In the United States Court of Federal Claims
No. 18-556C
(E-Filed: May 3, 2018)1
)
MANAGEMENT & TRAINING )
CORP., )
)
Plaintiff, )
) Bid Protest; Motion to Dismiss for
v. ) Lack of Standing, RCFC 12(b)(1).
)
THE UNITED STATES, )
)
Defendant. )
Alex P. Hontos, Minneapolis, MN, for plaintiff. Daniel D. Falknor and Phil Steger,
Minneapolis, MN, of counsel.
Antonia R. Soares, with whom were Chad A. Readler, Acting Assistant Attorney
General, Robert E. Kirschman, Jr., Director, Franklin E. White, Jr., Assistant Director,
United States Department of Justice, Washington, DC, for defendant. Dennis Adelson,
Peter Dickson, and Vijaya Surampudi, Office of the Solicitor, United States Department
of Labor, of counsel.
OPINION AND ORDER
CAMPBELL-SMITH, Judge.
The court has before it defendant’s motion to dismiss, ECF No. 16, which is
brought pursuant to Rule 12(b)(1) of the Rules of the United States Court of Federal
1
This opinion was issued under seal on April 30, 2018. Pursuant to ¶ 4 of the
ordering language, the parties were invited to identify source selection, proprietary or
confidential material subject to deletion on the basis that the material was
protected/privileged. No redactions were proposed by the parties. Thus, the sealed and
public versions of this opinion are identical, except for the publication date, this footnote
and the correction of one typographical error.
Claims (RCFC). The motion has been fully briefed, as follows: (1) defendant’s motion
to dismiss and appendix, ECF Nos. 16 and 16-1; (2) plaintiff’s response, ECF No. 17;
and, (3) defendant’s reply and appendix, ECF Nos. 18 and 18-1. For background
purposes, the court has also considered the complaint, ECF No. 1, plaintiff’s
memorandum and exhibits in support of its application for a temporary restraining order
and/or preliminary injunction, ECF No. 5, and plaintiff’s supplemental brief and exhibits,
ECF Nos. 12 and 12-1. Oral argument was deemed unnecessary. For the reasons set
forth below, defendant’s motion is GRANTED and the complaint is DISMISSED.
I. Factual Background
The award that underlies this protest is for contracted services for the operation of
the Gary Job Corps Center (Gary) in San Marcos, Texas. ECF No. 1 at 1. There are
actually two procurements concerning Gary that provide the background for this dispute.
One is a longer term five-year contract for the operation of Gary that was solicited, first,
on August 9, 2016, which resulted in a contract award to Adams and Associates (Adams).
ECF No. 16-1 at 102. That contract was awarded on October 30, 2017 and was
scheduled for a term of January 1, 2018 through December 31, 2022, with an initial
phase-in period of December 1-31, 2017. Id. The contract award, however, provoked a
Government Accountability Office (GAO) protest brought by Management & Training
Corporation (MTC), the incumbent contractor at Gary. Id.
After the procuring agency, the United States Department of Labor (DOL),
decided to take corrective action, MTC’s protest was dismissed as academic on
December 6, 2017. Id. Past performance of all offerors was then re-evaluated by DOL
and Adams was again selected as the awardee. Id. The contract won by Adams was
modified to start the phase-in period as of February 1, 2018; however, performance of the
modified contract was interrupted by a second GAO protest brought by MTC. Id.
In response to MTC’s second protest, DOL again proposed corrective action, and
also, according to the complaint, canceled the award to Adams. ECF No. 1 at 5; see also
ECF No. 5 at 85 (describing the selection decision in favor of Adams as “void”). MTC’s
second protest was dismissed by the GAO as academic. ECF No. 1 at 6. MTC continues
to operate Gary under extensions of its incumbent contract through April 30, 2018. ECF
No. 12 at 2-3; ECF No. 16-1 at 102. Thus, at this moment in time, DOL has not
successfully completed its procurement for the next longer term contract for an operator
of Gary, and is in the process of taking corrective action regarding its consideration of
proposals received in response to the solicitation issued in 2016. See ECF No. 17 at 3
(stating that “MTC’s bid is still under consideration by DOL after DOL’s second round
of corrective action for the full five-year contract to operate the Gary JCC.”).
The court turns to the other procurement activity that underlies this suit. DOL, in
March of 2018, solicited bids from a pool of recipients of Indefinite Delivery Indefinite
Quantity (IDIQ) contract awards to operate Gary on an interim basis after MTC’s
2
contract expires on April 30, 2018. ECF No. 16-1 at 102; ECF No. 12-1 at 96. The
“Contingency Contract Vehicle (CCV)” may be used to increase competition for interim
services when a Job Corps Center’s longer term contract award is delayed by bid protests.
ECF No. 16 at 1; ECF No. 16-1 at 102; see also ECF No. 5 at 7 (“The purpose of the
CCV was to obtain operators of a DOL Job Corps Center . . . in a contingency-type
situation.”). The CCV IDIQ competition provided DOL with fourteen contractors ready
to step in to operate a Job Corps Center on an interim basis. ECF No. 16 at 1-2. MTC is
one of these CCV IDIQ contractors. Id. at 1.
As a result of this competition, DOL selected Res-Care, Inc. (Res-Care) as the
CCV contractor to perform the task order services at Gary. ECF No. 1 at 1-2. The
phase-in period is taking place in April 2018, with Res-Care operating Gary from May 1,
2018 through September 30, 2018 as an initial performance period, with an additional six
month option period available, if exercised. ECF No. 16-1 at 102-03. MTC was not
informed of this task order competition, although the other thirteen CCV contractors
were. ECF No. 16 at 2. MTC filed a protest of the task order award to Res-Care on April
5, 2018 at the GAO. ECF No. 1 at 1-2.
DOL did not halt performance of Res-Care’s task order or issue a stop work order
in response to MTC’s protest. ECF No. 1 at 2. MTC filed a bid protest in this court on
April 17, 2018 challenging the agency’s failure to stay contract performance by Res-Care
in response to MTC’s GAO protest. DOL filed a justification of its override of the
automatic stay provided by the Competition in Contracting Act, 31 U.S.C.
§ 3553(d)(3)(A) (2012) (CICA stay), at the GAO on April 19, 2018, and filed its
justification of the CICA stay override in this court on April 20, 2018. ECF No. 16 at 3;
ECF No. 12 at 2. Motions to dismiss, alleging MTC’s lack of standing to protest the task
order award to Res-Care, have been filed in both fora, on April 18, 2018 at the GAO, and
on April 23, 2018 in this court. ECF No. 16 at 1-2. The court reserves discussion of
other relevant facts for the analysis section of this opinion.
II. Legal Standards
A. Standard of Review for Motions Brought Under RCFC 12(b)(1)
When reviewing a complaint to determine its jurisdiction over a plaintiff’s claims,
this court must presume all undisputed factual allegations to be true and construe all
reasonable inferences in favor of the plaintiff. Scheuer v. Rhodes, 416 U.S. 232, 236
(1974), abrogated on other grounds by Harlow v. Fitzgerald, 457 U.S. 800 (1982);
Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 747 (Fed. Cir. 1988) (citations
omitted). However, “[a] trial court may weigh relevant evidence when it considers a
motion to dismiss that challenges the truth of jurisdictional facts alleged in a complaint.”
Ferreiro v. United States, 350 F.3d 1318, 1324 (Fed. Cir. 2003) (citations omitted).
Plaintiff bears the burden of establishing subject matter jurisdiction, Alder Terrace, Inc.
v. United States, 161 F.3d 1372, 1377 (Fed. Cir. 1998) (citing McNutt v. Gen. Motors
3
Acceptance Corp. of Ind., 298 U.S. 178, 189 (1936)), and it must do so by a
preponderance of the evidence, Reynolds, 846 F.2d at 748 (citations omitted). If
jurisdiction is found to be lacking, this court must dismiss the action. RCFC 12(h)(3).
B. Bid Protest Standing
As a threshold jurisdictional matter, the plaintiff in a bid protest must show that it
has standing to bring the suit. Info. Tech. & Applications Corp. v. United States, 316
F.3d 1312, 1319 (Fed. Cir. 2003) (ITAC); Myers Investigative & Sec. Servs., Inc. v.
United States, 275 F.3d 1366, 1369 (Fed. Cir. 2002) (citation omitted). Standing arises
from prejudice, which is present if the plaintiff establishes that it is an interested party
with a direct economic interest in the procurement. ITAC, 316 F.3d at 1319 (citing Am.
Fed’n of Gov’t Employees v. United States, 258 F.3d 1294, 1302 (Fed. Cir. 2001)
(AFGE)). Bid protest standing is limited to those plaintiffs who are “‘actual or
prospective bidders or offerors whose direct economic interest would be affected by the
award of the contract or by the failure to award the contract.’” Weeks Marine, Inc. v.
United States, 575 F.3d 1352, 1359 (Fed. Cir. 2009) (quoting AFGE, 258 F.3d at 1302).
There are two prongs to the test for bid protest standing in the post-award context.
The protestor must “establish that it (1) is an actual or prospective bidder, and
(2) possesses the requisite direct economic interest.” Rex Serv. Corp. v. United States,
448 F.3d 1305, 1307 (Fed. Cir. 2006) (citing Myers, 275 F.3d at 1369). Generally, to
show direct economic interest, the protestor must have had a substantial chance of
winning the contract requirement but for the errors in the procurement. See id. at 1308
(citing Myers, 275 F.3d at 1370; Statistica, Inc. v. Christopher, 102 F.3d 1577, 1582
(Fed. Cir. 1996)). In some procurement scenarios, direct economic interest may be
established by the fact that a qualified contractor was “deprived of the opportunity to
compete” for the procured services. Distributed Sols., Inc. v. United States, 539 F.3d
1340, 1345 (Fed. Cir. 2008) (Distributed).
III. Analysis
The dispute as to MTC’s standing to bring this bid protest is straightforward under
binding precedent.2 In essence, two factual hypotheses might establish standing for MTC
2
The court promised the parties to render a decision within a short time-frame, and
truncates its analysis to keep that promise. Although both parties rely on decisions of this
court, none of the fact patterns in those cases is analogous to this case, and the court has
found the Court of Federal Claims cases cited by the parties to be unhelpful. Given the
need for a timely decision, the distinguishable fact patterns of the cited cases, and the rule
that decisions of this court are not binding precedent for this case, e.g., W. Coast Gen.
Corp. v. Dalton, 39 F.3d 312, 315 (Fed. Cir. 1994), the court restricts its standing analysis
4
in these circumstances. First, plaintiff could argue that MTC was a prospective bidder
and had a substantial chance of winning the CCV task order award that was won by
Res-Care. Myers, 275 F.3d at 1370 (stating that “the substantial chance rule continues to
apply”). Second, plaintiff could argue that MTC was a prospective bidder on a different
type of contract vehicle for interim services at Gary, that DOL deprived MTC of an
opportunity to compete for such a contract, and that this deprivation of a competitive
opportunity confers standing on MTC under Distributed. See 539 F.3d at 1345 (stating,
under the facts of that appeal, that the deprivation of “the opportunity to compete” for
services never procured directly by the government showed that the appellants possessed
“a direct economic interest in the government action at issue”). Neither of these
hypotheses is supported by the factual record before the court, which is undisputed, in
relevant part, by plaintiff.
A. Substantial Chance Requirement Not Satisfied
Plaintiff barely addresses the question of whether MTC had a substantial chance of
winning the task order awarded to Res-Care. Indeed, the only sentence in plaintiff’s
response brief that squarely addresses this issue is as follows:
And MTC likely would have prevailed over Res-Care: in both prior
procurements for the full five-year contract to operate the Gary JCC, the
agency rated MTC higher than Res-Care overall.
ECF No. 17 at 3 (citing ECF No. 5 at 70). This statement does not address the central
issue posed by the government’s motion to dismiss. As a CCV contractor, MTC is
prohibited from competing for any interim services task order for operating a Job Corps
Center for which it is the incumbent contractor. See ECF No. 16-1 at 15, 65 (“It is
understood and agreed that if an awardee operates a Center for which operation is being
changed, the incumbent is ineligible for award of the task order.”).
Thus, the court finds that because MTC was not eligible for the task order
competition for Gary, it did not have a substantial chance of winning the task order.
Indeed, MTC had no chance of winning the task order. Under Myers, MTC lacks
standing to protest the award of the task order to Res-Care.
B. MTC Does Not Have Standing under Distributed
The court begins with a review of the Distributed litigation. Acquisition of
software and related services was contemplated by the government, as part of a larger
project. Distributed, 539 F.3d at 1342. Rather than following through on a direct
to binding precedent, supplemented by guidance from a GAO decision that is factually
indistinguishable from this case.
5
purchase procurement, the government chose to assign this software acquisition task to
one of its project contractors, which then competed subcontracts to fulfill this need. Id. at
1343.
Disappointed potential software vendors lodged a protest, alleging that the
government violated statutes and regulations when it delegated the acquisition function to
the project contractor. Id. at 1344-45. This court found, because the government never
“commence[d] acquisition” of the software services, “that a Federal agency procurement
[wa]s not at issue.” Distributed Sols., Inc. v. United States, 76 Fed. Cl. 524, 527-28
(2007) (citations omitted), rev’d, 539 F.3d 1340 (Fed. Cir. 2008). The protest was
dismissed for lack of jurisdiction, and the issue of standing was not addressed by the trial
court. Id.
On appeal, the primary holding of the United States Court of Appeals for the
Federal Circuit was that the government’s decision to change course from a direct
acquisition of software to an assignment of that acquisition task to its project contractor
was a government action in connection with a proposed procurement. Distributed, 539
F.3d at 1343-46. The government’s solicitation of information from outside vendors,
accompanied by its ultimate decision to incorporate the acquisition task within the scope
of its project coordinator’s contract, constituted “pre-procurement decisions” subject to
protest under 28 U.S.C. § 1491(b) (2012). Id. at 1346. On this ground the Federal
Circuit reversed the trial court. Id.
In the course of its analysis, the Federal Circuit also found that the appellants
possessed standing to bring their protest, fulfilling both prongs of the test for standing.
Id. at 1344-45 (citing Rex, 448 F.3d at 1307). First, the protestors “established
themselves as prospective bidders in that they submitted qualifying proposals in response
[to the government’s request for information] and, according to their complaint, were
prepared to submit bids.” Id. at 1345. Second, the Federal Circuit found that the
appellants “possess[ed] a direct economic interest in the government action at issue in
that they were both deprived of the opportunity to compete for the provision of
acquisition and assistance solutions for [the project].” Id.
The discussion of standing in Distributed is very brief and contains no guidance as
to the particularity or breadth of any nuanced test for standing that might be discerned
therein. Indeed, although the Federal Circuit has often relied on Distributed for its
primary holding regarding the types of government actions which may be protested, e.g.,
AgustaWestland N. Am., Inc. v. United States, 880 F.3d 1326, 1330 (Fed. Cir. 2018), the
discussion of standing in Distributed has never been cited in another Federal Circuit
decision. In the court’s view, Distributed applies established Federal Circuit precedent
regarding bid protest standing to the facts of that case, but its discussion of standing has
limited usefulness in other factual scenarios.
6
The only principle regarding standing that is made clear in Distributed is that the
deprivation of an opportunity to compete may, in some circumstances, indicate that a
protestor possesses a direct economic interest in a procurement, as required by the second
prong of the bid protest standing test. That test, as stated in Rex, holds that the protestor
must “establish that it (1) is an actual or prospective bidder, and (2) possesses the
requisite direct economic interest.” 448 F.3d at 1307 (citing Myers, 275 F.3d at 1369).
The particular facts of a case determine whether a contract award in a narrowed
competition may be protested by an excluded contractor, whose standing derives from the
protestor’s substantial chance of obtaining a contract award in a less exclusive
competition. See, e.g., Tinton Falls Lodging Realty, LLC v. United States, 800 F.3d
1353, 1360 (Fed. Cir. 2015) (Tinton Falls) (“In short, the question of standing hinges on
whether Tinton Falls could compete for [an unrestricted] reopened bid if it wins its
protest of the initial contract award.”); see also id. at 1360 n.3 (“We hold only that under
the particular facts of this case, the Claims Court did not clearly err in finding that Tinton
Falls had a substantial chance of winning a reopened bid [with substantially different
eligibility requirements] should it prevail in its bid protest.”).
As explained in Myers, a protestor seeking a “rebid” of a narrow competition
“need only establish that it ‘could compete for the contract’ if the bid process were made
competitive.” 275 F.3d at 1370 (emphasis added) (quoting Impresa Construzioni Geom.
Domenico Garufi v. United States, 238 F.3d 1324, 1334 (Fed. Cir. 2001)). In one subset
of these “rebid” protests, the Federal Circuit has emphasized that the protestor of a
sole-source contract award may establish prejudice, and standing, if it has a substantial
chance of receiving a contract award in a more competitive procurement process:
A disappointed party can establish prejudice . . . by showing [that]
proceeding without the violation would have made the procurement official’s
decision to make a sole-source award rather than to conduct a competitive
bidding process irrational, and in a competitive bidding process, the
complaining party would have a substantial chance of receiving the award[.]
Emery Worldwide Airlines, Inc. v. United States, 264 F.3d 1071, 1086 (Fed. Cir. 2001)
(Emery) (emphasis added) (citations omitted). Considering these authorities -- namely
Distributed, Myers, Emery, and Tinton Falls -- a protestor may satisfy the “direct
economic interest” requirement for standing when the government agency’s limitations
on competition are challenged in order to give the protestor a substantial chance of
winning a contract in a more competitive selection process.
It would turn this type of standing analysis on its head to conclude that MTC has
standing for its protest before GAO. DOL invested many months recruiting and selecting
IDIQ contractors for its CCV contractor pool. This competitive process produced
thirteen CCV contractors eligible to compete for the interim services task order for Gary.
DOL then solicited bids from the eligible CCV contractors to obtain, competitively, the
most advantageous offers. Res-Care was selected through this competitive process and is
7
transitioning to perform at Gary. This is neither a sole-source award, nor a particularly
narrow or limited competitive process.
MTC’s protest, on the other hand, seeks to replace that competitive process, and
Res-Care, with an extension of MTC’s sole-source contract so that, without any
competition whatsoever, MTC can continue to perform at Gary until its latest protest at
the GAO is concluded. See ECF No. 12 at 3 (suggesting that MTC’s latest sole-source
contract should be extended); see also ECF No. 18-1 at 42 (extension clause in MTC’s
latest sole-source contract). Under these facts, MTC, a participant in the CCV
competition and a beneficiary of robust competition in that regard, asserts that it has
standing to cut off any further competition so that it may continue to monopolize the
contracting opportunity at Gary. This does not fit within the standing framework applied
in Distributed or in the other Federal Circuit decisions discussed in this opinion. Under
Distributed and other binding precedent, MTC does not have standing to challenge
DOL’s award to Res-Care.
C. GAO Decision on Indistinguishable Facts
Both parties cite to a GAO decision which the court finds persuasive. See
MINACT, Inc., B-414615, B-414615.2, 2017 CPD ¶ 221, 2017 WL 3001422 (Comp.
Gen. July 12, 2017). The facts in MINACT are indistinguishable from the facts of the
instant case. In MINACT, an incumbent Job Corps Center contractor, MINACT, Inc.
(MINACT), was operating that center through a sole-source contract. 2017 WL
3001422, at *2. As that sole-source contract reached the end of its term, DOL chose to
compete interim services for the center through the CCV vehicle. Id.
MINACT, a CCV contractor for DOL, did not receive the task order and protested
the task order award at the GAO. Id. DOL moved to dismiss the protest on the grounds
that MINACT was ineligible for the task order due to its incumbency and due to an
exclusionary clause in its CCV contract similar to the one at issue in the instant protest.
Id. at *2-3. The GAO agreed with DOL and found that MINACT was not an interested
party and thus lacked standing to protest the award of the task order to an eligible CCV
contractor. Id. at *3. The court finds the GAO’s reasoning to be persuasive and follows
that decision in this case.3
3
Plaintiff’s attempt to distinguish MINACT, on the basis that MTC’s GAO protest
challenges the legality of the exclusionary CCV clause and MINACT’s protest did not, is
not well taken. See ECF No. 17 at 8. Although the “legality” issue is raised in a footnote
in MTC’s GAO protest, ECF No. 18-1 at 91, and may not have been raised in the
MINACT protest, the “legality” challenge to the CCV contract clause is barred on
timeliness grounds. See infra.
8
D. Untimely Protest
The court notes that another threshold problem affects MTC’s GAO protest.
According to GAO timeliness rules, “challenges which go to the heart of the underlying
ground rules by which a competition is conducted, should be resolved as early as
practicable during the solicitation process, but certainly in advance of an award decision
if possible, not afterwards.” Caddell Constr. Co., B-401281, 2009 CPD ¶ 130, 2009 WL
1771287, at *3 (Comp. Gen. June 23, 2009); see also 4 C.F.R. § 21.2 (2017) (“Protests
based upon alleged improprieties in a solicitation which are apparent prior to bid opening
or the time set for receipt of initial proposals shall be filed prior to bid opening or the
time set for receipt of initial proposals.”). The clause in MTC’s CCV contract which
excludes MTC from competing for an interim CCV task order to manage Gary, i.e., the
contract term which produced the result which plaintiff now alleges is “illegal,” ECF No.
17 at 7-8, could have been protested by MTC, before its CCV award, but was not, as
evidenced by MTC’s CCV contract. Further, the CCV IDIQ competition was
contemporaneous with the competition for the longer term contract at Gary, where MTC
was both a bidder on the new longer term contract and the incumbent contractor. See
ECF No. 16-1 at 59, 102. MTC cannot claim that it did not know that its CCV contract
contained a clause that would eliminate its eligibility for a CCV task order at Gary.
Thus, no protest regarding the legality of that contract clause, ECF No. 16-1 at
65, is timely before the GAO so many months after the CCV contract was awarded to
MTC in 2016. Such a timeliness problem is a threshold issue. See, e.g., COMINT Sys.
Corp. v. United States, 700 F.3d 1377, 1383 (Fed. Cir. 2012) (finding that a protest of a
contract requirement that was known to the protestor before award was waived after
award); Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1313 (Fed. Cir. 2007)
(“We also hold that a party who has the opportunity to object to the terms of a
government solicitation containing a patent error and fails to do so prior to the close of
the bidding process waives its ability to raise the same objection subsequently in a bid
protest action in the Court of Federal Claims.”); Armorworks Enters., LLC, B-400394,
B-400394.2, 2008 CPD ¶ 176, 2008 WL 4415709, at *4 (Comp. Gen. Sept. 23, 2008)
(“Where alleged improprieties do not exist in the initial solicitation, but are subsequently
incorporated into the solicitation (e.g., via an amendment to the solicitation), they must
be protested not later than the next closing time for receipt of proposals following the
incorporation.”) (citations omitted). Because MTC’s challenge to its ineligibility for the
CCV task order award is untimely under these authorities, the GAO’s timeliness rule
provides an additional reason for the court to grant defendant’s motion to dismiss MTC’s
protest in this court.
IV. Conclusion
For the reasons stated in this opinion, MTC’s bid protest must be dismissed
because MTC is not an interested party and lacks standing to bring this action. Further,
even if the court’s standing analysis is incorrect, plaintiff’s ineligibility for the task order
9
competition, along with its waiver of any challenge to the contract clause which
eliminates it from consideration for the task order competition, compel a finding that
plaintiff has not met its burden to show likelihood of success on the merits of its
challenge to DOL’s override of the CICA stay. Thus, plaintiff’s application for a
temporary restraining order and/or preliminary injunction, ECF No. 4, must be denied.
Accordingly,
(1) Plaintiff’s Application for a Temporary Restraining Order and/or
Preliminary Injunction (ECF No. 4), filed April 17, 2018, is
DENIED;
(2) Defendant’s Motion to Dismiss (ECF No. 16), filed April 23, 2018,
is GRANTED;
(3) The clerk’s office is directed to ENTER final judgment
DISMISSING plaintiff’s complaint, without prejudice, for lack of
subject matter jurisdiction; and
(4) On or before May 14, 2018, the parties shall CONFER and FILE a
Proposed Redacted Version of this opinion, with any competition-
sensitive or otherwise protectable information blacked out.
IT IS SO ORDERED.
s/ Patricia Campbell-Smith
PATRICIA CAMPBELL-SMITH
Judge
10