Legal Research AI

Rio Grande Pipeline Co. v. Federal Energy Regulatory Commission

Court: Court of Appeals for the D.C. Circuit
Date filed: 1999-06-08
Citations: 178 F.3d 533, 336 U.S. App. D.C. 229
Copy Citations
30 Citing Cases

                  United States Court of Appeals

               FOR THE DISTRICT OF COLUMBIA CIRCUIT

         Argued April 21, 1999      Decided June 8, 1999 

                           No. 98-1194

                  Rio Grande Pipeline Company, 
                            Petitioner

                                v.

            Federal Energy Regulatory Commission and 
                    United States of America, 
                           Respondents 

                Longhorn Partners Pipeline, L.P., 
                            Intervenor

               On Petition for Review of Orders of the Federal 
                    Energy Regulatory Commission

     John B. Rudolph argued the cause for petitioner.  With 
him on the briefs was Alex A. Goldberg.  Lisa M. Tonery 
entered an appearance.

     Judith Albert, Attorney, Federal Energy Regulatory Com-
mission, argued the cause for respondents.  With her on the 

brief were Joel I. Klein, Assistant Attorney General, U.S. 
Department of Justice, John J. Powers, III, and Robert J. 
Wiggers, Attorneys, Jay L. Witkin, Solicitor, Federal Energy 
Regulatory Commission, and Susan J. Court, Special Coun-
sel.  Samuel Soopper, Attorney, entered an appearance.

     Lawrence A. Miller argued the cause for intervenor.  With 
him on the briefs was Kevin Hawley.

     Before:  Edwards, Chief Judge, Wald and Rogers, Circuit 
Judges.

     Opinion for the Court filed by Chief Judge Edwards.

     Edwards, Chief Judge:  Rio Grande Pipeline Company 
("Rio Grande") purchased 194 miles of an existing refined 
products pipeline from the Navajo Pipeline Company ("Nava-
jo") to deliver natural gas liquids ("NGLs") from the United 
States to Mexico.  In exchange for the pipeline, Rio Grande 
paid Navajo an agreed sum of money and granted Navajo 
Southern, Inc., a wholly owned subsidiary of Navajo, a minor-
ity interest in Rio Grande.  In the proceeding under review, 
Rio Grande sought to include the purchase price of the 
pipeline in its rate base.  Normally, a purchaser such as Rio 
Grande is only permitted to include the seller's depreciated 
original cost in its cost-of-service calculations;  however, Rio 
Grande pointed out that this transaction was different, be-
cause the pipeline was purchased for a new use and the 
purchase price was less than the cost of constructing a 
comparable facility.  Rio Grande therefore contended that it 
should be permitted to include the full purchase price of the 
pipeline in its rate base under the so-called "benefits excep-
tion" to the original cost rule.  The Federal Energy Regula-
tory Commission ("FERC" or "Commission") denied Rio 
Grande's request, holding that the benefits exception can 
never be employed when the seller acquires an equity interest 
in the purchasing entity.  Rio Grande petitions for review of 
this ruling, claiming that FERC's decision is flatly at odds 
with the benefits rule and that the agency's judgment defies 
reason.

     Before turning to the merits, we must first resolve three 
threshold issues:  (1) whether Longhorn Partners Pipeline 
("Longhorn") is a proper intervenor in the matter now before 
the court, (2) whether Rio Grande has been "aggrieved" by 
the contested orders, and (3) whether the contested orders 
are ripe for review.  With these threshold issues resolved, we 
then reach the question of whether FERC's rejection of Rio 
Grande's request to include the full purchase price of the 
pipeline in its rate base was arbitrary and capricious.

     On the record at hand, we conclude that Longhorn is not a 
proper intervenor in this action, because it does not have 
standing.  Indeed, it appears that Longhorn is really seeking 
to participate as an amicus.  Pursuant to our discretion under 
Rule 29(a) of the Federal Rules of Appellate Procedure, we 
will accord Longhorn amicus status so that its views on the 
common issues can be considered.  We also conclude that Rio 
Grande is an aggrieved party, because it faces real and 
present economic injury as a result of the orders here in 
dispute.  Likewise, because FERC's disputed policy is fully 
crystallized and raises a concrete legal question, we find that 
petitioner's claim is ripe for review by this court.  Finally, on 
the merits, we conclude that FERC's refusal to apply the 
benefits exception in the present case was arbitrary and 
capricious for lack of an adequate justification.  Accordingly, 
we grant Rio Grande's petition for review.

                          I. Background

     Rio Grande is a partnership formed by two pipeline compa-
nies, Juarez Pipeline Company and Amoco Rio Grande Pipe-
line Company, to construct and maintain an integrated com-
mon carrier pipeline to deliver NGLs from the United States 
to Mexico.  As a part of this project, Rio Grande sought to 
purchase 194 miles of an existing refined products pipeline 
from Navajo, which would then be converted to NGL service.  
According to Rio Grande, Navajo's willingness to sell this 
segment of pipeline "at a reasonable price was directly depen-
dent on its ability to acquire a partnership interest in our 
project."  Statement of William C. Lawson, Management 

Committee Chairman, Rio Grande, reprinted in Joint Appen-
dix ("J.A.") 61.  Accordingly, in exchange for the pipeline, Rio 
Grande agreed to pay an agreed sum of money to Navajo as 
well as grant Navajo Southern, Inc., a wholly owned subsid-
iary of Navajo, a minority partnership interest in Rio Grande.  
Rio Grande asserts, without contradiction, that the price paid 
for the pipeline, including the value of the partnership inter-
est and the cost of converting and integrating the acquired 
line, is at least $8 million less than the cost of constructing a 
comparable new line.  See id.

     Rio Grande then sought to justify the rates for its new 
service.  Under 18 C.F.R. s 342.2, pipelines may justify an 
initial rate for new service using one of two methods:  the 
carrier may either (1) file cost, revenue, and throughput data 
supporting the proposed rate pursuant to s 342.2(a), or (2) 
file a sworn statement that the proposed rate is agreed to by 
at least one non-affiliated person who intends to use the 
service, pursuant to s 342.2(b).  Rates justified under 
s 342.2(b) are simple to put into place, and often become 
effective without a FERC order addressing them.  However, 
these rates are ineffective if a protest to the initial rate is 
filed, in which case the carrier must seek a s 342.2(a) justifi-
cation.  Moreover, if a negotiated rate is challenged and a 
lower rate is found appropriate, the pipeline may have to pay 
reparations for the amount overcharged.  In contrast, a cost-
supported rate approved under s 342.2(a) is entitled to great-
er protection.  For example, if a challenge is brought to a 
cost-supported, Commission-approved rate and a reduction is 
required, that reduction is given only prospective effect.  See 
generally Arizona Grocery Co. v. Atchison, Topeka & Santa 
Fe Ry. Co., 284 U.S. 370, 387-89 (1932).

     In this case, Rio Grande filed a petition for a declaratory 
order, requesting approval of its initial rates.  In its petition, 
Rio Grande noted that a non-affiliated party, Petroleos Mexi-
canos ("PEMEX"), had agreed to the proposed initial rate of 
$1.26 per barrel and, thus, the rates could be justified under 
s 342.2(b).  However, Rio Grande made clear that it was not 
requesting FERC approval of a negotiated rate under 
s 342.2(b):

     [W]hether one or twenty "non-affiliated persons" agree 
     to its to-be-filed rate, [Rio Grande] is not assured that it 
     will be able to justify its "initial rate," if challenged, 
     unless it has the Commission's approval to include its 
     acquisition costs.  Regardless of a consignee or shipper's 
     prior agreement to the rate, [Rio Grande's] proposed 
     tariff may be protested.  In the event of a protest to a 
     negotiated rate, [Rio Grande] would have to submit "cost, 
     revenue and throughput data supporting such rate" and 
     incur the cost of a lengthy rate proceeding.  18 C.F.R. 
     s 342.2(a) (1995).  Accordingly, [Rio Grande] also sub-
     mits this Petition to establish its rate base and pre-
     justify its rates.
     
In re Rio Grande Pipeline Co., Verified Petition for Declara-
tory Order (Oct. 7, 1996), reprinted in J.A. 8 (footnote 
omitted).  In support of its request for approval under 
s 342.2(a), Rio Grande submitted detailed cost-of-service cal-
culations, which included the full purchase price of the new 
pipeline.

     Generally, when establishing the cost of service upon which 
a pipeline's regulated rates are based, FERC employs "origi-
nal cost" principles.  Under these principles, when a facility is 
acquired by one regulated entity from another, the seller's 
depreciated original cost is included in the cost-of-service 
computations, even though the price paid by the purchaser 
may exceed that amount.  See Northern Natural Gas Co., 35 
F.E.R.C. p 61,114, at 61,236 (1986).  Applying the original 
cost rule to this case, Rio Grande would not be permitted to 
include the full purchase price of the pipeline in its rate base;  
it would only be permitted to include Navajo's depreciated 
cost of the pipeline.  However, the Commission has created 
an exception to this general rule for cases where it is shown 
that the "acquisition results in substantial benefits to ratepay-
ers."  Longhorn Partners Pipeline, 73 F.E.R.C. p 61,355, at 
62,112 (1995) ("Longhorn I").  Under this "benefits excep-
tion," purchased facilities may be included in the rate base at 
the full purchase price if the purchaser can demonstrate that:  
(1) the acquired facility is being put to new use, and (2) the 

purchase price is less than the cost of constructing a compa-
rable facility.  See id. at 62,112-13.

     In its petition, Rio Grande argued that it had satisfied the 
requirements of the benefits exception.  It explained that, by 
acquiring the pipeline from Navajo rather than constructing a 
new one, it had saved at least $8 million.  It also explained 
that the pipeline would be put to a new use, because the 
transport of NGLs, unlike the transport of refined products, 
required pressurization, and because the line would serve 
entirely different markets and shippers than those served by 
the previous refined products service.  Accordingly, Rio 
Grande argued that it should be allowed to include the full 
purchase price of the pipeline in its rate base.

     FERC denied Rio Grande's request to allow the full pur-
chase price of the acquired line to be included in its cost-of-
service calculations, and, thus, rejected the proposed rates 
under s 342.2(a).  See Rio Grande Pipeline Co., 78 F.E.R.C. 
p 61,020, at 61,082-83 (1997) ("Rio Grande I").  In support of 
this position, FERC explained that "[t]he general rule ... is 
that the depreciated cost of an acquired asset must be used in 
cost-of-service calculations where the former owner not only 
receives the higher price but also has an equity interest in the 
acquiring company."  Id. at 61,082.  This position was war-
ranted, according to FERC, to ensure that a seller does not 
"benefit from the higher cost of service on the line, which it 
cannot do as the owner of a regulated asset at this time."  Id. 
(internal quotation marks omitted).  FERC noted, however, 
that since Rio Grande had supplied the affidavit required by 
s 342.2(b), and no entity had protested the charged rate, Rio 
Grande was free to charge the proposed rate in its transac-
tions with PEMEX.  See id. Rio Grande sought rehearing of 
the decision, which was denied on February 13, 1998.  See 
Rio Grande Pipeline Co., 82 F.E.R.C. p 61,147 (1998) ("Rio 
Grande II").  Rio Grande then timely petitioned for review in 
this court.

     In an entirely separate transaction, Longhorn, like Rio 
Grande, negotiated a deal to purchase a pipeline segment.  
And Longhorn similarly agreed to grant an equity interest to 

the seller of the pipeline segment in addition to the payment 
of a sum of cash.  After its deal had closed, Longhorn sought 
approval from FERC for the inclusion of the full purchase 
price of its new asset in its rate base under the benefits 
exception.  The Commission, however, denied Longhorn's 
request for the same reason it had denied Rio Grande's 
request:  the benefits exception could not apply where a 
selling entity acquired an equity interest in the purchaser.  
See Longhorn Partners Pipeline, 82 F.E.R.C. p 61,146, at 
61,543-44 (1998).

     Because of the possible precedential impact on its case, 
Longhorn sought to intervene in the Rio Grande proceedings 
before the Commission, but its motion was denied.  See Rio 
Grande II, 82 F.E.R.C. at 61,548.  In a separate action, 
Longhorn filed a petition for review of its own case in this 
court, Longhorn Partners Pipeline v. FERC, No. 98-1547 
(filed Nov. 17, 1998);  however, Longhorn also seeks to main-
tain intervenor status in the instant case before this court, 
over the objection of FERC.

                           II. Analysis

     A.   Longhorn's Intervenor Status
          
     Longhorn relies principally on 28 U.S.C. s 2348 in support 
of its motion to intervene.  In City of Cleveland v. NRC, 17 
F.3d 1515, 1517-18 (D.C. Cir. 1994) (per curiam), however, 
this court held that Article III standing is a prerequisite to 
s 2348 intervention, and it is uncontested that Longhorn 
lacks Article III standing with respect to the Commission's 
Rio Grande II order.  From this, it might be simply conclud-
ed that Longhorn cannot intervene under 28 U.S.C. s 2348.  
The matter is not so simple, however, for in the same year 
that City of Cleveland was issued, the court also issued 
American Train Dispatchers Ass'n v. ICC, 26 F.3d 1157 
(D.C. Cir. 1994), producing precedent that can be read as in 
direct conflict with City of Cleveland.

     In Train Dispatchers, we faced the preliminary question of 
whether to permit the Railway Labor Executives' Association 
("RLEA") to intervene in the proceedings challenging an ICC 

order although it had not participated at the agency level.  
The court in Train Dispatchers did two things with respect to 
the intervention question:  (1) it held that the court may, in its 
discretion, permit intervention under 28 U.S.C. s 2348,  and 
(2) it expressly allowed RLEA to intervene.  See Train 
Dispatchers, 26 F.3d at 1162 ("Thus, even assuming that 
RLEA is not entitled to intervene as of right here, we may 
allow it to intervene as a discretionary matter.  We choose to 
do so in this case....").  Were Article III standing a prere- 
quisite to intervention, the court could not have decided, as it 
did, to "grant RLEA's motion to intervene without deciding 
whether it has Article III standing."  Id.  This statement 
makes sense only to the extent that Article III standing is 
simply irrelevant to (or at least not dispositive of) the discre-
tionary decision to allow intervention.  Accordingly, it ap-
pears that City of Cleveland and Train Dispatchers conflict.

     The only conclusion we can draw from reading these two 
cases is that the two panels spoke past one another.  They 
rely on different lines of circuit precedent, and neither opin-
ion even acknowledges that the other line exists.  Given that 
our sister circuits are similarly divided, compare Ruiz v. 
Estelle, 161 F.3d 814, 830 (5th Cir. 1998) (holding that Article 
III standing is not a prerequisite to intervention), Associated 
Builders & Contractors v. Perry, 16 F.3d 688, 690 (6th Cir. 
1994) (same), Yniguez v. Arizona, 939 F.2d 727, 731 (9th Cir. 
1991) (same), Chiles v. Thornburgh, 865 F.2d 1197, 1213 (11th 
Cir. 1989) (same), and United States Postal Serv. v. Brennan, 
579 F.2d 188, 190 (2d Cir. 1978) (same), with Mausolf v. 
Babbitt, 85 F.3d 1295, 1300 (8th Cir. 1996) (holding that 
Article III standing is necessary for intervention), and Unit-
ed States v. 36.96 Acres of Land, 754 F.2d 855, 859 (7th Cir. 
1985) (concluding that intervention under Rule 24 requires 
interest greater than that of standing), we believe it impera-
tive that we now explain why we conclude that a prospective 
s 2348 intervenor must have standing to participate as an 
intervenor rather than only as an amicus curiae.

     In City of Cleveland, the court denied the Alabama Electric 
Cooperative's ("AEC") motion to intervene in a dispute be-
tween the Nuclear Regulatory Commission ("NRC") and two 

nuclear power plants as to whether the latter could suspend 
the antitrust conditions in their operating licenses.  Although 
it lacked Article III standing, in that it had no relationship 
whatsoever with the petitioners, their competitors, or the 
geographic market at issue, AEC sought to intervene on the 
side of the NRC, because it feared that an adverse decision 
could lead a competitor to seek a similar suspension of its 
antitrust conditions.  In denying AEC's motion, the court 
relied heavily upon Southern Christian Leadership Confer-
ence v. Kelley, 747 F.2d 777, 779 (D.C. Cir. 1984), wherein the 
court held that Article III standing is necessary for interven-
tion under Rule 24(a)(2) of the Federal Rules of Civil Proce-
dure.  In particular, the court focused upon what it consid-
ered the rationale underlying the Kelley decision, namely that 
"because a Rule 24 intervenor seeks to participate on an 
equal footing with the original parties to the suit, he must 
satisfy the standing requirements imposed on those parties."  
City of Cleveland, 17 F.3d at 1517.  Because a prospective 
s 2348 intervenor similarly seeks to participate like a party, 
the court reasoned, it should be treated like a party.  Accord-
ingly, as we had held in Kelley, it must satisfy the standing 
requirements imposed on parties.

     The City of Cleveland court did not differentiate those 
seeking to intervene with party-like status from those seeking 
a lesser degree of participation.  It instead assumed that 
prospective intervenors always sought to participate on an 
equal footing with the original petitioner.  Although the City 
of Cleveland court did not then address the situation we now 
face, we nevertheless believe that its more general conclusion 
remains valid:  there is no reason to believe that Congress 
intended to create two tiers of s 2348 intervenors based upon 
the presence or absence of standing.  See id.

     The language of s 2348 alone does not settle the proper 
relationship between Article III standing and intervention, 
but the general structure that Congress has provided for 
appellate review of agency action strongly militates towards 
reading s 2348 to require Article III standing as a prerequi-
site to intervention.  A party petitioning for review of agency 
action must have standing, and the intervention rules help to 

govern which existing suits a prospective party may legiti-
mately join.  In this case, Longhorn essentially seeks to 
participate as an amicus curiae--it sought only to contribute 
its views to those issues raised by Rio Grande's petition for 
review and, had Rio Grande ceded some of its oral argument 
time, to participate in oral argument.  Diamond v. Charles, 
476 U.S. 54, 62-64 (1986), says that an entity lacking Article 
III standing can do no more than that.  As Longhorn readily 
admits, in the status that it seeks, it could neither petition for 
rehearing en banc nor petition for certiorari unless Rio 
Grande first did the same.  Thus, for the sake of clarity, 
simplicity, and administrative rationality, we believe that such 
limited participation should be accorded in the form of ami-
cus, and not intervenor.  Those who possess Article III 
standing, on the other hand, can either petition for review 
directly, particularly if they desire to raise any additional 
issues, or intervene under s 2348, in which case they normal-
ly would be limited to the scope of the original petition for 
review.  See National Ass'n of Regulatory Utility Comm'rs 
v. ICC, 41 F.3d 721, 729-30 (D.C. Cir. 1994) (stating that only 
in extraordinary cases will an intervenor be permitted to 
raise additional issues not raised by petitioners).  For those 
who have participated before the agency, s 2348 explicitly 
provides that choice, allowing

     any party in interest in the proceeding before the agency 
     whose interests will be affected if an order of the agency 
     is or is not enjoined, set aside, or suspended [to] appear 
     as parties thereto of their own motion and as of 
     right....Communities, associations, corporations, firms, 
     and individuals, whose interests are affected by the order 
     of the agency, may intervene in any proceeding to review 
     the order.
     
For those who have Article III standing but failed to partici-
pate at the agency level, s 2348 merely permits intervention.

     On the record here, there is no doubt that Longhorn is not 
a proper intervenor.  It appears that Longhorn is really 
seeking to appear as an amicus.  Because we have discretion 
to grant a party such status, see Fed. R. App. P. 29(a), we will 

accord Longhorn amicus status so that its views on the 
common issues can be considered.

B.   Aggrievement and Ripeness

     FERC argues that Rio Grande is not aggrieved by the 
disputed orders, and that, even if it is aggrieved, the orders 
are not ripe for review.  The Commission is wrong on both 
counts.

     A party seeking review of a final Commission order must 
demonstrate that it has been "aggrieved" by the order.  See 
28 U.S.C. s 2344 (1994).

     Like all parties seeking access to the federal courts, 
     petitioners are held to the constitutional requirement of 
     standing.  Common to both these thresholds is the re-
     quirement that petitioners establish, at a minimum, inju-
     ry in fact to a protected interest.  To demonstrate injury 
     in fact, petitioners must identify an invasion of a legally 
     protected interest which is (a) concrete and particular-
     ized, and (b) actual or imminent, not conjectural or 
     hypothetical.
     
Shell Oil Co. v. FERC, 47 F.3d 1186, 2000 (D.C. Cir. 1995) 
(citations and internal quotation marks omitted).

     In this case, FERC argues that Rio Grande has not been 
injured, because Rio Grande may charge the rate it sought to 
charge pursuant to s 342.2(b).  However, this conclusion 
misses the point.  Rio Grande filed its petition for a declara-
tory order specifically because it sought the security of a rate 
approval under s 342.2(a).  FERC's refusal to approve Rio 
Grande's rate under s 342.2(a) means that the current rate 
may be rendered ineffective if any party files a protest.  Rio 
Grande argues that this affects both its present economic 
behavior--investment plans and creditworthiness--and its fu-
ture business relationships.  In particular, Rio Grande as-
serts that the orders "have had a profoundly negative effect 
on the active marketing of [this] project to new potential 
users," have made existing and potential investors "extremely 
skeptical over further investment in the project," and have 
"negatively impact[ed] both [Rio Grande's] ability to raise 

debt capital and its general creditworthiness."  Brief of Rio 
Grande at 19-20.  FERC does not dispute these contentions.

     On the record at hand, there can be no serious doubt over 
Rio Grande's aggrievement by virtue of FERC's orders.  As 
indicated, Rio Grande is suffering present economic injury as 
a result of the orders.  See, e.g., Great Lakes Gas Transmis-
sion Ltd. Partnership v. FERC, 984 F.2d 426, 430 (D.C. Cir. 
1993) (holding that showing of "present injurious effect on [a 
petitioner's] business decisions and competitive posture within 
the industry" is sufficient to prove that petitioner is ag-
grieved).  There can also be no doubt that Rio Grande 
satisfies the remaining Article III standing requirements, 
because its injury flows from the FERC orders under review 
and may be redressed if this court grants its petition for 
review.  It therefore has standing to petition for review of the 
FERC orders at issue here.

     FERC also claims that, even if Rio Grande has been 
aggrieved and has standing to contest the disputed orders, 
the case should nonetheless be dismissed as unripe.  On this 
score, FERC contends that Rio Grande's petition is unfit for 
review, because Rio Grande "has not shown that the contest-
ed orders have had any immediate impact on its daily affairs," 
and that FERC has "not applied its pronouncements on 
original cost to any of [Rio Grande's] actual rates."  Brief for 
FERC at 20-21.  This is a mangled view of the ripeness 
doctrine, and we reject it.

     As we noted in Mississippi Valley Gas Co. v. FERC, 68 
F.3d 503, 508 (D.C. Cir. 1995), in applying the ripeness 
doctrine,

     we are to consider the nature of the challenged issue and 
     inquire whether the agency action is sufficiently final for 
     review.  When a petitioner raises a purely legal question, 
     we assume that issue is suitable for judicial review.  
     However, our assessment of the finality of the agency 
     action also includes consideration of whether the agency 
     or the court will benefit from deferring review until the 
     agency's policies have crystallized and the question arises 
     in some more concrete and final form.
     
(citations and internal quotation marks omitted).  In other 
words, a case is ripe when it "presents a concrete legal 
dispute [and] no further factual development is essential to 
clarify the issues ... [and] there is no doubt whatever that 
the challenged [agency] practice has 'crystallized' sufficiently 
for purposes of judicial review."  Payne Enters., Inc. v. 
United States, 837 F.2d 486, 492-93 (D.C. Cir. 1988).  The 
Commission is quite wrong in its implicit suggestion that Rio 
Grande's petition must be dismissed absent a showing of 
"hardship," for, "under the ripeness doctrine, the hardship 
prong of the [Abbott Laboratories v. Gardner, 387 U.S. 136, 
149 (1967) ] test is not an independent requirement divorced 
from the consideration of the institutional interests of the 
court and agency."  Id. at 493;  accord City of Houston v. 
HUD, 24 F.3d 1421, 1431 n.9 (D.C. Cir. 1994).  Under these 
well-established principles, the Commission's claim that this 
case is unripe for review must be rejected.

     The record here shows conclusively that this case presents 
a concrete legal dispute and that FERC's policy is crystal-
lized.  In Rio Grande I, the Commission stated:

     In this case, whether or not Rio Grande satisfies the two-
     prong test, we must deny its request. That test presup-
     poses a write-up that would be permissible if the test 
     were satisfied.  That is not the case here.  In this 
     instance, the seller of the acquired line, Navajo, has an 
     equity position in Rio Grande through an affiliate, Navajo 
     Southern, one of the partners of Rio Grande.  Rio 
     Grande argues that in this case Navajo Southern's equity 
     interest should not be a bar to the write-up, because it 
     was essential to structuring an agreement acceptable to 
     Navajo so that the project could go forward.  The gener-
     al rule, however, is that the depreciated cost of an 
     acquired asset must be used in cost-of-service calcula-
     tions where the former owner not only receives the 
     higher price but also has an equity interest in the 
     acquiring company.  This is so because otherwise the 
     seller "might benefit from the higher cost of service on 
     the line, which it cannot do as the owner of a regulated 
     
     asset at this time."  Thus, we must deny Rio Grande's 
     request for a write-up.
     
78 F.E.R.C. at 61,082 (quoting Longhorn I, 73 F.E.R.C. at 
62,113).  In Rio Grande II, the Commission reaffirmed its 
position:

     Here, we have a regulated entity allegedly changing its 
     service and requesting a write-up of the assets dedicated 
     to the new service....In the absence of Navajo's equity 
     interest, this case might fall within one of the recognized 
     exceptions to the general rule.  However, we need not 
     address this issue because in this case a company is 
     selling the asset to itself.  To allow the write-up in this 
     situation would open the door to circumvention of the 
     purpose of the original cost concept....Accordingly, we 
     will deny rehearing.
     
82 F.E.R.C. at 61,548.  It is clear here that the Commission 
has decided that the benefits exception cannot be used where 
a selling entity acquires an equity interest in the purchaser as 
a result of the transaction, and has applied this new rule by 
denying Rio Grande's request for approval of its cost-justified 
rates.  Thus, because FERC's orders raise a concrete legal 
dispute regarding a policy that has crystallized to its final 
form, the orders are ripe for review.

C.   The Merits

     We now turn to the merits of Rio Grande's challenge:  
FERC's refusal to apply the benefits exception based on 
Navajo's equity interest in Rio Grande.  We review the 
Commission's orders under the usual arbitrary and capricious 
standard.  See Williston Basin Interstate Pipeline Co. v. 
FERC, 165 F.3d 54, 60 (D.C. Cir. 1999);  5 U.S.C. s 706(2)(A) 
(1994).  In this context, our role is "limited to assuring that 
the Commission's decisionmaking is reasoned, principled, and 
based upon the record."  Pennsylvania Office of Consumer 
Advocate v. FERC, 131 F.3d 182, 185 (D.C. Cir. 1997) (cita-
tions and internal quotation marks omitted).

     Rio Grande argues that the Commission acted arbitrarily 
and capriciously, because it did not adequately explain its 

refusal to permit the inclusion of the full cost of the acquired 
line in Rio Grande's rate base.  We agree.

     As noted above, normally when a facility is acquired by one 
regulated entity from another, the purchaser may only in-
clude the seller's depreciated original cost in its rate base, 
even though the price paid by the purchaser may exceed that 
amount.  However, under the benefits exception, the Com-
mission has permitted the purchasing pipeline to include the 
full purchase price of an acquired asset in its cost-of-service 
computations if the pipeline can show that:  (1) an acquired 
facility is being put to new use, and (2) the purchase price is 
less than the cost of constructing a comparable facility.  See 
Longhorn I, 73 F.E.R.C. at 62,112-13.

     In its orders below, FERC did not even reach the question 
of whether Rio Grande satisfied the two-prong exception;  
instead, it concluded that the exception could not be employed 
where the seller acquires an equity position in the purchaser:  
"[t]he general rule...is that the depreciated cost of an ac-
quired asset must be used in cost-of-service calculations 
where the former owner not only receives the higher price 
but also has an equity interest in the acquiring company."  
Rio Grande I, 78 F.E.R.C. at 61,082.  On rehearing, FERC 
did not waver from this position, stating that it considered the 
deal between Rio Grande and Navajo one in which the 
"company is selling the asset to itself."  Rio Grande II, 82 
F.E.R.C. at 61,548.

     The Commission now claims that it has simply interpreted 
its original cost rule and the exception thereto.  This self-
serving explanation cannot carry the day.  The Commission 
in this case has effectively added a new per se exclusion to the 
application of the benefits exception when an asset's seller 
acquires an interest in the purchaser.  The creation of this 
per se exception makes no sense and, indeed, FERC cites no 
established authority or plausible reasons in support of it.

     First, on its face, the retention of some interest in the 
acquired facilities in lieu of a money payment will reduce the 
cost basis included in Rio Grande's rate base and, thus, rates 
will be lower than if the facilities were sold solely for money.  

This result would appear to be in the public interest.  Re-
duced rates result because, as Rio Grande made clear at oral 
argument, the amount it seeks to include in its rate base is 
only the total amount of money paid and does not include the 
value of any equity interest.  Thus, in a situation such as this, 
if a company will sell its facility for $100 outright or $80 plus 
a 5% equity interest, the better deal for the ratepayer is the 
$80-plus-equity deal, because $80, rather than $100, may be 
included in the rate base.

     Moreover, it is clear that Rio Grande has put the pipeline 
to a new use:  transportation of NGLs.  From the perspective 
of an acquiring entity, concepts of "depreciation" are normally 
inapposite in such circumstances.  Thus, it hardly makes 
sense for FERC to require the use of a depreciated figure in 
this situation where the use is brand new.

     The Commission stated in Rio Grande II that "[t]o allow 
[a] write-up in this situation would open the door to circum-
vention of the purpose of the original cost concept." 82 
F.E.R.C. at 61,548.  Although this is a valid concern, the door 
was already opened to this possibility when FERC permitted 
the benefits exception in the first place.  And to the extent 
that FERC is worried about sham transactions where equity 
interests are involved, no party has claimed that every trans-
action of the sort at issue here is unethical and a sham.  
Indeed, there does not appear to be any difference between a 
deal of this sort and one in which a seller receives money for 
the asset, but later uses that money towards the acquisition of 
an interest in the purchaser.  Presumably, this second deal 
would qualify for consideration under the benefits exception, 
since the seller did not become affiliated with the purchaser 
as a result of the sale.  However, the Commission has not 
explained why the first deal is cause for such concern that it 
may never qualify for the benefits exception, whereas the 
second deal may.  In addition to this apparent inconsistency, 
it is also not clear how there could even be sham transactions, 
given the requirement that there must be a new use for the 
facility, and that the purchase price must be less than the cost 
of building anew.

     To the extent that the Commission is troubled by these 
transactions, there are surely ways, short of a per se exclu-

sion, to ensure that the deal was negotiated at arm's length.  
In fact, it is difficult to discern why the Commission would 
not consider other possibilities short of prohibiting the appli-
cation of the benefits exception to these sorts of deals, when 
limiting purchasers to all-cash deals could result in higher 
prices and thus harm to ratepayers.  Arguably, the Commis-
sion might decide that a per se rule or even a substantially 
more rigid version of the benefits test is appropriate based on 
reasoned findings regarding affiliate transactions.  However, 
we need not address these possibilities;  as it now stands, the 
Commission's orders defy good reason.  We therefore reverse 
and remand this case to the Commission for further consider-
ation.

                         III. Conclusion

     For the foregoing reasons, we deny Longhorn intervenor 
status in this proceeding, but grant it amicus status.  We also 
grant Rio Grande's petition for review and remand for further 
proceedings consistent with this opinion.

                                                      So ordered.