[Cite as Dublin v. Wirchanski, 2011-Ohio-2461.]
IN THE COURT OF APPEALS OF OHIO
THIRD APPELLATE DISTRICT
UNION COUNTY
CITY OF DUBLIN,
PLAINTIFF-APPELLANT, CASE NO. 14-10-22
v.
JOHN L. WIRCHANSKI, ET AL., OPINION
DEFENDANTS-APPELLEES.
Appeal from Union County Common Pleas Court
Trial Court No. 2008 CV 0535
Judgment Affirmed
Date of Decision: May 23, 2011
APPEARANCES:
Alan G. Starkoff and Asim Z. Haque for Appellant
Robert J. Behal and Michael Braunstein for Appellee, John L.
Wirchanski
Rick Rodger for Appellee, Union County Treasurer
Case No. 14-10-22
PRESTON, J.
{¶1} Plaintiff-appellant, the City of Dublin (hereinafter “Dublin”), appeals
the judgment of the Union County Court of Common Pleas, which denied
Dublin’s request to partially abandon its appropriation proceedings with respect to
two of the three parcels of land involved that were owned by defendant-appellee,
John Wirchanski (hereinafter “Wirchanski”). For the reasons that follow, we
affirm.
{¶2} This case concerns an appropriation action filed by Dublin on October
28, 2008 for three parcels of land owned by Wirchanski, and its subsequent
request to partially abandon the appropriation proceedings pursuant to R.C.
163.21(A)(1). Essentially, this case involves the issue of whether Dublin took
possession of Parcel 91-WL for purposes of R.C. 163.21(A), such that it was not
allowed to abandon its appropriation proceedings as to that particular parcel. The
facts are largely not in dispute and are stated as follows.
{¶3} In 2004, Dublin began contemplation of the US 33/SR 161/Post Road
interchange project. The design work for the project was conducted through 2006
and the construction plans for the project, which was broken down into three
-2-
Case No. 14-10-22
phases, were finalized sometime in 2007.1
{¶4} For its 33/161 Project, Dublin needed three specific parcels of land,
which were all owned by Wirchanski. As a result, Dublin contacted Wirchanski
around 2006 regarding his property and the construction of 33/161 Project. At that
time, these parcels, along with Wirchanski’s remaining adjoining property, were
being farmed on behalf of Wirchanski by a sharecrop farmer.
{¶5} Due to Wirchanski’s opposition in negotiations with Dublin for his
property, on October 28, 2008, Dublin commenced an appropriation lawsuit
against Wirchanski in order to appropriate, in fee simple, three parcels of land
from Wirchanski for the construction of the 33/161 Project.
{¶6} The three parcels of land are commonly referred to as Parcel 71-WD,
Parcel 91-WL and Parcel 92-WL,2 and the acreage of each of these takes are as
follows:
1. Parcel 71-WD: 4.651 acres
2. Parcel 91-WL: 13.407 acres
3. Parcel 92-WL: 1.745 acres
1
Prior to commencing the appropriation proceedings involved in the case sub judice, Dublin acquired by
means of eminent domain a fee simple interest in 3.449 acres of property underneath where the Industrial
Parkway was to go, which was located in between two of the parcels involved in this appropriation
proceedings.
2
These three tracts of land were commonly referred to as Parcel 71-WD, Parcel 91-WL, and Parcel 92-WL
during the proceedings below and were labeled as such administratively by Dublin. Because these
designations were consistently used throughout the proceedings and were accepted by the parties and the
trial court, we will continue to refer to the three tracts by their administrative labels for ease of our
discussion.
-3-
Case No. 14-10-22
At the same time the complaint was filed, pursuant to a Joint Motion for
Distribution of Funds and consistent with its appraisals, Dublin tendered a check
in the amount of $6,881,128.00 to Wirchanski, which was broken down by parcel
as follows:
1. Parcel 71-WD: $ 1,630,002.00
2. Parcel 91-WL: $ 4,982,599.00
3. Parcel 92-WL: $ 268,527.00
The parties stipulated further that the payment to Wirchanski entitled Dublin to
full possession of, and the absolute right to enter upon the property. Nevertheless,
Wirchanski disputed Dublin’s appraisals, in particular arguing that Parcel 91-WL
was worth somewhere between $8,076,876.00 - $8,980,525.00.
{¶7} The parties continued to litigate the issue regarding the value of the
appropriated real property for over a year, until April 21, 2010, when Dublin filed
a notice of partial abandonment. In particular, Dublin sought to abandon the
appropriation of Parcels 91-WL and 92-WL, but not the appropriation of Parcel
71-WD since, as it admitted in its pleading, it had already taken possession of that
particular parcel.
{¶8} Wirchanski filed a motion to strike claiming that Dublin could not
abandon part of its appropriation proceedings, but instead had to dismiss its entire
appropriation proceedings pursuant to R.C. 163.21(A). In addition, Wirchanski
also filed a motion in opposition claiming that Dublin could not abandon Parcels
-4-
Case No. 14-10-22
91-WL and 92-WL because it had already taken possession of those parcels.
Dublin filed a response and requested an evidentiary hearing on the issue of
possession and abandonment. The trial court overruled Wirchanski’s motion to
strike and ordered that an evidentiary hearing take place concerning the issue of
the possession of Parcels 91-WL and 92-WL.
{¶9} An evidentiary hearing was held on July 2, 2010 and July 23, 2010 for
the purpose of determining whether Dublin could rightfully exercise its statutory
right to abandon the remaining two parcels of land.
{¶10} On August 19, 2010, after reviewing all of the evidence presented at
the evidentiary hearing, the trial court issued its journal entry finding that Dublin
had not taken possession of Parcel 92-WL, but had taken possession of Parcel 91-
WL. As a result, the trial court found that Dublin could abandon Parcel 92-WL
but could not abandon Parcel 91-WL, and subsequently ordered the matter be set
for trial to determine the value of Parcel 91-WL.
{¶11} Dublin now appeals and raises the following assignment of error for
our review.3
ASSIGNMENT OF ERROR
THE TRIAL COURT ERRED AS A MATTER OF LAW BY
DENYING DUBLIN ITS STATUTORY RIGHT OF
3
Although Wirchanski appears to set forth an assignment of error of his own, no timely notice of cross
appeal was filed and the purported assignment of error will be disregarded as it is not properly before this
Court. See App.R. 4(B)(1).
-5-
Case No. 14-10-22
ABANDONMENT UNDER O.R.C. § 163.21, THEREBY
COMPELLING DUBLIN TO ACQUIRE 13.407 ACRES OF
PROPERTY FROM APPELLEE THAT ARE NO LONGER
NEEDED FOR A PUBLIC ROADWAY CONSTRUCTION
PROJECT.
{¶12} In its only assignment of error, Dublin argues that the trial court
erred as a matter of law in finding that Dublin had possessed Parcel 91-WL, and,
thus, was not permitted to abandon its appropriation proceeding as to that
particular parcel.
{¶13} The statutory provision at issue in the case sub judice is R.C. 163.21,
which in pertinent part, states:
(A)(1) If it has not taken possession of property that is
appropriated, an agency may abandon appropriation
proceedings under section 163.01 to 163.22 of the Revised Code
at any time after the proceedings are commenced but not later
than ninety days after the final determination of the cause.
(2) In all cases of abandonment as described in division (A)(1) of
this section, the court shall enter a judgment against the agency
for costs, including jury fees, and shall enter a judgment in favor
of each affected owner, in amounts that the court considers to be
just, for each of the following that the owner incurred:
(a) Witness fees, including expert witness fees;
(b) Attorney’s fees;
(c) Other actual expenses.
{¶14} However, before we address Dublin’s assignment of error, we must
first address the alleged procedural defect that Wirchanski claims occurred in this
case. In particular, Wirchanski claims that Dublin could not have filed its notice
of partial abandonment with respect to the individual parcels involved because,
-6-
Case No. 14-10-22
pursuant to R.C. 163.21, it was only permitted to abandon its “appropriation
proceedings” in its entirety. Initially, we note that Wirchanski did not file an
appeal or cross-assignment of error claiming that the trial court erred in allowing
Dublin to amend its complaint. Nevertheless, even if we were to assume that the
issue is properly before us to consider, we would find that the trial court did not
err because, regardless of whether Dublin could amend its complaint or had to
voluntarily dismiss its entire proceeding, the ultimate question that the trial court
had to determine was whether Dublin possessed Parcel 91-WL such that it would
not be permitted to abandon the appropriation proceedings under R.C.
163.21(A)(1). Since the trial court actually made a determination of “possession”
in its judgment entry, we find that no error occurred.
{¶15} While Wirchanski presented the exact issue below in his motion to
strike Dublin’s notice of partial abandonment, the trial court overruled
Wirchanski’s motion to strike finding that Dublin’s pleading was a motion for
leave to amend its complaint. Rejecting Wirchanski’s argument, the trial court
found that, “[a]lthough R.C. 163.21 may under certain circumstances authorize the
abandonment of an appropriation proceeding, once a Complaint has been filed,
R.C. 163.21 does not operate in isolation. The City’s Notice of Partial
Abandonment can be viewed an amendment to the Complaint and thereby within
the purview of Civil Rule 15.” (May 25, 2010 JE).
-7-
Case No. 14-10-22
{¶16} First of all, we believe that the trial court did not err in treating
Dublin’s pleading as a motion for leave to amend its complaint. Here, while
Dublin originally requested to appropriate Parcels 71-WD, 91-WL, and 92-WL, it
later requested to abandon Parcels 91-WL and 92-WL and to continue the
appropriation and subsequent valuation of Parcel 71-WD. Thus, it essentially was
asking the trial court to allow it to amend its original appropriation complaint to
only include Parcel 71-WD. Pursuant to Civ.R. 15(A), after responsive pleadings
have been served, “a party may amend his pleading only by leave of court or by
written consent of the adverse party,” and according to the rules, “[l]eave of court
shall be freely given when justice so requires.” Civ.R. 15(A). As the Ohio
Supreme Court has recognized, the proper way for a plaintiff to dismiss fewer than
all claims against a defendant is to amend the complaint pursuant to Civ.R. 15(A).
Pattison v. W.W. Grainger, Inc., 120 Ohio St.3d 142, 2008-Ohio-5276, 897
N.E.2d 126, at ¶19. Other courts have approved of Civ.R. 15’s application in
appropriation proceedings: Madison Cty. Bd. of Commrs. v. Bell, 12th Dist. No.
CA2005-09-036, 2007-Ohio-1373, ¶¶79-82 (finding no prejudicial error in the
trial court’s decision granting the board of commissioners leave to amend its
complaint; the original complaint sought a fee simple interest in the property, and
was amended to request only an easement); Dorsey v. Donohoo (1992), 83 Ohio
App.3d 415, 421-23, 615 N.E.2d 239 (finding no error in allowing the board of
-8-
Case No. 14-10-22
county commissioners to amend its appropriation petition to add an easement for
ingress and egress on the landowner’s property); Montgomery County v. McQuary
(1971), 26 Ohio Misc. 239, 239-42, 265 N.E.2d 812 (finding that Civ.R. 15(A)
applied to appropriation proceedings, but that the amended complaint brought into
consideration R.C. 163.21).
{¶17} Nevertheless, regardless of whether a party may amend its
appropriation complaint, like the trial court allowed Dublin to do in this case, or
whether a party must voluntarily dismiss its entire appropriation proceedings, any
attempted change to the underlying appropriation action automatically triggers
R.C. 163.21 considerations and must be dealt with first. Again, R.C. 163.21(A)
states that “[i]f it has not taken possession of property that is appropriated, an
agency may abandon appropriation proceedings.” Typically, the question that is
presented with respect to R.C. 163.21 is whether the agency’s particular action
constituted abandonment of the appropriation proceedings such that it now owes
the landowner costs and expenses of the litigation. For example, with respect to
dismissals, courts have generally held that when an agency voluntarily dismisses
its appropriation action, it has abandoned the appropriations proceedings for
purposes of R.C. 163.21(A), and, thus, must pay the landowner’s costs and
expenses of the litigation. See Ohio Edison Co. v. Franklin Paper Co., Inc.
(1985), 18 Ohio St.3d 15, 479 N.E.2d 843, at paragraph one of syllabus
-9-
Case No. 14-10-22
(discussing what actions constitute abandonment in appropriation proceedings
under R.C. 163.21 and holding an agency does not abandon an appropriation
proceeding for purposes of R.C. 163.21 when it pursues the proceedings to trial,
but does not prevail); Ohio Edison Co. v. Long (May 13, 1987), 9th Dist. No.
12883, at *1 (finding that an agency does not abandon its appropriation
proceedings for purposes of R.C. 163.21 when an agency voluntarily dismisses the
proceedings because the landowner prevails and conclusively establishes his
defense to the appropriation action); City of Toledo v. Chambers (Feb. 1, 1991),
6th Dist. No. L-90-021, at *2-3 (finding that an agency’s voluntary dismissal
amounts to an abandonment of the appropriation proceedings for purposes of R.C.
163.21 despite the agency’s claims that it intended to re-file its appropriation
action in the future); Dept. of Natural Resources v. Sellers (1968), 14 Ohio App.2d
132, 237 N.E.2d 328, paragraph one of the syllabus (holding that where an agency
files an action to appropriate property pursuant to Chapter 163, and such action is
voluntarily dismissed without prejudice prior to final determination, such
dismissal constitutes an abandonment of the proceedings under R.C. 163.21(A)).
Compare City of Alliance v. Whinery (Nov. 13, 2000), 5th Dist. No.
2000CA00137, at *2-3 (distinguishing Sellers and finding that landowner’s own
conduct contributed to city’s decision to dismiss the appropriation proceedings and
landowner was not an “affected owner” under R.C. 163.21 since she had already
-10-
Case No. 14-10-22
sold her property, thus city’s dismissal did not amount to an abandonment for
purposes of R.C. 163.21).
{¶18} Similarly, depending on the facts of the case, courts have held that an
agency has abandoned for purposes of R.C. 163.21(A) when it has “amended” its
original appropriation action. Madison Cty. Bd. of Commrs., 2007-Ohio-1373, at
¶¶79-82 (finding no prejudicial error in the trial court’s decision granting the board
of commissioners leave to amend its complaint; the original complaint sought a
fee simple interest in the property, and was amended to request only an easement).
See, also, Dorsey, 83 Ohio App.3d at 421-23 (finding that amendment did not
amount to an abandonment of the proceedings since the agency only added an
easement for ingress and egress on the landowner’s property, thus landowner was
not entitled to attorney fees and expenses); Montgomery County, 26 Ohio Misc. at
239-42 (finding that the amended complaint was tantamount to an abandonment of
the original proceedings such that the landowner was entitled to costs and
expenses).
{¶19} Here, it is clear that the proposed amendment to Dublin’s complaint
amounted to an abandonment of the appropriation proceedings as to Parcels 91-
WL and 92-WL. Thus, the only question was whether Dublin was allowed to
amend its complaint in that manner, because as the language in R.C. 163.21
explicitly states, an agency may abandon appropriation proceedings, “[i]f it has
-11-
Case No. 14-10-22
not taken possession of property that is appropriated.” R.C. 163.21(A) (emphasis
added). Since there was a dispute about whether Dublin had taken possession of
Parcel 91-WL, the trial court had to first determine whether Dublin had taken
possession of Parcel 91-WL before it could determine whether Dublin could
amend its complaint as to that parcel. Therefore, we find that the trial court
properly granted Dublin an evidentiary hearing, because ultimately if Dublin had
taken possession of Parcel 91-WL then it could not “abandon” its appropriation
proceedings as to that parcel, regardless of whether Dublin had to voluntarily
dismiss its entire action or could amend its appropriation complaint to exclude
Parcels 91-WL and 92-WL.
{¶20} Now with respect to Dublin’s assignment of error, Dublin claims that
the trial court erred as a matter of law in denying its right to statutorily abandon its
appropriation proceedings when the evidence did not support the trial court’s
finding that it had taken possession of Parcel 91-WL. We disagree.
{¶21} As we stated above, the central issue in this case is whether Dublin
took possession of Parcel 91-WL for purposes of R.C. 163.21(A), such that it
could not abandon its appropriation proceedings as to that particular parcel. We
believe that such a determination centers on the facts and circumstances of each
individual case and, as such, a trial court should be afforded broad discretion in
determining whether the public agency has taken possession of the appropriated
-12-
Case No. 14-10-22
property. Thus, an appellate court should not substitute its judgment for that of the
trial court unless its decision amounts to an abuse of discretion. An abuse of
discretion suggests the trial court’s decision is unreasonable, arbitrary, or
unconscionable. Blakemore v. Blakemore (1983), 5 Ohio St.3d 217, 219, 450
N.E.2d 1140. After reviewing the record, we find that the trial court did not abuse
its discretion in finding that Dublin had taken possession of Parcel 91-WL, and
thus, could not abandon its appropriation proceedings as to that particular parcel.
{¶22} An evidentiary hearing was conducted over two days. In addition to
the multitude of documentary evidence presented by both parties, Dublin
presented testimony from Dana McDaniel, the Deputy City Manager and Director
of Economic Development for the City of Dublin, who oversaw the 33/161
Project, and deposition testimony from Kenneth Richardson, Dublin’s Engineering
Manager-Design. Additionally, Wirchanski testified at the hearing and presented
deposition testimony from James Page, an engineer who was hired to prepare
maps, examine surveys, deeds and tax maps on the appropriated real property.
{¶23} After considering all of the testimony and documentary evidence
presented, the trial court ultimately concluded that Dublin had taken possession of
Parcel 91-WL. (Aug. 19, 2010 JE at 27). The trial court’s decision was largely
based on the following affirmative actions taken by Dublin, through its agents:
-13-
Case No. 14-10-22
1. Trucco Construction Company, the contractor hired by Dublin,
as its agent, entered Parcel 91-WL on or about November 2009 and
staked components of a drainage swell or drainage ditch outfall,
which was in furtherance of Dublin’s construction plan.
(Richardson Depo. at page 20, line 20 and page 21, line 2). Because
of the contractor’s stakes, Wirchanski testified that he instructed his
sharecrop farmer not to enter the staked area because there was the
possibility of his farmer’s equipment getting damaged. (July 23,
2010 Tr. at 31).
2. Clearcut, a subcontractor of Trucco Construction Company,
thereafter, was hired to clear an area of trees and vegetation on
Parcel 91-WL as required for the drainage swell or drainage ditch
outfall project pursuant to the construction plans. Clearcut actually
cleared some of the trees and vegetation on Parcel 91-WL sometime
between November 20 and December 1, 2009. (Richardson Depo. at
page 21, lines 3-7 and page 25, lines 4-13). The area cleared of trees
and vegetation was approximately 90-100 feet wide along a portion
of the south line of the parcel.
3. Dublin hired Performance Site Environment to conduct
environmental studies at two locations on the southern part of Parcel
91-WL for purposes of looking for possible old underground
gasoline storage tanks. (July 2, 2010 Tr. at 62); (Richardson Depo.
at page 21, lines 8-13 and page 22, lines 22-23). On or about
December 16, 2009, Performance Site Environment performed the
environmental studies for Dublin on Parcel 91-WL, and only
discovered metal feeder pipes, but found no gasoline storage tanks.
(Richardson Depo. at page 23, line 17-20). While Performance Site
Environment had to enter onto Parcel 91-WL to conduct its testing,
the trial court noted that pursuant to R.C. 163.03, Dublin was
permitted entry upon the property subject to the appropriation
proceeding for surveys, soundings, drillings, appraisals, and
examinations.
4. Trucco Construction Company stored concrete barriers and
water main pipe on Wirchanski’s property contiguous to, but not
within the bounds of Parcel 91-WL. (Richardson Depo. at page 27,
line 21 – page 28, line 3); (July 2, 2010 Tr. at 51-52, 103); (July 23,
-14-
Case No. 14-10-22
2010 Tr. at 28); (Plaintiff’s Exs. 19 and 20). Richardson testified
that once he became aware of the existence of the concrete barriers
and water main pipe on Wirchanski’s real property, as an employee
of Dublin, he directed that they be immediately removed. (July 2,
2010 Tr. at 52); (Richardson Depo. at page 28, lines 13-15).
5. On December 1, 2009, Richardson, on behalf of Dublin, took
several photographs of different parts of Parcel 91-WL, one of which
showed a piece of construction equipment, a Bobcat, still sitting in
the area where the trees and vegetation were removed on Parcel 91-
WL. (Richardson Depo. at page 32, lines 4-6 and lines 9-12 and
attached Ex. C).
(Aug. 19, 2010 JE at 20-22). The trial court found the photographs, particularly
the one that depicted a Bobcat sitting next to the area where the trees and
vegetation were removed on Parcel 91-WL, significant in rendering its conclusion.
(Id. at 21). As the trial court stated:
[i]t seems significant to the Court that the contractors and/or
subcontractors working on behalf of Plaintiff Dublin left
equipment sitting on parcel 91-WL and no testimony elicited,
nor evidence presented, by Plaintiff Dublin that this equipment
was directed to be removed from the property after Mr.
Richardson noted its existence. In fact, according to Mr.
Richardson, the purpose of the photographs in this situation was
to track progress and he merely commented that there was some
equipment in the photo upon parcel 91-WL. Moreover, this is
the same Mr. Richardson who noted the storage of materials by
Trucco on Defendant Wirchanski’s property, not within the
designated take area, and directed those materials removed.
(Id. at 21-22) (emphasis added). In addition to the actions taken by Dublin’s
agents that occurred directly on Parcel 91-WL, the trial court noted that Dublin
even conducted itself in a manner that further illustrated its current possessory
-15-
Case No. 14-10-22
interest regarding Parcel 91-WL. (Id. at 19-20). In particular, Dublin’s counsel
sent a letter, dated January 6, 2009, to Wirchanski advising Wirchanski not to
plant crops within the designated take areas since construction was anticipated to
begin in 2009 and no compensation would be given for lost crops within the take
areas. (Id.). In response, Wirchanski sent a letter to Dublin, dated January 15,
2009, expressing his confusion regarding Dublin’s letter. Wirchanski explained
that crops had been planted on the land in question for several months prior to the
letter and commencement of the appropriation action. (Id.). Furthermore,
sometime following the commencement of the appropriation action, Wirchanski
discussed the appropriation action with his sharecrop farmer and subsequently the
winter wheat on Parcel 91-WL was allowed to go fallow. (Id.).
{¶24} Based on the actions of the general contractor, its subcontractor, and
even Dublin itself, through its correspondence with Wirchanski concerning the use
of his property, the trial court found that Dublin had taken possession of Parcel 91-
WL to the extent that it would not be allowed to abandon its appropriation
proceedings as to that particular parcel. (Id. at 27).
{¶25} After reviewing the record, we cannot conclude that the trial court
abused its discretion in concluding that Dublin had taken possession of Parcel 91-
WL. The trial court applied the correct statute and addressed the appropriate legal
question: whether Dublin had taken possession of Parcel 91-WL. In addition, the
-16-
Case No. 14-10-22
trial court clearly articulated its findings of fact and conclusions of law, which we
find were supported by the evidence in the record. While Dublin separately
challenges each and every one of the above reasons the trial court made in support
of its conclusion, in this particular case, when looking at the totality of the
circumstances, we believe the trial court did not abuse its discretion in concluding
that Dublin had taken possession of Parcel 91-WL.
{¶26} Nevertheless, Dublin lastly argues that even if we uphold the trial
court’s decision that it had taken possession of Parcel 91-WL, we should find that
Dublin is able to “partially abandon” Parcel 91-WL and take only that portion of
Parcel 91-WL that it actually performed work on. Dublin claims that case law
outside of Ohio “overwhelmingly” supports its position that a public agency can
abandon part of a larger take on one parcel. Despite this fact, as Dublin
acknowledges in its appellate brief, there is a lack of Ohio case law regarding
abandonment, and we can find nothing in Ohio that supports its position that it
should be allowed to abandon just the part of Parcel 91-WL that it performed work
on. Furthermore, we note that in this particular case Dublin’s pleading only
sought to abandon Parcels 91-WL and 92-WL in their entirety. Dublin never
formally requested to be allowed to abandon only the portion of Parcel 91-WL that
it had actually performed work on. Therefore, we decline to address its “partial
abandonment” of Parcel 91-WL any further.
-17-
Case No. 14-10-22
{¶27} Dublin’s assignment of error is, therefore, overruled.
{¶28} Having found no error prejudicial to the appellant herein in the
particulars assigned and argued, we affirm the judgment of the trial court.
Judgment Affirmed
WILLAMOWSKI, J., concurs in Judgment Only.
/jlr
ROGERS, P.J., Concurring Separately.
{¶29} I concur with the result reached by the majority; however, I do so for
different reasons.
{¶30} An appropriation proceedings is initiated by the filing of a petition
pursuant to R.C. 163.05 which provides in pertinent part as follows:
An agency that has met the requirements of sections 163.04 and
163.041 [163.04.1] of the Revised Code, may commence
proceedings in a proper court by filing a petition for
appropriation of each parcel or contiguous parcels in a single
common ownership, or interest or right therein. The petition of a
private agency shall be verified as in a civil action. All petitions
shall contain:
(A) A description of each parcel of land or interest or right
there in sought to be appropriated, such as will permit ready
identification of the land involved; * * *. [Emphasis added.]
-18-
Case No. 14-10-22
R. C. 163.05. The language used in this statute obviously permits the inclusion of
more than one parcel of property to be included in the appropriation proceedings;
however, it is still only one appropriation proceedings.
{¶2} The statute at issue in this appeal provides that “if it has not taken
possession of property that is appropriated, an agency may abandon appropriation
proceedings * * *.” [Emphasis added.] R. C. 163.21. Nothing in the language
used in this section suggests that an agency may abandon one part of the
proceedings, while continuing with other portions. The City of Dublin has
attempted to distinguish the three properties included in its one petition and to
pretend that it filed three separate appropriation proceedings, which it could have
done, but did not.
{¶3} I would therefore find that there is no authority for abandoning one
portion or parcel of property listed in an appropriation petition without abandoning
all parcels listed in the petition. Since Dublin has admitted taking possession of
one of the three parcels, I submit that it cannot now abandon any other parcel
listed in the one petition.
{¶4} I concur with the majority’s conclusion as to the trial court’s finding
that Dublin has taken possession of Parcel 91-WL. However, due to the reasons
stated above, I would find that conclusion to be unnecessary as the entire
abandonment issue should have been denied.
-19-
Case No. 14-10-22
{¶5} The majority has made reference to the trial court’s suggestion that the
motion to abandon was an attempt to amend the petition. I disagree with the trial
court’s suggestion, and would further argue that a party is confined to its own
characterization of its actions, unless both parties are given notice of a suggested
change and an opportunity to respond. Even if Dublin’s motion to abandon was to
be treated as a motion to amend, no amendment was ever filed, or defined
specifically for the record. Furthermore, the trial court’s ruling was directed to the
issue of abandonment, not to any alleged amendment of the petition.
{¶6} I am aware that the trial court’s ruling included an order of
abandonment of Parcel 92-WL, which would be improper under my interpretation
of the statutes. However, since there is no assignment of error by either party
directed to that order, we need not address it.
{¶7} For the reasons stated above, I concur in the affirmance of the ruling
of the trial court.
/jlr
-20-