Texas Commission on Environmental Quality and Texas LNG Brownsville, LLC v. Vecinos Para El Bienestar De La Comunidad Costera, and City of Port Isabel, Texas
TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
NO. 03-21-00395-CV
Texas Commission on Environmental Quality and Texas LNG Brownsville, LLC,
Appellants
v.
Vecinos Para El Bienestar De La Comunidad Costera, and City of Port Isabel, Texas,
Appellees
FROM THE 419TH DISTRICT COURT OF TRAVIS COUNTY
NO. D-1-GN-20-004038, THE HONORABLE LORA J. LIVINGSTON, JUDGE PRESIDING
M E M O RAN D U M O PI N I O N
The Texas Commission on Environmental Quality (TCEQ) and Texas LNG
Brownsville, LLC, appeal the trial court’s order denying their plea to the jurisdiction regarding the
suit by appellees Vecinos Para El Bienestar De La Comunidad Costera and the City of Port Isabel.
Texas LNG applied to TCEQ for an air permit for construction of a liquefied natural gas (LNG)
terminal along the Brownsville Ship Channel, which Vecinos and Port Isabel opposed. After a
contested-case hearing at the State Office of Administrative Hearings, TCEQ issued the permit.
See An Order Granting the Application By Texas LNG Brownsville LLC for Permit No. 139561,
TCEQ Docket No. 2019-0624-AIR, SOAH Docket No. XXX-XX-XXXX, 2020 WL 2544372 (Tex.
Comm’n Envtl. Quality) (May 12, 2020) (final order) (TCEQ Order).
Vecinos and Port Isabel sought judicial review of TCEQ’s grant of the permit,
contending that TCEQ’s issuance of the permit was arbitrary and capricious and not reasonably
supported by substantial evidence. Texas LNG intervened and the suits were consolidated. TCEQ
and Texas LNG filed a joint plea to the jurisdiction, contending that the federal Natural Gas Act
provides that federal courts of appeals—not state courts—have exclusive jurisdiction to review
challenges to state agency permits required by federal law for natural-gas terminals. See 15 U.S.C.
§ 717r(d)(1). The trial court denied their plea to the jurisdiction. We will reverse the order and
dismiss the case.
STATUTORY BACKGROUND
The applicable laws and regulations and the cases and administrative opinions
interpreting those laws and regulations discussed in this opinion use a plethora of acronyms and
strings of initials for statutes, regulations, agencies, and procedures. For ready reference, this list
compiles the acronyms and strings of initials defined below in this opinion:
AQA Air Quality Analysis
BACT Best Available Control Technology
CAA Clean Air Act; can be used with multiple states
EPA federal Environmental Protection Agency
FCAA Federal Clean Air Act
FERC Federal Energy Regulatory Commission
LNG liquefied natural gas
NAAQS National Ambient Air Quality Standards
NGA Natural Gas Act
SIP State Implementation Plan
SOAH Texas State Office of Administrative Hearings
TAC Texas Administrative Code
TCAA Texas Clean Air Act
TCEQ Texas Commission on Environmental Quality
The Natural Gas Act (NGA) authorizes the federal government to regulate the
construction of natural-gas terminals. 15 U.S.C. § 717. The NGA vests the Federal Energy
2
Regulatory Commission (FERC) with the “exclusive authority to approve or deny an application
for the siting, construction, expansion, or operation of” an LNG terminal. Id. § 717b(e)(1). 1
Construction sites can be a source of emissions subject to air-quality regulation.
Stationary sources of air pollution are subject to the Federal Clean Air Act (FCAA). See, e.g.,
42 U.S.C. § 7401(a)(2). The FCAA requires the Environmental Protection Agency (EPA) to
identify air pollutants and establish National Ambient Air Quality Standards (NAAQS) for harmful
pollutants. Id. §§ 7408(a), 7409(a). But the FCAA assigns the primary responsibility for
implementing those air-quality standards to each state. Id. § 7407(a); Environmental Integrity
Project v. United States Envtl. Prot. Agency, 969 F.3d 529, 535 (5th Cir. 2020). The Fifth Circuit
has described this hybrid approach as “[a]n experiment in cooperative federalism.” Texas v. United
States Envtl. Prot. Agency, 829 F.3d 405, 411 (5th Cir. 2016); Luminant Generation Co. v. United
States Envtl. Prot. Agency, 675 F.3d 917, 921 (5th Cir. 2012). States must adopt and administer a
state implementation plan (SIP) meeting certain statutory criteria, for assuring air quality within
their geographic areas. 42 U.S.C. § 7410 (SIPs generally). In part, a SIP must include procedures
that enable the state or local regulatory authority to determine whether to determine whether
construction or modification of a facility or stationary source of air pollution will result in
interference with attainment or maintenance of a national standard. See 40 C.F.R. § 51.160(a)(2)
(requiring procedures for determining whether construction or modification of facilities interferes
with attainment of NAAQS); Luminant, 675 F.3d at 921-22. In addition, a SIP must include a
permitting program for reviewing new sources of emissions that are considered major or minor
1 The statute states that the Federal Power Commission has this authority. See 15 U.S.C.
§ 717a(9). However, the FPC’s authority over the Natural Gas Act was transferred to the Federal
Energy Regulatory Commission. See 42 U.S.C. § 7172(a)(1).
3
depending on their emission levels; though there are more express requirements for major sources
of emissions than minor sources, the FCAA and the SIP regulate the modification and construction
of “any stationary source within the areas covered by the plan as necessary to assure that national
ambient air quality standards are achieved . . . .” 42 U.S.C. § 7410(a)(2)(C); see also Luminant,
675 F.3d at 922.
The EPA has approved the Texas SIP, which is administered by TCEQ and
enforceable in all parts of Texas. 40 C.F.R. § 52.2270(a) (EPA approval); see also 30 Tex. Admin.
Code (TAC) § 101.21 2. As a result, before work begins on the construction of a new facility or
modification of an existing facility that may emit air contaminants, the planner of the construction
or modification must obtain an air-quality permit or permit amendment from TCEQ. See Tex.
Health & Safety Code § 382.0518(a); 30 TAC § 116.110(a)(1).
A person aggrieved by a TCEQ permitting decision is entitled to judicial review.
Tex. Gov’t Code § 2001.171. Under state law, that review is initiated by filing a petition in a
district court of Travis County. Tex. Health & Safety Code § 382.032(a). However, the NGA
provides that exclusive jurisdiction for review of certain TCEQ decisions lies in the United States
Fifth Circuit:
The United States Court of Appeals for the circuit in which a facility subject to
section 717b of this title or section 717f of this title is proposed to be constructed,
expanded, or operated shall have original and exclusive jurisdiction over any civil
action for the review of an order or action of a Federal agency (other than the
Commission) or State administrative agency acting pursuant to Federal law to
issue, condition, or deny any permit, license, concurrence, or approval (hereinafter
collectively referred to as “permit”) required under Federal law, other than the
Coastal Zone Management Act of 1972 (16 U.S.C. 1451 et seq.).
2 All references to the Texas Administrative Code will be to the 2016 version of the TCEQ
rules effective when the application was made.
4
15 U.S.C. § 717r(d)(1) (emphases added). 3 The jurisdiction statute does not distinguish between
major or minor sources of emissions. Id. Further, federal law requires that “any” stationary source
comply with national air quality standards. 42 U.S.C. § 7410(a)(2)(C).
DISCUSSION
By their sole issue, appellants TCEQ and Texas LNG contend that the trial court
erred in denying their plea to the jurisdiction because federal law (namely, section 717r(d)(1) of
the NGA) vests the Fifth Circuit with original and exclusive jurisdiction over actions challenging
a state agency’s issuance of permits required by concerning construction, expansion, or operation
of natural-gas terminals.
1. We apply a de novo standard of review.
The existence of subject-matter jurisdiction is a question of law, so we review the
trial court’s ruling on a plea to the jurisdiction de novo. See Texas Nat. Res. Conservation Comm’n
v. IT-Davy, 74 S.W.3d 849, 855 (Tex. 2002); City of New Braunfels v. Allen, 132 S.W.3d 157, 161
(Tex. App.—Austin 2004, no pet.). The party asserting the plea must establish an incurable
jurisdictional defect apparent from the face of the pleadings that makes it impossible for the
plaintiff’s petition to confer jurisdiction on the trial court. Anderson v. American Fed’n of Gov’t
Emps., AFL-CIO, 338 S.W.3d 709, 713 (Tex. App.—Houston [1st Dist.] Apr. 17, 2011, pet.
3 Port Isabel notes that the Natural Gas Act provides that “[e]xcept as specifically provided
in [Chapter 15B of the Natural Gas Act], nothing in [Chapter 15B] affects the rights of states under
. . . the Clean Air Act (42 U.S.C. 7401 et seq.).” 15 U.S.C. § 717b(d)(2). The jurisdictional
provision at issue here is in Chapter 15B of the Natural Gas Act and specifically affects the
jurisdiction of state courts. See 15 U.S.C. § 717r(d)(1).
5
denied). We construe the pleadings liberally in the nonmovant’s favor and indulge every
reasonable inference and resolve any doubts in favor of jurisdiction. Texas Dep’t of Parks &
Wildlife v. Miranda, 133 S.W.3d 217, 228 (Tex. 2004).
Review of this appeal requires interpretation of federal statutes. When interpreting
a federal statute, the Texas Supreme Court generally follows the decisions of the United States
Supreme Court. In re Facebook, Inc., 625 S.W.3d 80, 87-88 (Tex. 2021). When the statutory
language is plain, courts must enforce it according to its terms. Id. (citing Jimenez v. Quarterman,
555 U.S. 113, 118 (2009)). Unless otherwise defined, words will be interpreted as taking their
ordinary meaning at the time Congress enacted the statute. Id. A statute must be read as a whole
because the meaning of statutory language, plain or not, depends on context. Id.
2. TCEQ’s Order is within the NGA’s special federal-circuit judicial-review provision.
Appellees’ pleadings demonstrate the incurable defect for jurisdiction in Texas state
courts because they show that the suits fall within the scope of the NGA’s judicial-review
provision, which establishes exclusive and original jurisdiction in the Fifth Circuit. See 15 U.S.C.
§ 717r(d)(1). The TCEQ Order concerns a permit for construction of an LNG terminal;
construction of such facilities is subject to section 717b(e) of the NGA, entitled “Exportation or
importation of natural gas; LNG terminals.” The proposed site for the LNG terminal on the
Brownsville Ship Channel is within the Fifth Circuit’s territorial jurisdiction. The Order was
issued by TCEQ—a state administrative agency.
As to whether the TCEQ was “acting pursuant to federal law,” though Appellees’
pleadings cite TCEQ’s application of the TCAA including provisions relating to use of the Best
Available Control Technology (BACT), TCEQ was acting pursuant to federal law because it issued
6
the new-source review permit 4 consistent with Texas’s SIP and as required by the FCAA. See
Environmental Integrity Project, 969 F.3d at 535 (explaining that new-source-review program
under Title I of FCAA requires operators to obtain preconstruction permits, “issued by the states,
through mechanisms called [SIPs])” before building or modifying facility. The TCEQ Order states
that “[t]he maximum offsite concentrations from Air Quality Analysis (AQA) are all below
applicable National Ambient Air Quality Standards (NAAQS) and Commission Effects Screening
Levels.” 2020 WL 2544372 at *1. The NAAQS are federal standards, “promulgated pursuant to
section 109 of the Federal Clean Air Act, as amended,” to be enforced by TCEQ. See 30 TAC
§ 101.21. That is, the permit was required by federal law (other than the Coastal Zone
Management Act of 1972 (16 U.S.C. § 1451)) that delegates to the states regulatory authority
stationary sources within their jurisdiction. 42 U.S.C. § 7410(a)(2)(C). Therefore, unchallenged
factual allegations in the appellees’ pleadings demonstrate that the challenged TCEQ Order falls
within the scope of the Act’s exclusive-jurisdiction provision, section 717r(d)(1).
Port Isabel argues that we should interpret the NGA’s exclusive-jurisdiction
provision narrowly because its claims were purely state-law claims under the TCAA and that
review should be in state courts. See Tex. Health & Safety Code § 382.032(a) (stating that appeal
of TCEQ action goes to Travis County district court); see Sabre Travel Int’l, Ltd. v. Deutsche
Lufthansa AG, 567 S.W.3d 725, 738, 741 (Tex. 2019) (finding that Airline Deregulation Act did
not preempt airline’s state-law tortious-interference claim against ticket seller because it did not
relate to airline’s prices, routes, or services). Here, however, we have forum preemption—not
4 The TCEQ Order specifies that the application was for a new source review. Tex.
Comm’n on Envtl. Quality, An Order Granting the Application By Texas LNG Brownsville LLC
for Permit No. 139561, TCEQ Docket No. 2019-0624-AIR, SOAH Docket No. XXX-XX-XXXX, 1,
2020 WL 2544372 at *1 (Tex. Comm’n Envtl. Quality) (May 12, 2020) (final order).
7
subject-matter preemption—because Congress created an exclusive federal forum for the
described actions. See Mills v. Warner Lambert Co., 157 S.W.3d 424, 427-28 (Tex. 2005) (per
curiam). In Mills, the Texas Supreme Court contrasted subject-matter preemption with forum
preemption. The court held that, though state laws governing claims for drugs were preempted by
the federal Food, Drug, and Cosmetic Act (FDCA), the FDCA did not preempt state courts from
exercising jurisdiction over the claim because the FDCA lacked any forum-preemption language
or intent. See id. (discussing 21 U.S.C. § 379r). The court contrasted the FDCA with the Employee
Retirement Income Security Act and the National Labor Relations Act which, respectively, had
federal forum preemption expressly in statutory language (in ERISA 5) and implicitly due to the
creation of a complex and interrelated federal scheme of law, remedy, and administration
(NLRA 6). Congress can expressly designate an exclusive federal forum for specified claims
irrespective of the law to be applied. Id. Although Port Isabel contends that its claim for judicial
review is based purely on state law, Congress has adopted a hybrid model of federal and state
regulation and enforcement in the air-quality field but has expressly provided that permit decisions
relating to LNG facility construction must be reviewed exclusively by federal courts of appeal
even if the permits at issue were considered by state agencies acting pursuant to federal law. See
15 U.S.C. § 717r(d)(1). As discussed above, in issuing the TCEQ Order, TCEQ was carrying out
its responsibility under the FCAA to implement the NAAQS—federally created standards. See 30
TAC § 101.21.
5 “[T]he district courts of the United States shall have exclusive jurisdiction of civil actions
under this subchapter . . . .” 29 U.S.C. § 1132(e)(1).
6 San Diego Bldg. Trades Council v. Garmon, 359 U.S. 236, 243-44 (1959).
8
Port Isabel contends that the section 717r(d)(1) applies only to decisions by FERC
and cases in which a state agency acts “directly” pursuant to federal and not state law; Port Isabel
argues that this action is based purely on state law as the only statute “directly in issue” is the
TCAA—not the FCAA or NGA. Section 717r(d)(1) does not limit its reach to decisions by FERC
or to cases in which federal law is “directly in issue.” It expressly extends to orders by a “State
administrative agency acting pursuant to Federal law”—with no use of the word “directly.”
Port Isabel notes further that the TCEQ Order mentions the NAAQS once and does
not cite the FCAA or NGA. Port Isabel also notes that no witnesses referenced the NGA or FCAA
in the SOAH hearing or the pre-hearing depositions. Port Isabel contends that, under appellants’
reading, the Fifth Circuit would have original and exclusive jurisdiction to hear every single TCEQ
air-permit challenge.
We are not persuaded by these arguments. The TCEQ Order’s finding that the
NAAQS are not violated shows that TCEQ acted “pursuant to Federal law” in issuing the
air-quality permit required for the construction of an LNG terminal. FERC’s approval of the
construction permit for this LNG facility is conditioned on obtaining permits and approvals,
including a New Source Review permit from TCEQ. See Texas LNG Brownsville LLC,
169 FERC ¶ 61,130, 61856, 2019 WL 6250555, at ¶ 62 (“The project . . . is subject . . . to the New
Source Review minor source construction permitting program under Texas regulations.”). This
proceeding arises from TCEQ’s new-source review, a permitting program required by federal law
intended to ensure compliance with the NAAQS. Whether the deposition or hearing witnesses
mentioned federal law—which the attorneys disputed at the trial-court hearing—does not control
whether TCEQ acted pursuant to federal law in issuing the permit. Moreover, not every air-quality
permit issued by TCEQ will be subject to Fifth Circuit review because the plain terms of section
9
717r(d)(1) limit its application to permits concerning facilities subject to 15 United States Code
sections 717b (LNG terminals) and 717f (natural-gas transportation facilities under FERC order
to extend or improve transportation facilities). Nothing in the record or otherwise shows that these
two classes of facilities encompass the full gamut of air-quality permits issued by TCEQ such that
all air-quality permits issued by TCEQ would be subject to Fifth Circuit review.
Vecinos asserts that Fifth Circuit review of a state agency’s decision under state
procedures and regulations will create a “particularly awkward posture.” But Congress directed
the circuit courts to review state agency decisions in the circumstances prescribed in section
717r(d)(1). Vecinos notes that, in a similar case involving Vecinos, the Fifth Circuit noted the
“unusual posture” of a petition seeking direct review of a state agency’s decision in the Fifth
Circuit. Shrimpers and Fishermen of the RGV v. Texas Comm’n on Envtl. Quality, 968 F.3d 419,
423 (5th Cir. 2020). In that case, the Shrimpers and Vecinos sought review of a TCEQ decision
granting air permits regarding construction of another LNG facility on the Brownsville Ship
Channel that was deemed a new major source of air pollution. Id. at 422-23. In that case,
Shrimpers and Vecinos filed for review in both the state and federal systems. Id. at 423. The Fifth
Circuit did not decide whether section 717r(d)(1) conferred jurisdiction over that challenge,
however, because it found that Shrimpers and Vecinos lacked standing because they had not shown
that their members suffered injuries-in-fact from TCEQ’s decision. Id. at 424. The concurring
judge questioned whether Congress intended to give federal courts jurisdiction over what he
described as “state-law claims brought by Texans against the State of Texas.” Id. at 427 (Oldham,
10
J., concurring). 7 But these concerns do not defeat Congress’s grant of jurisdiction. Further, other
federal circuits have exercised jurisdiction over state air-quality and similar water-quality permits
issued regarding facilities subject to the NGA, as we will now discuss.
3. Other federal circuits have exercised their exclusive jurisdiction under the NGA.
Although decisions by other federal courts of appeals do not bind the Fifth Circuit,
review of other cases persuades us that the Fifth Circuit has original and exclusive jurisdiction
over this case on judicial review under section 717r(d)(1). See Town of Weymouth v. Massachusetts
Dep’t of Envtl. Prot., 961 F.3d 34 (1st Cir. 2020), amended on other grounds, 973 F.3d 143 (1st
Cir. 2020); Delaware Riverkeeper Network v. Secretary Pennsylvania Dep’t of Env’t Prot., 833
F.3d 360 (3d Cir. 2016); see also Friends of Buckingham v. State Air Pollution Control Bd., 947
F.3d 68 (4th Cir. 2020). As further explained below, the Weymouth and Buckingham cases show
7 At the trial-court hearing underlying this appeal, the trial court expressed skepticism “that
anything would go straight to the Fifth Circuit.” The court and TCEQ’s counsel discussed the
dilemma that appellees could be dismissed from state court on its conclusion that the Fifth Circuit
has exclusive jurisdiction, but then have the Fifth Circuit later dismiss on its independent
conclusion that it has no jurisdiction. However, the trial court noted that Port Isabel and Vecinos
could file in both systems and abate their state suit pending a determination by the Fifth Circuit on
whether to exercise jurisdiction. Port Isabel and Vecinos did not seek abatement in the trial court
or here.
Vecinos noted difficulties in seeking relief in parallel under both systems. Vecinos
described abatement as “not an efficient course” and noted that the court systems have different
timetables for seeking review; while judicial review in the state system requires filing suit within
30 days after the effective date of the ruling, order, or decision, Tex. Health & Safety Code
§ 382.032 (citing Tex. Water Code § 5.351), seeking review at the Fifth Circuit is subject to a four-
year limitations period, 28 U.S.C. § 1658. Vecinos also asserted that seeking review in both
systems would undercut jurisdictional arguments in each system. Indeed, appellants cite Vecinos’
pleading that the Fifth Circuit had original and exclusive jurisdiction over judicial review of a
TCEQ air permit issued to another proposed LNG terminal on the Brownsville Ship Channel as
support for appellants’ arguments, citing Shrimpers & Fishermen of RGV v. Texas Comm’n on
Envtl. Quality, 968 F.3d 419, 421, 423 (5th Cir. 2020) (per curiam). We acknowledge that the
litigants face choices in strategy, but we must decide only the case presented to us on the
applicable law.
11
federal circuit courts exercising original and exclusive jurisdiction over state agencies’ decisions
pursuant to the FCAA as implemented through a SIP and the state’s clean air act. Weymouth, 961
F.3d at 38-40; Buckingham, 947 F.3d at 80, 92-93. The Buckingham opinion makes clear that the
NAAQS are a national standard set by the federal EPA which are then implemented through a SIP
to limit emissions from major and minor stationary sources, 947 F.3d at 72—a description that
could have been appropriately drafted for this case. The Delaware Riverkeeper opinion shows a
federal circuit court exercising jurisdiction over a state agency’s decision pursuant to a similar
federal water-protection scheme implemented through state laws and agency action. 833 F.3d at
371-72.
In Weymouth, the First Circuit exercised original jurisdiction under the NGA over
a petition for review of an air permit issued by the Massachusetts Department of Environmental
Protection (MDEP) for a natural-gas compressor station. 961 F.3d at 38. FERC issued a certificate
of public convenience and necessity conditioned on the applicant’s compliance with the state and
federal clean air acts as determined by MDEP. Id. at 39. MDEP issued a Non-Major8
Comprehensive Air Quality Plan Approval. Id. Though no party challenged jurisdiction in
Weymouth, the First Circuit explained why it had jurisdiction to conduct an original review of a
state agency’s action. Id. at 39-40. The First Circuit stated that MDEP acted pursuant to the FCAA
to issue the permit, noting that the EPA approved the Massachusetts CAA as a SIP, that by doing
so the EPA delegated its authority to MDEP to administer the FCAA in Massachusetts, and that
MDEP, “in enforcing the Massachusetts CAA, is in fact acting pursuant to the federal CAA.” Id.
8As the FCAA discusses new source reviews of major and minor sources of emissions,
Luminant Generation Co. v. United States Envtl. Prot. Agency, 675 F.3d 917, 921 (5th Cir. 2012),
a “non-major” plan applies to minor emissions.
12
at 39 n.2, 40, n. 4. The First Circuit also wrote that MDEP’s actions pursuant to the FCAA
“provides the federal ‘ingredient’ for purposes of Article III jurisdiction.” Id. at 40, n.4. The First
Circuit’s review focused on MDEP’s application of the Massachusetts CAA in its order—including
compliance with NAAQS—and vacated the air permit and remanded to the agency because of
MDEP’s failure to follow its own procedures for assessing whether an electric motor was the
BACT. Id. at 38, 47.
In Buckingham, the Fourth Circuit exercised original jurisdiction under the NGA to
review an air permit issued by Virginia’s State Air Pollution Control Board. 947 F.3d at 80. The
court did not discuss why it had jurisdiction over this permit concerning a natural-gas facility other
than to cite the NGA, including excerpting the language that it had jurisdiction to review an order
or action of a “State administrative agency acting pursuant to Federal law to issue . . . any permit
. . . required under Federal law.” Id. (citing 15 U.S.C. § 717r(d)(1)). The Fourth Circuit analyzed
the permit using Virginia laws and regulations. Id. at 92-93. The court vacated the permit and
remanded it to the Virginia Board. Id. at 93.
The Third Circuit explored and explained its jurisdiction under the NGA to conduct
original review of a state agency’s water permit in Delaware Riverkeeper. 833 F.3d at 371-72. In
that case, the Pennsylvania Department of Environmental Protection (PADEP) contended that the
Third Circuit lacked jurisdiction because the NGA provided jurisdiction only to state agency
actions taken pursuant to federal law, while a water-quality certification at issue was required by
federal law. Id. at 371. While federal-state cooperation under the Clean Water Act is not expressed
through an SIP as it is in the FCAA, the Third Circuit explained that the federal Clean Water Act
similarly allows states to promulgate water quality standards subject to EPA oversight such that
the issuance of a water-quality certification concerning facilities regulated under the NGA was not
13
purely a matter of state law. Id. The court wrote, “A state issues a Water Quality Certification for
an interstate natural gas facility to certify compliance with state water quality standards,
promulgated under federal supervision, as well as with federally-established Clean Water Act
requirements.” Id. Because the certification verified compliance with federal standards, it was
issued “pursuant” to federal law and invoked the NGA’s permission of state regulation “subject to
federal judicial review.” Id. at 371-72. The court wrote:
The Natural Gas Act preempts state environmental regulation of interstate natural
gas facilities, except for state action taken under those statutes specifically
mentioned in the Act: the Coastal Zone Management Act, the Clean Air Act, and
the Clean Water Act. In other words, the only state action over interstate natural
gas pipeline facilities that could be taken pursuant to federal law is state action
taken under those statutes. . . . Congress intended state actions taken pursuant to the
two non-excepted statutes, the Clean Water Act and the Clean Air Act, to be subject
to review by the Courts of Appeals. . . . To bar this Court’s review of PADEP’s
actions in permitting an interstate natural gas facility pursuant to the Natural Gas
Act and the Clean Water Act would frustrate the purpose of Congress’s grant of
jurisdiction . . . .
Id. at 372. While Delaware Riverkeeper concerned action pursuant to the Clean Water Act, the
Third Circuit expressly considered actions under the Clean Air Act to be similar under the NGA.
Id. The Third Circuit exercised jurisdiction, concluded that the agency did not act arbitrarily or
capriciously, and denied the petitions for review. Id. at 367, 389.
Port Isabel argues that, by contrast, Texas LNG sought the permit from TCEQ
directly, not as a condition of its FERC permit for its natural-gas facility as in these cases, see
Weymouth, 961 F.3d at 39, Delaware Riverkeeper, 833 F.3d at 369. But FERC’s approval of the
CCN in Weymouth was conditioned on the applicant’s “compliance with the CAA (state and
federal) as determined by [the Massachusetts Department of Environmental Protection].” 961 F.3d
at 39. Similarly, in Delaware Riverkeeper, the FERC “condition” required the applicant to receive
14
all applicable authorizations under federal law, but some of those authorizations were to be
obtained from the state. 833 F.3d at 369. While TCEQ applied state laws and regulations to
evaluate the application for a state permit, TCEQ exercised that authority through the SIP of the
FCAA, which was approved by the EPA, 40 C.F.R. § 52.2270(a), and its assessing compliance
with NAAQS, which are national standards set by the EPA and enforced by TCEQ. See 42 U.S.C.
§§ 7407-09(a); 30 TAC § 101.21. The LNG facility for which the air permit was issued is the
subject of the FERC permitting process for the LNG terminal, and FERC’s approval of the
construction permit for this LNG facility is conditioned on obtaining permits and approvals,
including a New Source Review permit from TCEQ. See Texas LNG, 169 FERC ¶ 61,130, 61856,
2019 WL 6250555, at ¶ 62. This proceeding arises from TCEQ’s new-source review.
The cases from the federal circuits bolster our determination that appellees’
petitions for judicial review are within the scope of the Fifth Circuit’s original and exclusive
jurisdiction. Like those cases, this case concerns a permit issued regarding a natural-gas facility
subject to the NGA. The Fifth Circuit has original and exclusive jurisdiction over this judicial
review of the TCEQ Order and permit. See 15 U.S.C. § 717r(d)(1). Accordingly, the Texas state
courts lack jurisdiction over this petition for judicial review. We resolve Appellants’ sole issue in
their favor.
15
CONCLUSION
Because the Texas state courts lack jurisdiction over this case, we reverse the trial
court’s order denying the plea to the jurisdiction. We dismiss this case.
__________________________________________
Darlene Byrne, Chief Justice
Before Chief Justice Byrne, Justices Triana and Kelly
Reversed and Dismissed
Filed: July 21, 2023
16