finding mere intent on the part of the defendants to seek a favorable PPA, and that the issue was therefore not ripe for judicial review. We agree.

*429The “basic rationale” ■ of the ripeness doctrine is to “prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agencies from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.” Abbott Labs. v. Gardner, 387 U.S. 136, 148-49, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967), overruled on other grounds by Califano v. Sanders, 430 U.S. 99, 97 S.Ct. 980, 51 L.Ed.2d 192 (1977). Ripeness encompasses two overlapping doctrines concerning the exercise of federal court jurisdiction. See Reno v. Catholic Soc. Servs., Inc., 509 U.S. 43, 57 n. 18, 113 S.Ct. 2485, 125 L.Ed.2d 38 (1993). The first of these is drawn from “Article III limitations on judicial power,” id., and “hence goes, in a fundamental way, to the existence of jurisdiction.” Simmonds v. INS, 326 F.3d 351, 357 (2d Cir.2003). “The second is a more flexible doctrine of judicial prudence, and constitutes an important exception to the usual rule that where jurisdiction exists a federal court must exercise it.” Id. In either case, “the question of ripeness may be considered on a court’s own motion.” Nat’l Park Hospitality Ass’n v. Dep’t of Interior, 538 U.S. 803, 808, 123 S.Ct. 2026, 155 L.Ed.2d 1017 (2003).

“Constitutional ripeness is a doctrine that, like standing, is a limitation on the power of the judiciary. It prevents courts from declaring the meaning of the law in a vacuum and from constructing generalized legal rules unless the resolution of an actual dispute requires it.” N.Y. Civil Liberties Union v. Grandeau, 528 F.3d 122, 131 (2d Cir.2008) (internal quotation marks omitted). The district court held that Vermont’s efforts to secure favorable pricing for its in-state retail utilities violated the prohibition discussed in New England Power Co. v. New Hampshire, 455 U.S. 331, 335-36, 102 S.Ct. 1096, 71 L.Ed.2d 188 (1982), against providing “residents an ‘economic benefit’ not available to customers in other states.” Entergy Nuclear, 838 F.Supp.2d at 239. However, we believe that the district court erred in applying this “generalized legal rule” in the absence of a fully-formed PPA.

The dormant Commerce Clause, a doctrine inferred from the Commerce Clause of the United States Constitution, see U.S. Const, art. I, § 8 cl. 3, is a “restriction on permissible state regulation.” Hughes v. Oklahoma, 441 U.S. 322, 326, 99 S.Ct. 1727, 60 L.Ed.2d 250 (1979). The dormant Commerce Clause stands for the “principle that one state in its dealings with another may not place itself in a position of economic isolation.” H.P. Hood & Sons, Inc. v. DuMond, 336 U.S. 525, 538, 69 S.Ct. 657, 93 L.Ed. 865 (1949) (internal quotation marks omitted). A state law may burden interstate commerce when it “has the practical effect of requiring out-of-state commerce to be conducted at the regulating state’s direction.” Am. Booksellers Found. v. Dean, 342 F.3d 96, 102 (2d Cir.2003) (internal quotation marks omitted). When a statute “directly controls commerce occurring wholly outside the boundaries of a State,” it is invalid under the dormant Commerce Clause because it “exceeds the inherent limits of the enacting State’s authority.” Healy v. Beer Inst., 491 U.S. 324, 336, 109 S.Ct. 2491, 105 L.Ed.2d 275 (1989). “The transmission of electric current from one state to another ... is interstate commerce” subject to the Commerce Clause. Pub. Utils. Comm’n of R.I. v. Attleboro Steam & Elec. Co., 273 U.S. 83, 86, 47 S.Ct. 294, 71 L.Ed. 549 (1927), abrogated on other grounds by Quill Corp. v. North Dakota ex rel. Heit*430kamp, 504 U.S. 298, 112 S.Ct. 1904, 119 L.Ed.2d 91 (1992).

The district court largely based its conclusion on the Supreme Court’s decision in New England Power, which considered an order of a New Hampshire regulatory commission prohibiting an in-state power plant from exporting some of its output to out-of-state retail utilities in an effort to reduce prices for in-state consumers. 455 U.S. at 335-36, 102 S.Ct. 1096. The Supreme Court stated that the Commerce Clause “precludes a state from mandating that its residents be given a preferred right of access, over out-of-state consumers, to natural resources located within its borders or to the products derived therefrom.” Id. at 338, 102 S.Ct. 1096. On this basis, the Court held that New Hampshire’s “exportation ban” constituted “precisely the sort of protectionist regulation that the Commerce Clause declares off-limits to the states,” because it was “designed to gain an economic advantage for New Hampshire citizens at the expense of [the power plant’s] customers in neighboring states.” Id. at 339, 102 S.Ct. 1096.

The order at issue in New England Power did not violate the dormant Commerce Clause simply because it conferred an economic benefit on New Hampshire residents, however. Rather, by preventing a power plant from exporting its output to other states, the effect of the order was to “overtly block[ ] the flow of interstate commerce at a State’s borders.” City of Phila. v. New Jersey, 437 U.S. 617, 624, 98 S.Ct. 2531, 57 L.Ed.2d 475 (1978). Such laws have “the undeniable effect of controlling commercial activity occurring wholly outside the boundary of the State.” Healy, 491 U.S. at 337, 109 S.Ct. 2491. “While a State may seek lower prices for its consumers, it may not insist that producers or consumers in other States surrender whatever competitive advantages they may possess.” Browm-Forman Distillers Corp. v. N.Y. State Liquor Auth., 476 U.S. 573, 580, 106 S.Ct. 2080, 90 L.Ed.2d 552 (1986). Although the record shows that Vermont was interested in obtaining favorable pricing for the power produced by Vermont Yankee for Vermont retail utilities, it does not show that Vermont was also seeking to prevent retail utilities in other states from negotiating favorable rates with Entergy as well. Cf. SPGGC, LLC v. Blumenthal, 505 F.3d 183, 194 (2d Cir.2007) (holding that a statute prohibiting the in-state sale of certain types of “gift certificates” did not violate the dormant Commerce Clause because it did “not, by its terms or its effects, directly regulate sales of gift cards in other states.... [or] prevent other states from regulating gift card sales differently within their own territories”). The record also does not demonstrate that Vermont sought to impose a “prohibition[ ] on out-of-state access to in-state resources,” Camps Newfound/Owatonna, Inc. v. Town of Harrison, Me., 520 U.S. 564, 578, 117 S.Ct. 1590, 137 L.Ed.2d 852 (1997), by limiting the extent to which Vermont Yankee could sell power to other states, as was the case in New England Power.

At present, in the absence of a completed PPA and without evidence regarding its effect on out-of-state power consumers, we cannot determine whether the PPA Vermont has sought will have a direct impact on commerce in other states. We also do not have a factual record concerning incidental effects of such an agreement on interstate commerce and the commensurate benefits of the agreement within Vermont. Entergy’s claim cannot be characterized as “purely legal” in that it “may be decided without further factual development.” Gary D. Peake Excavating Inc. v. Town Bd. of Town of Hancock, 93 F.3d 68, 72 (2d Cir.1996). *431This case therefore does not present a “concrete dispute affecting cognizable current concerns of the parties within the meaning of Article III,” and is therefore not “ripe within the constitutional sense.” Ehrenfeld v. Mahfouz, 489 F.3d 542, 546 (2d Cir.2007) (internal quotation marks omitted).

Of course, we do not suggest that any PPA providing favorable pricing for Vermont residents would pass muster under the dormant Commerce Clause. A regulation that “evinces” discriminatory purpose against interstate commerce, “or unambiguously discriminates in its effect ... almost always is ‘invalid per se.’ ” Brown & Williamson Tobacco Corp. v. Pataki 320 F.3d 200, 209 (2d Cir.2003) (quoting Nat'l Elec. Mfrs. Ass’n v. Sorrell 272 F.3d 104, 108 (2d Cir.2001)). For example, an agreement requiring Entergy “to seek regulatory approval in [Vermont] before undertaking a transaction in another” state would likely be per se invalid under the dormant Commerce Clause. Brown-Forman, 476 U.S. at 582, 106 S.Ct. 2080; see also Baldwin v. G.A.F. Seelig, Inc., 294 U.S. 511, 521, 55 S.Ct. 497, 79 L.Ed. 1032 (1935) (holding that one state “has no power to project its legislation into [another state] by regulating the price to be paid in that state for [products] acquired there”). It is also likely that Vermont could not require Entergy to “affirm that [its] prices are no higher than the prices being charged in [other] states.” Healy, 491 U.S. at 335, 109 S.Ct. 2491. An agreement requiring Vermont Yankee to allot a certain percentage of it output to satisfy local demand would also likely violate the dormant Commerce Clause. See New Eng. Power, 455 U.S. at 338-39, 102 S.Ct. 1096.36 Finally, we note that a facially-neutral statute that imposes an incidental “burden on interstate commerce incommensurate with the local benefits secured,” Nat’l Elec. Mfrs. Ass’n, 272 F.3d at 108, would fail the balancing test articulated by the Supreme Court in Pike v. Bruce Church, Inc., 397 U.S. 137, 142, 90 S.Ct. 844, 25 L.Ed.2d 174 (1970).37

However, no agreement is before us. Accordingly, the analysis required under the dormant Commerce Clause may not be performed, and so Entergy’s claim is unripe at this time. Cf. Middle S. Energy, Inc. v. City of New Orleans, 800 F.2d 488, 491 (5th Cir.1986) (“When and how the Council exercises its option, if it ever does, are the critical determinants of the propriety of federal court jurisdiction over this matter. Until the City Council actually votes to exercise the purchase option, we must be careful to ‘avoid imposition under [our] jurisdiction through obtaining futile or premature interventions, especially in the field of public law.’” (quoting Pub. Serv. Comm’n of Utah v. Wycoff Co., 344 U.S. 237, 243, 73 S.Ct. 236, 97 L.Ed. 291 (1952))). We therefore vacate the district *432court’s grant of a permanent injunction enjoining the defendants from conditioning a new CPG for Vermont Yankee on the execution of a favorable PPA.38

C. Federal Power Act Claim

Under the Federal Power Act, FERC has jurisdiction over “the transmission of electric energy in interstate commerce and ... the sale of electric energy at wholesale in interstate commerce.” 16 U.S.C. § 824(b)(1). FERC’s authority includes “exclusive jurisdiction over the rates to be charged [a utility’s] interstate wholesale customers.” Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 966, 106 S.Ct. 2349, 90 L.Ed.2d 943 (1986). This authority is exclusive, “without regard to the source of production.” New Eng. Power, 455 U.S. at 340, 102 S.Ct. 1096. After a rate has been approved by FERC, “a State may not conclude in setting retail rates that the FERC-approved wholesale rates are unreasonable. A State must rather give effect to Congress’ desire to give FERC plenary authority over interstate wholesale rates, and to ensure that the States do not interfere with this authority.” Nantahala, 476 U.S. at 966, 106 S.Ct. 2349. Under the filed-rate doctrine, “the right to a reasonable rate is the right to the rate which [FERC] files or fixes, and that, except for review of [FERC’s] orders, the courts can assume no right to a different one on the ground that, in its opinion, it is the only or the more reasonable one.” Mont.-Dakota Utils. Co. v. Nw. Pub. Serv. Co., 341 U.S. 246, 251-52, 71 S.Ct. 692, 95 L.Ed. 912 (1951). The filed-rate doctrine applies with equal force to federal and state courts. See Ark. La. Gas Co. v. Hall, 453 U.S. 571, 581-82, 101 S.Ct. 2925, 69 L.Ed.2d 856 (1981). The filed-rate doctrine also applies to efforts by state regulators to modify the terms of a FERCmandated rate determination or cost allocation. See Entergy La., Inc. v. La. Pub. Serv. Comm’n, 539 U.S. 39, 47-49, 123 S.Ct. 2050, 156 L.Ed.2d 34 (2003).

In recent years, FERC has “encouraged transmission providers to establish ‘Regional Transmission Organizations’ — entities to which transmission providers would transfer operational control of their facilities for the purpose of efficient coordination.” Morgan Stanley Capital Grp., 554 U.S. at 536, 128 S.Ct. 2733. Regional transmission organizations (RTOs), in turn, are managed by “independent system operators” (ISOs), which are nonprofit entities that coordinate the transmission of power and auctions for energy across regional markets. Id. at 536-37, 128 S.Ct. 2733 (citing Midwest ISO Transmission Owners, 373 F.3d at 1364). To accommodate the development of regional power markets, FERC “has begun to permit sellers of wholesale electricity to file ‘market-based’ tariffs,” which, “instead of setting forth rate schedules or rate-fixing contracts, simply state that the seller will enter into freely negotiated contracts with purchasers.” Id. at 537, 128 S.Ct. 2733. In Simon v. KeySpan Corp., we held that there was “no need for us to decide whether the filed rate doctrine always applies to market-based auction rates.” 694 F.3d 196, 204-05 (2d Cir.2012). However, when the doctrine does apply, as when the auction process for establishing market-based rates is adequately safeguarded by FERC, a plaintiffs claim that the rates- for energy *433are unreasonable is barred by the filed-rate doctrine. Id. at 207-08.

Entergy argues that Vermont’s efforts to obtain a favorable PPA violate the market-based tariff approved by FERC for the New England regional wholesale market. According to Entergy, capping the prices it can charge Vermont residents would interfere with the rates FERC has approved for the market, and so the PPA is “preempted” under the filed-rate doctrine. However, the market-based tariff approved by FERC for Vermont Yankee states only that Entergy “may sell electric energy and capacity from time to time at rates, terms and conditions established by agreement with the purchaser____All such transactions shall be voluntary.” The market-based tariffs only other guidance on rates is that “[a]ll sales shall be made at rates established by agreement between the purchaser and Entergy Nuclear VY.”

We agree with the district court’s determination that this claim is not ripe. In addition to the fact that a new favorable PPA has not yet been executed, Entergy has not sought a determination from FERC about whether the terms of such a PPA would violate the market-based tariff.39 Because FERC has the exclusive jurisdiction to “determine just and reasonable wholesale rates or to insure that agreements affecting wholesale rates are reasonable,” Entergy’s recourse should be first to FERC to determine whether the PPA — if and when executed — complies with this standard. See Miss. Power & Light Co. v. Miss, ex rel. Moore, 487 U.S. 354, 374, 108 S.Ct. 2428, 101 L.Ed.2d 322 (1988); see also In re Permian Basin Area Rate Cases, 390 U.S. 747, 767, 88 S.Ct. 1344, 20 L.Ed.2d 312 (1968) (“[C]ourts are without authority to set aside any rate selected by the Commission which is within a ‘zone of reasonableness.’ ” (quoting Fed. Power Comm’n v. Natural Gas Pipeline Co. of Am., 315 U.S. 575, 585, 62 S.Ct. 736, 86 L.Ed. 1037 (1942)) (emphasis added)); Pub. Util. Dist. No. 1 of Snohomish Cnty. v. Dynegy Power Mktg., Inc., 384 F.3d 756, 761-62 (9th Cir.2004) (holding that a utility may not seek injunctive relief alleging manipulation of FERC-approved market based tariffs because doing so would “encroach[ ] upon the substantive provisions of the tariff, an area reserved exclusively to FERC, both to enforce and to seek remedy” (internal quotation marks omitted)); Cal. Pub. Utils. Comm’n, 132 FERC ¶ 61,047, at *17 (“The Commission’s authority under the [Federal Power Act] includes the exclusive jurisdiction to regulate the rates, terms and conditions of sales for resale of electric energy in interstate commerce by public utilities.” (emphasis added)), clarified on reh’g, 133 FERC ¶ 61,059 (2010). We therefore agree with the district court that Entergy’s claim under Count Two is unripe at the present time. Entergy Nuclear, 838 F.Supp.2d at 234-35.

CONCLUSION

For the reasons stated above, we AFFIRM the district court’s grant of a declaratory judgment that Act 74 and Act 160 are facially preempted by the Atomic Energy Act. We REVERSE the district court’s determination that Vermont’s efforts to condition a new Certifícate of Public Good for Vermont Yankee on the exe*434cution of a favorable power purchase agreement violate the dormant Commerce Clause. We AFFIRM the district court’s determination that Entergy’s challenge under the Federal Power Act is unripe. We AFFIRM the district court’s grant of a permanent injunction enjoining the defendants from enforcing sections 6522(c)(2) or 6522(c)(4) in title 10 of the Vermont Statutes, as enacted by Act 74, or sections 248(e)(2), 248(m), or 254 in title 30 of the Vermont Statutes, as enacted by Act 160. Finally, we VACATE the district court’s permanent injunction enjoining the defendants from conditioning the issuance of a Certifícate of Public Good on the execution of a below-wholesale-market power purchase agreement between Entergy and Vermont utilities or otherwise requiring Vermont Yankee to sell power to Vermont utilities at preferential rates.

Judge CARNEY concurs in a separate opinion.

. Entergy Nuclear Vermont Yankee, LLC, and Entergy Nuclear Operations, Inc., are co-holders of the Nuclear Regulatory Commission Facility Operating License No. DPR-28 and Renewed Facility Operating License No. DPR28. They are also indirect subsidiaries of parent Entergy Corporation, a Delaware cor*398poration headquartered in New Orleans, Louisiana, that owns and operates twelve nuclear reactors in ten locations in the United States.

. Entergy does not appeal the district court’s determination as to Act 189.

. The Board is a three-member quasi-judicial state agency that regulates a variety of public utilities in Vermont, including power facilities. It supervises the utilities’ rates, service quality, and overall financial management. See Vt. Stat. Ann. tit. 30, §§ 9, 203.

.The criteria the Board must consider in deciding whether to issue a CPG relate to such issues as power generation stability, economic impact on the State, aesthetic and environmental issues, and likelihood of compliance with federal regulations. See Vt. Stat. Ann. tit. 30, § 248(b).

. The Department oversees laws relating to public service corporations and represents the State of Vermont in the procurement of energy in hearings before the Board in an advocacy capacity. See Vt. Stat. Ann. tit. 30, §§ 1, 2, 203.

. Although VYNPC included retail utilities from outside Vermont, by 2009, Central Vermont Public Service and Green Mountain Power had accumulated a combined stake of 92.5% of VYNPC.

. Spent fuel rods are typically stored in deep pools of treated water at the reactor site for a period of at least five years. Once the spent fuel rods’ temperature and radiation emissions have sufficiently diminished, they can be moved into dry casks — consisting of sealed metal cylinders on a concrete pad — for long-term storage. Dry casks are monitored by the NRC for public health and safety. See 10 C.F.R. § 961.11. at App. E(B)(3); U.S. Nuclear Regulatory Comm'n, Backgrounder on Dry Cask Storage of Spent Nuclear Fuel (Feb. 28, 2013), available at http://www.nrc.gov/ reading-rm/doc-collections/fact-sheets/dry-cask-storage.html.

. Section 6523 was subsequently recodified to title 30 of the Vermont Statutes relating to the powers of the Board. See Vt. Stat. Ann. tit. 30, § 8015.

. Entergy is not challenging section 6523 in the instant appeal.

.In its subsequent Order, the Board confirmed that Entergy's total obligation under the 2005 MOU to make payments into the Fund would be $15,625,000 from 2005 to 2012, made in quarterly payments of $625,000. In re Entergy Nuclear Vt. Yankee, LLC, 249 P.U.R.4th 1, 2006 WL 1418626, at *21 (Vt.Pub.Serv.Bd. Apr. 26, 2006).

. The 2005 MOU was not included in the record on appeal, but was introduced below as Plaintiffs’ Trial Exhibit 465 (Document 46-19).

. The Board imposed the flood analysis requirement in part in response to the U.S. Department of Energy’s "failure to remove the spent nuclear fuel [generated by Vermont Yankee] in a timely fashion.” Entergy Nuclear Vt. Yankee, 95 Fed.Cl. at 179-80.

.This, in turn, represents fifty-five percent of Vermont Yankee’s total power output. The remainder is sold on the wholesale market to retail utilities in other states. See In re Proposed Sale of Vt. Yankee Nuclear Power Station, 175 Vt. 368, 829 A.2d 1284, 1285 (2003); *403In re Entergy Nuclear Vt. Yankee, LLC, 2006 WL 1418626, at *12.

. The preamble to Act 160 was not published in the Vermont Statutes, but is contained in West's historical notes to Chapter 157 of title 10, Vermont Statutes Annotated (West 2011).

. Though the original bill called for Act 189 to be codified as an addition to section 254 of title 30 of the Vermont Statutes, the final version of Act 189 was not codified. Entergy Nuclear Vt. Yankee, LLC v. Shumlin, 838 F.Supp.2d 183, 213 (D.Vt.2012).

. The Court also considered a challenge to section 25524.1(b), which required the State Energy Commission to determine on a case-by-case basis whether there would be "adequate capacity” for the short-term storage of spent nuclear fuel before granting certification for the construction of a new plant. Pacific Gas, 461 U.S. at 197, 103 S.Ct. 1713. The Court determined that the challenge to section 25524.1(b) was not ripe for review because, under the case-by-case methodology required by the statute, the Court could not "know whether the [State] Energy Commission will ever find a nuclear plant’s storage capacity to be inadequate.” Id. at 203, 103 S.Ct. 1713 (internal quotation marks omitted).

. Indeed, the power market in California was not opened to competition until the late 1990s. See David B. Spence, Can Law Manage Competitive Energy Markets?, 93 Cornell L.Rev. 765, 779-81 (2008).

. The orders may be read in full at Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities, Order 888, 61 Fed. Reg. 21,540, 21,541-43 (FERC May 10, 1996) (codified at 18 C.F.R. pt. 37); and at Open Access Same-Time Information System (Formerly Real-Time Information Networks) and Standards of Conduct, Order 889, 61 Fed. Reg. 21,737, 21,740-41 (FERC Apr. 24, 1996) (codified at 18 C.F.R. pt. 37).

. See U.S. Energy Info. Admin., The Changing Structure of the Electric Power Industry 2000: An Update, at 74-77 (2000), available at http://www.eia.gov/cneaf/electricity/chg_ stru_update/update2000.pdf.

. See, e.g., New York v. United States, 505 U.S. 144, 197, 112 S.Ct. 2408, 120 L.Ed.2d 120 (1992) (noting that "public opposition” undermined a state’s efforts to identify sites for nuclear waste disposal); State of Nev. v. Watkins, 914 F.2d 1545, 1550-51 (9th Cir.1990) (noting the opposition of the Nevada Legislature to the storage of spent nuclear fuel in the state); see also Michael B. Gerrard, Fear and Loathing in the Siting of Hazardous and Radioactive Waste Facilities: A Comprehensive Approach to a Misperceived Crisis, 68 Tul. L.Rev. 1047, 1137-46 (1994) (discussing the sources of public opposition to spent nuclear fuel storages sites).

. As the party asserting preemption, Entergy carries the burden of proof. See Silkwood, 464 U.S. at 255, 104 S.Ct. 615 (stating that Kerr-McGee, as the party asserting the preemption claim, bore the “burden to show that Congress intended to [preempt] such [punitive damages] awards in the Atomic Energy Act)”; see also English, 496 U.S. at 85-86, 110 S.Ct. 2270 (following the approach set out in Silk-wood). We thus reject the burden-shifting approach that the district court imported from Equal Protection Clause and First Amendment jurisprudence. See Entergy Nuclear, 838 F.Supp.2d at 225, 230-31 (citing Vill. of Arlington Heights v. Metro. Hous. Dev. Corp., 429 U.S. 252, 271 n. 21, 97 S.Ct. 555, 50 L.Ed.2d 450 (1977), and Mt. Healthy City Sch. Dist. Bd. of Educ. v. Doyle, 429 U.S. 274, 285-86, 97 S.Ct. 568, 50 L.Ed.2d 471 (1977)).

. See also Loyal Tire & Auto Ctr., Inc. v. Town of Woodbury, 445 F.3d 136, 145 (2d Cir.2006) (Sotomayor, J,) (noting, in the context of Interstate Commerce Act preemption, that a court must inquire into whether the state or local regulation is “genuinely responsive” to the proffered rationale).

. Moreover, the statute provides that "public health issues,” including those related to storage of nuclear waste, are to be considered in determining whether to permit the continued operation of Vermont Yankee. As this phrase is not defined in the statute, we must look to the legislative intent to determine its meaning. See Universal Church v. Geltzer, 463 F.3d 218, 223 (2d Cir.2006) (“[W]e may look to the legislative history to determine the legislative intent where the plain statutory language is ambiguous____").

. Indeed, the Board recognized alternative sources of energy in its Order approving the sale of Vermont Yankee to Entergy in 2002, but noted some of the related problems:

We cannot assume, as urged by several members of the public, that the power from Vermont Yankee can be quickly replaced by renewable resources. Vermont already gets a higher percentage of its power from renewable sources (mostly large hydro-power dams) than many other states. With the exception of large hydro dams, renewable energy resources tend to be relatively small sources of generation, particularly in relation to Vermont Yankee. Thus, instead of renewable sources, Vermont utilities would need to rely on fossil fuel generating stations to replace much of the power now provided by Vermont Yankee. This option would have the very serious disadvantage of significantly increasing the emission of air contaminants and greenhouse gases.

In re Vt. Yankee Nuclear Power Corp., 2002 WL 1997942 (footnote omitted).

. We note that in its 2006 Order granting a new CPG to Vermont Yankee to store additional spent nuclear fuel on site, the Board made the following argument regarding the effect of the plaint shutting down:

In the absence of the dry fuel storage project, a substantial likelihood exists that Vermont Yankee would shut down by 2008 due to the inability to store the spent nuclear fuel it generates. [Vermont retail utilities] could replace the power with other purchases, but such replacement power would probably cost more (perhaps significantly more) than the Vermont Yankee power.

In re Entergy Nuclear Vt. Yankee, LLC, 2006 WL 1418626, at *20.

. In conducting this analysis, we do not suggest that Vermont Yankee's status as a merchant generator precludes every possible economic argument Vermont could offer as a basis for regulating the plant. See Pacific Gas, 461 U.S. at 208-09, 215, 103 S.Ct. 1713; see also Nieman v. NLO, Inc., 108 F.3d 1546, 1552 (6th Cir.1997) ("[W]hile recognizing that Congress has preempted the entire field of nuclear safety regulation, the Supreme Court has been willing to uphold the application of state law where it affects nuclear regulation only indirectly, i.e., where state law amounted to economic regulation....”). We note only that the rationales proffered here are implausible in light of the actual effect of Act 160, and that the non-safety-related rationales for a legislative decision to shut down Vermont Yankee are not adequately supported by the record.

. We acknowledge that Pacific Gas does not explain with precision the role legislative history plays in the analysis of an Atomic Energy Act preemption claim. See English, 496 U.S. at 84 n. 7, 110 S.Ct. 2270 ("Whether the suggestion of the majority in Pacific Gas that legislative purpose is relevant to the definition of the pre-empted field is part of the holding of that case is not an issue before us today. ...”); see also Kerr-McGee Chem. Corp. v. City of W. Chi., 914 F.2d 820, 827 (7th Cir.1990) ("It is not clear how heavily legislative purpose is to be weighed in determining preemption.”); Norris v. Lumbermen's Mut. Cos. Co., 881 F.2d 1144, 1150-51 (1st Cir.1989) (interpreting the "teaching of Pacific Gas & Electric ” as requiring an analysis of a state statute's text and effect). But see Skull Valley, 376 F.3d at 1252 ("[W]e are required to follow the preemption analysis set forth in Pacific Gas, Silk-wood, and English, which requires consideration of the purpose. of the allegedly preempted statute, along with its effects.”). Moreover, the Pacific Gas Court conducted a methodical analysis of the legislative intent undergirding the federal Atomic Energy Act to determine its scope and effect, 461 U.S. at 205-11, 103 S.Ct. 1713, and we see no reason why the state statute at issue should not be so scrutinized as well.

. See also Belanger v. Salvation Army, 556 F.3d 1153, 1155 (11th Cir.2009); Nike, Inc. v. McCarthy, 379 F.3d 576, 581-82 (9th Cir.2004); Femedeer v. Haun, 227 F.3d 1244, 1249 (10th Cir.2000).

. Our analysis focuses on whether radiological safety was the primary purpose under-girding the passage of Act 160, not simply whether safety was only one of several considerations. See Pacific Gas, 461 U.S. at 196, 213, 103 S.Ct. 1713 (identifying "both safety and economic aspects to the nuclear waste issue,” yet finding no preemption where the Warren-Alquist Act had "a non-safety rationale” (emphasis added)); cf. Vango Media, Inc. v. City of N.Y., 34 F.3d 68, 73 (2d Cir.1994) (finding that while the challenged statute had “an associated economic impact on society,” its "primary interest” was the preempted field of "public health”).

. We reach this conclusion without needing to consider the legislative history behind S.289, which — had it passed — would have permitted Vermont Yankee to operate for twenty years after March 21, 2012. We note that although S.289 arguably shares “a common heritage” with Act 160, it is "not before the Court, and indeed, ... was not passed.” *422S.289’s "provisions and [its] pedigree do not taint other parts of” Act 160. Pacific Gas, 461 U.S. at 215-16, 103 S.Ct. 1713; see also Pension Benefit Guar. Corp. v. LTV Corp., 496 U.S. 633, 650, 110 S.Ct. 2668, 110 L.Ed.2d 579 (1990) ("[Subsequent legislative history is a hazardous basis for inferring the intent of an earlier Congress.” (internal quotation marks omitted)). However, we note that consideration of S.289’s legislative history would nonetheless confirm our analysis of Act 160, as its record contains numerous references to radiological safety concerns. For instance, during a meeting of the Senate Finance Committee debating the bill, a Department commissioner adverted to the recent tritium leak at the Vermont Yankee site and suggested delaying the vote on S.289, commenting that determining “what sort of public health and safety issues ... we need to address is sort of priority one.” Various senators also reiterated concerns regarding the potential safety risks to Vermont residents living near the plant during the hearings on S.289. Echoing an earlier comment by the chair of the Senate Finance Committee during its debates regarding Act 160, one senator argued on the Senate floor that the other senators should consider "safety concerns, although I’m not supposed to talk about that so I won’t go into detail on that, but it’s certainly in everybody’s mind in this room, we all know it.”

. As previously discussed, sections 6522(b)(4) and 6523(a)(1)(A) sweep all MOUs executed before July 1, 2005, into the ambit of Act 74, including the MOU executed on June 21, 2005.

. Our concerns regarding the intent behind Act 74 are consistent with a recent opinion of the Federal Circuit, which examined the provision in the 2005 MOU requiring that Entergy perform an analysis of the stability of the river bank near a proposed spent nuclear storage facility "due to the perceived inadequacies of a previously performed NRC-required flood analysis.” Vt. Yankee Nuclear Power Corp. v. Entergy Nuclear Vt. Yankee, LLC, 683 F.3d 1330, 1349 (Fed.Cir.2012). The Federal Circuit noted that "because the requirement to perform an additional analysis was directly motivated by safety concerns, it is clear that the flood analysis requirement was likely preempted under Pacific Gas." Id.

.We cite this provision of the 2005 MOU not for the purpose of ruling on whether a party may validly waive the right to bring a preemption challenge, but only to demonstrate the impermissible intent on the part of *426the Vermont Legislature. But see Olympic Pipe Line Co. v. City of Seattle, 437 F.3d 872, 883 (9th Cir.2006) (“Preemption is a power of the federal government, not an individual right of a third party that the party can ‘waive.’ [The plaintiff] could not, therefore, waive a right that it did not possess.”).

. We have limited our analysis to Acts 74 and 160 in light of the district court’s determination that Entergy's challenge to Act 189 is moot, a ruling that neither party challenges. Moreover, we recognize that the legislative history of Act 189, which was passed after Act 160, is an imperfect indicator of the legislative intent behind Acte 74 and 160. See Pension Benefit Guar. Corp., 496 U.S. at 650, 110 S.Ct. 2668. However, we nonetheless note that Act 189 directly regulates on the basis of radiological safety by requiring assessments of Vermont Yankee's electrical, emergency, primary containment, and heat removal systems, with periodic audits to be conducted by a public oversight panel. Act 189, §§ 3, 6. Furthermore, the legislative history behind Act 189 demonstrates that the purpose of the Act was to allow Vermont regulators to conduct an "independent safety inspection” of Vermont Yankee, in large part because Vermont legislators doubted the competence of the NRC. Several Vermont legislators also expressed concern that a nuclear accident could tarnish Vermont's "environmentally friendly” image. In addition, the testimony of Department commissioners and Vermont legislators contains familiar examples of coaching to avoid explicit references to radiological safety. Indeed, the committee chairperson drafting Act 189 specifically described the bill as a "reliability assessment because safety is not within our purview.” Moreover, during a hearing of the House Natural Resources Committee, a member of the Department distributed a handout entitled, '.'Everything You Wanted to Ask About Preemption But Shouldn't,” and provided testimony advising Vermont legislators on how to discuss Act 189 in a manner that disguised their concerns about radiological safety. Testimony presented to the Committee explicitly referenced Pacific Gas and recommended that Vermont legislators discuss closing Vermont Yankee because it caused non-radiological environmental problems or was "unreliable,” so as to avoid a preemption challenge. During later hearings, legislators openly admonished each other for using the word "safety” and similar terms and expressed concerns over the prospect of preemption.

. We agree with the district court’s determination that Entergy's initial challenge to Act 189 is moot, as Entergy has already completed the studies of Vermont Yankee’s safety systems required by the statute, and the results have been reported to the Vermont Legislature. In addition, because we hold that Act 160 is preempted by the Atomic Energy Act, the Board will no longer be able to consider the studies mandated by Act 189. See Entergy Nuclear, 838 F.Supp.2d at 233.

. Agreements of this nature would be "scrutinized strictly, i.e., 'the burden falls on the State to justify [the discrimination] both in terms of the local benefits flowing from the statute and the unavailability of nondiscriminatory alternatives adequate to preserve the local interests at stake.' " Brown & Williamson, 320 F.3d at 209 (quoting Hunt v. Wash. State Apple-Advertising Comm’n, 432 U.S. 333, 353, 97 S.Ct. 2434, 53 L.Ed.2d 383 (1977)).

. A statute or regulation would discriminate against commerce itself when the statute

(i) shifts the costs of regulation onto other states, permitting in-state lawmakers to avoid the costs of their political decisions,
(ii) has the practical effect of requiring out-of-state commerce to be conducted at the regulating state's direction, or (iii) alters the interstate flow of the goods in question, as distinct from the impact on companies trading in those goods.

Am. Booksellers Found. v. Dean, 342 F.3d 96, 102 (2d Cir.2003) (internal quotation marks omitted).

. Because we vacate the district court’s grant of an injunction regarding Entergy's dormant Commerce Clause claim, we need not address the question of whether Entergy's suit sought to enjoin the proper officials under Ex Parte Young, 209 U.S. 123, 28 S.Ct. 441, 52 L.Ed. 714 (1908), and Verizon Maryland Inc. v. Public Service Commission of Maryland, 535 U.S. 635, 122 S.Ct. 1753, 152 L.Ed.2d 871 (2002).

. Entergy also has not offered an explanation for why it did not seek review of the 2001 PPA before FERC, and the record does not reveal any prior attempts to do so. Nonetheless, FERC's "passive permission for a rate to go into effect does not constitute a finding that the rate is just and reasonable,” as required by the Federal Power Act pursuant to 16 U.S.C. § 824d(a). See Morgan Stanley Capital Grp., 554 U.S. at 546, 128 S.Ct. 2733.